Upload
jada-oleary
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
Ref.: New Acquisition Policy by DAU, 20 May 2003, PMT-352
Review of DoD’s New AcquisitionPolicy and its Impact on Programs and Systems Engineering
by Al BrunsINCOSE Gateway ChapterWednesday, 30 July 2003
•DoD Directive 5000.1Principles retained; innovation/flexibility
emphasized
•DoD Instruction 5000.2Focused on required outcomes and statutory
requirements and less on regulatory requirements
•DoD Regulation 5000.2-R- Cancelled; becomes “guide” not a regulation
- Provides expectations (TEMP, C4ISP, etc..), best practices and lessons learned
New Acquisition PolicyNew Acquisition PolicyConstructConstruct
New Acquisition PolicyNew Acquisition PolicyConstructConstruct
IOCBAConcept
RefinementSystem Development
& DemonstrationProduction &Deployment
Systems Acquisition
Operations &Support
C
Sustainment
• Process entry at Milestones A, B, or C
• Entrance criteria met before entering phase
• Evolutionary Acquisition or Single Step to Full Capability
FRP DecisionReview
FOC
LRIP/IOT&EDesign
ReadinessReview
TechnologyDevelopment
(ProgramInitiation)
ConceptDecision
New
Pre-Systems Acquisition
Increment IIIncrement II
Increment IIIIncrement III
Technology Opportunities & User Needs
The Defense Acquisition Management The Defense Acquisition Management FrameworkFramework
DoDI 5000.2, May 2003DoDI 5000.2, May 2003
The Defense Acquisition Management The Defense Acquisition Management FrameworkFramework
DoDI 5000.2, May 2003DoDI 5000.2, May 2003
Common element is CAPABILITIES • Initial Capabilities Document (ICD) replaces MNS at Milestone A
Describes desired capability. Evaluates multiple materiel approaches. Recommends a materiel approach.
• Capability Development Document (CDD) replaces ORD at Milestone B
Describes the SDD effort and provides KPPs for the increment. Describes program to get to complete solution.
• Capability Production Document (CPD) replaces ORD at Milestone C
Describes the SDD effort to produce materiel solution for the increment and provides KPPs for the production increment.
Details will be implemented by CJCSI 3170.01C & CJCSM 3170.01
New Requirements Documents New Requirements Documents New Requirements Documents New Requirements Documents
Technology Development StrategyTechnology Development Strategy
• Required ACAT I and IA programs. Based on AoA results
• Contents:- Rational for EA or single-step strategy
- For EA, description of how program will be divided into technology spirals & development increments
- Appropriate limits on prototypes produced and deployed during the TD Phase
- Performance Goals and Exit Criteria to be met prior to proceeding into SDD and producing additional prototypes
- Overall cost, schedule and performance goals for the total R&D effort
- Specific cost, schedule and performance goals and exit criteria for the first technology spiral demonstration, and a test plan to ensure that they are met.
New/Revised from previous 5000.2:
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
• “Concept Decision” - new decision point prior to Milestone A
• Analysis of materiel approaches done prior to Concept Decision, and documented in Initial Capabilities Document (ICD). MNS is eliminated.
• New phase prior to Milestone A, “Concept Refinement”
• Analysis of Alternatives (AoA) due at Milestone A vice program initiation (Milestone B). Used to refine the initial concept and provide basis for the Technology Development Strategy.
Oversight & ReviewOversight & ReviewACAT ID/IAM Programs*ACAT ID/IAM Programs*Oversight & ReviewOversight & Review
ACAT ID/IAM Programs*ACAT ID/IAM Programs*
Defense AcquisitionBoard
Defense AcquisitionBoard
C3I OverarchingIntegrated Product
Team (OIPT)
C3I OverarchingIntegrated Product
Team (OIPT)
C3ISR Systems
OverarchingIntegrated Product
Teams (OIPT)
OverarchingIntegrated Product
Teams (OIPT)
Weapon Systems
Director, Defense Systems
OUSD(AT&L)
Defense AcquisitionExecutive
Chief Information
Officer
IT AcquisitionBoard
IT AcquisitionBoard
Major AIS
*Note: Space Programs have been delegated to the Air Force and most missile defense programs to the Missile Defense Agency
The acquisition responsibilities of USD(Intel) vs. ASD(NI2)/DoD CIO are a work in process.
