40
Lead and Direct Measure, Analyse and Improve Deliver Enable to Deliver Sasol Technology Commissioning Manual Cleaning of process equipment QMS / 360P/Volume 4.5, Rev 1 Issued by: Commissioning Engineering Applicable to: Internal and external to Sasol Technology Document Control Status: Approved Process Type: Mandatory Key Words: cleaning, washing, steaming 1 Purpose (of this document) The purpose of this mandatory procedure is to describe the techniques and procedures to clean process equipment during the initial operations of a plant. 2 Scope This procedure is applicable to: all process lines; all utility lines; Proposed by : A. Oosthuizen Approved by : R. Brink Validity : This document is only valid for 14 days after 13 May 2022, if printed Copyright : This document is protected by copyright and is the sole property of Sasol Technology. The information is proprietary to Sasol Technology and any unauthorised use, disclosure or copying or any other means of duplication or reproduction is prohibited. Copyright © 2009. Sasol Technology. All rights reserved Page 1 of 40

QMS360P Vol 4.5 Rev 1 Cleaning of Process Equipment

Embed Size (px)

DESCRIPTION

QMS360P Vol 4.5 Rev 1 Cleaning of Process Equipment

Citation preview

Sasol Technology Work Instruction for:

Sasol Technology Commissioning ManualCleaning of process equipmentQMS / 360P/Volume 4.5, Rev 1Issued by: Commissioning EngineeringApplicable to: Internal and external to Sasol TechnologyDocument Control Status: Approved Process Type: Mandatory Key Words: cleaning, washing, steaming1 Purpose (of this document)The purpose of this mandatory procedure is to describe the techniques and procedures to clean process equipment during the initial operations of a plant.2 Scope

This procedure is applicable to:all process lines;all utility lines;vacuum systems;steam boiler;oil systems;oxygen systems; andprocess equipment.3 Revision Description

This document has been rewritten to be in line with the new format for QMS documentation.4 Approvals

Proposed:SIGNED

09/09/2009

Andrew Oosthuizen

Chief Commissioning EngineerDate

Recommended:SIGNED

09/09/2009

Dirk Bosch

Principal Commissioning EngineerDate

Approved:SIGNED

09/09/2009

Richard Brink

Manager Commissioning EngineeringApproved and Effective Date

Any comments and proposals for revisions or additions to be directed in writing to:

MANAGEMENT SYSTEMS [email protected] 4687

Table of contents

Page11Purpose (of this document)

12Scope

23Revision Description

24Approvals

55Purpose

56General precautions

56.1The following precautions are recommended

77Flushing

78Rumbling flushing

89Blowing

89.1Air blowing general

99.2Direct air blowing

99.3Accumulation air blowing

1010Steam blowing

1010.1General

1310.2Steaming

1410.3Fixed program

1410.4Target plate blowing

1511Acid cleaning or pickling

1511.1Chemical cleaning

1811.2Chemical cleaning precautions

1812Degreasing

1812.1Degreasing theory

2013Hand cleaning

2014Pigging

2115Sand blasting

2216Cleaning of oxygen systems

2216.1Preparation

2216.2Cleaning

2316.3Mechanical cleaning

2316.4Aqueous detergents

2416.5High pressure hot water cleaning

2416.6Solvent cleaning

2516.7Inspection methods

2616.8Acceptance criteria

2717Generic machine precautions

2718Appendices

2819Acknowledgements

2820Review Cycle

29Appendix A: Comparisons of cleaning methods

31Appendix B: Definition of cleaning classes

32Appendix C: Cleaning Decision Tree

5 Purpose

5.1 During manufacturing, construction and pre-commissioning of equipment, the surfaces of the equipment is exposed to the environment. This may cause the formation of scales, mildews and rust. 5.2 The manufacturer of the piping or equipment may also apply surface coatings to protect the surfaces against exposure to the environment. 5.3 These contaminants as well as construction debris may result in the contamination of processes, fouling and failure of equipment and thus need to be removed prior to commissioning.

5.4 Several methods exist for the cleaning of equipment and need to be used in conjunction with each other and correctly to provide the required result. These methods include the following:a Flushing

b Air blowing

c Steam blowing

d Acid Cleaning

e Alkaline Cleaning

f Hand cleaning and

g Pigging

h Sand Blasting

i Cleaning Oxygen Systems

5.5 These methods will be discussed in detail in the following sections 6 General precautions

6.1 The following precautions are recommended

6.1.1 For cleaning of process systems, all equipment that can be damaged or fouled during the cleaning process must be removed. These include dosing points, flow meters, injectors etc.

6.1.2 All equipment that restricts the free flow of the cleaning medium should be removed from the system prior to cleaning. These include orifice plates.

6.1.3 All equipment that will be exposed to pressure above their design pressure during cleaning should be removed or isolated

6.1.4 Systems being cleaned should not be exposed to pressures and temperatures above their design conditions

6.1.5 Cleaning methods is intended to remove foreign objects from system, thus ensure adequate free space in front, around and below the point where these objects may exit.

