TRANSNET SOC LTD
Registration Number 1990/000900/30
[hereinafter referred to as Transnet]
REQUEST FOR QUOTATION [RFQ] No GSM/15/11/1351
FOR THE PROVISION OF: NATCOR OCCUPATIONS OPTIMISATION
EVALUATION FOR A PERIOD OF 12 MONTHS
FOR DELIVERY TO: TENDER BOX 48th FLOOR
TRANSNET CORPORATE CENTRE
CARLTON CENTRE
150 COMMISSIONER STREET
JOHANNESBURG
2001
ISSUE DATE: 15 January 2016
COMPULSORY BRIEFING SESSION: 21 January 2016
CLOSING DATE: 04 February 2016
CLOSING TIME: 12:00
NOTE: FOR A COPY OF THE RFQ, PLEASE SEND AN EMAIL REQUEST TO
Transnet Request for Quotation No GSM/15/11/1351 Page 2 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Section 1
NOTICE TO BIDDERS
_____________________________________________________________________________________
Quotations which must be completed as indicated in Section 2 of this RFQ are to be submitted as follows:
METHOD: Hand deliver or Postal Address (no-email will be accepted and late tenders
will not be accepted)
CLOSING VENUE: The Tender Box, 48th Floor, Transnet Corporate Centre, Carlton Centre,
150 Commissioner Street, Johannesburg, 2001
_____________________________________________________________________________________
1 RESPONSES TO RFQ
Responses to this RFQ [Quotations] must not include documents or reference relating to any other
quotation or proposal. Any additional conditions must be embodied in an accompanying letter.
2. FORMAL BRIEFING
A Compulsory pre-proposal RFQ Briefing Session will be conducted at Transnet Corporate Centre, 8th
Floor, Room 809, 150 Commissioner Street, Johannesburg on the 21 January 2016, at 10h00 for a
period of ± 2 hours. [Respondents to provide own transportation and accommodation]. The briefing
session will start punctually and information will not be repeated for the benefit of Respondents arriving
late.
2.1 A Certificate of Attendance in the form set out in Section 5 hereto must be completed and
submitted with your Proposal as proof of attendance is required for a Compulsory RFQ
briefing.
2.2 Respondents failing to attend the compulsory RFQ briefing will be disqualified.
2.3 Respondents without a valid RFQ document in their possession will not be allowed to attend the
RFQ briefing.
2.4 Transnet will not be held responsible if any Bidder who did not attend the compulsory session
subsequently feels disadvantaged as a result thereof.
2.5 Respondents failing to attend the compulsory RFQ briefing will be disqualified.
2.6 The briefing session will start punctually at 10:00 and information will not be repeated for the
benefit of Respondents arriving late.
3 BROAD-BASED BLACK ECONOMIC EMPOWERMENT [B-BBEE]
Transnet fully endorses and supports the Government’s Broad-Based Black Economic Empowerment
Programme and it would therefore prefer to do business with local business enterprises who share
these same values. Transnet will accordingly allow a “preference” to companies who provide a valid B-
BBEE Verification Certificate. All procurement transactions will be evaluated accordingly.
Transnet Request for Quotation No GSM/15/11/1351 Page 3 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
3.1 B-BBEE Scorecard and Rating
As prescribed in terms of the Preferential Procurement Policy Framework Act (PPPFA), Act 5 of
2000 and its Regulations, Respondents are to note that the following preference point systems
are applicable to all bids:
the 80/20 system for requirements with a Rand value of up to R1 000 000 (all applicable
taxes included); and
the 90/10 system for requirements with a Rand value above R1 000 000 (all applicable
taxes included).
Bidders are to note that if the 90/10 preference point system is stipulated in this RFQ
and all Bids received are equal to or below R1 000 000.00, the RFQ must be cancelled.
The value of this bid is estimated to exceed R1 000 000 (all applicable taxes included); and
therefore the 90/10 system shall be applicable.
When Transnet invites prospective suppliers to submit Proposals for its various expenditure
programmes, it requires Respondents to have their B-BBEE status verified in compliance with the
Codes of Good Practice issued in terms of the Broad Based Black Economic Empowerment Act
No. 53 of 2003.
The Department of Trade and Industry recently revised the Codes of Good Practice on 11
October 2013 [Government Gazette No. 36928]. The Revised Codes will replace the Black
Economic Empowerment Codes of Good Practice issued on 9 February 2007. The Revised Codes
provide for a one year transitional period starting 11 October 2013. During the transitional
period, companies may elect to be measured in terms of the Revised Codes or the 2007 version
of the Codes. After the first year of the implementation of the Revised Codes, B-BBEE
compliance will be measured in terms of the Revised Codes without any discretion. Companies
which are governed by Sector-specific Codes will be measured in terms of those Sector Codes.
As such, Transnet will accept B-BBEE certificates issued based on the Revised Codes. Transnet
will also continue to accept B-BBEE certificates issued in terms of the 2007 version of the Codes
provided it was issued before 10 October 2014. Thereafter, Transnet will only accept B-BBEE
certificates issued based on the Revised Codes.
Respondents are required to complete Annexure A [the B-BBEE Preference Point Claim Form]
and submit it together with proof of their B-BBEE Status as stipulated in the Claim Form in order
to obtain preference points for their B-BBEE status.
Note: Failure to submit a valid and original B-BBEE certificate or a certified copy
thereof at the Closing Date of this RFQ will result in a score of zero being allocated
for B-BBEE.
[Refer clause 19 below for Returnable Documents required]
4 Communication
Respondents are warned that a response will be liable for disqualification should any attempt be made
by a Respondent either directly or indirectly to canvass any officer(s) or employee of Transnet in
respect of this RFQ between the closing date and the date of the award of the business.
Transnet Request for Quotation No GSM/15/11/1351 Page 4 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
A Respondent may, however, before the closing 04 February 2016 at 12:00, direct any written
enquiries relating to the RFQ to the following Transnet employee:
Name: Abednego Marosane Email: [email protected]
Respondents may also, at any time after the closing date of the RFQ, communicate with the Secretariat
of the Transnet Acquisition Council on any matter relating to its RFQ response:
Telephone 011 308 3528 Email: [email protected]
5 Tax Clearance
The Respondent’s original and valid Tax Clearance Certificate must accompany the Quotation. Note that
no business shall be awarded to any Respondent whose tax matters have not been declared by SARS to
be in order.
6 VAT Registration
The valid VAT registration number must be stated here: _______________________ [if applicable].
7 Legal Compliance
The successful Respondent shall be in full and complete compliance with any and all applicable national
and local laws and regulations.
8 Changes to Quotations
Changes by the Respondent to its submission will not be considered after the closing date and time.
9 Pricing
All prices must be quoted in South African Rand on a fixed price basis, excluding VAT.