RGS JCIDS
Integrated atDepartment
Systems
Requirements
Bottom Up, Often Stovepiped
National Military Strategy
JointVision
Joint Concept of Operations
Joint ConceptsIntegrated Architectures
Joint Capabilities
Top Down, Born Joint
Transformation to the Joint CapabilitiesTransformation to the Joint CapabilitiesIntegration and Development SystemIntegration and Development System
Increment 2
Increment 3
Evolutionary AcquisitionEvolutionary Acquisition
• Urgency of Requirement
• Maturity of Key Technologies
• Interoperability, Supportability, and Affordability of Alternative Acquisition Approaches
• Cost/Benefit of Evolutionary vs. Single Step Approach
Key ConsiderationsKey Considerations
Single Step to Single Step to Full Capability ?Full Capability ?
OROR
• Two development processes to implement Evolutionary Acquisition Strategy- Incremental Development: End-state requirement is
known, and requirement will be met over time in several increments
- Spiral Development: Desired capability is identified, but end-state requirements are not known at Program Initiation. Requirements for future increments dependent upon technology maturation and user feedback from initial increments
• Evolutionary acquisition strategies shall be preferred approach to satisfying operational needs.
• Spiral development shall be the preferred process.
Evolutionary Acquisition
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
Evolutionary Acquisition –Evolutionary Acquisition –Incremental & Spiral DevelopmentIncremental & Spiral DevelopmentEvolutionary Acquisition –Evolutionary Acquisition –
Incremental & Spiral DevelopmentIncremental & Spiral Development
Time
- Incremental
- Spiral
Warfighter Capability
Known increment
Known increment
Known increment
Known increment
Partially known
increment
Not known increment
Not known increment
==
First Fielded Capability
Technology Demos
Feedback from warfighter
Time
Cap
abil
ity
Evolutionary Acquisition
Initial O
perationally
Useful Capability
Technology BaseRequirements
Capability
Time
NO CAPABILITY
Cap
abil
ity
Single Step ApproachTechnology Base
Requirements
CapabilityFOCIOC
Evolutionary ApproachEvolutionary Approach
• Time-Phased Requirements
• A Modular Open Systems Approach to facilitate Technology Insertion
• Evolutionary Sustainment Strategies
• T&E Consistent with Evolutionary Approach
• Full Funding
Key EnablersKey Enablers
CR TD SDD PD OS
B CA
B C
Increment 2
B C
Increment 3
Each Increment Must Have…Each Increment Must Have…
• Approved Operational Requirements • Interoperability Key Performance Parameter
• Performance, Cost and Schedule Goals (Acquisition Program Baseline)
• Operational and Live Fire Testing (If Required) • Compliance with Acquisition Oversight Requirements• An Acquisition Strategy that reflects consideration of Logistics
Planning; Manpower, Personnel and Training; Environmental and Security Factors; Protection of Critical Program Information; and Spectrum Management
• Other information tailored to the conditions of the program
Each Increment is Managed as a Unique AcquisitionEach Increment is Managed as a Unique Acquisition
B C
Increment 2
B C
Increment 3
YesYesNoNoMultiple iterations
NoNoNoYesAll capabilities required in initial increment
Preferred process(Previously used mostly in Software development)
Achieves increased capability from predictable maturing technology
Traditional acquisition strategy
Other characteristics
YesYesNoNo
User feedback from earlier iterations used to define final requirement
YesYesYesNoUseful intermediate capabilities
NoYesYesFull requirements defined at outset
Spiral Development **
Incremental Development
Pre-planned Product
Improvement (P3I)
Single Step to Full
Capability Criteria
Acquisition Strategy Comparison TableEvolutionary Acquisition *
Yes
* Preferred strategy ** Preferred process
Often used in hardware development
AcquisitionStrategy
Requirement CommentReference
Spectrum CertificationCompliance
47 USC 305 & 901-904PL 102-538OMB A-11, Part 2DoDD 4650.1
Name changeFormerly – ApplicationFor FrequencyAllocation
ProgrammaticEnvironmental Safety & Health Evaluation
42 USC 4321 FromDoD 5000.2-R
WhenRequired
MS B, orMS C if no B
MS B, orMS C if no B
Statutory Information Requirements Changed/Added
DoD Instruction 5000.2 DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
DoD Instruction 5000.2 DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
Electronic Warfare T&E Report
Sec. 220, PL 103-160 & Sec. 214, PL 103-337
annually FromDoD 5000.2-R
Requirement CommentReference
Certification of Compliance with Financial Management Modernization Plan (FM acq programs only)
PL 107-249
15 USC 644(e)
WhenRequired
MS A, B, and C
MS B, orMS C if no B
Statutory Information Requirements Changed/AddedContinued…..
