OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 1
QUALITY ASSURANCE
AND
QUALITY CONTROL
MANUAL
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 2
1. INTRODUCTION
2. MANAGEMENT RESPONSIBILITY
3. QUALITY SYSTEM
4. PROJECT AND CONTRACT REVIEW
5. DOCUMENT CONTROL
6. PURCHASING AND MATERIAL CONTROL
7. PRODUCT IDENTIFICATION & TRACEABILITY
8. PROCESS CONTROL
9. INSPECTION & TESTING
10. INSPECTION, MEASURING & TEST EQUIPMENT
11. CONTROL OF NON-CONFIRNING ACTIONS &
CORRECTIVE ACTIONS
12. AUDIT RECORD & TRAINING RECORD
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 3
1.1 INTRODUCTION
M/s OCEAN STAR CONSTRUCTION L.L.C is a locally registered company and started to
establish in Dubai with (G+1) commercial license. The launch of M/s OCEAN STAR
CONSTRUCTION L.L.C as a competent, efficient Construction LLC in the year 2008 to
distinguish itself as an organization to contribute in its own way for the economical growth
of the nation.
1.2 SCOPE
M/s OCEAN STAR CONSTRUCTION L.L.C recognizes that in today’s competitive
marketplace, effective quality systems are essential when providing quality cost effective
services to our clients. Management is totally committed to providing Commercial and
Residential General Contracting & Interiors fitout Services that comply fully with the
specifications and expectations of our valued clients. Therefore, it is the policy of our
company to adhere strictly to this quality control program and to insure that this program
and the requirements of our customers are met on each and every project we execute.
1.3 PURPOSE
The purpose of QA is to ensure that the project team’s processes are sound and that QC
is properly provided on every substantive environmental document.
Quality work is consistently performed and that quality deliverables are consistently
produced.
Project continuity occurs in record-keeping and document review.
Orderly procedures are established to provide QC for scientific calculations, technical
analyses, conclusions, and determinations.
Demonstrate to clients of M/s Ocean Star Construction L.L.C., the total commitment to
Quality and service.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 4
1.4 QA/QC POLICY
M/s OCEAN STAR CONSTRUCTION L.L.C policy is to maintain an effective “ Quality
Management System” to ensure that the required level of services excellence if achieved
to meet the requirements of international standards, Project Specifications and this
Company’s quality assurance manual.
The quality can be obtained through appropriate planning and control of environmental
documents and by specific quality control activities such as reviewing, checking,
testing, and quality assurance.
The maintenance and operations of the company quality system will be the
responsibility of all employees within the company.
The quality system incorporates company quality management policy, objectives,
organizations and procedures associated with all of the company activities.
The policy is full endorsed on behalf of the company by the Managing Director.
Company’s Management Team who will by direction and example, ensure that this
policy is understood, accepted and implemented, throughout the organization.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 5
2.1 RESPONSIBILITY
The Management has the responsibility to define and document its policy and objectives
for and commitment to quality. Management will ensure that its policy is understood,
implemented, and maintained at all levels of the organization.
The structure for reporting relationship and interfaces for projects as per the contract
requirements.
Quality Representative shall be nominated by management to maintain the Quality
system. It is the responsibilities of the key personnel to manages, performs, or verifies
work affecting QA/QC.
All resource requirements shall be identified and provided on an ongoing basis Job
responsibilities / authorities are defined in the Quality Manual, Procedures and work
instructions for key personnel.
2.2 ALLOCATION OF RESOURCES AND PERSONNEL
Management shall identify in-house requirements and provide adequate resources and
trained personnel as needed to support required QA/QC verification activities. Verification
activities shall include inspection, testing and monitoring of the construction processes
and audits of the quality systems.
2.3 MANAGEMENT REVIEW
The QA/QC Manual policies and procedures shall be reviewed at appropriate intervals by
management to ensure continuing suitability and effectiveness. These reviews will include
assessment of the results of internal audits and shall assess overall conformance to
client’s requirements and expectations. Records of such reviews and audits shall be
maintained.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 6
3.1 QUALITY SYSTEM
The quality system has been developed to produce awareness that encompasses the
elements in international standards and to provide a base from which to build on the
efficiency of the quality system.
M/s Ocean Star Construction L.L.C. has established and shall maintain and document this
QA/QC system as a means of ensuring that the services we provide our clients conform to
specified requirements. This QA/QC system shall include:
a. Documented quality system procedures and instructions to ensure that all activities
are performed in accordance with established requirements.
b. Effective management support to ensure compliance and the use of the QA/QC
procedures and instructions.
