Upload
steelcat
View
39
Download
1
Embed Size (px)
DESCRIPTION
The signature structure of Puente de la Unidad project is a 304m (997ft) long asymmetrical cable- stayed bridge, with a main clear span of 185.6m (609ft).
Citation preview
PUENTE DE LA UNIDAD
INTERNATIONAL BRIDGE TECHNOLOGIES, INC.
Monterrey, Mexico
©2009 Copyright International Bridge Technologies, Inc.
Project Description
CABLE STAYED BRIDGE Overview
The signature structure of Puente de la Unidad project is a 304m (997ft) long asymmetrical cable-
stayed bridge, with a main clear span of 185.6m (609ft). The main pylon is inclined 30° to the vertical
and reaches a total height of 152.1m (499ft) from the top of foundation. Nearly all the main structural
components are made of 50MPa (7.25ksi) strength concrete. Thirteen pairs of harped stay cables support
the main span and are anchored on the outside of the roadway. One pair of vertical stays is anchored
into the back of the pylon. Main span carries 2 lanes of traffi c in each direction with pedestrian walkway
provided in middle. Pictures of the bridge are shown below.
International Bridge Technologies (IBT) was the lead designer for the bridge. The specifi c design tasks included:
• Main Span: Conceptual, Preliminary, and Final Design• Stay-Cables: Conceptual, Preliminary, and Final Design• Construction Methods: Conceptual, Preliminary, Final Design, and on-site support• Pylon: Conceptual, Preliminary, and Oversight of Final Design• Foundation: Conceptual, Preliminary, and Oversight of Final Design
The design of the bridge included detailed, 3-D FEM, non-linear, and time-dependent analysis. In addition, detailed studies were performed to ensure compatibility of the extensive network of post-tensioning tendons and non-orthogonal reinforcement.
Sistemas Optimos Constructivos S.A. (SOCSA) served as the prime consultant for the full viaduct project. SOCSA performed preliminary analysis and fi nal design for the pylon and foundation. West Wind Inc. provided wind studies and cable damping requirements.
PUENTE DE LA UNIDAD
INTERNATIONAL BRIDGE TECHNOLOGIES, INC.
Monterrey, Mexico
©2009 Copyright International Bridge Technologies, Inc.
• Original or Innovative Applications of New or Existing Techniques: The fundamental behavior of a cable-stayed structure
is well understood. Typically the bridges are
symmetric by span and pier layout, and the balancing
of forces is accounted for in the basic concept. In
the case of this bridge, the asymmetry required the
design to go back to a more basic level to ensure
the structural load paths were well-established and
adequate capacities provided. Because the main span
is reliant on the counter-
balance of the pylon, a
delicate balance exists. The
structural capacity of the
pylon must be considered
in parallel with the ballast it
provides, and these two goals
did not always work in the
same direction. The Puente
de la Unidad project is a good example of an existing
bridge concept (cable-stay) used in an alternate way
to provide a striking visual appearance, and achieve
the goal of providing a single support outside of the
main riverbed.
• Future Value to the Engineering Profes-sion: As indicated above, this project presents a
good example how a complex project can be solved
by understanding the basic behavior and providing
reliable load paths. The value of dedicating time
at the conceptual phase is refl ected in this project.
Three locations on the bridge illustrate this. The fi rst
is the transition from the force in the edge beams to
the pylon, the second is the resolution of axial loads
between the pylon and main span, and third the
specially shaped spread footing to accommodate the
monotonic loads. These solutions are shown on the
following pages.
• Social and Economic Considerations: The bridge project includes a long viaduct to provide
congestion relief to the crowded streets of Monterrey.
Also, the Santa Catarina riverbed can crest at a level
where most other adjacent bridges are under water.
This bridge will provide a critical escape route for
the citizens on the South side of the river. In addi-
tion to these benefi ts, the design was performed with
consideration of local materials and construction skill
level. The bridge details were all considered in such
a away to promote ease of
construction.
• Complexity: The Puente
de la Unidad project pre-
sented many challenges due
to its complexity. Typically
the roadway geometry is
adjusted to accommodate
the bridge, but the opposite
was done for this project. The complexities included
large openings in the pylon at grade to allow traf-
fi c fl ow, the introduction of a vertical curve to the
alignment of the bridge deck, variable cross-fall at the
span along the pylon, and allowing for ramp connec-
tions on either side of the bridge. All challenges were
successfully incorporated into the fi nal design.
• Meeting and Exceeding Owner/Client Needs: The primary achievement for the Puente de
la Unidad project was the delivery of a design under
a very tight schedule. The design schedule was 9
months, and the contractor selection was selected in
advance of the fi nal design completion. The bridge
construction was completed in 15 months, a time
frame rarely achieved for this complex of structure.
The bridge was completed for $16.8 million, and was
within 3% of estimated costs.
s
d example of an existing
a a
co
• de
se
to
th
ad
th
was done for this project T
STRUCTURAL SYSTEMS
PUENTE DE LA UNIDAD
INTERNATIONAL BRIDGE TECHNOLOGIES, INC.
Monterrey, Mexico
©2009 Copyright International Bridge Technologies, Inc.
Excavation of Foundation Foundation Reinforcement Cage
Starter Bars for Pylon Foundation Post-TensioningFoFoF ununddadatititionon PP Pososttt-TTeTensnsiioio ininingngg
Transition Span FrameTrTrT anan isisitititionon SS Spapap nn FFrFramamee
Flow of Forces FlFlFlowow o offff FFoForcrceses
FOUNDATION, PYLON BASE, AND TRANSITION SPAN
Key Features• Soil was injection grouted for added strength.
• Foundation was a spread footing and post-
tensioned in primary directions.
• Spread footing dimensions were optimized
for the monotonic loading. A trapezoidal
plan area was designed with a wider toe at the
front of the footing.
• 8000m3 (10500yd3) of concrete used for
foundation. Mass concrete casting procedures
implemented.
• Large axial forces at edge beams need to be
transferred to central pylon. Well-defi ned
load path provided by central and diagonal
beams.
PUENTE DE LA UNIDAD
INTERNATIONAL BRIDGE TECHNOLOGIES, INC.
Monterrey, Mexico
©2009 Copyright International Bridge Technologies, Inc.
MAIN PYLON
Pylon Section Pylon Back Wall Post-Tensioning
Climbing Form Pylon Elevation Completed Pylon
Key Features
• Pylon is hollow with a typical width of 5m (16.4ft), which tapers to 15m (49.2ft)
from deck to foundation. The back wall of the pylon is post-tensioned.
• Pylon inclination provides signifi cant balance to main span forces.
• Pylon and deck forces resolved at one location and distributed to the foundation
by twin legs.
• Pedestrian access permitted through pylon.
• Pylon and span designed to allow for loss of back stays (i.e. terrorist attack.)
PUENTE DE LA UNIDAD
INTERNATIONAL BRIDGE TECHNOLOGIES, INC.
Monterrey, Mexico
©2009 Copyright International Bridge Technologies, Inc.
Key Features • Main Span cast in 12m (39.3ft) sections.
Edge beams and steel beams cast in place,
followed by pre-cast panels with CIP stitch.
• In place of standard cantilever construction,
a moving casting table was used. The table
would launch to cast each segment and
be supported on the river bed. The bridge
geometry was evaluated on a real-time
basis and adjusted for each new casting.
• New in-line stay damper used to suppress
cable vibrations.
MAIN SPAN
Main Span Section Main Span Section Construction
Pre-cast Panel Placement Completed Bridge, Stay Anchors
Completed Bridge, Elevation