10 Prices Subject to Confirmation
Prices quoted which are subject to confirmation will not be considered.
11 Negotiations
Transnet reserves the right to undertake post-tender negotiations with selected Respondents or any
number of shortlisted Respondents.
12 Binding Offer
Any Quotation furnished pursuant to this Request shall be deemed to be an offer. Any exceptions to
this statement must be clearly and specifically indicated.
13 Disclaimers
Transnet is not committed to any course of action as a result of its issuance of this RFQ and/or its
receipt of a Quotation in response to it. Please note that Transnet reserves the right to:
modify the RFQ’s goods / service(s) and request Respondents to re-bid on any changes;
reject any Quotation which does not conform to instructions and specifications which are detailed
herein;
disqualify Quotations submitted after the stated submission deadline;
not necessarily accept the lowest priced Quotation;
Transnet Request for Quotation No GSM/15/11/1351 Page 5 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
reject all Quotations, if it so decides;
place an order in connection with this Quotation at any time after the RFQ’s closing date;
award only a portion of the proposed goods / service/s which are reflected in the scope of this
RFQ;
split the award of the order/s between more than one Supplier/Service Provider; or
make no award at all.
Transnet reserves the right to award business to the highest scoring bidder/s unless objective criteria
justify the award to another bidder.
Transnet reserves the right to lower the threshold for Technical by 10% should no Bidders pass the
predetermined minimum threshold in respect of Technical.
14 Transnet’s supplier integrity pact
Transnet’s Integrity Pact requires a commitment from suppliers and Transnet that they will not engage
in any corrupt and fraudulent practices, anti-competitive practices; and act in bad faith towards each
other. The Integrity Pact also serves to communicate Transnet’s Gift Policy as well as the remedies
available to Transnet where a Respondent contravenes any provision of the Integrity Pact.
Respondents are required to familiarise themselves with the contents of the Integrity Pact which is
available on the Transnet Internet site [www.transnet.net/Tenders/Pages/default.aspx] or on request.
Furthermore, Respondents are required to certify that they have acquainted themselves with all the
documentation comprising the Transnet Integrity Pact and that they fully comply with all the terms and
conditions stipulated in the Transnet Supplier Integrity Pact as follows:
YES NO
Should a Respondent need to declare previous transgressions or a serious breach of law in the
preceding 5 years as required by Annexure B to the Integrity Pact, such declaration must accompany
the Respondent’s bid submission.
15 Evaluation Criteria
Transnet will utilise the following criteria [not necessarily in this order] in choosing a Supplier/Service
Provider, if so required:
Transnet Request for Quotation No GSM/15/11/1351 Page 6 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
STAGE ONE: Test for Administrative Responsiveness
The test for administrative responsiveness will include the following:
Administrative Responsiveness Check
Whether the Bid has been lodged on time
Whether all returnable documents and/or schedules [where applicable] were completed and
returned by the closing date and time
Verify the validity of all returnable documents
The test for Administrative Responsiveness [Stage One] must be passed for a
Respondent’s Proposal to progress to Stage Two for Substantive Responsiveness Check
STAGE TWO: Test for Substantive Responsiveness
The test for substantive responsiveness will include the following:
Check for Substantive Responsiveness
Whether any general pre-qualification criteria set by Transnet, have been met
Whether the Bid contains a priced offer
Whether the Bid materially complies with the scope and/or specification given
The test for Substantive Responsiveness [Stage Two] must be passed for a Respondent’s
Proposal to progress to Stage Three for Technical Evaluation
Stage 1 Stage 2 Stage 3 Stage 4
Administrative
Responsiveness Substantive
Responsiveness
70% Minimum Threshold
Weighted Scoring / 100
Price (90)
B-BBEE (10) Scorecard
RETURNABLE DOCUMENTS
& SCHEDULES
PRE- QUALIFICATION
TECHNICAL WEIGHTED
SCORE
Transnet Request for Quotation No GSM/15/11/1351 Page 7 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
STAGE THREE: Minimum Threshold of 70% for Technical Criteria and Functional Requirements
The test for the Technical/Functional threshold will include the following:
Technical Criteria Scoring Guideline Weighting
Resources – Competence of Engineers
proposed
Bidder to provide detailed CV’s of
Engineers proposed and project
organogram showing resources
allocated. Scoring will be based on
average simulation experience of
Engineers assigned to the project.
0. Non-responsive
1. 1 to 3 year’s experience in respect of rail
simulation projects, and no experience
using OpenTrack.
2. 1 to 3 years’ experience in respect of rail
simulation projects, with at least 1 project
using OpenTrack.
3. 3 to 5 years’ experience in respect of rail
simulation projects, with at least 2 projects
using OpenTrack.
4. 5 years’ experience in respect of rail
simulation projects with more than 2
projects using OpenTrack.
40
Competence of methodology proposed
Bidder to provide outline of factors to
consider when train plan optimisation is
done
0. Non-responsive
1. Proposed methodology provides input on
network only.
2. Proposed methodology provides input on
network and occupation variation inputs.
3. Proposed methodology shows how train
plan input will be iterated with current
capacity constraints.
4. Proposed methodology shows how future
train plan (with future volume mix and
future network design) will be developed
iteratively.
20
Transnet Request for Quotation No GSM/15/11/1351 Page 8 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
The minimum threshold of 70% for Technical/Functionality Evaluation [Stage Three]
must be met or exceeded for a Respondent’s Proposal to progress to Stage Four for
Final evaluation (Price and BBBEE)
STAGE FOUR: Evaluation and Final Weighted Scoring
Price Criteria [Weighted score 90 points]:
Evaluation Criteria
Commercial offer
Transnet will utilise the following formula in its evaluation of Price:
PS = 90
Where:
Ps = Score for the Bid under consideration
Pt = Price of Bid under consideration
Pmin = Price of lowest acceptable Bid
Previous rail system experience shown
through the total number of rail capacity
optimisation projects applying
simulations, executed by the
organisation
Bidder to provide detail list of previous
projects showing relevant project
experience. Details to be included:
Project name
Project description
Client
Project duration
Project Budget
Contact person
0. No previous projects executed by the
organisation.
1. One to three projects executed by the
organisation.
2. Four to Six projects executed by
organisation.
3. Seven to Ten projects executed by
organisation.
4. Over Ten projects executed by
organisation.
