Upload
mohamed-wahid
View
250
Download
23
Tags:
Embed Size (px)
Citation preview
X Gas Field Development (Phases
Gas Field Development (Phases
CONTRACT NO.
PROJECT
COMPANY
SITE
0
Rev.
DOCUMENT
Doc. No. :
Gas Field Development (Phases X)
CONTRACT NO.
PROJECT
COMPANY
23/05/08
Date
X
Project No. :
DOCUMENT
No.
RELAY SETTING
STUDY
Doc. No. : NC-
)
RELAY SETTING
: ONS
: X
(PHASES
FROM MPC
: X
: X
Issued for
Description
GAS FIELD DEVELOPMENT
PHASES
ONSHORE FACILITIES
Project No. : ONS-09-0
132kV TEMPORARY POWER
RELAY SETTING
NC-
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
RELAY SETTING
ONS-09-0-CO
X GAS FIELD DEVELOPMENT
(PHASES X)
FROM MPC
X
X GAS FIELD
Issued for Approval
Description
GAS FIELD DEVELOPMENT
PHASES X,
ONSHORE FACILITIES
0-CO-4127
32kV TEMPORARY POWER
FROM MPCRELAY SETTING
-6340S-550-1600
RELAY SETTING
(CT2000:5)
1600-0004
)
RELAY SETTING
CO-4127
GAS FIELD DEVELOPMENT
)-132kV TEMPORARY POWER
FROM MPC
GAS FIELD
Approval Hir.
ORIGI
GAS FIELD DEVELOPMENT
,
ONSHORE FACILITIES
32kV TEMPORARY POWER
FROM MPCRELAY SETTING STUDY
1600-0004
Rev. No. :
RELAY SETTING STUDY
GAS FIELD DEVELOPMENT
132kV TEMPORARY POWER
Hir. S.M.K.
ORIGI PRPD
Doc. Class :
32kV TEMPORARY POWER
FROM MPC STUDY(CT2000:5)
Sh. No.
0
STUDY
132kV TEMPORARY POWER
S.M.K. S.M.K.
PRPD CHKD
Scale :
32kV TEMPORARY POWER
(CT2000:5)
No. : 1 of
Page 1
132kV TEMPORARY POWER
A.F.
APP
D
CONT.
APPRD.
Scale : NTS
of 158 Rev. 0
1 of 158
ONT.
PPRD.
0
X Gas Field Development (Phases
Gas Field Development (Phases
PAGE REV
Doc. No. :
Gas Field Development (Phases X)
REV PAGE
RELAY SETTING
STUDY
Doc. No. : NC-
)
TABULATION OF REVISED PAGES
REV PAGE
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
TABULATION OF REVISED PAGES
PAGE REV
RELAY SETTING
(CT2000:5)
1600-0004
)
TABULATION OF REVISED PAGES
PAGE
Rev. No. :
TABULATION OF REVISED PAGES
REV PAGE
0
PAGE REV
Page 2
REV PAGE REV
2 of 158
REV
X Gas Field Development (Phases
Gas Field Development (Phases
1. INTRODUCTION
2. SCOPE
3. SYSTEM DESCRIPTIO
3.1.Reference Documents
3.2.System Analysis Software
3.3. Electrical System Representation
4. CALCULATION CRITERIA
5. LOAD FLOW AND FAULT
6. RELAY TYPE AND LOCAT
7. RELAY SETTINGS
8. RESULTS
9. TRANSIENT ACTIONS
9.1 TRANSIENT ACTION OF THE RELAYS WITH TRANSIENT STABILITY
9.2 TRANSIENTS CHECKS
10.0 OTHER PARAMETERS TO BE SET
10.1 TRANSFORMER AUTOMATIC VOLTAGE REGULATOR
10.2 INRUSH CURRENT SETTINGS
11. CONCLUSIONS
Doc. No. :
Gas Field Development (Phases X)
1. INTRODUCTION
3. SYSTEM DESCRIPTIO
3.1.Reference Documents
System Analysis Software
3.3. Electrical System Representation
CALCULATION CRITERIA
LOAD FLOW AND FAULT
RELAY TYPE AND LOCAT
RELAY SETTINGS
8. RESULTS
9. TRANSIENT ACTIONS
9.1 TRANSIENT ACTION OF THE RELAYS WITH TRANSIENT STABILITY
9.1.1 33KV UNDER VOLTAGE RELAY ACTION IN TRANSIENT STABILITY
9.1.2 Under voltage, Bus Transfer
TRANSIENTS CHECKS
10.0 OTHER PARAMETERS TO BE SET
10.1 TRANSFORMER AUTOMATIC VOLTAGE REGULATOR
10.2 INRUSH CURRENT SETTINGS
. CONCLUSIONS
RELAY SETTING
STUDY
Doc. No. : NC-
)
3. SYSTEM DESCRIPTION AND INPUT DATA
3.1.Reference Documents
System Analysis Software
3.3. Electrical System Representation
CALCULATION CRITERIA
LOAD FLOW AND FAULT RESULTS
RELAY TYPE AND LOCATIONS
9. TRANSIENT ACTIONS
9.1 TRANSIENT ACTION OF THE RELAYS WITH TRANSIENT STABILITY
9.1.1 33KV UNDER VOLTAGE RELAY ACTION IN TRANSIENT STABILITY
9.1.2 Under voltage, Bus Transfer
TRANSIENTS CHECKS
10.0 OTHER PARAMETERS TO BE SET
10.1 TRANSFORMER AUTOMATIC VOLTAGE REGULATOR
10.2 INRUSH CURRENT SETTINGS
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
TABLE OF CONTENTS
N AND INPUT DATA
System Analysis Software
3.3. Electrical System Representation 3.3.1.Network Topology 3.3.2. Network Parameters and Data
RESULTS
9.1 TRANSIENT ACTION OF THE RELAYS WITH TRANSIENT STABILITY
9.1.1 33KV UNDER VOLTAGE RELAY ACTION IN TRANSIENT STABILITY
9.1.2 Under voltage, Bus Transfer
10.0 OTHER PARAMETERS TO BE SET
10.1 TRANSFORMER AUTOMATIC VOLTAGE REGULATOR
10.2 INRUSH CURRENT SETTINGS
RELAY SETTING
(CT2000:5)
1600-0004
)
TABLE OF CONTENTS
3.3.1.Network Topology
3.3.2. Network Parameters and Data
9.1 TRANSIENT ACTION OF THE RELAYS WITH TRANSIENT STABILITY
9.1.1 33KV UNDER VOLTAGE RELAY ACTION IN TRANSIENT STABILITY
9.1.2 Under voltage, Bus Transfer
10.1 TRANSFORMER AUTOMATIC VOLTAGE REGULATOR
Rev. No. :
TABLE OF CONTENTS
3.3.1.Network Topology
3.3.2. Network Parameters and Data
9.1 TRANSIENT ACTION OF THE RELAYS WITH TRANSIENT STABILITY
9.1.1 33KV UNDER VOLTAGE RELAY ACTION IN TRANSIENT STABILITY
10.1 TRANSFORMER AUTOMATIC VOLTAGE REGULATOR
0
3.3.2. Network Parameters and Data
9.1 TRANSIENT ACTION OF THE RELAYS WITH TRANSIENT STABILITY
9.1.1 33KV UNDER VOLTAGE RELAY ACTION IN TRANSIENT STABILITY
Page 3
9.1.1 33KV UNDER VOLTAGE RELAY ACTION IN TRANSIENT STABILITY SIMULATION
3 of 158
SIMULATION
X Gas Field Development (Phases
A.I.1 GAS
A.I.2 INPUT DATA
A.I.3LOAD FLOW
A.I.4SHORT CIRCUIT ANALYSIS
A.I.5 DYNAMIC STUDIES
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
A.I.7 INTENDED STUDY SYSTEM
Gas Field Development (Phases
APPENDIX I
STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT
A.I.1 GAS PLANT ELECTRICAL NETWORK REPRESENTATION
A.I.2 INPUT DATA
A.I.3LOAD FLOW
A.I.4SHORT CIRCUIT ANALYSIS
A.I.5 DYNAMIC STUDIES
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
A.I.7 INTENDED STUDY SYSTEM
Doc. No. :
Gas Field Development (Phases X)
APPENDIX I
STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT
PLANT ELECTRICAL NETWORK REPRESENTATION
A.I.4SHORT CIRCUIT ANALYSIS
A.I.5 DYNAMIC STUDIES
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
A.I.7 INTENDED STUDY SYSTEM
RELAY SETTING
STUDY
Doc. No. : NC-
)
STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT
PLANT ELECTRICAL NETWORK REPRESENTATION
A.I.4SHORT CIRCUIT ANALYSIS
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
A.I.7 INTENDED STUDY SYSTEM
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT
PLANT ELECTRICAL NETWORK REPRESENTATION
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
RELAY SETTING
(CT2000:5)
1600-0004
)
STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT
PLANT ELECTRICAL NETWORK REPRESENTATION
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
Rev. No. :
STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
