    Engr Nand Kumar SoofiDir QS), NHA Islamabad

    PRESENTED BY

    QUANTITY SURVEYING & ESTIMATION

    NATIONAL HIGHWAY AUTHORITY

  • 8/13/2019 Qs and Estimation Presentation

    3/42

    Quantity surveying is primarily related to construction and the management of the

    cost and budget of the projects.

    Role of Quantity Surveyor starts from conceptual stage till the financial closure of the

    project.

    A Quantity Surveyor is likely to be involved in a contractual , technical and financial

    capacity.

    QUANTITY SURVEYING & ESTIMATION

    QUANTITY SURVEYING

  • 8/13/2019 Qs and Estimation Presentation

    4/42

    QUANTITY SURVEYOR (QS) is a construction management professional.

    The functions of a Quantity surveyor are broadly concerned with the

    control of the cost on construction projects, the management and

    maintenance of the budget, valuations and any contractual matters arising

    through the course of the project .They are required to make sure that theproject remain feasible and efficient.

    QUANTITY SURVEYING & ESTIMATION

    QUANTITY SURVEYOR

  • 8/13/2019 Qs and Estimation Presentation

    5/42

    Whenever any Project is proposed, it is important that the cost involved is known in

    advance.

    These include :

    Construction Cost (Direct Cost) Labour Materials

    Plant

    Overheads & Profit (Indirect Cost) Site Preparation Cost

    (Including Mobilization & De mobilization Cost)

    Professional fees, Taxes, Insurances , Bank charges , Staff expenses and othercharges

    Running and maintenance Costs for the new Road/Building.

    Profit of the Company

    QUANTITY SURVEYING & ESTIMATION

    QUANTITY SURVEYOR

  • 8/13/2019 Qs and Estimation Presentation

    6/42

    Estimation of Project

    Item Rate Analysis

    Procurement of Materials Invoices or Bills / IPCs

    Escalation Payment Certificates

    Variation Orders

    Cash Flow Plans Financial Management i.e. controlling budget of project

    Contract Administration related to financial matters.

    QUANTITY SURVEYING & ESTIMATION

    ROLE OF QUANTITY SURVEYOR

  • 8/13/2019 Qs and Estimation Presentation

    7/42

    QS

    CostEstimation

    Measurement

    ProcurementPrice

    Adjustment

    Payment

    QUANTITY SURVEYING & ESTIMATIONRESPONSIBILITIES OF QS

  • 8/13/2019 Qs and Estimation Presentation

    8/42

    MEASUREMENT

    The process of measuring the quantities / scope of works is known as measurement.

    Controlling the construction cost by accurate measurement of the work is required in the

    construction industry.

    MEASUREMENT

    Also known as TAKING-OFF

    QUANTITY SURVEYING & ESTIMATION

    MEASUREMENT

  • 8/13/2019 Qs and Estimation Presentation

    9/42

  • 8/13/2019 Qs and Estimation Presentation

    10/42

    By using this Measurementknowledge, a QS will be able:

    To prepare the Bill of Quantities or Specification document for

    tendering purposes.

    QUANTITY SURVEYING & ESTIMATION

    MEASUREMENT

  • 8/13/2019 Qs and Estimation Presentation

    11/42

    Bill of Quantities(BOQ)

    The BOQ is a document used in tendering in the construction industry in which

    materials, parts and Labor are itemized.

    In the BOQ item wise quantities/scope of works is mentioned. The quantities are

    measured / Taken off from design drawings and specifications.

    BILL OF QUANTITIES (BOQ)

    QUANTITY SURVEYING & ESTIMATION

  • 8/13/2019 Qs and Estimation Presentation

    12/42

  • 8/13/2019 Qs and Estimation Presentation

    13/42

  • 8/13/2019 Qs and Estimation Presentation

    14/42

    ESTIMATIONThe process of calculating the quantities of various items of work,

    and the expenses likely to be incurred.

