Quantity Surveying Book

Embed Size (px)

DESCRIPTION

notes and examples on building measurements and cost estimations

Citation preview

  • 1

    UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION

    REVITALISATION PROJECT-PHASE II

    YEAR 2- SE MESTER 2

    THEORY

    Version 1: December 2008

    NATIONAL DIPLOMA IN QUANTITY SURVEYING

    TENDERING AND ESTIMATING II

    COURSE CODE: QUS 210

  • 2

    TABLE OF CONTENTS

    WEEK 1:

    1.0 PRICING OF PRELIMINARIES I

    1.1 What are Preliminary Items?

    1.2 Estimating for Typical Preliminary Items

    WEEK 2: 2.0 PRICING OF PRELIMINARIES II

    WEEK 3: 3.0 PRELIMINARIES ANALYSIS WORKSHOP 3.1 Preliminary Bill

    3.2 Class Workshop

    WEEK 4:

    4.0 PREPARATION OF TENDER

    4.1 Decision to Tender

    4.2 Collection of Information

    4.3 Enquiries and Quotations

    4.4 Visit to Site

    4.5 Visit to Consultants Offices

    4.6 Receipt of quotations

    4.7 Planning and Mid Tender Review

    4.8 Preparation Of The Estimate

    4.9 Final Review

    4.10 Action after Submitting a Tender

    4.10.1 Action with a successful tender

    4.10.2 Action with an Unsuccessful Tender

    4.11 Factors in Pricing General and Special Attendance on Subcontractors

    WEEK 5:

    5.0 MAJOR FACTORS AFFECTING TENDER PRICE

    5.1 Factors Affecting Tender Price

  • 3

    WEEK 6:

    6.0 PRICIPLES OF ANALYTICAL ESTIMATING

    6.1 Elements of a Unit Rate

    6.2 Calculation of Unit Rates

    6.2.1 Materials

    6.2.2 Plant

    6.2.3 Overheads

    6.2.4 Profit

    WEEK 7:

    7.0 BUILD-UP HOURLY RATE FOR PLANT & EQUIPMENT

    7.1 Calculation of Unit Rates

    7.2 Groundworks

    7.2.1 Hand Excavation

    7.3 Excavation using Mechanical Plant

    7.4 Banksmen

    7.5 Disposal of Excavated Material

    7.6 Earthwork Support

    WEEK 8:

    8.0 BUILD-UP UNIT RATE FOR SURFACE EXCAVATION

    8.1 Surface Excavation

    8.2 Removal of Excavated Materials

    WEEK 9:

    9.0 BUILD-UP UNIT RATE FOR CONCRETE WORK I

    9.1 Concrete Work

    9.2 Reinforcement

    9.3 Guide to Using this Student Learning Pack

    9.4 Concrete Works

    9.4.1 Site Mixed Concrete

    9.4.2 Ready Mixed Concrete

    9.5 Concrete Reinforcement

    WEEK 10:

  • 4

    10.0 BUILD-UP UNIT RATE FOR CONCRETE WORK II

    9.6 Concrete Work

    9.6.1 Site Mixed Concrete

    9.6.2 Ready-Mixed Concrete

    9.8 Concrete Work

    9.7 Reinforcement

    WEEK 11:

    11.0 BUILD UP UNIT RATES FOR REINFORCEMENT

    11.1 Bar Reinforcement

    WEEK 12: 12.0 BUILD-UP UNIT RATE FOR FORMWORK 12.1 Formwork

    WEEK 13:

    13.0 BUILD-UP UNIT RATE FOR ROOFING

    13.1 Roofing

    WEEK 14:

    14.0 BUILD UP UNIT RATE FOR MASONRY

    14.1 Guide to Using this Student Learning Pack

    14.2 Masonry works

    14.3 Fact and Figures

    WEEK 15: 15.0 PRACTICE QUESTIONS FOR TUTORIAL CLASS 15.1 Questions

  • 5

    Course: Tendering and Estimating II

    Course Code: QUS 210

    Contact Hours: 2hrs

    Course Specification: Theoretical Content

    General Objective for Week 1: Appreciate the Build-up for Preliminary

    Items

    WEEK 1: PRICING OF PRELIMINARIES I (1.0)

    1.1 What are Preliminary Items?

    Preliminary items are items of cost which do not relate to any particular work section and

    usually listed in the first bill of quantities. Many estimators prefers to inserts a lump sum for

    all the preliminaries usually worked out as a percentage of the total of the measured works. It

    is good practice however to put a price to each of the item. The price quoted should read at

    after careful consideration of each item as it applies to the particular job at hand e.g water for

    the works. It will be pipe bone water readily available on site or water has to be transported to

    site on trucks.

    1.2 Estimating for Typical Preliminary Items

    (1) Site Supervision: These include the salaries and allowances paid to the site agent or

    engineer and the administrative staff on the site such as cashiers, clerks, time keepers,

    material checkers, store controllers etc. when this staff are sent aways from the area in

    which they normally work and this necessitate them having to leave away from their

    usual place of residence for a period of time a subsistence allowance may have to be

    added to cover the additional expenses they will incure e.g

    site agent

    salary / month = 10,000

    Housing allowance = 8,000

    Transport allowance = 2,500

    20,500 = 20,500

    Cashier

    Salary / month = 5,000

    Housing allowance = 4,000

    Transport = 2,000

    11,000 = 11,000

  • 6

    Clerk

    Salary / month = 3,500

    Housing = 1,600

    Transport = 1,500

    6,600 6,600

    Store controller

    Salary / month = 3,500

    Housing = 1,600

    Transport = 1,500

    6,600 = 6,600

    Messenger

    Salary / month

    Salary / month = 1,000

    Housing = 800

    Transport = 500

    2300 = 2,300

    47,000/month

    Contract duration 12 month

    Add 1 month before project and

    Add 3 months for defect liability period

    Total month 16

    16 months x 47,000 = 752,000

    Add 10% for insurance and I.T.F = 75,200

    827,200

    Add 25% for profit and overhead = 206,800

    1,034,000

    (2) Site Accommodation

    The contractor is usually expected to provide and maintain temporary site

    accommodation for

    (i) Supervising consultant on site

    (ii) Site agent and site staff

    (iii) Hut for workmen

    (iv) Storage, shed for materials, tools etc.

    Pricing for these must cover the cost of:

  • 7

    (a) Initial construction of accommodation

    (b) Removal on completion and making good ground disturbed

    (c) Maintenance of accommodation throughout duration of the project

    (d) Furniture including ventilation and air conditioning

    (e) Overhead and profit from these estimator must remove the resale value of

    items are still useable at the end of the projects e.g

    Site office

    Initial construction cost

    Architect office 7.5m2

    Engineer office 7.5m2

    Quantity Surveying 7.5m2

    Site agent 7.5m2

    General office 10m2

    Contractors room 12m2

    Rest room 2.5m2

    54.5m2 55m2

    Circulation space 10% 5.5m2

    60.5m2

    61m2

    61m2 at 9,000 = 549,000

    Less resale value of items (about 27%) 149,000

    N400,000

    Demolish and cart away from site including making good @ 500/m2 x 61m2

    = 30,500

    (3) Mechanical Plant

    This include all mechanical plant not allocated to unit rate such as cranes, lift,

    dumpers, hoist, tractor, generating set, drills, forklift etc. the contractor is expected to

    allow for this items whether they are purchased specifically for the project or they are

    already owned by the firm or they are to be hired for the period they are required on

    the project. The usual thing is to allow for

    (a) cost of transporting plant to site

    (b) Hire rate for the period plant is on site

    (c) Cost of maintenance on site

    (d) Profit and overhead

  • 8

    (3) Tools

    This include items such as shovels, portable drills, wheel barrows, batch boxes, guage

    etc. smaller tools such as hammer, trowel, plumb level, plumb lines, paint brushes etc.

    that are associated with a particular trade are not aloe for, here. They are usually taken

    care of in the tool allowance included in the all in-labour rate for such fields. If the

    project is large enough to used up small tools such as paint brushes, sand papers etc.

    then the cost of such are included in the unit rate for the items that required their use

    in pricing consideration is given to the cost of purchasing of the tools less their resale

    value.

    (4) Scaffolding

    The total height and the type of construction determined the amount and type of

    scaffolding required for a project, the contractor may purchase scaffolding for use in

    the work. Whatever they may be, in pricing consideration is usually given to the

    following.

    (a) Hire rate for the duration of the project

    (b) Labour cost for erecting scaffolding on site

    (c) Labour cost for adopting scaffolding for special uses

    (d) Labour cost for dismantling scaffolding at the end of the project

    (e) Transportation cost for bringing to site and removing from site all scaffolding

    (f) Profit and overhead

  • 9

    WEEK 2: PRICING OF PRELIMINARIES II

    (6) Water For The Work

    Water required for the project is provided in either of the two ways supply by water

    tankers if the site is far from a source or pipe bone water. In pricing consideration is given

    the following:

    If the site is far from the source: Cost of water supply by water tanker. It may be

    necessary to write out an approximate estimate of the quantity of water required for the

    project from previous project, certain allowance can be made for concrete work 480

    liters/m3

    For Block work 350 liters/m2

    Rendering 30 liters/m2

    Workman hut 2000/day

    Site accommodation 20,000/day

    Based on these allowances total quantity of water can be estimated for the whole project

    and priced at prevailing water tanker rate for that areas.

    Cost of Temporary Storage:

    This include

    (a) Cost of labour and materials in constructing surface tank, overhead tank, pipe work

    and its pumps.

    (b) Cost of cleaning and maintaining tanks, water pipes and water pumps.