40
Total Points 100
Minimum Threshold 70%
Transnet Request for Quotation No GSM/15/11/1351 Page 9 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Broad-Based Black Economic Empowerment criteria [Weighted score 10 points]
B-BBEE - current scorecard / B-BBEE Preference Points Claims Form [Annexure A]
Preference points will be awarded to a bidder for attaining the B-BBEE status level of contribution in
accordance with the table indicated in Annexure A:
B-BBEE Status Level of Contributor Number of Points
[Maximum 10]
1 10
2 9
3 8
4 5
5 4
6 3
7 2
8 1
Non-compliant contributor 0
Evaluation Criteria Final Weighted Scores
Price 90
B-BBEE - Scorecard 10
TOTAL SCORE: 100
16 Validity Period
Transnet desires a validity period of 120 [hundred and twenty] days from the closing date of this RFQ.
17 Banking Details
BANK: ________________________________________________
BRANCH NAME / CODE: __________________________________
ACCOUNT HOLDER: _____________________________________
ACCOUNT NUMBER: _____________________________________
18 Company Registration
Registration number of company / C.C. __________________________________
Registered name of company / C.C. __________________________________
19 Disclosure of Prices Quoted
Respondents must indicate here whether Transnet may disclose their quoted prices and conditions to
other Respondents:
YES NO
Transnet Request for Quotation No GSM/15/11/1351 Page 10 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
20 Returnable Documents
Returnable Documents means all the documents, Sections and Annexures, as listed in the tables
below.
a) Respondents are required to submit with their Quotations the Mandatory Returnable
Documents, as detailed below.
Failure to provide all these Returnable Documents at the Closing Date and time of this
RFQ will result in a Respondent’s disqualification. Respondents are therefore urged to
ensure that all these Documents are returned with their Quotations.
All Sections, as indicated in the footer of each page, must be signed, stamped and dated by the
Respondent. Please confirm submission of these Mandatory Returnable Documents by so
indicating [Yes or No] in the table below:
Mandatory Returnable Documents Submitted
[Yes or No]
SECTION 2 : Quotation Form
Annexure B: Scope of Work
Bidder to provide detailed CV’s of Engineers proposed and project organogram showing
resources allocated.
Bidder to provide Methodology proposed showing outline of factors to consider when train
plan optimisation is done.
Bidder to provide detail list of previous projects showing relevant project experience
Details to be included:
Project name
Project description
Client
Project duration
Project Budget
Contact person
b) In addition to the requirements of section (a) above, Respondents are further required to submit
with their Quotations the following Essential Returnable Documents as detailed below.
Failure to provide all these Returnable Documents may result in a Respondent’s
disqualification. Respondents are therefore urged to ensure that all these documents
are returned with their Quotations.
Transnet Request for Quotation No GSM/15/11/1351 Page 11 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
All Sections, as indicated in the footer of each page, must be signed, stamped and dated by the
Respondent. Please confirm submission of these essential Returnable Documents by so indicating
[Yes or No] in the table below:
Essential Returnable Documents Submitted
[Yes or No]
SECTION 1 : Notice to Bidders
- Valid and original B-BBEE Verification Certificate or certified copy thereof [Large
Enterprises and QSEs]
Note: failure to provide a valid B-BBEE Verification Certificate at the closing date and
time of the RFQ will result in an automatic score of zero for preference
- Valid and original B-BBEE certificate/sworn affidavit or certified copy thereof from
auditor, accounting officer or SANAS accredited Verification Agency [EMEs]
Note: failure to provide a valid B-BBEE Verification Certificate at the closing date and
time of the RFQ will result in an automatic score of zero being allocated for
preference
- In the case of Joint Ventures, a copy of the Joint Venture Agreement or written
confirmation of the intention to enter into a Joint Venture Agreement
- Original valid Tax Clearance Certificate [Consortia / Joint Ventures must submit a
separate Tax Clearance Certificate for each party]
SECTION 3 : Standard Terms and Conditions of Contract for the Supply of Services to
Transnet
SECTION 4 : Vendor Application Form
- Original cancelled cheque or bank verification of banking details
- Certified copies of IDs of shareholder/directors/members [as applicable]
- Certified copies of the relevant company registration documents from Companies and
Intellectual Property Commission (CIPC)
- Certified copies of the company’s shareholding/director’s portfolio
- Entity’s letterhead
- Certified copy of VAT Registration Certificate [RSA entities only]
- Certified copy of valid Company Registration Certificate [if applicable]
- A signed letter from Respondent’s auditor or accountant confirming most recent
annual turnover figures
ANNEXURE A – B-BBEE Preference Points Claim Form
Transnet Request for Quotation No GSM/15/11/1351 Page 12 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Section 2
QUOTATION FORM
I/We________________________________________________________________________________
_
hereby offer to supply the goods/services at the prices quoted in the Price Schedule below, in
accordance with the conditions related thereto.
I/We agree to be bound by those terms and conditions in:
the Standard Terms and Conditions for the Supply of Goods or Services to Transnet [Section 3
hereof]; and
any other standard or special conditions mentioned and/or embodied in this Request for Quotation.
I/We accept that unless Transnet should otherwise decide and so inform me/us, this Quotation [and, if
any, its covering letter and any subsequent exchange of correspondence], together with Transnet’s
acceptance thereof shall constitute a binding contract between Transnet and me/us.
I/We further agree that if, after I/we have been notified of the acceptance of my/our Quotation, I/we
fail to deliver the said goods/service/s within the delivery lead-time quoted, Transnet may, without
prejudice to any other legal remedy which it may have, cancel the order and recover from me/us any
expenses incurred by Transnet in calling for Quotations afresh and/or having to accept any less
favourable offer.
Transnet Request for Quotation No GSM/15/11/1351 Page 13 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Price Schedule
I/We quote as follows for the services required, on a “fixed price” basis, excluding VAT:
Items Description Of Services
Total Cost (excl. VAT)
1 Data gathering and building of model
2 Running scenarios 1,2 & 3, plus its optimal occupation
rules
3 Running scenarios 4-8, plus its optimal occupation
rules
4 Report & review
5 Allowance for disbursements
TOTAL COST (excl. VAT) for a period of
twelve(12) months
DISCOUNT(S)
GRAND TOTAL (incl. VAT) for a period of
twelve(12) months
Optional Pricing:
Items Description Of Services
Total Cost (excl. VAT)
A Updating model for CBTA (Scenario 9) and
determining optional occupation rules
B High level analysis of the impact on maintenance
organisation(scenarios 3 & 6)
TOTAL COST (excl. VAT) for a period of
twelve(12) months
DISCOUNT(S)
GRAND TOTAL (incl. VAT) for a period of
twelve(12) months
(Bidders are required to provide a clear breakdown of the professional fees and structure, including
disbursements)
Disbursements must be based on estimated costs but must not exceed 10% of the total
cost for services proposed. Payment of actual disbursements will be subject to Transnet’s
policies and/or procedures.
