Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
58
REHABILITAION OF RDA ROADS IN NORTHERN
PROVINCE
SUMMARY OF BILLS
Description Amount (LKR)
BILL No. 1 PRELIMINARIES
BILL No. 2 REHABILITATION OF VALUKKI ARU PUNUGUDUTIVU KURIKATTUWAN ROAD (0.00 TO 24.5 KM)
SUB BILL NO 2A SITE CLEARING
SUB BILL NO 2B EARTH WORKS
SUB BILL NO 2C SUB BASE,BASE AND SHOULDERS
SUB BILL NO 2D SURFACING
SUB BILL No.2E BRIDGES, CULVERTS AND OTHER STRUCTURES
SUB BILL No.2F INCIDENTAL WORKS
BILL No. 3 Rehabilitation of Jaffna-Ponnalai-Point pedro Road (14+50 - 29+05 km), (30+50 - 36+50 km) & (41+00 - 54+60 km)
SUB BILL NO 3A SITE CLEARING
SUB BILL NO 3B EARTH WORKS
SUB BILL NO 3C SUB BASE,BASE AND SHOULDERS
SUB BILL NO 3D SURFACING
SUB BILL No.3E BRIDGES, CULVERTS AND OTHER STRUCTURES
SUB BILL No.3F INCIDENTAL WORKS
BILL No. 4 Rehabilitation of Jaffna Mainipay Karainagar Road
SUB BILL NO 4A SITE CLEARING
59
SUB BILL NO 4B EARTH WORKS
SUB BILL NO 4C SUB BASE,BASE AND SHOULDERS
SUB BILL NO 4D SURFACING
SUB BILL No.4E BRIDGES, CULVERTS (33 Nos.)
SUB BILL No.4F DRAINAGE AND RETAINING WALLS
SUB BILL No.4G INCIDENTAL WORKS
BILL No. 5 DAY WORKS
TOTAL OF BOQ ITEMS
CONTINGENCIES
B. Add 10 % for Physical Contingencies : {A x 10 %}
C. Add 10% for Price Escalation : {A x 10 %}
D. Bid Price : {A + B + C}
E. Amount of VAT(15%) : { D x 15%}
Grand Total : {D+E}
Bid Price excluding VAT is LKR ………………………………………….(State in words)
60
REHABILITAION OF 03 Nos. RDA ROADS IN NORTHERN
PROVINCE Item Pay
Item
Description Unit Qty Rate Amount
Bill No. 01:Preliminaries 103 TRAFFIC SAFETY AND MANAGEMENT
1.01 103(1) Traffic Safety and Control Month 24.00
1.02 103(2) Provision and maintenance of
temporary diversion roads if any
PS 31,000,000.00
108.00 OBLIGATIONS OF THE CONTRACTOR AND GENERAL REQUIREMENT
1.03 108(1) s LS
1.04 108(2) Removal of the site establishment
for the Contractor and
Reinstatement of lands excluding
those that are handed over to
Employer
LS
109.00 WORKMANSHIP AND QUALITY CONTROL
1.05 109(3) Special tests ordered by the
Engineer
PS 8,000,000.00
113 PREPARATION OF SHOP DRAWINGS
1.06 113(1) Providing shop drawings km 151.00
117 SETTING OUT , CROSS SECTION SURVEY AND DRAWINGS 1.07 117(1) Cross-sectional detailing of full
width as specified km 151.00
118 PROJECT SIGN BOARD
1.08 118(1) Provide and maintain Project Sign
Board
Nr(#) 12.00
119 PROVISION OF INSURANCE, BONDS AND SECURITIES
1.09 119(1) Provide Performance Security LS
61
1.10 119(2) Provide Insurance of the Works &
Contractor's Equipment as per
Sub-clause 18.1 of the Conditions
of Contract
LS
1.11 119(3) Provide Insurance as per Sub-
clause 18.2 of the Conditions of
Contract
LS
1.12 119(4) Provide Insurance as per Sub-
clause 18.3 of the Conditions of
Contract
LS
1.13 119(5) Provide Bank Guarantee for
Advance Payment
LS
154 MONTHLY PROGRESS REPORT AND PHOTOGRAPHS
1.14 154(1) Monthly Progress Report Mo. 24.00
1.15 154(2) Supply Digital Photographs Mo. 24.00
1.16 154(3) Supply of Video Compact Disks (
VCD)
Mo. 24.00
203 UTILITIES RELOCATION
1.17 203(3) Relocation of utility services as per
requirements of the utility service
agency and the road agency
PS 200,000,000.00
1109 ROAD MAINTENANCE OF ANY SECTIONS OF EXISTING ROAD DURING CONSTRUCTION OF OTHER SECTIONS WITHIN THE SITE
1.18 1109(1) Road Maintenance Category 1) km-month
3,576.00
1.19 1109(2) Road Maintenance Category 2) (minimum rate shall be Rs.8,000)
km-month
3,576.00
Bill No. 01 Carried to Summary
62
Bill No. 02: Rehabilitation of Valukki Aru Pungudutivu Kurikattuwan
Road (0.00 to 24.5 km) SUB BILL NO 2A:SITE CLEARING
CLEARING AND GRUBBING 2A.01 201(1) Clearing and grubbing m2 132,200.00
2A.02 Removing mud in sea water for
platform width
PS Item Allow 3,000,000.00
