112

QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

  • Upload
    buitram

  • View
    215

  • Download
    1

Embed Size (px)

Citation preview

Page 1: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection
Page 2: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 2 of 82 Revision 00A

TABLE OF CONTENTS

1. Introduction 5 1.1. Purpose 5 1.2. CECP Objectives 6

2. Project Description 7 2.1. Overview of Auckland Point Logistics Facility 7 2.2. Surrounding Development 7 2.3. Location and Description 9 2.4. Filling and Excavation Works 10 2.5. Area 2 Drainage Management 11 2.6. Overview of Auckland Point Area 2 Facility Layout 11 2.7. Roads 12 2.8. Traffic and Car Parking 12

3. Legislative Framework 14 3.1. National Strategies 14 3.2. Commonwealth Legislation 14 3.3. Queensland Legislation 14 3.4. Guidelines and Standards 15 3.5. Licenses and Permits 16

4. Environmental Risk Assessment Process 17

5. Environmental Management Process 18 5.1. Environmental Policy 18 5.2. Gladstone Port Corporation Environmental Policy 18 5.3. Roles and Responsibilities 18 5.4. Reporting Requirements 20 5.5. Environmental Procedures and Forms 21

6. Site Specific Environmental Aspects 22 6.1. General Construction 23 6.2. Construction Noise and Vibration 25 6.3. Soil Erosion and Sediment Control 27 6.4. Management of ASS 30 6.5. Waste Management 33 6.6. Hazardous Substances Management 36 6.7. Contaminated Sites 40 6.8. Air Quality 42 6.9. Greenhouse Gas 45 6.10. Surface Water Quality 46 6.11. Weed and Pest Management 51 6.12. Red Imported Fire Ant 53

Page 3: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 3 of 82 Revision 00A

6.13. Mosquito and Biting Midge 55 6.14. Visual Amenity 56 6.15. Lighting 57 6.16. Traffic and Transport 58 6.17. Indigenous Cultural Heritage 60 6.18. Non-Indigenous Cultural Heritage 61 6.19. Stakeholder Management 63

7. Environmental Performance 65 7.1. Environmental Inspection 65 7.2. Environmental Auditing 65 7.3. Environmental Monitoring 67 7.4. Reporting and Compliance Checking 68 7.5. Identifying Environmental Issues and Corrective Actions 68

8. Communication 71 8.1. Internal Communication 71 8.2. External Communication 71 8.3. Community Engagement and Consultation 71

9. Training and Environmental Awareness 73 9.1. New-Hire Orientation – Environmental Awareness 73 9.2. Supervisor Construction Environmental Awareness Training 74 9.3. Hazardous Material Management and Spill Response Training 74 9.4. Construction Execution Plans 74 9.5. Toolbox Talks 74 9.6. Job Hazard Analysis 75

10. Emergency Preparedness and Response 76

11. Document Control 77 11.1. Document Control and Record Management 77 11.2. CECP Review 77

Page 4: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 4 of 82 Revision 00A

List of Acronyms

ASS Acid Sulphate Soils

DERM Department of Environment and Resource Management

DPI&F Department of Primary Industries and Fisheries

CECP Construction Environmental Control Plan

GPC Gladstone Port Corporation

HSSE Health, Safety, Security and Environment

JHA Job Hazard Analysis

LNG Liquefied Natural Gas

MLWS Mean Low Water Springs

MSQ Maritime Safety Queensland

MSDS Material Safety Data Sheets

PASS Potential Acid Sulphate Soils

QASSIT Queensland Acid Sulphate Soils Investigations Team

QCLNG Queensland Curtis Liquefied Natural Gas

QGC Queensland Gas Company

RIFA Red Imported Fire Ants

SOPEP Shipboard Oil Pollution Emergency Plan

WMS Work Method Statement

List of Attachments Attachment A Site Drawings

Attachment B Environmental Risk Register

Attachment C QGC Environmental Policy

Attachment D Sample Environmental Inspection Checklists

Page 5: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 5 of 82 Revision 00A

1. Introduction 1.1. Purpose

This Construction Environmental Control Plan (CECP) is being submitted by Queensland Gas Company (QGC). The CECP focuses on land-based construction activities within Area 2 of the Auckland Point Logistic Facility, Gladstone, Queensland a component of the Queensland Curtis Liquefied Natural Gas (QCLNG) Project. The Auckland Point Area 2 component comprises the development, construction and operation of a Personnel and Construction Materials Movement Area located at Auckland Point within the Gladstone Strategic Port Area.

The environmental impact assessment process for the QCLNG Project has identified certain environmental management aspects that require integration into the construction phase. The intention of this CECP is to describe the Project’s system for minimising and managing environmental risks associated with construction activities at Auckland Point Area 2. This CECP addresses the current permit Conditions of Approval issued for construction at Auckland Point. The following permit relevant to Construction at Auckland Point was issued at the time of preparation of this CECP:

Auckland Point Land Operational Works Permit (OPW) – DA 2010/03.

The document is to be updated following the issue of additional permits applicable to construction, as the design and procurement process progresses and prior to commission such that the document remains current and to identify the site specific environmental management measures that will be required.

The CECP includes an overview of the legal obligations pertaining to the construction activities at Auckland Point Area 2, as well as measures and policies that will be implemented. Key objectives and performance criteria will be adopted and will be the primary requirement for auditing and compliance monitoring purposes. Any non-conformances will be reported in accordance with the reporting requirements. Each environmental aspect is discussed in the CECP in relation to the potential environmental impact, control measures to avoid or limit impacts and monitoring requirements.

Community engagement strategies are discussed in the CECP. An appropriate engagement and complaints handling process will help to determine where environmental impacts such as noise and changes to air quality may occur and where management measures may be required.

Lastly, an Emergency Response for Environmental Incidents Management Plan has been developed for construction activities at Auckland Point Area 2, and these broad strategies are discussed in this CECP.

Page 6: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 6 of 82 Revision 00A

1.2. CECP Objectives

The key objectives of the CECP are to:

Set out a plan such that works are carried out in a manner using the implementation of appropriate environmental management practices.

Implement a system for compliance with applicable legislation and non-legislation requirements and obligations and commitments including:

- Relevant legislative requirements

- Licences and approvals

- Non-legislative requirements and commitments

Develop, implement and monitor measures to address pollution.

Respond to changes in environmental conditions during the proposed works through review and monitoring and control programmes.

The CECP consists of a suite of environmental planning and management instruments (e.g. Management Sub-Plans, Work Method Statements) that will be implemented during construction at Auckland Point Area 2 to limit and manage environmental and community risks and impacts.

Page 7: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 7 of 82 Revision 00A

2. Project Description This CECP has been prepared to manage the construction of Auckland Point Area 2 – Personnel and Construction Materials Movement Area. This area (approximately 64,500m2 in total) is required to facilitate the movement of personnel, freight and equipment which is being transported to and from Curtis Island. Plans for the facility are included in Attachment A.

2.1. Overview of Auckland Point Logistics Facility

QGC proposes to construct a logistics facility (consisting of offices, material staging/storage areas and car parks) at Auckland Point (refer to Figure 1). This facility will function in conjunction with an on-site marine facility to provide access to the QCLNG site on Curtis Island and allow for the movement of personnel and materials for the construction phase of the QCLNG Project.

The supporting logistics facility is proposed to consist of four main areas which are described in Table 1:

Table 1 Auckland Point Logistics Facility

Area Purpose Area One Freight Handling Area/Employment Centre 3.0 Ha Two Personnel and Construction Materials Movement

Area 6.45 Ha

Tree Intermediate Holding and Loading Area 0.6 Ha Four Lay-down Area 10.33 Ha

In addition, the following areas will be incorporated in the Logistics Facility:

COMMON ACCESS AREA, directly adjacent to proposed Area 2 of approximately 0.72 Ha.

PROPOSED ROAD AREA, for the construction of two access roads to provide access between Areas 1, 2 and 3 and surrounding road networks of approximately 1.27 Ha.

2.2. Surrounding Development

The greater Auckland Point area includes four existing wharves. To the north east of the site is the Barney Point Wharf, to the north west is the Auckland Point Tug Berth, within Lot 300 north west of Area 1 and 3 is the Origin LPG terminal. These wharves are utilised for the export and storage of goods. The land proposed to be used for the Auckland Point Logistics Facility is an existing brown field site owned by GPC and is described in the Gladstone Planning Scheme as Strategic Port Land.

Page 8: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 8 of 82 Revision 00A

Figure 1 Auckland Point Logistics Facility Site Layout (Source: QGC)

Page 9: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 9 of 82 Revision 00A

2.3. Location and Description

Auckland Point Area 2 is located in the north eastern corner of Lot 300 on SP120920 at Auckland Point, Gladstone. Area 2 is on the eastern side of Lot 300, with McFarlan Drive bounding the northern and eastern edge. Proposed Access Road 1 is located to the south and connects Tug Berth Access Road with McFarlan Drive. Access to Area 2 is currently achievable from the north western boundary through the existing security fenece of the Barney Point Coal Terminal.

The nearest sensitive receptors to Area 2 are the residences located on Harbour Terrace approximately 500m from the Area 2 site boundary.

Area 2 site is located on undeveloped, reclaimed land which has recently had bulk earthworks carried out by Gladstone Port Corporation (GPC) to achieve a site that drains freely and is suitable to handle the vehicles travelling on it. Area 2 will be further developed by QGC including carrying out:

Minor Earthworks (Cut and Fill)

Installation of temporary buildings, fences, roads, utilities and services

Machinery operation and lighting

Construction related truck movements.

Page 10: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 10 of 82 Revision 00A

Photo 1 Auckland Point Area 2

2.4. Filling and Excavation Works

Upon completion of rough grading, QGC, using experienced contractors, will commence construction of the surfacing layers. Typically 100mm of crushed gravel will be layered and compacted across the work area, graded in accordance with the detailed design drawings, except where road cross sections require additional materials. During earthworks, temporary drainage shall be established to manage construction storm water. This shall be routed through temporary ditches, using a combination of check dams, silt fencing, sedimentation control ponds and/or treatment to limit suspended solids and particulate matter being discharged.

The finished surface will have an asphaltic surface treatment (chip seal) for dust control. This will be maintained throughout the duration of the operations of the facility as ongoing measures to tackle fugitive dust control. In addition, a water truck will be available to provide moisture to any dry areas between maintenance periods. The roads will also be regularly kept clean of any standing dust and debris which can become airborne.

Asphalt paving will be required for the road connecting Area 2 to Tug Berth Access Road. Paving will also be required for the road located on the west boundary of Area 2. These roads will handle large volumes of traffic.

Page 11: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 11 of 82 Revision 00A

Paved areas and roads will be designed to accommodate maximum allowable vehicle loading.

2.5. Area 2 Drainage Management

Bulk earthworks at Auckland Point have be carried out by GPC taking into account the overall drainage requirements of the site to achieve a site that drains freely. The site drainage at Area 2 will be designed to channel and control run-off internal to the work areas, which in turn will limit the sedimentation released to the overall area drainage scheme. In addition these areas will be sealed and maintained which will also limit contamination to the surface water.

2.6. Overview of Auckland Point Area 2 Facility Layout

This area is required is required to facilitate the movement of personnel, freight and equipment which is being transported to and from Curtis Island. The proposed layout for Area 2 is as shown on the drawings.

Final surfacing and hard standing, incorporating requirements for site drainage of the area (tied into the drainage outside of the area).

Provide for the movement of personnel who live within a radius of 60km from Gladstone and will be required to work on Curtis Island.

Provide approximately 900 car and 60 motorcycle parking spaces.

The following temporary facilities will be provided to support construction operations:

- Security/Visitor office

- Management office

- Security huts

- Ferry operation office

- Toilet unit

- Training and induction facility

- Turnstile unit

- Smoking area

A five (5) space car parking area will be provided next to the Security / Visitors Office.

Footpaths will be provided to separate pedestrian traffic from vehicular traffic.

A passenger walkway at grade level crossing McFarlan Drive will be used to mobilise workers from Area 2 to ferries.

The road along the western boundary of the parking area will provide a 16 vehicle lane for trucks awaiting loading onto the self-propelled Ro-Ro vessels.

A road along the eastern boundary of the parking area will provide a 14 vehicle lane for buses waiting to pick up and drop off passengers from the ferry landing.

Page 12: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 12 of 82 Revision 00A

A 7m wide access road (Access Road 1) will be constructed along the south boundary of the site which will connect the existing Tug Berth Access Road to Area 2 and McFarlan Drive.

2.7. Roads

Access Road 1 (approximately 670m in length) will be at least 10m wide and will be designed to handle heavy construction equipment traffic. This road will be a paved two way road and will be used as the main access to Area 2 and the Barney Point coal facility. The sub base, base and pavement for the construction of Access Road 1 (RD1), will be designed to handle heavy construction equipment traffic. Refer to the drawings included in the drawings included in Attachment A.

All other internal roads will be 6m wide and will have to be designed for heavy vehicle movement. Internal roads will not have high volumes of traffic and therefore an asphaltic surface treatment (chip seal) can be used.

2.8. Traffic and Car Parking

Internal traffic movement between and within Areas 1 and 2 is managed by a Traffic Management Plan and will comply with the control measures outlined in Section 6.16. An explanation of the proposed traffic management strategy is set out below.

All vehicles for the Construction Services Facility will enter to the south of the car park and exit at the stop sign located to the north. The direction of travel is one-way, travelling in clockwise direction. Large vehicles will enter the site via the entrance security hut in the south eastern corner and be marshalled through the facility, exiting via the exit security gate and stop sign opposite to the north of Area 1. Trucks direct to vessels will then travel from the truck marshalling area in Area 1 to the loading dock via RD-1.

The internal traffic movement has been designed for adequate and safe traffic movement. RD-1 will be used as the main access to Area 2. Therefore, all personnel parking in Area 2 and trailers going from Area 1 to the self-propelled RO-RO vessels and back will transit using this road. Trailers from Area 1 will line up along the road bordering the western boundary of Area 2 where wheels and undercarriage will be inspected for pests, and where required be washed. This road will be used exclusively by trucks and trailers going to and coming back from Curtis Island. A bypass road will be provided around the truck wash unit. This bypass will be used by vehicles not boarding the self-propelled RO-RO vessels and that do not need to be washed.

Wheel washing will be performed as an efficient means to comply with the requirements of Section 46 of the Land Protection (Pest and Stock Route Management) Act 2002 in the transfer of pests from the mainland to Curtis Island.

Page 13: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 13 of 82 Revision 00A

It is not expected to have oversized truck movements of any significant number. The road width for RD-1 is 10m to allow for safe two-way traffic movement, and the possibility of any large vehicle movements. Large vehicle movements will be coordinated with other users of Port Central, and timings of movements planned during times of the day, or on days, when other users’ requirements are at their lowest.

Signage at the entrance to Port Central area and on RD-1, will warn other users of this access way’s potential of high traffic volumes during peak times, which is when project employees will be starting and finishing shifts. The signage will clearly communicate the days and times when this can be anticipated, and a contact name and phone number to which concerns can be addressed. Flag men will be assigned to manage and facilitate traffic flow during these peak times, working with other users of the Port Central area, as required.

Daily transportation of personnel is planned during the construction phase of the QCLNG plant, to and from Auckland Point and Curtis Island. The Auckland Point marine facility will provide for the movement of 800 personnel who live within a radius of 60 kilometres of Auckland Point, to and from Curtis Island each work day.

In general, the project will receive freight between 8:00am and 3:00pm. This is intended to work self-propelled RO-RO vessel movements separately from passenger ferry movements, the result of which is de-coupling the peak private vehicle and truck movements through the overall Port Central area, and the surrounding road infrastructure.

Coal terminal access will be relocated from the existing quayside location and another gate will be provided by GPC to a less congested location at the South-East corner of the Area 2 perimeter. This alternative will allow the Coal Terminal traffic and other users of this area, access to move directly along RD-1, avoiding the interactions with the wharf, marshalling or ferry loading activities.

Page 14: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 14 of 82 Revision 00A

3. Legislative Framework A list of applicable legislation is identified in this section. A range of guidelines and associated standards relevant to construction works and environmental protection are also listed below.

3.1. National Strategies

The following national strategies provide high-level guidance and consideration for the design, construction and operation of the Auckland Point Logistics Centre and have been considered in the preparation of this CECP.

National Strategy for Ecologically Sustainable Development 1992

National Strategy for the Conservation of Australia’s Biological Diversity 1996

National Greenhouse Strategy 1998

National Environmental Protection (Ambient Air Quality) Measure 1998

3.2. Commonwealth Legislation

Commonwealth Legislation that is relevant to the Auckland Point Project site includes:

Environmental Protection and Biodiversity Conservation Act 1999

Native Title Act 1993

Australian Heritage Council Act 2003

Aboriginal and Torres Strait Island Heritage Protection Act 1984

3.3. Queensland Legislation

State Legislation that is relevant to the Auckland Point Project site includes:

Environmental Protection Act 1994

Environmental Protection Regulation 2008

Environmental Protection (Waste Management) Policy 2000

Environmental Protection (Waste Management) Regulation 2000

Environmental Protection (Water) Policy 2009

Environmental Protection (Air) Policy 2008

Environmental Protection (Noise) Policy 2008

Land Protection (Pest and Stock Route Management) Act 2002

Plant Protection Act 1989

Plant Protection Regulation 2002

Vegetation Management Act 2009

Nature Conservation Act 1992

Nature Conservation (Wildlife) Regulation 1994

Page 15: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 15 of 82 Revision 00A

Aboriginal Cultural Heritage Act 2003

Water Act 2000

Fisheries Act 1994

Dangerous Goods Safety Management Act 2001

Dangerous Goods Safety Management Regulations 2001

Coastal Protection and Management Act 1995

3.4. Guidelines and Standards

Table 2 below provides a list of relevant standards and guidelines that are applicable to the construction activities at Auckland Point Area 2.

Table 2 Performance Guidelines and Standards

Aspect Performance Guidelines/Standards

Risk AS/NZS ISO 31000:2009 Risk Management – Principles and Guidelines Water National Water Quality Management Strategy – Australian and New Zealand

Guidelines for Fresh and Marine Water Quality, ANZECC/ARMCANZ, 2000.

National Water Quality Management Strategy – Australian Guidelines for Water Quality Monitoring and Reporting, ANZECC/ARMCANZ, 2000

Monitoring and Sampling Manual Version 1 2009 For sampling in compliance with the Environmental Protection (Water) Policy 2009

National Water Quality Management Strategy – Guidelines for Groundwater Protection in Australia, ANZECC/ARMCANZ, 1995.

National Water Quality Management Strategy – Australian Guidelines for Sewerage Systems – Effluent Management, ANZECC/ARMCANZ, 1997.

Department of Environment and Resource Management (2009) Queensland Water Quality Guidelines, Version 3. ISBN 978-0-9806986-0-2

Draft State Planning Policy Guidelines for Healthy Waters 2009, DERM.

Standard Methods of the Examination of Water and Wastewater – American Public Health Association (APHA)/Australian Waste Water Association (AWWA)

AS 2031 Selection of Containers and Preservation of Water Samples for Chemical and Microbiological Analysis

Waste AS 1216 Classification, Hazard identification and Information Systems for Dangerous Goods

AS 1678 Emergency Procedure Guides – Transport AS 1940 Storage and Handling of Flammable and Combustible Liquids AS 3780 The Storage and Handling of Corrosive Substances AS 2809 Road Tank Vehicles for Dangerous Goods AS 2931 Selection and Use of Emergency Procedure Guides for Transport of

Dangerous Goods Soils National Environmental Protection (Assessment of Site Contamination) Measure,

1999 NEPC. “Draft Guidelines for the Assessment and Management of Contaminated Land in

Queensland” (Department of Environment 1998)

Page 16: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 16 of 82 Revision 00A

Aspect Performance Guidelines/Standards

Soil Erosion and Sediment Control, Engineers Guidelines for Queensland, Institute of Engineers QLD, 1996.

Air AS 3580 Methods of Sampling and Analysis of Ambient Air

Queensland and EPA Air Quality Sampling Manual November 1997

Methods and Guidance for the Modelling and Assessment of Air Pollutants in NSW – DRAFT February 2005 (NSW EPA)

Approved Methods and Guidance for the Modelling and Assessment of Air Pollutants in NSW –August 2001 (NSW EPA)

National Road Transport Commission/ NEPC - Stationary Exhaust Noise Test Procedures for In- Service Motor Vehicles, April 2000.

Noise Queensland EPA Noise Management Manual Third Edition March 2000

AS 1055: 1997 Parts 1 & 2 Acoustics – Description and Measurement of Environmental Noise

AS 1259.2 – 1990 Acoustics – Measurement of airborne noise emitted by earth-moving machinery and agricultural tractors – Stationary test condition Part 1: Determination of compliance with limits for exterior noise

AS 2436: 1981 Guide to Noise Control on Construction, Maintenance and Demolition Sites

AS 2670.1: 2001 Evaluation of human exposure to whole-body vibration Part 1: General Requirements

Vehicle Standard (Australian Design Rule 28/01 – External Noise of Motor Vehicles) 2006.

British Standard 7385: Part 1-1990 Evaluation and Measurement for Vibration in Buildings - Guide for measurement of vibrations and evaluation of their effects on buildings

Australian Dangerous Goods Code: Transport of Dangerous Goods

Dangerous Goods AS 1216 Classification, Hazard Identification and Information Systems for Dangerous Goods

AS 1678 Emergency Procedure Guides – Transport

AS 1940 Storage and Handling of Flammable and Combustible Liquids

AS 2508 Safe Storage and Handling Information Cards for Hazardous Materials

AS 2809 Road Tank Vehicles for Dangerous Goods

AS 3780 – 1994 The Storage and Handling of Corrosive Substances

AS 2931 Selection and Use of Emergency Procedure Guides for Transport of Dangerous Goods.

3.5. Licenses and Permits

The Contractor will comply with the relevant licences, permits, registrations and approvals obtained by QGC that are applicable to the construction work.

Page 17: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 17 of 82 Revision 00A

4. Environmental Risk Assessment Process The design and construction and associated risk management processes shall be in accordance with the relevant standards including but not limited to: Workplace Health and Safety Advisory Standards and Codes of Practice; and Australian Standards, except where the risk management processes demonstrate that higher standards of risk control are required to adequately manage those hazards inherent to the construction activities, in which case these should be incorporated into the designs.

The Contractor has used a risk management process to put in place appropriate environmental control measures addressing the design and construction of the Works and which takes account of the relative construction activities, standards and reasonably foreseeable misuse, on a basis of observing the “Hierarchy of Controls” principles e.g.:

Elimination of the hazard

Substitution with a less hazardous material, process or equipment

Designing the equipment / process to mitigate the risk

Separation/isolation of the hazard to reduce the requirement for administrative/personal protective equipment controls.

The full Risk Register will be maintained electronically in the site files and will be updated throughout the duration of the construction activities or when works change. An initial Risk Register has been prepared for construction works at Auckland Point Area 2 and this is provided as Attachment B. Additional risks will be assessed and control measures implemented as they are identified during further development of Work Method Statements (WMS).

Page 18: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 18 of 82 Revision 00A

5. Environmental Management Process 5.1. Environmental Policy

QGC and its contractors are committed to the protection and enhancement of the environment and to the communities in which they operate. Construction activities carried out at Auckland Point will conform to the QGC Environmental Policy as presented in Attachment C. In order to achieve this, Bechtel’s activities will be executed according to the following:

Compliance with current environmental and other legal requirements.

Where possible, restriction of disturbance of fauna, flora and soil on projects.

Prevention and reduction of waste, soil, air, water pollution and disturbance of the surroundings.

Correct handling of environmental-threatening products and limitations of their use, where reasonably practicable.

Rational use of water, energy, fuels and materials.

Implementation of measures to prevent environmental incidents and emergency situations.

Encouragement of environmental awareness of all employees and subcontractors by education, training and written work instructions or procedures.

5.2. Gladstone Port Corporation Environmental Policy QGC and its contractors will seek to achieve the principles of the GPC Environmental Policy including:

Continual improvement in environmental performance by highlighting any environmental risks, incidents, complaints or changes in legislation.

Ensuring that action is taken to prevent or control any environmental harm that may be caused.

Operating in a manner that allows for sustainable development and minimised environmental harm to the port and surrounding areas.

5.3. Roles and Responsibilities

QGC will require that its contractors be responsible for implementing and adhering to the obligations in this CECP, the Environmental Policy as stated above and the management measures as provided in Section 5.