    (c) Cost of removal of water storage and temporary pipe work and making good ground

    disturbed

    (d) Overheads and profits

    (a) Pipe Bone Water:

    Pricing will include

    (i) Cost of water connection by water board

    (ii) Cost of labour and material for laying pipes

    (iii)Cost of temporary storage

    (iv) Water rate are usually charged as flat rate per plot. Therefore no need to estimate

    approximately

    (v) Cost of disconnection, removal of pipe and making good defect

    (vi) Overhead and profit

  • 10

    (7) Lighting and Power for Work

    As in the case of water, provision of power is effected in either of two ways

    (a) Power generating set: If site is far from existing mains, pricing will include

    (i) cost of hiring generating set for the duration of the project.

    (ii) Cost of cables, wiring and light fittings

    (iii) Cost of running and maintaining generating set for duration of project

    (iv) Cost of labour and materials for constructing temporary sheds for generators

    (v) Cost of dismantling shed, removal and making good

    (vi) Cost of transporting generating set to site and removal on completion of project.

    (vii) Overhead and profit

    (b) Electrical supply from electrical authority mains, pricing will include

    (i) Cost of connection to the electrical authority

    (ii) Cost of cables, wiring and light fittings

    (iii) Cost of electricity bills

    (iv) Cost of disconnection on completion of project

    (v) Cost of hiring a standby generator in case of electricity failure

    (vi) Overhead and profit

    (8) Temporary Road

    In certain building and civil engineering construction, temporary road have to be

    constructed from the existing road to the site in order to get access to and make

    possible the distribution of materials to various part of the site. Temporary road may

    also be required is first worked and priced with the following considerations

    (a) Cost of labour during clearing the road

    (b) Cost of excavation either by hand or by mechanical plant

    (c) Cost of labour and materials in laying laterite, blinding, gravel

    (d) Cost of maintaining the road for the duration of the project

    (e) Cost of removal of temporary road if not required at completion of all works on

    site and making good ground disturbed

    (f) Overhead and profits

    (9) Temporary Telephone

    If the project requires the telephone, the constructor must arrange for telephone

    communication to be installed on site for easy communication for the duration of the

    contract, pricing will include

    (a) Cost of telephone installation by telephone organization in this case NITEL

    (b) Cost of telephone bills

  • 11

    (c) Cost of maintenance

    (d) Cost of disconnection\

    (e) Overhead and profit

    (10) Control of Traffic and the Additional Cost

    Reconstruction and repairing of existing road, lying sewers, water mains etc. in

    existing roads and construction works in congested areas may create the necessity for

    closing part of some road temporarily to traffic. In such cases the provision of one

    way traffic control, diversions and access to adjoining houses, shops etc. may become

    necessary. The following should be given consideration

    (a) control of traffic which involves

    (i) Cost of speed breakers

    (ii) Cost of constructing barriers

    (iii) Cost of red flags

    (iv) Cost of labour flagging traffic

    (v) Cost of providing diversion

    (vi) Cost of removal of sign board to adjoining house, shops, garage etc.

    (b) The provision of access road to adjoining houses, shops, garages etc

    (i) Cost of labour and materials to provide pedestrian and vehicular access to shops,

    houses, cars and park etc.

    (c) Additional cost of work on existing road where traffic is involved

    (i) Cost of delays to progress of work due to traffic and congestion

    (ii) The presence of existing water mains, cable sewers, culverts etc.

    (iii) Watching and lighting the work

    (iv) Overhead and profit

    (11) Welfare and Safety of Work People

    This will comprise the cost of

    (a) First aid box

    (b) Drugs, antiseptics, bandages etc.

    (c) Providing a nurse or medical attendant

    (d) Maintaining first aid box

    (e) Removal

    (f) Protective clothing such as overall, element, nose mask, face mask, ear plug, boot

    eye shield (industrial goggle)

    (g) Safety equipment such as hose, fire fighting equipment

    (h) Overhead and profit

  • 12

    (12) Temporary Fencing, Hoardings, Screeds, Fans Gantries and Similar Items.

    Each will comprise the cost of

    (a) Labour and materials

    (b) Maintenance

    (c) Removal and making good

    (d) Overhead and profit

    (13) SITE SECURITY:

    This will comprise

    (a) Cost of labour and materials to construct temporary security shed post

    (b) Labour and materials to installed security lighting, intruder alarms

    (c) Furniture, stationeries, tags, I.D card etc.

    (d) Wages for workmen

    (e) Hiring of watch dogs

    (f) Removal of sheds and lightening on completion of project and making good ground

    disturbed

    (g) Overhead and profit

    (14) Removing Rubbish and Site Clearance on Completion of Project.

    This involves the cost of

    (a) Labour and materials clearing off such rubbish.

    (b) Plant, lorry and labour loading such lorry transporting the rubbish from site

    (c) Labour and materials cleaning up door, windows etc.

    (d) Overhead and profit

    (15) Site Meeting: this will Comprise the Cost of:

    (a) Provision of stationeries at each meeting

    (b) Provision of refreshment at each meeting

    (c) Wages of attendant

    (d) Overhead and profit

    (16) Setting out of the Work:

    this will comprise the cost of

    (a) Pegs, templates and ropes or line

    (b) Hiring of theodolite, precise level and other survey equipment

    (c) Bringing to site and removing from site all the above name equipment

  • 13

    (d) Fees for engineer and the assign team

    (e) Overhead and profit

  • 14

    WEEK 3: PRELIMINARIES ANALYSIS WORKSHOP (3.0) 3.1 Preliminary Bill The preliminaries bill gives the contractors the opportunity to price overheads which is

    described in the Code of Estimating Practice as the cost of administering a project and

    providing general plant, site staff, facilities and site based services and other items not

    included in bill rates.

    Preliminaries costs vary from contract to contract depending on complexity of work, size of

    contract, specialist plant and equipment required, conditions imposed by the employer etc.

    On relatively simple contracts preliminary costs may be in the order of 10 15% of the

    contract sum whereas on complex contracts this figure could be much higher.

    A contractor must calculate the cost of the preliminary items separately for each contract, no

    two contracts are the same.

    SMM7 recommends that fixed and time-related charges should be identified separately in a

    bill of quantities.

    A fixed charge is defined as the cost of work which can be considered as being independent

    of duration

    A time-related charge is defined as the cost of work which is to be considered as dependant

    on duration.

    3.2 Class Workshop

    The appendix below is a summary of the bill for the case study project. Students will be

    expected to appreciate and be able to work out how preliminary items in the bill are priced

    and distributed between time or cost related and fixed charges for the purpose of monthly

    valuations.

    Procedures:

    The work book will be made available to students at the beginning of the lecture. Time will

    be allowed for students to read and comprehend the notes. Students will then be asked to sit

    in groups of between 3 and 4 to discuss their understanding and set up query list on the

    project.

    After about 30 minutes, each group will be required to use the preliminaries breakdown form

    to identify percentage allocation of each preliminary item across the table and to provide

    justification for the allocation on each item.

  • 15

    Appendix 1 attached shows the tender submission details and actual progress achieved on site

    for monthly valuation purposes on a typical construction project.

    (a) Allocate the preliminaries to time related and lump sums sections (Use form

    Appendix 2).

    APPENDIX 1 TENDER SUBMISSION DETAILS

    Bill No. Preliminaries

    A Supervision 14,000.00

    B Plant 1,200.00

    C Scaffolding 1,200.00

    D Welfare Facilities 2,100.00

    E Site Huts 1,000.00

    F Site Telephones 400.00

    G Temporary Lighting & Power 400.00

    H Programme 200.00

    J Watching 1,250.00

    K Site Hoarding 1,800.00

    L Temporary Roads 950.00

    M Setting Out 400.00

    N Drying the Works 500.00

    O Cleaning Away Rubbish 500.00

    P Water for the Works 727.00

    Q Insurance Against Injury to Person and Property 3,401.00

    Total Bill No. 1 30,028.00

    Bill No. 3 External Works

    A Soiling and Seeding 4,082.16

    B Paths and Pavings 6,111.27

    C Retaining and Screen Walls 2,017.33

    D Drainage 9,127.16

    E Fencing 1,812.19

  • 16

    Total Bill No. 3 23,150.11

    Bill No. 2 Measured Work

    A Demolition 1,200.00

    B Excavation and Earthwork 11,526.16

    C Concrete Work 29,526.41

    D Brickwork and Blockwork 31,416.12

    E Roofing 14,112.16

    F Woodwork 35,516.44

    G Plumbing and Mechanical Installations 18,642.12

    H Electrical Installations 9,216.14

    J Floor, Wall and Ceiling Finishings 17,316.18

    K Glazing 4,127.13

    L Painting and Decorating 12,011.14

    184,610.00

    Bill No. 4 Prime Cost Sums

    Nominated Sub-Contractor

    A Piling 8,500.00

    B Profit 5% 425.00

    C General Attendance Item 170.00

    D Specialist Landscaping 27,000.00

    E Profit 5% 1,350.00

    F General attendance Item 600.00

    Nominated Suppliers

    G Kitchen Equipment 18,000.00

    H Profit 5% 900.00

    J Sanitary Fittings 12,000.00

    K Profit 5% 600.00

  • 17

    L Ironmongery 5,000.00

    M Profit 5% 250.00

    Statutory Undertakings

    N Water Main Connection 1,200.00

    O Profit 5% 60.00

    P Gas Main Connection 500.00

    Q Profit 5% 25.00

    R Electrical Main Connection 5% 500.00

    S Profit 5% 25.00

    T Sewer Connection 1,400.00

    U Profit 5% 70.00

    Total Bill No. 4 78,575.00

    Tender Summary

    Bill No. 1 Preliminaries 30,028.00

    Bill No. 2 Measured Work 184,610.00

    Bill No. 3 External Work 23,150.11

    Bill No. 4 Prime Cost and Provisional Sums 78,575.00

    Bill No. 5 Daywork 9,050.00

    TOTAL TENDER SUM 325,413.11

    Bill No. 2

    Item A complete

    Item B complete

    Item C complete

    Item D complete

    Item E complete

  • 18

    Item F 50% complete

    Item G 40% complete

    Item H 40% complete

    Item J 20% complete

    Item L 10% complete

    Bill No. 3

    Item A 20% complete

    Item B 20% complete

    Item C 40% complete

    Item D 40% complete

    Bill No. 4

    Item A complete

    Item D 8,600

    Item G 8,000

    Item J 6,000

    Item L 2,000

    Item N complete

    Item P complete

    Item R complete

    Bill No. 5

    Variations 9,000.00 agreed.