REMOVAL OF STRUCTURES & OBSTRUCTIONS 2A.03 202(1) Dismantle & remove brick
masonry structures
m3 150.00
2A.04 202(1)a Dismantle & remove Random
Rubble masonry structures
m3 250.00
2A.05 202(1)
b
Dismantle & remove Dressed
stone mosonary structures
m3 30.00
2A.06 202(2) Dismantle & remove concrete
structures
m3 270.00
2A.07 202(3) Remove fencing m 5,800.00
Sub Bill No. 2A Carried to Summary
SUB BILL NO 2B:EARTH WORKS ROADWAY EXCAVAITON
2B.01 301(4) Roadway excavaiton , soil
suitable for fill
m3 30,600.00 -
EMBANKMENT CONSTRUCTION
2B.02 304(1) Trim, level and compact
Original ground
m2 136,000.00
63
2B.03 304(2) Embankment construction,
Type 1
m3 49,300.00
2B.04 Construction ogf Causeway 2
km
PS 1,000,000,000.00
2B.05 304(3) Embankment construction,
Type 1 m3 36,000.00
2B.06 304(4) Providing & place geo fabric
(weight of fabric minimum
500g/m2)
m2 113,600.00
2B.07 304(4B
)
Embankment construction using
Rock fill (1-10Kg)
m3 80,740.00
2B.08 304(4C
)
Embankment construction using
Rock fill 1-50Kg)
m3 16,400.00
2B.09 304(4D
)
Embankment construction using
Rock fill (100-250Kg)
m3 28,800.00
2B.10 304(4E
)
Embankment construction using
Rock fill (.25T -.75T)
m3 48,000.00
Sub Bill No. 2B Carried to Summary
SUB BILL NO 2C:SUB BASE,BASE AND SHOULDERS
GRANULAR PAVEMENT
2C.01 401(1) Sub base as compacted in position m3 22,740.00
2C.02 307(5) Sub base as constructed using Geo grid layer or Geotextiles
m2 9,500.00
2C.03 405(1) Dense graded aggregate base minimum 200 mm thickness
m3 25,800.00
2C.04 408(1) Scarify and Remove existing bitumen layer
m2 58,000.00
64
SHOULDERS
2C.05 409(1) Earthen shoulder as compacted in position
m3 5,000.00
Sub Bill No. 2C Carried to Summary
SUB BILL NO 2D:SURFACING
PRIME COAT AND TACK COAT
2D.01 501(5)
b
Bituminous Prime Coat using
CSS -1 at 1 litre per m2
m2 209,120.00
2D.02 502(1) Bituminous Tack Coat
(Cationic Emulsion grade CRS1
at 0.3-0.5litre/m2)
m2 209,120.00
BITUMINOUS SURFACING
2D.03 506(1) Asphalt concrete in wearing
course 50mm compacted
thickness
m2 209,120.00
Sub Bill No. 2D Carried to Summary
SUB BILL No.2E : BRIDGES, CULVERTS AND OTHER STRUCTURES
STRUCTURES -BRIDGES
2E.01 303(3) Providing & maintaining of a
temporary by-pass to
accommodate the traffic flow
during the construction, and
removing of the same after
completion of new bridge.
Allow Item P.S 300,000.00
2E.02 202(1) Removal and disposal of
existing structure including
foundation in the area under
new foundation and
transporting the reusable
material to a place within 10
km as directed and stacking the
same after completion of the
by-pass.
Allow Item PS 150,000.00
2E.03 302(10) Construction of necessary
cofferdams cribs sheeting,
shoring and bracing and their
subsequent removal.
Allow Item P.S 150,000.00
65
2E.04 302(11) Dewatering Allow Item P.S 100,000.00
2E.05 302(8) Back fill with approved soil
type 1 with proper layer
compaction as directed by
engineer
m3 192.00
2E.06 302(2) Excavaiton for foundation in
marshy soil
m³ 800.00
2E.07 302(9) Providing sand filling. m³ 128.00
2E.08 1001(4) Mixing & laying 1:3:6 (37.5
mm) for foundation slab
m³ 74.00
2E.09 1008(1) Form work smooth finish
using plywood (shutter 15mm)
and class 11 timber bearers and
joists and jungle timber props
for bridge abutment,wingwalls
etc.
m2 760.00
2E.10 1002(1) Supply and fabricate Tor steel
Grade 460 reinforcement as
per drawing
Ton 18.00
2E.11 1001(4) Concrete grade 30 for box
bridge as per drawing
including vibrator
m³ 203.00
2E.12 1406(7) Painting with enamal 2 coats to
parapets
m2 44.00
2E.13 1406(8) Painting and stenciling figures
and letters as either side of
parapet
Nos 8.00
2E.14 Supplying fixing &
whitewashing to guard stones
on retaining walls.