Transnet Request for Quotation No GSM/15/11/1351 Page 14 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Notes to Pricing:
a) All Prices must be quoted in South African Rand, exclusive of VAT
b) To facilitate like-for-like comparison bidders must submit pricing strictly in accordance with this
price schedule and not utilise a different format. Deviation from this pricing schedule could result
in a bid being disqualified.
c) Please note that should you have offered a discounted price (s), Transnet will only consider such
price discount(s) in the final evaluation stage if offered on an unconditional basis.
d) Disbursement costs must be in line with Transnet business travel policy.
Transnet Request for Quotation No GSM/15/11/1351 Page 15 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Section 3
STANDARD TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS OR SERVICES TO TRANSNET
A Supplier/Service Provider shall be obliged to adhere to the Standard Terms and Conditions for
the Supply of Goods and Services to Transnet as expressed hereunder. Should the Respondent
find any condition(s) unacceptable, it should indicate which condition(s) is/are unacceptable
and offer an alternative(s). A Quotation submitted by a Respondent will be subjected to review
and acceptance or rejection of its proposed contractual terms and conditions by Transnet’s
Legal Counsel, prior to consideration for an award of business.
1 SOLE AGREEMENT
Unless otherwise agreed in writing, these terms [Terms and each Term] and Transnet’s purchase
order(s) [Order or Orders] represent the only conditions upon which Transnet SOC Ltd [Transnet]
procures goods [the Goods] or services [the Services] specified in the Order from the person to whom
the Order is addressed [the Supplier/Service Provider]. Transnet does not accept any other
conditions which the Supplier/Service Provider may specify, unless otherwise agreed to by Transnet in
writing. In the event of any inconsistency between these Terms and any Order, these Terms shall take
precedence.
2 CONFORMITY WITH ORDER
Goods/Services shall conform strictly with the Order. The Supplier/Service Provider shall not vary the
quantities specified and/or the specification, if any, stipulated in the Order, without the prior written
consent of Transnet. The Supplier/Service Provider warrants that the Goods/Services shall be fit for their
purpose and of satisfactory quality.
3 DELIVERY AND TITLE
3.1 The delivery dates and addresses are those in the Order. Time shall be of the essence in respect
of the Supplier’s/Service Provider’s obligations under the Order.
3.2 The Supplier/Service Provider will not be excused for delay in delivery or performance except due
to circumstances outside its control and then only subject to the Supplier/Service Provider having
notified Transnet in writing on becoming aware of such circumstances. Transnet may terminate
an Order, in whole or in part, without incurring any liability to the Supplier/Service Provider if such
a delay becomes, in Transnet’s absolute opinion, significant.
3.3 If on delivery, the Goods/Services do not conform to the Order, Transnet may reject the
Goods/Services and the Supplier/Service Provider shall promptly rectify any defects or in
Transnet’s opinion, supply appropriate replacement Goods/Services at the Supplier’s/Service
Provider’s expense within the specified delivery times, without any liability due by Transnet.
4 PRICE AND PAYMENT
4.1 Prices specified in an Order cannot be increased. Payment for the Goods/Services shall be made
by Transnet against an original undisputed invoice(s) [a Tax Invoice], supporting documentation
and month-end statement from the Supplier/Service Provider. Tax Invoices plus supporting
documentation shall be posted to the address shown in the Order.
Transnet Request for Quotation No GSM/15/11/1351 Page 16 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
4.2 Payment of the Supplier’s/Service Provider’s valid Tax Invoice(s) will be made by Transnet in the
South African currency and on the terms stated in the Order, the standard payment terms being
30 [thirty] days from date of receipt by Transnet of a month-end statement, unless otherwise
agreed to in writing. Transnet shall arrange for payment of such Tax Invoices and any pre-
authorised additional expenses incurred, provided that the authorised expenses are supported by
acceptable documentary proof of expenditure incurred [where this is available]. Any amounts due
in terms of these Terms shall be paid to the Supplier/Service Provider, taking into account any
deduction or set-off and bank charges.
5 PROPRIETARY RIGHTS LIABILITY
If any allegations should be made or any claim asserted against Transnet that ownership of, or any act or
omission by Transnet in relation to Goods/Services or any written material provided to Transnet relating
to any Goods/Services or pursuant to an Order being a violation or infringement of any third party’s
contractual, industrial, commercial or intellectual property rights including but not limited to any patent,
registered design, design right, trade mark, copyright or service mark on any application thereof, the
Supplier/Service Provider hereby indemnifies Transnet against and hold it harmless from any and all
losses, liabilities, costs, claims, damages and expenses [including any legal fees] arising directly or
indirectly from such allegation or claim provided that this indemnity shall not apply where the allegation
or claim arises solely as a result of the Supplier/Service Provider following a design or process originated
and furnished by Transnet. The Supplier/Service Provider shall either
a) procure for Transnet the right to continue using the infringing Goods; or
b) modify or replace the Goods/Services so that they become non-infringing,
provided that in both cases the Goods/Services shall continue to meet Transnet’s requirements and any
specifications stipulated in the Order. Should neither option be possible, the Supplier/Service Provider
may remove, with Transnet’s prior written consent, such Goods/Services and will pay to Transnet a sum
equivalent to the purchase price. If Transnet refuses to give such consent, the Supplier/Service Provider
shall have no liability in respect of any continued use of the infringing Goods/Services after
Supplier’s/Service Provider’s prior written request to remove the same.
6 PROPRIETARY INFORMATION
All information which Transnet has divulged or may divulge to the Supplier/Service Provider and any
information relating to Transnet’s business which may have come into the Supplier’s/Service Provider’s
possession whilst carrying out an Order, and the existence of the Order, shall be treated by the
Supplier/Service Provider as confidential information and shall not, without Transnet’s prior written
consent, be disclosed to any third party, or be used or copied for any purposes other than to perform the
Order. This clause does not apply to information which is public knowledge or available from other
sources other than by breach of this Term. Upon request by Transnet, the Supplier/Service Provider shall
return all materials issued pursuant to the Order and, pending this, shall protect Transnet’s rights in any
such materials. Such confidential information shall at all material times be the property of Transnet.
Transnet Request for Quotation No GSM/15/11/1351 Page 17 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
7 PUBLICITY
The Supplier/Service Provider shall not name Transnet or use its trademarks, service marks [whether
registered or not] or Goods in connection with any publicity without Transnet’s prior written consent.
8 TERMINATION OF ORDER
8.1 Transnet may cancel an Order in whole or in part at any time upon at least 7 [seven] days’
written notice to the Supplier/Service Provider, or when there is a change in control of the
Supplier/Service Provider or the Supplier/Service Provider commits any serious breach or any
repeated or continued material breach of its obligations under these Terms and/or Order or shall
have been guilty of conduct tending to bring itself into disrepute, on written notice to the
Supplier/Service Provider when such work on the Order shall stop.