All employees of M/s Ocean Star Construction L.L.C. shall strive to improve the quality of
our services to our clients. The QA/QC program is a process of continuous improvement
which requires input from everyone in our organization. Everyone in our organization shall
comply and endeavor to improve the process where possible.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 7
4.1 PROPOSAL/TENDER SUBMISSION
When the Company received an inquiry/tender Invitation from the Consultant/Client,
management will review the requirements of the inquiry/tender and determine if a proposal
will be submitted to perform the work. If management decides to submit a proposal for the
work, a Project Manager and Quantity Surveyor are assigned the responsibility of
generating the proposal to perform the work. The proposal must include all costs related
to completing the work in accordance with the client's requirements and specifications.
4.2 CONTRACT REVIEW
The contract review shall commence at the contract award stage when the actual contract
document is reviewed against the inquiry and tender documents.
The contract reviews are an ongoing process, which continues throughout the project. Any
resulting changes shall be review and distributed to relevant department heads.
The project documents and contract review activities, interfaces, and communication shall
be coordinated with the client as required to clarify all issues and to ensure that the
responsibilities of both parties are well defined and documented.
4.3 PROJECT EXECUTION
When the project/work award to M/s Ocean Star Construction L.L.C., Project Manager
shall immediately setup the project in accordance with the execution and staffing plan
established during the proposal. All key staff members shall be notified and sent as much
information concerning their responsibilities to the project as soon as possible. The Project
Manager shall develop a project QA/QC file containing the basic QA/QC manual and all
related specific activities' QA/QC procedures and instructions.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 8
5.1 DOCUMENT CONTROL
All documents both internal and external relating to the requirements of the quality system
shall be controlled through documented procedure, reviewed and approved prior to
release.
Upon award, each project is assigned a project number and the Project Manager
establishes a "Project Job File". This file shall contain a complete set of all project related
contract documents, specifications, drawings, etc. All information generated during the life
of the project shall be maintained in this job file.
A listing shall be made of all drawings, specifications, vendor data, etc. that are to be
submitted to the client for review and approval. A copy of all documents returned by the
client approved, or approved as noted, shall be maintained in the job file.
A complete set of all documents required for proper execution of the work shall be
maintained at the project site. Any revisions received shall be immediately forwarded to
the project site for use while executing the project.
All changes after contract award shall be properly documented and any associated
addition or deduction to the contract price shall be immediately identified and submitted to
the client for review and approval
Master register shall be maintained within quality assurance archives showing the current
status of the documents at all times.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 9
6.1 PURCHASING
Purchasing of materials shall be strictly in accordance with documented procedure to
ensure correct data is included on purchase orders and only companies on the approved
vendor/supplier list.
Purchase orders shall be clear and precise on the goods and certification required. The
content of the purchase order shall be checked by authorized for adequacy prior to
dispatch.
All subcontractors shall be selected on the basis of their ability to meet subcontract
requirements, including established quality requirements. The selection of subcontractors,
and the type and extent of control exercised by the Project Manager shall be dependent
upon the type of service, client requirements, and where appropriate on records of
subcontractors’ previously demonstrated capability and performance.
All purchasing documents shall contain data clearly describing the material or service
ordered for the specific project.
6.2 MATERIAL CONTROL
All material delivered will be inspected before and during installation, any damage found
will be reported to the concerned vendor/supplier.
All material ordered will be stock/place in good condition and properly accounted during
and after completion of the project.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 10
7.1 PRODUCT IDENTIFICATION & TRACEABILITY
Where appropriate, the Project Manager shall establish and maintain procedures for
identifying materials and equipment from applicable drawings, specifications, or other
documents, during all stages of production, delivery, and installation.
Various method may be used for identification and traceability purposes; these can be
color code, tagging, drawing, unique number or other classifications.
Records shall be maintained for all traceable items as defined in the quality procedures.
These records shall be comprehensive enough to ensure total traceability for the life of the
product.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 11
8.1 PROCESS CONTROL
All stage of process shall be controlled through documented procedures and work
procedures/method statements.
Documented work instructions defining the manner of executing the work to ensure that
an acceptable level of quality is maintained at all times. The instructions shall also specify
equipment, materials, skills and working environments required to comply with applicable
standards, codes, and quality plans.
In process inspection and test shall be pre-determined through quality plans, all stage
inspections shall be verified as being successfully carried out and accepted prior to final
inspection.
