Regional Open Houses
GO Transit Service Expansion November 2016
2
Today
3
Tomorrow: Modern, Integrated Network
4
Metrolinx is embarking on a massive transformation of the existing GO rail system to provide:
• Four times the number of trips outside of weekday rush-hour periods, including evenings and weekends.
• Twice the number of trips during weekday rush-hour periods. • Line extensions to new communities.
GO Transit Expansion
• Bringing new transit options and new levels of service doesn’t come easy.
• Metrolinx is undertaking one of the largest infrastructure projects in North America.
• There is community-level disruption required to build a region-wide, integrated transit network.
5
Infrastructure Needs for GO Expansion
What’s going on in your neighbourhood
• Expanding GO Service as part of a rapid transit network – Future 15-minute electrified service; currently half-hour in your area
• Infrastructure needed to provide this level of service – Add a 4th Track
– Widen 4 rail bridges
– Modify Danforth Station – Planning Study underway
– Build Electrification Infrastructure (e.g. overhead catenary system)
• New GO/SmartTrack stations announced – Don Yard/Unilever (between Cherry Street and Eastern Avenue)
– Gerrard (in the vicinity of Carlaw Avenue)
6
Lakeshore East Service
TODAY FUTURE
7
115 daily trips (between Don River and Scarborough GO Station)
408 daily trips
Service Planning and Phasing is still not complete
Beginning the Conversation
• First round of public meetings in February/March
• Ongoing briefings for local community groups such as the Danforth East Community Association and the Danforth Village Residents’ Association
• On the ground – face-to-face, door-to-door outreach by the local Community Relations Specialist
8
Transit Project Assessment Process
9
What Are We Assessing
Natural Environment Terrestrial, aquatic habitat and species Species of conservation concern Sensitive areas and features Stormwater Management
Socio-Economic Environment Land Use Property Air Quality Noise and Vibration Traffic and Transportation Utilities Electromagnetic
Interference/Electromagnetic Fields Cultural Environment Archaeological resources
Built Heritage resources Cultural Heritage landscapes
10
GO Rail Network Electrification TPAP Study Area
11
Electrification - Power Supply & Distribution
• Metrolinx and Hydro One are EA co-proponents
12
Electrification - Overhead Contact System (OCS)
• The span between OCS supports ranges from 50 to 65 metres.
13
Cantilevers: one foundation required Portals: two foundations required
Electrification - Bridge Modifications
14
Location: Lititz Pike, Lancaster, PA
Electrification - Pedestrian Bridges Reinforce or Replace
15
Wallace Ave. Drury Lane
PAPE Mooregate Ave / Tara Ave
Electrification-Lakeshore East Corridor Traction Power Facilities
16
Electrification – Stouffville Corridor Traction Power Facilities
17
Electrification - Visual/Aesthetics
18
Electrification - Tree/Vegetation Removals
Vegetation/Tree Removal may be required to : • Minimize the risk of tree limbs
falling on the track or overhead wires.
• Secure the safety of maintenance workers when working in an electrified environment.
• Maintain the safety of our customers and neighbours.
19
Noise Assessment – Approach
• When building new infrastructure, Metrolinx models noise
• Noise modeling compares current noise levels to 2025 service levels
• Sensitive receptors are identified such as residences, hospitals, daycares etc.
• When noise is expected to increase >5dB at sensitive receptors, then mitigation is considered
• Mitigation could include noise walls, berms, rail dampeners etc.
20
Lakeshore East Don River to Scarborough GO Station TPAP Study Area
21
New 4th Track Location
22
New track on south side between the Don River Bridge and Gerrard Street shifting to the north side between Pape Avenue and Scarborough GO Station.
New 4th Track - Bridge Modifications
Woodbine Ave. – Widen to the North Warden Ave. – Widen to the North
Danforth Ave. – Widen to the North Birchmount Rd. – Widen North Abutment 23
Construction Completed 2025
TPAP Completion (Tentative) Summer/Fall 2017
TPAP Notice of Commencement (Tentative) Winter/Spring 2017
Public Meetings November 2016
Prepare Draft EPR Fall 2016/Winter 2017
Completion of Environmental Impact Studies Underway
4th Track and Electrification - Next Steps
24
Q & A
25
26