8.2 Transnet shall pay the Supplier/Service Provider a fair and reasonable price for justified work in
progress, where such price reflects only those costs not otherwise recoverable by the
Supplier/Service Provider, at the time of termination, and the Supplier/Service Provider shall give
Transnet full assistance to check the extent of such work in progress. Payment of such price
shall be in full and final satisfaction of any claims arising out of such termination and upon such
payment the Supplier/Service Provider shall deliver to Transnet all work, including any materials,
completed or in progress. The sum payable to the Supplier/Service Provider under this clause
will not in any event exceed the total amount that would have been payable to the
Supplier/Service Provider had the Order not been terminated.
8.3 In the event of termination the Supplier/Service Provider must submit all claims within 2 [two]
months of termination after which time claims will only be met in what Transnet considers
exceptional circumstances.
8.4 If the Goods or Services are not provided in accordance with an Order, the Order shall be
deemed terminated and the Supplier/Service Provider shall compensate Transnet for any costs
incurred in obtaining substitute Goods or any damage caused due to the failure or delay in the
delivery.
9 ACCESS
The Supplier/Service Provider shall be liable for the acts, omissions and defaults of its personnel or
agents who, for the purposes of the Order, shall be treated as if they are the Supplier’s/Service Provider’s
employees. The Supplier/Service Provider shall ensure that any such personnel or agents, whilst on
Transnet’s premises, shall comply with Transnet’s health and safety, security and system security rules
and procedures as and where required.
10 WARRANTY
The Supplier/Service Provider warrants that it is competent to supply the Goods/Services in accordance
with these Terms to the reasonable satisfaction of Transnet and that all Goods/Services delivered under
the Order: (a) conform and comply in all relevant legislation, standards, directives and orders related to
[inter alia] the Goods/Services in force at the time of delivery, and to any specifications referred to in the
Order; (b) will not cause any deterioration in the functionality of any Transnet equipment; and (c) do not
infringe any third party rights of any kind. The Supplier/Service Provider hereby indemnifies Transnet
Transnet Request for Quotation No GSM/15/11/1351 Page 18 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
against all losses, liabilities, costs, claims, damages, expenses and awards of any kinds incurred or made
against Transnet in connection with any breach of this warranty.
11 INSOLVENCY
If the Supplier/Service Provider shall have a receiver, manager, administrator, liquidator or like person
appointed over all or any part of its assets or if the Supplier/Service Provider compounds with its
creditors or passes a resolution for the writing up or administration of the Supplier/Service Provider,
Transnet is at liberty to terminate the Order or Orders forthwith, or at its option, to seek performance by
any such appointed person.
12 ASSIGNMENT
The Supplier/Service Provider shall not assign its obligations under an Order without Transnet’s prior
written consent, which consent shall not be unreasonably withheld or delayed.
13 NOTICES
Notices under these Terms shall be delivered by hand to the relevant addresses of the parties in the
Order or may be served by facsimile or by email, in which event notice shall be deemed served on
acknowledgement of receipt by the recipient.
14 LAW
Orders shall be governed by and interpreted in accordance with South African law and any disputes
arising herein shall be subject to South African arbitration under the rules of the Arbitration Foundation of
South Africa, which rules are deemed incorporated by reference in this clause. The reference to
arbitration shall not prevent Transnet referring the matter to any South African courts, having
jurisdiction, to which the Supplier/Service Provider hereby irrevocably submits but without prejudice to
Transnet’s right to take proceedings against the Supplier/Service Provider in other jurisdictions and/or
obtaining interim relief on an urgent basis from a court of competent jurisdiction pending the decision in
other courts or from instituting in any court of competent jurisdiction any proceedings for an interdict or
any other injunctive relief. If the Supplier/Service Provider does not have a registered office in the South
Africa it will at all times maintain an agent for service of process in South Africa and shall give Transnet
the name and address of such agent as such may be amended, in writing, from time to time.
15 GENERAL
Completion or termination of an Order shall be without prejudice to any Term herein which by its nature
would be deemed to continue after completion or termination, including but not limited to clauses 5, 6, 7
and 10. Headings are included herein for convenience only. If any Term herein be held illegal or
unenforceable, the validity or enforceability of the remaining Terms shall not be affected. No failure or
delay by Transnet to enforce any rights under these Terms will operate as a waiver thereof by Transnet.
All rights and remedies available to either party under these Terms shall be in addition to, not to the
exclusion of, rights otherwise available at law.
Transnet Request for Quotation No GSM/15/11/1351 Page 19 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
16 COUNTERPARTS
These Terms and conditions may be signed in any number of counterparts, all of which taken together
shall constitute one and the same instrument. Any party may enter into this agreement by signing any
such counterpart.
Transnet Request for Quotation No GSM/15/11/1351 Page 20 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
By signing this RFQ document, the Respondent is deemed to acknowledge that he/she has
made himself/herself thoroughly familiar with all the conditions governing this RFQ,
including those contained in any printed form stated to form part hereof and Transnet SOC
Ltd will recognise no claim for relief based on an allegation that the Respondent overlooked
any such condition or failed to properly take it into account for the purpose of calculating
quoted prices or otherwise.