0
A.I.6 STATIC AND DYNAMIC EQUIVALENT OF GAS PLANT ELECTRICAL NETWORK
Page 44 of 158
X Gas Field Development (Phases
-Attachments
NC-6340S
NC-6340S
Gas Field Development (Phases
Attachments
6340S-550-1600-0004
6340S-550-1600-0004
Doc. No. :
Gas Field Development (Phases X)
Attachments
0004-RELAY SETTING STUDY
0004-RELAY SETTING STUDY
RELAY SETTING
STUDY
Doc. No. : NC-
)
RELAY SETTING STUDY
RELAY SETTING STUDY
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
RELAY SETTING STUDY-AT01(CT2000:5)
RELAY SETTING STUDY-AT02(CT2000:5)
RELAY SETTING
(CT2000:5)
1600-0004
)
(CT2000:5)
(CT2000:5)
Rev. No. :
0
Page 55 of 158
X Gas Field Development (Phases
1. INTRODUCTION
The phase
hydrocarbon fluid by the sub
of
The Temporary Electrical Power required for phases
Mobi
transformer.
Six generators that are connected to the
that contains 132kV cable and 13
The
2. SCOPE
The objective of this document is to do relay settings and coordination analysis for temporary supply
the
in document
The results of this study provide the exact settings of the
must be
3. SYSTEM DESCRIPTION AND INPUT DATA
3.1.
DW 6340S 120 1633 0001NC 6340S 120 1634 0001NC 6340S 999 1630 0020NCVP 6340S 1600 LG 0001 077NC 6340S 550 1600 001NC 6340S 550 1600 002NC 6340S 550 1600 003NC 6340S 550 1600 005SLD 6340S 550 1600 0002
Gas Field Development (Phases
INTRODUCTION
The phases X
hydrocarbon fluid by the sub
of X city.
The Temporary Electrical Power required for phases
Mobin Petrochemical Complex through 132
transformer.
Six generators that are connected to the
that contains 132kV cable and 13
The temporary supply relay setting
SCOPE
The objective of this document is to do relay settings and coordination analysis for temporary supply
the 33KV outgoing to the
in document VP 6340S 1600 LG 0001 077
The results of this study provide the exact settings of the
must be tuned before commissioning of the plant.
SYSTEM DESCRIPTION AND INPUT DATA
Reference Documents
DW 6340S 120 1633 0001NC 6340S 120 1634 0001NC 6340S 999 1630 0020NC 6340S 999 1630 0021VP 6340S 1600 LG 0001 077NC 6340S 550 1600 001NC 6340S 550 1600 002NC 6340S 550 1600 003NC 6340S 550 1600 005SLD 6340S 550 1600 0002
Doc. No. :
Gas Field Development (Phases X)
INTRODUCTION
X within the
hydrocarbon fluid by the sub
The Temporary Electrical Power required for phases
n Petrochemical Complex through 132
Six generators that are connected to the
that contains 132kV cable and 13
temporary supply relay setting
The objective of this document is to do relay settings and coordination analysis for temporary supply
33KV outgoing to the Gas plant relays that are coordinated
VP 6340S 1600 LG 0001 077
The results of this study provide the exact settings of the
tuned before commissioning of the plant.
SYSTEM DESCRIPTION AND INPUT DATA
Reference Documents
DW 6340S 120 1633 0001 NC 6340S 120 1634 0001 NC 6340S 999 1630 0020
6340S 999 1630 0021 VP 6340S 1600 LG 0001 077NC 6340S 550 1600 001 NC 6340S 550 1600 002 NC 6340S 550 1600 003 NC 6340S 550 1600 005 SLD 6340S 550 1600 0002
RELAY SETTING
STUDY
Doc. No. : NC-
)
within the X Gas Field Development project
hydrocarbon fluid by the sub-marine pipelines. The refinery is located at
The Temporary Electrical Power required for phases
n Petrochemical Complex through 132
Six generators that are connected to the
that contains 132kV cable and 132/33kV transformer.
temporary supply relay setting and coordination studies are described in this document.
The objective of this document is to do relay settings and coordination analysis for temporary supply
Gas plant relays that are coordinated
VP 6340S 1600 LG 0001 077
The results of this study provide the exact settings of the
tuned before commissioning of the plant.
SYSTEM DESCRIPTION AND INPUT DATA
General Single Line Diagram Electrical Load Summary Short Circuit and Load Flow Study Dynamic Stability Study
VP 6340S 1600 LG 0001 077 (Issued with no name)Switching Overvoltage StudyLoad Flow StudyShort Circuit StudyMotor Starting Study
Single Line Diagram
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
Gas Field Development project
marine pipelines. The refinery is located at
The Temporary Electrical Power required for phases
n Petrochemical Complex through 132kv underground cable line and a 132kV/33
Six generators that are connected to the X National grid are assumed to supply electric power through circuit
2/33kV transformer.
and coordination studies are described in this document.
The objective of this document is to do relay settings and coordination analysis for temporary supply
Gas plant relays that are coordinated
VP 6340S 1600 LG 0001 077.
The results of this study provide the exact settings of the
tuned before commissioning of the plant.
SYSTEM DESCRIPTION AND INPUT DATA
General Single Line DiagramElectrical Load SummaryShort Circuit and Load Flow StudyDynamic Stability Study(Issued with no name)Switching Overvoltage StudyLoad Flow Study made by TOMShort Circuit Study made by TMotor Starting Study Single Line Diagram
RELAY SETTING
(CT2000:5)
1600-0004
)
Gas Field Development project
marine pipelines. The refinery is located at
The Temporary Electrical Power required for phases X Gas Plant shall be supplied from Power Plan
v underground cable line and a 132kV/33
National grid are assumed to supply electric power through circuit
2/33kV transformer.
and coordination studies are described in this document.
The objective of this document is to do relay settings and coordination analysis for temporary supply
Gas plant relays that are coordinated by another vendor and made available to us
The results of this study provide the exact settings of the concerned
SYSTEM DESCRIPTION AND INPUT DATA
General Single Line Diagram Electrical Load Summary Short Circuit and Load Flow StudyDynamic Stability Study (Issued with no name) Switching Overvoltage Study made by TOM
made by TOM made by TOM made by TOM
Rev. No. :
Gas Field Development project are designed to process the incoming
marine pipelines. The refinery is located at X Village, about 270 km South
Gas Plant shall be supplied from Power Plan
v underground cable line and a 132kV/33
National grid are assumed to supply electric power through circuit
and coordination studies are described in this document.