Each member of the project team is responsible for conforming to applicable Australian and Queensland laws and regulations and for conducting work in accordance with permit requirements and the CECP. Specific responsibilities of project entities and personnel are addressed in the following sections. Furthermore, all personnel are responsible for the

Page 19: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 19 of 82 Revision 00A

environmental performance of their activities and for complying with the general environmental duty as set out in Section 319(1) of the Environmental Protection Act 1994 which states:

“A person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to minimise the harm.”

The following table (Table 3) provides a summary of the likely responsibilities and accountabilities of various parties who will have active roles in the implementation of the CECP.

Table 3 Summary of Roles and Responsibilities

Role Responsibilities

QGC Project proponent with overall responsibility for project delivery and commitments arising under the CECP.

Contractor Site Manager Environmental management performance.

Implement company environmental policies and procedures on site during the construction of the works through allocated field personnel.

Provide resources to carry out their duties compliant with the CECP.

Implement corrective actions or modify practices in order to address any complaints received.

Completion of the contract works.

Contractor HSSE Manager

Maintain a master copy of the CECP containing a record of the completion of planned actions, monitoring records and reports that are made available during audits.

Implement CECP requirements on site.

Advise Contractor Site Manager with regards to environmental matters.

Provide copies of the CECP to the relevant project staff having responsibilities defined in the CECP.

Conduct site specific induction training for all personnel prior to commencement of work.

Keep conditions of licenses and permits up to date and readily available on site.

Undertake regular monitoring in relation to environmental management issues and verify that monitoring results are made available to the community consultative committees.

Notify the relevant State agency of any environmental incidents including any remedial action taken.

Implement adequate and accurate identification and reporting of any non-conformances and any other environmental issues that

Page 20: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 20 of 82 Revision 00A

Role Responsibilities

may arise during construction.

Record and respond to complaints received.

Environmental Inspectors (multiple)

• Perform duties such as baseline surveys, assisting preparation of work plans and field compliance activities.

• Raise awareness of potential environmental impacts to Project personnel such that mitigation measures and actions may be instituted to maintain compliance with Project requirements.

• Review construction work plans and activities to advise and determine that proper and required environmental controls are incorporated.

• Notify management of any circumstances that warrant agency notification or management action in support of effective environmental compliance.

• Monitor all Field Engineering activities are planned and conducted in accordance with applicable environmental regulations and site-specific requirements.

• When appropriate, participate in Government agency and authority meetings to review environmental requirements and compliance.

• Conduct regular field inspections of construction activities for compliance with existing permits, approvals and all applicable environmental regulations.

• Providing guidance to Construction Superintendents for resolution of environmental compliance issues.

Conducting Environmental Training for Construction personnel and preparing training materials and guideline sheets to facilitate compliance and communication.

Contractor Superintendent

Accountable to the Contractor Site Manager for execution of the Works in accordance with this CECP.

Implement the work is undertaken in accordance with the CECP, specifications and drawings.

Manage subcontractors perform work in accordance with the CECP.

5.4. Reporting Requirements

QGC will require its contractor to establish formal reporting requirements as per the HSSE Incident Recording, Reporting and Investigation Procedure. The Contractor will report environmental incidents to the administering authority or relevant agency as required by law and shall provide QGC with any reports made to the respective agency.

Page 21: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 21 of 82 Revision 00A

5.5. Environmental Procedures and Forms

Environmental procedures and forms have been prepared for implementation across the construction activities to address risk and compliance management systems. The management tools that are applicable include:

Procedures – provide instruction for specific environmental tasks for consistency in approach and quality of results. Environmental procedures are developed for managing issues including water monitoring, contamination testing, noise monitoring and dust monitoring, and are linked to the Work Method Statements.

Page 22: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 22 of 82 Revision 00A

6. Site Specific Environmental Aspects The environmental aspects addressed in this CECP include:

General Construction

Construction Noise and Vibration

Soil Erosion and Sediment Control

Management of Acid Sulphate Soils

Waste Management

Hazardous Substances Management

Contaminated Sites

Air Quality

Greenhouse Gas

Surface Water Quality

Weed and Pest Management

Red Imported Fire Ant

Mosquito and Biting Midge

Visual Amenity

Lighting

Traffic and Transport

Indigenous Cultural Heritage

Non-indigenous Cultural Heritage

Stakeholder Management

Management measures for Acid Sulphate Soils (ASS) have been identified; however ASS is not anticipated to be encountered at this location. The materials have been inspected and tested and are documented to be clean and free from ASS contamination.

The following aspects have not been further addressed in this CECP as these are considered not applicable to Auckland Point Area 2 or will not be impacted by construction activities.

Terrestrial Ecology

Groundwater Quality management

Page 23: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 23 of 82 Revision 00A

6.1. General Construction

Aspect

General construction environmental management.

Objectives

1. Manage construction and worksite to avoid environmental harm and potential environmental harm in accordance with the Environmental Protection Act 1994.

2. Manage construction and worksite in accordance with Condition of Approval for the Auckland Point Operational Works Land Permit Final Conditions (DA 2010/03) and the CECP.

3. Avoid or limit construction impacts to the local community.

Potential Impacts on Environmental Values

Non-compliance with Conditions of Approval may lead to environmental harm occurring or community complaints. This may lead to fines, prosecution or requirements to remediate. The Company’s reputation may also be impacted.

Control Strategy

1. Monitor compliance with the Conditions of Approval by undertaking regular audits.

2. Prepare and implement a community engagement strategy for the construction phase. This is to incorporate an ongoing notification system to keep stakeholders informed about the construction and any impacts they may experience. The strategy is also to incorporate a complaints handling system.

Actions

1. The site will be maintained in a state that is satisfactory to Gladstone Ports Corporation.

2. “For Construction” Drawings for the works shall be provided to GPC for review and compliance at least 10 working days prior to the commencement of the works.

3. Construction worksites are to be designed to incorporate environmental management measures such as stormwater retention and treatment, noise attenuation and dust minimisation. Construction worksites are to be designed to avoid unnecessary impacts to local flora and fauna.

4. Necessary services connections will be made to the site within access corridors that are to be approved by GPC. All services shall be appropriately metered to allow the respective service providers to identify the appropriate users for the levy of charges.

5. Construction vehicle access is to occur on a sealed or stabilised roadway to avoid dust generation.

6. Access to properties adjacent to Auckland Point site access roads are to be maintained in good condition at all times.

7. Construction activities are to be undertaken in accordance with the Job Hazard Analysis (JHA) which is to incorporate environmental management measures for each construction

Page 24: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 24 of 82 Revision 00A

activity.

Performance Indicators

1. Enforcement action undertaken by DERM or Council.

2. Construction activities are carried out in a manner that does not contravene the Construction Environmental Management Plan and subsidiary environmental management plans.

3. Site inspections have been completed at the required frequency by appropriate personnel and records of inspection maintained.

4. Any actions raised during site inspections are to be rectified as soon as reasonably possible.

5. Corrective actions were taken to address non-compliances.

6. Monitoring has been carried out in accordance with the Conditions of Approval and as required under the CECP. The results of monitoring required by Conditions of Approval are recorded and reported to the administering authority when requested.

7. Community complaints handled in accordance with the system adopted for the QCLNG Project, complaints are promptly attended to and closed out.

Monitoring

1. Regular weekly inspections of the construction worksite by a competent person to determine compliance with the Conditions of Approval and the CECP.

Reporting

1. Notification of Emergencies will be in accordance with the conditions of approval.

2. Exception reporting will be in accordance with the conditions of approval.

3. Environmental checklist completed and submitted to the Contractor HSSE Manager for review. Defects identified during these inspections are added to the sites Corrective Action Register.

4. Any environmental incidents or complaints are reported within 24 hours of receipt / reporting to the Contractor HSSE manager, GPC and other agencies as appropriate.

Corrective Action

1. Any actions raised during site inspections are to be rectified as soon as possible. The construction worksite layouts are to be reviewed by an environmental professional before work commences.

Training

1. Site Specific Induction

2. Personnel are to be familiar with the GPC Environmental Policy which will be available on site at all times.

Page 25: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 25 of 82 Revision 00A

6.2. Construction Noise and Vibration

Aspect

Potential exists for construction noise and vibration to impact on nearby residents, project personnel and the surrounding environment and may cause structural problems in adjacent buildings.

Objectives

To carry out construction in accordance with the Conditions of Approval and in a manner that limits the impact of noise and vibration on surrounding residents and industry.

The key objectives are:

1. To prevent noise and vibration nuisance at nearby residences from construction activities.

2. Maintain a reasonable acoustic environment for living, in particular for sleeping, and use of properties along the corridor of construction influence during construction works.

3. Significant heritage buildings and other structures are protected from the effects of vibration from construction activities.

Potential Impacts on Environmental Values

Noise impacts to residents may cause environmental nuisance as described in the Environmental Protection Act 1994.

Control Strategy

Implement measures that limit noise and vibration levels to achieve compliance with the Environmental Protection Regulation 2008 and Environmental Protection (Noise) Policy 2008.

Where practicable works will be undertaken in daylight hours not excluding the need for night works for special activities where approved.

Noisy activities will be scheduled, where possible, between 7.00am and 6.00pm.

Approved transport routes suitable for construction traffic will be used.

Equipment used on site will be well maintained to limit noise and vibration impact.

The speed of heavy vehicle traffic on the haul road will continue to be limited

Actions

1. Advise personnel at induction and at subsequent tool box meetings of requirements in regard to limiting use of audible signals, unnecessary revving of engines, unnecessary engine braking and generally exercising due courtesy to local residents and fellow workers.

2. Construction work shall not commence prior to 6.00am and shall be restricted to 6.00pm, Monday to Saturday inclusive. No works shall be carried out outside these hours without prior written approval.

3. Adjacent landholders and neighbouring communities will be advised in writing of any predicted atypical noise events at least 7 days prior.

4. Noise minimising construction methods (e.g. eliminating the need for reversing on site) will

Page 26: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 26 of 82 Revision 00A

be implemented to limit noise generation sources (e.g. as reversing alarms) in noise sensitive areas.

5. Approved transport routes suitable for construction traffic (e.g. Port Access Road, Hanson Road) will be used.

6. Where possible, select transport routes (e.g. Port Road Access, Hanson Road) and times to limit noise impacts on residents.

7. Engines will be turned off when not in use.

8. Limit the height from which the material is dropped into the truck when loading rock and other materials into trucks.

9. Locate generators, compressors and other noise generating equipment away from offices and work areas.

10. Equipment on site will be well maintained so as to limit noise and vibration impact.

11. Generators to be fitted with silencers prior to use.

12. Provide appropriate hearing protection to affected workers if noise levels exceed the 85 dB(A) limit for protection of worker’s health.

13. Maintain haul routes in a smooth condition to limit truck rattling.

14. Maintain awareness of construction workers in relation to minimising noise impacts from equipment operation.

Performance Indicators

1. Noise and vibration from the site activities must not cause an environmental nuisance at any sensitive place.

2. Noise or vibration complaints from nearby residents.

3. Noise and vibration levels meet limits specified in Environmental Protection Regulation 2008 and Environmental Protection (Noise) Policy 2008.

4. Monitor and report regularly on the performance of construction works with regards environmental guidelines for noise and vibration.

Monitoring

1. When requested by the administering authority, noise monitoring will be undertaken within a reasonable and practicable timeframe to investigate any complaint related to noise.

2. The method of measurement and reporting of noise levels must comply with the latest edition of the DERM Noise Measurement Manual.

3. Operators shall undertake daily pre-start checks to verify equipment is well maintained.

4. Records of plant maintenance will be maintained on site.

5. Complaints relating to noise and vibration will be recorded on the Complaints Register and complaints will be investigated.

Page 27: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 27 of 82 Revision 00A

Reporting

1. Non- Compliance and Incident Reports will be prepared by the Contractor HSSE Manager.

2. Records of all complaints received and corrective actions undertaken to prevent reoccurrence.

3. Records of noise and vibration monitoring shall be retained for the duration of the construction activities and five (5) years after completion of works.

Corrective Action

1. Identify the source of the noise or vibration and cease that activity until the source has been altered or noise abatement measures instigated.

2. Construction work shall not commence prior to 6.00am (as per Environmental Protection (Noise) Policy 1997) and shall be restricted to daylight hours, Monday to Saturday inclusive. No works shall be carried out outside these hours without written approval from GPC.

3. Where possible, schedule operations so that noisy equipment is used separately, rather than concurrently.

4. Complaints shall be addressed in consultation with the Contractor HSSE Manager and noise monitoring conducted as required.

5. Direct that work practices be modified as necessary to reduce the duration and/or level of noise or vibration.

6. If vibration cannot be reduced and is likely to cause building damage or discomfort to sensitive receptors, review current plan and develop a more comprehensive management plan that may include building condition surveys.

Training

1. Site Specific Induction

2. Environmental Awareness Training Package – Noise and Vibration Module.

3. Toolbox Talk – Noise Monitoring

4. Toolbox Talk – Vibration Monitoring

5. Toolbox Talk – Complaint Management

6.3. Soil Erosion and Sediment Control

Aspect

Erosion and sedimentation of stockpiled material, cleared areas and waterways.

Objectives

To provide effective erosion and sediment control measures to mitigate the potential effects of

Page 28: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 28 of 82 Revision 00A

construction on local waterways, land use and the general environment.

The key objectives are:

1. To prevent sedimentation leaving the construction site.

2. To prevent the erosion of the construction area.

3. To prevent sediment-laden water entering stormwater or nearby waterways.

Potential Impacts on Environmental Values

Sediment laden run-off may enter nearby receiving waters during construction.

Natural waterways and flow paths may be reduced due to the construction of the plant.

Control Strategy

1. A Sediment and Erosion Control Plan is to be developed within 30 days of commencement of construction.

2. Stage excavation activities in a manner to limit areas exposed and therefore vulnerable to erosion and sedimentation.

3. Erosion and sediment control structures (e.g. sediment fencing around exposed areas and material stockpiles, shake down grids / rubble at unsealed egress points) will be installed to limit erosion of disturbed areas and prevent the contamination of waterways.

4. Uncontaminated stormwater run-off will be diverted around areas disturbed by construction activities or where contaminants or wastes are stored or handled that may contaminate stormwater.

5. Measures for the management of stormwater and drainage from construction worksites and stockpile placement sites.

6. Erosion and sediment control structures will be regularly inspected and maintained, particularly prior to and following heavy rainfall events.

7. Planning the stages of various works to limit erosion.

Actions

1. A Stormwater Management Plan will be prepared and implemented on site.

2. Sediment traps and other erosion-control measures will be installed along the boundaries of the construction areas to limit the movement of soil into watercourses during high rainfall.

3. Inspect, maintain and / or replace erosion and sediment control devices where effectiveness is impeded or not achieved, especially after rain.

4. Sandbag or rock check dams will be installed in the diversion channels that direct stormwater towards the stormwater collection points.

5. Erosion and sediment control devices such as sediment fences, rock check dams and shallow diversion drains shall be installed prior to site disturbance where required.

6. On-site drainage shall be constructed to guarantee that run-off is directed to sediment control devices

7. Surface runoff shall not be directed through exposed areas and stockpiled material shall be

Page 29: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 29 of 82 Revision 00A

stored or bunded away from overland flow paths.

8. Cut-off drains will be installed to direct surface water flows to existing drainage lines, especially where required around stockpiles.

9. Minimising as far as practicable the area of land which is bare of vegetation at any one time and commencing re-vegetation works as soon as possible after clearing an area.

10. Regular maintenance and inspection of erosion controls, especially after rain.

11. If required, erosion prone areas will be barricaded to restrict human and vehicular access.

12. If required on erosion prone slopes, cross-slope windrows will be installed to reduce surface water erosion.

13. The construction of temporary retention systems within each respective sub-catchment.

14. Sediment control devices that are required to be removed to allow construction access will be reinstated at the completion of work each day.

15. Where required, run-off water from external catchments and undisturbed areas will be directed around disturbed areas using a system of diversion and cut-off drains.

Performance Indicators

1. Sediment leaves the construction site boundaries and no visible discolouration of receiving waters.

2. Stormwater management devices installed, maintained and working properly.

3. Sediment is tracked onto external or internal sealed roads.

4. Visible evidence of erosion as a result of construction activities.

5. Sediment-laden water enters stormwater system or nearby waterways.

6. Adverse impacts on downstream watercourses.

7. Any erosion or sedimentation issues are rectified within 24 hours of reporting.

8. Appropriate water quality triggers for discharges offsite will be based on ANZECC 2000 Guidelines, Port Curtis Integrated Monitoring Program (PCIMP) data (zone 1) and the Queensland Water Quality Guidelines.

Monitoring

1. Inspect / monitor erosion and sediment control devices to verify effectiveness is achieved and maintain. Report made and filed.

2. Undertake visual inspections for sediment plumes and verify that appropriate erosion control measures are in place to suit the construction activities taking place at the time.

3. All incidents and complaints shall be logged in the Environmental Incidents and Complaints Register.

4. All sediment and erosion controls shall be cleaned out at regular intervals such that at least 60% capacity of the control is maintained during construction.

Page 30: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 30 of 82 Revision 00A

5. Monitoring of stormwater discharges will be done by a qualified person in accordance with the latest edition of the DERM Water Quality Sampling Manual.

Reporting

1. Environmental checklist completed and submitted to the Contractor HSSE Manager for review. Defects identified during these inspections are added to the sites Corrective Action Register.

2. Environmental incidents or complaints are reported within 24 hours of receipt / reporting to the Contractor HSSE Manager, GPC or other agency as appropriate.

Corrective Action

1. Should the water quality or water flow in nearby receiving waters be altered due to construction works corrective and preventative actions are to be implemented immediately such as review of sediment and erosion controls and maintenance of control devices.

2. Any loss of sediment laden water from site will require corrective and preventative actions to be undertaken.

3. Ineffective erosion and sediment controls are replaced with alternatives within 24 hours of reporting.

4. Damaged erosion and sediment controls are fixed / replaced as soon as possible within 24 hours of reporting.

5. Remove deposited material from roadways.

6. Review corrective action implementation for effectiveness.

Training

1. Site Specific Induction

2. Toolbox Talk – Erosion and Sedimentation Control

6.4. Management of ASS

Aspect

During construction Actual Acid Sulphate Soils (AASS) and Potential Acid Sulphate Soils (PASS) are not expected to be encountered on site. The materials have been inspected and tested and are documented to be clean and free from ASS contamination. The management ASS and PASS has been detailed here in the event that ASS/PASS is encountered.

Objectives

Manage the environmental or public health impacts associated with working in actual or potential acid sulphate soils encountered during earthworks.

The key objectives are:

Acid sulphate soils are not disturbed or excavated unnecessarily.

Page 31: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 31 of 82 Revision 00A

No PASS fill material will be incorporated into the fill until monitoring tests indicate that actionable levels of oxidisable sulphur are below Queensland Acid Sulphate Soils Investigation Team (QASSIT) guidelines.

No physical evidence in the works of acid sulphate soils on site such as yellow efflorescence on soil surface, iron staining of soils or water, sulphurous odour or low water pH.

Control Strategy

Reasonable and practicable control measures will be implemented to limit disturbance and manage ASS where required.

Actions

1. Where required, PASS disturbance shall be limited.

2. Construction works will comply with management measures outlined in the QCLNG Acid Sulphate Soil Management Plan.

3. PASS shall be neutralised in a timely manner following dry excavation.

4. Measures shall be implemented to contain and treat leachate.

5. Incorporate knowledge of location of PASS/AASS into earthworks program.

6. Neutralisation of PASS using incorporation and mixing of agricultural lime at rates determined from testing of materials at time of placement.

7. Material excavated from the PASS/ASS areas shall be tested in accordance with the QASSIT Guidelines to confirm the presence of ASS. Material deemed to contain PASS shall be neutralised with lime and disposed of as per the DERM approved plan. Where approved, PASS will be reburied within 12 hours below Mean Low Water Springs (MLWS).

8. The Contractor HSSE Manager shall be notified immediately suspected ASS are encountered.

9. Management of ASS is to be confirmed by the Contractor HSSE Manager following completion of acid sulphate soil testing.

10. Personnel will be advised at induction of ways to identify ASS.

11. Soils validated as neutral may be used as reclamation fill on site.

12. Excavated PASS or AASS shall be spread in layers of 300 mm loose and each layer shall be limited at the calculated rate. Soils will require drying and must be worked several times to guarantee thorough mixing of lime. Mixing shall be performed by disc plough, rotary hoe or equivalent.

13. Limit treatment of ASS during foreseeable or extended periods of wet weather.

14. Net acidity levels should remain constant or negative if treatment is undertaken of PASS.

15. pH must remain within QASSIT guidelines for existing PASS (6.5-9.0).

16. Runoff pH should remain within QASSIT guidelines (6.5-9.0).

Page 32: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 32 of 82 Revision 00A

Performance Indicators

1. Material excavated from the PASS/ASS areas shall be tested in accordance with the QASSIT Guidelines to confirm presence / absence of ASS.

2. Any reburial of PASS must occur within 12 hours of exposure and below MLWS.

3. Results shall be reviewed upon receipt of the results to detect any unforeseen changes to PASS/Net Neutralising PASS testing or treatment areas.

4. Validation testing shall be undertaken to confirm the effectiveness of lime treatment. Treatment shall be deemed successful where pH is in range 6.5 – 8.5 and Total Potential Acidity is zero. Treatment that has been unsuccessful (i.e. outside of above mentioned ranges) shall be re-limed and re-mixed with acid generating potential retested. Records of validation testing shall be maintained on site.

5. Records of monitoring results shall be maintained on site and available upon request.

Monitoring

1. Monitoring for ASS will occur in areas of ASS disturbance as specified in the ASS Management Plan.

2. Material excavated from PASS/ASS areas shall be tested in accordance with the QASSIT Guidelines to confirm presence / absence of ASS.

3. Any reburial of PASS must occur within 12 hours of exposure and below MLWS.

4. Results shall be reviewed upon receipt of the results to detect any unforseen changes to PASS/Net Neutralising PASS testing or treatment areas.

5. Validation sampling will be conducted following remediation or covering of contaminated soil and sign-off will be obtained from a qualified/certified auditor.

6. Records of monitoring results shall be maintained on site and available upon request.

Reporting

1. Field screening and sampling results must be updated as taken and reviewed, available in a suitable format for inspections by the DERM.

Corrective Action

1. If acid sulphate soil levels exceed QASSIT levels, re-treat with Aglime and re-test.

2. If Net Neutralising PASS is unexpectedly located, lab test and lime as advised.

Training

1. Site Specific Induction

2. Environmental Awareness Training – Acid Sulphate Soils Module

3. Toolbox Talk – Acid Sulphate Soil Impacts

Page 33: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 33 of 82 Revision 00A

6.5. Waste Management

Aspect

A potential exists for environmental harm from incorrect waste management as follows:

Solid and liquid construction waste and organic wastes may detract from the amenity of the area and have the potential to contaminate land and waterways.

Many of the waste products generated in the site workshop or with maintenance activities are classified as Regulated Waste under the Environmental Protection Act 1994 and must be disposed of in the appropriate manner.

Objectives

1. To implement waste management principles (Reduce, Re-use, Recycle) and effective and sustainable disposal strategies.

2. Maintain the aesthetic appeal of the area and the habitat of the surrounding environment by proper handling and disposal of wastes.

3. Prevent mixing of waste streams.

4. Identify and correctly dispose of those waste products identified as ‘Regulated Wastes’ under Schedule 7 of the Environmental Protection Regulation 2008.

5. Implement Waste Tracking Procedures for those waste products identified as ‘Trackable Waste’ under Schedule 1 of the Environmental Protection (Waste Management) Regulation 2000.

Potential Impacts on Environmental Values

Incorrectly handled wastes could cause environmental harm and contamination. Waste disposal increases the burden on landfill. Incorrect waste disposal can be an unsustainable practice.

Control Strategy

1. Manage waste in accordance with the Conditions of Approval, the Waste Management plan for the site and relevant legislation.

2. Educate the workforce to familiarise them with waste types and management practices.

Actions

1. A Waste Management Plan for the activities on site will be prepared, in consultation with the administering authority and then implemented.

2. Procure the correct quantities for materials for construction works to limit waste and excess materials.

3. Waste generated in the carrying out of construction activities will be stored, handled and transferred in a proper and efficient manner.

4. A waste-minimisation program will assess opportunities for reduction at source, reuse and recycling as well as recovery of materials or conversion of waste into useable materials.

5. Where possible, waste containers used at the construction site will be colour-coded to help assist in the segregation efforts onsite.

Page 34: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 34 of 82 Revision 00A

6. Source re-use options on site for waste materials, e.g. re-use waste concrete to stabilise site accesses, re-use timber formwork, re-use steel off-cuts where possible.

7. When procuring materials determine whether companies will accept back waste packaging and palettes.

8. Personnel shall undergo a site specific induction that includes waste management practices and applicable legislative requirements.