Management shall continue review of established QA/QC procedures to ensure ongoing
suitability and effectiveness. As the need for new activity QA/QC process procedures is
identified they will be created and implemented. Records shall be maintained for qualified
processes, equipment, and personnel, as appropriate.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 12
9.1 INSPECTION & TESTING
Inspection and test requirements shall be determined through approved quality plans,
procedures or other documented methods.
9.2 INSPECTION & TESTING OF PURCHASE MATERIALS
All materials and equipment shall be inspected and tested to ensure conformance with the
project requirements before it is released for use.
Where incoming materials are released for urgent construction purposes, it shall be
positively identified and recorded in order to permit immediate recall and replacement in
the event of nonconformance to specified requirements.
9.3 INSPECTION & TESTING DURING CONSTRUCTION
During actual construction of a project, the Project Manager shall ensure that;
a) All inspection and testing activities are performed in accordance with the quality plan
and documented procedures;
b) Ensure specification and drawing conformance by the use of established process
monitoring and control methods;
c) Ensure that all required inspections and tests have been completed and necessary
reports have been received and verified before the finished work is released to the client.
d) Identify and correct any nonconforming work.
9.4 FINAL INSPECTION & TESTING
The quality plan or documented procedures for final inspection and testing require that all
specified inspection and tests, including those specified either by established quality
procedures or the client, are carried out and that the work meets specified requirements.
The Project Manager shall ensure that all final inspections and testing activities are in
accordance with the quality plan and documented procedures.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 13
9.5 INSPECTION & TEST RECORD
The Project Manager shall ensure that all records which give evidence that the work has
passed specified inspection and / or testing acceptance criteria are maintained in the
project QA/QC file for future reference.
Records shall be maintained as evidence that all items have passed inspection and test to
the defined acceptance criteria.
9.6 INSPECTION & TEST STATUS
The inspection and test status of items in the process of being built into the product shall
be identified in accordance with approved project procedures.
The identification of inspection and test status shall be maintained, as necessary,
throughout the project to ensure that all work has passed the required inspections and
testing specified.
Records shall be maintained to verify any inspection authority who shall be responsible
for the release of the goods.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 14
10.1 INSPECTION, MEASURING & TEST EQUIPMENT
The Project Manager shall ensure that all inspection, measuring, and test equipment is
controlled, calibrated, and maintained, whether owned by M/s Ocean Star Construction,
rented or provided by the client. Equipment shall be used in a manner which ensures that
measurement uncertainty is known and is consistent with the required measurement
capability.
Any inspection, measuring or test equipment required to give precise, accurate results
shall be calibrated to recognized standards or specifications.
Any items of equipments, which requires calibration, shall be calibrated by an approved
laboratory, who shall supply a certificate, signed by an authorized person to confirm
conformance of the equipment.
Records shall be maintained of all inspection, measuring and test equipment in the
calibration system
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 15
11.1 CONTROL OF NON-CONFIRMING ACTIONS
The Project Manger shall establish and maintain procedures to ensure that any work that
does not conform to specified requirements is prevented from inadvertent release to the
client. Control shall provide for identification, documentation, evaluation, segregation when
practical, disposition of nonconforming work, and for notification to management as
required.
11.2 CORRECTIVE ACTIONS
Corrective actions requirements shall be controlled by the Project Manager by establish,
documents and maintained procedures.
Procedures shall provide for identification of the non-conformance and timely resolution
through approved corrective action methods.
The procedures shall provide for an investigation into the cause of the non-conformance
and identity of a corrective action to prevent recurrence.
OCEAN STAR CONSTRUCTION L.L.C. QA/QC MANUAL
Page 16
12.1 INTERNAL QUALITY AUDITS
An auditor who is independent of the activity being audited shall carry out internal quality
audits. Audits shall be scheduled on the basis of the status and importance of the activity.
The finding from the internal audits shall be documented and a report issued to the
auditor. A proposed corrective action shall be submitted for approval in the event of any
non-compliance found in accordance with this manual.
12.2 QUALITY RECORDS
Quality records are to be maintained to demonstrate achievement of the required quality
and the effective operation of the quality system.
All quality records shall be legible and identifiable to the project involved. Quality records
shall be stored and maintained in such a way that they are readily retrievable in facilities
that provide a suitable environment to minimize deterioration or damage to prevent loss of
the records.
12.3 TRAINING
Management and supervision shall maintain a training program to ensure all personnel
are fully competent to carry out their assigned task. Personnel performing specific
assigned tasks shall be qualified on the basis of appropriate education, training, and / or
experience, as required. Appropriate records of training shall be maintained on each
individual's training and qualifications.