The objective of this document is to do relay settings and coordination analysis for temporary supply
by another vendor and made available to us
concerned relays of the temporary supply
Short Circuit and Load Flow Study
made by TOM
OM made by TOM
0
designed to process the incoming
X Village, about 270 km South
Gas Plant shall be supplied from Power Plan
v underground cable line and a 132kV/33kV, 100MVA power
National grid are assumed to supply electric power through circuit
and coordination studies are described in this document.
The objective of this document is to do relay settings and coordination analysis for temporary supply
by another vendor and made available to us
of the temporary supply
Page 6
designed to process the incoming
X Village, about 270 km South East
Gas Plant shall be supplied from Power Plan
, 100MVA power
National grid are assumed to supply electric power through circuit
The objective of this document is to do relay settings and coordination analysis for temporary supply up to
by another vendor and made available to us
of the temporary supply which
6 of 158
designed to process the incoming
East
Gas Plant shall be supplied from Power Plant of
, 100MVA power
National grid are assumed to supply electric power through circuit
up to
by another vendor and made available to us
which
X Gas Field Development (Phases
3.2.
PASHA (Power Apparatus and System Homological Analysis), Version studies. The software is product of TOM and serving the electrical utilities and the industries
years worldwide.
3.3.
Single line diagram
view of the overall electrical network represented in the present studies.
Gas plant is analyzed and equalized in Appendix I.
line diagram as represented in
Documents
Here,
loads are
induction motor loads are summed and represented as equivalent m
bars.
detailed representation of GAS PLANT electrical systems.
Figure 2 shows the electrical network representation whe
PLANT is represented inside the network, please see also drawing
6340S 550 1600 000
represented
are selected such that the
comes from the overall
documentation and reportings easiear.
In
and the
Therefore, they are included in the representation of the electrical networks as
report the neighboring factories are
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
side of the external plants cannot
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
all the motor fault contribu
shown in
Gas Field Development (Phases
System Analysis Software
PASHA (Power Apparatus and System Homological Analysis), Version studies. The software is product of TOM and serving the electrical utilities and the industries
years worldwide.
Electrical System Representation
3.3.1. Network Topology
Single line diagram
view of the overall electrical network represented in the present studies.
Gas plant is analyzed and equalized in Appendix I.
line diagram as represented in
Documents NC 6340S 999 1630 0020
Here, 11 KV motor loads are represented separately based on their dynamic models.
loads are also
induction motor loads are summed and represented as equivalent m
bars. Static loads are lumped represented on their appropriate locations.
detailed representation of GAS PLANT electrical systems.
Figure 2 shows the electrical network representation whe
PLANT is represented inside the network, please see also drawing
6340S 550 1600 000
represented as
are selected such that the
comes from the overall
documentation and reportings easiear.
n fault and relay coordination studies
and their contributions
Therefore, they are included in the representation of the electrical networks as
report the neighboring factories are
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
side of the external plants cannot
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
all the motor fault contribu
shown in EXTERNAL
Doc. No. :
Gas Field Development (Phases X)
System Analysis Software
PASHA (Power Apparatus and System Homological Analysis), Version studies. The software is product of TOM and serving the electrical utilities and the industries
years worldwide.
Electrical System Representation
Network Topology
Single line diagram of the involving
view of the overall electrical network represented in the present studies.
Gas plant is analyzed and equalized in Appendix I.
line diagram as represented in
NC 6340S 999 1630 0020
KV motor loads are represented separately based on their dynamic models.
also represented separately based on their dynamic models
induction motor loads are summed and represented as equivalent m
Static loads are lumped represented on their appropriate locations.
detailed representation of GAS PLANT electrical systems.
Figure 2 shows the electrical network representation whe
PLANT is represented inside the network, please see also drawing
6340S 550 1600 0001 at the end of this report inside appendix I.
as equivalent induction motor
are selected such that the
comes from the overall loads and
documentation and reportings easiear.
fault and relay coordination studies
ir contributions in device
Therefore, they are included in the representation of the electrical networks as
report the neighboring factories are
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
side of the external plants cannot
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
all the motor fault contributions to short circuit are congregated in the coupled bus.
EXTERNAL area in Figure 2.
RELAY SETTING
STUDY
Doc. No. : NC-
)
System Analysis Software
PASHA (Power Apparatus and System Homological Analysis), Version studies. The software is product of TOM and serving the electrical utilities and the industries
Electrical System Representation
of the involving plants are
view of the overall electrical network represented in the present studies.
Gas plant is analyzed and equalized in Appendix I.
line diagram as represented in drawing
NC 6340S 999 1630 0020,
KV motor loads are represented separately based on their dynamic models.
represented separately based on their dynamic models
induction motor loads are summed and represented as equivalent m
Static loads are lumped represented on their appropriate locations.
detailed representation of GAS PLANT electrical systems.
Figure 2 shows the electrical network representation whe
PLANT is represented inside the network, please see also drawing
at the end of this report inside appendix I.
equivalent induction motor
are selected such that the static power requirment
loads and induction motors existing i
documentation and reportings easiear. The
fault and relay coordination studies we need to consider the maximum planed and in operation fault level
in device setting studies. The neighboring factories play important rule in this regard.
Therefore, they are included in the representation of the electrical networks as
report the neighboring factories are called
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
side of the external plants cannot be closed together.
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
tions to short circuit are congregated in the coupled bus.
area in Figure 2.
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
PASHA (Power Apparatus and System Homological Analysis), Version studies. The software is product of TOM and serving the electrical utilities and the industries
plants are used to
view of the overall electrical network represented in the present studies.
Gas plant is analyzed and equalized in Appendix I. For the purpose of the equalization, the Gas Plant, single
drawing DW 6340S 120 1633 0001
, NC 6340S 999 1630 002
KV motor loads are represented separately based on their dynamic models.
represented separately based on their dynamic models
induction motor loads are summed and represented as equivalent m
Static loads are lumped represented on their appropriate locations.
detailed representation of GAS PLANT electrical systems.
Figure 2 shows the electrical network representation whe
PLANT is represented inside the network, please see also drawing
at the end of this report inside appendix I.
equivalent induction motors and loads
power requirment and the dynamic behaviour
induction motors existing i
The Gas plant
we need to consider the maximum planed and in operation fault level
studies. The neighboring factories play important rule in this regard.
Therefore, they are included in the representation of the electrical networks as
called External plants
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
be closed together.
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
tions to short circuit are congregated in the coupled bus.
RELAY SETTING
(CT2000:5)
1600-0004
)
PASHA (Power Apparatus and System Homological Analysis), Version studies. The software is product of TOM and serving the electrical utilities and the industries
used to produce the study power system. Figure 1
view of the overall electrical network represented in the present studies.
For the purpose of the equalization, the Gas Plant, single
DW 6340S 120 1633 0001
NC 6340S 999 1630 002
KV motor loads are represented separately based on their dynamic models.
represented separately based on their dynamic models
induction motor loads are summed and represented as equivalent m
Static loads are lumped represented on their appropriate locations.
detailed representation of GAS PLANT electrical systems.
Figure 2 shows the electrical network representation where the static and dynamic equivalent of the GAS
PLANT is represented inside the network, please see also drawing
at the end of this report inside appendix I.
and loads. The parameters of the equivalent induction motors
and the dynamic behaviour
induction motors existing i
Gas plant equivalent is shown in
we need to consider the maximum planed and in operation fault level
studies. The neighboring factories play important rule in this regard.