9. Efforts are to be made to reduce the quantity of waste produced and reuse and recycle waste, in accordance with waste management hierarchy.

10. Regulated waste such as batteries, oil filters and chemicals are to be handled by an appropriately licensed waste removal contractor and recycled where possible or disposed of.

11. Hazardous liquid wastes awaiting disposal, such as hydrocarbons and oils, shall be stored appropriately in accordance with AS1940:2004 ‘The Storage and Handling of Flammable and Combustible Liquids’.

12. Hazardous waste material generated during any phase of the development will be segregated from other waste streams, clearly labelled and appropriately stored.

13. Waste oil will be kept in bunded area and removed for recycling by an appropriately licensed contractor.

14. Adequate waste receptacles will be provided in appropriate locations with correct identification signage.

15. Regulated waste will only be reprocessed, recycled, stored, incinerated or disposed at a licensed regulated waste facility.

16. Wastes will be disposed of frequently to reduce on site storage.

17. Liquid wastes will be stored in bunded areas in sealed containers.

18. Wastes will be segregated for recycling purposes to the level that is available within local government areas and by local contractors.

19. Waste receptacles shall be clearly labelled with the type of waste that will be placed therein.

20. Food wastes shall be removed from site at the earliest convenience to control vermin and odour. Food wastes shall be stored in bins that have lids to exclude wildlife and water. Open skips are not recommended.

21. Waste generated by site will be recorded in a waste register with the following information:

• Date removed from site

• Waste type

• Quantity (Litres or m3)

• Origin

• Destination

• Final fate, (e.g. recycled, burial etc)

Page 35: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 35 of 82 Revision 00A

• Reference number of waste transport certificate

22. Waste tracking certificates (DERM approved 5 docket system) shall accompany trackable regulated wastes.

23. Green waste should be reused on site wherever possible.

24. Precautions shall be in place to check that rubbish and waste is suitably contained on site until disposal and is prevented from escaping into bushland, creeks, stormwater, and/or onto neighbouring properties.

25. On the completion of works the site shall be cleared of all rubbish and waste and be left in a clean and tidy condition.

26. Where incorrect placement of rubbish is occurring, staff should be reminded at prestart meetings or toolbox talks.

27. Concrete wash water from agitator trucks or concrete pumping equipment is to be washed out into a bunded area on site.

Performance Indicators

1. Contamination of soil, water or air as a result of inappropriate waste management.

2. Safety issues associated with hazardous or regulated wastes.

3. Reuse and recycling levels of wastes on site where practically possible.

4. Correct disposal of regulated and contaminated wastes.

5. Incidents involving environmental harm occurring from construction wastes.

6. The handling and transporting of dangerous goods occurs in accordance with the relevant Australian Standards.

7. Waste management practices do not result in degradation of health to personnel or sensitive receptors.

Monitoring

1. Regular weekly inspection of the waste handling facilities to verify waste has been appropriately segregated

2. Receptacles shall be checked to verify correct types of waste are being deposited in each relevant receptacle.

3. Compliance with waste management plans will be audited regularly.

4. Maintained site register.

5. Regular 6-monthly audits of onsite waste disposal and recycling facilities.

Reporting

1. Waste register to be maintained and updated.

2. Record will be maintained of estimated quantities of waste materials recycled and re-used

Page 36: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 36 of 82 Revision 00A

onsite.

3. Non- Compliance and Incident Reporting will be carried out and closed out by the Contractor HSSE Manager.

4. If regulated waste is disposed of in an improper or unlawful manner, the administering authority must be notified of all relevant facts, matters and circumstances known concerning the disposal.

5. Waste tracking documentation will be recorded and sent to the DERM within 7 days of disposal of waste. Green or yellow copies will be stored in the site files with the waste register.

6. Waste handling procedures will be reviewed as required to mitigate waste management issues or transgressions.

Corrective Action

1. Re-train personnel and replace bins as necessary if rubbish becomes contaminated.

2. Amend waste management plan if required.

Training

1. Site Specific Induction

2. Environmental Awareness Training – Waste Management module

3. Toolbox Talk – Waste Management

4. Toolbox Talk – Waste Tracking

5. Toolbox Talk – Recycling and Reuse

6.6. Hazardous Substances Management

Aspect

A potential exists for fuel, oil, chemicals and other potentially hazardous materials to leak or be spilled contaminating surrounding land and water. Contaminated soils are considered ‘Regulated’ under the Environmental Protection Act 1994.

Objectives

To limit potential construction hazards and risks for construction workers and limit the potential for environmental harm from construction activities.

The key objectives are:

1. Prevent contamination of land or water on or around the site in accordance with the Auckland Point Operational Works Land Permit Final Conditions (DA 2010/03) and the CECP.

2. Spills of fuel and oil are contained and cleaned up so that no environmental harm occurs.

Statutory Requirements

Page 37: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 37 of 82 Revision 00A

1. Environmental Protection Act 1994

2. Environmental Protection Regulation 2008

3. Workplace Health and Safety Regulations 1997

4. Dangerous Goods and Safety Management Regulation 2001

5. DERM Permit No. SPCC00425710 (DA 2010/03)

6. AS1940:2004 ‘The storage and handling of flammable and combustible liquids’

7. AS3780:1994 ‘The storage and handling of corrosive substances’

Control Strategy

1. The construction site is appropriately managed in accordance with the Workplace Health and Safety Act 1995.

2. Fuel and chemical storages will comply with Australian Standards including, AS1940: Storage and Handling of Flammable and Combustible Liquids, and AS3780: The Storage and Handling of Corrosive Substances.

3. Develop emergency response procedures, and implement in the event of accidents and emergencies.

4. Provide fire and life safety measures, including ventilation, smoke extraction and fire fighting systems for the duration of the construction phase.

5. Relevant spill equipment is available and located in easily accessible areas, including refuelling vehicles.

6. Relevant plant, including marine vessels, will be equipped with adequate spill response equipment.

7. Personnel are trained to use spill equipment and familiar with disposal requirements.

Actions

1. Develop and implement safety measures for the construction works including strategies that address flood, fire and chemical hazard, communications, access for emergency services, response coordination and management.

2. Develop and implement a communication process with the Department of Community Safety in relation to emergency procedures.

3. Where possible, minimum quantities of hazardous substances necessary for construction will be maintained.

4. Report any toxic, infective or hazardous contaminants that are uncovered during the works.

5. Personnel shall receive induction training pertaining to storage and handling procedures, spill response and environmental incident reporting procedures.

6. Refuelling equipment shall be by manual operation only (e.g. operator must depress handle to pour and contain an automatic cut off when tank is full).

7. Fuelling and maintenance of vehicles and equipment shall comply with the relevant regulations and standards and it shall be undertaken at locations away from drainage systems. Precautions shall be in place to verify accidental spills do not escape into surface

Page 38: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 38 of 82 Revision 00A

waters. Such precautions may include fitting equipment with Banlaw Dry-Break (or equivalent) fuel nozzles, use of absorbent material to soak up excess oil and use of drip trays.

8. Signage shall be displayed in accordance with DGSM Regulation requirements.

9. The storage of fuel, oil and degreasers shall be contained within impervious bunded areas and comply with AS1940 ‘The Storage and Handling of Flammable and Combustible Liquids’ and shall be less than 10m3.

10. Storage of corrosive substances shall be in accordance with AS3780 “The Storage and Handling of Corrosive Substances”.

11. Incompatible chemicals, gases and hazardous substances will be segregated or separated where required.

12. Smoking will be confined to designated areas.

13. Servicing of plant will be performed in designated areas or offsite in the instance of major works, where any potential spills can be contained.

14. Spill response kits will be placed at designated locations nearby to high risk activities on the worksite. High risk activities include locations where liquid hazardous materials are stored, where refuelling and equipment maintenance are taking place (e.g. spill kits, absorbent pads, absorbent material, booms etc). The spill response kits shall be suitable for oil/fuel spills to both land and water.

15. Impervious surfacing or drip trays will be used under stationary plant and equipment as required during emergency maintenance.

16. Details of all chemicals on site will be maintained in the Hazardous Substances Register.

17. In the event of a spill to water the following actions will be undertaken:

• Identify source of spill/leak and shut down immediately where safe to do so.

• Notify HSSE Manager immediately.

• Immediately inform the GPC, relevant environmental agencies and any other crew or ships in the immediate vicinity of the spill in accordance with SOPEP (dealt with in the Marine Fuel and Oil Spill Management Plan).

• Use absorbent booms and skimmers in spill response kit to soak up as much of the spill as possible.

• Continue to soak up or skim fuel from water body until no visible slick.

• Remove booms on the outgoing tide once clearance / approval has been received from GPC and DERM.

• Check for any injury or mortality to fish and monitor for signs of environmental harm.

18. Spill response equipment that has been used in spill response shall be disposed of in appropriate regulated waste bins or in accordance with the Waste Management Plan.

Performance Indicators

1. Chemicals and fuels, including any spillage, is contained within an onsite containment

Page 39: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 39 of 82 Revision 00A

system and controlled in a manner that prevents harm to the environment.

2. Incidents involving hazardous material handling and storage.

3. Safe environment maintained for construction workers.

4. Limit construction hazards and risks for construction workers, nearby communities, pedestrians and passing motorists.

5. Correct disposal of contaminated products and recording of incidents.

6. Spills to water and no visual evidence of oily sheens.

7. Reduction of spill volumes and frequencies.

8. Effective and efficient clean-up of spills.

Monitoring

1. Regular visual inspections and job observations of refuelling and of storage facilities.

2. Regular weekly inspection of spill kits and re-stock when required.

3. All incidents and complaints shall be logged in the Environmental Incident and Complaints Register, investigated and actioned in accordance with Complaints Procedure.

Reporting

1. All spills to be recorded and entered into the Site Spill Register.

2. Waste transport certificates dockets shall be included on the waste register including reference to docket number, quantity of waste etc.

Corrective Action

1. In the event of a spill to land or water the approved site Emergency Response for Environmental Incidents Management Plan will be followed.

2. Identify cause of contamination, clean up in accordance with local government regulations and take preventative action to limit a re-occurrence.

3. Large quantities of contaminated soil shall be removed from the spill site and transported for bio-remediation in accordance with local government regulations and the Waste Management Plan.

4. An incident report shall be completed for any chemical, fuel or oil spills and logged into the Site Spill Register.

5. Restock any used items from spill kit.

6. Oil/hydrocarbon contaminated materials will be disposed of appropriately.

7. Contaminated soil shall be removed from the spill site and disposed of in accordance with Waste Management Plan for this site.

8. Leaking containers shall be placed on spill trays.

9. Emergency Contacts:

Page 40: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 40 of 82 Revision 00A

Regional Harbour Master (Gladstone) Phone (07) 4973 1200

Marine Unit Coordinator for GPC Phone (07) 4973 1208

DERM Pollution Hotline Phone 1300 130 372

QPWS Phone 1300 130 372

DPI&F Phone 13 25 23

Training

1. Site Specific Induction Induction

2. Environmental Awareness Training Package – Hazardous Substances Management and Spill Response Modules.

3. Mock Emergency Drill – Spill response and the application of spill response material.

6.7. Contaminated Sites

Aspect

A potential exists for fuel, chemicals and other hazardous materials may leak or be spilled contaminating surrounding land. Contaminated soils are considered ‘Regulated’ under the Environmental Protection Act 1994.

Objectives

To certify that storage and handling of dangerous goods on-site does not cause environmental harm or injury to individuals, and to manage potential soil contamination during construction operations.

Control Strategy

1. Relevant spill equipment will be available and located in easily accessible areas.

2. Personnel will be inducted and trained in safe work practices to limit the risk of spillage.

3. Refuelling vehicles have oil and chemical spill kits where appropriate.

4. Marine vessels are to be equipped with spill response equipment and staff familiar with its deployment and use.

5. Appropriate numbers of personnel will be trained to use spill equipment and familiar with its disposal.

Actions

1. Storage of fuel, oil and degreasers shall be contained within impervious bunded areas and comply with AS1940 ‘The Storage and Handling of Flammable and Combustible Liquids’. Floors shall slope to collection sumps for ease of draining.

2. Storage of corrosive substances shall be in accordance with AS3780 ‘The Storage and Handling of Corrosive Substances’.

3. Other hazardous materials will be stored in designated areas in accordance with the

Page 41: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 41 of 82 Revision 00A

relevant standards and be protected from possible vehicle damage. This may include bunding, concrete slabs, bunded pallets, lockable enclosures etc.

4. Incompatible chemicals will be segregated or separated where required.

5. Servicing of plant will be performed where practicable in designated areas, where any potential spills can be contained.

6. Installation of oil/water separators in bunded areas and monitoring of groundwater and surface water to verify any releases are identified and remediated as soon as practicable.

7. Adequate quantities of spill response material (e.g. spill kits, absorbent pads, absorbent material, booms etc) shall be maintained on site.

8. When working in close proximity to or over water or in a marine environment, spill kits shall be available for both water and land based applications.

9. Impervious surfacing or drip trays will be used under stationary plant and equipment as required during maintenance.

10. Vehicle and plant wash down waters will be passed through a coarse sediment trap followed by an oil interceptor.

11. Details of chemicals on site will be maintained in the Hazardous Substances Register detailing the location and quantities of hazardous substances will be established and maintained, including details of storage, use and disposal.

12. Major repairs will be performed off site at the approved vehicle workshops.

13. Spill response equipment that has been used in spill response shall be disposed of in appropriate regulated waste bins or removed offsite by a licensed contractor.

14. If an area of contamination is reported, the cause will be identified and the area of contamination contained. The impact may be contained by isolating the source or implementing controls around the affected site.

15. Contaminated soils are to be disposed of off-site at a licensed facility. Contaminated soils may require DERM disposal permits if land is listed on the contaminated land or environmental management register. Refer to www.epa.qld.gov.au/ecoaccess/contaminated_land/disposal_permits for details.

16. Remediation will be performed as soon as practical after the discovery of contamination.

17. Validation sampling of any remediated area will be used to establish the site as “clean” in line with the relevant DERM Contaminated Land and National Environment Protection Measure (NEPM) Guidelines.

18. Wastes will be classified, transported and disposed of in accordance with Queensland Environmental Protection (Waste Management) Policy 2000 and Environmental Protection (Waste Management) Regulation 2000.

Performance Indicators

1. Implementation of Contamination Management controls and techniques in accordance with

Page 42: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 42 of 82 Revision 00A

applicable standards/guidelines.

2. Spill containment facilities constructed in accordance with AS 1940 (2004) and AS 3780 (1994).

3. Correct disposal of contaminated products and recording of incidents.

4. Reduction of spill volumes and frequencies.

5. Effective and efficient clean-up of spills.

Monitoring

1. The integrity of storage facilities for hazardous materials and wastes and bunded areas will be routinely inspected by the Contractor HSSE Manager.

2. Incidents and complaints will be logged in the Incident Database, investigated and actioned.

Reporting

1. Non- Compliance and Incident Reporting will be investigated and closed out by the Contractor HSSE Manager.

2. The Contractor will maintain records of complaints received and corrective actions undertaken to prevent reoccurrence.

3. Waste transport certificates dockets shall be included on the waste register including reference to docket number, quantity of waste etc.

Corrective Action

1. Identify cause of land contamination, clean up in accordance with local government regulations and take preventative action to limit a re-occurrence.

2. Large quantities of contaminated soil shall be removed from the spill site and transported for bio-remediation in accordance with local government regulations.

3. Small quantities of contaminated soil shall be disposed of in accordance with Waste Management Procedures for this site.

Training

1. Site Specific Induction.

2. Environmental Awareness Training Package – Hazardous Substances Management and Spill Response Modules.

3. Mock Emergency Drill – Spill response and the application of spill response material.

6.8. Air Quality

Aspect

The release of noxious or offensive odours, airborne contaminants or dust from earthworks

Page 43: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 43 of 82 Revision 00A

operations, construction activities and topsoil stockpiles poses a potential environmental risk to nearby residents, project personnel and the surrounding environment.

Objectives

1. Ambient air quality is maintained at properties adjacent to worksites and in the surrounding area throughout the construction period.

2. Community concerns and complaints about air quality are addressed quickly and effectively.

Potential Impacts on Environmental Values

Air quality impacts may cause community complaints; noxious or offensive odours or airborne contaminants and excessive levels of dust may also impact construction workers health.

Control Strategy

Practicable control measures will be undertaken, including the installation of barriers and equipment to reduce air pollution and to prevent air borne contaminants created by the work from affecting the site’s personnel and neighbours in accordance with the Environmental Protection Regulation 2008 and Environmental Protection (Air) Policy 2008.

Actions

1. Limit the extent of excavation and clearing creating exposed surfaces as far as possible.

2. Limit the length of time excavated and cleared surfaces are exposed.

3. Regular watering of the construction site and access roads. Watering frequency will be increased during periods of high risk (e.g. high winds).

4. Where it is impracticable to water the site, dust control fences shall be installed to prevent windblown dust.

5. Avoiding or minimising dust generating activities (e.g. stripping, excavation) during high risk times such as dry and windy conditions.

6. Promptly removing and disposing of materials, mud or the like spilled onto the road surface which may cause a dust nuisance.

7. The sealing (with gravel or other material) of internal roads.

8. Restricting the movement of heavy vehicles to designated and restricted roads wherever practicable.

9. Limiting the speed of vehicular traffic on unsealed roads.

10. A dust sweeping vehicle will be employed where required to remove dust and dirt from hard surfaced roads.

11. A wheel shake down pad will be erected next to the site entrance.

12. Take measures to limit dust-creating material (earth or similar material) is not transported from construction sites to roads or other areas in the public domain.

13. Vehicles carrying bulk materials that could cause air pollution will be covered prior to

Page 44: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 44 of 82 Revision 00A

leaving site.

14. Encouraging reduction in engine idling during on and off-loading activities: trucks and heavy equipment will not idle for extended periods (e.g. longer than five minutes) adjacent to residential and commercial buildings.

15. If necessary in laydown areas, a layer of geotextile will be placed and covered with a crushed stone layer.

16. Re-vegetation works to be undertaken in a timely manner.

17. Stockpiles to be kept as low as possible. Maximum height will be a function of safety, the angle of repose, and the available area to store the material and most importantly, the equipment which is used to create and manipulate the pile.

18. Progressive rehabilitation to limit the exposed area and potential for dust generation.

Performance Indicators

1. The release of noxious or offensive odours resulting from construction activities must not cause an environmental nuisance at any nuisance sensitive place.

2. The release of dust and /or particulate matter resulting from construction activities must not cause an environmental nuisance at any nuisance sensitive place.

3. Excessive dust emissions during windy/dry periods.

4. Unauthorised burning.

5. Complaints relating to air quality from surrounding areas.

6. Visible dust clouds >0.5m off the ground are limited.

7. Less than 1 gram insoluble solids (not including coal) per m2 per month at any nuisance sensitive place.

Monitoring

1. Regular visual monitoring of dust emissions will be conducted and watering frequency altered as required under the direction of Contractor HSSE Manager.

2. The entire area of construction and associated access areas will be regularly inspected to assess the effectiveness of air quality protection measures by Contractor HSSE Manager.

3. When requested by the administering authority, air quality monitoring, including dust deposition monitoring, will be undertaken within a reasonable and practicable timeframe to investigate any complaint related to air quality. The data and analysed results will be notified to the administering authority within 28 days of completion of the monitoring. Monitoring will be carried out at a place(s) relevant to the potentially affected nuisance sensitive place and at upwind control sites.

4. Records of plant maintenance will be kept on site.

Page 45: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 45 of 82 Revision 00A

Reporting

1. Non- Compliance and Incident Reports will be prepared by the Contractor HSSE Manager.

2. Records will be maintained onsite of complaints received and corrective actions undertaken to prevent reoccurrence.

Corrective Action

1. Locate the source of the airborne contaminant problem and improve control mechanisms.

2. Non-Compliance and Incident Reporting will be investigated and closed out by Environment Manager.

3. Locate the source of the dust problem and cover or water the exposed areas.

4. If dust persists, cease the dust creating activities until more suitable weather conditions exist.

5. If monitoring at a nuisance sensitive place indicates levels exceeding the conditions of approval, the non-compliance must be addressed and dust abatement measures immediately implemented so that emissions do not result in further nuisance.

Training

1. Site Specific Induction

2. Environmental Awareness Training Package – Air Pollution Module.

3. Toolbox Talk – Dust Monitoring

4. Toolbox Talk – Complaint Management

6.9. Greenhouse Gas

Aspect

Emission of contaminants into the air from diesel usage.

Objectives

1. Keep emissions from plant and equipment as low as practically possible.

2. Where possible environmental friendly products will be used.

Control Strategy

Practicable control measures will be undertaken to reduce air pollution and to prevent air borne contaminants created by the work from affecting the site’s personnel and neighbours, including any adjacent bushland, in accordance with the Environmental Protection Regulation 2008 and Environmental Protection (Air) Policy 2008.

Actions

1. Schedule deliveries of construction materials and/or disposal of waste materials to limit the

Page 46: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 46 of 82 Revision 00A

length and number of trips required, by ensuring full loads and sourcing materials locally where practicable.

2. Vehicles, plants and equipment will be maintained and operated according to manufacturer’s instructions to maximise efficiency.

3. Program works to limit double handling and materials transfer.

4. Limiting travel to necessary trips.

5. Enforcing speed limits and idling of vehicles.

6. Turn off vehicles, plant and equipment rather than allowing idling when not required.

Performance Indicators

1. Unsightly emissions from construction equipment (clouds of smoke).

2. Complaints resulting from spray painting / abrasive blasting activities.

Monitoring

1. Supervisors and the Contractor HSSE Manager will undertake daily visual inspections to verify that air borne contamination mitigation measures are appropriate to weather conditions and work being undertaken at the time.

Reporting

1. The Contractor HSSE Manager shall maintain a register of complaints on site using Incident Database.

2. Records of fuel use and waste production will be maintained onsite.

3. Record the results of any investigation / monitoring arising from a complaint.

4. Report emissions as required by the National Pollutant Inventory (NPI).

5. Daily and weekly checklist shall be completed.

Corrective Action

1. Locate the source of the air borne contaminant problem and improve control mechanisms.

2. Complaints shall be addressed consultation with the Contractor HSSE Manager.

Training

1. Site Specific Induction.

2. Environmental Awareness Training Package – Air Pollution Module.

6.10. Surface Water Quality

Aspect

A potential exists for the contamination of surface water areas as follows:

Page 47: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 47 of 82 Revision 00A

• Spills or leaks during fuelling and maintenance of vehicles and equipment or leakage from hydrocarbon storage areas may contaminate the surrounding surface water drainage and groundwater systems.

• Surface water runoff and discharge waters may enter the surrounding drainage systems.

• Sewerage facilities on site may lead to water pollution, propagation of vermin and odour nuisance.

Objectives

To limit the potential impacts associated with erosion and to prevent the release of contaminants that may adversely affect surface water quality.

The key objectives are:

Implement adequate control measures to prevent the construction work from adversely impacting on the water quality of natural drainage systems and stormwater. Such control measures shall be in accordance with the Environmental Protection (Water) Policy 2009. Prior to release, any stormwater captured within the containment system must be free from contaminants or wastes.

No discharge of sediment, or contaminant that produces any slick, discoloration or visible evidence of oil or grease, scum, litter or other objectionable matter to waterways from site.

No significant changes to surface water quality or flows.

• Uncontrolled discharge of sewage does not occur.

• Protect the visual amenity of the wider project area for recreational users.

Potential Impacts on Environmental Values

Sediment laden run-off may enter nearby receiving waters during construction.

Hydrocarbon run-off may occur if spills are not adequately contained and construction equipment is not maintained.

Natural waterways and flow paths may be reduced due to the construction activities.

Control Strategy

1. All construction activities will be undertaken in compliance with the Stormwater Management Plan for the site, Conditions of Approval and the CECP.

2. Monitor water quality prior to any discharges.

3. Water quality conditions comply with permit / licence conditions prior to all discharges.

4. Limit potential sources or pathways for contaminants to enter waterways.

5. Drainage works will be designed to cater for peak flow conditions. This has been factored into the design of the Auckland Point Facility site layout and ongoing operations.

6. Settled/treated stormwater runoff waters will only be released from the site to waters in compliance with the release limits listed in Schedule C, Table 4.