SIGNED at ___________________________ on this _____ day of __________________________
20___
………………………………………………………
SIGNATURE OF RESPONDENT’S AUTHORISED REPRESENTATIVE
NAME: ______________________________________________
DESIGNATION: _______________________________________
REGISTERED NAME OF COMPANY:
________________________________________________________
PHYSICAL ADDRESS:
____________________________________________________________________________________
____________________________________________________________________________________
Respondent’s contact person: [Please complete]
Name :
Designation :
Telephone :
Cell Phone :
Facsimile :
Email :
Website :
Transnet urges its clients, suppliers and the general public
to report any fraud or corruption to
TIP-OFFS ANONYMOUS : 0800 003 056
Transnet Request for Quotation No GSM/15/11/1351 Page 21 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Section 4
VENDOR APPLICATION FORM
Respondents are to furnish the following documentation and complete the Vendor Application Form below:
1. Original cancelled cheque OR letter from the Respondent’s bank verifying banking details [with
bank stamp]
2. Certified copy of Identity Document(s) of Shareholders/Directors/Members [where applicable]
3. Certified copies of the relevant company registration documents from Companies and Intellectual
Property Commission (CIPC)
4. Certified copies of the company’s shareholding/director’s portfolio
5. A letter on the company’s letterhead confirm physical and postal addresses
6. Original valid SARS Tax Clearance Certificate
7. Certified copy of VAT Registration Certificate
8. A valid and original B-BBEE Verification Certificate / sworn affidavit or certified copy thereof
meeting the requirements for B-BBEE compliance as per the B-BBEE Codes of Good Practice
9. Certified copy of valid Company Registration Certificate [if applicable]
VVeennddoorr AApppplliiccaattiioonn FFoorrmm
Company trading name
Company registered name
Company Registration Number or ID Number if a Sole Proprietor
Form of entity [√] CC Trust Pty Ltd Limited Partnership Sole Proprietor
VAT number [if registered]
Company telephone number
Company fax number
Company email address
Company website address
Bank name Branch & Branch code
Account holder Bank account number
Transnet Request for Quotation No GSM/15/11/1351 Page 22 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Postal address
Code
Physical Address
Code
Contact person
Designation
Telephone
Annual turnover range [last financial year] < R5 m R5 - 35 m > R35 m
Does your company provide Products Services Both
Area of delivery National Provincial Local
Is your company a public or private entity Public Private
Does your company have a Tax Directive or IRP30 Certificate Yes No
Main product or services [e.g. Stationery/Consulting]
Complete B-BBEE Ownership Details:
% Black
ownership
% Black women
ownership
% Disabled
Black ownership
% Youth
ownership
Does your entity have a B-BBEE certificate Yes No
What is your B-BBEE status [Level 1 to 9 / Unknown]
How many personnel does the entity employ Permanent Part time
If you are an existing Vendor with Transnet please complete the following:
Transnet contact person
Contact number
Transnet Operating Division
Transnet Request for Quotation No GSM/15/11/1351 Page 23 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Duly authorised to sign for and on behalf of Company / Organisation:
Name Designation
Signature
Date
Transnet Request for Quotation No GSM/15/11/1351 Page 24 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
RFQ FOR THE PROVISION OF NATCOR OCCUPATIONS OPTIMISATION EVALUATION FOR A PERIOD
OF 12 MONTHS
Section 5: CERTIFICATE OF ATTENDANCE OF RFQ BRIEFING
It is hereby certified that –
1. ___________________________________
2. ___________________________________
Representative(s) of _______________________________________ [name of entity]
attended the RFQ briefing in respect of the proposed Services to be rendered in terms of this RFQ on
_________________________20___
____________________________ ______________________________
TRANSNET’S REPRESENTATIVE RESPONDENT’S REPRESENTATIVE
DATE _______________________ DATE _________________________
EMAIL ________________________________
Transnet Request for Quotation No GSM/15/11/1351 Page 25 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
RFQ FOR THE PROVISION OF NATCOR OCCUPATIONS OPTIMISATION EVALUATION FOR A PERIOD
OF 12 MONTHS
ANNEXURE A: B-BBEE PREFERENCE POINTS CLAIM FORM
This preference form contains general information and serves as a claim for preference points for Broad-
Based Black Economic Empowerment [B-BBEE] Status Level of Contribution.
1. INTRODUCTION
1.1 A total of 10 preference points shall be awarded for B-BBEE Status Level of Contribution.
1.2 Failure on the part of a Bidder to fill in and/or to sign this form and submit a B-BBEE Verification
Certificate from a Verification Agency accredited by the South African Accreditation System
[SANAS] or a Registered Auditor approved by the Independent Regulatory Board of Auditors
[IRBA] or an Accounting Officer as contemplated in the Close Corporation Act [CCA] together
with the bid will be interpreted to mean that preference points for B-BBEE Status Level of
Contribution are not claimed.
1.3 Transnet reserves the right to require of a Bidder, either before a Bid is adjudicated or at any time
subsequently, to substantiate any claim in regard to preferences, in any manner required by
Transnet.
2. GENERAL DEFINITIONS
2.1 “all applicable taxes” include value-added tax, pay as you earn, income tax, unemployment
insurance fund contributions and skills development levies;
2.2 “B-BBEE” means broad-based black economic empowerment as defined in section 1 of the
Broad-Based Black Economic Empowerment Act;
2.3 “B-BBEE status of contributor” means the B-BBEE status received by a measured entity based
on its overall performance using the relevant scorecard contained in the Codes of Good Practice
on Black Economic Empowerment, issued in terms of section 9(1) of the Broad-Based Black
Economic Empowerment Act;
2.4 “Bid” means a written offer in a prescribed or stipulated form in response to an invitation by
Transnet for the provision of goods, works or services;
2.5 “Broad-Based Black Economic Empowerment Act” means the Broad-Based Black Economic
Empowerment Act, 2003 [Act No. 53 of 2003];
2.6 “comparative price” means the price after the factors of a non-firm price and all unconditional
discounts that can utilised have been taken into consideration;
2.7 “consortium or joint venture” means an association of persons for the purpose of combining
their expertise, property, capital, efforts, skills and knowledge in an activity for the execution of a
contract;
2.8 “contract” means the agreement that results from the acceptance of a bid by Transnet;
2.9 “EME” means any enterprise with an annual total revenue of R5 [five] million or less;
Transnet Request for Quotation No GSM/15/11/1351 Page 26 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
2.10 “firm price” means the price that is only subject to adjustments in accordance with the actual
increase or decrease resulting from the change, imposition, or abolition of customs and excise
duty and any other duty, levy, or tax, which, in terms of the law or regulation, is binding on the
contractor and demonstrably has an influence on the price of any supplies, or the rendering costs
of any service, for the execution of the contract;
2.11 “functionality” means the measurement according to predetermined norms, as set out in the
bid documents, of a service or commodity that is designed to be practical and useful, working or
operating, taking into account, among other factors, the quality, reliability, viability and durability
of a service and the technical capacity and ability of a bidder;
2.12 “non-firm prices” means all prices other than “firm” prices;
2.13 “person” includes reference to a juristic person;
2.14 “rand value” means the total estimated value of a contract in South African currency, calculated
at the time of bid invitations, and includes all applicable taxes and excise duties;
2.15 “subcontract” means the primary contractor’s assigning or leasing or making out work to, or
employing another person to support such primary contractor in the execution of part of a project
in terms of the contract;
2.16 “total revenue” bears the same meaning assigned to this expression in the Codes of Good
Practice on Black Economic Empowerment, issued in terms of section 9(1) of the Broad-Based
Black Empowerment Act and promulgated in the Government Gazette on 9 February 2007;
2.17 “trust” means the arrangement through which the property of one person is made over or
bequeathed to a trustee to administer such property for the benefit of another person; and
2.18 “trustee” means any person, including the founder of a trust, to whom property is bequeathed in
order for such property to be administered for the benefit of another person.
3. ADJUDICATION USING A POINT SYSTEM
3.1 The Bidder obtaining the highest number of total points for the evaluation criteria as enumerated
in Section 1 of the RFQ will be awarded the contract, unless objective criteria justifies the award
to another bidder.
3.2 Preference points shall be calculated after prices have been brought to a comparative basis taking
into account all factors of non-firm prices and all unconditional discounts.