Therefore, they are included in the representation of the electrical networks as
xternal plants. The external plants are represented by their
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
be closed together. Maximum fault current contribution
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
tions to short circuit are congregated in the coupled bus.
Rev. No. :
PASHA (Power Apparatus and System Homological Analysis), Version 2008, was used for performing the studies. The software is product of TOM and serving the electrical utilities and the industries
produce the study power system. Figure 1
view of the overall electrical network represented in the present studies.
For the purpose of the equalization, the Gas Plant, single
DW 6340S 120 1633 0001 is represented
NC 6340S 999 1630 0021 are used to provide the required data.
KV motor loads are represented separately based on their dynamic models.
represented separately based on their dynamic models. Other 6KV motors and
induction motor loads are summed and represented as equivalent motor loads on
Static loads are lumped represented on their appropriate locations. Please refer to appendix I for
re the static and dynamic equivalent of the GAS
PLANT is represented inside the network, please see also drawing DW 6340S 550 1600 0002
at the end of this report inside appendix I. The dynamic loads
. The parameters of the equivalent induction motors
and the dynamic behaviour
induction motors existing in the Gas Plant.
valent is shown in GASEQUAL
we need to consider the maximum planed and in operation fault level
studies. The neighboring factories play important rule in this regard.
Therefore, they are included in the representation of the electrical networks as
. The external plants are represented by their
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
aximum fault current contribution
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
tions to short circuit are congregated in the coupled bus.
0
, was used for performing the studies. The software is product of TOM and serving the electrical utilities and the industries
produce the study power system. Figure 1
For the purpose of the equalization, the Gas Plant, single
is represented in PASHA software.
are used to provide the required data.
KV motor loads are represented separately based on their dynamic models. Some of 6
Other 6KV motors and
otor loads on their corresponding bus
Please refer to appendix I for
re the static and dynamic equivalent of the GAS
DW 6340S 550 1600 0002
The dynamic loads of this plant
. The parameters of the equivalent induction motors
and the dynamic behaviour of the load matches those
n the Gas Plant. Equalization, makes
GASEQUAL area in Figure 2.
we need to consider the maximum planed and in operation fault level
studies. The neighboring factories play important rule in this regard.
Therefore, they are included in the representation of the electrical networks as it is shown in Figure 2. In this
. The external plants are represented by their
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars o
aximum fault current contributions
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
tions to short circuit are congregated in the coupled bus. The external plants are
Page 7
, was used for performing the studies. The software is product of TOM and serving the electrical utilities and the industries for twenty three
produce the study power system. Figure 1 shows a
For the purpose of the equalization, the Gas Plant, single
in PASHA software.
are used to provide the required data.
Some of 6 KV motor
Other 6KV motors and 400 V
their corresponding bus
Please refer to appendix I for
re the static and dynamic equivalent of the GAS
DW 6340S 550 1600 0002, and DW
of this plant
. The parameters of the equivalent induction motors
of the load matches those
Equalization, makes
area in Figure 2.
we need to consider the maximum planed and in operation fault level
studies. The neighboring factories play important rule in this regard.
shown in Figure 2. In this
. The external plants are represented by their
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
transformer of these plants is also considered in the studies. This is because the bus bars on 20KV or 33KV
s of these plants
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
The external plants are
7 of 158
, was used for performing the for twenty three
hows a
For the purpose of the equalization, the Gas Plant, single
in PASHA software.
are used to provide the required data.
KV motor
400 V
their corresponding bus
Please refer to appendix I for
re the static and dynamic equivalent of the GAS
DW
of this plant are
. The parameters of the equivalent induction motors
of the load matches those
Equalization, makes
area in Figure 2.
we need to consider the maximum planed and in operation fault levels
studies. The neighboring factories play important rule in this regard.
shown in Figure 2. In this
. The external plants are represented by their
lumped loads equivalence. For these lumped loads 80% motor loads is considered. One incoming
or 33KV
of these plants
are imposed in their respective board when a bus coupler is closed while one incomer is opened. Therefore
The external plants are
X Gas Field Development (Phases
The existence of the connection of
This is shown in Figure 2
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of th
represented in this report.
The box
feeds
motor
11KV
As mentioned the equalization is just made to simplify the reporting, the actual
considered inside the Gas plant
Gas Field Development (Phases
The existence of the connection of
This is shown in Figure 2
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of th
represented in this report.
The box RELAY
feeds the various substations
motors of the Gas plant
11KV area.
As mentioned the equalization is just made to simplify the reporting, the actual
considered inside the Gas plant
Doc. No. :
Gas Field Development (Phases X)
The existence of the connection of
This is shown in Figure 2 in
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of th
represented in this report.
RELAY is introduced inside the
the various substations
s of the Gas plant is also considered. The selected equivalent motors are intdicated in Figure 2 in
As mentioned the equalization is just made to simplify the reporting, the actual
considered inside the Gas plant
RELAY SETTING
STUDY
Doc. No. : NC-
)
The existence of the connection of MOB
in GRID area. The
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of th
is introduced inside the
the various substations inside the Gas plant. The bahaviour of 33KV relays protecting the
is also considered. The selected equivalent motors are intdicated in Figure 2 in
As mentioned the equalization is just made to simplify the reporting, the actual
considered inside the Gas plant but it does not included in the reports.
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
MOBIN power generation plant to
. The detailed representation of the X
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of th
is introduced inside the Gas plant equivalent to consider for the outgoing 33KV relays
inside the Gas plant. The bahaviour of 33KV relays protecting the
is also considered. The selected equivalent motors are intdicated in Figure 2 in
As mentioned the equalization is just made to simplify the reporting, the actual
but it does not included in the reports.
RELAY SETTING
(CT2000:5)
1600-0004
)
power generation plant to
detailed representation of the X
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of th
Gas plant equivalent to consider for the outgoing 33KV relays
inside the Gas plant. The bahaviour of 33KV relays protecting the
is also considered. The selected equivalent motors are intdicated in Figure 2 in
As mentioned the equalization is just made to simplify the reporting, the actual
but it does not included in the reports.
Rev. No. :
power generation plant to X National GRID
detailed representation of the X national power grid is already
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of th
Gas plant equivalent to consider for the outgoing 33KV relays
inside the Gas plant. The bahaviour of 33KV relays protecting the
is also considered. The selected equivalent motors are intdicated in Figure 2 in
As mentioned the equalization is just made to simplify the reporting, the actual
but it does not included in the reports.