Actions

1. The release of contaminants from the stormwater discharge points to water will comply with

Page 48: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 48 of 82 Revision 00A

the following Stormwater Release Limits for construction: Schedule C Table 4

RELEASE POINT

MONITOR-ING POINT

QUALITY CHARACTER-ISTICS

LIMIT LIMIT TYPE MINIMUM MONITORING FREQUENCY

Limits for Construction

Temperature BG ± 2ºC Range

pH 6.5 – 8.5 Range

Total Suspended Solids 50 mg/L Maximum

Total hydrocarbons 10 mg/L and no visible sheen, oil or objectionable material

Maximum

Dissolved Oxygen 4 mg/L Minimum

Prior to discharge and daily during discharge events

Periods of no discharge must be recorded

Cadmium 5.5 *µg/L Maximum

Chromium (Cr III) 27.4 *µg/L Maximum

Chromium (Cr IV) 4.4 *µg/L Maximum

Cobalt 1 *µg/L Maximum

Copper 1.3 *µg/L Maximum

Lead 4.4 *µg/L Maximum

Mercury (inorganic) 0.4 *µg/L Maximum

Nickel 70 *µg/L Maximum

Silver 1.4 *µg/L Maximum

Tributlytin 0.006 *µg/L Maximum

Vanadium 100 *µg/L Maximum P

rescribed in Storm

water M

anagement P

lan

Prescribed in S

tormw

ater Managem

ent Plan

Zinc 15 *µg/L Maximum

Quarterly:

Prior to discharge; and

During first day of discharge

Periods of no discharge must be recorded.

Source – Environmental Authority PFL11/PEN100725510 Schedule C, Table 4 - STORMWATER RELEASE LIMITS *Dissolved Fraction

2. Prior to release, any stormwater captured within a containment system must be free from contaminants or wastes that may cause environmental harm.

3. Graded areas will be mechanically compacted and stabilised to limit the potential for erosion.

4. Reasonable and practicable measures will be taken to prevent pollution of the waterway as a result of silt run-off, oil and grease spills from machinery, concrete truck washout and alike. Wastewater from cleaning equipment must not be discharged directly or in-directly to any watercourses, marine waters, or stormwater systems.

5. Construction of the works is to be carried out only by means of suitable plant and equipment and measures are to be taken to limit turbidity in tidal waters as a result of the

Page 49: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 49 of 82 Revision 00A

construction.

6. Washdown waters and other potentially contaminated water will be collected.

7. Diversion channels and silt fences will be constructed around topsoil stockpiles, which will be located outside drainage areas and protected from erosion.

8. Stormwater drains will be established with erosion-control structures.

9. Where required, control measures such as contours and shallow diversion channels shall be installed to prevent, as far as practicable, large amounts of stormwater from entering the construction site.

10. Where required, clear runoff from undisturbed areas shall be directed around the disturbed areas.

11. Perimeter of pits and excavations will be contoured to limit ingress of stormwater.

12. Following rainfall events the performance of erosion and sediment control devices and the quality of water runoff leaving the site will be inspected and recorded.

13. Appropriate water quality triggers for discharges offsite will be based on ANZECC 2000 Guidelines, Port Curtis Integrated Monitoring Program (PCIMP) data (zone 1) and the Queensland Water Quality Guidelines.

14. Where necessary, runoff shall be contained within detention systems, prior to discharge.

15. Where required additional erosion-control measures such as interceptor structures will be employed to reduce the velocity of overland flow in areas of high slope.

16. Storage of fuel, oil and degreasers shall be contained within impervious bunded areas and comply with AS1940 ‘The Storage and Handling of Flammable and Combustible Liquids’.

17. Storage of corrosive substances shall be in accordance with AS3780 ‘The Storage and Handling of Corrosive Substances’.

18. Fuelling and maintenance of vehicles and equipment shall comply with the relevant regulations and standards and it shall be undertaken at locations away from drainage systems.

19. Vehicle and plant wash down waters will be passed through a coarse sediment trap followed by an oil interceptor.

20. Water which is contaminated by fuels, oil, chemicals or hazardous waste shall not be discharged into stormwater or natural drainage systems. Such liquids shall where practicable be placed in drums and disposed of in accordance with Local Authority and Government regulations.

21. Any spillage of wastes, contaminants or other materials shall be cleaned up as quickly as practicable. Spills shall not be cleaned up by hosing, sweeping or otherwise releasing such wastes to any external stormwater drainage system, roadside gutter or waters.

22. If there are any signs of sediment loss, implement and maintain erosion control devices (e.g. filter fence) to contain sediment contaminated water and prevent contamination of

Page 50: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 50 of 82 Revision 00A

waters, until the completion of all works.

23. Adequate quantities of spill response material (e.g. spill kits, absorbent pads, absorbent material, booms etc) shall be maintained on site.

24. The Contractor Superintendent will be advised of any chemical, fuel or oil spills into a dam or waterway.

25. Concrete trucks will be washed in a designated, lined and contained wash out area.

26. Major services of equipment will be performed off site where practically possible.

27. QGC to notify GPC, DERM, and/or Gladstone Regional Council where the incident is of the nature that requires notification under the Environmental Protection Act 1994 and associated policies (i.e. material or serious environmental harm).

Performance Indicators

1. Uncontrolled discharges of contaminated water leaves the construction site boundaries.

2. Visible evidence of water quality impacts as a result of construction activities.

3. Sediment-laden water enters stormwater system or nearby waterways.

4. Adverse impacts on downstream watercourses.

5. Any erosion or sedimentation issues are rectified within 24 hours of reporting.

Monitoring

1. Stormwater release from site will be monitored for compliance with the Stormwater Release Limits for construction as per Table 4 Schedule C – Water

2. When requested by the administering agency, water quality monitoring will be undertaken within a reasonable and practicable timeframe to investigate any water quality issues or incidents.

3. Disturbed areas, the stockpile area and all stormwater drainage channels will be regularly inspected and findings recorded by the Contractor HSSE Manager. During construction, there will be daily inspections after all major rainfall.

4. Visual inspections to verify spills are cleaned promptly; sedimentation prevention measures appear effective and are not damaged.

5. Visual inspections to verify that appropriate measures are in place to suit the construction activities taking place at the time.

6. Incidents and complaints shall be logged in the Incident Database, investigated and actioned.

Reporting

1. A report will be prepared and submitted outlining activities occurring on site during the week including any site issues, discharges, rainfall, monitoring results and non conformances.

2. Records will be maintained of all complaints received and corrective actions undertaken to

Page 51: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 51 of 82 Revision 00A

prevent reoccurrence.

3. Any environmental incidents or complaints are reported within 24 hours of receipt / reporting.

Corrective Action

1. If oil or grease is detected the source shall be identified and equipment fixed. Where feasible the oil or grease shall be captured and placed in drums for removal from site in accordance with Local Authority Regulations.

2. Provide additional training to personnel where required.

Training

1. Site Specific Induction

2. Environmental Awareness Training – Water Quality Module.

3. Toolbox Talk – Water Quality Monitoring

4. Mock Emergency Drill – Spill response and the application of spill response material.

6.11. Weed and Pest Management

Aspect

Clearing of native vegetation and disruption to surrounding areas may significantly increase the threat of weed infestation from declared weeds already existing on or surrounding the site and other noxious weeds may be introduced to the area.

Objectives

To prevent the spread or introduction of pest and weed species as a result of Project activities.

Potential Impacts on Environmental Values

Potential for environmental harm as a result of pest infestation.

Control Strategy

1. Limit the possibility of declared weed growth on site by reducing clearing of native vegetation where possible.

2. Control the introduction of declared weeds by reducing possible sources of weed seeds potentially introduced to site.

Actions

1. Regular weed and pest inspections will be undertaken on site.

2. Routine pest control inspections will be carried out on site.

3. All vehicles and machinery will require a declaration of weed hygiene by the supplier pursuant to S45(2) of the Land Protection Act (Pest and Stock Route Management) Act 2002 to identify potential weed infestation prior to their initial commencement of works.

Page 52: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 52 of 82 Revision 00A

4. Earthmoving machinery and light vehicles shall be free of accumulations of dirt and organic matter before mobilisation to site.

5. Earthmoving plant / machinery shall be cleaned before demobilising off-site.

6. Packaging material for equipment will be checked and removed and infested/contaminated material sent to a licensed facility for disposal.

7. During induction personnel will be advised of the responsibilities with regard to weed spread prevention techniques and any associated risks (including health risks where applicable) during construction.

8. Access will be limited to designated roads and paths.

9. Known declared weeds found on site will be communicated to personnel and displayed in crib huts and form part of follow up training at Toolbox Meetings as required.

10. Seed used in rehabilitation or landscaping works shall be free of declared weeds.

11. Plants and soil will be inspected for weeds and pests before removal from the site.

Performance Indicators

1. Reduction in weed species occurring on site.

2. Spreading of existing weeds on site.

3. Pest infestations on site.

4. All vehicles entering site to be free of weeds and weed seeds.

Monitoring

1. Conduct a preliminary site survey to identify any existing declared weeds or weed infestations on site.

2. Routine pest inspections and treatment will be carried out on site.

3. Surveys and mapping of weed infested areas of the site will be conducted and infested areas will continue to be monitored every six months.

4. Regular visual inspections of the site will be undertaken.

Reporting

1. Weed hygiene declarations to be completed and maintained in site files.

2. Presence of noxious weeds will be reported to the appropriate local authorities.

Corrective Action

1. Identify method of introduction of noxious species or spread of local weeds and modify work methods to limit a re-occurrence.

2. Weed infestations shall be treated as advised by the Land Protection Officer.

3. The works, adjoining areas, any previously infected areas within the works corridor shall be

Page 53: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 53 of 82 Revision 00A

re-inspected at the completion of the maintenance period and new infestations treated.

Training

1. Site Specific Induction.

2. Environmental Awareness Training – Weeds and Pest Management Modules.

3. Toolbox Talk – Weeds.

6.12. Red Imported Fire Ant

Aspect

Red Imported Fire Ants (RIFA) may be introduced to site in high risk items including imported fill, construction machinery, hay bales, potted plants or other landscaping materials. They are a serious menace to people, property and the natural environment. Bites are very painful causing blistering and sometimes an allergic reaction.

Objectives

To prevent the spread or introduction of Eastern Red Fire Ant as a result of construction activities.

Control Strategy

1. Use staff awareness to assist in identification of Fire Ant colonies.

2. Liaise with statutory bodies to assist in the eradication of RIFAs.

Actions

1. Where required Biosecurity Queensland – Department of Employment, Economic Development and Innovation (DEEDI) shall be contacted to carry out an initial site inspection and make sure that an Approved Risk Management Plan is in place.

2. All personnel will receive induction training to increase awareness and assist in identification of RIFAs.

3. All activities on site shall be undertaken in accordance with the Approved Risk Management Plan (ARMP 3540).

4. The Contractor HSSE Manager shall verify that DEEDI have not imposed any restrictions on movements from the site. If restrictions have been imposed, all instructions will be followed.

5. Verify that if high risk items such as materials or machinery are being brought to site from a Fire Ant Restricted Area that a DEEDI approved Movement Certificate is supplied. In the event that a certificate cannot be supplied, entry to the site will not be permitted.

6. Verify that suppliers of high risk materials or restricted items have an Approved Risk Management Plan. A copy of all suppliers’ Approved Risk Management Plans shall be maintained on site.

Page 54: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 54 of 82 Revision 00A

7. All earthmoving machinery and light vehicles brought to site from areas known to be infected with RIFAs shall be washed free of accumulations of dirt and organic matter and inspected before mobilisation to site. Note - currently all plant and machinery mobilised from South East Queensland meet this criteria.

8. All subcontractors / suppliers and plant owners / operators shall be provided with information regarding the responsibilities in terms of fire ant management.

9. Fire ant fact sheets shall be supplied to all suppliers of plant and equipment.

10. If RIFAs are suspected, nests will not be disturbed as this may encourage the colony to move. A potential RIFA infestation will be reported to DEEDI.

11. Approval shall be obtained from DEEDI prior to removing any high risk or restricted items from the site. A fire ant declaration form or movement certificate will be required to accompany these materials to their destination.

12. Personnel will be trained to identify RIFAs during a site specific induction as follows:

• Small, reddish-brown ants (2 – 6 mm long) that are very aggressive when disturbed.

• Nests commonly appear as dome-shaped mounds up to 250 mm high with no obvious opening. However, RIFAs may also build less obvious nests in potted plants and in or under other items stored on the ground (e.g. soil, organic mulches, potting mixes, baled hay & straw, building and landscaping materials and equipment).

Performance Indicators

1. Reduction/eradication of fire ant colonies on site.

2. Fire ant colony establishment on site.

Monitoring

1. DEEDI inspection of site conducted where required.

2. Weekly visual assessment of site to identify any ants that meet the identification criteria.

3. All high risk or restricted items coming to site shall be inspected.

4. Remain vigilant and keep an eye out for RIFAs and their nests.

Reporting

1. All fire ant presence on site is to be reported to the Environmental Officer and DEEDI.

2. Copies of all DEEDI approved Movement Certificates shall be maintained in site files. This documentation shall be maintained for a minimum period of 12 months.

Corrective Action

1. Identify if the RIFAs were introduced and take measures to prevent a re-occurrence.

2. Develop an action plan in consultation with the DPI&F and implement on site

Biosecurity DEEDI Call Centre Phone 13 25 23

Page 55: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 55 of 82 Revision 00A

RIFA Control Centre Phone (07) 3310 2907

Training

1. Site Specific Induction

2. Environmental Awareness Training – RIFA and Pest Management module

3. Toolbox Talk – RIFAs

6.13. Mosquito and Biting Midge

Aspect

Mosquitoes and biting midge present environmental, workplace health and a general public health concern. The Mosquito and Biting Midge Management Plan aim to control these pest species their habitats.

Objectives

To undertake Project activities such that potential health impacts on Project personnel and nearby sensitive receptors arising from mosquitoes and biting midges are limited.

Control Strategy

1. A Mosquito and Biting Midge Management Plan to be implemented on site.

2. The work areas will be assessed prior to undertaking works and on an informal basis to identify potential breeding sites.

3. Controls plans will be based on, and conform to, the DERM Mosquito Management Code of Practice for Queensland.

Actions

1. Assessment of the Auckland Point Component area will be undertaken prior to works and on an ongoing informal basis to identify potential breeding sites by Contractor HSSE Manager.

2. Potential breeding sites created by construction activities, such as potholes, depressions and wheel ruts, are to be filled as soon as practicable to prevent ponding.

3. Drainage systems for stormwater, irrigation and sewage effluent will be designed in accordance with relevant standards to limit mosquito and midge breeding.

4. Offices will be fitted with protective barriers, such as fly screens and air-conditioning.

5. Insect repellent will be made available to site personnel as required.

6. Queensland Health and the Gladstone Regional Council will be consulted regarding appropriate control measures.

Performance Indicators

1. Production of potential mosquito and biting midge breeding sites resulting from Project activities.

Page 56: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 56 of 82 Revision 00A

Monitoring

1. Areas of ponding and pooled water that cannot be easily drained, removed or backfilled will be inspected regularly for presence of larvae by the Contractor HSSE Manager.

2. Inspections of potential breeding grounds will be undertaken following rain.

3. The Mosquito and Biting Midge Management plan will be reviewed periodically to guarantee continuous improvement of the program.

Reporting

1. Records of any medical treatment of Project personnel required arising from mosquito borne disease or biting midge activity will be maintained by the Contractor HSSE Manager.

Corrective Action

1. Where breeding sites are identified, the Contractor HSSE Manager will investigate reasons behind the increase.

2. Personnel will be re-trained in mitigation measures where required.

3. Work policies and procedures will be reviewed to improve the management system.

Training

1. Site Specific Induction

6.14. Visual Amenity

Aspect

Maintaining the visual amenity of Auckland Point Area 2 and surrounding area.

Objectives

To limit any potential impacts on visual amenity associated with the construction of Auckland Point Area.

Control Strategy

1. Construction areas will be maintained in a safe, neat and orderly manner.

Actions

1. To limit the potential impacts on visual amenity during construction areas will be maintained in a safe, neat and orderly manner.

2. Significant trees within the Auckland Point area will be retained to provide shade and visual amenity where practicable.

Performance Indicators

1. Exceeding visual impact on surrounding areas (residential/marine).

Page 57: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 57 of 82 Revision 00A

2. Complaints regarding visual amenity from operational practices.

Monitoring

1. Monitoring of impacts on visual amenity will occur throughout construction.

Reporting and Corrective Action

1. Non-compliance and Incident reporting will be investigated and closed out by the Contractor HSSE Manager.

2. Records will be maintained of all complaints received and corrective actions undertaken to prevent reoccurrence.

Training

1. Site Specific Induction.

6.15. Lighting

Aspect

Lighting will be required for some construction activities for safe operations and this may impact on the surrounding neighbours, mariners and marine fauna.

Objectives

To reduce as much as practicable lighting impacts on sensitive receptors.

Potential Impacts on Environmental Values

Construction lighting at Auckland Point may impact on the surrounding neighbours, mariners and marine fauna.

Control Strategy

Lighting design guidelines (utilising efficient lighting design) will be developed and implemented.

Actions

1. Details of lighting on the site shall be provided to GPC for approval.

2. Lighting will only be available for the duration of the illumination requirement.

3. Vehicular roadways will not be lit unless necessary. Low or ground level reflectors and reflective road lines will be utilised instead.

4. As far as possible all lighting (with the exception of emergency lighting) will be localised.

5. Project lighting will comply with lighting design guidelines (utilising efficient lighting design).

6. Lights on the loading jetties will be directed away from the Port of Gladstone to the extent possible.

7. Lighting should not impact on the visibility of Navigational Aids utilised for the primary

Page 58: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 58 of 82 Revision 00A

shipping channels and access to the marine facility.

8. External lighting will be located as necessary to comply with occupational health and safety requirements while minimizing where practicable light spill into marine environment.

9. Light will be screened/hooded to the extent possible so they are restricted to the immediate work area.

10. Movement or time sensitive lights will be used to limit external lighting impacts.

11. Complaints shall be recorded in the Complaint Register and auctioned in accordance with the Incident Reporting Procedure.

12. Complaints will be responded to by Contractor HSSE Manager.

Performance Indicators

1. Comply with lighting over spill standards.

2. Complaints regarding lighting from surrounding residential and marine uses.

Monitoring

1. Complaints shall be recorded in the Complaint Register.

Reporting

1. Regular updates shall be provided to the community (e.g. complaints, newspaper articles, reference group meetings).

2. Complaints shall be reported on the Complaints Register.

Corrective Action

1. Identify cause of non-conformance and modify construction methods.

2. Where feasible implement barriers and or signs to reduce the disturbance lifestyle or livelihood.

Training

1. Provide additional training to personnel where appropriate.

6.16. Traffic and Transport

Aspect

The construction area and surroundings will be subject to a Traffic Management Plan. For traffic and transport not covered by this plan, the following details of the will be associated with Auckland Point.

Objectives

Manage construction traffic and transport issues to limit the potential impacts on the community and the operation of the road network.

Page 59: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 59 of 82 Revision 00A

Control Strategy

1. A Traffic Management Plan will be prepared and implemented on site.

2. A Traffic Signage Plan will be prepared and provided to GPC at least 20 working days prior to the commencement of works.

Actions

1. The use of buses and car pools by the workforce will be encouraged in order to limit disruption to local traffic.

2. Implement traffic management measures to control truck and heavy vehicle movements, limit traffic impacts caused by construction vehicles and prevent disruption to traffic flows.

3. Identify and implement measures to manage traffic flows resulting from any changes to traffic conditions. This may include notification to local community and businesses.

4. Heavy vehicles and vehicles carrying large indivisible articles will avoid built-up and residential areas, and travel on approved B-double haulage routes (e.g. Port Access Road and Hanson Road).

5. Movement of large vehicles, vehicles carrying large indivisible articles or Dangerous Goods (e.g. 20-tonne flammable and combustible liquids) will be managed in accordance with guidelines, regulations and permits.

6. Concept design layouts for intersections and associated concept stormwater upgrades to pits and pipe sizes will be in accordance with the Queensland Urban Drainage Manual.

7. Preliminary conceptual layout for the Access Roads 1 and 2 at Auckland Point and site preparation of Areas 1 – 4 will be designed in accordance with the Queensland Urban Drainage Manual, to verify overland flow and road drainage do not adversely affect the continuing operation and maintenance of the Auckland Point rail balloon loop.

8. Foreshore access in Area 2 shall be modified to reflect the approved layout of the Marine facilities for personnel and freight transfers. The foreshore area shall allow access to be made in an emergency vehicle and for the maintenance of the foreshore.

Performance Indicators

1. Exceeding traffic delays to external Gladstone road network.

2. Traffic-related complaints and incidents caused from excessive traffic density.

Monitoring

1. The number of incidents or complaints received in relation to Project traffic will be monitored. Incidents will be investigated and complaints responded to in a timely fashion.

Reporting

1. Non- Compliance and Incident Reporting will be investigated and closed out by Contractor HSSE Manager.

Page 60: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 60 of 82 Revision 00A

2. Records will be maintained of complaints received and corrective actions undertaken to prevent reoccurrence.

Corrective Action

1. The Traffic Management Plan will be regularly reviewed and updated as required.

Training

1. Site Specific Induction

6.17. Indigenous Cultural Heritage

Aspect

No significant indigenous cultural heritage values have been identified within the construction area, however there is always the possibility that cultural artefacts will be unearthed during the construction phase and may be damaged or destroyed.

Objectives

To prevent harm to Indigenous cultural heritage items during construction.

The key objectives are:

1. Prevent or limit damage to potential indigenous cultural heritage sites and artefacts.

2. Report all potential sites or artefacts to traditional owners and DERM.

Potential Impacts on Indigenous Cultural Heritage

Damage may occur during excavation to artefacts that were not previously identified.

Control Strategy

1. To educate personnel on the identification of indigenous cultural heritage and understand the duty of care requirements.

2. To prevent damage to indigenous cultural heritage items (sites, areas etc) through increased awareness of the importance of indigenous cultural heritage.

3. To promote the preservation of indigenous cultural heritage.

Actions

1. Personnel will be advised at induction and at subsequent tool box meetings of requirements with regards to cultural heritage issues.

2. If, during construction of the works, items of cultural heritage are discovered, construction activity at the particular location will cease immediately and the items will be left and kept in a safe condition. The Contractor HSSE Manager shall be notified immediately.

3. The construction area will be clearly defined and no works will occur outside this area.

4. QGC shall carry out any instructions received from the DERM (Cultural Heritage) representative.

Page 61: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 61 of 82 Revision 00A

5. The find will not be removed or further disturbed unless given direction by the Aboriginal authority and DERM.

6. If, during construction of the Works, skeletal remains are exposed, construction activity in the vicinity of the particular location shall cease immediately and the Police will be notified immediately of the find. The Contractor Site Manager will be notified immediately of the discovery. No work shall be resumed until the Police have authorised access.

7. Exclusion zones shall be established and clearly signed around all areas of known cultural heritage value within the construction site.

8. Entry to exclusion zones shall only be permitted for authorised personnel only.

Performance Indicators

1. Unauthorised disturbance to cultural heritage sites.

2. Damage to cultural heritage artefacts or sites.

Monitoring

1. Visual monitoring of construction works, including clearing of vegetation and ground disturbance activities for the presence of items of indigenous cultural heritage significance.

2. Watching brief to be maintained during clearing and topsoil stripping activities.

Reporting

1. Identify cause of damage to cultural heritage items and provide additional training to personnel in recognition of such items.

2. Incidents and complaints shall be logged in the Incident Database, investigated and actioned.

3. Surveys and monitoring conducted will be recorded daily.

Corrective Action

1. Take actions as directed by the Traditional Owners and DERM.

Training

1. Site Specific Induction.

2. Environmental Awareness Training – Indigenous Cultural Heritage Module.

3. Toolbox Talk – Indigenous Cultural Heritage.

6.18. Non-Indigenous Cultural Heritage

Aspect

No significant non indigenous cultural heritage values have been identified within the construction area.

Page 62: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 62 of 82 Revision 00A

Objectives

To prevent harm to Non-Indigenous cultural heritage items during construction.

The key objectives are:

1. Prevent or limit damage to potential indigenous cultural heritage sites and artefacts.

2. Report potential sites or artefacts to traditional owners and DERM.

Potential Impacts on Non-Indigenous Cultural Heritage

Damage may occur during excavation to artefacts that were not previously identified.

Control Strategy

1. To educate personnel on the identification of non-indigenous cultural heritage and understand the duty of care requirements.

2. To prevent damage to non-indigenous cultural heritage items, sites, areas etc. through increased awareness of the importance of and protection of non-indigenous cultural heritage.

3. To promote the preservation of non-indigenous cultural heritage.

Actions

1. Personnel will be advised at induction and at subsequent tool box meetings of requirements in regard to cultural heritage issues.

2. Areas of non-indigenous cultural heritage significance shall be clearly identified, marked and where required protected.

