11/14/2018 1 QUENTIN ROAD STUDY Dundee Road to Lake Cook Road Cook County Department of Transportation and Highways Public Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information Meeting #1 Public Hearing Public Information Meeting #2 2015 2018 Study Timeline 2019 2017 2016 Environmental Studies & Stakeholder Coordination Alternatives Analysis & Screening X Scoping Solicit public input on issues and concerns the project should address Draft Environmental Assessment (EA) We Are Here Public Information Meeting #3

QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

1

QUENTIN ROAD STUDYDundee Road to Lake Cook Road

Cook County

Department of Transportation and Highways

Public Information Meeting #3November 13, 2018

Final EA

2

Purpose & NeedEstablish why the project is needed

Public Involvement

Public InformationMeeting #1

Public HearingPublic InformationMeeting #2

2015 2018

Study Timeline

201920172016

Environmental Studies & Stakeholder Coordination

Alternatives Analysis & ScreeningX

ScopingSolicit public input on issues andconcerns the project should address

Draft Environmental Assessment (EA)

We Are Here

Public InformationMeeting #3

Page 2: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

2

3

Study Update

Alternatives Analysis Recap

Results of Evaluation Rounds 3 and 4

Meeting Agenda

NORTH

Regional Limits10 miles

Quentin Road – Regional Limits

Schaumburg

Hawthorn Woods

4

Page 3: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

3

NORTH

Project Study Limits

1 mile

Lake Cook Road

Dundee Road

5

PALATINE

PALATINE

DEER PARK

NORTH

Quentin Road – Study Limits

Established the basis for a range of reasonable alternatives

Purpose:  Address existing and 2040 transportation needs 

Strive to balance the transportation needs with the unique environmental setting along Quentin Road

Transportation Needs:

1. Improve the facility condition and design

2. Improve safety

3. Improve mobility

4. Enhance system linkage

Project Purpose and Need

6

Page 4: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

4

Study Update

Environmental Stakeholder Coordination 

Focus Group Topics

Safety for all Users

Water 

Animal/Vegetation

Roadway Character

Completed Additional Environmental Studies

77

Environmental Stakeholder Coordination

8

Forest Preserves of Cook County

Friends of the Forest Preserve

Openlands

Build Quentin Right

Deer Grove Natural Areas Volunteers

Cook County Department of Transportation and Highways

Environmental Stakeholder Group Members

Page 5: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

5

Focus Groups

Small groups of environmental stakeholder members were formed to provide open and transparent dialogue on important topics and share data and insight between various stakeholders.

WaterAnimal /

Vegetation

RoadwayCharacter

Safety forAll Users

9

Alternatives Evaluation Process

10

Four evaluation rounds with more detailed studies conducted in following rounds

Round 1 – Purpose and Need Screening

Round 2 – Refined Purpose and Need Screening

Round 3 – Performance and Impacts Evaluation

Round 4 – Refined Performance and Impacts Evaluation

Consistent, fair and transparent process

Goal is to balance the transportation needs along the corridor while minimizing impacts to the adjacent human and natural resources of the corridor

Cook County will make the ultimate decision while considering input from project stakeholders

Page 6: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

6

Evaluation Round 4:Refined Performance and 

Impacts Evaluation

Evaluation Round 3:Performance and Impacts 

Evaluation

Evaluation Round 1:Purpose and Need 

Screening

Evaluation Round 2:Refined Purpose and Need 

Screening

Alternatives Evaluation Flowchart

XALT 1

ALTER

NATIVES CONSIDER

ED

ALT 4 ALT 4

Combination RoutesALTS 9 ‐ 14

Legend

Alternative DroppedXAlternative #

Alternative Carried 

Forward

ALT #

Parallel Routes

ALT 7 & 8X

ALT 2 ALT 2

ALT 6 ALT 6

ALT 3 ALT 3

ALT 5 ALT 5

No Build No Build

11

Evaluation Round 4:Refined Performance and 

Impacts Evaluation

Evaluation Round 3:Performance and Impacts 

Evaluation

Evaluation Round 1:Purpose and Need 

Screening

Evaluation Round 2:Refined Purpose and Need 

Screening

XALT 1

ALTER

NATIVES CONSIDER

ED

ALT 4 ALT 4 X

Combination RoutesALTS 9 ‐ 14

X

Legend

Alternative DroppedXAlternative #

Alternative Carried 

Forward

ALT #

Parallel RoutesALT 7 & 8

X

ALT 2 ALT 2

ALT 6 ALT 6

ALT 3 ALT 3

ALT 5 ALT 5

No Build No Build

12

Alternatives Evaluation Flowchart

Page 7: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

7

Round 3 Results: Performance and Impacts Evaluation

13

Developed variations of alternatives (A – D)

Lane widths (12‐foot vs. 11‐foot)