0
National GRID is also considered.
national power grid is already
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
network which includes the 63KV of the Esfahan is used to provide the equivalent of the power grid as
Gas plant equivalent to consider for the outgoing 33KV relays
inside the Gas plant. The bahaviour of 33KV relays protecting the
is also considered. The selected equivalent motors are intdicated in Figure 2 in
As mentioned the equalization is just made to simplify the reporting, the actual 33KV relays behavior is also
Page 8
is also considered.
national power grid is already
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the
e power grid as
Gas plant equivalent to consider for the outgoing 33KV relays that
inside the Gas plant. The bahaviour of 33KV relays protecting the 11KV
is also considered. The selected equivalent motors are intdicated in Figure 2 in
relays behavior is also
8 of 158
is also considered.
national power grid is already
represented in PASHA software elsewhere. The 1990 deck of the 400KV, 230KV, and 132KV of the X
e power grid as
that
11KV
is also considered. The selected equivalent motors are intdicated in Figure 2 in
relays behavior is also
X Gas Field Development (Phases
Figure 1: The overall view of the study system
Gas Field Development (Phases
Figure 1: The overall view of the study system
Doc. No. :
Gas Field Development (Phases X)
Figure 1: The overall view of the study system
RELAY SETTING
STUDY
Doc. No. : NC-
)
Figure 1: The overall view of the study system
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
Figure 1: The overall view of the study system
RELAY SETTING
(CT2000:5)
1600-0004
)
Rev. No. :
0
Page 99 of 158
X Gas Field Development (Phases
Figure 2: The study system
Gas Field Development (Phases
Figure 2: The study system
Doc. No. :
Gas Field Development (Phases X)
Figure 2: The study system
RELAY SETTING
STUDY
Doc. No. : NC-
)
of this report
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
of this report; Gas plant equivalent (Appedix I) is introduced
RELAY SETTING
(CT2000:5)
1600-0004
)
; Gas plant equivalent (Appedix I) is introduced
Rev. No. :
; Gas plant equivalent (Appedix I) is introduced
0
; Gas plant equivalent (Appedix I) is introduced
Page 1010 of 158
X Gas Field Development (Phases
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
which includes the drawn equipment data on system
Table 1
dynamic loads are represented with type
8000000
appenix I.
Table 2 shows the system parameters after base conversion.
considered equal to 14.3 km per phase.
Appendix I.
Gas Field Development (Phases
3.3.2. Network Parameters and Data
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
which includes the drawn equipment data on system
Table 1 contain
dynamic loads are represented with type
8000000 to 89
appenix I.
Table 2 shows the system parameters after base conversion.
considered equal to 14.3 km per phase.
Appendix I.
Doc. No. :
Gas Field Development (Phases X)
Network Parameters and Data
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
which includes the drawn equipment data on system
contains the base DATA
dynamic loads are represented with type
8999999. For the detailed data base of the Gas plant equipment please refer to Table I.1 of
Table 2 shows the system parameters after base conversion.
considered equal to 14.3 km per phase.
RELAY SETTING
STUDY
Doc. No. : NC-
)
Network Parameters and Data
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
which includes the drawn equipment data on system
base DATA for equipment parameters
dynamic loads are represented with type
For the detailed data base of the Gas plant equipment please refer to Table I.1 of
Table 2 shows the system parameters after base conversion.
considered equal to 14.3 km per phase.
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
which includes the drawn equipment data on system
for equipment parameters
dynamic loads are represented with types 9000 to 9030 and those lumped loads are represented with type
For the detailed data base of the Gas plant equipment please refer to Table I.1 of
Table 2 shows the system parameters after base conversion.
considered equal to 14.3 km per phase. For GAS PLANT deta
RELAY SETTING
(CT2000:5)
1600-0004
)
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
which includes the drawn equipment data on system base.This is selected
for equipment parameters of the equivalent study system
to 9030 and those lumped loads are represented with type
For the detailed data base of the Gas plant equipment please refer to Table I.1 of
Table 2 shows the system parameters after base conversion. The length of 132KV temporary cable is
For GAS PLANT detailed input data please refer to Table I.2 of
Rev. No. :
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
base.This is selected to be
of the equivalent study system
to 9030 and those lumped loads are represented with type
For the detailed data base of the Gas plant equipment please refer to Table I.1 of
The length of 132KV temporary cable is
iled input data please refer to Table I.2 of
0
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
to be 10MVA.
of the equivalent study system
to 9030 and those lumped loads are represented with type
For the detailed data base of the Gas plant equipment please refer to Table I.1 of
The length of 132KV temporary cable is
iled input data please refer to Table I.2 of
Page 11
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
of the equivalent study system. The equivalent
to 9030 and those lumped loads are represented with type
For the detailed data base of the Gas plant equipment please refer to Table I.1 of
The length of 132KV temporary cable is
iled input data please refer to Table I.2 of
11 of 158
The data are provided in two groups. One is from PASHA data bases which contains the fundamental data
of equipment, usually based on the equipment ratings. The second one is according to PASHA edit pages
. The equivalent
to 9030 and those lumped loads are represented with types
For the detailed data base of the Gas plant equipment please refer to Table I.1 of
The length of 132KV temporary cable is
iled input data please refer to Table I.2 of
X Gas Field Development (Phases
Gas Field Development (Phases
CABLE
SIZE
1(500)
1(400)
1(800)
Used for Tie
connections
and those not
known
Note : RATING MVA IS
Doc. No. :
Gas Field Development (Phases X)
CABLE
Type
MANUFACT.
FICT
FICT
FICT
Note : RATING MVA IS OBTAINED FROM CABLE CURRENT CAPACITY, RATINGS ARE
RELAY SETTING
STUDY
Doc. No. : NC-
)
Table 1
PA
SH
A L
IB.
33
6
15
OBTAINED FROM CABLE CURRENT CAPACITY, RATINGS ARE
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
Table 1 Data base for system equipment
CABLES AND LINES
RA
TIN
G M
VA
RA
TIN
G K
V
100 33
5 6
160 15
OBTAINED FROM CABLE CURRENT CAPACITY, RATINGS ARE
RELAY SETTING
(CT2000:5)
1600-0004
)
Data base for system equipment
CABLES AND LINES DATA BASE
RA
TIN
G K
V
RE
SIS
TA
NC
E
PU
/KM
OBTAINED FROM CABLE CURRENT CAPACITY, RATINGS ARE
Rev. No. :
Data base for system equipment
DATA BASE
RE
AC
TA
NC
E
PU
/KM
0.0001
0.0001
0.0001
OBTAINED FROM CABLE CURRENT CAPACITY, RATINGS ARE THE PU BASES
0
SU
SE
PT
AN
CE
PU
/KM
ZE
RO
PU BASES
Page 12
ZE
RO
SE
QU
EN
CE
RE
SIS
TA
NC
E-
PU
/KM
ZE
RO
12 of 158
ZE
RO
SE
QU
EN
CE
RE
AC
TA
NC
E-
PU
/KM
0.0003
0.0003
0.0003
X Gas Field Development (Phases
RA
TIN
G (
BA
SE
) M
VA
*400A grounding resistor considered,
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
Gas Field Development (Phases
RA
TIN
G (
BA
SE
) M
VA
U1
/U2
KV
/KV
A grounding resistor considered,
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
Doc. No. :
Gas Field Development (Phases X)
CO
NN
EC
TIO
N T
YP
E
**
A grounding resistor considered,
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
RELAY SETTING
STUDY
Doc. No. : NC-
)
PA
SH
A L
IB.
!""#$% %&'"
A grounding resistor considered,
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
TRANSFORMERS
RE
SIS
TA
NC
E P
U
RE
AC
TA
NC
E P
U
( %&'"
) %&'"
*+",-%"' %&
(.+-
!""#$% %&'"
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
RELAY SETTING
(CT2000:5)
1600-0004
)
TRANSFORMERS DATA BASE
RE
AC
TA
NC
E P
U ZERO SEQUENCE
RE
SIS
TA
NC
E P
U*
( %&'"
) %&'"
*+",-%"' %&
.+- %&'"
!""#$% %&'"
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
Rev. No. :
DATA BASE
ZERO SEQUENCE
RE
SIS
TA
NC
E P
U*
RE
AC
TA
NC
E P
U
( %&'"
) %&'"/
*+",-%"' %&'"%
%&'"
!""#$% %&'"
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
0
MIN
. T
AP
/
/
/
/
/
/
/
/
/
/
!""#$% %&'"
/
**X means Yn and from simulation point of view DY11 is equal to DY5, and DY1 is equal to DY7,
Page 13
TA
P S
TE
P
MA
X. T
AP
13 of 158
RA
TIO
DV
Ty
pe
or
MA
NU
FA
CT
.