3. Disturbance to or removal of any unmarked cultural sites / material is not permitted without permission.

4. Exclusion zones shall be established and clearly signed around areas of known cultural heritage value within the construction site.

5. Entry to exclusion zones shall only be permitted for authorised personnel only.

Performance Indicators

1. Unauthorised disturbance to cultural heritage sites.

2. Damage to cultural heritage artefacts or sites.

Monitoring

1. Visual monitoring of construction works, including clearing of vegetation and ground disturbance activities for the presence of items of non indigenous cultural heritage significance.

2. Watching brief to be maintained during clearing and topsoil stripping activities.

Reporting

1. Identify cause of damage to cultural heritage items and provide additional training to personnel in recognition of such items.

Page 63: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 63 of 82 Revision 00A

2. Incidents and complaints shall be logged in the Incident Database, investigated and actioned.

3. Surveys and monitoring conducted to be recorded.

Corrective Action

1. Take actions as directed by the Traditional Owners and DERM.

Training

1. Site Specific Induction

2. Environmental Awareness Training – Non-Indigenous Cultural Heritage Module.

3. Toolbox Talk – Non-Indigenous Cultural Heritage

6.19. Stakeholder Management

Aspect

A potential exists for poor stakeholder relations due to the following:

Residents exist within close proximity to the work, and there is a risk that they may be adversely affected by construction activities.

Increased risk of road accidents due to increased volume of traffic on local roads, particularly during mobilisation of plant and equipment.

Objectives

1. Limit disturbance to the quality of lifestyle and livelihood of nearby residents.

Statutory Requirements

1. Environmental Protection Act 1994; and

2. Environmental Protection Regulation 2008.

Management Strategy

1. Community to be notified at earliest convenience of any potential disruptions.

2. Community to be informed by regular project communication (e.g. Updates, project progress, delays, etc)

3. Transparent community relations / communication plan.

4. Other stakeholders (e.g. schools, interest groups etc) to be consulted wherever required.

Actions

1. Construction activities will be planned to have minimal impact on the community.

2. No timber, water, gravel or any other resource will be taken from adjoining land without the written consent of the land owner.

3. Road warning signs and lighting will be erected where required.

Page 64: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 64 of 82 Revision 00A

4. The delivery of major/heavy loads to the site will be planned to limit disruption to local traffic and to avoid school buses.

5. Landholders likely to be affected will be advised of the program, for heavy or large loads, up to two weeks prior to the movement of these loads.

6. The use of buses and car pools by the workforce will be encouraged in order to limit disruption to local traffic.

7. All efforts shall be made to check that gates and fences bounding the site and access roads through the site are maintained in good repair.

8. Personnel will be advised at induction not to trespass on neighbouring properties.

9. All complaints received will be investigated, recorded and reported and appropriate actions will be taken.

Performance Indicators

1. Environmental nuisance to nearby residents or the public from construction activities.

2. Complaints from nearby residents.

Monitoring

1. Regular visual inspections of neighbouring boundaries.

2. All complaints shall be recorded in the Complaint Register and actioned in accordance with the Incident Reporting Procedure.

Reporting

1. Complaints shall be reported in the Complaint Register.

2. Regular updates shall be provided to the community (e.g. complaints, newspaper articles, reference group meeting etc).

Corrective Action

1. Identify cause of non-conformance and modify construction methods.

2. Where feasible, implement barriers and/or signs to reduce the disturbance to the resident’s lifestyle or livelihood.

3. Provide additional training to personnel where appropriate.

Training

1. Site Specific Induction

2. Toolbox Talk – Stakeholder Relations

3. Toolbox Talk – Complaints Management

Page 65: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 65 of 82 Revision 00A

7. Environmental Performance 7.1. Environmental Inspection

The Contractor HSSE Manager, will perform and document regular field inspections (at least two per work week) to verify that the environmental requirements specified in this CECP are being implemented during construction activities. The actual inspection schedules will be dictated by the type of construction activities occurring and the environmental requirements relevant to those activities. Subcontractors will be expected to inspect their work areas and storage/laydown areas daily. The Contractor HSSE Manager will periodically verify these activities are occurring by reviewing the Subcontractor’s environmental records using Environmental Field Inspection Procedures, including applicable checklists and forms for completing the inspections.

The environmental inspection checklists will include details of observations, the responsible party, and when the situation will be mitigated. Example checklists are included as Attachment D. The Contractor HSSE Manager will implement required environmental improvements and maintain an Action Tracking database that will identify the status of corrective actions. Open actions will be reviewed in the weekly progress meeting to help promote timely closeout.

If necessary, “stop work” orders will be issued if construction activities are not in accordance with the applicable environmental requirements and may result in a significant adverse impact to the environment if the activity continues. For example, a culturally significant artefact find or a significant hazardous substance spill. If such conditions exist, the Contractor HSSE Manager will take appropriate action to halt and correct the problem and immediately notify the Contractor Site Manager, and other personnel, as appropriate. The construction activity in question will not resume until corrective actions have been taken.

Should site self assessments by the Contractor HSSE Manager indicate trends considered unacceptable by the Contractor Site Manager, offsite evaluations and audits may be performed through Contractor and/or QGC HSSE personnel. The results of those evaluations will be shared with the Contractor Site Manager and the Contractor HSSE Manager.

Inspections records and audit reports will be available for review by the administering agency upon request.

7.2. Environmental Auditing

Environmental audits are intended to determine whether the requirements of the CECP are properly implemented and maintained on site. Accordingly, auditing is to be undertaken to confirm that activities are carried out in line with the defined requirements, and are producing the required performance outcomes. The audits will cover the full spectrum, from compliance

Page 66: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 66 of 82 Revision 00A

with strategic procedures to compliance with job-specific procedures. These audits will be initiated by the relevant Contractor HSSE Manager and performed by a suitably qualified external Third Party Auditor who is accepted by the administering authority. An audit will be conducted within three (3) months of commencement of construction activities at Auckland Point. A copy of the final version of the auditor’s report will be submitted directly to the administering authority within twenty (20) business days of completing the audit, and accompanied with a statutory declaration, stating that the report accurately represents the findings of the Third Party Auditor. Thereafter, audits will be conducted annually.

An audit procedure will include the following:

Review the scope, plan and schedule of the audit.

- Examine objective evidence (documented environmental records, direct observations of non-conformance/potential opportunities and personnel interviews) to verify conformance with CECP requirements.

- Give specific attention to continual improvement actions developed in response to previous audit findings.

- Post-audit communication to present audit findings, clarify any misunderstandings and summarise the audit findings.

The audit program will be reviewed annually and revised to reflect any improvements to the methodology, auditors or timeframe of audits.

An Audit Summary Report will be completed within three weeks of completing an audit and the results discussed at the next management meeting.

The Audit Summary Report will list improvement actions required to prevent a recurrence of any identified issues or to maximise opportunities for improvement.

A summary of Project elements that will be subject to audit is provided in Table 4 below.

Table 4 Audit Requirements

Element to be Audited Area or Function to be Audited

Application of CECP Audit to determine the extent of compliance with the various components of the CECP.

Monitoring results and documentation

Audit monitoring results against defined performance criteria.

Have results of monitoring and inspection programs been documented?

Have environmental or health risks been documented and managed?

Incident documentation and emergency preparedness

Reporting and managements of incidents.

An audit to assess management, documentation and reporting of incidents/emergency situations. Are incidents reported and

Page 67: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 67 of 82 Revision 00A

Element to be Audited Area or Function to be Audited

documented?

Are there options available for improvement and management of processes where incidents have occurred?

Induction, training and awareness

Induction and training registers will be audited annually to verify personnel receive relevant inductions and training, as appropriate to their roles and responsibilities within the scheme.

Management Review Audit of:

Information and environmental management strategies remain current

Opportunities for improvement have been identified

Requests or directions from relevant stakeholders have been considered

Changes in environmental management practices or pollution, contamination or legislation have been incorporated

The CECP has been reviewed/updated to account for changes to the program.

7.3. Environmental Monitoring

Specific monitoring measures for the following environmental aspects, during construction, have been discussed in the management plans presented for each aspect in the previous section:

General Construction

Construction Noise and Vibration

Soil Erosion and Sediment Control

Management of Acid Sulphate Soils

Waste Management

Hazardous Substances Management

Contaminated Sites

Air Quality

Greenhouse Gas

Surface Water Quality

Weed and Pest Management

Red Imported Fire Ant

Mosquito and Biting Midge

Visual Amenity

Lighting

Page 68: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 68 of 82 Revision 00A

Traffic and Transport

Indigenous Cultural Heritage

Non-indigenous Cultural Heritage

Stakeholder Management

Monitoring will be undertaken by suitably qualified personnel. All instruments, equipment and measuring devices used for measuring or monitoring must be calibrated, and appropriately operated and maintained. Results of monitoring will be maintained on record, compiled and reported internally and will be made available for inspection as required by QGC’s Environmental Management System. Any external audits conducted by GPC, DERM or other government agencies and auditors appointed by QGC will also be recorded internally and will be made available for inspection.

The administering authority must be notified within seven (7) days of completion of analysis of any result of a monitoring program that indicates an exceedance of any limit specified in the project approvals. The written notification must include:

The full analysis results

Details of investigation or corrective actions taken

Any subsequent analysis.

Potential Acid Sulphate Soils (ASS) has been identified on Curtis Island, however, it is not considered to be of considerable concern nor is it detrimental to the project. A site specific Acid Sulphate Soils Management Plan (ASSMP) has been prepared for the construction of the Marine Facility, and is integrated within the wider QCLNG Project Acid Sulphate Soil Strategic Management Framework.

7.4. Reporting and Compliance Checking

To assist in meeting Project environmental compliance requirements, environmental compliance reviews/coordination meetings will be held among appropriate Project personnel, including the Contractor Site Manager, the Contractor HSSE Manager, the lead Subcontractor representatives and other staff (as applicable). The purpose of these meetings will be to discuss current and future construction activities as they relate to maintaining environmental compliance. Typically, these meetings will occur as part of the Weekly Subcontractor Progress Review Meetings, but may be held more frequently as construction activities warrant.

7.5. Identifying Environmental Issues and Corrective Actions

7.5.1. Emergency and Incident Management

An environmental emergency or incident will be regarded as any action that harms or has the potential to cause significant harm to the environment. In the event that an environmental emergency or incident occurs, the following steps will be followed immediately:

Page 69: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 69 of 82 Revision 00A

Prevent further pollution/environmental harm (including impacts on air, water quality, flora and fauna and noise environment)

Clean-up and/or control polluting substance(s)

Implement mitigation measures to prevent recurrence of a similar incident

Document the incident and instigate an incident investigation as appropriate.

Incidents will be reported within a maximum window of 24 hours to the relevant Contractor HSSE Manager. Any emergency or incident which results in the release of contaminants or mismanagement of waste not in accordance, or reasonably expected to be not in accordance with project approvals, will be reported by the Contractor HSSE Manager to the Gladstone Port Corporation and other appropriate agencies, in accordance with statutory requirements. The notification of emergencies or incidents must include the following:

The holder of the development approval

The location of the emergency or incident

The number of the development approval

The name and telephone number of the Contractor HSSE Manager

The time of the release/mismanagement incident

The time the holder became aware of the release/mismanagement incident

The suspected cause of the release/mismanagement incident

The environmental harm caused, threatened, or suspected to be caused by the release/mismanagement incident

Actions taken to prevent further release and mitigate any environmental harm caused by the release/mismanagement incident.

Not more than fourteen (14) days following the initial notification of an emergency or incident, written advice must be provided of the information previously supplied, and:

Proposed actions to prevent a recurrence of the emergency or incident

Outcomes of actions taken at the time to prevent or minimise environmental harm/ nuisance.

7.5.2. Complaints and Responses

Attention to complaints should be carefully managed, be prompt and effective, and should form a key part of the environmental reporting mechanism. All complaints received must be recorded including details of complainant, reasons for the complaint, investigations undertaken, conclusions formed and actions taken. Except in cases where the complaint is considered to be a matter for which the holder is in compliance, is frivolous, vexatious, or based on a mistaken belief, corrective action must be taken as soon as practicable to investigate the cause and resolve the complaint. Corrective actions, recommendations and procedures, including

Page 70: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 70 of 82 Revision 00A

modifications to practices where applicable, should be made and closed out under the direction of the Contractor Site Manager.

The procedure for complaints should include:

A procedure for receiving and responding to complaints that is acceptable to the relevant agency.

A process for registering and handling complaints received in terms of:

- Time and date of complaint

- The identity of the complainant and the recorder of the complaint

- The specific action or activity causing the complaint

- Whether environmental compliance requirements are being met

- The action taken to address the complaint if necessary

A database for tracking of complaints and actions taken in response.

Immediate communication of the complaint to the Contractor.

Details on how the action taken is to be communicated to the complainant and the Contractor.

Feedback to the complainant and the relevant agency as required within a specified time period.

Any subsequent remedial action required to avoid cause for future complaints if relevant.

Regular reporting to the relevant agency of complaints and corrective actions.

Monitoring and auditing of the complaint handling system.

Page 71: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 71 of 82 Revision 00A

8. Communication 8.1. Internal Communication

Environmental protection will be achieved through clear and concise internal communications, which will include regularly scheduled environmental meetings. Minutes will be recorded for follow-up on specific or corrective actions raised during the environmental meetings.

8.2. External Communication

For clear and unambiguous communication the Contractor HSSE Manager will have responsibility for contact with all environmental agencies. Only personnel nominated by the Contractor Site Manager should be involved in consultation with external agencies on environmental issues.

The Contractor HSSE Manager will make regular contact with the various environmental agencies to keep them informed of the work status. The Contractor HSSE Managers involvement with regulatory agencies will be initially coordinated with QGC. This regular contact may include meetings and scheduled site visits, so that open discussion is maintained on all environmental aspects of the construction activities. The Contractor HSSE Manager may also attend other meetings with regulatory agencies, municipal agencies, and citizen groups as requested to help maintain communication concerning permit conditions, mitigation practices, and problem resolution.

Following the initial coordination with regulatory agencies performed by QGC mentioned above, when the Contractor HSSE Manager attends meetings with regulatory agencies, the Contractor HSSE Manager will continue to invite QGC to attend meetings, unless and until directed to do otherwise by QGC. Further details and clarification (e.g. a decision tree stating when QGC is to be invited) regarding the interface with regulatory agencies will be developed by QGC as the QCLNG Project progresses. Field Engineering personnel may also be requested to contact environmental agencies as part of their permitting activities.

8.3. Community Engagement and Consultation

Stakeholder management measures specific to the construction activities have been detailed in the management section and tables above. In general the community engagement process established includes:

Early establishment of community information services which may include telephone service, project website and email service, regular newsletters, scheduled information sessions or open days.

Availability of information through the QCLNG Project website generally and in response to specific inquiries about environmental performance.

Page 72: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 72 of 82 Revision 00A

Early and on-going engagement with owners and occupants of premises adjacent to the proposed works or proposed mitigation measures.

Where required, special procedures to respond to complaints, issues or incidents, such as face-to-face meetings and on-going communications with affected parties and a documented process for issues resolution.

Further to the process outlined above the consultation with property owners and occupants of residences identified as potentially affected by the construction works, as well as the wider community, will be conducted throughout the construction period.

Page 73: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 73 of 82 Revision 00A

9. Training and Environmental Awareness Environmental education is an important part of an effective environmental compliance program and the overall HSSE program. The curricula stress the importance of maintaining “environmental awareness” in the personnel's everyday duties. Presentations will be followed by a question and answer period.

Project personnel will receive training an induction into the CECP to familiarisation them with the relevant management systems and requirements, as appropriate to their roles and responsibilities.

Environmental management training will address:

The role of the CECP

Personnel responsibilities

Incident and emergency response

Health and safety instruction

Identification and understanding of the environmental issues outlined in the CECP

Specific topics as applicable to the individual’s role

Gladstone Ports Corporation Limited’s environmental policy.

Attendance records for personnel induction/training will be maintained onsite.

9.1. New-Hire Orientation – Environmental Awareness

New-hire orientation and training is a mandated part of training for onsite construction personnel and will be delivered by the Contractor HSSE Manager or a designated training coordinator. In addition to HSSE performance and site rules, the following environmental topics will be covered:

General site maintenance (e.g. good housekeeping, environmental controls maintenance).

Waste management rules and requirements (e.g., waste transfer, burn restrictions, aerosol can segregation, storage area management, proper labelling, and waste disposal).

Hazardous material/waste handling (e.g. hazard identification, MSDS, incompatible segregation, container management, proper labelling).

Erosion and sediment control (e.g. assessing site conditions and erosion control requirements, installing and maintaining erosion and sediment control measures while working in an area, reporting non-functioning erosion control measures).

Sensitive areas protection (e.g. working only within approved limits, maintaining buffers zones around sensitive resources, storing hazardous materials away from ocean shores and streams).

Endangered species awareness and protection (e.g. endangered species in the area, identifying unusual plants and animals in the area, reporting sightings).

Page 74: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 74 of 82 Revision 00A

Interaction with local wildlife (e.g. hunting, fishing and foraging rules, how to behave when you encounter a wild and/or potentially dangerous animal).

Dust control measures (e.g. speed restrictions).

Pest control (e.g. red imported fire ants, biting midges, feral animals).

Unanticipated discoveries (e.g. stop work immediately if archaeological artefacts, contaminated soils, containers, pipes, and/or tanks are discovered/uncovered, immediately notify supervisor).

Spill prevention and response (e.g. proper storage of hazardous materials, secondary containment, spill response, and notifications).

Environmental awareness training will be included in each construction New-Hire Orientation. Each new starter will be required to attend New-Hire Orientation before working on the job site and records will be kept of personnel who attend.

9.2. Supervisor Construction Environmental Awareness Training

Supervisors and Foremen will receive additional environmental awareness training to aid them in recognizing and responding to environmental compliance related conditions. This training discusses overall environmental compliance program and provides compliance recognition training. This training stresses the Supervisor’s role in recognizing and responding to environmental compliance needs.

9.3. Hazardous Material Management and Spill Response Training

Supervisors, foremen and subcontractors will receive additional hazardous material management training, including how to avoid spills and how to respond to minor spills. Attendees will be documented. This training will be presented by the Contractor HSSE Manager.

Additional environmental training classes may be developed for Project specific situations and/or issues. If required, these training classes will be prepared and presented by the Contractor HSSE Manager.

9.4. Construction Execution Plans

Work Method Statements (WMS) convert construction specifications into a task or method-specific approach.

9.5. Toolbox Talks

Toolbox Talks will be held regularly in order to cascade relevant information is communicated to the workforce and that feedback can be provided on issues of interest or concern. These talks will be undertaken to review issues associated with upcoming work activities, including cultural heritage, the environment and safety. Records will be kept for Toolbox Talk Agendas,

Page 75: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 75 of 82 Revision 00A

attendance and outcomes. Sessions will include discussion of strategies to be implemented as identified in job hazard analysis (JHAs).

9.6. Job Hazard Analysis

A JHA will be undertaken to help personnel identify, analyse and manage the hazards associated with their work. The JHA will formalise the process of hazard identification and management that most people follow when working. The JHA will require personnel to examine the task they are about to undertake by:

Breaking the job into separate, defined steps.

Identifying the potential hazards (safety and environmental) that could occur during each defined step.

Listing the method to be followed to prevent or limit the risk of injury, loss, damage or environmental incident that may be caused by each potential hazard.

Page 76: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 76 of 82 Revision 00A

10. Emergency Preparedness and Response Preparedness includes developing response procedures for anticipated emergencies, pre-positioning emergency response materials (e.g. spill kits, fire fighting tools) and training and equipping adequate numbers of emergency responders. In addition to the available capability to QGC and its subcontractors, specialty subcontractors may be available for response to exceptional emergencies, such as a large fuel spill on water.

An Emergency Response for Environmental Incidents Management Plan, including safety, security and environmental procedures, describes the preparedness measures and response that will be conducted in the event of an emergency. Environmental emergencies may involve spills of dangerous goods on land or water, unanticipated discovery of hazardous materials, unanticipated discovery of cultural resources, wildfire, unauthorised discharge of storm water or other contaminated water, unauthorised release of air pollutants, and unexpected encounters with wildlife. Response to an emergency generally follows these steps:

Stop the source of the problem if it is safe to do so

Contain the problem to the extent possible

Report the problem

Clean up and remediate the affected resources.

Page 77: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Page 77 of 82 Revision 00A

11. Document Control 11.1. Document Control and Record Management

The system used for control of management and technical documents including “controlled” documents subject to revision will enable the complete management of all documents, including the identification of document or drawing lists, author and recipient management, and various forms of reporting.

11.2. CECP Review

This CECP, its operation and implementation, and the associated elements of the accompanying environmental management systems, will be reviewed every 6 months for conformance with the QCLNG environmental policies and objectives, and legal and other requirements. In addition, if during construction, Corrective or Preventative Actions are raised indicating that amendments are required to the CECP; this will also trigger the review process. A review may also be undertaken following request by the administering authority.

The outcomes of the management review process will be incorporated as improvements to the CECP, WMS’ and other procedures/plans, to facilitate regulatory and policy compliance and continuous improvement.

The agenda for the management reviews will typically include:

Progress of the CECP implementation

Management effectiveness

Adequacy of resources

Results of the audits

Critical non-conformance or repeated non-conformances

Overall performance against benchmarks

Organisation changes

Training.

If the text or body of the CECP is required to be updated at any stage during the construction process, a revised copy will be submitted relevant agencies with a consultation or approval role.

Page 78: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Revision 00A

Attachment A – Site Drawings Auckland Point Area 2 G1004-2-AP2-11

Page 79: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

AUDIT TESTING SCHEDULE

G1004-2-AP2-11

D:\Jobs C

urrent\G

oldingsB

GLng\D

etail D

esign\A

cad\G

1004-2-A

P2-06.dw

g, 6/07/2010 6:25:00 P

M

Page 80: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated. Bechtel Confidential

© Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Revision 00A

Attachment B – Auckland Point Area 2 Risk Register

Page 81: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1 MobilisationPlant & Equipment mobilised to site

Air emissions

Greenhouse gas emissions

Generation of noise and vibration

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Hydrocarbons entering water degrading water quality

Quite Possible

FrequentDam.>$100K to

$500KSerious Env.

UBechtel Dangerous Goods

and Hazardous Substances Management

Remotely Possible

FrequentDam.>$10K to

$100KMaterial Env.

A

Hydrocarbons entering surface water degrading surrounding habitat

Quite Possible

FrequentDam.>$100K to

$500KSerious Env.

UBechtel Dangerous Goods

and Hazardous Substances Management

Remotely Possible

FrequentDam.>$10K to

$100KMaterial Env.

A

2 Piling in Marine EnvironmentPlant & Equipment mobilised to site

Greenhouse gas emissions

Generation of noise and vibration

Introduction of noxious weeds in dirt and soil

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Weed and Pest Management Plan and

Golding WMS

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Introduction of fire ants in dirt and soil

Unusual But Possible

Frequent

Dam.>$100K to $500K

Serious Env. Harm

UBechtel Weed and Pest Management Plan and

Golding WMS

Conceivable but very unlikely

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Wide loads creating traffic hazards on public roads

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Core Process - CP-406 - External Stakeholder

Interaction

Unusual but possible

FrequentDam. to $10KEnv. Nuisance

A

Disturbance of acid sulphate soilsQuite

PossibleFrequent

Dam.>$100K to $500K

Serious Env. Harm

U

Bechtel Soil Contamination Management Plan, Acid

Sulphate Soil Management Plan and Golding WMS

Remotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Air pollution - exhaust emissions and dust from equipment

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Air Quality and Dust Management Plan

and Golding WMS

Remotely Possible

Frequent ADam. to $10KEnv. Nuisance

UBechtel Air Quality and Dust Management Plan

and Golding WMS

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

AAir pollution - exhaust emissions from plant

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

High noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or residents

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Noise Abatement

Management Plan and Golding WMS

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

High noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Noise Abatement

Management Plan and Golding WMS

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Dam.>$10K to $100K

Material Env. Harm

A

ADam. to $10KEnv. Nuisance

A

Dam.>$10K to $100K

Material Env. U

Remotely Possible

FrequentBechtel Noise Abatement

Management Plan and

Disturbance of contaminated materials (eg. Tributyl Tin Deposits)

Unusual But Possible

Introduction of noxious weeds in dirt and soil

Introduction of fire ants in dirt and soil

Unusual But Possible

Quite Possible

FrequentAlmost Certain

Air pollution - exhaust emissions from plant

High noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or

Quite Possible

Frequent

FrequentRemotely Possible

UDam. to $10KEnv. Nuisance

Bechtel Air Quality and Dust Management Plan

and Golding WMS

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Soil Contamination

Management Plan and Golding WMS

Conceivable but Very Unlikely

Frequent

FrequentConceivable

but Very Unlikely

Frequent

Frequent

Dam.>$10K to $100K

Material Env. Harm

U

Dam.>$10K to $100K

Material Env. Harm

Remotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Weed and Pest Management Plan and

Golding WMS

Bechtel Weed and Pest Management Plan and

Golding WMSA

Dam.>$10K to $100K

Material Env. Harm

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

Page 1 of 29

Page 82: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Concrete spill from equipment failures (concrete pump burst, formwork burst etc)

Concrete entering groundwater degrading water quality

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env.