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
NEWFrom
Congress
NEWFrom
Congress
Technology Development Strategy
Sec. 803, PL 107-314
NEWFrom
Congress
MS A, B and C
Benefits Analysis & Determination (applies to bundled acquisitions; part of acq strategy)
Regulatory Information Requirements Added
CommentReference
Initial Capabilities Document (ICD)
CJCSI 3170.01NEW from Joint Staff
Replaces MNS
Capability DevelopmentDocument (CDD)
CJCSI 3170.01 NEW from Joint Staff
Replaces ORDCapability ProductionDocument (CPD)
CJCSI 3170.01
Technology ReadinessAssessment (PM-level)
DoDI 5000.2Revised from DoD 5000.2-R requirement for an Independent Technology Assessment for all programs
WhenRequired
MS A
MS B
MS C
MS B & C
Regulatory Information Requirements Changed/Added
Independent Technology Readiness Assessment (ACAT ID only – as required by DUSD(S&T))
DoDI 5000.2 MS B & C
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
Earned ValueManagement Systems
FromDoD 5000.2-R
OMB Cir A-11, part 7
See ANSI/ EIA-748-1998
Defense AcquisitionExecutive Summary (DAES) (MDAP & MAIS)
DoDI 5000.2QuarterlyPOM or BES submitUCR breach
FromDoD 5000.2-R
Contractor Cost DataReport (CCDR)
DoD 5000.4-M-1 See the referenceFromDoD 5000.2-R
Report Reference When Required Comment
DoD 5000.4-M-2-180 days prior to contract award-60 days after contract award-60 days after start of subsequent software releases-within 120 days after software release or final delivery
NEW from OSD
Director, PA&E
Other Reports Changed/Added
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
DoD Instruction 5000.2DoD Instruction 5000.2 Operation of the Defense Acquisition SystemOperation of the Defense Acquisition System
Software ResourcesData Report (ACAT I/IA programs for all major contracts & sub – contracts for any software development elements with a projected software effort greater than $25M (FY02 constant dollars)
Defense Acquisition ManagementDefense Acquisition Management Framework – Key PointsFramework – Key Points
Defense Acquisition ManagementDefense Acquisition Management Framework – Key PointsFramework – Key Points
• Evolutionary acquisition is the preferred strategy for rapid acquisition of mature technology; spiral development is the preferred process
• MDA may authorize entry at any point consistent with phase-specific entrance criteria and statutory requirements
• Non-mandatory guidance on best practices, lessons learned and expectations are available in the Interim Guidebook (former DoD 5000.2-R)
• Validated and approved ORDs are still required until revised CJCSI 3170.01 is published
Operations & Support
Sustainment
Sustainment
Disposal
FOC
System Development& Demonstration
System Integration
System Demonstration
B
Pre-Systems Acquisition
A
TechnologyDevelopment
Systems Acquisition
IOC
Production & Deployment
CLRIP Full-Rate Prod &
Deployment
FRPDecisionReview
The Defense Acquisition Management The Defense Acquisition Management FrameworkFramework
The Defense Acquisition Management The Defense Acquisition Management FrameworkFramework
• Process entry at Milestones A, B, or C• Entrance criteria met before entering phases• Evolutionary Acquisition or Single Step to
Full Capability
Relationship to Requirements Process
Initial Capabilities Document (ICD)
Capability Development Document (CDD)
Validated & approved by operational validation authority
Capability Production Document (CPD)
DesignReadinessReview
Concept Refinement
ConceptDecision
User Needs &Technology Opportunities