/
Ty
pe
or
MA
NU
FA
CT
.
X Gas Field Development (Phases
*0.1"
*0.1"
*0.1"
*0.1"
*0.1"
*0.1"
*0.1"
*0.1
*0.1"
*0.1
*0.1"
*0.1
*0.1"
*0.1
*0.1"
*0.1"
Gas Field Development (Phases
RA
TE
D
KW
*0.1"
*0.1"
.1"
*0.1"
.1"
*0.1"
.1"
*0.1"
*0.1"
*0.1"
*0.1"
*0.1"
*0.1"
*0.1"
.1"
*0.1"
*Driven Typ
Doc. No. :
Gas Field Development (Phases X)
PA
SH
A
VO
LT
AG
E
LIB. KV
*Driven Type: Mechanical
RELAY SETTING
STUDY
Doc. No. : NC-
)
VO
LT
AG
E
BA
SE
KV MVA REACT.
Mechanical Torque Formula=(A+B(1
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
MOTORS
MA
GN
ET
IZIN
G
REAC T.-PU R
ES
IST
.-P
U
Torque Formula=(A+B(1
RELAY SETTING
(CT2000:5)
1600-0004
)
MOTORS DATA BASE
STATOR
RE
SIS
T.-
PU
RE
AC
T-P
U
Torque Formula=(A+B(1-s)+C(1-s)2)Tmo where A+B+C=1, B and C is written and s is slip.
Rev. No. :
DATA BASE
RE
SIS
T.-
PU
)Tmo where A+B+C=1, B and C is written and s is slip.
0
ROTOR
RE
AC
T.-
PU
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*2
*2
*2
)Tmo where A+B+C=1, B and C is written and s is slip.
Page 14
Type or Man ufac turer
H (
Sec
.)
(to
tal)
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*23
*2
*2
*2
)Tmo where A+B+C=1, B and C is written and s is slip.
14 of 158
OTHERS
(to
tal)
(d
rive
n)
Driven
TYPE*
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
)Tmo where A+B+C=1, B and C is written and s is slip.
X Gas Field Development (Phases
Gas Field Development (Phases
RA
TE
D
MVA
*Driven Typ
Doc. No. :
Gas Field Development (Phases X)
PA
SH
A
VO
LT
AG
E
LIB. KV
Type: Mechanical Torque Formula=(A+B(1
RELAY SETTING
STUDY
Doc. No. : NC-
)
BA
SE
MVA REACT.-
nical Torque Formula=(A+B(1
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
LUMPED LOAD
MA
GN
ET
IZIN
G
REAC
-PU RE
SIS
T.-
PU
nical Torque Formula=(A+B(1
RELAY SETTING
(CT2000:5)
1600-0004
)
LUMPED LOADS DATA BASE
STATOR
RE
AC
T-P
U
nical Torque Formula=(A+B(1-s)+C(1-s)2)Tmo where A+B+C=1, B and C is written and s is slip.
Rev. No. :
DATA BASE
RE
SIS
T.-
PU
)Tmo where A+B+C=1, B and C is written and s is slip.
0
ROTOR
RE
AC
T.-
PU
% STATIC
)Tmo where A+B+C=1, B and C is written and s is slip.
Page 15
% STATIC Load
H (
Se
c.)
(t
ota
l)
)Tmo where A+B+C=1, B and C is written and s is slip.
15 of 158
OTHERS
(to
tal)
(d
rive
n)
Driven
TYPE*
4
4
4
4
4
4
4
4
4
)Tmo where A+B+C=1, B and C is written and s is slip.
X Gas Field Development (Phases
PASHA
LIB.
RATED
POWER
MVA
Gas Field Development (Phases
*10A grounding resistor considered
X'd
RATED
POWER TYPE
%."
.%."
Doc. No. :
Gas Field Development (Phases X)
A grounding resistor considered
DIRECT AXIS
'd
RATED
VOLTAGE
KV
%."
.%."
RELAY SETTING
STUDY
Doc. No. : NC-
)
A grounding resistor considered
DIRECT AXIS
X"d
RATED PASHA
VOLTAGE
LIB.
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
GENERATOR DATA BASE
"d
RESISTANCE
PU
RELAY SETTING
(CT2000:5)
1600-0004
)
GENERATOR DATA BASE
Xq
RESISTANCE REACTANCE
PU
Rev. No. :
GENERATOR DATA BASE
X'q
REACTANCE
PU
RESISTANCE
0
QUADRATURE AXES
X'q 'q
ZERO SEQUENCE
RESISTANCE-
PU
5
5
Page 16
QUADRATURE AXES
'q X"q
ZERO SEQUENCE
REACTANCE
PU
16 of 158
QUADRATURE AXES
X"q "q
H
REACTANCE-
(SEC)
&
X Gas Field Development (Phases
===========================
SYSTEM TITLE: TEMPORARY SUPPLY TO PHASES 9
STUDY TITLE:
SYSTEM MVA BASE = 10.000
PASHA ACTUAL DYNAMIC FAULT IS ACTIVE
B U S B A R D A T A I N P U T
------------------------
S Y N C H R O N O U S G E N E R A T O R S
BUSBAR P Q RES SYN
NAME (MW) (MVAR) R XD XD' XD" (MSEC) (MSEC)
GT1 107.04 78.05 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT2 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT3 100.00 7
GT4 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT5 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT6 100.00 77.64 0.0001 0.
WARNING
GRIDG 60.00 40.00 0.000
END OF SYNCHRONOUS MACHINE DATA
S T A T I C L O A D S
BUSBAR
NAME P(MW) Q(MVAR) MAG(PU) ANG(DEG) VNOM.(KV)
MBIN132 0.00 0.00 1.0000 0.000 132.000 MOBIN
GT6 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT4 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT2 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT1
GC1 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC2 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC4 0.00 0.00 1.0000 0.000 15.000 MOBIN
Gas Field Development (Phases
===========================
SYSTEM TITLE: TEMPORARY SUPPLY TO PHASES 9
STUDY TITLE:
SYSTEM MVA BASE = 10.000
PASHA ACTUAL DYNAMIC FAULT IS ACTIVE
B U S B A R D A T A I N P U T
------------------------
S Y N C H R O N O U S G E N E R A T O R S
GENERATION GENERATOR IMPEDANCES PU 0
BUSBAR P Q RES SYN
NAME (MW) (MVAR) R XD XD' XD" (MSEC) (MSEC)
GT1 107.04 78.05 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT2 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT3 100.00 77.64 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT4 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT5 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT6 100.00 77.64 0.0001 0.
WARNING - TDO' OF FOLLOWING MACHINE MISSING
GRIDG 60.00 40.00 0.000
END OF SYNCHRONOUS MACHINE DATA
S T A T I C L O A D S
BUSBAR LOAD INITIAL VOLTAGES AREA
NAME P(MW) Q(MVAR) MAG(PU) ANG(DEG) VNOM.(KV)
MBIN132 0.00 0.00 1.0000 0.000 132.000 MOBIN
GT6 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT4 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT2 0.00 0.00 1.0000 0.000 15.000 MOBIN
0.00 0.00 1.0000 0.000 15.000 MOBIN
GC1 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC2 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC4 0.00 0.00 1.0000 0.000 15.000 MOBIN
Doc. No. :
Gas Field Development (Phases X)
Table 2: List of DATA which ar
===========================
SYSTEM TITLE: TEMPORARY SUPPLY TO PHASES 9
SYSTEM MVA BASE = 10.000
PASHA ACTUAL DYNAMIC FAULT IS ACTIVE
B U S B A R D A T A I N P U T
-------------------------------------
S Y N C H R O N O U S G E N E R A T O R S
GENERATION GENERATOR IMPEDANCES PU 0
BUSBAR P Q RES SYN
NAME (MW) (MVAR) R XD XD' XD" (MSEC) (MSEC)
GT1 107.04 78.05 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT2 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
7.64 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT4 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT5 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT6 100.00 77.64 0.0001 0.