    The estimated cost of a work is a close approximation of its actual cost.

    PURPOSEto give the owner/ client a reasonably accurate idea of the cost to help

    him to decide whether the work can be undertaken as proposed or needs to be

    curtailed or abandoned, depending upon the availability of funds and prospectivedirect and indirect benefits.

    QUANTITY SURVEYING & ESTIMATION

    COST ESTIMATION

  • 8/13/2019 Qs and Estimation Presentation

    15/42

    The only accurate estimation can enable the leaders to make vital

    decisions regarding fate of the project.

    If job is over estimated,

    The firm will not be able to compete with its competitors

    If the job is under estimated, The firm will face huge financial losses.

    QUANTITY SURVEYING & ESTIMATION

    IMPORTANCE OF COST ESTIMATION

  • 8/13/2019 Qs and Estimation Presentation

    16/42

  • 8/13/2019 Qs and Estimation Presentation

    17/42

  • 8/13/2019 Qs and Estimation Presentation

    18/42

    The primary aim of preparation of CSR is to provide the facility to theEngineers,in taking rational & quick decisions on following aspects.

    To Prepare Project Estimates & PC- I

    To Evaluate Tenders

    To decide on claims & Variations Orders

    To conduct arbitrations matters

    QUANTITY SURVEYING & ESTIMATION

    COMPOSITE SCHEDULE OF RATES (CSR)

  • 8/13/2019 Qs and Estimation Presentation

    19/42

    In order to prepare Schedule of Rates and to keep it effective, the basicrequirements are :

    Collection of first hand healthy / correct information regardingManpower, Material and Equipment costs.

    Merging the above information in proper proportion according to theconstructional requirement to create the rate of work item

    Updating the data inputs every year or from time to time to revalidatethe items rates .

    QUANTITY SURVEYING & ESTIMATION

    COMPOSITE SCHEDULE OF RATES (CSR)

  • 8/13/2019 Qs and Estimation Presentation

    20/42

    RATE ANALYSIS

    Materials cost

    Manpower cost

    Machinary cost

    Profit & Overhead

    QUANTITY SURVEYING & ESTIMATION

    RATES ANALYSIS OF EACH ITEM OF CSR CONSISTS

    OF FOUR BASIC INPUT

  • 8/13/2019 Qs and Estimation Presentation

    21/42

  • 8/13/2019 Qs and Estimation Presentation

    22/42

  • 8/13/2019 Qs and Estimation Presentation

    23/42

    TermsEscalation, Price Adjustments & Increase / Decrease.

    MeaningAdjustment of Contract Price for increase or decrease of prices of

    adjustable materials / services.

    It is a compensation to the parties (Contractor or Client) for market price

    fluctuation and not extra benefit to anyone.

    Adjusted during contract period for the work done over a specified period.

    Basic formula: Price Adjustment = Quantity x (current ratebase rate).

    PEC formula: Pn=A+b Ln + c Fn + d Cn + e Sn + f Bn

    Lo Fo Co So Bo

    Appendix-C represents price adjustment factors in the Bidding Documents.

    QUANTITY SURVEYING & ESTIMATION

    PRICE ADJUSTMENT

  • 8/13/2019 Qs and Estimation Presentation

    24/42

    Base cost indices or prices shall be those prevailing on the day 28 days

    prior to the latest date of bid submission.

    Current indices or prices shall be those prevailing on the day 28 days prior

    to the last day of the period to which a particular monthly statement is

    related.

    QUANTITY SURVEYING & ESTIMATION

    BASE, CURRENT & PROVISIONAL INDICES

  • 8/13/2019 Qs and Estimation Presentation

    25/42

    Bidders quote price on prevailing market rates.

    Cost of basic construction materials fluctuate unpredictably

    during the contract period.

    Unlimited cost increase not foreseeable & cannot be built in

    competitive bidding process.