    Materials on Site 6,237 agreed.

    The following AIs were received from the Architect in respect of the following Prime

    Cost and Provisional Sums:

    1. Accept a quotation of 10122.50 from Keane & Bonney Piling Ltd.

    It was observed that the Piling nominated sub-contractor had erroneously left out the

    main contractors discount in their quotation for the works.

    Effect the necessary corrections before valuation.

  • 19

    2. Accept a quotation of 27500.00 from Landson Landscape plc.

    3. Accept a quoation of 19012.00 from Kitchen & Sons for the supply of kitchen fittings.

    4. Accept a quoation of 13176.00 from Loo Ltd for the supply of sanitary fittings.

    5. Accept a quoation of 8820.00 from Smith & Smith for the supply of ironmongery.

  • 20

    APPENDIX 2

    JCT 80

    Breakdown of Preliminary Items

    Cost

    Related

    Time

    Related

    Lump Sums Total

    Start Finish

    Supervisor

    Plant

    Welfare

    Site Huts

    Telephones

    Temporary

    Lighting and

    power

    Programme

    Watching

    Site Hoarding

    Temp Roads

    Setting Out

    Drying the works

    Cleaning Rubbish

    Water

    Insurance

    TOTALS

  • 21

    Questions:

    (1) Define prelimiaries and give three examples of a prelimiary item

    (2) How do contractors price these items?

    (3) Define fixed costs and provide five examples of an item you think would be priced as a

    fixed cost item

    (4) Define time related costs and give five examples of preliminary items you think a

    contractor would price as a time-related cost.

    GENERAL OBJECTIVE FOR WEEK 4:

    Know the tendering procedures.

  • 22

    WEEK 4: PREPARATION OF TENDER (4.0)

    Reference: CIOB (1997) Code of Estimating Practice, 6th Edition. Ascot: CIOB

    The preparation of a tender can be divided into six stages.

    4.1 Decision to Tender

    The tender documents arrive and the estimator records all relevant information such as:

    The time allowed for preparing the tender Drawings available The approximate value and extent of the project The client, Architect, Q.S and other consultant Value of main contractors own work Project Details eg phased work, conditions of contract, access to site, working conditions. Firm price or fluctuating price tender required Current workload and timetable for project After reviewing the above information, management must decide whether to tender for the

    project or decline the invitation. If it is decided not to submit a price, the tender documents

    should be returned immediately to the architect/supervising officer. If it is decided that a

    tender should be submitted, the contractor move to the next stage.

    4.2 Collection of Information

    The time allowed for preparing a tender is always limited; the estimator must plan the

    programme very carefully. The work which has to be undertaken in a typical 4 week tender

    period comprises:

    Despatching enquires Visit consultants offices Visit the site Receipt of quotations and examinations The mechanical process of pricing the tender documentation Meetings with plant manager, contracts manager etc to determine a preliminary

    programme, construction methods and likely plant requirements.

    4.3 Enquiries and Quotations

  • 23

    Suppliers

    Enquires should state:

    The specification of the material The quantity required The anticipated delivery dates The terms upon which the price is required The date by which the quotation is required The address of the site and access details Period for which the quotation is open for acceptance

    Sub-contractors

    Photocopies of the relevant parts of the bill of quantities, specifications and if possible copies

    of drawings, should be sent out to perspective sub-contractors. Enquires should state clearly:

    The items to be priced The terms of the main contract The period for which the quotation is open for acceptance The plant, materials, attendance etc to be provided by the main contractor Anticipated commencement and completion dates The form of contract and details from the appendix The terms of payment Date by which the quotation is to be submitted Address and details of the site

    4.4 Visit to Site

    The visit to site can be made after all enquires have been despatched and before prices begin

    to come back. The visit to the site will enable the estimator to produce a report giving the

    following information:

    The position of the site in relation to roads etc Names of local and statutory authorities Details of site/ground conditions, spot items etc Site access, egress and possible site layouts

  • 24

    Facilities for disposal of surplus excavated materials etc

    4.5 Visit to Consultants Offices

    It may be that only drawings showing plans and elevations will be sent out with the tender

    documents and that further details and working drawings can be examined at the consultants

    offices e.g. the estimator may require further details of manufactured joinery, steelwork

    joinery fittings etc, before these sections can be priced accurately.

    4.6 Receipt of quotations

    Prices received from sub-contractors and suppliers are examined for sufficiency, terms etc

    4.7 Planning and Mid Tender Review

    The project is discussed with other managers to determine a preliminary programme,

    construction methods, sequence of work, site layouts and what other plant, services, labour

    and site staff are required.

    It must be decided whether:

    All labour can be obtained locally or will it be necessary to recruit for the project. Sufficient plant is already owned or is it necessary to purchase/hire additional items. It would be desirable to sub-let any further work. The preliminary programme should also be prepared containing the following information:

    Contract starting and completion dates Any work to be done in stages Work to be sub-let by main contractor Work to be done by nominated sub-contactors (if JCT 98 form)

    4.8 Preparation Of The Estimate

    It can be divided into 4 stages:

    1. The establishment of all-in rates for key items i.e. labour, gang costs, plant costs etc.

    2. The selection of domestic sub-contractors and suppliers

    3. The use of these all-in rates together with costs per unit for materials to calculate unit

    rates for each item in the bill

    4. The pricing of the preliminaries and project overheads

    4.9 Final Review

  • 25

    The consideration of the estimate to produce a tender is the responsibility of management.

    The estimator and other senior staff will prepare reports for consideration by management

    who will consider the following items before determining the tender figure;

    Project reports Conditions of contract Contractual and construction risks Terms of the quotations from sub-contractors Capital required for the project Technical and management staff required Current workload Market Conditions Competition Reputations of client, consultants and area.

    Following evaluation of the alternatives, risk and scope for profitability the mark up is

    determined and the actual tender figures calculated. The decision being made within the

    framework of company policy.

    A record of all tenders should be kept together will the results (if known) for future reference.

    4.10 Action after Submitting a Tender

    4.10.1 Action with a successful tender

    Check contract documents to ensure that:

    The dates, penalties etc are the same as those contained in the tender documents The bills have been copied correctly from the original The drawings are those which were circulated with the tender documents Disseminate information

    Information should be made available to those responsible for purchasing, construction

    planning and plant.

    Feedback information

    Feedback from site on labour and plant outputs etc, to be kept for future pricing

    Cost/Value Reconciliation

    At regular intervals during the construction period, the costs at that time should be compared

    with a meaningful valuation of work done in order to check that the job is on target

  • 26

    4.10.2 Action with an Unsuccessful Tender

    It the tender has been unsuccessful the contractor must assess why this is the case. Records

    of tenders submitted must be kept and estimators must evaluate their performance. Suppliers

    and sub-contractors should be notified of results as soon as possible.

    Factors in Pricing General and Special Attendance on Subcontractors Each site has its own peculiar characteristics which can have considerable influence on the

    total cost of development. Some of the more important factors are:

    (1) Location of site: - Due to higher wastages, materials and other cost, it is expensive to

    erect a similar building in an urban area than in a provincial setting. Some parts of the

    areas are subject to higher rainfall than others and this can lead to a greater loss of

    working time even within the same region, the cost of operating on different sites can

    vary widely. A project on a remote country site may involve long length of temporary

    access road and temporary power cable for electricity supplies and increase cost of

    transporting operatives and materials and components, protection of adjoining buildings

    and the public and restrictions on the use of mechanical plant. Taking these problems will

    incure additional cost. Furthermore, a very expose site may make working conditions

    more difficult and costly. Some locations may be more vulnerable to vandalism and theft

    and so require more costly protective measures.

    (2) Demolition site clearance: A site may contain buildings which requires demolition, paved

    areas which requires breaking up and trees which requires felling, grubbing up and

    disposal of their roots, another site may be cleaned of all obstruction.

    (3) Contours: Few sites are entirely level. The most steeply slopping, the more greater will

    be the cost of foundation and earthwork, the steeping of strip foundation increase their

    cost. Most buildings requires constant floor levels and this will involve considerable

    excavation and fill on its slopping site.

    (4) Ground conditions: Where the strata is low load bearing capacity. It may be necessary to

    introduce pile or other more expensive types of foundation. Raft foundations on made up

    ground or in areas liable to mining subsidence may be three trust as expensive as normal

    strip foundations where as pile foundation used to convey loads to a deeper load bearing

    strata could be as much as five times as expensive. The cost of excavation in rock could

    be five to eight times as expensive as working in normal ground, the provably length of

    haul in the disposal of surplus soil also needs consideration. Where ground water is close

    to the surface of the site, costly pumping operations may be needed. A wet site may also

    involve raising temporary sheds and offices on brick bases and more costly temporary

  • 27

    roads. The types of strata will also influence the form and extent of timbering or other

    means of supporting that will be needed to the sides of excavations.

    GENERAL OBJECTIVE FOR WEEK 5:

    Know factors affecting tender figures.