TDO' OF FOLLOWING MACHINE MISSING
GRIDG 60.00 40.00 0.0006 0.0025 0.0025 0.0000 0.00 0.00 GRID
END OF SYNCHRONOUS MACHINE DATA
S T A T I C L O A D S
LOAD INITIAL VOLTAGES AREA
NAME P(MW) Q(MVAR) MAG(PU) ANG(DEG) VNOM.(KV)
MBIN132 0.00 0.00 1.0000 0.000 132.000 MOBIN
GT6 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT4 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT2 0.00 0.00 1.0000 0.000 15.000 MOBIN
0.00 0.00 1.0000 0.000 15.000 MOBIN
GC1 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC2 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC4 0.00 0.00 1.0000 0.000 15.000 MOBIN
RELAY SETTING
STUDY
Doc. No. : NC-
)
Table 2: List of DATA which ar
SYSTEM TITLE: TEMPORARY SUPPLY TO PHASES 9-10
PASHA ACTUAL DYNAMIC FAULT IS ACTIVE
B U S B A R D A T A I N P U T
-------------
S Y N C H R O N O U S G E N E R A T O R S
GENERATION GENERATOR IMPEDANCES PU 0
BUSBAR P Q RES SYN-X DA-TR-X DA
NAME (MW) (MVAR) R XD XD' XD" (MSEC) (MSEC)
GT1 107.04 78.05 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT2 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
7.64 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT4 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT5 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT6 100.00 77.64 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
TDO' OF FOLLOWING MACHINE MISSING
0.0025 0.0025 0.0000 0.00 0.00 GRID
LOAD INITIAL VOLTAGES AREA
NAME P(MW) Q(MVAR) MAG(PU) ANG(DEG) VNOM.(KV)
MBIN132 0.00 0.00 1.0000 0.000 132.000 MOBIN
GT6 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT4 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT2 0.00 0.00 1.0000 0.000 15.000 MOBIN
0.00 0.00 1.0000 0.000 15.000 MOBIN
GC1 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC2 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC4 0.00 0.00 1.0000 0.000 15.000 MOBIN
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
Table 2: List of DATA which ar
INPUT DATA
GENERATION GENERATOR IMPEDANCES PU 0-C TIME CONST
X DA-ST-X TDO' TDO" AREA
NAME (MW) (MVAR) R XD XD' XD" (MSEC) (MSEC)
GT1 107.04 78.05 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT2 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
7.64 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT4 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT5 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
1303 0.0158 0.0102 7550.00 30.00 MOBIN
TDO' OF FOLLOWING MACHINE MISSING
0.0025 0.0025 0.0000 0.00 0.00 GRID
LOAD INITIAL VOLTAGES AREA
NAME P(MW) Q(MVAR) MAG(PU) ANG(DEG) VNOM.(KV)
MBIN132 0.00 0.00 1.0000 0.000 132.000 MOBIN
GT6 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT4 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GT2 0.00 0.00 1.0000 0.000 15.000 MOBIN
0.00 0.00 1.0000 0.000 15.000 MOBIN
GC1 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC2 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC3 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC4 0.00 0.00 1.0000 0.000 15.000 MOBIN
RELAY SETTING
(CT2000:5)
1600-0004
)
Table 2: List of DATA which are represented in
INPUT DATA
C TIME CONST
X TDO' TDO" AREA
NAME (MW) (MVAR) R XD XD' XD" (MSEC) (MSEC)
GT1 107.04 78.05 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT2 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
7.64 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT4 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT5 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
1303 0.0158 0.0102 7550.00 30.00 MOBIN
0.0025 0.0025 0.0000 0.00 0.00 GRID
Rev. No. :
e represented in PASHA software
INPUT DATA
X TDO' TDO" AREA
GT1 107.04 78.05 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT2 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
7.64 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT4 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
GT5 100.00 74.45 0.0001 0.1303 0.0158 0.0102 7550.00 30.00 MOBIN
1303 0.0158 0.0102 7550.00 30.00 MOBIN
0.0025 0.0025 0.0000 0.00 0.00 GRID
0
PASHA software
Page 17
17 of 158
X Gas Field Development (Phases
GC5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC6 0.00 0.00 1.0000 0.000 15.000 MOBIN
INT1 0.00 0.00 1.0000 0.000 132.000 ALL
1S11A
1S11B 0.00 0.00 1.0000 0.000 33.000 ALL
MBF1321 0.00 0.00 1.0000 0.000 132.000 ALL
GRID 0.00 0.00 1.0000 0.000 132.000 ALL2
J1 0.00 0.00
J2 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J3 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J4 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J5 0.00
J6 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J7 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J8 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J9 0.00
ACIDA 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
COMMU 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
C2REC 3.40 2.11 1.0000 0.000 20.000 EXTERNAL
UREAA
SEAWA 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
4THAR 13.60 8.43 1.0000 0.000 20.000 EXTERNAL
ASU 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
10THO
9THOL 20.40 12.64 1.0000 0.000 20.000 EXTERNAL
AU1400 0.09 0.05 1.0000 0.000 0.400 AU1
AU16KV 0.85 0.53 1.0000 0.000 6.000 AU1
AU2400 0.09 0.05 1.0000 0.000 0.400 AU2
AU36KV 0.85 0.53 1.0000 0.000 6.000 AU3
AU3400 0.09 0.05 1.0000 0.000 0.400 AU3
AU4400 0.09 0.05 1.0000 0.000 0.400 AU4
AU5400 0.0
AU66KV 0.85 0.53 1.0000 0.000 6.000 AU6
AU6400 0.09 0.05 1.0000 0.000 0.400 AU6
GRID132 0.00 0.00 1.0000 0.000 132.000 GRID
GRID230 0.00 0.00 1
JGRID 0.00 0.00 1.0000 0.000 20.000 GRID
GRID20 0.00 0.00 1.0000 0.000 20.000 GRID
GRIDG 0.00 0.00 1.0000 0.000 230.000 GRID
OUT1 0.00 0.00 1.0000 0.00
J0 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
PH678 17.00 10.54 1.0000 0.000 33.000 EXTERNAL
STEQU1 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU1 0.00 0.00 1.0000 0.000
STEQU2 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU2 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM1 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM2 0.00 0.00 1.0000 0
09 0.00 0.00 1.0000 0.000 33.000 RELAY
REL1 0.00 0.00 1.0000 0.000 33.000 RELAY
08 0.00 0.00 1.0000 0.000 33.000 RELAY
Gas Field Development (Phases
GC5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC6 0.00 0.00 1.0000 0.000 15.000 MOBIN
INT1 0.00 0.00 1.0000 0.000 132.000 ALL
1S11A 0.00 0.00 1.0000 0.000 33.000 ALL
1S11B 0.00 0.00 1.0000 0.000 33.000 ALL
MBF1321 0.00 0.00 1.0000 0.000 132.000 ALL
GRID 0.00 0.00 1.0000 0.000 132.000 ALL2
J1 0.00 0.00
J2 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J3 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J4 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J5 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J6 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J7 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J8 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J9 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
