Client: Website: Project Name: Email: Project ID: Contact: Last Updated: 8/3/2020 CIVIL WORKS S# DWG REF DETAIL REF CSI No DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE 1 General Requirements 1 LS Subtotal Base bid 310000 DIVISION 31 - EARTHWORK 310000 EARTHWORK 2 CU101, ES102, MS102, TS102 Excavation and backfill for utility pipe trenching 2700 cu. m 3 MS101 Remove underground mechanical piping incl. excavation, backfilling and any pavement repair/replacement Note: Quantity is taken from Mechanical site demo drawing. Existing pavements are not shown on this drawing 181 Lin. m 4 C508 Temporary erosion control Note: Temporary erosion control details are provided only. Erosion control plans are not given 1 ls Subtotal 320000 DIVISION 32 - EXTERIOR IMPROVEMENTS 5 CU101 F1, A7/C503 Sawcut, remove and replace AC pavement at utility trenching (412 Lin. m) as: - 50mm AC surface course - 150mm Base course (M30 or M40) - 150mm Subbase course (C 40) 720 sq. m 6 CU101 Sawcut, remove and replace concrete sidewalk at utility trenching (10 locations) as: - 100mm Concrete slab - 150mm Aggregate base course 50 sq. m 7 CU101 Restore grass area at utility trenching 230 sq. m Subtotal 330000 DIVISION 33 - UTILITIES 8 CU101 100mm sewer line 14 Lin. m 9 ES102, TS102 E501, T501 Concrete ductbanks 110 cu. m 10 CU101, ES102 E504 (1800x2000x2350mm deep) Electrical concrete manhole 4 ea 331100 WATER UTILITY DISTRIBUTION PIPING 11 CU101 150mm DIP water fill line 83 Lin. m 12 CU101 Ground cleanout 2 ea Subtotal Total (base bid) Bid option 2 SITEWORK 020000 DIVISION 02 - EXISTING CONDITIONS 020000 DEMOLITION 13 CD101,102 Remove sidewalk and curb 129 sq. m 14 CD101,102 Remove AC pavement 523 sq. m 15 CD101,102 Remove parking stall stripping and pavement markings 2400 Lin. m 16 CD101,102 Remove mechanical pit and curb island. Backfill resulting void 10 sq. m Subtotal QUANTITY TAKE-OFF SHEET (Hidden for Privacy) (Hidden for Privacy) (917) 675-3388 www.qtoestimating.com [email protected] (Hidden for Privacy) 1

QUANTITY TAKE-OFF SHEET

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: QUANTITY TAKE-OFF SHEET

Client: Website:

Project Name: Email:

Project ID: Contact:

Last Updated: 8/3/2020

CIVIL WORKS

S# DWG REF DETAIL REF CSI No DESCRIPTION QTY UNITUNIT

PRICE

TOTAL

PRICE

1 General Requirements 1 LS

Subtotal

Base bid

310000 DIVISION 31 - EARTHWORK

310000 EARTHWORK

2

CU101,

ES102,

MS102,

TS102

Excavation and backfill for utility pipe trenching 2700 cu. m

3 MS101

Remove underground mechanical piping incl. excavation,

backfilling and any pavement repair/replacement

Note: Quantity is taken from Mechanical site demo

drawing. Existing pavements are not shown on this

drawing

181 Lin. m

4 C508

Temporary erosion control

Note: Temporary erosion control details are provided

only. Erosion control plans are not given

1 ls

Subtotal

320000 DIVISION 32 - EXTERIOR IMPROVEMENTS

5 CU101 F1, A7/C503

Sawcut, remove and replace AC pavement at utility

trenching (412 Lin. m) as:

- 50mm AC surface course

- 150mm Base course (M30 or M40)

- 150mm Subbase course (C 40)

720 sq. m

6 CU101

Sawcut, remove and replace concrete sidewalk at utility

trenching (10 locations) as:

- 100mm Concrete slab

- 150mm Aggregate base course

50 sq. m

7 CU101 Restore grass area at utility trenching 230 sq. m

Subtotal

330000 DIVISION 33 - UTILITIES

8 CU101 100mm sewer line 14 Lin. m

9ES102,

TS102E501, T501 Concrete ductbanks 110 cu. m

10CU101,

ES102E504 (1800x2000x2350mm deep) Electrical concrete manhole 4 ea

331100 WATER UTILITY DISTRIBUTION PIPING

11 CU101 150mm DIP water fill line 83 Lin. m

12 CU101 Ground cleanout 2 ea

Subtotal

Total (base bid)

Bid option 2

SITEWORK

020000 DIVISION 02 - EXISTING CONDITIONS

020000 DEMOLITION

13 CD101,102 Remove sidewalk and curb 129 sq. m

14 CD101,102 Remove AC pavement 523 sq. m

15 CD101,102 Remove parking stall stripping and pavement markings 2400 Lin. m

16 CD101,102Remove mechanical pit and curb island. Backfill resulting

void10 sq. m

Subtotal

QUANTITY TAKE-OFF SHEET

(Hidden for Privacy)

(Hidden for Privacy)

(917) 675-3388

www.qtoestimating.com

[email protected]

(Hidden for Privacy)

1

Page 2: QUANTITY TAKE-OFF SHEET

Client: Website:

Project Name: Email:

Project ID: Contact:

Last Updated: 8/3/2020

CIVIL WORKS

S# DWG REF DETAIL REF CSI No DESCRIPTION QTY UNITUNIT

PRICE

TOTAL

PRICE

QUANTITY TAKE-OFF SHEET

(Hidden for Privacy)

(Hidden for Privacy)

(917) 675-3388

www.qtoestimating.com

[email protected]

(Hidden for Privacy)

310000 DIVISION 31 - EARTHWORK

310000 EARTHWORK

17 CS101,102 C504, C511 Excavation for fence footings and sign post footings 5 cu. m

18 C508

Temporary erosion control

Note: Temporary erosion control details are provided

only. Erosion control plans are not given

1 ls

Subtotal

320000 DIVISION 32 - EXTERIOR IMPROVEMENTS

19 A1,D1/C510 C511 2400mm H Chain link fence incl. (1) double gate 44 Lin. m

20CS101,

A1,D1/C510C504, C511 Concrete footing for fence and signage posts 2 cu. m

21 D1/C510Concrete pad

Note: Pad thickness is not given12 sq. m

22 CS101,102 Grass area 136 sq. m

23 CS121 A4/C503 200x150x1800mm Precast concrete wheel stop 8 ea

24 CS101 C504 Post mounted regulatory signage 13 ae

321123 AGGREGATE BASE COURSES

25 CS101,102 C503 Gravel base below curb 21 cu. m

26 D1/C510 100mm gravel surface 4.8 cu. m

321217 HOT MIX BITUMINOUS PAVEMENT

27 CS101,102 F1/C503

AC pavement as:

- 50mm AC surface course

- 150mm Base course (M30 or M40)

- 150mm Subbase course (C 40)

390 sq. m

321236 SLURRY SEAL

28 CS101,102Note 9 on

CS101Solar reflective coating on asphalt pavement 8130 sq. m

321613CONCRETE SIDEWALKS AND CURBS AND

GUTTERS

29 CS101,102 D9,F9/C503 160x200 Precast concrete curb 274 Lin. m

30 CS101,102 D7/C503 160x100 Precast concrete slant curb 63 Lin. m

31 CS101,102 C503 Plain concrete below curb 8 cu. m

32 CS101,102 C503

Concrete sidewalk and ramp as:

- 100mm Concrete slab

- 150mm Aggregate base course

190 sq. m

33CS101,102,

CS505,507A1/C505 Truncated domes 18 sq. m

321723 PAVEMENT MARKINGS

34 CS101 D9/C504 300mm wide yellow striping (Loading/unloading striping) 1252 Lin. m

35 CS101 A5/C504 300mm wide yellow striping (parking island striping) 493 Lin. m

36 CS101,102 C504 100mm wide white striping 1975 Lin. m

37 CS101,102 C1/C505 1600mm H ADA signage striping 8 ea

38 CS101,102 F9/C504 450x150 Parking stall unit number marking 239 ea

Subtotal

Total (Option 2)

Bid option 6

39 D5/C510 C511 2400mm H Chain link fence incl. (1) double gate 28 Lin. m

40 D5/C510 C511 Concrete footing for fence posts 1 cu. m

41 D5/C510Concrete pad

Note: Pad thickness is not given12 sq. m

42 D5/C510 100mm gravel surface 4 cu. m

43 ES103 E501 Concrete ductbanks 49 cu. m

44CU101,

ES103Excavation and backfill for utility trenches 380 cu. m

2

Page 3: QUANTITY TAKE-OFF SHEET

Client: Website:

Project Name: Email:

Project ID: Contact:

Last Updated: 8/3/2020

CIVIL WORKS

S# DWG REF DETAIL REF CSI No DESCRIPTION QTY UNITUNIT

PRICE

TOTAL

PRICE

QUANTITY TAKE-OFF SHEET

(Hidden for Privacy)

(Hidden for Privacy)

(917) 675-3388

www.qtoestimating.com

[email protected]

(Hidden for Privacy)

45CU101,

ES103F1, A7/C503

Sawcut, remove and replace AC pavement at utility

trenching as:

- 50mm AC surface course

- 150mm Base course (M30 or M40)

- 150mm Subbase course (C 40)

96 sq. m

46CU101,

ES103

Sawcut, remove and replace concrete sidewalk at utility

trenching (5 locations) as:

- 100mm Concrete slab

- 150mm Aggregate base course

40 sq. m

47CU101,

ES103Restore grass area at utility trenching 110 sq. m

48 C508

Temporary erosion control

Note: Temporary erosion control details are provided

only. Erosion control plans are not given

1 ls

Total (Option 6)

3

Page 4: QUANTITY TAKE-OFF SHEET
Page 5: QUANTITY TAKE-OFF SHEET
Page 6: QUANTITY TAKE-OFF SHEET
Page 7: QUANTITY TAKE-OFF SHEET
Page 8: QUANTITY TAKE-OFF SHEET
Page 9: QUANTITY TAKE-OFF SHEET
Page 10: QUANTITY TAKE-OFF SHEET
Page 11: QUANTITY TAKE-OFF SHEET
Page 12: QUANTITY TAKE-OFF SHEET
Page 13: QUANTITY TAKE-OFF SHEET
Page 14: QUANTITY TAKE-OFF SHEET