    Contractors can execute work only at right costs. Contracts cannot be executed properly unless a mechanism

    equitable to the parties are included for price adjustment.

    QUANTITY SURVEYING & ESTIMATION

    WHY PRICE ADJUSTMENT?

  • 8/13/2019 Qs and Estimation Presentation

    26/42

    Results of non-adjustments: Project delay, disputes,

    termination of contracts resulting more cost for the

    Employer

    Exclusions Variation Orders due to Non BOQ Items

    Claims

    Temporary Works like General Items

    QUANTITY SURVEYING & ESTIMATION

  • 8/13/2019 Qs and Estimation Presentation

    27/42

  • 8/13/2019 Qs and Estimation Presentation

    28/42

  • 8/13/2019 Qs and Estimation Presentation

    29/42

  • 8/13/2019 Qs and Estimation Presentation

    30/42

  • 8/13/2019 Qs and Estimation Presentation

    31/42

  • 8/13/2019 Qs and Estimation Presentation

    32/42

  • 8/13/2019 Qs and Estimation Presentation

    33/42

  • 8/13/2019 Qs and Estimation Presentation

    34/42

  • 8/13/2019 Qs and Estimation Presentation

    35/42

    Cost Element Description WeightageFactor C

    1 2 3

    (i) Fixed Portion Min 0.35 as per PEC

    guidelines

    (ii) Labor

    Max 0.65 and no

    factor should be less

    than 0.05 ether than

    labor and diesel as per

    PEC guidelines

    (iii) Cement

    (iv) Reinforcing Steel

    (v) High Speed Diesel (HSD)

    (vii) Bitumen

    (viii)

    Total 1.000

    QUANTITY SURVEYING & ESTIMATION

    APPENDIX-C TO BID

  • 8/13/2019 Qs and Estimation Presentation

    36/42

    Variation is alteration in the form of addition, substitution or omission

    from the original scope of the contract works.

    Almost all construction projects vary from the original design, scope anddefinition. Whether small or large, construction projects will have

    inevitably depart from the original tender design, specification and

    drawings prepared by the design team.

    Those changes can be of different nature and may include additional

    works, changing material specifications, changing working conditions,

    design changes before, during and even after work execution and so on

    and so forth

    QUANTITY SURVEYING & ESTIMATION

  • 8/13/2019 Qs and Estimation Presentation

    37/42

    The most frequent effect of variation orders is the increase in cost. Variation orders may

    affect the projectstotal direct and indirect costs. Therefore, any major addition or alteration

    in the design may eventually increase the project cost.

    Additional payment for contractor, increase in overhead expenses, rework and demolition

    were considered as the most frequent effect of variation orders.

    QUANTITY SURVEYING & ESTIMATION

    EFFECT OF VARIATION

  • 8/13/2019 Qs and Estimation Presentation

    38/42

    CONSTRUCTION PAYMENT

    The process of paying /transfer of money or goods for the construction

    works done. A QS will be able to:

    Prepare the Interim valuation of works in progress on site for

    purposes of interim payments.

    Prepare the financial statement of regular intervals during the

    construction period.

    Do a settlement of the final accounts of the project.

    QUANTITY SURVEYING & ESTIMATION

    PAYMENT

  • 8/13/2019 Qs and Estimation Presentation

    39/42

    Supplementary services may also be provided by

    the Professional Quantity Surveyor if required:

    Preparation of feasibility studies of a project.

    Projection of estimated project or development expenditure and

    anticipated income cash flows.

    Evaluation of contractors registered for prequalification.

    Comparative cost studies on the economics of the project during

    design stage.

    Project management of construction project.

    QUANTITY SURVEYING & ESTIMATION

    SUPPLEMENTARY SERVICES

  • 8/13/2019 Qs and Estimation Presentation

    40/42

    With all these skills place QUANTITY SURVEYORS in a strong positionto take a leading

    managerial role throughout the development of a project~