“RAABSTEG” FELDBACH (AUT)Institute for Timber Engineering and Wood Technology,
TU Graz / AustriaCase study no. 3
Leonardo da Vinci project no. CZ/06/B/F/PP-168007
WP6 – Case StudiesPC 3 – A set of case studies
General Information
Type of building:(Covered) Pedestrian and bicycle bridge
Structural System:Cable supported single-span girder withsuspended bridge deck
Owner:City of Feldbach / Austria
Location:Feldbach / Austria
Erection date:08 / 1998
Architectural, structural and construction design:LIGNUM CONSULT, Graz / Austria
Manufacturer of the timber structure:Stingl GesmbH, Trofaiach / Austria
Longitudinal Section andStructural System
Longitudinal Section(with dimensions)
Structural System(with dimensions)
Cross section
Detail: Deck Construction
Detail
Main girder 2 x 200 / 450 mmout of GL36c- (BS 18 c)- twin girder
machine gradedC35m- (MS 13)-lamellas
machine graded C40m- (MS 17)-lamellas
Load carrying:- in longitudinal direction as T-beam- in longitudinal direction for horizontal forces- in cross direction for load distribution purposes
CLT - plate 130 mm(19_l_NF+34_q+24_l+34_q+19_l_NF)Detail
Detail: Connection Suspension Bar on Main Girder
Detail: Support Detail – Connection on Tie Bar
Detail: Railing System
Assembling / Transport
Transport by means of a truckwith a trailer
Assembling in the production hall of the manufacturer
Erection
Erection concept Erection by means of three auto-cranes
Impressions
View in londitudinal directionView from the cycle track
Impressions
View from Raab River