13
1 of 13 Questions for Marta General Questions 1. Why did the plans change from locating on the West of 400 to the East? More specifically in 2005, in your executive summary, you wrote: “The Northridge cluster did not advance because of the limited amount of developable land. The area around Northridge Road and GA 400 is already built out and would require considerable redevelopment effort for TOD. Stakeholders felt strongly that the cluster areas with higher percentages of undeveloped land and strong redevelopment potential should be given higher standing in the process” These considerations are even more valid now. What happened? Why do you need a station at Northridge? MARTA Response: Since 2005, land use, demographics and travel patterns along the GA 400 corridor have changed and MARTA has entered into a new Federal planning process. As part of this current Federal planning process, MARTA has considered data from previous studies as well as current information and input from stakeholders and the community. All of this information assists in the decision making process. We are still at the beginning of the Federal planning process and no final determination has been made regarding potential station locations or alignments. Although a station is currently proposed at Northridge, the technical analysis and community input gathered during this study will assist in making a final determination. 2. Fulton Country School System and the city of Sandy Springs have both formally declared positions against development on the west side of 400. Are you concerned that the city you are going through and the neighborhood school systems are both against your plans? MARTA Response: Positions taken by the Fulton County School System and the City of Sandy Springs have been documented and included in this study. These positions, and feedback from other stakeholders, will be considered when decisions are made on how the proposed project proceeds through the Federal planning process.

Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

1 of 13

Questions for Marta

General Questions

1. Why did the plans change from locating on the West of 400 to the East? More specifically in 2005, in your executive summary, you wrote:

“The Northridge cluster did not advance because of the limited amount of developable land. The area around Northridge Road and GA 400 is already built out and would require considerable redevelopment effort for TOD. Stakeholders felt strongly that the cluster areas with higher percentages of undeveloped land and strong redevelopment potential should be given higher standing in the process” These considerations are even more valid now. What happened? Why do you need a station at Northridge? MARTA Response: Since 2005, land use, demographics and travel patterns along the GA 400 corridor have changed and MARTA has entered into a new Federal planning process. As part of this current Federal planning process, MARTA has considered data from previous studies as well as current information and input from stakeholders and the community. All of this information assists in the decision making process. We are still at the beginning of the Federal planning process and no final determination has been made regarding potential station locations or alignments. Although a station is currently proposed at Northridge, the technical analysis and community input gathered during this study will assist in making a final determination.

2. Fulton Country School System and the city of Sandy Springs have both

formally declared positions against development on the west side of 400. Are you concerned that the city you are going through and the neighborhood school systems are both against your plans?

MARTA Response: Positions taken by the Fulton County School System and the City of Sandy Springs have been documented and included in this study. These positions, and feedback from other stakeholders, will be considered when decisions are made on how the proposed project proceeds through the Federal planning process.

Page 2: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

2 of 13

3. Are there any studies that document lessons learned from prior expansions? North Springs?

MARTA Response: Information from previous transportation/transit planning studies as well as local and regional planning studies were reviewed and considered in this process. Some examples of previous work efforts considered in the corridor include:

• The Atlanta Northside Strategy

• North Fulton Comprehensive Transportation Plan (ARC 2010)

• Concept 3 Transit Vision, adopted in 2008 by the ARC

• The North Line Transit-Oriented Development Study (MARTA 2006)

• The North Line Alternatives Analysis (MARTA 2003)

• The Three Corridors Feasibility Study (MARTA 1998) Financial questions

4. Other than the ARC Regional Transportation Plan, are there any

feasibility studies that justify Marta expanding beyond North Springs? Were any of the ARC Plan assumptions validated?