Nos 24.00
CONSTRUCTION OF BRIDGE AND CAUSEWAY
2E.15 302(11) Dewatering LS
2E.16 202(2) Dismantle and removal of
Concrete Structures
Cum 300.00
66
2E.17 302(5) Excavaiton in unclassified soil
and back filling with suitable
material for structures
Cum 870.26
2E.18 302(8) Back fill with Granular
Material
Cum 90.85
2E.19 304(2)a Embankment Construction
TypeII
Cum 122.76
2E.20 405(1) Dense Graded aggregate base
(Under approach slab)
Cum 7.86
2E.21 705(1) Aggregate backfill Cum 87.24
2E.22 705(2) Filter medium Cum 8.20
2E.23 705(3) Impervious layer Cum 20.38
2E.24 706(1) Weep holes using type 600
PVC pipes of 75 mm dia.
lm 88.22
2E.25 502(2) Bituminous tack coat Using
CRS 1 at a rate of .5 liter per
sqm
sqm 218.06
2E.26 Asphalt concrete inwearing
course 50mm Thick
sqm 218.06
2E.27 New kerbs in bridges lm 54.00
2E.28 Bridge lower kerbs lm 33.00
2E.29 1001(1) Grade 15/40 Blinding Concrete Cum 5.56
2E.30 1001(4) Grade 30/20 concrete for
capping beams, deck, cuirtain
walls, ballast wall etc.
Cum 210.98
67
2E.31 1001(6) Grade 40/20 concrete for deck Cum 87.57
2E.32 1002(1) Supplying, bending and laying
Tor steel (460 N/mm2 ) as
reinforcement
Ton 11.70
2E.33 1008(1) Formwork, smooth finish sqm 311.26
2E.34 1008(2) Formwork, rough finish sqm 384.17
2E.35 1009(1) Expansion joints lm 24.00
2E.36 1010(2) Bearing pads width 75mm and
12mm thick
lm 43.20
2E.37 1012(1) Stainless steel dowels as
shown on drawing
nr 25.00
2E.38 1013(1) Bituminous sealing belt lm 43.20
2E.39 1015(1) Polythene displacers as shown
on drawings
lm 285.00
2E.40 1016(1) Formimg of service duct in the
deck as shown on drawings
lm 54.00
2E.41 1017(1) Cover slabs for service ducts
as shown on drawing
nr 108.00
2E.42 1018(1)
a
Pre-cast reinforced concrete
railing & uprights as shown on
drawing
lm 38.48
2E.43 1403(7) Pre-cast reinforced concrete
railing & painting
sqm 77.94
2E.44 1019(1) End pillasters as shown on
drawing
nr 4.00
68
2E.45 1020(1)
a
50mm dia PVC drain pipes
fixed through service duct as
shown on drawing
nr 14.00
2E.46 1020(1)
b
110mm dia PVC drain pipes
fixed through service duct as
shown on drawing
nr 14.00
2E.47 1001(3)
b
Concrete Grade 25(20) Cum 385.63
2E.48 1003(1e
) &
1003(2e
)
Pre Cast pre-stressed beam
16.5m long
nr 22.00
2E.49 Painting Structure sqm 24.19
2E.50 Culvert& Bridge numbering nr 2.00
Hume Pipe Culvert at causeway 3 raw 15 numbers
HUME PIPE CULVERT AT CAUSEWAY 3 ROWS 15 NUMBERS
2E.51 707(7) 900mm hume pipe 4ft nr 1,372.00
2E.52 707(7) Collar nr 1,080.00
2E.53 1001(1) Concrete Grade 20(20) m3 1,537.55
2E.54 1008(2) Formwork m2 5,416.93
2E.55
Fixing concrete encased Hume pipe using crane
nr 1,372.00
2E.56
Repairing and extend Bridge to required size
PS Item Allow 100,000,000.00
69
STRUCTURES -CULVERTS AND OTHER RETAINING
STRUCTURES 2E.57 402(1) Earth filling for approaches and
carriageway m3 87.00
2E.58 301(5) Allow for Bailingout water P.S Item Allow 16,500.00
2E.59 302(6) Providing coffer damming with Item Sand bags and subsequent removal
P.S Item Allow 120,000.00
2E.60 301(16) Breaking Road surface m2 45.00
2E.61 202(1) Demolishing R.R Masonary m3 42.94
2E.62 202(2) Demolishing reinforced concrete m3 14.19
2E.63 301(14) Excavaiton in Marshy soil m3 319.21
2E.64 Minimum 750mm sand filling beused under bottom of slab & compacted well.
m3 65.00
2E.65 1001(3) 75mm thick screed concrete 1:3:6(37.5mm) in bottom of excavaiton
m3 7.00
2E.66 1008(1) Form work smooth finish with class 2 timber for bridge beams, bridge deck under sides including dismantling
m2 388.92
2E.67 1001 (3) Concrete grade 30(20) for drop walls,walls,slab.
m3 76.00
2E.68 1006 (3) Rendering 19mm thick 1:3 Ct. sand motor
m2 15.50
2E.69 Painting and stenciling figures and letters on either side of parapet
Nos. 6.00
70
2E.70 808(5) Precast Concrete guard stones supplied and fixed.