6.1.6 Equipment material of construction should be verified as compatible to the chosen cleaning medium. This include valve internals, filter cartridges, packing, screens and meshes.

6.1.7 At all times wear the appropriate personal protective clothing and equipment.

6.1.8 Within existing facilities or where the owner has taken care, custody and control of the facility a work permit is required for all cleaning work.

6.1.9 Ensure all persons involved are trained and competent to do the work required and operate the applicable equipment

6.1.10 Notification high pressure water cleaning in progress must be placed outside the fence around the work area where applicable.

6.1.11 Working area must be fenced with one entrance.

6.1.12 All high pressure connections must be fitted with anti whip devices.

6.1.13 Ensure that all equipment is in good and safe condition for operation. Plant Supervisor must complete equipment inspection check list in accordance with SSP S-011 1 before any work can commence on the plant.

6.1.14 If equipment is not used correctly injuries can result from:

a hoses coming loose;

b pipes being blocked which may rupture under pressure;

c high pressure water;

d slipping / tripping; and

e if pressure is not released on completion.7 Flushing

7.1 Flushing is the process whereby the kinetic energy of moving water is used to remove loose dirt, construction debris and foreign objects from piping. The kinetic energy can be achieved by means of gravity or by pumping the water through the system

7.2 Flushing is normally used in applications were fluids are used in the process application and water will not have an adverse affect during commissioning and start-up.

7.3 Flushing is effective for piping diameter less than 250mm and a minimum flow velocity of 4 m/s is recommended.7.4 In the case where water movement is provided by pumping, the pump should be protected from dirt and foreign objects by installing a 20 60 mesh or strainer on the suction side of the pump.

7.5 For flushing austenitic stainless steel, the water used for flushing should not contain more than 30 ppm chloride ion. If the water used does contain more than this amount of chloride, it should be flushed with demineralised water; alternatively the piping should be flushed with a neutralizing solution of sodium nitrate. A solution of 4ppm sodium nitrate for every 1 ppm chloride is recommended.

7.6 Piping should be thoroughly drained and dried after flushing and it is recommended that an air connection be provided to dry the system of free water. This is to prevent excessive rust formation in the piping after flushing.8 Rumbling flushing

8.1 Rumble flushing or air rumbling is the process where water is introduced into a system or pipeline, and then under controlled conditions either air, nitrogen or steam can be introduced to increase the effectives of just straight forward flushing.

8.2 The same precautions as with flushing should be followed with the addition the system being flushed should be properly secured as rumbling my cause additional vibrations with the system being cleaned.

9 Blowing

9.1 Air blowing general

9.1.1 Air blowing is normally used in process application which is gas based and the introduction of water into the system may lead to mal-operating during commissioning and start-up.

9.1.2 Larger line sizes can also be cleaned with air blowing compared to water flushing and is dependent on the availability of blowing medium.

9.1.3 For blowing it is recommended that a flow of 35 60 m/s be achieved for effective blowing.

9.1.4 Air or nitrogen can be used as the blowing medium depending on the availability and the process requirements.

9.1.5 If Air is used, the following is applicable:

a Air needs to be readily available.

b If not, compressors will be needed.

c Normally at atmospheric humidity and thus contains water vapour.

d Air can be heated to reduce moisture content.

e Air can be dried using desiccants.

f Air should be oil free.

9.1.6 If nitrogen is used, the following is applicable:

a Nitrogen needs to be dry and oxygen free.

b It must be available in remote location via tankers.

c Large volumes can be maintained through vaporization rigs

d Safety precaution during blowing must be strictly administered.

9.1.7 Two methods of blowing are normally used namely:

a Direct blowing

b Accumulation or kinetic blowing

9.2 Direct air blowing

9.2.1 During direct blowing, the process equipment or piping is connected directly to a continuous constant supply of compressed medium i.e. air or nitrogen. This can be a supply from a utility main, permanently installed compressor in the process or a temporary compressor.

9.2.2 The following precautions should be followed when direct blowing is used:a Nitrogen is heavier than air and displaces it. Sufficient space around the exit point is required for the nitrogen to dissipate into the air.

b Due to the large amount of kinetic energy used in blowing, foreign objects tend to exit the process equipment at high speed. The area in front of the exit point should be kept clear or a solid barrier installed.

c Blowing is associated with excessive noise. The area should be barricaded and personal noise protection used.

9.3 Accumulation air blowing

9.3.1 Accumulation blowing (kinetic blowing) is used were a limited amount of air or nitrogen is available or in larger line sizes where the available air supply is not sufficient to obtain the velocities required.

9.3.2 The method uses the theory of gasses ability to store a large amount of energy though compression and converting it into kinetic energy when suddenly releases.

9.3.3 The method entails the initial compression of the system to be blown with the blowing medium and then suddenly releasing by means a valve or bursting disk.

