DetailsARCELORMITTAL TUBULAR PRODUCTS PROJECTAL - JUBAIL, KINGDOM OF SAUDI ARABIA

Additional Works Carried by NSH Due to CISDI Drawing Revisions:

S. No.DescriptionDrawing Reference No.NSH Submitted Claim (SR) AMTPJ Approved (SR)Ref. CCF No. Remarks1Dismantling Work at Preceding Billet Saw Foundation10010001DR5003ST002-C2 (Old) 10010001DR5003ST002-D2 (New)3,074.692,412.40CCF/033CCF Approved2Dismantling Work at Detection Foundation100110001DR5006ST005-B12,226.998,935.71CCF/033CCF Approved3Dismantling Work at 115 / 13.8KV Sub Station Foundation10010001DR5054ST002-A2 (Old); 100110001DR5054ST002-2/C (New)3,569.352,162.69CCF/033CCF Approved4Additional Works for Cooling Bed Foundation10010001DR5005ST015-6A & 10010001DR5005ST015-6B11,370.427,001.00CCF/032CCF Approved5Additional Works for Hot Mill Equipment Foundation (Due to Revision)10010001DR5005ST004-28,011.603,355.60CCF/032CCF Approved6Charges For Rebar Wastage at Intermediate Foundation 1/7 due to drawing revision.10010001DR5008ST002-11 A4,183.254,183.25CCF/074CCF Approved10010001DR5008ST002-15 A10010001DR5008ST002-20 A10010001DR5008ST002-11 B10010001DR5008ST002-15 B10010001DR5008ST002-20 C7Rectification work for Intermediate Transportation Foundation (3/7)10010001DR5008ST002-A8 (Old) 10010001DR5008ST002-B8 (New)32,814.2812,613.46CCF/074CCF Approved8Rectification work for QA Line Foundation 10010001DR5008ST004-4B3,440.250.0Not Accepted by AMTPJ9Rectification work for Crane Rail Foundation 10010001DR5003ST009-22,279.272,050.52CCF/067CCF Approved10Additional Work - Rectification of Sand Filter Foundation due to drawing revision.10010001DR5050ST002-A (Old) 10010001DR5050ST002-B(New)4,824.612,855.54CCF/067CCF Approved11Additional Rebar Installation for 115 / 13.8 KV Sub Station Columns.10010001DR5054ST002-2/C (Old) 10010001DR5054ST002-3(A-D)2,700.001,890.00CCF/074CCF Approved12Additional Work - Installation of additional rebar for cantilever beam at Cooling Bed Foundation.10010001DR5005STC-015-916,695.308,649.37CCF/074CCF Approved13Additional Work - Installation of additional rebar at Intermediate Transportation (3/7 & 4/7) Foundation due to changes in drawing by CISDI.10010001DR5008ST002-B; (RFI: 2617 - Rev. 02 dated 24 Oct. 2010 & RFI: 2693 Rev.03 dated 01 Nov. 2010)11,760.008,820.00CCF/074CCF Approved14Additional Work - Modification of Anchor Box due to drawing revision.10010001DR5005ST005-14B (Old) 10010001DR5005ST005-14C(New)4,275.004,275.00CCF/055CCF Approved15Additional Work - Rectification works at Piling and Binding Foundation - OCTG - 110010001DR5008ST009-8A,9A,10A,13A & 16A (Old) 10010001DR5008ST009-8B,9B,10B,13B,& 16B (New)4,470.094,470.00CCF/055CCF Approved16Additional Work - At OCTG - 2 due to drawing revision.10010001DR5008ST014-4-A (Old) 10010001DR5008ST014-4-B(New)7,563.537,563.53CCF/055CCF Approved17Additional Works - Main Utility Electrical Room due to drawing revision.54,461.9550,121.56CCF/055CCF Approved18Additional Work - Rectification work at Zone - 4 Equipment Platform