Nos. 16.00
2E.71 1021(1) Fabricate & lay for steel as reinforcement (Details annexed)
M.Ton 6.39
2E.72 Construction of Bridge at Causeway 200M long 11 m width
PS Item Allow 300,000,000.00
2E.73 Repairing and extend Bridge and Culvert to required size
PS Item Allow 50,000,000.00
RETAINING WALL STRUCTURE AT 23RD KM
2E.74 302(2a) Approved Earth filling between retaining wall and road platform and the earth to be compacted well in layers of 150 to 225mm.
m3 468.75
2E.75 302(2) Excavaiton in Marshy soil m3 825.00
2E.76 302(6) Providing coffer damming with Item Sand bags and subsequent removal
P.S Item Allow 150,000.00
2E.77 1008(1) Form work smooth finish with class 2 timber for bridge beams, bridge deck under sides including dismantling
m2 4,002.38
2E.78 1001(3) Concrete grade 15(40) m3 1,487.50
2E.79 Supplying fixing & whitewashing to guard stones.
Nos. 834.00
2E.80 '705(1) 50-200mm. dry stone lining behind abutment & wingwalls as per drawing.
m3 150.00
2E.81 705(2) 75mm. thick 40mm. stone filter layer behind dry stone lining as per drawing.
m3 0.60
71
2E.82 '705(3) Clay puddled & laid behind abutments & wingwalls to form the impervious layer as per drawing.
m3 150.00
2E.83 808(2) Forming weep holes in vertical wall using 75mm dia. P.V.C. pipes and finished smooth with dripledge and surround complete .
lm. 334.00
2E.84 Repairing and extend Bridge and Culvert to required size
P Sum Item Allow 45,000,000.00
Sub Bill No. 2E Carried to Summary
Sub Bill No.2F : INCIDENTAL WORKS
TOP SOILING
2F.01 801(1) Furnish, Spread and compact top soil
m2 41,200.00
GRASSING
2F.02 802(1) Grass sodding(Excluding royalty, transport and watering and maintenance)
m2 41,200.00
RIP RAP PROTECTION FOR EMBANKMENT SLOPES
2F.03 1006(2) Embankment construction using rock fill (1 - 50 kg )
m3 3,000.00
2F.04 Embankment construction using rock fill (100 - 250 kg )
m3 9,600.00
2F.05 804(1) Embankment construction using rock fill (0.25 - 0.75 kg )
m3 6,000.00
ROAD MARKING
2F.06 Application of Road markings as per specification edge line, Centre line of 100 mm width, 3 mm thick, using Road marking paints ,
m2 6,985.00
72
2F.07 Application of Road markings std pedestrian crossing using thermo plastic paints, (Yellow) inclusive barricading
m2 1,158.00
2F.08 Providing & fixing yellow studs on Pedestrian crossing
Nos. 1,120.00
2F.09 Providing & fixing white studs on Centre line.
Nos. 4,170.00
ROAD SIGNS
2F.10 811(1) Single pole, sign area up to 0.5m2 nr 210.00
2F.11 811(2) Double pole, sign area up to 2.0m2 nr 75.00
2F.12 811(3) Chevron warning sign nr 55.00
KILOMETER POSTS
2F.13 819(1) Provide ,Install and paint new kilometre post
nr 28.00
STREET LIGHTING
2F.14 Provide street lighting PS Item Allow 2,500,000.00
Sub Bill No. 2F Carried to Summary
Bill No. 03: Rehabilitation of Jaffna-Ponnalai-Point pedro Road (14+50
- 29+05 km), (30+50 - 36+50 km) & (41+00 - 54+60 km)
Sub Bill No.3A : SITE CLEARING
CLEARING AND GRUBBING
3A.01 201(1) Clearing and grubbing m2 244,100.00
REMOVAL OF STRUCTURES & OBSTRUCTIONS
3A.02 202(1) Demolishing dry coursed masonry including stacking or loading
m3 1,000.00
73
3A.03 202(1)a
Demolishing coursed masonry in cement mortar including stacking or loading
m3 1,000.00
3A.04 202(1)b
Demolishing random rubble masonry in cement mortar including stacking or loading
m3 500.00
3A.05 202(1) Demolishing reinforced cement concrete and debries cleaned.
m3 500.00
3A.06 202(3) Remove fencing (Provisional Quantity)
l.m 20,000.00
Sub Bill No.3A Carried to Summary
Sub Bill No.3B : EARTH WORKS
ROADWAY EXCAVAITON
3B.01 301(4) Roadway excavaiton in unclassified soil(cutting measurement)loading & transport up to 3km
m3 60,560.00
EMBANKMENT CONSTRUCTION
3B.02 304(1) Trim, level and compact Original ground 95%std.