  • 28

    WEEK 5: MAJOR FACTORS AFFECTING TENDER PRICE (5.0)

    Construction cost is a broad phrase or term and can be interpreted to mean cost of any sort

    to anyone associated with construction work. It depends on the point of view let us say you

    are a contractor, your costs are your expenditure on labour, materials and plant. The clients

    cost of land, consultant fees and so on.

    The base cost of construction therefore comprises of expenditure on materials, labour and

    plant, the quantities of materials, labour and plant required for a job are determined &

    attaching prices to these defines the basic construction cost, but to these are also a variety of

    factors that affect this basic cost: -

    5.1 Factors Affecting Tender Price

    (1) Market Condition:

    The volume of work in progress in the area at a given point in time affect construction

    cost. When the market is burying with many project, tender price list are generally high.

    Most consultants are busy and competition is not keen. However during ausle times when

    there are few projects, contractors are anxious to out bid themselves so as to stay in

    business, so construction cost tends to be lower.

    (2) Availability of Materials:

    When required materials are readily available in an area where a project is to be executed,

    materials will be cheaper than where they are not so available. Generally, materials are

    cheaper where they are produced e.g if you can buy cement directly from Ashaka, the

    price will be a lot cheaper than in Kaduna because of transportation and profit margins of

    middlemen and so on. Imported materials for similar reasons are more expensive than

    locally produced materials.

    (3) Availability Of Labour:

    Where a certain type of labour is not readily available in the area where a project is to be

    constructed, it may be necessary to import from an area where such labour is available.

    Some inducement may have to be offered before such labour will move from its base

    such as transportation, accommodation, inconveniences allowances etc. these add to the

    cost of construction.

  • 29

    (4) Transportation:

    The farther a site is from town, the more expensive will be the construction cost e.g the

    same building to be constructed in Barnawa and also near Kaduna Airport will cost

    differently, the additional cost of transporting materials, labour and plants to the airport

    site will increase the cost of construction.

    (5) Location:

    The standard of living in an area affects the cost of construction. People are willing to pay

    higher prices for construction in places like Lagos and Abuja than are to pay in other

    places like Benin, Kaduna or Enugu.

    (6) Location of Site: -

    The particular location of the site can have significant effect on cost. Remote site may

    require additional cost for the provision or access roads and temporary services or the

    provision of additional security measures. Also, a site in a congested or restricted area

    also gives rise to major problems such as delivery & storage of materials and

    components, protection of adjoining buildings and the public, restriction on the use of

    mechanical plants and so on, all these will increase the cost of construction.

    (7) Time Consideration: -

    For certain reasons, a project may need to be completed in a very short time, this tends to

    push up construction cost. Labourers may be required to work overtime and overtime

    rates are usually higher than normal rates. Incentives scheme may have to be introduced

    to increase labour productivity. Closure supervision is necessary as mistake must be

    avoided, there may be time to apply remedial action.

    (8) Site Condition:

    May affect the construction cost of a particular building. The nature of ground may

    necessitate more complex form of foundation. The ground water level when close to

    surface will involve costly water pumping operation. A wet site may involve rising

    temporary sheds and offices above ground level and they involve more costly temporary

    roads. Steeply sloping site may involve major cost in cutting and filling requirements,

    existence of buried pipes and cables may involve major cost to re-root such.

    (9) Total Height of Building:

    The higher a building is, the longer it takes and more difficult it is to get the point of

    execution of works. It is also more difficult to work at such height. Labour charges for

  • 30

    working at great height are higher than abnormal height, there is also the cost of

    providing additional safety measures and insurance. Also, the need for special

    scaffolding, hoist, tower crane, elevators etc. will tend to increase the cost of very tall

    building over the cost of building requiring the same quantities at ground level.

    (10) Legislation:

    Has a way of affecting construction cost in dramatics manner as we have seen in Nigeria

    over the years e.g minimum wage, import restrictions and duties, labour policies, fiscal

    policies such as exchange rates, interest rates etc. in for costing construction cost, an

    estimator need to keep an eye on legislation, to decide which are likely to affect

    construction cost and how.

    (11) Class of Contractors:

    There are various types of contractors in the market. These gives rise to different

    classification.

    - Small contractors comprises of one man board of directors. They usually carry little

    general overhead and keep very few permanent staff

    - Medium contractors usually have a board of at least two but not more than five

    directors they employ a few more permanent staff, have a reasonable office and

    possess some equipment and official cars.

    - Large contractors have a lot of times publicly owned with many share holders having

    at least six members on their board of directors, fleet of cars and equipments, large

    office space and a lot of staffs of various discipline. Generally, the larger the firm, the

    higher their cost. Also, the level of profit expected by the share holder of larger firms

    is a lot more than that required by the smaller contractors. The rates for the small

    contractors therefore tends to be much lower than for large contractors (e.g AG

    Ferrero and small firms)

    (12) Type of Client:

    the type of client or developer can affect the cost of

    construction.

    Some clients are willing to and are capable of paying more for construction than

    others. Also, some clients have methods to be taken into consideration while

    estimating construction cost (e.g U.N.T.L will pay on time than N.N.P.C when a

    contract is carried out)

    (13) Types of Consultants:

  • 31

    - Architect: - Some architects are very difficult to work with, their initial designs are

    not detailed and they rely a lot on instructions on site. Many variations occur and

    delays are frequent. These will add to the cost of construction. The same applies to

    Engineers and other designers. Contractors are therefore known to increase their

    prices by a certain percentage when it is known that they would be working with

    particular consultant.

    (14) Types of Tendering:

    Open tendering generally brings lower prices than selective tendering, and this in turn

    result in lower price than negotiated tendering which brings the highest price of fall.

    GENERAL OBJECTIVE FOR WEEK 6:

    Use rate analysis to price items in the bill of quantities.

  • 32

    WEEK 6: PRICIPLES OF ANALYTICAL ESTIMATING (6.0) 6.1 Elements of a Unit Rate

    To analyse something is to break it down into its constituent parts and study each part in

    detail. Therefore analytical estimating involves the analysis and costing of construction

    resources to produce an estimate.

    The production of an estimate normally involves the calculation of unit rates i.e. the cost of

    an individual measured item for example a square metre of brickwork, a cubic metre of

    concrete or a metre of skirting. As found in a Bill of Quantities.

    Analytical estimating is therefore the most accurate form of estimating as each resource and

    unit rate is analysed and costed individually. This form of estimating is used for pricing

    contracts with bills of quantities, specifications and drawings or where the contractor has

    measured and prepared their own quantities of work.

    6.2 Calculation of Unit Rates

    Unit Rates maybe calculated in one of two ways:

    Net Rate (Excludes Overheads and Profit) Gross Rate (Includes Overheads and Profit)

    Unit Rate

    Materials Labour Plant

    Overheads Profit

  • 33

    In our industry most estimators will calculate costs based on net rates these will then be

    enhanced later to include overheads and profit. Gross rates are sometimes referred to as all-

    in rates.

    The Resources which compromise a unit rate are labour, materials and plant.

    In the construction industry labour is often employed in two main ways, these are:

    1. Direct

    Often referred to as cards in, the employer pays all the costs of employment including for

    example national insurance and sick pay amongst others.

    2. In-Direct

    These workers are self employed or referred to in industry as on the lump these are often

    labour only sub-contractors without the normal costs of employment along with the other

    legal protections such as redundancy, sick pay and minimum notice periods.

    Labour may be paid for on an hourly, daily, weekly or piecework basis. Directly employed

    operatives are usually paid in accordance with a working rule agreement which will specify

    the rates and allowances to be paid. However, some contractors are trying to move away

    from the national wage bargaining and introduce local wage rates. Ultimately the actual rates

    paid for labour will depend on market forces.

    6.2.1 Materials

    Several factors affect the cost contractors pay for materials.

    In the box below highlight the factors you think impact on the price a contractor pays.

    In the material element of a unit rate, in addition to the actual cost of the material the

    estimator must also consider:

    Transportation costs Unloading and Stacking costs Materials movement on site Extra Materials to compensate for:

    o Wastage o Allowance for materials being measured net in B o Q o Loss in consolidation, shrinkage etc

    Note: Where prices of materials are described by suppliers as ex works this means the price

    at the factory and delivery costs will have to be added.

    6.2.2 Plant

  • 34

    Plant may be divided into two main categories, the costs of which can be allocated to

    contracts in differing ways.

    Non-Mechanical Plant

    Basic items of plant including barrows, hosepipes, spades, trestles, scaffolding, small

    powered hand tools etc

    With the exception of scaffolding and one or two other items it is virtually impossible to

    allocate the cost of non-mechanical plant items to a contract, let alone to a specific unit rate

    e.g. a wheelbarrow may be used on several contracts in its lifetime.

    The cost may be included in overhead charges as a percentage, as a lump sum in the

    preliminaries bill or, more accurately, on longer contracts a list of non-mechanical plant items

    is prepared, costed and included in the contract sum.

    Mechanical Plant

    Mechanical plant such as excavators, lorries, dumpers, mixers etc require a more complex

    approach. Mechanical plant can be very expensive. Contractors may buy, hire or lease plant.

    The purchase of plant must be viewed as an investment on which a return is required. Only

    detailed analysis will show whether it is in the contractors interest to buy, hire or lease

    mechanical plant.

    6.2.3 Overheads

    Overheads may be defined as the cost of maintaining (running) the contractors organisation.

    There are two types of overheads:

    (1) Head Office

    Annual cost of staff salaries, expenses, rents, rates, gas, water, electricity, telephones,

    office equipment, postage, insurance, maintenance of buildings and equipment etc. The

    cost of these items is expressed as a percentage of a companys turnover and included in

    the tender.