MARTA Response: Yes, other studies have been conducted in the past (see question 3). In 2003, MARTA initiated the North Line Alternatives Analysis (AA) to evaluate and select an alternative for an extension of the existing heavy rail line from its current terminus at North Springs. Based on the ARC’s regional travel demand model the study area was not transit supportive due to a combination of high incomes and low household and employment densities. Subsequently, the decision was made to redirect future planning activities and conduct a land use and market analysis. The resulting North Line Transit Oriented Development (TOD) Study offered an opportunity to examine transit expansion feasibility in the GA 400 corridor through the possible implementation of new development patterns. With recent changes in land use and travel patterns, as well as strong population and employment growth, recent transit ridership projections have increased when compared to previous studies. These modeled ridership projections were determined using the latest ARC Regional Transportation Plan’s travel demand model.

Page 3: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

3 of 13

Even though potential stations, alignments and other considerations may have been ruled out in previous studies, MARTA’s current long range planning efforts in the GA 400 corridor must objectively consider all reasonable alternatives, based on current and future conditions, to meet the transportation needs in this corridor and avoid any indication of a bias towards a particular alternative. This is one of the requirements of the federal project development process that MARTA must satisfy to ensure eligibility for federal funding.

5. What were the proposed costs for those expansions, what were the actual costs thru completion? MARTA Response: Based on high level conceptual planning, preliminary cost estimates along GA 400 for Heavy Rail Transit (HRT), Bus Rapid Transit (BRT), and Light Rail Transit (LRT) are: HRT: $1.60 Billion BRT: $0.47 Billion LRT: $1.80 Billion Cost estimates will change as the proposed project moves through detailed environmental review and preliminary engineering.

6. Can we see a current, and or high level P&L from Marta's organization?

MARTA Response: For MARTA’s profit and loss statement (P&L), the closest document the Authority has to that would be its annual budget. The budgets for FY 2010 through 2014 are available on the MARTA website at www.itsmarta.com. The FY 2015 was recently adopted by the MARTA Board and will be available on the website sometime in the fall. Attached on the next page are highlights from the recently adopted FY15 budget.

Page 4: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

4 of 13

Page 5: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

5 of 13

7. Are there any recent comps/evaluations that reveal how property values are impacted by Rail Transit additions?

MARTA Response: The American Public Transportation Association has performed two relevant and recent studies on this topic. http://www.apta.com/resources/statistics/Documents/NewRealEstateMantra.pdf

Page 6: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

6 of 13

http://www.apta.com/resources/reportsandpublications/Documents/Economic-Impact-Public-Transportation-Investment-APTA.pdf http://www.nhc.org/media/documents/TransitImpactonHsgCostsfinal_-_Aug_10_20111.pdf

8. Was Northridge included in the detailed analysis of the ROW acquisition? Can you share the ROW acquisition analysis with us?

MARTA Response: Conceptual alignments have not gone through an extensive Right-of-Way (ROW) assessment. This will occur later in the Federal planning process as potential alignments undergo environmental review. Additionally, MARTA has a resolution with GDOT allocating up to 60 feet of ROW for transit in corridors where GDOT is planning to implement Managed Lanes. GA 400 is a Managed Lane project corridor and the conceptual alignments currently under consideration are entirely within GDOT ROW.

9. It appears that federal funds are being sought (FTA requirements)

under the New Starts (5309) grant program? How much $ is being requested from the FTA grant? Is the project dependant on this grant to succeed?

MARTA Response: MARTA is hoping to qualify for the New Starts (5309) grant program. This program has a maximum match of 50% and is highly competitive on a national level. Therefore, we are not certain how much money from the grant program we will receive. MARTA is also conducting a study to identify other funding sources and project delivery methods.

10. Who is funding the project?

MARTA Response: Funding sources for the proposed project have not yet been identified. However, it is unlikely that MARTA will be able to fund any future expansion through the existing penny sales tax. As previously stated, MARTA is conducting a study to identify other funding sources and project delivery methods.

Process questions

Page 7: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

7 of 13

11. Why are we ignoring all the costly, time-consuming efforts and decisions made before the new commission took charge?

MARTA Response: As stated in the response to Question #4, MARTA’s current long range planning effort in the GA 400 corridor takes into account previous studies/efforts to objectively consider all reasonable alternatives, based on current and future conditions, to meet the transportation needs in this corridor and avoid any indication of a bias towards a particular alternative.