9.3.4 Two methodologies are normally used, namely:

a Full system compression

b Accumulator firing compression

9.3.5 Full system compression entails the full system to be compressed with a release mechanism installed on the exit point. I bursting disk is normally used. This method is recommended for large, long piping sections as the amount of energy that can be stored is proportional to the system size.

9.3.6 Accumulation compressor entails the use of a drum or accumulator that is installed at the back end of the system, charged with the blowing medium and the released or fired into the system by means of a release mechanism. A fast acting valve is, i.e. ball valve, is recommended. The method is recommended for smaller, shorter systems, as the amount of energy that can be stored is proportional to the size the accumulator used.

9.3.7 An air pressure of between 2 and 3 bar gauge is sufficient to blow a system clean but 3 to 4 blows is normally required.

9.3.8 The following precautions should be followed when accumulation blowing is used:

a Nitrogen is heavier than air and displaces air. Sufficient space around the exit point is required for the nitrogen to dissipate into the air.

b Due to the large amount of kinetic energy used in blowing, foreign objects tend to exit the process equipment at high speed. The area in front of the exit point should be kept clear or a solid barrier installed.

c Blowing is associated with excessive noise. The area should be barricaded and personal noise protection used. An explosion like noise is generated by the sudden release of air and good communication to all relevant parties is recommended.

d Protect all windows in the close vicinity of the blowing activity as the shock wave generated may shatter them.

e Never pressurize the system more than the design pressure of the system.f Accumulation blowing induces large forces on the piping system that may result in it jumping or kicking. The design of the system and supports must be verified to support the forces induced by accumulation blowing. Additional support, kick-blocks and anchors are often required.10 Steam blowing

10.1 General

10.1.1 Steam blowing is generally used for the cleaning of steam utility piping and steam process piping.

10.1.2 The system must be designed to handle the temperature and consequent expansion to utilise this method.

10.1.3 The method uses the combination of kinetic and thermal energy of the steam to remove debris from the line as well as to strip rust and scale from the internal surface of the pipe.

10.1.4 In order to ensure the effective cleaning of pipe internal surface a series of thermal expansion cycles are required to loosen the impurities.

10.1.5 A series of heating and cooling cycles are used to ensure the thermal expansion and contraction of the pipe.

10.1.6 Steam from a main supply or temporary boiler can be used for this procedure.

10.1.7 This method requires the repetitive throttling of the steam flow through or into the system to be cleaned and it is recommended that a sacrificial valve or a throttling glove valve be in stalled to regulate the flow.

10.1.8 After blowing, the valve, or internals, should be replaced. A bypass valve a of the line size being cleaned is recommended for effective heating of the line.

10.1.9 Two methodologies can be used to determine the amount of steam required for blowing:

a Mass- flow criteria

b Disturbance factor criteria

10.1.10 Mass flow Criteria

The mass flow criteria state that the mass flow used for blowing the system, should be equal to the mass flow in the system during normal full load operation

10.1.11 Disturbance factor criteria

The concept of disturbance factor is to pass steam through the line so as to carry the debris more effectively than would be accomplished by steam flow at normal full load requirements. This results in the need for steam blowing with greater kinetic energy than that of the normal operating condition.

The disturbance factor is the ratio:

This can be expressed as:

Where V is the specific volume of the steam and F is the mass flow rate of the steam.

Subscript 1 refers to the blowing condition, and subscript 2 refers to the normal maximum load condition.

10.1.12 The ratio, sometimes also called the shifting factor, should be greater than one.

10.1.13 Experience has shown that a line blown with a disturbance factor of 1, 5 or greater is well cleaned, once acceptable target plates have been obtained. The disturbance factor must be assessed just downstream of the throttling valve, or at the initial point of cleaning.

10.1.14 The following precautions should be noted of during steam blowing:

a A thorough potential deviation analysis (PDA) should be done on each steam blowing application to identify all the relevant risks and develop mitigating actions.

b Sufficient size drains should be installed on the steam piping to remove solid foreign objects. On larger lines it is recommended that the entire line be visually be inspected prior to blow to ensure it is free from large foreign objects. Failure to do so might lead to the system having to be cut open, cleaned and re-welded or fitted to remove the objects.

c Remove all condensate traps prior to blowing the system.

d Trap systems should be provided with throttling globe valves to control the steam escaping through the traps during the heating cycle.

e Thermal expansion should be monitored during the first heating and cooling cycled and verified with the design and by site inspection to confirm expansion slide plates remain on their supports. The system should be heated to full design temperature to fully evaluate the thermal expansion.

f All scaffolding or temporary platforms on or close to the system being blown should be removed. It is recommended that the whole system be inspected prior to blowing for any equipment that might limit the movement of the system

g Considerable noise generation is normally associated with steam blowing. A silencer arrangement, with particle al screen, should be used to limit the noise generated. Such a silencer should be securely mounted on an engineering approved support or base. Silencers repeatedly used for such applications, should be regularly inspected for cracks on the internals. It is recommended that such silencers be inspected by approved inspection authority prior to each application.

