29
MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY document.xlsBMS DSP-qf-PRJ-02 Rev.1 PROJECT Number Contractor Shop Drawings Submittal Log Client : Page Contractor: Approval & Signature Sequen Report Da Contract & Project Name : Project Director 2nd Ap Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap. Design Engineer # 1 Design Engineer # 2 Design Engineer # 3 RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV. Action Code: Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Specification No. No. Sequence B = Approved as Noted or B.O.Q No. C = Not Approved (Or Teansmittal Number) D = For Information APPOINTED DES Eng DES#1, or 2 or 3 Planned Date Returned Action Approval Required Sub. Date Submitted By A/E Needed By On Site Building Management System BM-01 R2 1 0 BM-02 R2 2 BM-03 R2 3 etc …….. ….. ….. ……..

QRD-OP-08 Shop Drawings Submittals Log

Embed Size (px)

Citation preview

Page 1: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xlsBMS DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Building Management System

BM-01 R2 1 0

BM-02 R2 2

BM-03 R2 3

etc …….. ….. ….. ……..

Page 2: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Security & Access Control

SA-01 R1 1 0

SA-02 R1 2

SA-03 R1 3

etc …….. ….. ….. ……..

Page 3: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Telecommunication

S-03 R2 1 0

T-01 R1 2

T-02 R1 3

etc …….. ….. ….. ……..

Page 4: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

Page 5: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Voice Alarm

VA-01 R1 1 0

VA-02 R1 2

VA-03 R1 3

etc …….. ….. ….. ……..

Page 6: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

QRD-OP-08

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Page 7: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Electrical

E-00 1 0 ESD-00

E-01 R1 2

E-02 R1 3

etc …….. ….. ….. ……..

Page 8: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Fire Fighting

FF-01 R1 1 0

FF-02 R1 2

FF-03 R1 3

etc …….. ….. ….. ……..

Page 9: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Drainage (Foul & waste Water)

S-01 R2 1 0

DR-01 R2 2

DR-02 R1 3

etc …….. ….. ….. ……..

Page 10: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

Page 11: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Cold & Hot Water Supply

S-0 R1 1 0

PL-01 R2 2

PL-02 R2 3

etc …….. ….. ….. ……..

Page 12: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Lighting Protection

LP-01 R1 1 0

LP-02 R1 2

LP-03 R1 3

LP-04 R2 4 ….. ……..

Page 13: QRD-OP-08 Shop Drawings Submittals Log
Page 14: QRD-OP-08 Shop Drawings Submittals Log

MATHAHER EL TATWEER FOR CONSTRUCTION COMPANY

document.xls DSP-qf-PRJ-02 Rev.1

PROJECT Number Contractor Shop Drawings Submittal Log Client : Page

Contractor: Approval & Signature Sequen Report Date

Contract & Project Name : Project Director 2nd Ap

Project Contact Person (i.e PM / PE / etc..) Site Representative 1st Ap.

Design Engineer # 1

Design Engineer # 2

Design Engineer # 3

RELEASED FOR FINAL APPROVAL BY THE CLIENT OR HIS REPRESENTATIVE YES / NO REV.

Action Code:Document Item Rev. Sub. Shop Drawing Description A = Approved as Submitted Notes

Specification No. No. Sequence B = Approved as Notedor B.O.Q No. C = Not Approved

(Or Teansmittal Number) D = For Information

APPOINTED DES Eng

DES#1, or 2 or 3 Planned Date Returned Action Approval Required

Sub. Date Submitted By A/E Needed By On Site

Air Conditioning & Ventilation

AC-01 - 1 Of 2 R3 1 0

AC-02 - 2 Of 2 R2 2

AC-02 R3 3

etc …….. ….. ….. ……..