12. What is the timeline for this project beyond Phase II?

MARTA Response: The tentative timeline for completing the project beyond Early Scoping –Phase II is:

• Adoption of a Locally Preferred Alternative by the MARTA Board –

September 2014 • Notice of Intent (NOI) to Prepare Environmental Impact

Statement (EIS) – November 2014 • Complete EIS – December 2016 • FTA Issues Record of Decision (ROD) – February 2017 • Engineering – 3-5 years • Full Funding Grant Agreement • Construction – 2-3 years • Operation

13. How does DOT land fall into the equation? Get used by MARTA? Specifically the 17 acres at Northridge Rd.?

MARTA Response: MARTA has a resolution with GDOT allocating as much as 60 feet of ROW for transit on Managed Lane project corridors. GA 400 is a Managed Lane project corridor. The 17 acres near the Northridge Rd. interchange are being used by GDOT for bridge replacement and interchange improvements.

14. What is the role of the Atlanta Regional Commission (ARC), are they currently engaged in the project? Is the project considered an Area Plan (Section 50-8-98 of Georgia Code)?

MARTA Response: ARC is engaged in the project as a stakeholder and is part of the GA 400 Transit Initiative’s Technical Advisory Committee

Page 8: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

8 of 13

(TAC). The GA 400 Transit Initiative is currently not considered an Area Plan per Section 50-8-98 of Georgia Code as this applies only to the existing system. Below is a link to the MARTA system’s Area Plan Review: http://documents.atlantaregional.com/land%20use/Area_Plan_Review_Maps-MARTA_Rail_Corridor.pdf

15. Can you describe the process for FTA/NEPA? Who / what is conducting this process?

MARTA Response: The previous and current Federal planning processes are illustrated below. The first illustrates the process we have been following. The second illustrates the current process that the project hopes to be “grandfathered” into. MARTA is working with a consultant team led by Parsons Brinckerhoff to guide us through the environmental review and project development portions of the process.

16. March 2013 presentation, Have the Financial and Implementation plans been started? Completed?

MARTA Response: As previously stated in Questions #9 and #10, MARTA is currently conducting a study to identify other funding sources

Page 9: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

9 of 13

and project delivery methods. A financial plan must be finalized before the FTA will issue a Record of Decision (ROD) for a proposed project.

Analysis questions

17. Was there an analysis of the Pitts Rd vs Northridge Rd station? Why the

change? Can we see the analysis?

MARTA Response: During our Screen 2 evaluation, feedback from the public determined that Pitts Rd. should be removed and Northridge Rd. added to the list of potential station locations. This information is available in the GA 400 Definition of Alternatives Report – Appendix. http://www.itsmarta.com/uploadedFiles/GA400_Definition_of_Alternatives_Appendix_Aug30_FINAL.pdf

18. Was there an analysis of the East vs West side station? Why the change? Can we see the analysis?

MARTA Response: At this stage in the analysis, having evaluated several alternatives on both sides of the GA 400 right-of way during the screening process, three (3) conceptual alternatives have emerged as the most viable from a community and technical standpoint. The conceptual alternatives include bus rapid transit, light rail, and an extension of the existing heavy rail service from the North Springs station to the Windward Parkway area in an alignment along the east side of the GA 400 corridor. A conceptual alignment on the east side has been used for the purpose of performing a preliminary transit ridership forecast and developing preliminary cost estimates. However, no decisions on alignment, whether east or west side have been made at this time. Further analysis will be conducted as part of a detailed environmental analysis of potential alignment and station impacts. The technical analysis and community input gathered during the study will assist in making a final determination.

19. Where is the no-build alternative in the fatal flaw analysis?

MARTA Response: The Fatal Flaw Analysis does not contain a No-Build Alternative as the purpose of the analysis is to identify Build Alternatives to advance into Screen 1. The environmental review process will include a No-Build Alternative that must be analyzed as a

Page 10: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

10 of 13

viable alternative to the Locally Preferred Alternative (LPA) once it is selected.