    (2) Project or Site

    Project site costs including non productive (manual) site staff, site office costs, storage

    facilities and other preliminary / site organisation costs. Items are priced as individual

    items and may be fixed or time related costs or a mix of fixed and time related costs. The

    costs of these items are included in the tender.

  • 35

    6.2.4 Profit

    The amount of profit that a contractor can make is determined by a number of factors

    largely outside the remit of an estimator. However, in larger companies the senior or

    managing estimator may be a member of the management team and in smaller companies

    / firms the estimator may be a director or the managing director. In both cases they may

    be party to, or may have to make commercial decisions regarding profit margins.

    Factors affecting profit levels are:

    Market forces of supply and demand Amount of competition Who the competitor are Size / Value of contract Risk involved in contract Interest rates.

    Student Questions

    1. Define analytical estimating

    2. Explain the difference between net and gross unit rates

    3. List the elements of a unit rate

    4. Identify the organisations, which produce working rule agreements

    5. Define non-productive time and holiday credits.

  • 36

    WEEK 7: BUILD-UP HOURLY RATE FOR PLANT & EQUIPMENT (7.0)

    7.1 Calculation of Unit Rates

    The following sections cover the calculation of unit rates. The process of calculating unit

    rates could be described as mechanical because you must consider each of the unit rate

    elements in turn. Some rates may include all elements, others only one, but you must think

    carefully about each element and calculation before commencing.

    You may use the Wessex Price Book, or other similar price book, for information on the

    output/productivity of labour and plant. Materials and plant prices can be obtained from

    builders' merchants and plant hire firms.

    In practice estimators must always use productivity outputs analysed from site feedback

    and the current cost o f other resourcs.

    In the following unit rate calculations the hourly labour rates used are 9.50 for craft

    operatives and 7.00 for labour operatives.

    7.2 Groundworks

    SAQ 2

    Explain how the following factors may affect unit rates for groundworks?

    Type of excavation e.g. trenches, pits, basements Ground conditions e.g. clay, sand, soil, rock Depth of excavation Ground water Time of year when excavating Mechanical or hand excavation Distance and availability of tips Estimated bulking of materials 7.2.1 Hand Excavation

    Excavation work is usually measured in cubic metres (m3)

    Typical labour outputs for excavating in firm earth ;

    Reduce levels maximum depth 0.25m 3.15 hours/m3

    Trenches max. depth 1.00m 3.25 hours/m3

    Basements max. depth 2.00m 3.94 hours/m3

  • 37

    ADD the following factors for other ground conditions ;

    Dry or wet clay 20%

    Compact gravel 50%

    Rock not requiring a compressor 75%

    Running silt or sand 100%

    Example

    Excavate trench maximum depth 1.00m in firm earth, unit of measurement m3.

    Labour;

    - p

    3.25 hours for a labourer @ 7.00/hour 22 - 75

    ---------

    Net Rate per m3 22 - 75

    If you want a Gross Rate add for

    overheads and profit, say 10% 2 - 28

    ----------

    Gross Unit Rate per m3 25 - 03

    ======

    TQs 1 - 3

    Calculate net unit rates for the following ;

    1. Excavate to reduce levels max. depth 0.25m in firm earth,

    unit of measure m3

    2. Ditto basements max. depth 2.00m in dry clay

    unit of measure m3

    3. Ditto to reduce levels depth 0.25m in compact gravel

    unit of measure m2 (square metres)

    7.2.2 Mechanical Excavation

  • 38

    Rates for different types of mechanical plant vary enormously between contractors

    depending on the method used to calculate the costs.

    When calculating all-in hourly rates for mechanical plant the following items should be

    considered ;

    Capital cost Depreciation Interest on capital Expected life of plant Number of hours worked per annum Maintenance Insurance Road licence Operators wage Fuel Lubricants

    Think about how the above factors will affect the hourly cost of mechanical plant.

    Example

    The following is one method of calculating the all-in hourly cost of a mechanical excavator.

    This method is neither the simplest nor most complex method which can be used but it does

    produce realistic costs.

    Capital cost (purchase price) 37,000

    Residual Value (resale/scrap value) 6,000

    Interest on capital 6% compound

    Expected Life 5 years

    Hours worked per annum 1600

    Maintenance costs 10% of capital cost per annum

    Insurance included in company overheads

    Road Licence 200 per annum

    Operative's rate 7-50 per hour

  • 39

    Fuel 5 litres/ hour @ 40p/litre

    Lubricants allow 10% of fuel costs

    Standing Charge p

    Capital Cost 37,000-00

    Less Residual value 6,000-00

    -------------

    Depreciation 31,000-00

    Interest 6% compound on 37,000 over 5 years 12,506-00

    Maintenance 10% of capital cost per annum 18,500-00

    Road licence 200 per annum for 5 years 1,000-00

    -------------

    Total for 5 years 63,006-00

    -------------

    Therefore cost per hour is;

    Total cost for 5 years divided by total hours worked in five years

    63006 / (1600 hours x 5 years) 7-88

    Running Charge

    Drivers wages 1856 hours @ 7.50 13,920-00

    Fuel 1600 hours x 5 litres/hour x 40p/litre 3,200-00

    Lubricants 10% of fuel costs 320-00

    -------------

    Total for 1600 hours 17,440-00

    -------------

    Therefore cost per hour is 17440 / 1600hours 10-90

    Therefore total cost per hour is:

    Standing Charge 7-88

    Running Charge 10-90

    ---------

    Total Hourly Cost 18-78

  • 40

    ======

    TQ 4

    Using the following information calculate the "all- in" hourly cost for a 16 ton tipper lorry ;

    Capital cost 68,000

    Residual Value 5,000

    Interest on capital 6% compound

    Expected Life 10 years

    Hours worked per annum 2160

    Maintenance costs 10% of capital cost per annum

    Insurance 3000 per annum

    Road Licence 1,200 per annum

    Operatives rate 7-50 per hour

    Fuel 10 litres per hour@ 80p/litre

    Lubricants allow 10% of fuel costs

    7.3 Excavation using Mechanical Plant

    Excavate trenches maximum depth 2.00m in clay.

    Calculate the net rate per m3 using an excavator with an output of 5m3/hour for excavating

    and loading into lorries.

    Hourly cost of excavator / output in m3 per hour

    18-78 / 5m3 per hour 3 - 76

    SAQ 3

    The output of the excavator may also be expressed in hours per m3 , what is the output in

    hours per m3 ?

    Recalculate the rate using your output in hours per m3.

    7.4 Banksmen

    Banksmen are usually employed to supervise excavator/s. They check the excavation for

    obstacles i.e. underground services, make sure the excavator operator is working to the

    correct line and level and trim the sides and bottoms of excavations when necessary.

  • 41

    TQ 5

    Recalculate the last rate and include for one banksman supervising two excavators,

    banksmans rate 7.00 per hour.

    7.5 Disposal of Excavated Material

    SAQ 4

    Explain how the following factors may affect the cost of disposing of excavated material

    Bulking of material Availability of tips/landfill sites Distance to tip Average speed of lorry Loading time Tipping time Tipping charges/costs Consider alternatives

    TQ6

    Using the excavator and lorry from the previous example and the following information,

    calculate the cost per m3 for disposing of excavated material off site

    Note ; The following items are all variables (will vary on every contract) therefore a new

    rate must be calculated for each contract

    Assume ;

    16 ton lorry will carry approx. 6.5m3 of bulked clay

    Output of excavator 5m3 per hour

    Distance to tip 5 miles round trip

    Average speed 20 miles per hour

    Tipping time 15 minutes

    Tipping charge 20 per load

    7.6 Earthwork Support

    Defined in the Standard Method of Measurement as ;

    Whatever is necessary to support the faces of excavations other than steel sheet piles. It is

    measured to the faces of all excavations over 250mm deep.

  • 42

    The contractor has to decide what is necessary and cost it accordingly. This is referred to as a

    contractors risk item

    The following factors affect the cost of earthwork support ;

    Ground conditions Depth of excavation Distance between opposing faces of excavation Method of support used

    Contractors should also consider alternative methods of construction, which may be less

    expensive e.g. over excavate and backfill.

    Timber used for earthwork support (EWS) can be re-used up to say 6 times therefore the cost

    of providing the timber should be divided by the number of uses to obtain a cost per use.

    Operatives fixing EWS are usually paid an additional allowance for skill and responsibility.

    Materials

    100 x 100 costs 1-92/m

    150 x 100 costs 2-88/m

    150 x 150 costs 4-32/m

    200 x 50 costs 1-92/m

    Labour

    Fixing EWS in moderately firm earth to faces of excavation up to 2.00m apart and up to

    2.00m deep (see sketch) - 0.77 hours per m2

    Ditto in loose ground or running sand (as sketch) -

    1.65 hours / m2

    Hourly rate 7.50 / hour

  • 43

    WEEK 8: BUILD-UP UNIT RATE FOR SURFACE EXCAVATION (8.0)

    8.1 Surface Excavation

    In building up rate for excavation, the following should be considered.

