1
Planning Practice Current Flow Method (in Chinese) Planning and P6 How to Evaluate a Programme Resource under P3 Activity Movement Chart Tender Planning Under P3 Tender Planning Under P6 Progress Measurement Claim Analysis Site Utilisation Planning Soil Category and Temporary Work Design RC WOKS (Based on Marina Barrage Project experience) BASE RAFT SLAB RAW DATA: - Total Qty: 5043 m3; - Total Duration: 45 day; : - Barbender: 30 men; - Carpenter cum concretor: 20 men; - Casting method: mobile concrete pump with trunk distributor TYPICAL CASTING UNIT: - 35m x 10m, 460 m3; - Duration: 4d; PRODUCTION RATE FROM RAW DATA: 5043/45/50=2.24 m3/man.d © 2005 - 2011. Johnny Xu. All Rights Reserved. Updated in August 2011. Contact Me . Read My Guest Book! Sign My Guest Book! Page 1 of 1 Johnny Xu Huiyi, Planning Engineer 12/12/2012 http://www.p3planningengineer.com/

RC Works Production Rate

  • Upload
    roldski

  • View
    18

  • Download
    1

Embed Size (px)

DESCRIPTION

RC

Citation preview

Page 1: RC Works Production Rate

Planning PracticeCurrent Flow Method

(in Chinese)Planning and P6How to Evaluate a

ProgrammeResource under P3

Activity Movement Chart

Tender Planning Under P3

Tender Planning Under P6

Progress Measurement

Claim Analysis

Site Utilisation Planning

Soil Category and Temporary Work Design

RC WOKS (Based on Marina Barrage Project experience)

BASE RAFT SLABRAW DATA:- Total Qty: 5043 m3;- Total Duration: 45 day; : - Barbender: 30 men;- Carpenter cum concretor: 20 men;- Casting method: mobile concrete pump with trunk distributorTYPICAL CASTING UNIT: - 35m x 10m, 460 m3;- Duration: 4d;PRODUCTION RATE FROM RAW DATA:5043/45/50=2.24 m3/man.d