h Lagging should be installed on the steam line prior to blowing. This will not only ensure the safety of the personnel but also ensure effective heating up of the system. On long piping section is almost impossible the heat the piping to design temperature without lagging being installed as it is part of the design intent.

i For lines blown in opposite directions than normal process flow, the thermal expansion design should be verified for the flow direction during blowing.

j Heating up should be done slowly through the steam traps bypasses in order to effectively drain all condensate and thus preventing water hammer.

k The line should always be kept open during the cooling down cycles to ensure that a vacuum does not form which can result in the collapse of the piping or associated vessels.

l After the full cleaning cycle the line should be placed in service as soon as possible or preserved under nitrogen blanket.

m Valves in the system should be heated fully and the differential pressure equalized prior to being operated. During blowing, these valves should be fully open or fully closed to ensure that they are not damaged.

1.1.2 Three methodologies can be used for steam cleaning:a Steaming applicable to utilities lines and steam tracing

b A fixed program for heat exchangers, steam injectors, atomizers, vessels, drums, de-super heater and any other steam equipment using steam or generating steam that will NOT BE USED IN TURBINE APPLICATIONS

c Steam blowing to target plate specification for steam systems that generate on transport steam to turbines applications

10.2 Steaming

Steaming entails the single blow of a system with steam until it is free from debris and foreign objects.10.3 Fixed program

10.3.1 Fixed program entail the blowing of the system in three consecutive cycles up to, or as close as possible, to design temperature.

10.3.2 Blowing for 10 15 minutes at this temperature and then cooling down to a surface temperature at least 200oC below the blowing temperature.

10.3.3 The delta temperature between hot and cold stages will ensure enough thermal expansion to release mill scale and rust.

10.4 Target plate blowing

10.4.1 Target plate blowing consists of blowing to a target plate specification. This specification entails the installation of a small metallic plate in the main steam flow, at a right angle, and measuring the amount of impacts, caused by small debris particles, rust and mill scale during blowing, after each blow.

10.4.2 Depending on the application various materials are used for the target plates including:

a carbon Steel;

b stainless steel;

c aluminium; and

d brass.

10.4.3 The manufacturer of the applicable equipment that will be serviced by the related piping will specify a target plate or impingement specification. Such a specification should include the following:

a Material to be used for target plate ea. Carbon steel

b Duration of impingement blow ea hour

c Area size to be inspected ea. 10cm2

d Number of raised impingement /embedded pits per area ea. one

e Number of impingement per area ea < 2/cm2

f Acceptable size of such impingements ea < 1 mm

10.4.4 In absence of such a guarantee specification requirement, the following is generally used for steam driven turbines:

a Stainless steel target plate, polished to mirror finish

b 15 min blow at superheated temperature

c No raised pits

d Less than1 impingement larger that 0.5 mm per square centimetre

10.4.5 To obtain such stringent specification the following guidelines should be followed:

a A minimum of 3 cycles of blowing is recommended before measurement start.

b Blow at least design flow and temperature for 3 hours during each cycle.

c Up to 10 cycles of blowing may be required to reach specification.

d Cooling down the pipe external temperature during the cooling cycle to below 200oC that of the external surface during blowing. This will ensure adequate thermal expansion and contraction to loosen mill scale and rust.

e Use of brush pigging prior to steam blowing will reduce the blowing cycles required.

f Internal sandblasting, with fine specification sand, of fittings prior to installation will reduce team cycles required to reach the specification.

g Install target plates after blowing, before cooling down, to measure specification. Condensate present in the steam during warming up of the system from cold may also cause impingement on the plate which will thus not be a true reflection of the surface quality of the piping.11 Acid cleaning or pickling

11.1 Chemical cleaning

11.1.1 Chemical cleaning is reliant on the properties of some acid chemicals to dissolve rust, slag and mill scale that forms on the metal surface and is used in various systems:

a Compressor suction piping

b Boiler feed water systems

c Oil systems of rotating equipment

d Oxygen service systems

11.1.2 Acid cleaning is not required for stainless steel systems care must be taken in designing the circulating system to ensure the entire system is sufficiently exposed to the cleaning and neutralising medium. Specific care must be taken in system where crevices are present as it is difficult to ensure complete neutralisation in these areas leading to corrosion.

11.1.3 Mineral acids such as hydrogen chloride or organic acid such as citric acid is normally used, but an approved; experience contractor will recommend the correct formulation for the specific application.