    (a) Types of excavation i.e surface or trench excavation

    (b) Means of excavation i.e manual or mechanical

    (c) Nature of excavation

    (d) Volume of excavation (bulking)

    (e) Distance of tipping (haulage)

    Bulking

    Sand 12.5%

    Gravel 10%

    Clay 133 1/3%

    Rock 50%

    Multiplier

    Medium labour constant multiplier

    Sand and gravel 0.75

    Natural soil 1.00

    Stiff clay 1.50

    Soft rock 3.00

    Hard rock 8.00

    OUTPUT

    Excavation 2.5m3 / labour /day

    Spreading and leveling 4.5m3 / labour / day

    Wheeling / haulage 8.0m3 / labour / day

    Placing of concrete 4m3 / labour / day

    Task I:

    Surface excavation n.e 300mm deep and average 150mm, considered a gang of 12 labour and

    the supervisor. Calculate the cost/m3 given that the supervisor is N1500/day and the labourer

    N700/day

  • 44

    Solution

    Labour cost

    1 supervisor @ 1500/day N1500

    12 labourer @ 700/day N8,400

    Add 5% for tools N495

    N10,395

    Output of gangs / day = 2.5m3 x 12 = 30m3

    Labour cost/m3 = 10,395 x 1/30 = 346.50

    Add profit and overhead 20% 69.30

    Cost/m3 = 415.80

    Task II

    Cost of spreading and leveling excavated materials n.e 50m from excavation. Consider a

    gang of 12 labourers and 1 supervisor

    Solution

    1 Supervisor @ 1500 = N1500

    12 labouers @ 700 = N8,400

    5% Tools = 495__

    10,395

    Output gang / day = 4.5 x 12 = 54m3

    Loabour cost / m3 = 10,395/54 = 192.50

    Add overhead and profit 20% = 38.50 97.33

    8.2 Removal of Excavated Materials

    Use wheel barrows when the distinction is less than or equal to 50m .Used lories/tipper.

    When the distance is greater than 50m.

    Task III

    Removal of excavated materials using the same distance of cart away is less than or equal to

    50m using the same information used for excavation of surface

    Solution

    1 Supervisor, 12 labourers and 5% for tools = 10,395

    Out out of gang/day 8.0 x 12 = 96m3

    Labour cost / m3 = 10,395/96 = 108.28

  • 45

    Add 20% profit and overhead = 21.66

    225.94

    355.88

    When lories / tipper are used the following should be considered

    (b) Cost of hire or cost of owning

    (c) The capacity of the lorry

    (d) Total distance to and fro the hill

    (e) Speed of lorry

    (f) Tipping time

    (g) Labour loading the lorry

    (h) Bulking of materials

    TASK IV

    (a) For the cost of hiring plant is 600/hr

    (b) Capacity of lorry 6m3

    (c) Total distance to and fro is 3km

    (d) Speed of lorry 30km/hr

    (e) Tipping time 9 minutes

    (f) Output of labourer loading the lorry is 2hrs / labour /m3

    (g) Bulking of materials 133 %

    SOLUTION

    Volume of excavated material = 6/133 x 100 = 4.5m3 (assume 4 labour)

    loading time = 4.5m3 x 2hrs = 2.25hrs

    4

    Traveling time = 3km x 60m = 6mins

    30km/hr

    Total time for loading + traveling + tipping

    2.25 + 6m + 9

    2.25 = 2.15hr + 6m + 9m

    Cost of hiring lorry/hr

    = 2.5hrs x N600/hr

    = N1500/hr

  • 46

    Therefore, cost/m3 = N1500 = 333.33/m3

    Labour loading

    Cost for 1 labour /m3 = 150/8 x 2.5hr x 4 labour = 187.50

    Add 5% for tools = 9.38

    196.88

    333.33/m3

    530.21

    Add 20% overhead and profit 106.04

    636.25

  • 47

    WEEK 9: BUILD-UP UNIT RATE FOR CONCRETE WORK I (9.0)

    9.1 Concrete Work

    Explain how the following factors may affect unit rates for concrete work ;

    Whether ready mixed or site mixed concrete is used Whether concrete is reinforced Surcharges for part loads Location of mixing plant on site Type and size of mixing plant Method of transporting, hoisting, placing and compacting mixed concrete Cost of protecting and curing unset concrete Operatives working with concrete receive additional payments for skill and responsibility.

    Items of plant should be priced separately.

    Concrete is usually measured in m3

    Site Mixed Concrete

    TQ 7

    Calculate the cost of mixing a m3 of Grade 15 concrete on site using the following

    information ;

    To produce 1m3 of mixed Grade 15 concrete requires ;

    250Kg of cement at 80 per tonne

    600Kg of sand at 10 per tonne

    1200Kg of aggregate at 9 per tonne

    Waste say 5%

    Concrete mixer all-in rate 2-50 per hour, output 2m3 per hour

    Labour rate 7.20 per hour

    Labour out put 0.5m3 per hour

    Ready-Mixed Concrete

    TQ 8

    Calculate the cost per m3 for laying plain concrete 20N/mm2 in foundations over 300mm

    thick laid against faces of excavation.

    Ready mixed concrete costs 49.00/m3

  • 48

    Waste say 5%

    Labour output 1.00 hours/m3

    Labour rate 7.20 per hour

    SAQ 4

    What will happen to the labour output if the concrete is laid in foundations 150mm thick?

    Reinforcement is measured separately in bills of quantities. Would you expect the unit rate

    for laying reinforced concrete (excluding the cost of reinforcement) to differ from the unit

    rate for plain (unreinforced) concrete for similar items of work and if so why?

    9.2 Reinforcement

    Reinforcement may be bar type or mesh/fabric

    Waste

    Bars are usually delivered to site already cut and bent, if this is the case then allow 1% for

    loss and damage.

    If straight bars are to be cut and bent on site allow 5% for waste.

    On complex reinforced concrete work steel fixers are usually paid a craft operatives rate.

    When laying straight bars or mesh an enhanced labourers rate is usually paid.

    Mesh reinforcement is sheet material therefore allowances have to made for general waste

    say 2.5% plus an additional allowance for laps. The percentage to allow for laps will depend

    on the lap specified e.g. 150mm side and end laps.

    TQs 9-10

    Sheets of mesh are approximately 4.80m x 2.40m if they are to be laid with 150mm side and

    end laps what % must be allowed for loss in cover due to the laps ?

    Mesh reinforcement Ref. A193 in beds laid with 200mm side and end laps.

    Calculate the rate per m2.

    Mesh costs 14-00 per sheet

    Labour 0.05 hours / m2 at 7.20 / hour

    Allow say 20p / m2 for spacers and tying wire

    9.3 Guide to Using this Student Learning Pack

    Throughout this and the series of learning packs you will find, extensive notes on the various

    aspects of work you will be measuring followed by a series of three tasks, These tasks are

  • 49

    designed to increasingly develop your skills in the aspect of measurement covered by the

    learning pack, and will include, one basic task, which requires you to copy down a worked

    example, using the correct measurement layouts. The second task and third tasks form the

    second section of the class, where the class develops into a tutorial based

    9.4 Concrete Works

    As with groundwork, before looking at the calculation of unit rates we must understand that

    our final unit rate will be influenced by several variables.

    Task One

    In the box below, describe how you think the following factors would impact on cost.

    When considering concrete there are two main methods of producing concrete:

    1. Site mixed concrete

    2. Ready mixed concrete

    In addition to the method of concrete production when costing concrete work we must also

    consider concrete accessories including:

    1. Formwork

    2. Reinforcement

    3. Operatives working with concrete usually receive additional payments for skill and

    responsibility

    4. Items of plant concerned with concrete mixing and placing are usually measured

    separately.

    9.4.1 Site Mixed Concrete

    1. Ready mixed or site mixed concrete

    2. Whether the concrete is reinforced or un-reinforced

    3. Surcharges for part-loads

    4. Location of site in reference to mixing plant

    5. Type and size of mixing plant

    6. Method of transportation, hoisting, placing and compacting mixed

    concrete

    7. Protection of un-set and curing concrete

  • 50

    Calculate the cost of mixing one m3 of grade 15 concrete on site using the following

    information:

    The production of 1m3 of grade 15 concrete requires:

    250kg of cement at 92.70 / tonne 600Kg of sand at 17.25 / tonne 1200kg of aggregate at 18.02 / Tonne Waste allowance say 7.5% In addition allow for:

    concrete mixer @ all in rate of 3.00 / hr Labour rate @ 8.68 / hr

    9.4.2 Ready Mixed Concrete

    Calculate the cost per m3 for laying plain concrete 20N/mm2 in foundations over 300mm

    thick laid on or against earth or unbinded hardcore.

    Ready mixed concrete say 80.59 / m3 Waste say 5% Labour output = 1.00hrs / m3 Labour rate 8.68 / hr Questions:

    1. How would the labour output be affected if the concrete is laid in foundations 150mm

    thick?

    2. What would be the financial impact? (If any)

    9.5 Concrete Reinforcement

    Reinforcement is measured separately in bill of quantities. Would you expect the unit rate for

    laying reinforced concrete (excluding the cost of reinforcement) to differ from the unit rate

    for plain (unreinforced) concrete for similar items of work, if so why

    Reinforcement maybe either bar reinforcement or mesh / fabric reinforcement.

    Waste

    Bars are usually delivered to site already cut and bent, if this is the case then allow 1% for

    loss and damage.

    If straight bars are to be cut and bent on site allow 5% waste

    On complex reinforced concrete work steel fixers are usually paid a craft operatives rate.

    When laying straight bars or mesh an enhanced rate is usually paid.

  • 51

    Mesh reinforcement is sheet material therefore allowances have to be made for general waste,

    say 2.5% plus an additional allowance for laps. The percentage to allow for laps will depend

    on the lap specified e.g. 150mm side and end laps.

    Qu 1.

    Sheets of mesh are approximately 4.80m x 2.40m if they are to be laid with 150mm side and

    end laps what percentage must be allowed for loss in cover due to the laps?

    Qu 2

    Calculate the rate per m2 for laying mesh reinforcement Ref A193 in beds, laid with 200mm

    side and end laps.

    Additional information

    Mesh costs 15.08 per sheet Labour 0.05hrs / m2 @ 8.68 / hour Allow say 20p / m2 for spacers and tying wire Waste on mesh 5%

  • 52

    WEEK 10: BUILD-UP UNIT RATE FOR CONCRETE WORK II

    9.6 Concrete Work

    Explain how the following factors may affect unit rates for concrete work;

    Whether ready mixed or site mixed concrete is used Whether concrete is reinforced Surcharges for part loads Location of mixing plant on site Type and size of mixing plant Method of transporting, hoisting, placing and compacting mixed concrete Cost of protecting and curing unset concrete Operatives working with concrete receive additional payments for skill and responsibility.