UBechtel Surface Water and

Groundwater Quality Management Plan,

Conceivable but Very Unlikely

FrequentDam.>$10K to

$100KMaterial Env.

A

Waste disposal

Concrete structures reducing the visual amenity of area

OccasionalUnusual But

PossibleConcrete entering surface waters degrading surrounding habitat

Frequent

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$100K to $500K

Serious Env. Harm

U

Bechtel Surface Water and Groundwater Quality Management Plan,

Dangerous Goods and Hazardous Substances Management Plan and

Dam. to $10KEnv. Nuisance

ADam. to $10KEnv. Nuisance

URemotely Possible

Frequent

FrequentQuite

Possible

Visual pollution from excess concrete, reo, nails, formwork, packaging materials

Not satisfying public perceptionsUnusual But

PossibleFrequent

FrequentRemotely Possible

UDam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

A

ADam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

A

Degraded surface water quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible

FrequentDam. to $10KEnv. Nuisance

URemotely Possible

Frequent

Degraded soil quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible

FrequentDam. to $10KEnv. Nuisance

URemotely Possible

Frequent

Occasional

Bechtel Waste Management Plan and

Golding WMS

Conceivable but Very Unlikely

Unusual But Possible

Concrete entering surface waters degrading water quality

FrequentConceivable

but Very Unlikely

U

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$100K to $500K

Serious Env. Harm

Remotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

Wastewaters entering groundwater degrading water quality

UUnusual But

PossibleFrequent

Not satisfying public perceptionsDam. to $10KEnv. Nuisance

ADam. to $10KEnv. Nuisance

URemotely Possible

FrequentBechtel Core Process - CP-406 - External Stakeholder

Interaction

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

A

Dam.>$10K to $100K

Material Env. Harm

Frequent

Dam.>$100K to $500K

Serious Env. Harm

U

Quite Possible

Remotely Possible

Remotely Possible

U

Dam.>$100K to $500K

Serious Env. Harm

Frequent

Hydrocarbons entering groundwater degrading water quality

Quite Possible

Frequent

Hydrocarbons entering land and contaminating soils

Frequent

Bechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Quite Possible

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible

Frequent

A

Dam.>$10K to $100K

Material Env. Harm

FrequentRemotely Possible

U

Dam.>$100K to $500K

Serious Env. Harm

Remotely Possible

U

Dam.>$10K to $100K

Material Env. Harm

Frequent A

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

FrequentDam. to $10KEnv. Nuisance

Bechtel Noise Abatement Management Plan and

Golding WMS

Bechtel Noise Abatement Management Plan and

Golding WMSFrequent

FrequentDam. to $10KEnv. Nuisance

A

Env. NuisanceA

Material Env. Harm

UPossible

FrequentManagement Plan and Golding WMS

High noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Vibrations may cause structural damage to adjacent buildings

Quite Possible

Unusual But Possible

to personnel on site and/or surrounding residents

PossibleFrequent

Bechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Bechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Bechtel Surface Water and Groundwater Quality Management Plan,

Dangerous Goods and Hazardous Substances Management Plan and Bechtel Surface Water and Groundwater Quality Management Plan,

Dangerous Goods and Hazardous Substances Management Plan and

Bechtel Waste Management Plan and

Golding WMS

Bechtel Waste Management Plan and

Golding WMS

Bechtel Core Process - CP-406 - External Stakeholder

Page 2 of 29

Page 83: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

4Installation of Underground Services - water, conduits

Excavation, backfill and associated concrete works covered in earthworks and concrete sections

Refer above N/A N/A N/A

Air emissions

Generation of noise and vibration

Delivery of pipes, conduits, sand etc

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Waste disposal

5Plant and equipment maintenance and servicing - Marine works

Establishment of site workshop covered by earthworks, concrete works and underground services sections

Refer above N/A N/A N/A

Dam. to $10KEnv. Nuisance

AQuite

Possible

Visual pollution from excess tape, glues, rubber bands, packaging materials etc

Dam. to $10KEnv. Nuisance

URemotely Possible

FrequentBechtel Waste

Management Plan and Golding WMS

Quite Possible

FrequentDam. to $10KEnv. Nuisance

A

FrequentRemotely Possible

U

Dam.>$10K to $100K

Material Env. Harm

Bechtel Waste Management Plan and

Golding WMS

Dam. to $10KEnv. Nuisance

A

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

FrequentBechtel Waste

Management Plan and Golding WMS

ADam. to $10KEnv. Nuisance

Quite Possible

FrequentSoil contamination from excess tape, glues, rubber bands, packaging materials etc

Degraded surface water quality from excess tape, glues, rubber bands, packaging materials etc

FrequentQuite

Possible

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

Frequent

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

FrequentQuite

PossibleHydrocarbons entering soil resulting in contamination

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible

Frequent

FrequentRemotely Possible

U

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Dam.>$10K to $100K

Material Env. Harm

A

A

Dam.>$10K to $100K

Material Env. Harm

Traffic problems on public roads. Not satisfying public perceptions

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

Frequent

Remotely Possible

Frequent

Bechtel Core Process - CP-406 - External Stakeholder

Interaction

UCEMP & ECP's - Noise and Vibration Section

Noise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Dam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

ADam. to $10KEnv. Nuisance

URemotely Possible

FrequentBechtel Noise Abatement

Management Plan and Golding WMS

Frequent

FrequentQuite

PossibleAir pollution - dust from plant and equipment

Noise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to personnel on site and/or nearby residents

Quite Possible

Frequent

FrequentRemotely Possible

UDam. to $10KEnv. Nuisance

Bechtel Air Quality and Dust Management Plan

and Golding WMS

Dam. to $10KEnv. Nuisance

ABechtel Air Quality and Dust Management Plan

and Golding WMS

ADam. to $10KEnv. Nuisance

Env. NuisanceA

Air pollution - exhaust emissions from plant and equipment

Quite Possible

FrequentDam. to $10KEnv. Nuisance

URemotely Possible

Frequent

Env. NuisanceU

PossibleFrequentNot satisfying public perceptions

PossibleFrequent 406 - External Stakeholder

Interaction

Page 3 of 29

Page 84: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

Fire and Explosion

Air emissions

Generation of noise and vibration

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Remotely Possible

U

Dam.>$100K to $500K

Serious Env. Harm

Frequent

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

A

Dam.>$10K to $100K

Material Env. Harm

Frequent

Frequent

Dam.>$10K to $100K

Material Env. Harm

AFrequent

Dam.>$100K to $500K

Serious Env. Harm

URemotely Possible

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Frequent

Dam.>$10K to $100K

Material Env. Harm

AFrequent

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

Hydrocarbons entering land and contaminating soils

Hydrocarbons entering water degrading water quality and surrounding habitat

Hydrocarbons entering groundwater degrading water quality

Quite Possible

Quite Possible

Quite Possible

Remotely Possible

U

Dam.>$10K to $100K

Material Env. Harm

FrequentBechtel Noise Abatement

Management Plan and Golding WMS

ADam. to $10KEnv. Nuisance

Frequent

Noise & vibration levels from plant and equipment (cranes, welders, small tools etc) is a nuisance to personnel on site and/or surrounding residents

Noise & vibration levels from plant and equipment cranes, welders, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible

U

Dam.>$10K to $100K

Material Env. Harm

FrequentUnusual But

Possible

Dam.>$10K to $100K

Material Env. Harm

FrequentRemotely Possible

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

A

Quite Possible

FrequentDam. to $10KEnv. Nuisance

U

Frequent

Dam.>$10K to $100K

Material Env. Harm

UAir pollution - gas cylinder releasesQuite

Possible

Dam.>$100K to $500K

Serious Env. Harm

A

Air pollution - exhaust emissionsRemotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Bechtel Core Process - CP-406 - External Stakeholder

Interaction and Golding Emergency Response Plan and Golding WMS

Dam.>$100K to $500K

Serious Env. Harm

A

Poor public relationsUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. Harm

UConceivable

but Very Unlikely

Occasional

Dam.>$100K to $500K

Serious Env. Harm

UConceivable

but Very Unlikely

OccasionalGolding Emergency Response Plan and

Golding WMS

Unusual But Possible

Loss of human lifeUnusual But

PossibleFrequent

Destruction of buildings from fire U

Dam.>$100K to $500K

Serious Env. Harm

Golding Emergency Response Plan and

Golding WMSFrequent A

Dam.>$100K to $500K

Serious Env. Harm

Remotely Possible

OccasionalConceivable

but Very Unlikely

U

Dam.>$1M to $2M

Serious Env. Harm

Frequent A

Dam.>$1M to $2M

Serious Env. Harm

Occasional

Quite Possible

Frequent

Dam.>$1M to $2M

Serious Env. Harm

Quite Possible

A

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Hydrocarbons entering groundwater degrading water quality

URemotely Possible

Occasional

Dam.>$1M to $2M

Serious Env. Harm

A

URemotely Possible

OccasionalDam. to $10KEnv. Nuisance

Bechtel Core Process - CP-406 - External Stakeholder

Interaction

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan, Bechtel Dangerous Goods

and Hazardous Substances Management Plan, Surface water and

Groundwater Quality Management Plan,

Bechtel Air Quality and Dust Management Plan

and Golding WMS

Transportation of large volumes of hydrocarbons to site

Accident involving transportation of large volume of hydrocarbons to

site

Bechtel Air Quality and Dust Management Plan

and Golding WMS

Bechtel Noise Abatement Management Plan and

Golding WMS

Increased vehicular movements on public roads - poor public relations

Unusual But Possible

OccasionalDam. to $10KEnv. Nuisance

Page 4 of 29

Page 85: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

Hydrocarbon spill during refuelling and maintenance

Wash down of tools, plant and equipment

Hydrocarbons entering land and contaminating soils

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Hydrocarbons entering groundwater degrading water quality

Rain causing overflow from hydrocarbon storage bunds

Poor disposal of regulated Waste

General Waste Disposal

Water Contamination from poor waste disposal practices

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

UBechtel Waste

Management Plan and Golding WMS

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

A

A

Dam.>$10K to $100K

Material Env. U

Dam.>$10K to $100K

Material Env. Harm

U

Dam.>$10K to $100K

Material Env. A

Remotely Possible

FrequentVisual pollution from excess packaging

Quite Possible

FrequentBechtel Waste

Management Plan and

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Dam.>$10K to $100K

Material Env. Harm

U

Quite Possible

Frequent

Land contamination from steel scraps

Land contamination from oily rags and filters

Quite Possible

Frequent

Legal non - compliance

Land contamination from battery acids

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

U

Quite Possible

Frequent U

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Hydrocarbons entering water degrading water quality

Quite Possible

Occasional

Dam.>$100K to $500K

Serious Env. Harm

URemotely Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Hydrocarbons entering land and contaminating soils

Quite Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

A

Occasional

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Occasional

Dam.>$10K to $100K

Material Env. Harm

Occasional

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

OccasionalUnusual But

PossibleRemotely Possible

U

Dam.>$100K to $500K

Serious Env. Harm

FrequentQuite

Possible

Bechtel Waste Management Plan and

Golding WMS

Bechtel Waste Management Plan and

Golding WMS

Bechtel Waste Management Plan and

Golding WMS

Bechtel Waste Management Plan and

Golding WMS

Unusual But Possible

Unusual But Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

Occasional

AURemotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

A

Hydrocarbons entering groundwater degrading water quality

Quite Possible

Frequent

Dam.>$100K to $500K

Serious Env. Harm

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Dam.>$10K to $100K

Material Env. Harm

FrequentRemotely Possible

U

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

A

A

URemotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Quite Possible

Hydrocarbons entering land and contaminating soils

Frequent

Dam.>$10K to $100K

Material Env. Harm

Page 5 of 29

Page 86: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

6Site Office, Crib and Ablution Facilities

Establishment of site workshop covered by clearing and grubbing, earthworks, concrete works and underground services sections

Refer above N/A N/A N/A

Air emissions

Generation of noise

Spill of waste products from ablution facilities

Waste disposal

Paper usage Use of natural resource

Use of electricity

Storage of waste products prior to disposal off site

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

A

Remotely Possible

ContinuousDam. to $10KEnv. Nuisance

A

ADam. to $10KEnv. Nuisance

ContinuousRemotely Possible

Dam. to $10KEnv. Nuisance

U

FrequentDam. to $10KEnv. Nuisance

U

ContinuousDam. to $10KEnv. Nuisance

U

Quite Possible

Continuous

Quite Possible

Surface water pollution (waste paper, food scraps, packaging materials etc)

Green house gas emissions

Feral animal populations increase as a result of feeding from food

Almost Certain

Quite Possible

Remotely Possible

UDam. to $10KEnv. Nuisance

ContinuousBechtel Waste

Management Plan and Golding WMS

ADam. to $10KEnv. Nuisance

Frequent

FrequentDam. to $10KEnv. Nuisance

AContinuousDam. to $10KEnv. Nuisance

URemotely Possible

Bechtel Waste Management Plan and

Golding WMS

Remotely Possible

Wastewaters entering groundwater degrading water quality

Land contamination (waste paper, food scraps, packaging materials etc)

Unusual But Possible

Conceivable but Very Unlikely

U

Dam.>$10K to $100K

Material Env. Harm

Frequent

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

ADam. to $10KEnv. Nuisance

Frequent

FrequentDam. to $10KEnv. Nuisance

AFrequent

Dam.>$10K to $100K

Material Env. Harm

UConceivable

but Very Unlikely

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Unusual But Possible

Wastewaters entering land and contaminating soils

Wastewaters entering surface water degrading water quality and surrounding habitat

Remotely Possible

FrequentRemotely Possible

UFrequent

Dam.>$10K to $100K

Material Env. Harm

ADam. to $10KEnv. Nuisance

Material Env. Harm

U

Dam. to $10KEnv. Nuisance

FrequentQuite

Possible

U

Dam. to $10KEnv. Nuisance

FrequentRemotely Possible

UBechtel Noise Abatement

Management Plan and Golding WMS

A

Dam. to $10KEnv. Nuisance

FrequentRemotely Possible

UBechtel Noise Abatement

Management Plan and Golding WMS

A

A

Remotely Possible

FrequentDam. to $10KEnv. Nuisance

Bechtel Air Quality and Dust Management Plan

and Golding WMS

Air pollution - generator exhaust emissions

Noise levels from generator and is a nuisance to personnel on site and/or nearby residents

Noise levels from generator is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible

FrequentDam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

FrequentQuite

Possible

FrequentRemotely Possible

UDam. to $10KEnv. Nuisance

Material Env. Harm

A

ADam. to $10KEnv. Nuisance

PossibleFrequent

packaging

Poor public relations if housekeeping not up to scratch

PossibleFrequent

FrequentQuite

Possible

Management Plan and Golding WMS

Bechtel Core Process - CP-406 - External Stakeholder

Interaction and Bechtel Waste Management Plan

and Golding WMS

Bechtel Waste Management Plan and

Bechtel Dangerous Goods and Hazardous

Substances Management Plan, Surface water and

Groundwater Quality Management Plan and

Bechtel Waste Management Plan and

Golding WMS

Bechtel Air Quality and Dust Management Plan

and Golding WMS

Page 6 of 29

Page 87: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

Poor housekeeping

7Works in a Marine Environment - Craneage, Refuelling, Maintenance, Ablution Facilities

Plant & Equipment mobilised to site

Air emissions

Generation of noise and vibrations

Sedimentation Dam.>$10K to $100K

Material Env. Harm

U

Dam. to $10KEnv. Nuisance

UDam. to $10KEnv. Nuisance

ARemotely Possible

Frequent

Bechtel Stormwater, Soil Erosion and Sedimentation

Management Plan and Golding WMS

Frequent

Frequent

FrequentRemotely Possible

U

Dam.>$10K to $100K

Material Env. Harm

Bechtel Stormwater, Soil Erosion and Sedimentation

Management Plan and Golding WMS

Quite Possible

Sediment entering surface waters deteriorating water quality

Changes to natural flows causing localised flooding

Quite Possible

Dam. to $10KEnv. Nuisance

A

A

Dam.>$10K to $100K

Material Env. Harm

Remotely Possible

Frequent

Bechtel Stormwater, Soil Erosion and Sedimentation

Management Plan and Golding WMS

Frequent

Frequent

FrequentRemotely Possible

UDam. to $10KEnv. Nuisance

Bechtel Noise Abatement Management Plan and

Golding WMS

Quite Possible

High noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Loss of spoilQuite

Possible

ADam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

FrequentQuite

Possible

High noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or residents

Dam. to $10KEnv. Nuisance

FrequentRemotely Possible

UBechtel Noise Abatement

Management Plan and Golding WMS

A

A

URemotely Possible

FrequentDam. to $10KEnv. Nuisance

Bechtel Air Quality and Dust Management Plan

and Golding WMS

Air pollution - exhaust emissions from plant

Quite Possible

FrequentDam. to $10KEnv. Nuisance

A

Dam.>$10K to $100K

Material Env. Harm

URemotely Possible

FrequentDam. to $10KEnv. Nuisance

Bechtel Core Process - CP-406 - External Stakeholder

Interaction

Wide loads creating traffic hazards on public roads

Quite Possible

FrequentDam. to $10KEnv. Nuisance

Dam.>$10K to $100K

Material Env. Harm

FrequentUnusual But

PossibleIntroduction of fire ants in dirt and soil

FrequentConceivable

but very unlikely

U

A

A

URemotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

Bechtel Weed and Pest Management Plan and

Golding WMS

Introduction of noxious weeds in dirt and soil

Unusual But Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

Remotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Remotely Possible

ContinuousDam. to $10KEnv. Nuisance

ADam. to $10KEnv. Nuisance

Dam.>$10K to $100K

Material Env. Harm

U

U

AEnv. Nuisance

ContinuousPossible

Remotely Possible

ContinuousDam. to $10KEnv. Nuisance

A

Env. NuisanceU

ContinuousDam. to $10KEnv. Nuisance

U

Frequent

Quite Possible

Quite Possible

PossibleContinuous

Continuous

Food scraps and wrappers scattered by birds and animals

Increased odours (human health & hygiene)

Aesthetic appeal not satisfying public perceptions

Quite Possible

as a result of feeding from food scraps

Bechtel Waste Management Plan and

Golding WMS

Bechtel Waste Management Plan and

Golding WMS

Bechtel Weed and Pest Management Plan and

Golding WMS

Management Plan and Golding WMS

Bechtel Waste Management Plan and

Golding WMS

Page 7 of 29

Page 88: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine Facilities Auckland Point - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Residual Risk after ControlsControl Reference

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. HarmDam.>$100K to $500KSerious Env. Harm

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Spill of waste products from ablution facilities

Hydrocarbon spill during refuelling and maintenance

Land disturbance

Waste disposal

Bechtel Soil Contamination Management Plan and

Acid Sulphate Soils Management Plan and

Golding WMS

Remotely Possible

FrequentFrequent

Dam.>$100K to $500K

Serious Env. Harm

U

U

ARemotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

U

Bechtel Marine Fuel and Oil Spill Management Plan,

Surface Water and Groundwater Quality

Management Plan and Golding WMS

U

A

Occasional

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

Frequent

Dam.>$100K to $500K

Serious Env. Harm

URemotely Possible

Bechtel Marine Fuel and Oil Spill Management Plan, Waste Management Plan

and Golding WMS

Disturbance of acid sulphate soilsQuite

Possible

Water pollution from items dropped into the water eg. Off cuts, excess concrete, waste etc

Quite Possible

Spilt wastewaters entering surface water and degrading water quality

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

FrequentRemotely Possible

Hydrocarbons entering groundwater degrading water quality

Quite Possible

Frequent

Dam.>$100K to $500K

Serious Env. Harm

Bechtel Marine Fuel and Oil Spill Management Plan,

Surface Water and Groundwater Quality

Management Plan and Golding WMS

A

A

Dam.>$10K to $100K

Material Env. Harm

Bechtel Marine Fuel and Oil Spill Management Plan,

Surface Water and Groundwater Quality

Management Plan and Golding WMS

Remotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

Dam.>$100K to $500K

Serious Env. Harm

FrequentQuite

Possible

Hydrocarbons entering land and contaminating soils during loading on land

A

AU

Bechtel Marine Fuel and Oil Spill Management Plan,

Surface Water and Groundwater Quality

Management Plan and Golding WMS

Remotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

Hydrocarbons entering surface water degrading water quality

Quite Possible

Frequent

Dam.>$100K to $500K

Serious Env. Harm

Bechtel Marine Fuel and Oil Spill Management Plan,

Surface Water and Groundwater Quality

Management Plan and Golding WMS

Remotely Possible

Frequent

Dam.>$10K to $100K

Material Env. Harm

U

Bechtel Marine Fuel and Oil Spill Management Plan,

Surface Water and Groundwater Quality

Management Plan and Golding WMS

Remotely Possible

FrequentHydrocarbons entering surface water and degrading surrounding habitats

Quite Possible

Frequent

Dam.>$100K to $500K

Serious Env. Harm

U

Dam.>$10K to $100K

Material Env. Harm

A

Page 8 of 29

Page 89: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Non-Marine - Auckland Point Area 1 and 2 Mainland Facilities - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site

Air emissions

Greenhouse gas emissions

Generation of noise and vibration

Erosion and Sedimentation

Importation of fill materials

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc) or vehicular accident

Hydrocarbons entering surface water degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

U Bechtel Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering surface water degrading surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management

Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Hydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management

Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management

Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Spillage on public roads leading to sediment entering waterways

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Stormwater, Soil Erosion and Sedimentation Management Plan and Golding WMS

Remotely Possible

U Bechtel Air Quality and Dust Management Plan and Golding WMSConceivable but Very

UnlikelyFrequentSpillage on public roads creating dust nuisance Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Soil contamination through introduction of contaminated material in imported fill

Unusual But Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Soil Contamination Management Plan and Golding WMSConceivable but Very

Unlikely

U Bechtel Stormwater, Soil Erosion and Sedimentation Management Plan and Golding WMS

Remotely Possible FrequentChanges to natural flows causing localised flooding Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Loss of sediment into surface water degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

U Bechtel Stormwater, Soil Erosion and Sedimentation Management Plan and Golding WMS

Remotely Possible

U Bechtel Stormwater, Soil Erosion and Sedimentation Management Plan and Golding WMS

Remotely Possible FrequentLoss or degradation of soil Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

High noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible FrequentHigh noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or residents

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Air pollution - exhaust emissions from plant Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible FrequentAir pollution - dust from stockpiles Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Air pollution - exhaust emissions and dust from equipment

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

U Bechtel Core Process - CP-406 - External Stakeholder Interaction Unusual but possible FrequentWide loads creating traffic hazards on public roads Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Introduction of fire ants in dirt and soilUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. HarmU Bechtel Weed and Pest Management Plan and Golding WMS

Conceivable but very unlikely

U Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. Harm

Dam.>$100K to $500KSerious Env. Harm

Page 90: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Land disturbance

Stockpiling of material

Pit dewatering leading to scouring

Pit dewatering without testing discharge waters

Damage to sewerage & water mains leading to leakage of waters

Wastewaters entering surface water degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan

and Golding WMSRemotely Possible Frequent

Dam.>$100K to $500K

Serious Env. Harm

A

Wastewaters entering surface water degrading surrounding habitat

Quite Possible FrequentDam.>$500K to $1MSerious Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan

and Golding WMSRemotely Possible Frequent

Dam.>$100K to $500K

Serious Env. Harm

A

Wastewaters entering groundwater degrading water quality

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan

and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Wastewaters entering land and contaminating soils Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan

and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Bitumen and Asphalt Deliveries

3 Concrete Works - MainlandExcavation and backfill covered in earthworks section

Refer above N/A N/A N/A

Occasional

U Bechtel Core Process - CP-406 - External Stakeholder Interaction Remotely PossibleDam. to $10KEnv. Nuisance