3.3 Points scored will be rounded off to 2 [two] decimal places.
3.4 In the event of equal points scored, the Bid will be awarded to the Bidder scoring the highest
number of preference points for B-BBEE.
3.5 However, when functionality is part of the evaluation process and two or more Bids have scored
equal points including equal preference points for B-BBEE, the successful Bid will be the one
scoring the highest score for functionality.
3.6 Should two or more Bids be equal in all respect, the award shall be decided by the drawing of lots.
Transnet Request for Quotation No GSM/15/11/1351 Page 27 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
4. POINTS AWARDED FOR B-BBEE STATUS LEVEL OF CONTRIBUTION
4.1 In terms of Regulation 5(2) and 6(2) of the Preferential Procurement Regulations, 2011,
preference points shall be awarded to a Bidder for attaining the B-BBEE status level of
contribution in accordance with the table below
B-BBEE Status Level of
Contributor
Number of Points
[Maximum 10]
1 10
2 9
3 8
4 5
5 4
6 3
7 2
8 1
Non-compliant contributor 0
Note: Refer to Section 1 of the RFQ document for further information in terms of B-BBEE ratings.
4.2 Bidders who qualify as EMEs in terms of the B-BBEE Act must submit a certificate issued by an
Accounting Officer as contemplated in the CCA or a Verification Agency accredited by SANAS or a
Registered Auditor. Registered auditors do not need to meet the prerequisite for IRBA’s approval
for the purpose of conducting verification and issuing EME’s with B-BBEE Status Level Certificates.
4.3 Bidders other than EMEs must submit their original and valid B-BBEE status level verification
certificate or a certified copy thereof, substantiating their B-BBEE rating issued by a Registered
Auditor approved by IRBA or a Verification Agency accredited by SANAS.
4.4 A trust, consortium or joint venture will qualify for points for its B-BBEE status level as a legal
entity, provided that the entity submits its B-BBEE status level certificate.
4.5 A trust, consortium or joint venture will qualify for points for their B-BBEE status level as an
unincorporated entity, provided that the entity submits their consolidated B-BBEE scorecard as if
they were a group structure and that such a consolidated B-BBEE scorecard is prepared for every
separate bid.
4.6 Tertiary institutions and public entities will be required to submit their B-BBEE status level
certificates in terms of the specialised scorecard contained in the B-BBEE Codes of Good Practice.
4.7 A person will not be awarded points for B-BBEE status level if it is indicated in the Bid documents
that such a Bidder intends subcontracting more than 25% [twenty-five per cent] of the value of
the contract to any other enterprise that does not qualify for at least the same number of points
that such a Bidder qualifies for, unless the intended subcontractor is an EME that has the
capability and ability to execute the subcontract.
4.8 A person awarded a contract may not subcontract more than 25% [twenty-five per cent] of the
value of the contract to any other enterprise that does not have an equal or higher B-BBEE status
Transnet Request for Quotation No GSM/15/11/1351 Page 28 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
level than the person concerned, unless the contract is subcontracted to an EME that has the
capability and ability to execute the subcontract.
5. B-BBEE STATUS AND SUBCONTRACTING
5.1 Bidders who claim points in respect of B-BBEE Status Level of Contribution must
complete the following:
B-BBEE Status Level of Contributor _________ = _________ [maximum of 10 points]
Note: Points claimed in respect of this paragraph 5.1 must be in accordance with the table
reflected in paragraph 4.1 above and must be substantiated by means of a B-BBEE certificate
issued by a Verification Agency accredited by SANAS or a Registered Auditor approved by IRBA or
an Accounting Officer as contemplated in the Close Corporation Act.
5.2 Subcontracting:
Will any portion of the contract be subcontracted? YES/NO [delete which is not applicable]
If YES, indicate:
(i) What percentage of the contract will be subcontracted? ………………%
(ii) The name of the subcontractor ……………………………………………………………………………
(iii) The B-BBEE status level of the subcontractor …………………
(iv) Is the subcontractor an EME? YES/NO
5.3 Declaration with regard to Company/Firm
(i) Name of Company/Firm……………………………………………………………………
(ii) VAT registration number……………………………………………………………………
(iii) Company registration number……………………………………………………………
(iv) Type of Company / Firm
□Partnership/Joint Venture/Consortium
□One person business/sole propriety
□Close Corporations
□Company (Pty) Ltd
[TICK APPLICABLE BOX]
(v) Describe Principal Business Activities
……………………………………………………………………………………………………………………………
………........................................................................................................................
Transnet Request for Quotation No GSM/15/11/1351 Page 29 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
................................................................................................................................
.......................................................................................................................
(vi) Company Classification
□Manufacturer
□Supplier
□Professional Service Provider
□Other Service Providers, e.g. Transporter, etc.
[TICK APPLICABLE BOX]
(vii) Total number of years the company/firm has been in business……………………………….
Transnet Request for Quotation No GSM/15/11/1351 Page 30 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
RFQ FOR THE PROVISION OF NATCOR OCCUPATIONS OPTIMISATION EVALUATION
ANNEXURE B: PURPOSE, BACKGROUD AND SCOPE OF WORK
1. PURPOSE
The purpose of this document is to provide the scope of work and project deliverables to determine the
optimal rules for the planning of occupations on the Natcor, with the intent to maximise the available slot
capacity. The aim is to maximise line capacity whilst still performing all the maintenance required.
2. BACKGROUND
Natcor is the Transnet Freight Rail GFB (General Freight Business) corridor between Gauteng and Durban
that has been identified as a major growth corridor. A concept study was done to determine what
capacity needs to be created to ensure that the predicted volume demand increases can be met. The
corridor is expected to see growth from the current (2014) levels of 27 Mt p.a. to 105 Mt p.a. by 2043. As
part of the study, various interventions were suggested to support this growth. First of these was to
ensure current operations are running efficiently before injecting expansion capital.
One of the items identified for improvement was the availability of the rail network. Calculations from
simulations showed that the practical capacity is not fully achieving the UIC guideline of 65% of
theoretical capacity. Planned maintenance occupations play a major role in reducing line capacity,
followed by temporary speed restrictions and technical/operational failures. Currently there is no clear
guideline for the optimal implementation of track occupations in order to maximise the line slot capacity.
The intention is to evaluate various scenarios to assist in the optimising of maintenance planning with
regards to its operational impact, but without reducing or changing the actual maintenance performed.
3. SCOPE AND DELIVERABLES
The scope for the provision of the “Natcor Occupation Optimisation Evaluation” will comprise of the
following areas:
3.1 BASELINE SCOPE OF WORK
3.1.1 Build a complete reference model of the current Natcor corridor network (from City Deep to
Booth).
Use the model to establish a base case – the slot capacity without any occupations or
disruptions, to determine maximum theoretical/design capacity and throughput times.