    Items of plant should be priced separately.

    Concrete is usually measured in m3

    9.6.1 Site Mixed Concrete

    TQ 7

    Calculate the cost of mixing a m3 of Grade 15 concrete on site using the following

    information ;

    To produce 1m3 of mixed Grade 15 concrete requires ;

    250Kg of cement at 80 per tonne

    600Kg of sand at 10 per tonne

    1200Kg of aggregate at 9 per tonne

    Waste say 5%

    Concrete mixer all-in rate 2-50 per hour, output 2m3 per hour

    Labour rate 7.20 per hour

    9.6.2 Ready-Mixed Concrete

    TQ 8

    Calculate the cost per m3 for laying plain concrete 20N/mm2 in foundations over 300mm

    thick laid against faces of excavation.

  • 53

    Ready mixed concrete costs 49.00/m3

    Waste say 5%

    Labour output 1.00 hours/m3

    Labour rate 7.20 per hour

    SAQ 4

    What will happen to the labour output if the concrete is laid in foundations 150mm thick?

    Reinforcement is measured separately in bills of quantities. Would you expect the unit rate

    for laying reinforced concrete (excluding the cost of reinforcement) to differ from the unit

    rate for plain (unreinforced) concrete for similar items of work and if so why?

    9.7 Reinforcement

    Reinforcement may be bar type or mesh/fabric

    Waste

    Bars are usually delivered to site already cut and bent, if this is the case then allow 1% for

    loss and damage.

    If straight bars are to be cut and bent on site allow 5% for waste.

    On complex reinforced concrete work steel fixers are usually paid a craft operatives rate.

    When laying straight bars or mesh an enhanced labourers rate is usually paid.

    Mesh reinforcement is sheet material therefore allowances have to made for general waste

    say 2.5% plus an additional allowance for laps. The percentage to allow for laps will depend

    on the lap specified e.g. 150mm side and end laps.

    TQs 9-10

    Sheets of mesh are approximately 4.80m x 2.40m if they are to be laid with 150mm side and

    end laps what % must be allowed for loss in cover due to the laps ?

    Mesh reinforcement Ref. A193 in beds laid with 200mm side and end laps.

    Calculate the rate per m2.

    Mesh costs 14-00 per sheet

    Labour 0.05 hours / m2 at 7.20 / hour

    Allow say 20p / m2 for spacers and tying wire

    9.8 Concrete Work

    Concrete

    Material

    - cement

  • 54

    - sand

    - aggregate

    plant concrete mixer, poker, vibrator

    1m3 of .. weight 1440

    TASK

    Example a tonne of cement cost N14,000, sand cost 560/m3, coarse aggregate cost 900/m3 for

    a mix of 1:2:4. Calculate the cost/m3

    Solution

    1m3 cet will cost 1.44 @ 14,000 = 20,160

    2m3 of sand will cost 2 x 560/m3 = 11,120

    4m3 of aggregate will cost 4 x 900/m3 = 3,600

    24,880

    7m3 = 24,880

    1m3 will cost 24,880 = N3,554.29

    7

    Add 50% of void and compaction 1,777.14

    5,331.44

    Add 20% overhead and profit 1066.29

    6,397.73

    Mix shrinkage broken stone

    cement sand agg cement sand agg

    tonnes m3 m3 tonnes m3 m3

    1:1:2 0.524 0.36 0.72 0.552 0.38 0.76

    1:2:4 0.304 0.42 0.84 0.32 0.44 0.88

    1:3:6 0.440 0.44 0.88 0.23 0.46 0.92

    (void and compaction here have been taken care of)

    Plant

    Cost of mixer/hr

    The cost of owning and operating a 10/7 concrete mixer. Assume initial cost of N150,000, a

    scrap value of N10,000

    Life span of 6yrs @ 2000 hrs/year

    Compute the cost/hr

  • 55

    Capital cost/hr = initial cost scrap value

    Life span (hr)

    Therefore, Capital cost/hr = 150,000 10,000 = N11.66/hr

    6 x 2000

    Running cost

    Repairs and maintenance 10% of capital cost

    = N1.17/hr

    Fueling 1.8 liters @ N22 = 39.60/hr

    Oil and grease 20% of capital cost = 2.34__

    43.71/hr

    Cost of concrete mixer

    Cost of mixer / day = 54.77/hr x 8hrs = 438.16

    Cost of labourer / day 8 labour @ N400 = 3,200

    Add 5% for tools = 160_____

    Cost of labour and mixer 3,798.16

    Assume output of mixer / day = 20m3

    Therefore, cost /m3 = 3,798.16 = N189.91

    20m3

    Cost of placing concrete in foundation

    6 labourers need @ an output of 4m3/day

    Cost of 6 labourers = 6 x 400 = 2,400

    Add 5% for tools 120

    Cost/m3 = 2,520 = 630 4

    Cost of concrete in foundation

    Cost of conc /m3 = N6,397.73

    Add 5% of waste 319.88

    Cost of mixing / m3 189.91

    Cost of placing 630

    Add 20% for overhead and profit 7,537.52

    1,507.51

    N9,045.04

  • 56

    WEEK 11: BUILD UP UNIT RATES FOR REINFORCEMENT (11.0) 11.1 Bar Reinforcement Most bar reinforcement is bought in straight length of about 16ft. It is usually

    priced in tonne (1000kg) reinforcement supplied to site in which cost of

    transportation is not included in the calculation for unit rate, labour cost for

    unloading and stacking, cutting, bending and fixing are calculated. Some times

    bar reinforcement can be purchased already and bend to shape e.g links and

    stirrups and labour cost calculated will then only include the cost of fixing on site.

    Allowance for bending wire at intersections has to be made. The labour output

    should be taken as follows

    Cutting and bending

    Diameter 6 8 10 12 16 20 25 32 40 50

    Hours 63 45 35 27.2 22.5 15 12.5 10 8 6

    Fixing/tonne

    Diameter 6 8 10 12 16 20 25 32 40 50

    Hours 63 45 35 27.2 22.5 15 12.5 10 8 6

    NOTE:

    1. Assume 3hrs for unloading 1 tonne of reinforcement

    2. Allow 5% waste for cutting form straight length

    3. Allow 1% waste reinforcement already cut to shape

    4. for bars in short length e.g links and stirrups, allow 33% for extra labour

    Tying wire/tonne

    Diameter 6 8 10 12 16 20 25 32 50

    Hours 15 15 12 10 8 8 6 5 4

    Allow say N1000/tonne for spacers (biscuit)

    TASK I

    16mm mild steel bars reinforcement in straight and bent bars in suspended slab

    kg

    Solution

  • 57

    A Material Labour

    A1 16mm

    A2 Tying wire B1 Cutting and bending

    A3 Spacers B2 Fixing

    A1 Materials/tonne (1000kg)

    Assume cost of 16mm @ 34,000/tonne = 34,000

    Unloading and stacking 3hrs@400 = 1,200_

    35,200

    Allow 5% for waste 1760_

    36,960

    A2 Tying wire

    Assume 8kg @ 60/kg = 480

    Allow 5% for waste 24__

    504_

    A3 Spacers = N1000

    Allow 3% waste 30

    1030

    Material collection

    A1 36,960/tonne

    A2 504/tonne

    A3 1030/tonne)_

    38494/tonne

    Labour

    B1 Cutting and bending

    22.5hrs @ 50/hr = 1,125

    B2 fixing: 22.5hrs @50/hr = 1,125

    Labour collection

    B1 = 1,125

    B2 = 1,125

    2,250

    Summary

    Material = 38,494

    Labour = 2,250_

    40,744

  • 58

    Add 25% O/P = 10,186_

    50,930/tonne

    Cost/kg = 50,930 = 50.93

    = N51/kg

  • 59

    WEEK 12: BUILD-UP UNIT RATE FOR FORMWORK (12.0)

    12.1 Formwork

    Formwork measures the actual faces of work covered or to be supplied. The

    following must be taken into consideration in determining the size of the formwork

    1. The amount of material required

    2. The kind of finishes required i.e sawn faced or smooth finish, ground finish,

    biscuit etc. This determine the types of materials to be used as formwork and the

    surface from finish required is removed.

    3. the height to be supported. This determine the height of props and types of

    props.

    4. Normal labour for fabricating, erecting and striking of formwork.

    5. the number of uses required of the formwork this is usually a matter of

    experience.

    In small contract it may be possible to reuse the same formwork twice depending on

    the repetitive nature of the work.