A

Dam.>$100K to $500K

Serious Env. Harm

A

Visual pollution from excess bitumen or asphalt Unusual But

PossibleFrequent

Dam. to $10KEnv. Nuisance

U Bechtel Surface Water and Groundwater Quality Management Plan and Golding WMS

Conceivable but Very Unlikely

Occasional

Surface water quality degradation from excess bitumen or asphalt

Unusual But Possible

FrequentDam.>$100K to

$500KSerious Env. Harm

Occasional

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Soil quality degradation from excess bitumen or asphalt

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Soil Contamination Management Plan and Golding WMS Remotely Possible

U Bechtel Core Process - CP-406 - External Stakeholder Interaction Remotely PossibleOccasion

alTraffic problems on public roads Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$100K to $500K

Serious Env. Harm

A

Surface water quality degradation Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

U Bechtel Surface Water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible

U Bechtel Surface Water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible FrequentLegal non compliance Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Unprotected discharge point leading to erosion from water pressure

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Surface Water and Groundwater Quality Management Plan and Golding WMS

Conceivable but Very Unlikely

U Bechtel Soil Contamination Management Plan and Golding WMS Remotely Possible FrequentSoil quality degradation by leaching of sediments (eg. pH changes)

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Water quality degradation by leaching of sediments (eg. p H changes)

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

U Bechtel Surface Water and Groundwater Quality Management Plan and Soil Contamination Management Plan and Golding WMS

Remotely Possible

U Bechtel Soil Contamination Management Plan, Acid Sulphate Soil Management Plan and Golding WMS

Remotely Possible FrequentDisturbance of acid sulphate soils Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Disturbance of contaminated materials (eg. old waste dump etc)

Unusual But Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Soil Contamination Management Plan and Golding WMSConceivable but Very

Unlikely

U Bechtel Unanticipated Discoveries Management Plan and Golding WMS

Conceivable but Very Unlikely

FrequentDamage to cultural heritage sites and artefactsUnusual But

PossibleFrequent

Dam.>$10K to $100KMaterial Env. Harm

Page 91: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Air emissions

Generation of noise and vibration

Concrete trucks delivering to site

Wash down of concrete trucks, tools and equipment

Wastewaters entering soil resulting in contamination

Hydrocarbon spill resulting from equipment failures (burst hoses, leaks etc)

Concrete spill from equipment failures (concrete pump burst, formwork burst etc)

Dam.>$100K to $500K

Serious Env. AU

Bechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

Conceivable but Very Unlikely

FrequentConcrete entering surface waters degrading water quality

Unusual But Possible

Occasional

Dam.>$100K to $500K

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

and Golding WMSRemotely Possible

U Bechtel Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible FrequentHydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering soil resulting in contamination

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible

Dam.>$10K to $100K

Material Env. Harm

A

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

and Golding WMSRemotely Possible Frequent

UBechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

and Golding WMSRemotely Possible Frequent

Wastewaters entering groundwater degrading water quality

Unusual But Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Wastewaters entering surface waters degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

and Golding WMSRemotely Possible

U Bechtel Core Process - CP-406 - External Stakeholder Interaction Remotely Possible FrequentTraffic problems on public roads. Not satisfying public perceptions

Quite Possible FrequentDam. to $10KEnv. Nuisance

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

High noise & vibration levels from nailing guns, jackhammers, concrete pumps, vibrators etc is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible FrequentHigh noise & vibration levels from nailing guns, jackhammers, concrete pumps, vibrators etc is a nuisance to personnel on site and/or residents

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Air pollution - dust particles from saw cutting, jackhammers

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

Air pollution - exhaust emissions from concrete trucks, concrete pumps

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible Frequent

Page 92: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Concrete entering soil resulting in contamination

Waste disposal

Concrete structures reducing the visual amenity of area

4Installation of Underground Services - water, conduits

Excavation, backfill and associated concrete works covered in earthworks and concrete sections

Refer above N/A N/A N/A

Air emissions

Generation of noise and vibration

Dam. to $10KEnv. Nuisance

AU Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible FrequentNoise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to personnel on site and/or nearby residents

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Air pollution - dust from plant and equipment Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible FrequentAir pollution - exhaust emissions from plant and equipment

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Not satisfying public perceptionsUnusual But

PossibleFrequent

Dam. to $10KEnv. Nuisance

U Bechtel Core Process - CP-406 - External Stakeholder Interaction Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentVisual pollution from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Degraded surface water quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

Dam.>$10K to $100K

Material Env. Harm

A

Degraded soil quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Unusual But Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

and Golding WMS

Conceivable but Very Unlikely

Frequent

UBechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

and Golding WMS

Conceivable but Very Unlikely

FrequentConcrete entering groundwater degrading water quality

Unusual But Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$100K to $500K

Serious Env. Harm

A

Serious Env. Harm

A

Concrete entering surface waters degrading surrounding habitat

Unusual But Possible

Occasional

Dam.>$100K to $500K

Serious Env. HarmU

Bechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and Hazardous Substances Management Plan

and Golding WMS

Conceivable but Very Unlikely

U Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

UnlikelyFrequent

quality Possible al$500K

Serious Env. Harm

Page 93: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Delivery of pipes, conduits, sand etc

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Waste disposal

5Plant and equipment maintenance and servicing - Mainland

Establishment of site workshop covered by earthworks, concrete works and underground services sections

Refer above N/A N/A N/A

Occasional

Dam.>$500K to $1M

Serious Env. Harm

A

Dam.>$1M to $2M

Serious Env. Harm

A

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$500K to $1MSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management

Plan, Surface water and Groundwater Quality Management Plan, Golding Emergency Response Plan and Golding WMS

Remotely Possible

UBechtel Dangerous Goods and Hazardous Substances Management

Plan, Surface water and Groundwater Quality Management Plan, Golding Emergency Response Plan and Golding WMS

Remotely PossibleOccasion

alHydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$1M to $2MSerious Env. Harm

Occasional

Dam.>$1M to $2M

Serious Env. Harm

ADam.>$1M to $2MSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management

Plan, Surface water and Groundwater Quality Management Plan, Golding Emergency Response Plan and Golding WMS

Remotely PossibleAccident involving transportation of

large volume of hydrocarbons to site

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible Frequent

Occasional

Dam. to $10KEnv. Nuisance

ADam. to $10KEnv. Nuisance

U Bechtel Core Process - CP-406 - External Stakeholder Interaction Remotely PossibleTransportation of large volumes of

hydrocarbons to siteIncreased vehicular movements on public roads - poor public relations

Unusual But Possible

Occasional

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Visual pollution from excess tape, glues, rubber bands, packaging materials etc

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentDegraded surface water quality from excess tape, glues, rubber bands, packaging materials etc

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam.>$10K to $100K

Material Env. Harm

A

Soil contamination from excess tape, glues, rubber bands, packaging materials etc

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible Frequent

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering soil resulting in contamination

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible

U Bechtel Core Process - CP-406 - External Stakeholder Interaction Remotely Possible FrequentTraffic problems on public roads. Not satisfying public perceptions

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

ANoise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam. to $10KEnv. Nuisance

U CEMP & ECP's - Noise and Vibration Section Remotely Possible

Page 94: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Fire and Explosion

Air emissions

Generation of noise and vibration

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Dam.>$10K to $100K

Material Env. Harm

AUBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible Frequent

Hydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible Frequent

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Noise & vibration levels from plant and equipment cranes, welders, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible FrequentNoise & vibration levels from plant and equipment (cranes, welders, small tools etc) is a nuisance to personnel on site and/or surrounding residents

Unusual But Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Air pollution - gas cylinder releases Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible FrequentAir pollution - dust Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam.>$100K to $500K

Serious Env. Harm

A

Air pollution - exhaust emissions Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

U Bechtel Core Process - CP-406 - External Stakeholder Interaction and Golding Emergency Response Plan and Golding WMS

Conceivable but Very Unlikely

Occasional

Poor public relationsUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. Harm

Occasional

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$100K to $500K

Serious Env. Harm

A

Loss of human lifeUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. HarmU Golding Emergency Response Plan and Golding WMS

Conceivable but Very Unlikely

U Golding Emergency Response Plan and Golding WMSConceivable but Very

UnlikelyOccasion

alDestruction of buildings from fire

Unusual But Possible

FrequentDam.>$100K to

$500KSerious Env. Harm

Page 95: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Hydrocarbon spill during refuelling and maintenance

Wash down of tools, plant and equipment

Hydrocarbons entering land and contaminating soils

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Hydrocarbons entering groundwater degrading water quality

Rain causing overflow from hydrocarbon storage bunds

Poor disposal of regulated Waste

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Land contamination from steel scraps Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentLand contamination from battery acids Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam.>$10K to $100K

Material Env. Harm

A

Legal non - compliance Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

Occasional

Hydrocarbons entering groundwater degrading water quality

Quite PossibleOccasion

al

Dam.>$100K to $500K

Serious Env. Harm

Occasional

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite PossibleOccasion

al

Dam.>$100K to $500K

Serious Env. HarmU

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

A

Hydrocarbons entering land and contaminating soils

Quite PossibleOccasion

alDam.>$10K to $100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

Occasional

A

Unusual But Possible

Occasional

Dam.>$10K to $100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

A

Unusual But Possible

Occasional

Dam.>$10K to $100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

Unusual But Possible

Occasional

Dam.>$10K to $100KMaterial Env. Harm

U

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible Frequent

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

AHydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible

Page 96: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

General Waste Disposal

6Site Office, Crib and Ablution Facilities

Establishment of site workshop covered by clearing and grubbing, earthworks, concrete works and underground

Refer above N/A N/A N/A

Air emissions

Generation of noise

Spill of waste products from ablution facilities

Waste disposal

Dam. to $10KEnv. Nuisance

AU Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentSurface water pollution (waste paper, food scraps, packaging materials etc)

Quite PossibleContinuo

usDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Land contamination (waste paper, food scraps, packaging materials etc)

Unusual But Possible

Continuous

Dam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMS

Conceivable but Very Unlikely

FrequentWastewaters entering groundwater degrading water quality

Remotely Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Wastewaters entering surface water degrading water quality and surrounding habitat

Remotely Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMS

Conceivable but Very Unlikely

UBechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan and

Golding WMSRemotely Possible FrequentWastewaters entering land and contaminating soils

Unusual But Possible

FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Noise levels from generator is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible

U Bechtel Noise Abatement Management Plan and Golding WMS Remotely Possible FrequentNoise levels from generator and is a nuisance to personnel on site and/or nearby residents

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Air pollution - generator exhaust emissions Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

U Bechtel Core Process - CP-406 - External Stakeholder Interaction and Bechtel Waste Management Plan and Golding WMS

Remotely Possible FrequentPoor public relations if housekeeping not up to scratch

Quite Possible FrequentDam. to $10KEnv. Nuisance

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Visual pollution from excess packaging Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentLand contamination from oily rags and filters Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

FrequentEnv. Nuisance

ALand contamination from steel scraps Quite Possible FrequentMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

Page 97: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site Dam. to $10K

Env. NuisanceAU Bechtel Weed and Pest Management Plan and Golding WMS Remotely Possible FrequentIntroduction of noxious weeds in dirt and soil Quite Possible Frequent

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Paper usage Use of natural resource

Use of electricity

Storage of waste products prior to disposal off site

Poor housekeeping

U Bechtel Waste Management Plan and Golding WMS Remotely Possible Frequent

Dam. to $10KEnv. Nuisance

A

Aesthetic appeal not satisfying public perceptions Quite Possible FrequentDam.>$10K to $100KMaterial Env. Harm

Dam.>$10K to $100K

Material Env. Harm

A

U Bechtel Waste Management Plan and Golding WMS Remotely PossibleContinuou

sIncreased odours (human health & hygiene) Quite Possible

Continuous

Dam. to $10KEnv. Nuisance

Continuous

Dam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Food scraps and wrappers scattered by birds and animals

Quite PossibleContinuo

usDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely PossibleContinuou

sFeral animal populations increase as a result of feeding from food scraps

Quite PossibleContinuo

usDam. to $10KEnv. Nuisance

Continuous

Dam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Green house gas emissions Almost CertainContinuo

usDam. to $10KEnv. Nuisance

U Bechtel Air Quality and Dust Management Plan and Golding WMS Remotely Possible

Env. NuisanceA

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible Frequent

U Bechtel Waste Management Plan and Golding WMS Remotely Possible Frequentpackaging materials etc)

Quite Possibleus Env. Nuisance

Page 98: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Marine - RG Tanna Facilities - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

1 Mobilisation Plant & Equipment mobilised to site

Air emissions

Greenhouse gas emissions

Generation of noise and vibration

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Hydrocarbons entering water degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Remotely Possible FrequentDam.>$10K to

$100KMaterial Env.

A

Hydrocarbons entering surface water degrading surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Remotely Possible FrequentDam.>$10K to

$100KMaterial Env.

A

2 Piling in Marine Environment Plant & Equipment mobilised to site

Greenhouse gas emissions

Generation of noise and vibration

Frequent

Dam.>$10K to $100K

Material Env. A

Dam. to $10KEnv. Nuisance

A

Vibrations may cause structural damage to adjacent buildings

Unusual But Possible

FrequentDam.>$10K to

$100K UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

High noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

High noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or surrounding residents

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible Frequent

Air pollution - exhaust emissions from plant

Almost Certain FrequentDam. to $10KEnv. Nuisance

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Introduction of fire ants in dirt and soilUnusual But

PossibleFrequent

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Weed and Pest Management Plan and Golding WMS

Conceivable but Very Unlikely

UBechtel Weed and Pest Management Plan and

Golding WMSRemotely Possible Frequent

Introduction of noxious weeds in dirt and soil

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Disturbance of acid sulphate soils Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Soil Contamination Management Plan,

Acid Sulphate Soil Management Plan and Golding WMS

Remotely Possible

UBechtel Soil Contamination Management Plan

and Golding WMSConceivable but Very

UnlikelyFrequent

Disturbance of contaminated materials (eg. Tributyl Tin Deposits)

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

AUBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

High noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

High noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or residents

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible Frequent

Air pollution - exhaust emissions from plant

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Air pollution - exhaust emissions and dust from equipment

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible

UBechtel Core Process - CP-406 - External

Stakeholder InteractionUnusual but possible Frequent

Wide loads creating traffic hazards on public roads

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Introduction of fire ants in dirt and soilUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. HarmU

Bechtel Weed and Pest Management Plan and Golding WMS

Conceivable but very unlikely

UBechtel Weed and Pest Management Plan and

Golding WMSRemotely Possible Frequent

Introduction of noxious weeds in dirt and soil

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. Harm

Dam.>$100K to $500KSerious Env. Harm

Page 99: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Concrete spill from equipment failures (concrete pump burst, formwork burst etc)

Concrete entering groundwater degrading water quality

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and

Conceivable but Very Unlikely

FrequentDam.>$10K to

$100KMaterial Env.

A

Waste disposal

Concrete structures reducing the visual amenity of area

4Installation of Underground Services - water, conduits

Excavation, backfill and associated concrete works covered in earthworks and concrete sections

Refer above N/A N/A N/A

Air emissions

Generation of noise and vibration

Delivery of pipes, conduits, sand etc

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

UBechtel Core Process - CP-406 - External

Stakeholder InteractionRemotely Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Core Process - CP-406 - External

Stakeholder Interaction

Not satisfying public perceptionsUnusual But

PossibleFrequent

Dam. to $10KEnv. Nuisance

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

Dam. to $10KEnv. Nuisance

Visual pollution from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Degraded surface water quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Degraded soil quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentMaterial Env.

Harm

Adamage to adjacent buildings Possible

Frequent $100KMaterial Env. Harm

Uand Golding WMS

Remotely Possible

Hydrocarbons entering soil resulting in contamination

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

A

U CEMP & ECP's - Noise and Vibration Section Remotely Possible Frequent

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

ATraffic problems on public roads. Not satisfying public perceptions

Quite Possible

Dam. to $10KEnv. Nuisance

A

Noise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

AUBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

Noise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to personnel on site and/or nearby residents

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Air pollution - dust from plant and equipment

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible Frequent

Air pollution - exhaust emissions from plant and equipment

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Frequent

Dam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

A

Dam.>$100K to $500K

Serious Env. Harm

AU

Bechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and

Hazardous Substances Management Plan and Golding WMS

Conceivable but Very Unlikely

FrequentConcrete entering surface waters degrading surrounding habitat

Unusual But Possible

Occasional

Dam.>$100K to $500K

Serious Env. Harm

Frequent

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Concrete entering surface waters degrading water quality

Unusual But Possible

Occasional

Dam.>$100K to $500K

Serious Env. HarmU

Bechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and

Hazardous Substances Management Plan and Golding WMS

Conceivable but Very Unlikely

U

Bechtel Surface Water and Groundwater Quality Management Plan, Dangerous Goods and

Hazardous Substances Management Plan and Golding WMS

Remotely Possible FrequentWastewaters entering groundwater degrading water quality

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Remotely Possible

UBechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Remotely Possible FrequentHydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv. Nuisance

A

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous

Substances Management Plan and Golding WMS

Remotely Possible

UBechtel Core Process - CP-406 - External

Stakeholder InteractionRemotely Possible FrequentNot satisfying public perceptions Quite Possible Frequent

Dam. to $10KEnv. Nuisance

Page 100: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Waste disposal

5Plant and equipment maintenance and servicing - Marine works

Establishment of site workshop covered by earthworks, concrete works and underground services

Refer above N/A N/A N/A

Fire and Explosion

Air emissions

Generation of noise and vibration

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Hydrocarbon spill during refuelling and maintenance

Noise & vibration levels from plant and equipment cranes, welders, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Noise & vibration levels from plant and equipment (cranes, welders, small tools etc) is a nuisance to personnel on site and/or surrounding residents

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

Dam. to $10KEnv. Nuisance

Dam.>$100K to $500K

Serious Env. Harm

FrequentDam. to $10KEnv. Nuisance

UBechtel Air Quality and Dust Management Plan

and Golding WMS

Remotely Possible

Loss of human lifeUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. HarmU

Golding Emergency Response Plan and Golding WMS

Conceivable but Very Unlikely

Occasional

FrequentDam.>$1M to $2MSerious Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan,

Golding Emergency Response Plan and Golding WMS

Transportation of large volumes of hydrocarbons to site

Accident involving transportation of large volume of hydrocarbons to site

Hydrocarbons entering groundwater degrading water quality

Quite Possible

Dam.>$10K to $100K

Material Env. Harm

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Waste Management Plan and Golding

WMS

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible FrequentHydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible FrequentHydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible Frequent

U

A

ABechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

Dam. to $10KEnv. Nuisance

A

Air pollution - gas cylinder releases Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible Frequent

Dam.>$100K to $500K

Serious Env. Harm

Dam.>$10K to $100K

Material Env. Harm

A

UBechtel Core Process - CP-406 - External

Stakeholder Interaction and Golding Emergency Response Plan and Golding WMS

Conceivable but Very Unlikely

Occasional

Remotely Possible FrequentDam. to $10KEnv. Nuisance

Air pollution - exhaust emissions Quite Possible

A

Dam.>$100K to $500K

Serious Env. Harm

APoor public relationsUnusual But

PossibleFrequent

UGolding Emergency Response Plan and

Golding WMSConceivable but Very

UnlikelyOccasiona

lDestruction of buildings from fire

Unusual But Possible

FrequentDam.>$100K to

$500KSerious Env. Harm

Occasional

Dam.>$1M to $2M

Serious Env. Harm

A

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$1M to $2M

Serious Env. Harm

AU

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan,

Golding Emergency Response Plan and Golding WMS

Remotely PossibleOccasiona

l

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$1M to $2MSerious Env. Harm

Occasional

Dam. to $10KEnv. Nuisance

AIncreased vehicular movements on public roads - poor public relations

Unusual But Possible

Occasional

Dam. to $10KEnv. Nuisance

UBechtel Core Process - CP-406 - External

Stakeholder InteractionRemotely Possible

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

A

FrequentVisual pollution from excess tape, glues, rubber bands, packaging materials etc

Quite Possible FrequentDam. to $10KEnv. Nuisance

Dam.>$10K to $100K

Material Env. Harm

Dam. to $10KEnv. Nuisance

A

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Remotely Possible FrequentDam. to $10KEnv. Nuisance

Degraded surface water quality from excess tape, glues, rubber bands, packaging materials etc

Quite Possible

A

Dam. to $10KEnv. Nuisance

ASoil contamination from excess tape, glues, rubber bands, packaging materials etc

Quite Possible Frequent

Page 101: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Wash down of tools, plant and equipment

Hydrocarbons entering land and contaminating soils

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Hydrocarbons entering groundwater degrading water quality

Rain causing overflow from hydrocarbon storage bunds

Poor disposal of regulated Waste

General Waste Disposal

6Site Office, Crib and Ablution Facilities

Establishment of site workshop covered by clearing and grubbing, earthworks, concrete works and

Refer above N/A N/A N/A

Air emissions

Generation of noise

Spill of waste products from ablution facilities Dam. to $10K

Env. NuisanceA

Frequent

Wastewaters entering land and contaminating soils

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible Frequent

Dam. to $10KEnv. Nuisance

A

Air pollution - generator exhaust emissions

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible

Bechtel Waste Management Plan and Golding WMS

Land contamination from oily rags and filters

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Legal non - compliance Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Dam. to $10KEnv. Nuisance

Conceivable but Very Unlikely

FrequentDam. to $10KEnv. Nuisance

AWastewaters entering surface water degrading water quality and

Remotely Possible

FrequentDam.>$10K to

$100K U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

Noise levels from generator is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

Dam. to $10KEnv. Nuisance

A

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

Dam. to $10KEnv. Nuisance

ANoise levels from generator and is a nuisance to personnel on site and/or nearby residents

Quite Possible FrequentDam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

AUBechtel Core Process - CP-406 - External Stakeholder Interaction and Bechtel Waste

Management Plan and Golding WMSRemotely Possible Frequent

Poor public relations if housekeeping not up to scratch

Quite Possible FrequentDam. to $10KEnv. Nuisance

Frequent

Dam.>$10K to $100K

Material Env. Harm

AVisual pollution from excess packaging Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

A

FrequentLand contamination from steel scraps Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

FrequentDam.>$10K to

$100KMaterial Env. Harm

U

Dam.>$10K to $100K

Material Env. Harm

Dam. to $10KEnv. Nuisance

A

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Remotely Possible FrequentDam. to $10KEnv. Nuisance

Water Contamination from poor waste disposal practices

Quite Possible

A

Dam. to $10KEnv. Nuisance

ALand contamination from battery acids Quite Possible Frequent

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely PossibleOccasiona

l

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering water degrading water quality

Quite PossibleOccasion

al

Dam.>$100K to $500K

Serious Env. Harm

Dam.>$10K to $100K

Material Env. Harm

A

A

Hydrocarbons entering land and contaminating soils

Quite PossibleOccasion

al

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely PossibleOccasiona

l

A

Unusual But Possible

Occasional

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely PossibleOccasiona

l

Dam.>$10K to $100K

Material Env. Harm

A

Unusual But Possible

Occasional

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely PossibleOccasiona

l

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely PossibleOccasiona

l

Dam.>$10K to $100K

Material Env. Harm

Unusual But Possible

Occasional

Dam.>$10K to $100K

Material Env. HarmU

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Hydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Remotely Possible FrequentHydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Page 102: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Waste disposal

Paper usage Use of natural resource

Use of electricity

Storage of waste products prior to disposal off site

Poor housekeeping

7Works in a Marine Environment - Craneage, Refuelling, Maintenance, Ablution Facilities

Plant & Equipment mobilised to site

Air emissions

Generation of noise and vibrations

Sedimentation

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Dam.>$10K to $100K

Material Env. A

A

Hydrocarbons entering land and contaminating soils during loading on Quite Possible Frequent

Dam.>$10K to $100K U

Bechtel Marine Fuel and Oil Spill Management Plan, Surface Water and Groundwater Quality Remotely Possible Frequent

Changes to natural flows causing localised flooding

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Stormwater, Soil Erosion and

Sedimentation Management Plan and Golding WMS

Remotely Possible FrequentDam. to $10KEnv. Nuisance

Dam. to $10KEnv. Nuisance

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Stormwater, Soil Erosion and

Sedimentation Management Plan and Golding WMS

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

High noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or residents

Quite Possible FrequentDam. to $10KEnv. Nuisance

A

Wide loads creating traffic hazards on public roads

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Core Process - CP-406 - External

Stakeholder InteractionRemotely Possible

Introduction of fire ants in dirt and soilUnusual But

PossibleFrequent

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Weed and Pest Management Plan and Golding WMS

Conceivable but very unlikely

A

Sediment entering surface waters deteriorating water quality

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Stormwater, Soil Erosion and