20. Re: pp19 Definition of Alternatives (May 2013) supportive land use is misleading, scoring appears to be incorrect. Population per station vs total. Same in Screen 2 pp32 table 3.1-9 MARTA Response: The May 2013 Definition of Alternatives report was an interim document. The final document for the Definition of Alternatives is from August 2013 and is located on the GA 400 project website. In that document, Table 3.1-9 displays population total and population density by station. Alternative GA 400-1 (Heavy Rail Transit) had 5 potential stations, while alternative GA 400-1A (Bus Rapid Transit or Light Rail Transit) had 6. The data and scoring are correct. The transit supportive land use is Table 3.2-6 did have an error. The numbers in the table were transposed incorrectly. 198 is where 33 should be, and vice versa. MARTA has received a corrected version of this document and will update the website. Below is the updated table.

21. The future land use and zoning analysis indicates 74 acres of mixed use zoning within ½ mile of the Northridge station, where exactly was the ½ mile measure from? E or W side?

MARTA Response: At this stage in the project, potential station locations were placed in the middle of the bridge spans crossing over GA 400. This was done since no determination has been made over the exact locations of any potential station in the corridor. An example of

Page 11: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

11 of 13

this can be seen below where the blue dot represents the center of the potential Northridge station area. The red dotted line corresponds to a ½ mile buffer area surrounding the blue dot.

22. Definition of Alternatives Technical Appendix – Aug 2013: The fatal flaw analysis puts disproportionate weight on the criteria. Seems to be a flaw in the flaw analysis? How can a ratio of 4:1 (e.g. construction costs ratio) get the same qualitative valuation as a ratio of 1.1:1(vacant land ratio)?

a. Construction cost $200M/mi (1) vs $50M/mi (2) b. Opportunity acres 92 (1) vs 111 (2)

Page 12: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

12 of 13

c. Zoning 198 acres (2) vs 33 acres (1) d. Vacant land 141 (1) vs 159 (2)

MARTA Response: The Fatal Flaw analysis occurred prior to the Definition of Alternatives. The data above is from the Appendix - Screen 2 evaluation which analyzed alternatives GA400-1 (HRT) and GA 400-1A (LRT or BRT). Additionally, the scoring methodology is outlined in the Evaluation Process section of the Definition of Alternatives report. While this evaluation process may have caused some disparity with certain measures, it did provide a consistent framework that can be applied across all goals and measures in Screen 1 and 2.

23. The ROW analysis and impact to utilities (2.7 pp8 Conceptual design

technical Analysis) is based on a 40ft ROW. The required ROW for several options is > 40ft. When will a revised impact and cost be completed?

MARTA Response: A more detailed assessment of right-of-way impacts will be performed later in the process as part of the environmental review process.

Specifics questions

24. Please describe the planned station type for Pitts / Northridge and Holcomb Br.?

MARTA Response: Potential stations in the Pitts/Northridge Rd. and Holcomb Bridge Rd. areas are community stations. This station type fits in with surrounding existing and future development patterns. They generally have less parking, more of a “walk-up” feel and more of a low-profile presence.

25. What are some examples of walk-up stations currently in place?

MARTA Response: All stations within MARTA are walk-up accessible. Some have a more regional context such as Airport or North Springs station with increased parking and connectivity. Community stations along the corridor are intended to be more “walkable” with less parking and more interaction with transit supportive developments.

Page 13: Questions for Marta General Questionsnorthridgeforest.net/MartaFiles/MARTA_Responses_to_NCA_Questio… · MARTA Response: ARC is engaged in the project as a stakeholder and is part

13 of 13

26. Is the Northridge station project impacted by Chattahoochee River Corridor or National Park regulations?

MARTA Response: While a potential station in the Northridge area would most likely have minimal impacts to the Chattahoochee River National Park, the future to-be-determined alignment would have to cross the river and the national park. The impacts of doing this will be assessed and mitigation strategies will be developed later in the process under the draft Environmental Impact Statement (DEIS).