    Materials

    Materials Unit Rate

    1 x 12 x 12 sawn Length 130

    1 x 12 x 12 wrought Length 230

    2 x 4 x 12 Length 120

    4 x 4 x 12 Length 180

    5 nails Kg 135

    4 nails Kg 135

    3 nails Kg 135

  • 60

    2 nails Kg 150

    Labour output are mostly conveniently calculated/m3 of timber

    Labour output for suspended slab

    Description Output

    Unloading and stacking 2.5m3/lbour/day = 250

    Cutting, fabricating and erecting 0.80m3/gang/day (2carpenters + labour

    Striking 12m2/gang/day

    Allowance for waste

    Cutting and fixing of timber 10%

    Nails 20%

    TASK I

    Sawn formwork to horizontal soffit of suspended slab m2

    Assume 3m height above floot level

    Solution

    Materials

    A1 1 x 12 x 12 softwoods planks

    A2 2 x 4 hardwood battens

    A3 4 x 4 hardwood props

    A4 4 nails

    Labour

  • 61

    B1 Unloading and stacking

    B2 Cutting, fabricating and erecting

    B3 Striking

    NOTE:

    3.6 x 1.2 for the calculation and divide by 4.32m2 after all to arrive at cost/m2. This

    convenient size allow for more length of timber piece to be used and there by

    simplifies the calculation

    A1 4nr sawn softwood planks @ 180 720.00

    Add 10% waste 72.00 792.00

    A2 2 x 4 x 12 battens 2 x 3.6 = 7.2

    4 x 12 = 4.8

    12.00

    12.00m = 3 length or 3.33 + 1 = 4 x 480.00 3.6m

    Allow 10% waste 48.00_ 528.00

    A3 props @ 1.00m c/c

    4 x 4 x 12 props 8nr x 3 = 24m

    24 7 lengths @ 180 1,260

    36 add 10% for waste 126_ 1,386

    A4 1kg of nail 4 @ 135 135.00

    Allow 20% waste 27.00 162.00

  • 62

    Material for collection

    A1 792.00

    A2 582.00

    A3 1,386.00

    A4 162.00

    N2,868.00

    Assume 3 uses

    Cost/use = 2,868 = 956 3

    Cost/m2 = 956 = 239 4.32

    Labour

    Volume of timber

    25 x 300 x 3600 x 4nr = 0.108

    50 x 100 x 3600 x 2nr = 0.0136

    50 x 100 x 1200 x 4nr = 0.24__ 0.408

    Allow 10% for waste 0.041___ 0.449m3

    Unloading and stacking

    2.50m3 = 1 labour / day = N250.00

    Therefore, 0.45m3 = 700 x 0.45 = N126 = 126 2.5

    Cutting, fixing and erecting (gang)

    2 carpenters @ 1500 = 3000

    1 labour @ 700 = 700_ 3,700 0.8m3 = 1 gang/day = N3,700

  • 63

    0.45m3 = 3,700 x 0.45 = 2,081.25 = 2,081.25 0.8 Striking

    12m2 = 1 gang/day = 3,700

    4.32m2 = 3,700 x 4.32 = 1,332 = 1,332__ 12m 3,539.25

    Labour cost collection

    Cost of labour = 3,539.25 = N819.27 4.32

  • 64

    Summary

    Materials = 221.30

    Labour = 819.27 1,040.57

    Add 25% P/O 260.14_ N1,300.71

  • 65

    WEEK 13: BUILD-UP UNIT RATE FOR ROOFING (13.0)

    13.1 Roofing

    Corrugated roofing sheet, operation output /gang / day

    Aluminium of galvanized iron unloading + fixing 40m2

    Fixing ridge cap 35m

    Raking and cutting 30m

    Straight cutting 30m

    Asbestors unloading + fixing 30m2

    Fixing ridge cap 20m

    Raking + cutting 25m

    Straight + cutting 25m

    Felt roofing unloading + laying of layer 120m2

    Spreading bitumen primer 80m2

    Spreading bitumen 80m2

    Spreading chips 100m2

    Laying gutters < 1m girth 20m

    Raking cutting 90m

    TASK I

    0.7mmm thick corrugated aluminium long span roof covering fixed to timber purlins (m.s)

    @900mm c/c with 50mm galvanized drive screw with felt and metal washer including

    100mm side laps (measured net) in m-square i.e (100mm2)

    (A) Materials

    A1 0.7m long span Aluminium sheet

    A2 Galvanized drive screw + washers

  • 66

    (B) Labour

    B1 Unloading and fixing

    Laps = (0.75 0.10) x 1m

    = 0.65m2

    A1 roofing sheet required = 100m2

    0.65m2

    = 153.85

    Add 5% for waste 7.70

    161.55m2

    Cost/m2 = N1200

    161.55@1200 = N193,860

    A2 Galvanized drive screw

    Number required = 4no/m2 x 100m2 = 400nr

    Allow 10% for waste 40______

    440 pieces

    N6/screw

    Cost 440 pieces @ N6 = N2640

    Material collection

    Corrugated roofing sheet N193.860

    Screw + washer 2,640__

    196.500

    Labour

    A gang / day

    2 carpenters (roofers) @1500/day = N3000

    1 labourer @700/day = 700

    =N3700

    Add 5% for tools =_185_________

    3885/gang/day

    Unloading and fixing 1 gang /day output = 40m2

  • 67

    40m2 = 1 gang / day = N3885

    100m2 = 3885 x 100m2 = 9,712.50

    40m2

    Summary

    Materials N196,500.00

    Labour 9,712.50__

    206,212.50

    Allow 25% for profit and over head 51,553.13__

    257,765.63

    Therefore, cost/m2 = 257,765.63 = N2577.66

    100m2

    TASK II

    2 layers of bituminous felt roof covering laid on flat weighing 25kg/roll of 20m2 with 100 and

    150mm end and side laps respectively and finished with 6mm chipping. Assume 100m2

    covering.

    MATERIAL LABOUR

    (1) Felt (2 layers ) unloading + fixing of felt

    (2) Bitumen primer spreading bitumen primer

    (3) Bitumen (3 layers) spread bitumen

    (4) chipings spreading chippings

    Plant

    Boiler

    A1 laps

    (20m x 0.15m) + (0.085 x 0.10m) = 3.085m2 = 3.09m2

    Covering capacity / roll = 20.00m2

    Less laps 3.09____

    16.91m2

    Nr of rolls required = 100m2 = 5.91 roll

    Allow 3% for waste = 0.18

    6.09 roll/layer

    Therefore, 2 layers will be required = 6.09 x 2 = 12.18 rolls

  • 68

    12.18 rolls@2500 = N30,450

    Bitumen primer

    A2 Assume a covering capacity of 7m2/liters

    Therefore, bitumen required 100m2 = 14.29 liters

    7 liters

    Allow 5% waste 0.71_____

    15.00 liters

    20 liters / drum = 1600

    Therefore, 15 liters will cost 1600 x 15 = N1,200

    20

    A3 Bitumen (3 layers)

    Assume a covering capacity of 2kg

    (m2 bitumen required / layer = 2 x 100m2 = 200kg

    Allow 10% for waste 20

    220

    For 3 layers x 3

    660kg

    480kg / drum of R115 / 15 (type) cost N20,000

    Therefore 660kg will cost 20,000 x 660 = N27,500

    480

    A4 Assume a covering capacity of 60m2 / tonne

    Chippings of tonne required = 1/60 x 100m2 = 1.67 tonne

    Or 100m2 / 60m2 1.67 tonnes

    If 1 tonne of chippings cost N7,000

    Therefore 1.75 tonnes will cost 1.75 x 7000 = N12,250

  • 69

    Material cost collection

    A1 felt = 30,450

    A2 primer = 1200

    A3 bitumen = 27,500

    A4 chippings = 12,250

    N71,400

    B1 unloading and fixing

    Output = 120m2/gang/day (felt)

    100m2 = 1/120 x 100 = 0.83 (a layer)

    2 layers = 2 x 0.83 = 1.66

    B2 Output = 80m2 / gang / day (primer)

    = 100m2 = 1/80 x 100 = 1.25

    B3 Output = 80m2 / gang / day (bitumen)

    3 layers = 3 x 1.25 = 3.75

    Chippings 1.00

    7.66

    B4 Output = 100m2 / 100m (chippings) = 1.00

    7.66 gang @ N1,575 = N12,064.50

    (d) PLANT: cost of plant/hr N150

    Cost of plant/day N150 x 8hrs = N1200

    Summary

    A. Material = 71,400.00

    Labour = 12,064.50

    Plant = 1,200.00

    84,664.50

    Add 25% profit and overhead 21,166.50

    105,830.03

    Cost/m2 = N105,830.63 = 1,058.31

    100m2

  • 70

    NOTE:

    Allowance has to be made for the following

    - Irregularity of surfaces

    - Compression of toweling 80%

    - General waste (residue + application)

    TASK I

    12.5mm thick c/s (1:4) rendering trowel smooth

    (a) Wall

    (b) Concrete soffit (100m2)

    Material labour

    Cement 1m3 mixing

    Sand 4m3 rendering

    5m3

    1m3 cement 28 bags @ 700 = N19,000.00

    Transport, loading and unloading 28 bags @ 10 bags = 280___

    19,880

    Allow 2% waste 397.00

    20,277.60

    4m3 of sand

    4m3 of sand @ N600/m3 = 2,400

    Allow 5% for waste = 2,520

    Cement = 20,277.60

    22,797.00

    Allow 25% for shrinkage 5,699.40

    28,497.00

    Cost/m2 = 28,499

    5m3

    = N5,699.40

    Volume of mortar required 100m2 x 0.0125m3

    1.25m3

    Allow 80% 1.00___

  • 71

    2.25m3

    Therefore, 2.25m3 of mortar @ 5,699.40 = 12,823.65

    Labour

    1. Mixing = 1m3 = 1 labour day@ N700/day

    2.25m3 = N700 x 2.25m3 = N1575

    2. Rendering = 30m2 = 1 gang/ day = N3885 (reference to roof)

    100m2 = N3885 x 100m2 = N12,950

    30m2

    Labour

    1. Mixing 675

    2. Rendering 12,950_

    13,625.00

    Add 5% for tools 681.25__

    14,306.25

    Summary

    Material = 12,823.65

    Labour = 14,306.25

    27,129.9

    Add 25% P/OH 6,782.48_

    33,912.38

    Cost/m2 = 33,912.38 = N339.12

    100

  • 72

    WEEK 14: BUILD UP UNIT RATE FOR MASONRY (14.0)

    14.1 Guide to Using this Student Learning Pack

    Throughout this and the series of learning packs you will find, extensive notes on the various

    aspects