QMUL2/2/12
1
Current status of new alignment system.Drawing status update.Laser alignment.Module removal from frames for new kit. Stave(lets ) for 2012Module frame thoughts.IV tests and silicon
Current state of the new alignment system.. But about 50% of it has to be dismantled for the granite in mid Feb
started now....
2
Light curtain Tx
Prototype laser
Light curtain mirror
Drawing Status
• David Mongomery (Marks’s Ex boss) has contacted Mark on his mobile.
• Apparently he sent a package to me with drawing etc. Unfortunatley nothing has arrived.
• David has printed off the list of models Mark was working on.
• MDG now trying to decide just what it all means.
• David to arrange a meeting with Ian and myself to see just who will be doing the work.
3
Laser support
4
Where we started fromusing standard optical components
Where we finished.With a custom support. Awaiting it’s cover
Laser module ND filter pinhole
Aluminium reference support for granite
Completed X,Y,Z,Theta stage set for removing modules onto vacuum jig by support from underneath
5
Summery of Stave(let) to build in 2012
• Shield studies stavelet. (C channel, presumably single sided ?) Could use existing frame. If not fitted with locking points. Note:- we only have one C channel frame. We could have 2 if we fit modified pins
to the other (US) frame. But....
• Stavelet 4 (probably made by the US so not our problem hopefully! But see above)
• Electrical stave 250 (still to be confirmed, may be double sided) Might fit existing frame BUT may need support for EOS card. Perhaps this needs a
drawing?. Again no locking points.
• Electrical stavelet (130nm). Probably needs new frame.
6
7
Option 1Modify locking point
Option 2Make temporary extension
8
Option 3 Make wider core
9
Option 4Make more offset BCC
10
Option 5Make 2 part locking point
11
Option 6With a change of module........
FOR AGAINST
Option 1, modify locking point
Moves locking point away Needs yet another set of moulds etc for a temporary problem.
Option 2,Make temporary custom ext
Means that the 120mm stave are OK. No need to modify anything
Extra leaverage.Increases frame width
Option 3, wider core
Keeps stiffness Needs new jigs etc etc
Option 4, modify BCC
No chance
Option 5, 2 part clamp
neat Needs more design and R+D. Removal for re-work not nice! Post construction fitting not good.
Option 6 , new module
neat Long term...
12
Thoughts..• Separate out the locking point problem from the stave population.
• If we make an temporary extension piece then everything we have (with the exception of the new frame) works as before.
• As far as mounting tests go, one can make special narrow version of the core.
• We can make special wide frames if we want to use extension pieces to prove the point.
• We can say very little about the new modules BUT it is important that the module, stave , locking point , frame designers and module placement people all talk to each other. At the moment we are very disconnected!
• Only one constraint .. the granite and hence the distance apart of the two walls has a maximum value of approximately 385mm Meaning the frame can not be wider than 380mm approximately
But this needs to be checked on a drawing ......
13
What to test re... Iv’s
• Aim is to measure I/V. Objective is to prove adhesive has no effect...So..• Perform I/V on naked silicon, or a module depending on what I receive.• Stick onto dummy stavelet. ( I have such an item but with no cooling tubes)• Measure I/V after cure at room temp.• Cycle between +30 and -60 and then re-measure at room temp. (We can place the whole stavelet into our environmental chamber and we have a box
that we can flood with N2)• Measure I/V at +30 and at -60. (we can do this inside the chamber) • Cycle a number of times• Re-measure.
• Awaiting offer of silicon from Ashley
• If we do not do this, what are we going to use to stick modules onto our next stavelet? This is the SP shield studies stavelet that was/is expected in Jan 2012.
14