Foundation due to drawing revision.10010001DR5005ST006-3A (Old) 10010001DR5005ST006-3B(New)28,351.8723,078.47CCF/058CCF Approved19Additional Work - At Q.A. Line Foundation " Core Cutting" as per reveised drawing10010001DR5005ST004-4-C (Old) 10010001DR5005ST004-4-D(New)15,110.0014,320.00CCF/058CCF Approved20Modification work at Hot Mill (Zone -2) to accommodate steel column structure.Opening as per drawing is 890mm x 3000mm but in actual column size is about 1400mm x 3150mm in dimension.22,331.8815,400.46CCF/062CCF Approved21Additional Work - At Sliding Chain Foundation due to drawing revision.10010001DR5008ST008-12-C6,916.004,940.00CCF/067CCF Approved22Pile rectification works at Piling , Binding and transfer for LPL area due to drawing revisionPile Cut - Off level revision5,937.654,539.63CCF/067CCF Approved23Additional Work at Sand Filter Bank Foundation due to drawing revision10010001DR5050ST022-6-C (Old) 10010001DR5050ST022-6-D (New)2,602.282,602.28CCF/067CCF Approved24Breaking of Column Sizing Mill Plate (Zone - 8) due to drawing revision.10010001DR5050ST017-C (Old) 10010001DR5050ST017-D (New)3,166.282,746.46CCF/081CCF Approved25Hot Mill Zone - 3 Foundation: Rectification work due to drawing revision.10010001DR5005ST005-12-B (Old) 10010001DR5005ST005-12-C (New)22,312.893,206.28CCF/088CCF Approved26Additional Work - Main Utility Electrical Room Modification Work due to drawing revision.10010001DR5050ST016-4-A (Old) 10010001DR5050ST016-4-B (New)55,320.0035,471.81CCF/089CCF Awaiting Approval27Additional Work - Main Utility Electrical Room Breaking of concrete wall for cable entry due to drawing revision. 10010001DR5050ST016-4-A (Old) 10010001DR5050ST016-4-B (New)7,724.006,925.10CCF/104CCF Approved28Add'l. Work - Core Cutting at Detection Fdn. No. 1 & Tube Collection Fdn. for Pockets10010001DR5006ST004-11-B 10010001DR5006ST006-11-C 4,800.004,800.00CCF/105CCF Approved29Add'l. Work - After Phospating No. 2 - Breaking of existing concrete foundation and making extension as per revised drawing.10010001DR5008ST017-10-A 10010001DR5008ST017-10-B 35,501.2932,729.79CCF/110CCF Approved30ER 06 - Rectification Works- Breaking of Cable Trench due received revised drawing from CISDI10010001DR5006ST007-3-A 10010001DR5006ST014-3-A 48,756.9537,290.89CCF/119CCF Approved31Additional Works at Quenching Pit and OCTG - 1 Foundation. Changes in elevation.10010001DR5008ST013-A (Old) 10010001DR5008ST017-B (New) 4,930.003,174.46CCF/121CCF Approved32Additional Works at Quenching Pit due to drawing revision. Changes in wall elevation.10010001DR5050ST007- B (Old) 10010001DR5050ST007-D (New) 4,668.443,580.69CCF/131CCF Approved33Sacrificial Sheet Pile for the construction of Water Tunnel due to late issuance of drawings and without any prior notice to hold the construction of adjacent structure. (Ref. Variation Order No. 11)909,764.00108,000.00CCF/109CCF Approved34Removable Sheet Pile for the same reason above.(Ref. Variation Order No. 11)133,596.00776167.57CCF/109CCF Approved