m2 250,200.00
3B.03 304(2) Embankment construction, Type 1
m3 48,009.00
3B.04 304(3) Embankment construction, Type 2
m3 18,616.00
3B.05 304(4) Providing & place geo fabric (weight of fabric minimum 500g/m2)
m3 64,650.00
3B.06 304(4) Embankment construction using Rock fill (1-10Kg)
m3 62,580.00
3B.07 304(4) Embankment construction using Rock fill 1-50Kg)
m3 16,640.00
3B.08 304(4) Embankment construction using Rock fill (100-250Kg)
m3 16,192.00
74
3B.09 304(4) Embankment construction using Rock fill (.25T -.75T)
m3 22,244.00
CHANNEL EXCAVAITON
3B.10 307(1) Channel excavaiton, suitable soil
m3 7,200.00
3B.11 307(3) Channel excavaiton, soft rock (Provisionl Quantity)
m3 1,440.00
3B.12 307(4) Channel excavaiton, unsuitable soil
m3 5,760.00
Sub Bill No.3B Carried to Summary
Sub Bill No.3C : SUB BASE, BASES AND SHOULDERS GRANULAR PAVEMENT
3C.01 401(1) Sub base as compacted in position m3 57,063.50
3C.02 307(5) Sub base as constructed using Geo grid layer or Geotextiles
m2 24,000.00
3C.03 405(1) Dense graded aggregate base minimum 200 mm thickness
m3 59,772.00
3C.04 408(1) Scarify and Remove existing bitumen layer
m2 119,525.00
3C.05 SHOULDERS
3C.06 409(1) Earthen shoulder as compacted in position
m3 22,197.50
Sub Bill No.3C Carried to Summary
75
Sub Bill No.3D :SURFACING PRIME COAT AND TACK COAT
3D.01 501(5)b Bituminous Prime Coat using CSS -1 at 1 litre per m2
m2 298,860.00
3D.02 502(1) Bituminous Tack Coat (Cationic Emulsion grade CRS1 at 0.5litre/m2)
m2 298,860.00
BITUMINOUS SURFACING
3D.03 506.2a Asphalt concrete in wearing course 50mm compacted thickness
m2 298,860.00
Sub Bill No.3D Carried to Summary
Sub Bill No.3E : BRIDGES, CULVERTS AND OTHER STRUCTURES
CONSTRUCTION OF 10 NoS. 1.5 M X 1.0 M SINGLE CELL BOX CULVERT
3E.01 202(2) Demolishing reinforcement concrete
PS 200,000.00
3E.02 301(14) Excavaiton for foundation in unclassified soil
m3 280.00
3E.03 302(11) Dewatering. PS 500,000.00
3E.04 1001(4) Mixing and laying 1:3:6(19mm) concrete as screed to Drop wall and Bottom slab
m3 9.00
3E.05 1001(4) Mixing & Laying Gr 30 Concrete to Dropwall and Culvert
m3 157.00
3E.06 1008(1) Formwork smooth finish for general purpose using 25 mm thick planks & struts of class 11 timber and round jungle timber props 100 -150 mm dia including dismanting
m2 867.00
3E.07 1002(1) Fabricate & lay tor steel as Reinforcement
Kg 27,340.00
76
3E.08 304(2) Approved soil (Type I & II materials) excavaiton using machinery for backfilling construction including loading and piling.
m3 50.00
3E.09 304(2) Approved soil spread and compacted Machine Rammer in Narrow places.
m3 50.00
3E.10 808(5) Casting St type Guard stones in Concrete (1:2:4) 19mm & cement
No 80.00
3E.11 808(5) Fixing new Guard stones in 225mm thick cement concrete 1:3:6 (37.5 mm ) and cement 219 Kg/cu.m with minimum cover 75 mm x 300 mm depth
No 80.00
3E.12 White washing ,two coat to Guard stones
No 80.00
CONSTRUCTION OF 05 NoS. 2.5 M X 1.0 M SINGLE CELL BOX CULVERT
3E.13 202(2) Demolishing reinforcement concrete
PS 160,000.00
3E.14 301(14) Excavaiton for foundation in unclassified soil
m3 328.00
3E.15 302(11) Dewatering. PS 400,000.00
3E.16 1001(4) Mixing and laying 1:3:6(19mm) concrete as screed to Drop wall and Bottom slab
m3 7.20
3E.17 1001(4) Mixing & Laying Gr 30 Concrete to Dropwall and Culvert
m3 168.80
3E.18 1008(1) Formwork smooth finish for general purpose using 25 mm thick planks & struts of class 11 timber and round jungle timber props 100 -150 mm dia including dismanting
m2 775.20
3E.19 1002(1) Fabricate & lay tor steel as Reinforcement
Kg 29,288.00
77
3E.20 304(2) Approved soil (Type I & II materials) excavaiton using machinery for backfilling construction including loading and piling.