Sedimentation Management Plan and Golding WMS

Remotely Possible Frequent

Dam. to $10KEnv. Nuisance

Dam.>$10K to $100K

Material Env. Harm

A

UBechtel Noise Abatement Management Plan

and Golding WMSRemotely Possible Frequent

Remotely Possible FrequentDam. to $10KEnv. Nuisance

Loss of spoil Quite Possible

A

Dam. to $10KEnv. Nuisance

AHigh noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible Frequent

Air pollution - exhaust emissions from plant

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible Frequent

Dam. to $10KEnv. Nuisance

A

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

FrequentDam. to $10KEnv. Nuisance

A

Frequent

Dam.>$10K to $100K

Material Env. Harm

Dam.>$10K to $100K

Material Env. Harm

A

Introduction of noxious weeds in dirt and soil

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Weed and Pest Management Plan and

Golding WMSRemotely Possible

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Aesthetic appeal not satisfying public perceptions

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Continuous

Dam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Increased odours (human health & hygiene)

Quite PossibleContinuo

usDam. to $10KEnv. Nuisance

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

Continuous

Food scraps and wrappers scattered by birds and animals

Quite PossibleContinuo

usDam. to $10KEnv. Nuisance

Continuous

Dam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Feral animal populations increase as a result of feeding from food scraps

Quite PossibleContinuo

usDam. to $10KEnv. Nuisance

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

UBechtel Air Quality and Dust Management Plan

and Golding WMSRemotely Possible

Continuous

Green house gas emissions Almost CertainContinuo

usDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

UBechtel Waste Management Plan and Golding

WMSRemotely Possible Frequent

Surface water pollution (waste paper, food scraps, packaging materials etc)

Quite PossibleContinuo

usDam. to $10KEnv. Nuisance

FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv. Nuisance

A

Land contamination (waste paper, food scraps, packaging materials etc)

Unusual But Possible

Continuous

Dam. to $10KEnv. Nuisance

UBechtel Waste Management Plan and Golding

WMSRemotely Possible

Wastewaters entering groundwater degrading water quality

Remotely Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater Quality Management Plan

and Golding WMS

Conceivable but Very Unlikely

Frequent

UnlikelyFrequent

Env. NuisanceAdegrading water quality and

surrounding habitatPossible

Frequent $100KMaterial Env. Harm

Uand Groundwater Quality Management Plan

and Golding WMS

Page 103: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure Consquences Risk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Spill of waste products from ablution facilities

Hydrocarbon spill during refuelling and maintenance

Land disturbance

Waste disposal

UBechtel Soil Contamination Management Plan and Acid Sulphate Soils Management Plan and

Golding WMSRemotely Possible FrequentDisturbance of acid sulphate soils Quite Possible Frequent

Dam.>$100K to $500K

Serious Env. Harm

Remotely Possible Frequent

FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Marine Fuel and Oil Spill Management Plan, Surface Water and Groundwater Quality

Management Plan and Golding WMS

FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Marine Fuel and Oil Spill Management Plan, Surface Water and Groundwater Quality

Management Plan and Golding WMS

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Material Env. Harm

A

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Marine Fuel and Oil Spill Management Plan, Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible

contaminating soils during loading on land

Quite Possible Frequent $100KMaterial Env. Harm

U Plan, Surface Water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible Frequent

UBechtel Marine Fuel and Oil Spill Management

Plan, Waste Management Plan and Golding WMS

Remotely PossibleOccasiona

l

Water pollution from items dropped into the water eg. Off cuts, excess concrete, waste etc

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

Hydrocarbons entering surface water and degrading surrounding habitats

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Marine Fuel and Oil Spill Management Plan, Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

A

UBechtel Marine Fuel and Oil Spill Management Plan, Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible Frequent

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

AHydrocarbons entering surface water degrading water quality

Quite Possible

Dam.>$10K to $100K

Material Env. Harm

A

Spilt wastewaters entering surface water and degrading water quality

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Hydrocarbons entering groundwater degrading water quality

Quite Possible

Dam.>$10K to $100K

Material Env. Harm

A

Page 104: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

GOLDING CONTRACTORS PTY LTDCTR86 Rev 01 Probability Exposure Consequences

A.B.N. 88 009 734 794 Risk Score GC-3-13-03 Almost Certain Very Rare

ENVIRONMENTAL RISK REGISTER Legend: U Unacceptable Risk - implement controls and reassess Quite Possible Rare

A Acceptable Risk - no additional controls necessary Unusual But Possible Infrequent

Site / Project / Location: QCLNG Non-Marine - RG Tanna Mainland Facilities - Risk Register Remotely Possible Occasional

Conceivable but Very Unlikely Frequent

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure ConsquencesRisk Score

1Earthworks / Roadworks / Excavation for concrete works / Trench Excavation / Backfill

Plant & Equipment mobilised to site

Air emissions

Greenhouse gas emissions

Generation of noise and vibration

Erosion and Sedimentation

Importation of fill materials

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc) or vehicular accident

Hydrocarbons entering surface water degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Hydrocarbons entering surface water degrading surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Hydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv.

NuisanceA

Spillage on public roads leading to sediment entering waterways

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Stormwater, Soil Erosion and Sedimentation

Management Plan and Golding WMSRemotely Possible

UBechtel Air Quality and Dust Management Plan and

Golding WMSConceivable but

Very UnlikelyFrequent

Spillage on public roads creating dust nuisance

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Soil contamination through introduction of contaminated material in imported fill

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Soil Contamination Management Plan and

Golding WMSConceivable but

Very Unlikely

UBechtel Stormwater, Soil Erosion and Sedimentation

Management Plan and Golding WMSRemotely Possible Frequent

Changes to natural flows causing localised flooding

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Loss of sediment into surface water degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Stormwater, Soil Erosion and Sedimentation

Management Plan and Golding WMSRemotely Possible

UBechtel Stormwater, Soil Erosion and Sedimentation

Management Plan and Golding WMSRemotely Possible FrequentLoss or degradation of soil Quite Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

High noise & vibration levels from plant and equipment is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Noise Abatement Management Plan and

Golding WMSRemotely Possible

UBechtel Noise Abatement Management Plan and

Golding WMSRemotely Possible Frequent

High noise & vibration levels from plant and equipment is a nuisance to personnel on site and/or residents

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Air pollution - exhaust emissions from plant

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible FrequentAir pollution - dust from stockpiles Quite Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Air pollution - exhaust emissions and dust from equipment

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible

UBechtel Core Process - CP-406 - External Stakeholder

InteractionUnusual but

possibleFrequent

Wide loads creating traffic hazards on public roads

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv.

NuisanceA

Introduction of fire ants in dirt and soilUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. HarmU

Bechtel Weed and Pest Management Plan and Golding WMS

Conceivable but very unlikely

UBechtel Weed and Pest Management Plan and Golding

WMSRemotely Possible Frequent

Introduction of noxious weeds in dirt and soil

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Dam.>$10K to $100KMaterial Env. Harm

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Dam.>$2MSerious Env. Harm

Dam.>$1M to $2MSerious Env. Harm

Dam.>$500K to $1MSerious Env. Harm

Dam.>$100K to $500KSerious Env. Harm

Page 105: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure ConsquencesRisk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Land disturbance

Stockpiling of material

Pit dewatering leading to scouring

Pit dewatering without testing discharge waters

Damage to sewerage & water mains leading to leakage of waters

Wastewaters entering surface water degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$100K to $500K

Serious Env. A

Wastewaters entering surface water degrading surrounding habitat

Quite Possible FrequentDam.>$500K to

$1MSerious Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$100K to $500K

Serious Env. A

Wastewaters entering groundwater degrading water quality

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Wastewaters entering land and contaminating soils

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. A

Bitumen and Asphalt Deliveries

3 Concrete Works - MainlandExcavation and backfill covered in earthworks section

Refer above N/A N/A N/A

Air emissions

Generation of noise and vibration Dam.>$10K to $100K

Material Env. Harm

UBechtel Noise Abatement Management Plan and

Golding WMSRemotely Possible Frequent

High noise & vibration levels from nailing guns, jackhammers, concrete pumps, vibrators etc is a nuisance to personnel on site and/or residents

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Noise Abatement Management Plan and Golding WMS

Remotely Possible Frequent

A

Dam.>$10K to $100K

Material Env. Harm

A

High noise & vibration levels from nailing guns, jackhammers, concrete pumps, vibrators etc is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible Frequent

Air pollution - dust particles from saw cutting, jackhammers

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible Frequent

Dam. to $10KEnv.

NuisanceA

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible Frequent

Dam. to $10KEnv.

NuisanceA

Air pollution - exhaust emissions from concrete trucks, concrete pumps

Quite Possible FrequentDam. to $10KEnv. Nuisance

Occasional

Dam. to $10KEnv.

NuisanceA

Dam.>$100K to $500K

Serious Env. Harm

A

Visual pollution from excess bitumen or asphalt

Unusual But Possible

FrequentDam. to $10KEnv. Nuisance

UBechtel Core Process - CP-406 - External Stakeholder

InteractionRemotely Possible

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSConceivable but

Very UnlikelyOccasiona

lSurface water quality degradation from excess bitumen or asphalt

Unusual But Possible

FrequentDam.>$100K to

$500KSerious Env. Harm

Occasional

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Soil quality degradation from excess bitumen or asphalt

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Soil Contamination Management Plan and

Golding WMSRemotely Possible

UBechtel Core Process - CP-406 - External Stakeholder

InteractionRemotely Possible

Occasional

Traffic problems on public roads Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$100K to $500K

Serious Env. Harm

A

Surface water quality degradation Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSRemotely Possible FrequentLegal non compliance Quite Possible Frequent

Dam.>$100K to $500K

Serious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Unprotected discharge point leading to erosion from water pressure

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan and Golding WMSConceivable but

Very Unlikely

UBechtel Soil Contamination Management Plan and

Golding WMSRemotely Possible Frequent

Soil quality degradation by leaching of sediments (eg. pH changes)

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

Water quality degradation by leaching of sediments (eg. p H changes)

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan and Soil Contamination Management Plan and Golding WMS

Remotely Possible

UBechtel Soil Contamination Management Plan, Acid Sulphate Soil Management Plan and Golding WMS

Remotely Possible FrequentDisturbance of acid sulphate soils Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam. to $10KEnv.

NuisanceA

Disturbance of contaminated materials (eg. old waste dump etc)

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Soil Contamination Management Plan and

Golding WMSConceivable but

Very Unlikely

UBechtel Unanticipated Discoveries Management Plan

and Golding WMSConceivable but

Very UnlikelyFrequent

Damage to cultural heritage sites and artefacts

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

Page 106: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure ConsquencesRisk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Concrete trucks delivering to site

Wash down of concrete trucks, tools and equipment

Wastewaters entering soil resulting in contamination

Hydrocarbon spill resulting from equipment failures (burst hoses, leaks etc)

Concrete spill from equipment failures (concrete pump burst, formwork burst etc)

Concrete entering soil resulting in contamination

Waste disposal

Concrete structures reducing the visual amenity of area

4Installation of Underground Services - water, conduits

Excavation, backfill and associated concrete works covered in earthworks and concrete sections

Refer above N/A N/A N/A

Air emissions

Generation of noise and vibration

UBechtel Noise Abatement Management Plan and

Golding WMSRemotely Possible Frequent

Noise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to personnel on site and/or

Quite Possible FrequentDam. to $10KEnv. Nuisance

A

Not satisfying public perceptions

Air pollution - exhaust emissions from plant and equipment

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible

Hydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

Wastewaters entering groundwater degrading water quality

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

FrequentDam. to $10KEnv. Nuisance

UBechtel Core Process - CP-406 - External Stakeholder

Interaction

ADam. to $10K

Env.

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible Frequent

Air pollution - dust from plant and equipment

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

ABechtel Core Process - CP-406 - External Stakeholder

InteractionRemotely Possible Frequent

Dam. to $10KEnv.

Nuisance

Unusual But Possible

FrequentDam. to $10KEnv. Nuisance

U

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Visual pollution from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentDegraded surface water quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10K

Env. Nuisance

A

Dam.>$10K to $100K

Material Env. Harm

A

Degraded soil quality from excess concrete, reo, nails, formwork, packaging materials

Quite Possible FrequentDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Conceivable but Very Unlikely

FrequentUnusual But

PossibleFrequent

Dam.>$10K to $100K

Material Env. Harm

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$100K to $500K

Serious Env. Harm

A

Concrete entering groundwater degrading water quality

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Conceivable but Very Unlikely

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Conceivable but Very Unlikely

FrequentConcrete entering surface waters degrading surrounding habitat

Unusual But Possible

OccasionalDam.>$100K to

$500KSerious Env. Harm

Frequent

Dam.>$100K to $500K

Serious Env. Harm

AConcrete entering surface waters degrading water quality

Unusual But Possible

OccasionalDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Conceivable but Very Unlikely

UBechtel Dangerous Goods and Hazardous Substances

Management Plan and Golding WMSRemotely Possible Frequent

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible

Dam.>$10K to $100K

Material Env. Harm

A

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible Frequent

Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Hydrocarbons entering soil resulting in contamination

Quite Possible Frequent

A

Dam.>$10K to $100K

Material Env. Harm

A

A

Wastewaters entering surface waters degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Surface Water and Groundwater Quality

Management Plan, Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

A

Remotely Possible FrequentDam. to $10K

Env. Nuisance

Traffic problems on public roads. Not satisfying public perceptions

Quite Possible

Page 107: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure ConsquencesRisk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Delivery of pipes, conduits, sand etc

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Waste disposal

5Plant and equipment maintenance and servicing - Mainland

Establishment of site workshop covered by earthworks, concrete works and underground services sections

Refer above N/A N/A N/A

Fire and Explosion

Air emissions

UBechtel Core Process - CP-406 - External Stakeholder

Interaction and Golding Emergency Response Plan and Golding WMS

Conceivable but Very Unlikely

Occasional

Poor public relationsUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. Harm

A

Destruction of buildings from fireUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. HarmU Golding Emergency Response Plan and Golding WMS

Conceivable but Very Unlikely

Hydrocarbons entering soil resulting in contamination

Transportation of large volumes of hydrocarbons to site

Accident involving transportation of large volume of hydrocarbons to site

Dam.>$1M to $2M

Serious Env. Harm

AOccasiona

l

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible

UGolding WMS

Remotely Possible Frequentnuisance to personnel on site and/or nearby residents

Quite Possible FrequentEnv. Nuisance

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

AAir pollution - gas cylinder releases Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

FrequentDam. to $10KEnv. Nuisance

UBechtel Air Quality and Dust Management Plan and

Golding WMS

Frequent

FrequentDam. to $10K

Env. Nuisance

ARemotely Possible

Air pollution - exhaust emissions Quite Possible FrequentDam. to $10KEnv. Nuisance

Air pollution - dust Quite Possible

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible

A

Dam. to $10KEnv.

NuisanceA

Dam.>$100K to $500K

Serious Env. Harm

Loss of human lifeUnusual But

PossibleFrequent

Dam.>$100K to $500K

Serious Env. HarmU Golding Emergency Response Plan and Golding WMS

Conceivable but Very Unlikely

Occasional

Dam.>$100K to $500K

Serious Env. Harm

A

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater

Quality Management Plan, Golding Emergency Response Plan and Golding WMS

Remotely PossibleOccasiona

l

Occasional

Dam.>$100K to $500K

Serious Env. Harm

A

Dam.>$500K to $1M

Serious Env. Harm

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$500K to

$1MSerious Env. Harm

Occasional

Dam.>$1M to $2M

Serious Env. Harm

AHydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$1M to $2MSerious Env. Harm

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater

Quality Management Plan, Golding Emergency Response Plan and Golding WMS

Remotely Possible

U

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater

Quality Management Plan, Golding Emergency Response Plan and Golding WMS

Remotely PossibleFrequentDam.>$1M to $2MSerious Env. Harm

Occasional

Dam. to $10KEnv.

NuisanceU

Bechtel Core Process - CP-406 - External Stakeholder Interaction

Remotely Possible A

Dam. to $10KEnv.

NuisanceA

Increased vehicular movements on public roads - poor public relations

Unusual But Possible

OccasionalDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentVisual pollution from excess tape, glues, rubber bands, packaging materials etc

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Degraded surface water quality from excess tape, glues, rubber bands, packaging materials etc

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

A

Soil contamination from excess tape, glues, rubber bands, packaging materials etc

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible Frequent

A

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

Bechtel Dangerous Goods and Hazardous Substances Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

U

Frequent

Dam.>$10K to $100K

Material Env. Harm

ATraffic problems on public roads. Not satisfying public perceptions

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Core Process - CP-406 - External Stakeholder

InteractionRemotely Possible

U CEMP & ECP's - Noise and Vibration Section Remotely Possible Frequent

Noise & vibration levels from plant and equipment (cranes, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Env. Nuisance

Page 108: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure ConsquencesRisk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

Generation of noise and vibration

Hydrocarbon spill resulting from equipment failures (eg. burst hoses, leaks etc)

Hydrocarbon spill during refuelling and maintenance

Wash down of tools, plant and equipmentHydrocarbons entering land and contaminating soils

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Hydrocarbons entering groundwater degrading water quality

Rain causing overflow from hydrocarbon storage bunds

Poor disposal of regulated Waste

General Waste Disposal

Dam.>$10K to $100K

Material Env. Harm

AOccasionalDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Dam.>$10K to $100K

Material Env.

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater

Quality Management Plan and Golding WMSRemotely Possible

Occasional

Dam.>$10K to $100K

Material Env. Harm

Unusual But Possible

OccasionalDam.>$10K to

$100KMaterial Env. Harm

U

Dam.>$10K to $100K

Material Env. HarmU

Bechtel Dangerous Goods and Hazardous Substances Management Plan, Surface water and Groundwater

Quality Management Plan and Golding WMSRemotely Possible

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

Dam.>$10K to $100K

Material Env. Harm

FrequentDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible FrequentHydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Noise & vibration levels from plant and equipment cranes, welders, small tools etc) is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Noise Abatement Management Plan and

Golding WMSRemotely Possible Frequent

Remotely Possible FrequentDam. to $10K

Env. Nuisance

A

Noise & vibration levels from plant and equipment (cranes, welders, small tools etc) is a nuisance to personnel on site and/or surrounding residents

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

AU Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentVisual pollution from excess packaging Quite Possible FrequentDam.>$10K to

$100K

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Land contamination from oily rags and filters

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentLand contamination from steel scraps Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Land contamination from battery acids Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentLegal non - compliance Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Occasional

Dam.>$10K to $100K

Material Env. Harm

AHydrocarbons entering groundwater degrading water quality

Quite Possible OccasionalDam.>$100K to

$500KSerious Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely PossibleOccasiona

l

Remotely PossibleOccasiona

l

Hydrocarbons entering land and contaminating soils

Quite Possible OccasionalDam.>$10K to

$100KMaterial Env. Harm

Hydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible

Dam.>$10K to $100K

Material Env. Harm

A

A

Unusual But Possible

OccasionalDam.>$10K to

$100KMaterial Env. Harm

Occasional

Unusual But Possible

Occasional

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely PossibleOccasiona

l

Dam.>$10K to $100K

Material Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible FrequentHydrocarbons entering groundwater degrading water quality

Quite Possible FrequentDam.>$100K to

$500KSerious Env. Harm

A

Dam.>$10K to $100K

Material Env. Harm

A

A

Hydrocarbons entering land and contaminating soils

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible Frequent

Dam.>$100K to $500K

Serious Env. Harm

Dam.>$10K to $100K

Material Env. Harm

A

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible Frequent

Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

Hydrocarbons entering groundwater degrading water quality

Quite Possible

A

Dam.>$10K to $100K

Material Env. Harm

AHydrocarbons entering surface water degrading water quality and surrounding habitat

Quite Possible Frequent

Dam. to $10KEnv.

NuisanceA

UBechtel Noise Abatement Management Plan and

Golding WMS

Page 109: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Impacts and Risk Assessment Practically impossible Continuous

No. Activity Aspect Impact Comments

Probability Exposure Consquences Risk Score Probability Exposure ConsquencesRisk Score

Dam. to $10KEnv. Nuisance

Significance of Risk Control Reference Residual Risk after Controls

6Site Office, Crib and Ablution Facilities

Establishment of site workshop covered by clearing and grubbing, earthworks, concrete works and underground services sections

Refer above N/A N/A N/A

Air emissions

Generation of noise

Spill of waste products from ablution facilities

Waste disposal

Paper usage Use of natural resource

Use of electricity

Storage of waste products prior to disposal off site

Poor housekeeping

U Bechtel Waste Management Plan and Golding WMS Remotely PossibleContinuou

s

Dam. to $10KEnv.

NuisanceA

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible

Feral animal populations increase as a result of feeding from food scraps

Quite Possible ContinuousDam. to $10KEnv. Nuisance

Surface water pollution (waste paper, food scraps, packaging materials etc)

Quite Possible ContinuousDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentDam. to $10K

Env. Nuisance

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Wastewaters entering land and contaminating soils

Unusual But Possible

FrequentDam.>$10K to

$100KMaterial Env. Harm

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Remotely Possible FrequentDam. to $10K

Env. Nuisance

Noise levels from generator and is a nuisance to personnel on site and/or nearby residents

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Noise Abatement Management Plan and

Golding WMSRemotely Possible

UBechtel Air Quality and Dust Management Plan and

Golding WMSRemotely Possible Frequent

Air pollution - generator exhaust emissions

Quite Possible FrequentDam. to $10KEnv. Nuisance

Poor public relations if housekeeping not up to scratch

Material Env. Harm

Dam.>$10K to $100K

Material Env. Harm

AU Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentAesthetic appeal not satisfying public perceptions

Quite Possible FrequentDam.>$10K to

$100KMaterial Env. Harm

Continuous

Dam. to $10KEnv.

NuisanceA

Dam. to $10KEnv.

NuisanceA

Increased odours (human health & hygiene)

Quite Possible ContinuousDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible

U Bechtel Waste Management Plan and Golding WMS Remotely PossibleContinuou

sFood scraps and wrappers scattered by birds and animals

Quite Possible ContinuousDam. to $10KEnv. Nuisance

Continuous

Dam. to $10KEnv.

NuisanceA

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentQuite Possible FrequentDam. to $10KEnv. Nuisance

Green house gas emissions Almost Certain ContinuousDam. to $10KEnv. Nuisance

A

Dam. to $10KEnv.

NuisanceA

A

Land contamination (waste paper, food scraps, packaging materials etc)

Unusual But Possible

ContinuousDam. to $10KEnv. Nuisance

U Bechtel Waste Management Plan and Golding WMS Remotely Possible Frequent

Dam.>$10K to $100K

Material Env. Harm

Dam. to $10KEnv.

NuisanceA

UBechtel Dangerous Goods and Hazardous Substances

Management Plan, Surface water and Groundwater Quality Management Plan and Golding WMS

Conceivable but Very Unlikely

Frequent

Conceivable but Very Unlikely

FrequentDam. to $10K

Env. Nuisance

Wastewaters entering groundwater degrading water quality

Remotely Possible

A

Dam. to $10KEnv.

NuisanceA

Wastewaters entering surface water degrading water quality and surrounding habitat

Remotely Possible

Frequent

UBechtel Noise Abatement Management Plan and

Golding WMSRemotely Possible Frequent

Noise levels from generator is a nuisance to the fauna of the area (nesting birds etc)

Quite Possible FrequentDam. to $10KEnv. Nuisance

FrequentDam. to $10K

Env. Nuisance

A

Dam. to $10KEnv.

NuisanceA

Dam. to $10KEnv.

NuisanceA

Dam. to $10KEnv.

NuisanceA

A

Quite Possible FrequentDam. to $10KEnv. Nuisance

UBechtel Core Process - CP-406 - External Stakeholder Interaction and Bechtel Waste Management Plan and

Golding WMSRemotely Possible Frequent

U Bechtel Waste Management Plan and Golding WMS Remotely Possible FrequentVisual pollution from excess packaging Quite Possible Frequent $100KMaterial Env. Harm

Page 110: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated.

Bechtel Confidential © Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Revision 00A

Attachment C – QGC Environmental Policy

Page 111: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated.

Bechtel Confidential © Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Revision 00A

Attachment D – Sample Environmental Inspection Checklists

Page 112: QUEENSLAND CURTIS LNG PROJECT - Shell · PDF fileSOPEP Shipboard Oil Pollution Emergency Plan WMS Work Method Statement List of Attachments ... Attachment D Sample Environmental Inspection

Electronic documents, once printed, are uncontrolled and may become outdated.

Bechtel Confidential © Copyright Bechtel Oil, Gas and Chemicals, Inc. 2010. All rights reserved.

25566-100-G01-GHX-00074 Revision 00A