TOTAL AMOUNT (SAR)1,499,510.111,210,333.52

Percentage of Acceptance80.72%

NSH Back-Charge CISDI (A)ARCELORMITTAL TUBULAR PRODUCTS PROJECTAL - JUBAIL, KINGDOM OF SAUDI ARABIA

Additional Works Carried by NSH Due to CISDI Drawing Revisions / Errors:

S. No.DescriptionDrawing Reference No.NSH Submitted Claim (SR)CCF Ref.CCF Amount (SAR)NFA Ref.NFA Amount (SAR)Reason / RemarrksAModification Works Due To Drawings Revisions / Errors:1Dismantling Work at Preceding Billet Saw Foundation10010001DR5003ST002-C2 (Old) 10010001DR5003ST002-D2 (New)3,074.69CCF/0333,074.69N / A2,412.40Drawing Revision Cost as per Approved V.O.2Dismantling Work at Detection Foundation100110001DR5006ST005-B12,226.99CCF/03312,226.99N / A8,935.71Drawing Revision Cost as per Approved V.O.3Dismantling Work at 115 / 13.8KV Sub Station Foundation10010001DR5054ST002-A2 (Old); 100110001DR5054ST002-2/C (New)3,569.35CCF/0333,569.35N / A2,162.69Drawing Revision Cost as per Approved V.O.4Additional Works for Cooling Bed Foundation10010001DR5005ST015-6A & 10010001DR5005ST015-6B11,370.42CCF/03211,370.42N / A7,001.00Drawing Revision Cost as per Approved V.O.5Additional Works for Hot Mill Equipment Foundation (Due to Revision)10010001DR5005ST004-28,011.60CCF/0328,011.60N / A3,355.60Drawing Revision Cost as per Approved V.O.6Charges For Rebar Wastage at Intermediate Foundation 1/7 due to drawing revision.10010001DR5008ST002-11 A4,183.25CCF/0744,183.25N / A4,183.25Drawing Revision Cost as per Approved V.O.7Rectification work for Intermediate Transportation Foundation (3/7)10010001DR5008ST002-A8 (Old) 10010001DR5008ST002-B8 (New)32,814.28CCF/07432,814.28N / A12,613.46Drawing Revision Cost as per Approved V.O.8Rectification work for Crane Rail Foundation 10010001DR5003ST009-22,279.27CCF/0672,279.27N / A2,050.52Drawing Revision Cost as per Approved V.O.9Additional Work - Rectification of Sand Filter Foundation due to drawing revision.10010001DR5050ST002-A (Old) 10010001DR5050ST002-B(New)4,824.61CCF/0674,824.61N / A2,855.54Drawing Revision Cost as per Approved V.O.10Additional Rebar Installation for 115 / 13.8 KV Sub Station Columns.10010001DR5054ST002-2/C (Old) 10010001DR5054ST002-3(A-D)2,700.00CCF/0741,890.00N / A1,890.00Drawing Revision Cost as per Approved V.O.11Additional Work - Installation of additional rebar for cantilever beam at Cooling Bed Foundation.10010001DR5005STC-015-916,695.30CCF/07416,695.30N / A8,649.37Drawing Revision Cost as per Approved V.O.12Additional Work - Installation of additional rebar at Intermediate Transportation (3/7 & 4/7) Foundation due to changes in drawing by CISDI.10010001DR5008ST002-B; (RFI: 2617 - Rev. 02 dated 24 Oct. 2010 & RFI: 2693 Rev.03 dated 01 Nov. 2010)11,760.00CCF/07411,760.00N / A8,820.00Drawing Revision Cost as per Approved V.O.13Additional Work - Modification of Anchor Box due to drawing revision.10010001DR5005ST005-14B (Old) 10010001DR5005ST005-14C(New)4,275.00CCF/0554,275.00N / A4,275.00Drawing Revision Cost as per Approved V.O.14Additional Work - Rectification works at Piling and Binding Foundation - OCTG - 110010001DR5008ST009-8A,9A,10A,13A & 16A (Old) 10010001DR5008ST009-8B,9B,10B,13B,& 16B (New)4,470.09CCF/0554,470.00N / A4,470.00Drawing Revision Cost as per Approved V.O.15Additional Work - At OCTG - 2 due to drawing revision.10010001DR5008ST014-4-A (Old) 10010001DR5008ST014-4-B(New)7,563.53CCF/0557,563.53N / A7,563.53Drawing Revision Cost as per Approved V.O.16Additional Works - Main Utility Electrical Room due to drawing revision.54,461.95CCF/05550,121.56N / A50,121.56Drawing Revision Cost as per Approved V.O.17Additional Work - Rectification work at Zone - 4 Equipment Platform Foundation due to drawing revision.10010001DR5005ST006-3A (Old) 10010001DR5005ST006-3B(New)28,351.87CCF/05828,351.87N / A23,078.47Drawing Revision Cost as per Approved V.O.18Additional Work - At Q.A. Line Foundation " Core Cutting" as per reveised drawing10010001DR5005ST004-4-C (Old) 10010001DR5005ST004-4-D(New)15,110.00CCF/05815,110.00N / A14,320.00Drawing Revision Cost as per Approved V.O.19Modification work at Hot Mill (Zone -2) to accommodate steel column structure.Opening as per drawing is 890mm x 3000mm but in actual column size is about 1400mm x 3150mm in dimension.22,331.88CCF/06222,331.88N / A15,400.46Drawing Revision Cost as per Approved V.O.20Additional Work - At Sliding Chain Foundation due to drawing revision.10010001DR5008ST008-12-C6,916.00CCF/0676,916.00N / A4,940.00Drawing Revision Cost as per Approved V.O.21Pile rectification works at Piling , Binding and transfer for LPL area due to drawing revisionPile Cut - Off level revision5,937.65CCF/0675,937.65N / A4,539.63Drawing Revision Cost as per Approved V.O.22Additional Work at Sand Filter Bank Foundation due to drawing revision10010001DR5050ST022-6-C (Old) 10010001DR5050ST022-6-D (New)2,602.28CCF/0672,602.28N / A2,602.28Drawing Revision Cost as per Approved V.O.23Plate Load Bearing TestCCF/07937,800.00N / A37,800.00As per CISDI's request24Breaking of Column Sizing Mill Plate (Zone - 8) due to drawing revision.10010001DR5050ST017-C (Old) 10010001DR5050ST017-D (New)3,166.28CCF/0813,166.28N / A2,746.46Drawing Revision Cost as per Approved V.O.25Installation of additional rebar for cantilever beam at Cooling Bed FoundationCCF/07416,695.30N / A8,649.37Drawing Revision Cost as per Approved V.O.26Rectification work for Intermediate Transportation Foundation (3/7)CCF/07432,814.28N / A12,613.46Drawing Revision Cost as per Approved V.O.27Installation of additional rebar at Intermediate Transportation (3/7 & 4/7) Foundation.CCF/07411,760.00N / A8,820.00Drawing Revision Cost as per Approved V.O.28Hot Mill Zone - 3 Foundation: Rectification work due to drawing revision.10010001DR5005ST005-12-B (Old) 10010001DR5005ST005-12-C (New)22,312.89CCF/08822,312.89N / A3,206.28Drawing Revision Cost as per Approved V.O.29Additional Work - Main Utility Electrical Room Modification Work due to drawing revision.10010001DR5050ST016-4-A (Old) 10010001DR5050ST016-4-B (New)55,320.00CCF/08955,320.00N / A35,471.81Drawing Revision Cost as per Approved V.O.30Additional Work at Hot Mill Zone 3 Slab -Construction Joint.CCF/09831,533.95N / A10,250.27Drawing Revision Cost as per Approved V.O.31Additional Work - Main Utility Electrical Room Breaking of concrete wall for cable entry due to drawing revision. 10010001DR5050ST016-4-A (Old) 10010001DR5050ST016-4-B (New)7,724.00CCF/1047,724.00N / A6,925.10Drawing Revision Cost as per Approved V.O.32Add'l. Work - Core Cutting at Detection Fdn. No. 1 & Tube Collection Fdn. for Pockets10010001DR5006ST004-11-B 10010001DR5006ST006-11-C 4,800.00CCF/1054,800.00N / A4,800.00Drawing Revision Cost as per Approved V.O.33Core Cutting for Bolt Pocket at Q.A. Line Foundation.CCF/10712,310.00N / A12,310.00Extra depth of Pockets34Add'l. Work - After Phospating No. 2 - Breaking of existing concrete foundation and making extension as per revised drawing.10010001DR5008ST017-10-A 10010001DR5008ST017-10-B 35,501.29CCF/11035,501.29N / A32,729.79Drawing Revision Cost as per Approved V.O.35ER 06 - Rectification Works- Breaking of Cable Trench due received revised drawing from CISDI10010001DR5006ST007-3-A 10010001DR5006ST014-3-A 48,756.95CCF/11948,264.76N / A37,290.89Drawing Revision Cost as per Approved V.O.36Additional Works at Quenching Pit and OCTG - 1 Foundation. Changes in elevation.10010001DR5008ST013-A (Old) 10010001DR5008ST017-B (New) 4,930.00CCF/1214,930.00N / A3,174.46Drawing Revision Cost as per Approved V.O.37Additional Works at Quenching Pit due to drawing revision. Changes in wall elevation.10010001DR5050ST007- B (Old) 10010001DR5050ST007-D (New) 4,668.44CCF/1314,668.44N / A3,580.69Drawing Revision Cost as per Approved V.O.38Block work in luie of mass concrete platform.CCF/092939,948.00N / A939,948.00Cost as per Approved V.O.39Backfilling for Steel Structure Erection due to wrong sequence of work at Scale Flume Channel; RHF Inner Side and Water Tunnel Area.CCF/100172,706.56N / A73,838.79Wrong sequence of work40Backfilling Works at Water Tunnel and Main Plant Building along grid D/E - 7/13 to serve as platform in the erection of steel structure.CCF/112186,932.94N / A186,932.94Cost as per Approved V.O.41Additional Work at Quenching Pit and OCTG - 1 Foundation due to drawing revision.CCF/1314,668.44N / A3,580.69Drawing Revision42Cost Difference Of 20mm dia. To 12mm dia. MS Rebar At Main BuildingCCF/16550,225.00NFA No. 28950,225.00Changes of rebar from 12 mm dia. (Early revision) to 20 mm dia. MS Rebar for the expansion joint dowel as pet the approved revises drawing of CISDI43Hilti Hit Anchor Bolt For Main Substation55535CCF/17055,535.00NFA No. 30755,535.00As per revises IFI drawing by CISDI, TQ SRFTI No. 1028 & SRFTI No. 104844Cable Trench construction inside Main Substation Building as per drawing revision.CCF/1745,097.97NFA No. 2854,844.23As per revises drawing by CISDI45Core cutting / drilling at Water Tunnel Top Slab for pipe sleeves and duct opening as per revised drawing..CCF/1765,350.00NFA No. 2855,350.00As per revises drawing by CISDI46Additional Work at Billet Saw Foundation 2/3 - Core drilling for additional anchor bolts pockets not shown in previous IFI drawing.CCF/2175,733.35NFA No. 4765,733.35Error in CISDI Drawing47Blast Resistant Door"Single Leaf" For Main substation And Electrical Room ER05CCF/22549,628.20NFA No. 48246,937.01As per CISDI IFI drawing48Modification of shear key and pockets at Cooling Bed # 2 as per Mechanical drawing to equipment erection. (Drawing mistake from CISDI)CCF/2283,200.00NFA No. 4822,288.00Difference between Mechanical and Civil Drawing49Concete breaking around electrical conduits to create small trench to reroute its location due to descripancy between mechanical and civil drawing .CCF/2305,964.00Discrepancy between the MEP drawing and civil drawing due to mistake of CISDI as per attached email from engineering50Additional Work at Charging Platform Foundation - Diamond core drilling for anchor bolts pockets & shear keys new locations.CCF/23214,880.00NFA No. 47613,693.40CISDI drawing layout for the bolts as casted do not conform to the Mechanical drawing51Core cutting / drilling for new anchor bolts location at Cooling Bed 1 & 2 and at Straightener Foundation No. 2 HT due to conflict between civil and mechanical drawings.CCF/238 Rev.1170,664.86Mistake between mechanical and civil drawing52Modification work - Slab thickening to accommodate anchor bolts height at Hot Mill Area as per TQ SRFTI-0983. Chipping of existing foundation and drilling holes for providing rebar and fixing with chemical bond as per TQ SRFTI-1380. All oof these were due to errors on CISDI issued drawings.CCF/24328,635.38Modification of Piping drawing and consequent core drilling53Various additional works at different locations:Mistake between mechanical and civil drawinga)Core cutting at Scale Flume Channel wall for pipe sleeves as per TQ SRFTI No. 1353CCF/2471,420.00Non respect of SEC Standard for cable entrance.b)Core cutting of two pockets at QA Line as per revised drawing by CISDI as per TQ SRFTI No. 1416.CCF/247953.67Late delivery of Equipment supplier data. Can't be charger on CISDIc)Breaking the concrete hollow block wall for 200 mm dia. pipe sleeves (6 nos.) and 120 mm dia. curing in transformer room concrete wall for 3 x 4 nos. PVC conduit pipe at Main Substation as per TQ SRFTI No. 1419 & No. 1391. CCF/2472,458.00Revision of trench after construction: Interference between trench and staircase foundationd)Core cutting for additional pipe sleeves at Physical Lab. Building as per revised drawing (Reference: Dwg. no. 1001000DR5058ST001-9-C & 1001000DR5058ST001-9-D).CCF/2472,768.00Did not integrate the trench in the design of the openinge)Concrete foundation breaking (portion only) to accommodate trench at Main Plant Area (Reference: Dwg. no. 1001000DR5008ST020-4-C & TQ SRFTI 1334 dated 17/12/2011).CCF/2471,800.00Mistake in the drawing by IFI Drawing f)Wall breaking for cable trench opening at Sea Water Cooling System as per TQ SRFTI No. 1345.CCF/2473,673.31Mistake in the drawing by IFI Drawing g)Breaking of Foundation base for motor erection as per SCF No. MEIP-038 & TQ SRFTI MEC No. 073CCF/2471,900.00Mistake in the drawing by IFI Drawing