m3 40.00
3E.21 304(2) Approved soil spread and compacted Machine Rammer in Narrow places.
m3 40.00
3E.22 808(5) Casting St type Guard stones in Concrete (1:2:4) 19mm & cement
No 80.00
3E.23 808(5) Fixing new Guard stones in 225mm thick cement concrete 1:3:6 (37.5 mm ) and cement 219 Kg/cu.m with minimum cover 75 mm x 300 mm depth
No 80.00
3E.24 White washing ,two coat to Guard stones
No 80.00
CONSTRUCTION OF 08 Nos. 3.0 M X 1.3 M SINGLE CELL BOX CULVERT
3E.25 202(2) Demolishing reinforcement concrete
PS 160,000.00
3E.26 301(14) Excavaiton for foundation in unclassified soil
m3 520.00
3E.27 302(11) Dewatering. PS 400,000.00
3E.28 1001(4) Mixing and laying 1:3:6(19mm) concrete as screed to Drop wall and Bottom slab
m3 13.60
3E.29 1001(4) Mixing & Laying Gr 30 Concrete to Dropwall and Culvert
m3 272.00
3E.30 1008(1) Formwork smooth finish for general purpose using 25 mm thick planks & struts of class 11 timber and round jungle timber props 100 -150 mm dia including dismanting
m2 1,069.60
3E.31 1002(1) Fabricate & lay tor steel as Reinforcement
Kg 30,056.00
78
3E.32 304(2) Approved soil (Type I & II materials) excavaiton using machinery for backfilling construction including loading and piling.
m3 64.00
3E.33 304(2) Approved soil spread and compacted Machine Rammer in Narrow places.
m3 64.00
3E.34 808(5) Casting St type Guard stones in Concrete (1:2:4) 19mm & cement
No 80.00
3E.35 808(5) Fixing new Guard stones in 225mm thick cement concrete 1:3:6 (37.5 mm ) and cement 219 Kg/cu.m with minimum cover 75 mm x 300 mm depth
No 80.00
3E.36 White washing ,two coat to Guard stones
No 80.00
CONSTRUCTION OF 05 NoS. 2.0 M X 1.7 M TWIN CELL BOX CULVERT
3E.37 202(2) Demolishing reinforcement concrete
PS 100,000.00
3E.38 301(14) Excavaiton for foundation in unclassified soil
m3 510.00
3E.39 302(11) Dewatering. PS 250,000.00
3E.40 1001(4) Mixing and laying 1:3:6(19mm) concrete as screed to Drop wall and Bottom slab
m3 11.00
3E.41 1001(4) Mixing & Laying Gr 30 Concrete to Dropwall and Culvert
m3 216.50
3E.42 1008(1) Formwork smooth finish for general purpose using 25 mm thick planks & struts of class 11 timber and round jungle timber props 100 -150 mm dia including dismanting
m2 872.00
3E.43 1002(1) Fabricate & lay tor steel as Reinforcement
Kg 31,250.00
79
3E.44 304(2) Approved soil (Type I & II materials) excavaiton using machinery for backfilling construction including loading and piling.
m3 65.00
3E.45 304(2) Approved soil spread and compacted Machine Rammer in Narrow places.
m3 65.00
3E.46 808(5) Casting St type Guard stones in Concrete (1:2:4) 19mm & cement
No 70.00
3E.47 808(5) Fixing new Guard stones in 225mm thick cement concrete 1:3:6 (37.5 mm ) and cement 219 Kg/cu.m with minimum cover 75 mm x 300 mm depth
No 70.00
3E.48 White washing ,two coat to Guard stones
No 70.00
CONSTRUCTION OF 04 Ns. 3.0 M X 1.7 M TWIN CELL BOX CULVERT
3E.49 202(2) Demolishing reinforcement concrete
PS 0.00 80,000.00
3E.50 301(14) Excavaiton for foundation in unclassified soil
m3 616.00
3E.51 302(11) Dewatering. PS 200,000.00
3E.52 1001(4) Mixing and laying 1:3:6(19mm) concrete as screed to Drop wall and Bottom slab
m3 12.40
3E.53 1001(4) Mixing & Laying Gr 30 Concrete to Dropwall and Culvert
m3 254.40
3E.54 1008(1) Formwork smooth finish for general purpose using 25 mm thick planks & struts of class 11 timber and round jungle timber props 100 -150 mm dia including dismanting
m2 841.60
3E.55 1002(1) Fabricate & lay tor steel as Reinforcement
Kg 34,584.00
3E.56 304(2) Approved soil (Type I & II materials) excavaiton using machinery for backfilling
m3 60.00
80
construction including loading and piling.