11.1.4 Two methods of acid cleaning are generally used:

a Dipping in a solution

b Circulating a solution

11.1.5 Acid cleaning is always done in a sequence of stages. The stages are as follows:

a Flushing

b Degreasing

c Intermediate rinsing

d Acid cleaning or Pickling

e Main Rinsing and Neutralizing

f Passivation

g Drying

h Preservation

11.1.6 Each of these steps will be discussed briefly:

a Flushing

i) Flushing with water is used to remove foreign objects, dust and debris from the system. Excessive amounts of debris and dust may also negatively impact on the reactivity of the acid.

ii) Flushing can also be used to test the circulation equipment being used for the acid cleaning for effectiveness and leaks.

b Degreasing

Decreasing is used to remove excess oil, lubricant and organics that is insoluble in acid from the system. Deceasing will be discussed in detail in the next section.c Intermediate flushing

Flushing with water at approximately 70oC for 15 minutes will neutralize the degreasing agent prior to acid cleaning. Full neutralization should be tested with a pH paper test on the surface of the piping or by measuring the pH of the flushing water.d Acid Cleaning/Pickling

iii) The solution used can be a solution of Hydrochloric or Citric acid at a 10% wt solution with water. A corrosion inhibitor should be added to prevent the equipment from rusting as it is removed from the bath or drained.

iv) The temperature of the solution should be between 60 70oC and agitated or circulated continuously.

v) 12 hours is recommended for an exposure period depending on the strength of the solution but 6 hours should be taken as a minimum.

vi) The pH of the solution should be constantly monitored to the suppliers specification and if the amount of Iron ion in the solution exceeds 0.4% by weight, the solution should be replaced.

vii) The solution should be disposed of in a responsible manner after being drained

e Main Rinsing and Neutralizing

viii) The system should not be allowed to dry prior to rinsing. Rinsing or neutralization can be done by means of flushing with clean water or with a neutralization solution of 1% to 1.5% wt Soda ash in water. Such solution should be at a pH of above 9 and at a temperature of between 70oC and 80oC

ix) Circulation of the neutralization solution should be for at least 10 minutes and the pH of the wet surface should be neutral afterwards. pH paper can be used for this test.In complex systems, all supply and return lines must be monitored to ensure continuous flow through each line. Restriction in any line may lead to the acid not being neutralised and consequent corrosion will damage that portion of the system.

f Passivation

Passivation is done to form a protective layer of Fe3O4 on the internal surface of the piping. This layer is normally a thin black hard layer. Passivation chemicals are normally proprietary solutions supplied by the contractor, but often have an amine base.g Drying

The system should be completely dried after acid cleaning by blowing it with nitrogen or warm airh Preservation

After chemical cleaning the system should be preserved under a nitrogen blanket or put into service as soon as possible11.2 Chemical cleaning precautions

11.2.1 The following precautions should be followed during chemical cleaning:

a A thorough potential deviation analysis (PDA) should be done on each chemical cleaning application to identify all the relevant risks and develop mitigating actions.

b Relevant and applicable safety clothing should be used at all times

c Disposal of chemical solution should be according to the local and company regulations

d MSDS documentation must be available for all chemicals used.

e Material compatibility test must be done on all material in the system to be chemical cleaned with the relevant cleaning solutions. This includes valve internals, gasket material, busting discs and sealants.

f Ensure that all chemical solution required are onsite and available prior to commencing the cleaning.

g Ensure that a temporary emergency shower is available in close proximity, during the cleaning operations

h Clearly demarcate the area in which the cleaning process take place and regulate access to this area.

i Acid cleaning should always be done by an approved and reputable contractor.

12 Degreasing

12.1 Degreasing theory

1.1.3 Degreasing uses the chemical theory that mineral oils and fats can be torn off the surfaces with a caustic solution and then be suspended in the solution while organic oils will be hydrolysed to glycerine or aliphatic sodium salts in the same solution thus degreasing the specific system.

1.1.4 The process is generally used to:a clean stainless steel piping;b clean carbon steel piping prior to acid cleaning;c clean out boiler drums; andd clean amine systems to prevent foaming during operation.

1.1.5 The system should be thoroughly flushed prior to commencing degreasing.1.1.6 Sodium Hydroxide or Sodium Carbonate is generally used to perform degreasing within a solution with water under the following conditions:a Sodium Hydroxide, 6% solution, 80oC-90oC, for 30 minutes

b Sodium Carbonate, 2% solution, 80oC-90oC, for 30 minutes

1.1.7 After degreasing the system should be thoroughly flushed until the pH of the flushing water is below 8.5.

1.1.8 The following precautions should be followed during chemical cleaning:a A thorough potential deviation analysis (PDA) should be done on each chemical cleaning application to identify all the relevant risks and develop mitigating actions.

b Relevant and applicable safety clothing should be used at all times.c Disposal of chemical solution should be according to the local and company regulations.d MSDS documentation must be available for all chemicals used.

e Material compatibility test must be done on all material in the system to be chemical cleaned with the relevant cleaning solutions. This includes valve internals, gasket material, busting discs and sealants.

f Ensure that all chemical solution required are onsite and available prior to commencing the cleaning.

g Ensure that a temporary emergency shower is available in close proximity, during the cleaning operations.h Clearly demarcate the area in which the cleaning process take place and regulate access to this area.

i It is recommended that degreasing be done by an approved and reputable contractor.13 Hand cleaning