Determine status quo slot capacity, considering existing infrastructure (intended
design as well as current condition), operational and maintenance regimes, temporary
speed restrictions and operational performance (network & rolling stock failures).
3.1.2 For all simulations, OpenTrack software shall be used, to ensure compatibility with Transnet
Freight Rail’s existing simulation models. The network parameters and occupation history for
the model will be supplied. The network from approximately Rooikop to Booth has already
Transnet Request for Quotation No GSM/15/11/1351 Page 31 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
been modelled in OpenTrack and must be verified/refined as part of this project. The section
from Rooikop to City Deep must be modelled as part of the project.
3.1.3 All trains are to be included, not just through-trains (i.e. trains joining to or departing from
Natcor, or terminating/ originating partially though the corridor must be included). The
Transnet Transportation Model (or TTM) must be used as input for the freight demand along
the route. The supplier shall adjust the schedule as required in order to determine the
maximum slot capacity on the Natcor.
3.1.4 Model the effect of removing or introducing pre-defined temporary speed restrictions
(TSRs).
3.1.5 Model various options that would improve the annual rail network capacity, including:
Not having all occupations start at the same time in daytime (i.e. some short time-
duration occupations to start early and some to start much later);
Having certain occupations at night when permissible;
Moving some occupations from weekdays to weekends;
A combination of the above, including the effect of pre-defined TSRs;
Other options, including the effect of monthly and annual line shutdowns
3.1.6 These options must be tested with
1. the current train length regime.
2. the 75-wagon container train regime
3. the eventual 150-wagon /100-wagon regime of the LTPF (Long-Term Planning
Framework).
3.1.7 Currently, the Northern Natcor (Rooikop – Newcastle) is constrained by the electrical power
available, leading to a 20 min headway limitation in that section only. This will be the first
option under which the scenarios will be tested. An expanded version of the existing train
plan shall be used.
3.1.8 This major electrical constraint will be eliminated in ±3 years’ time with existing CAPEX
projects. The model must then as a second scenario, be tested with an optimal train plan
that only considers signalling headway limitations. This will be developed in an iterative
manner, based on the demand growth as per the TTM.
3.1.9 The installation of block splits and/or crossovers to reduce headway is one of the planned
interventions. The effect of this on the occupation impact must be tested as well. The
locations proposed by Transnet for block split installation must be tested, and the results
analysed and suggestions made. An analysis of bottlenecks will be required here. Any other
subsequent sites where block split installation will increase slot capacity must then also be
tested.
The table below summarises the scenarios that must be tested with the various options as per 3.1.5:
Transnet Request for Quotation No GSM/15/11/1351 Page 32 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
Scenario options
NO Scenario
20 min
headway
limitation
Rooikop-
Newcastle
No electrical
limitation
With
TSR
Without
TSR
1 Design: Current design train lengths
without TSR, occupations or failures
– theoretical/ideal case
X X X
2 As-is: Current as-is train lengths;
existing maintenance & operational
performance
X X X X
3 Operational design (to-be):
Current design train lengths, sample
TSR & operational performance
X X X
4 Block splits only: Current design
train lengths with block splits X X X
5 75-wagon: Current design train
lengths, but container trains @ 75
wagons
X X X
6 Block splits & 75-wagon: Current
design train lengths with block splits
and container trains @ 75 wagons
x X X
7 Block splits & 150-wagon:
Current design train lengths with
block splits and container trains @
150 wagons
X X
8 All long trains: All trains with DP
(i.e. 150-wagon container trains &
100-wagon general freight trains)
and block splits
X X
9 CBTA (optional): Communication-
Based Train Authorisation (or in-cab
signalling) with reduced headways,
50-wagon trains (current design)
X X
Transnet Request for Quotation No GSM/15/11/1351 Page 33 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
3.1.1 The effect of longer trains on throughput and the impact of occupations thereon must also be tested, due to the longer time taken to clear the section.
3.1.2 In all cases, current & forecast PRASA (Metro and Shosholoza Meyl) schedules shall be used.
The TFR schedules shall be optimised around this. For scenarios 6-8, the projected PRASA
trains in 2040 shall be used.
3.1.3 For all solutions, the average daily throughput and run-time distribution of trains shall be the
major output. A graphical (train diagram) view of the daily plans must be produced.
3.1.4 The optimised input files and results as well as any data preparation spreadsheets shall be
provided to Transnet in such a manner that it can be used it with their own OpenTrack
software.
3.1.5 Train power and speed profiles must be produced.
3.2 OPTIONAL SCOPE OF WORK
3.2.1 Building of network with CBTA and scenario analysis (Scenario 9 above).
3.2.2 High-level analysis of impact on maintenance organisation, including overtime, and
recommendations. This must be done on scenario 3 (to-be design with new occupation rules)
and scenario 6 (75-wagon container trains and extra block split signals) only
3.3 STUDY LIMITS
The study shall include the Natcor only. For this exercise, Natcor is defined as from City Deep to Booth.
Traffic that enters into or departs from the Natcor must be included in the model.
3.4 DELIVERABLES
The following deliverables are required:
3.4.1 Verified and refined network model
3.4.2 Baseline report on Scenarios 1, 2 & 3, including the optimal occupation regime/rules
3.4.3 Report on scenarios 4 – 8, including the optimal occupation regime/rules
3.4.4 Optional deliverables:
1. Build model for and run scenario 9 (CBTA), including the optimal occupation
regime/rules
2. A high level analysis on the impact of the proposed occupation rule changes on the
maintenance organisation, including overtime effects (for scenarios 3 & 6).
3.4.5 Final report as well as presentation slides
3.4.6 Report and review, including at least five briefing sessions with stakeholders
Transnet Request for Quotation No GSM/15/11/1351 Page 34 of 34
_________________________ ____________________________
Respondent’s Signature Date & Company Stamp
3.4.7 For all deliverables, the following is required:
1. The various capacity and run-time results from the scenarios must be compared in a
graphic format.
2. A train diagram view of each scenario shall be presented.
3. The input files for each scenario shall be provided in electronic format
4. As part of 3.4.5 (Review & acceptance), a report and set of presentations shall be
provided. It will include the reasoning and assumptions made when optimising or de-
bottlenecking various aspects of the system to arrive at an optimum plan for the
various scenarios.
5. Updated input files where network changes were made. Together with 2 above, it must
allow Transnet to use these files with OpenTrack as a base for further in-house
exploration of options.
6. Interim results must be provided after scenario 1, in order for Transnet to validate the
results from the model built.
7. The prime desired output from this study is a set of Rules to be developed for use in
future occupation planning on the Natcor in order to optimise available capacity while
all required maintenance is still performed.
4 DURATION
All deliverables should be completed within 6 months, where after a 3 month review period will follow,