3E.57 304(2) Approved soil spread and compacted Machine Rammer in Narrow places.
m3 60.00
3E.58 808(5) Casting St type Guard stones in Concrete (1:2:4) 19mm & cement
No 80.00
3E.59 808(5) Fixing new Guard stones in 225mm thick cement concrete 1:3:6 (37.5 mm ) and cement 219 Kg/cu.m with minimum cover 75 mm x 300 mm depth
No 80.00
3E.60 White washing ,two coat to Guard stones
No 80.00
3E.61 808(5) Precast Concrete guard stones supplied and fixed.
Nos. 3,500.00
3E.62 1406(3) 1303(1)
Repairing and extend Bridge and Culvert to required size 3 nos
PS Item Allow 150,000,000.00
Sub Bill No.3E Carried to Summary
Sub Bill No.3F : INCIDENTAL WORKS TOP SOILING
3F.01 801(1) Furnish, Spread and compact top soil
m2 78,000.00
GRASSING
3F.02 802(1) Grass sodding(Excluding royality,tranport and watering and maintenance)
m2 78,000.00
ROAD MARKING
3F.03 810(1) Application of Road markings as per specification edge line,Centre line of 100 mm width and std pedestrian crossing, 3 mm thick, using Road marking paints
m2 9,075.50
3F.04 810(1) Application of Road markings yellow lines using thermo plastic paints inclusive barricading
m2 2,933.00
81
3F.05 810(3) Providing & fixing studs on Pedestrian crossing & Centre line
Nos. 5,784.00
ROAD SIGNS
3F.06 811(1) Single pole, sign area up to 0.5m2 PS Item Allow 2,500,000.00
3F.07 811(2) Double pole, sign area up to 2.0m2 PS Item Allow 1,200,000.00
3F.08 811(3) Chevron warning sign PS Item Allow 1,200,000.00
3F.09 KILOMETRE POSTS
3F.10 819(1) Provide, Install and paint new kilometre post
Nos. 34.00
Sub Bill No.3F Carried to Summary
Bill No. 04: Rehabilitation of Jaffna Mainipay Karainagar Road
Sub Bill No 4A- Site Clearing
4A.01 Allow for demolishing/ Rebuilding
structures as directed PS Allow
4,000,000.00
4A.02 201
Clearing and Grubbing within the
construction boundary including
removel of trees,stumps,roots and
other obstructions as directed
m2
148,200.00
Sub Bill No. 4A Carried to Summary
Sub Bill No 4B- Earth Works
4B.01 301 Excavaiton in Medium soil m³
37,050.00
4B.02 304 Trimming,Levelling and Compact
Original Ground to 95% m2
148,200.00
4B.03 304 Trimming,Levelling and Compact
Original Ground to 100% m2
123,500.00
4B.04 304 Embankment construction, Type 1,
using borrow material m3
19,320.00
Sub Bill No. 4B Carried to Summary
82
Sub Bill No 4C- Subbase ,Base and Shoulders
4C.01 401
Approved soil Excavaiton, spread &
compaction using machinery for
Subbase construction including
loading & piling. Trans dist.140 km
m³
37,050.00
4C.02 401
Approved soil spread & compaction
using machinery for Shoulder
construction including loading &
piling.
Trans dist. 140 km
m3
12,350.00
4C.03 408(2) Scarifying Road Surface To 50 mm
depth by roller m2
123,500.00
4C.04 409
Dense graded Aggregate Base
spreading watering and compacting
graded 37.5mm aggregate to form
dense aggregate base using machinary
.Trans .Dist 205 km
m ³
46,683.00
Sub Bill No. 4C Carried to Summary
Sub Bill No 4D- Surfacing
4D.01 501
Prime coat with Emulsion CSS1 using
1 ltrs/sqm including blinding with
sand & Transport of bitumen ave 400
km
m2 222300
4D.02 502
Tack coat with with CSS1 @ 0.75
ltrs/sqm including Transport bitumen
ave 400km
m2 249300
4D.03 506
Supply, Lay and Compact Asphalt
Concrete Wearing course material
using paver
m2 261765
Sub Bill No. 4D Carried to Summary
Sub Bill No 4E : Bridge & Culverts (33 Nos)
EARTH WORKS FOR BRIDGES AND CULVERTS
4E.01 103(2)
Providing And Maintaining By pass road
with fixing one hume pipe and Removing
after finishing the work as directed by
engineer
Allow Item PS
800,000.00
4E.02 202(2) Removal of existing structure as directed
by Engineer Allow Item PS
2,000,000.00
4E.03 302(6) Providing coffer dam Allow Item PS
100,000.00
83
4E.04 302(11) Dewatering during Work Allow Item PS
100,000.00
4E.05 302(8)
Back fill with approved soil type 1
(gravel)with proper layer compaction as
directed by engineer
m3
1,987.60
FOUNDATION AND STRUCTURES
4E.06 302(2) Excavaiton for foundation in marshy soil m³ 6135.7
4E.07 302(9) Providing sand filling. m³ 1112.1
4E.08 1001(2) Mixing & laying 1:3:6 (37.5 mm) for
foundation slab m³ 706.2
4E.09 1008(2)
Form work smooth finish using plywood
(shutter 15mm) and class 11 timber
bearers and joists and jungle timber props
for bridge abutment,wingwalls etc.