13.1 Hand cleaning is the principal of rubbing, wiping, broom sweeping, sanding or brushing the internals of equipment, including vessels, reactors and piping diameters larger than 600mm.13.2 The following precautions should be followed during any hand cleaning activity:a A vessel entry permit is required for any duty where a person is required to stick his head into an enclosed space. All vessel entry precautions must be adhered to during such cleaning processes.

b Relevant and applicable safety clothing should be used at all times.

c A standby person is required to monitor and assist the employee executing the cleaning when required.

d Only 24V supply and lower lighting may be used in an enclosed space.

e Continuously monitor the air quality as required by the vessel entry permit conditions.14 Pigging

14.1.1 PIG or Pigging is an abbreviation for Pipeline Inspection Gauge.

14.1.2 Pigging is the method generally described as the forcing a bullet shaped object, or a pig, through the line to perform some method of mechanical cleaning on the inside surface of the pipe. The pig is forced hydraulically by means of water through the pipe. Air is more commonly used.

14.1.3 Pigs are generally used in long pipelines that are difficult to access or require large volumes of water, air, steam or chemical solutions to clean.

14.1.4 Pigs for various duties are available, including the following:

a Rubber pigs for water removal.

b Foam pigs for removal of foreign objects and construction debris.

c Brush pigs for abrasive cleaning.

d Intelligent pigs for wall thickness measurements.

e Slug pigs for containing a batch or slug of chemical cleaning solution between a set of two pigs.

14.1.5 Systems normally require some design changes to enabling pigging to occur. This includes the following:

a Space at the start and end of the piping section for pig launchers and pig receivers. These are normally piping sections, bolted onto the pipe, with larger diameters than the pig it should launch or receive and has normally a hatch or manhole to load and unload the pigs.

b Pigging bars should be installed in equal diameters T to direct to flow of the pig

c Design pressure of pipe section should be evaluated to withstand the hydraulic forces.

d Piping supports should be reviewed and temporary supports installed where required withstanding the increase vibration caused by the pig.

14.1.6 A recommended pig velocity is between 1 and 4 m/s but depends on the application and the pigs being utilized.

14.1.7 It is recommended that pigging be done by an approved and reputable contractor.15 Sand blasting

15.1 Sandblasting is the method of cleaning the internal or external service by blowing a powerful jet of abrasive material onto the surface.

15.2 The following precautions should be followed during any sand blasting cleaning activity:

j A vessel entry permit is required for any duty where a person is required to stick his head into an enclosed space.

k Relevant and applicable safety clothing should be used at all times.l A standby person is required to monitor and assist the employee executing the cleaning when required.

m Only 24V supply and lower lighting may be used in an enclosed space.n Continuously monitor the air quality as required by the vessel entry permit.15.3 The following guidelines can be followed for sand blasting cleaning:

a Sandblast the lines internally to a finish of SA2.5 and inspect line internally with a boroscope.

b Avoid damaging the flanges when withdrawing the sand blasting head form the pipe. Flanges faces can be taped for protection.

c Care should be taken at elbows to avoid wall thinning.

d Dry, oil free, air or nitrogen should be used to blow the grit or aluminium oxide. Metallic shot is not recommended.

e Sandblasted surfaces should always be immediate preserved after cleaning, as the bare metal surfaces will start to rust immediately.

15.4 Sand blasting blowing speeds for different pipe bore sizes is suggested as follows:

o 25 mm Blow through

p 50 mm Blow through

q 75 mm 30 seconds per meter

r 100 mm 35 seconds per meter

s 150 mm 50 seconds per meter

t 200 mm 70 seconds per meter

u 300 mm 100 seconds per meter

16 Cleaning of oxygen systems

16.1 Preparation

1.1.9 Oxygen systems are defined as all pipe work and equipment containing pure gaseous oxygen or gas mixtures containing more than 23% oxygen.

1.1.10 Oxygen system needs to be cleaned properly prior to the introduction oxygen, as the presence of surface contamination, minute solid particles, oil or grease on the surface of the piping and equipment in the presence of gaseous oxygen may cause spontaneous combustion and subsequent fire.

1.1.11 All equipment items, instrumentation and valves are required to be designed, manufactured, supplied, transported and stored for oxygen service.

1.1.12 The contractor shall inspect all equipment and piping components prior to commencing fabrication, to ensure that all protective coatings have been removed. Any protective coatings shall be removed as a separate operation to any cleaning for oxygen service.16.2 Cleaning

16.2.1 Several methods of cleaning may be used to achieve the required level of cleanliness. The final choice will depend on the type of equipment or component, the length and layout of pipe work, the timing and location of cleaning operations etc. These include:

a Mechanical cleaning

b Aqueous detergent cleaning

c High pressure hot water cleaning

d Solvent cleaning

16.2.2 Most aqueous or solvent cleaners are not compatible with oxygen or leave non-compatible residues behind; therefore scrupulous care shall be taken in rinsing thoroughly immediately after the cleaning process to ensure the complete removal of all traces of the cleaning solvent.