Curbs and gutters vs. shoulders

Quantified environmental impacts

Right‐of‐way from the Forest Preserve and private property

Number of trees lost

Acres of direct impacts to wetlands and floodplains

Other environmental considerations

Future noise levels

Water quality 

Stormwater detention

Evaluation Round 4:Refined Performance and 

Impacts Evaluation

Evaluation Round 3:Performance and Impacts 

Evaluation

Evaluation Round 1:Purpose and Need 

Screening

Evaluation Round 2:Refined Purpose and Need 

Screening

XALT 1

ALTER

NATIVES CONSIDER

ED

ALT 4 ALT 4 X

Combination RoutesALTS 9 ‐ 14

X

Legend

Alternative DroppedXAlternative #

Alternative Carried 

Forward

ALT #

Parallel RoutesALT 7 & 8

X

ALT 2 ALT 2 ALT 2A thru 2D

2‐lanes with left turn lanes

X

ALT 6 ALT 6 ALT 6A thru 6D

5‐lanes (center median with left turn lanes)

X

ALT 3 ALT 3 ALT 3A thru 3D3‐lanes (center median with left turn lanes)

ALT 3C

ALT 5 ALT 5 ALT 5A thru 5D

4‐lanes with left turn lanes

ALT 5C

14

No Build No Build No Build No Build

Alternatives Evaluation Flowchart

Page 8: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

8

15

NORTH

33’ 55’

Alternative 3C                               Alternative 5C

Existing ROW Existing ROW

Round 4 Results: Refined Performance and Impacts Evaluation

16

Evaluated Alternatives 3C and 5C

Considered feedback from stakeholders and Focus Groups

Included additional environmental criteria

Completed additional environmental analyses

Water Quality

Salt Splash and Salt Spray

Identified project specific features of each alternative

Considered variances to standard design criteria to further reduce impacts

Page 9: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

9

Evaluation Round 4:Refined Performance and 

Impacts Evaluation

Evaluation Round 3:Performance and Impacts 

Evaluation

Evaluation Round 1:Purpose and Need 

Screening

Evaluation Round 2:Refined Purpose and Need 

Screening

XALT 1

ALTER

NATIVES CONSIDER

ED

ALT 4 ALT 4 X

Combination RoutesALTS 9 ‐ 14

X

Legend

Alternative DroppedXAlternative #

Alternative Carried 

Forward

ALT #

Parallel RoutesALT 7 & 8

X

ALT 2 ALT 2 ALT 2A thru 2D

2‐lanes with left turn lanes

X

ALT 6 ALT 6 ALT 6A thru 6D

5‐lanes (center median with left turn lanes)

X

17

ALT 3 ALT 3 ALT 3A thru 3D3‐lanes (center median with left turn lanes)

ALT 3C

ALT 5 ALT 5 ALT 5A thru 5D

4‐lanes with left turn lanes

ALT 5C

?

?

No Build No Build No Build XNo Build

Alternatives Evaluation Flowchart

Final EA

18

Purpose & NeedEstablish why the project is needed

Public Involvement

Public InformationMeeting #1

Public HearingPublic InformationMeeting #2

2015 2018

Study Timeline

201920172016

Environmental Studies & Stakeholder Coordination

Alternatives Analysis & ScreeningX

ScopingSolicit public input on issues andconcerns the project should address

Draft Environmental Assessment (EA)

Public InformationMeeting #3

We Are Here

Page 10: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

10

19

Next Steps

Conclude Public Comment Period on November 30th

Identify the Preferred Alternative

Prepare the Environmental Assessment (EA)

Hold a Public Hearing for Comments

Study Approval

20

What Will You See At This Public Meeting?

Series of exhibits and project information

Project team and staff are available to answer questions

Please provide input and comments

Provide Your Comments on the Two Remaining Alternatives

[email protected]

Comment period open until November 30th

Future Public Hearing

Page 11: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

11

THANK YOU FOR COMINGQUENTIN ROAD STUDY

Next presentation will begin shortly

Cook County

Department of Transportation and Highways

Public Information Meeting #3November 13, 2018

5N ex t

m i n u t e s

P re s e n t a t i o n i n

Cook County

Department of Transportation and Highways

Public Information Meeting #3November 13, 2018

Page 12: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

12

4N ex t

m i n u t e s

P re s e n t a t i o n i n

Cook County

Department of Transportation and Highways

Public Information Meeting #3November 13, 2018

3N ex t

m i n u t e s

P re s e n t a t i o n i n

Cook County

Department of Transportation and Highways

Public Information Meeting #3November 13, 2018

Page 13: QUENTIN ROAD STUDY - CookCountyIL.govPublic Information Meeting #3 November 13, 2018 Final EA 2 Purpose & Need Establish why the project is needed Public Involvement Public Information

11/14/2018

13

2N ex t

m i n u t e s

P re s e n t a t i o n i n

Cook County

Department of Transportation and Highways

Public Information Meeting #3November 13, 2018

1N ex t

m i n u t e

P re s e n t a t i o n i n

Cook County

Department of Transportation and Highways

Public Information Meeting #3November 13, 2018