m2 7497.93
4E.10 1002(1) Supply and fabricate Tor steel Grade 460
reinforcement as per drawing Ton 172.3
4E.11 1001(2)
Concrete of Grade 30 (19mm) using
concrete mixer(W/baching) for box bridge
as per drawing including vibrator
m³ 1888.3
4E.12 1406(8) Painting white back ground and stenciling
figures and letters as 3/1 Nos 66
Sub Bill No. 4E Carried to Summary
Sub Bill No 4F : Drainage & Retaining Wall
DRAIN CONSTRUCTION
4F.01 302(2) Excavaiton in Pitch Trench for
foundation in medium soil m3 6615
4F.02 1008(2)
Form work smooth finish using
plywood (shutter 15mm) and class 11
timber bearers and joists and jungle
timber props for Side drain
m2 24360
4F.03 1001(2) Mixing & Laying lean concrete of
1:3:6 (37.5mm) m3 567
84
4F.04 1002(1) Supply and fabricate of reinforcement
as per drawing ton 382.16
4F.05 1001(2)
Concrete of grade 25 (19mm) for side
drain& cover slab as per drawing
including vibrator (Tpt 205km)
m3 3908
4F.06 1001(11) Curing of Concrete slab & drain m2 329469
4F.07 806 Supply and Laying precast slab (450
mm*450 mm*50 mm) m2 2000
4F.08 807 Supply and Laying precast Kerbs LM 2000
RETAINING WALL
4F.09 302(2) Excavaiton in foundation m3 2025
4F.10 302(8) Back fill with Type 01 soil m3 2025
4F.11 1001(3) Laying screed concreting Grade - 15
(37.5mm) m3 253.125
4F.12 1001(2) Laying Mass concreting Grade - 15
(19mm) m3 4175
4F.13 705(3) Clay Puddle (Transport : 175 km) m3 450
4F.14 706(1) Weep hole, 100mm dia. PVC pipe
(Type 600) LM 500
4F.15 705(1) Aggregate back fill material 50-
200mm m3 225
4F.16 808(5) Fixing Guard stones Nos 810
85
Sub Bill No. 4F Carried to Summary
Sub Bill 4G Incidencial Construction
4G.01 811(1) Single pole,sign area upto 0.5 m2 Nos 200.00
4G.02 811(1a) Single pole,multiple sign area upto 1 m2
Nos 20.00
4G.03 811(2) Double pole sign area upo 2.0 m2 Nos 15.00
4G.04 811(3) Chevron warning sign Nos 50.00
4G.05 819(1) Provide,install & paint new kilometer post
Nos 27.00
4G.06 810(2) Road Marking center line 100 mm width using thermoplastic paints
sq.m 7,200.00
4G.07 810(2) Road Marking edge line thermoplastic paints
sq.m 2,080.00
4G.08 810(2) Road marking pedestal crossing thermoplastic paints
sq.m 1,800.00
4G.09 810(3) Road studs Nos 4,000.00
4G.10 Allow for providing Street lighting PS Allow
30,000,000.00
4G.11 Allow for providing Signalization for important junctions
PS Allow
20,000,000.00
Sub Bill No. 4G Carried to Summary
86
Bill No.5 : DAY WORKS 5.01 Surveyor Hr 900.00
5.02 Laboratory Technician (skilled) Hr 700.00
5.03 Carpenter Hr 1,300.00
5.04 Mason Hr 1,300.00
5.05 Steel Fixer Hr 600.00
5.06 Semi-skilled workman Hr 1,400.00
5.07 Unskilled workman (labourer) Hr 1,400.00
5.08 Bowser, water, up to 6,000 litres with Spray Bar
Hr 1,720.00
5.09 Backhoe, wheeled, 50 - 100 HP Hr 1,720.00
5.10 Backhoe, tracked, 50 - 100 HP Hr 1,720.00
5.11 Motor grader, 120 to140HP Hr 1,720.00
5.12 Mobile Crane 25 tonnes Hr 1,720.00
5.13 Water pump with hoses, 50 to 100 mm outlet
Hr 1,720.00
87
5.14 Concrete mixer, over 0.50 cu.m. Hr 1,720.00
5.15 Generator, 10 to 50 KVA Hr 1,720.00
5.16 Poker Vibrator, petrol driven Hr 1,720.00
5.17 Bituminous Emulsion CSS-1 Ltr. 6,300.00
5.18 Sand Cu.m 6,300.00
5.19 Aggregate base course Cu.m 6,300.00
5.20 Aggregate 5-20mm Cu.m 6,300.00
5.21 Cement kg 6,300.00
5.22 60/70 Bitumen Ltr. 6,300.00
5.23 Reinforcement kg 6,300.00
5.24 Diesel Ltr. 6,300.00
5.25 Bitumen MC30 Ltr. 6,300.00
Bill No. 5 Carried to Summary