16.2.3 Prior to commencing any solvent or aqueous cleaning, Contractor shall certify that the solvent or aqueous cleaner proposed for use is non-injurious to all the materials (metallic and non-metallic) used in the manufacture or fabrication of the item or component being cleaned.

16.3 Mechanical cleaning

16.3.1 Mechanical blast cleaning with grit or aluminium oxide using dry, oil free air, nitrogen or high pressure water as the carrier medium is acceptable for large, easily accessible areas.

16.3.2 Metallic shot shall not be used.

16.3.3 The use of proprietary abrasive cleaning processes as such shall be subject to specific review and approval by owner.

16.4 Aqueous detergents

16.4.1 Aqueous detergents shall be supplied in concentrated liquid form and shall be mixed according the manufacturers recommendation.

16.4.2 The solution may be heated to 50-650C to increase its effectiveness.

16.4.3 The following cleaning solutions have proved effective in obtaining the required level of cleanliness when used in accordance with the manufacturers recommendations:-

a Blue Gold Cleaner

b Beyond 2001(c Simple Green(d Crystal Simple Green(16.4.4 For larger equipment items high pressure, hot water cleaning with aqueous detergent may be used.

16.4.5 For piping systems, the aqueous detergent solution shall be circulated for a minimum of two hours or the manufacturers recommendation (whichever is longer) and then flushed with hot, clean, potable water until all traces of detergent are removed.

16.4.6 The system shall be dried with dry, oil free air or nitrogen or a combination of both.

16.4.7 The spent cleaner shall be disposed of in accordance with the manufacturers recommendation and local and national regulations.

16.5 High pressure hot water cleaning

16.5.1 Pre-wash the surface with hot water (at least 900C) to heat any oil or grease and reduce its viscosity followed by spraying with an aqueous detergent cleaner.

16.5.2 After the soak period as recommended by the manufacturer, wash the surface with hot water and allow drying.

16.5.3 The cleaning water shall be disposed of in accordance with local and national regulations.16.6 Solvent cleaning

16.6.1 Solvent cleaning may be accomplished in a one-step or two-step procedure.

16.6.2 The choice of which method to use will depend on the degree of contamination with oil and grease.

16.6.3 For heavily contaminated surfaces a two step procedure is recommended.

16.6.4 Recommended one step solvents are:

a Borothene

b Leksol(c AK 225

d Vertrel(e Novec(16.6.5 For two set solvent cleaning, the recommended first step solvents are:

a Art 98

b Glidsol( 66-2

c Actrel( 3349L

16.6.6 For piping systems the method of solvent cleaning shall be agreed with the owner.

16.6.7 Wherever possible solvents shall be sprayed onto the surface ensuring that all parts of the surface are contacted.

16.6.8 Where spraying is not possible, solvent shall be circulated for at least one hour or the manufacturers recommendations, whichever is greater.

16.6.9 The system shall be dried with dry, oil free air or nitrogen or a combination of both.

16.6.10 The spent solvent shall be disposed of in accordance with the manufacturers recommendations and local and national regulations.

16.6.11 Prior to any solvent cleaning, a fresh sample shall be stored for reference purposes.

16.7 Inspection methods

16.7.1 Immediately after drying, inspection shall be performed by each of the following methods:

a Visual inspection under a bright, white light.b Visual inspection under an ultraviolet light (wavelength 32-38m, 3200 4000 Amstrom units).c Light to be warmed up for 5 min prior to use

i) Inspection should not be carried out in direct sunlight or under florescent lighting

ii) Lighting intensity of light on the surface to be tested shall not be less than 500W/cm2

iii) Light should be kept 20 30 cm form the surface tested

16.7.2 Visual inspection by wiping and inspecting the wipe medium under bright, white light and ultraviolet light. For the wipe test, inspection shall be performed by wiping approximately 0.1m2 with a clean, white, lint-free cloth, or clean, lint-free filter paper.

16.7.3 If surfaces cannot be inspected visually, but hand access is possible, a wipe test as specified shall be utilised.

16.7.4 If it is not possible to perform a visual inspection or wipe test, a quantity of unused solvent shall be circulated over the surfaces. A 100ml sample shall be collected in a clean, glass container and examined for compliance, after which a 20ml sample shall be evaporated to dryness on a clean watch glass and examined for compliance.

16.8 Acceptance criteria

16.8.1 For final acceptance, oxygen systems shall be inspected either immediately prior to final closing welds (for items subject to pre-fabrication cleaning) or after post-erection cleaning and shall meet the following criteria:

a No moisture present

b No cleaning agent residue present

c No corrosion scale, particulate matter, weld spatter, flux residue from welding, cutting swarf or foreign materials such as sand or site debris present

d No paint, crayon or protective coatings present

e No hydrocarbon or organic material residues, such as oil, grease, adhesives or sealants present.

16.8.2 Visual inspection under ultraviolet light shall show no evidence of hydrocarbon fluorescence or significant quantities of textile fibres (not greater than 75 particles per 0.1m2). Areas of low intensity fluorescence shall be re-examined visually and with a wipe test to determine acceptability.