TOTAL AMOUNT (SAR)452,709.862,304,123.401,805,515.46

NSH Back-Charge CISDI (B)ARCELORMITTAL TUBULAR PRODUCTS PROJECTAL - JUBAIL, KINGDOM OF SAUDI ARABIA

Additional Works Carried by NSH Due to CISDI Drawing Revisions / Errors:

S. No.DescriptionDrawing Reference No.NSH Submitted Claim (SR)CCF Ref.CCF Amount (SAR)NFA Ref.NFA Amount (SAR)Reason / RemarksBAdditional Works due to wrong Drawing Sequense issuance:45Sacrificial Sheet Pile for the construction of Water Tunnel due to late issuance of drawings and without any prior notice to hold the construction of adjacent structure. (Ref. Variation Order No. 11)909,764.00CCF/109108,000.00N / A108,000.00Cost as per Approved V.O.46Removable Sheet Pile for the same reason above.(Ref. Variation Order No. 11)133,596.00CCF/109776,167.57N / A776,167.57Cost as per Approved V.O.TOTAL AMOUNT (SAR)1,043,360.00884,167.57884,167.57

NSH Back-Charge SIDARCELORMITTAL TUBULAR PRODUCTS PROJECTAL - JUBAIL, KINGDOM OF SAUDI ARABIA

Additional Works Carried by NSH Due to SID Drawing Revisions / Errors:

S. No.DescriptionDrawing Reference No.NSH Submitted Claim (SR)Amount (SR)Ref. CCF No. NFA Ref.NFA Amount (SAR)Reason / RemarrksAModification Works Due To Drawings Revisions / Errors:1Casting of pumps pedestals for pump installation at Main Pump House Building. This was due to wrong assignment of drawing.20,291.79CCF/228Cost Subject to Negotiationw/ NSH2Drilling for 32 nos. 28mm diameter for chemical anchor bolts at WTP Area 100 as per AMJ instruction SI - P - 018 due to wrong SID civil assignment drawing.10010001DR5003ST002-C2 (Old) 10010001DR5003ST002-D2 (New)3,074.691,920.00CCF/238 Rev.1Cost Subject to Negotiationw/ NSH3Core cutting for opening of 500mm diameter at 700mm thick wall on WTP Area 100 as per SCF No. MEIP - 053100110001DR5006ST005-B12,226.992,137.00CCF/245Cost Subject to Negotiationw/ NSH4Core cutting to accommodate 1100mm diameter pipe sleeve at 300mm thick wall of Sea Water Cooling System as per drawing revisions.10010001DR5054ST002-A2 (Old); 100110001DR5054ST002-2/C (New)3,569.3520,367.75CCF/245Cost Subject to Negotiationw/ NSHTOTAL AMOUNT (SAR)18,871.0344,716.54

IBSF Back-Charge CISDIARCELORMITTAL TUBULAR PRODUCTS PROJECTAL - JUBAIL, KINGDOM OF SAUDI ARABIA

Additional Works Carried by IBSF Due to CISDI Drawing Revisions / Errors:

S. No.DescriptionDrawing Reference No.CCF Ref.CCF Amount (SAR)NFA Ref.NFA Amount (SAR)ReasonAModification Works Due To Drawings Revisions / Errors:1Rectification Works of Frame Columns AAD-7 & AAD-8.CCF/054131,280.0076,659.00The frame columns has been delivered and erected after CISDI issued revision drawing.2Rectification of Purlin CB1441 & CB1310.CCF/06335,675.0032,255.00Horizontal brace connection plate fabricated incorrect due to the error in the drawing.3Rectification of Column Bracket and Plates to Installed Roof Beam.CCF/07319,860.0016,760.00The connection holes between column bracket and roof beam missing.4Rectification of Column Bracing and Frame Column (AAg-1). CCF/0774,825.004,425.00The connection holes between column bracing and frame column missing.5Cradle Frame for Lifting of Box Girder (BAD-20 & BAC-23).CCF/096180,290.00154,442.00Due to unavailability of lifting lugs to install box girders.6Rectification of Column Bracings and Frame Columns (AAc-6,AAc-9 & AAc-10).CCF/1013,435.003,135.00The connection holes between column bracing and frame column missing.7Rectification Works of Frame Columns (ST003&ST007), Purlin (ST005), Auxilliary Truss (ST006).CCF/12317,328.00NFA/35414,868.00The connection holes from frame colums,purlins and auxilliary truss are missing.9Rectification Works for Eave & Valley Gutter at Site.CCF/164115,500.00NFA/31250,795.00Cutting the bottom plate of the gutter to suit the gutter at column.10Rectification of Frame Column (AAC-26) and Roof Beams (CA2.31 & CA2.36)CCF/19216,325.00NFA/31812,125.00Incorrect holes at box girder and connection holes from roof beam and purlins are missing.11Rectification of Frame Column (AAC-7 & AAC-8),Column Bracing (AZF-14,AZF-19 & AZF-17) and Roof Beams (CA3.44)CCF/20326,029.00NFA/35426,029.00Column frame and column bracing holes not matching.12Rectification of Purlin (CB1477),Additional of Roof Panel and Removal of Roof Sheeting & Bracing.CCF/21055,873.00NFA/38625,073.00Incorrect position of connection plate for horizontal brace and purlin.13Rectification of Handrail (G.L. A/1-13 & G.L. A/14-18).CCF/21376,400.00NFA/46773,400.00The column along G.L. A/14-18 wider than column G.L. A/1-1314Rectification of Column (AAK-20),Stair No.263LA-1(G.L. K/30) and Removal of Roof Sheeting & Bracing for MEIP Works.CCF/22154,126.00NFA/4474,026.00Column frame and column bracing holes not matching.15Rectification of Stairs @ G.L. D (Steel Ladder to Crane Service - Platform 1)CCF/22286,280.00NFA/44786,280.00Staircase location is wrong.16Relocation of the Installed Steel Ladders.CCF/24070,781.00CCF approved awaiting for works completed and agreed amount.17Rectification of columns to install the visit platformCCF/242299,020.00Awaiting for CCF approval.18Removed and Reinstalled chequered plates and column bracing for chimney opening.CCF/24472,800.00CCF approved awaiting for works completed and agreed amount.19Modification of Wall Frame at G.L. A/7-8.CCF/24614,020.00CCF approved awaiting for works completed and agreed amount.20Modification of Gutter DE-7 at G.L. A/13-14 and Additional Support at G.L. A/14 as per latest revision.CCF/25830,180.00CCF on HOLD awaiting for engineering reply.

TOTAL AMOUNT (SAR)1,310,027.00580,272.00

SummaryARCELORMITTAL TUBULAR PRODUCTS PROJECTAL - JUBAIL, KINGDOM OF SAUDI ARABIA

Summary For Back-Charged Amount To CISDI

S. No.DescriptionFinal Back-Charged Amount Remarks($)(SAR)ANSH - Modification Works Due To Drawings Revisions / Errors:481,470.791,805,515.46BNSH - Additional Works due to wrong Drawing Sequense issuance:235,778.02884,167.57CIBSF - Modification Works Due To Drawings Revisions / Errors:154,739.20580,272.00TOTAL BACK-CHARGED AMOUNT 871,988.013,269,955.03