16.8.3 Where a wipe test is performed, no discolouration of the wiping medium, except that caused by oxidation of the parent material, no evidence of oily residue or any other visible particles on the wiping medium and no evidence of hydrocarbon fluorescence.

16.8.4 For the analysis of the circulated solvent, if laboratory analysis is available, a level of 200mg/m2 is considered an acceptable maximum for oil films.

16.8.5 For the evaporation test the sample shall not contain more than 20mg/kg residue.17 Generic machine precautions

17.1 During cleaning various high pressures portable equipment may be used for the provision of:

a steam;b air;c nitrogen;d vacuum; ande liquid circulation;17.2 The following general precautions should be followed with such machines and related auxiliary equipment:

f Make sure the machines are in a good operating condition. Most suppliers would be able to provide an equipment check sheet. The inspection check sheet should be in accordance to SSP-S-0111.

g All safety documentation for the equipment must be available on site ea. RV setting certificates, Pressure vessel inspection information etc.

h Declaring of competency must be available for the operators of the machines.

i All piping connections should be according to Sasol specification.

j Area around the machine should be demarcated or barricaded.

k Ensure that all personnel are trained to operate the equipment.

l The task at hand should be well understood.

m A risk assessment is required before the work start. This could be in the form of a possible deviation analysis (PDA).

n All flexible connection must be fitted with anti whip devices.

o Ensure that all nozzle connections is secure.

p During any high pressure cleaning a notice must be posted at the work area indicating that high pressure cleaning in progress.

q All electrical connections should be according to Sasol specifications.

r The person operating the machine should always be in eye contact with the operator performing the cleaning actions.

18 AppendicesAppendix A: Comparisons of cleaning methods Appendix B: Definition of cleaning classesAppendix C: Cleaning decision Tree 19 AcknowledgementsAcknowledgement to the following departments and persons for their contributions to this document:Dirk Bosch

Tas van Staden

Management Systems

20 Review Cycle

This document to be reviewed within:

6 months

1 year(

2 years

3 years

Appendix A: Comparisons of cleaning methods

MethodCleaning MethodProcess ApplicationEffectivenessMedium usedMin DiameterMax diameterCyclesPressureFlow

1FlushingLiquid EquipmentDebrisWaterN/A250mm1N/A> 4m/s

2Air blowing - DirectGas PipingDebrisAir or NitrogenN/A600 mm1N/A35 60 m/s

3Air blowing - AccumulationGas PipingDebrisAir or NitrogenN/A600 mm3-42-3 barN/A

4Steam Blowing - SteamingSteam UtilitiesDebrisSteamN/AN/A1N/ADesign

5Steam Blowing ProgramSteam Process EquipmentScale and rustSteam N.AN/A3N/ADesign

6Steam Blowing TargetSteam TurbinesScale and rustSteam N.AN/A4 -8N/ADesign

7Acid CleaningTurbine Suction

Oil systems

Oxygen systems

Boiler feed waterScale, rust, mill scaleInorganic/Organic AcidN/A600 mm1 cycle

7 stepsN/A

MethodCleaning MethodProcess ApplicationEffectivenessMedium usedMin DiameterMax diameterCyclesPressureFlow

8DegreasingBoiler drums

Amine Systems

Pre- acid cleanMineral and organic oils and fatsSodium Hydroxide

Sodium Carbonate

N/A600 mm1 Cycle

3 stepsN/AN/A

9Hand cleaningVessels

PipingDebrisElbow grease600 mmN/A1N/AN/A

10PiggingLong PipingFree Water

Debris

Scale and rustSynthetic Pig

Water or Air to drive pig50 mm850mm1-101 -4 bar/m2 pipe diameter1 1.5 m/s

11Sand blastingVessels & Large PipingScale, rust and protective coatingsSand, grid or alumina oxide250 mmN/A1N/AN/A

Appendix B: Definition of cleaning classesClassDefinition

1 Remove all lose debris

2 Remove all debris

Remove adhered material that would come loose under operation

3 Remove all debris

Remove adhered material that would come loose under operation

Remove all oil, grease and protective coatings

4 Remove all debris

Remove adhered material that would come loose under operation

Remove all oil, grease and protective coatings

Remove rust, mill scale and welding spatter to achieve bare metal.

Appendix C: Cleaning Decision TreeLead and Direct

Measure, Analyse and Improve

Deliver

Enable to Deliver

Proposed by:A. OosthuizenApproved by:R. Brink

Validity:This document is only valid for 14 days after 29 September 2009, if printed

Copyright:This document is protected by copyright and is the sole property of Sasol Technology. The information is proprietary to Sasol Technology and any unauthorised use, disclosure or copying or any other means of duplication or reproduction is prohibited. Copyright 2009. Sasol Technology. All rights reservedPage 1 of 32

_1027755793.unknown

_1027756018.unknown