ACIDA 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
COMMU 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
C2REC 3.40 2.11 1.0000 0.000 20.000 EXTERNAL
UREAA 6.12 3.79 1.0000 0.000 20.000 EXTERNAL
SEAWA 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
4THAR 13.60 8.43 1.0000 0.000 20.000 EXTERNAL
ASU 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
10THO 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
9THOL 20.40 12.64 1.0000 0.000 20.000 EXTERNAL
AU1400 0.09 0.05 1.0000 0.000 0.400 AU1
AU16KV 0.85 0.53 1.0000 0.000 6.000 AU1
AU2400 0.09 0.05 1.0000 0.000 0.400 AU2
AU36KV 0.85 0.53 1.0000 0.000 6.000 AU3
AU3400 0.09 0.05 1.0000 0.000 0.400 AU3
AU4400 0.09 0.05 1.0000 0.000 0.400 AU4
AU5400 0.09 0.05 1.0000 0.000 0.400 AU5
AU66KV 0.85 0.53 1.0000 0.000 6.000 AU6
AU6400 0.09 0.05 1.0000 0.000 0.400 AU6
GRID132 0.00 0.00 1.0000 0.000 132.000 GRID
GRID230 0.00 0.00 1
JGRID 0.00 0.00 1.0000 0.000 20.000 GRID
GRID20 0.00 0.00 1.0000 0.000 20.000 GRID
GRIDG 0.00 0.00 1.0000 0.000 230.000 GRID
OUT1 0.00 0.00 1.0000 0.00
J0 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
PH678 17.00 10.54 1.0000 0.000 33.000 EXTERNAL
STEQU1 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU1 0.00 0.00 1.0000 0.000
STEQU2 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU2 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM1 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM2 0.00 0.00 1.0000 0
09 0.00 0.00 1.0000 0.000 33.000 RELAY
REL1 0.00 0.00 1.0000 0.000 33.000 RELAY
08 0.00 0.00 1.0000 0.000 33.000 RELAY
Doc. No. :
Gas Field Development (Phases X)
GC5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC6 0.00 0.00 1.0000 0.000 15.000 MOBIN
INT1 0.00 0.00 1.0000 0.000 132.000 ALL
0.00 0.00 1.0000 0.000 33.000 ALL
1S11B 0.00 0.00 1.0000 0.000 33.000 ALL
MBF1321 0.00 0.00 1.0000 0.000 132.000 ALL
GRID 0.00 0.00 1.0000 0.000 132.000 ALL2
J1 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J2 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J3 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J4 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
J6 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J7 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J8 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
ACIDA 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
COMMU 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
C2REC 3.40 2.11 1.0000 0.000 20.000 EXTERNAL
6.12 3.79 1.0000 0.000 20.000 EXTERNAL
SEAWA 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
4THAR 13.60 8.43 1.0000 0.000 20.000 EXTERNAL
ASU 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
17.00 10.54 1.0000 0.000 20.000 EXTERNAL
9THOL 20.40 12.64 1.0000 0.000 20.000 EXTERNAL
AU1400 0.09 0.05 1.0000 0.000 0.400 AU1
AU16KV 0.85 0.53 1.0000 0.000 6.000 AU1
AU2400 0.09 0.05 1.0000 0.000 0.400 AU2
AU36KV 0.85 0.53 1.0000 0.000 6.000 AU3
AU3400 0.09 0.05 1.0000 0.000 0.400 AU3
AU4400 0.09 0.05 1.0000 0.000 0.400 AU4
9 0.05 1.0000 0.000 0.400 AU5
AU66KV 0.85 0.53 1.0000 0.000 6.000 AU6
AU6400 0.09 0.05 1.0000 0.000 0.400 AU6
GRID132 0.00 0.00 1.0000 0.000 132.000 GRID
GRID230 0.00 0.00 1.0000 0.000 230.000 GRID
JGRID 0.00 0.00 1.0000 0.000 20.000 GRID
GRID20 0.00 0.00 1.0000 0.000 20.000 GRID
GRIDG 0.00 0.00 1.0000 0.000 230.000 GRID
OUT1 0.00 0.00 1.0000 0.00
J0 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
PH678 17.00 10.54 1.0000 0.000 33.000 EXTERNAL
STEQU1 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU1 0.00 0.00 1.0000 0.000
STEQU2 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU2 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM1 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM2 0.00 0.00 1.0000 0
09 0.00 0.00 1.0000 0.000 33.000 RELAY
REL1 0.00 0.00 1.0000 0.000 33.000 RELAY
08 0.00 0.00 1.0000 0.000 33.000 RELAY
RELAY SETTING
STUDY
Doc. No. : NC-
)
GC5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC6 0.00 0.00 1.0000 0.000 15.000 MOBIN
INT1 0.00 0.00 1.0000 0.000 132.000 ALL
0.00 0.00 1.0000 0.000 33.000 ALL
1S11B 0.00 0.00 1.0000 0.000 33.000 ALL
MBF1321 0.00 0.00 1.0000 0.000 132.000 ALL
GRID 0.00 0.00 1.0000 0.000 132.000 ALL2
1.0000 0.000 132.000 EXTERNAL
J2 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J3 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J4 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
J6 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J7 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J8 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
ACIDA 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
COMMU 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
C2REC 3.40 2.11 1.0000 0.000 20.000 EXTERNAL
6.12 3.79 1.0000 0.000 20.000 EXTERNAL
SEAWA 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
4THAR 13.60 8.43 1.0000 0.000 20.000 EXTERNAL
ASU 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
17.00 10.54 1.0000 0.000 20.000 EXTERNAL
9THOL 20.40 12.64 1.0000 0.000 20.000 EXTERNAL
AU1400 0.09 0.05 1.0000 0.000 0.400 AU1
AU16KV 0.85 0.53 1.0000 0.000 6.000 AU1
AU2400 0.09 0.05 1.0000 0.000 0.400 AU2
AU36KV 0.85 0.53 1.0000 0.000 6.000 AU3
AU3400 0.09 0.05 1.0000 0.000 0.400 AU3
AU4400 0.09 0.05 1.0000 0.000 0.400 AU4
9 0.05 1.0000 0.000 0.400 AU5
AU66KV 0.85 0.53 1.0000 0.000 6.000 AU6
AU6400 0.09 0.05 1.0000 0.000 0.400 AU6
GRID132 0.00 0.00 1.0000 0.000 132.000 GRID
.0000 0.000 230.000 GRID
JGRID 0.00 0.00 1.0000 0.000 20.000 GRID
GRID20 0.00 0.00 1.0000 0.000 20.000 GRID
GRIDG 0.00 0.00 1.0000 0.000 230.000 GRID
OUT1 0.00 0.00 1.0000 0.000 33.000 ALL
J0 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
PH678 17.00 10.54 1.0000 0.000 33.000 EXTERNAL
STEQU1 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU1 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
STEQU2 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU2 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM1 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM2 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
09 0.00 0.00 1.0000 0.000 33.000 RELAY
REL1 0.00 0.00 1.0000 0.000 33.000 RELAY
08 0.00 0.00 1.0000 0.000 33.000 RELAY
RELAY SETTING
STUDY (CT2000:5)
-6340S-550-1600
)
GC5 0.00 0.00 1.0000 0.000 15.000 MOBIN
GC6 0.00 0.00 1.0000 0.000 15.000 MOBIN
INT1 0.00 0.00 1.0000 0.000 132.000 ALL
0.00 0.00 1.0000 0.000 33.000 ALL
1S11B 0.00 0.00 1.0000 0.000 33.000 ALL
MBF1321 0.00 0.00 1.0000 0.000 132.000 ALL
GRID 0.00 0.00 1.0000 0.000 132.000 ALL2
1.0000 0.000 132.000 EXTERNAL
J2 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J3 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J4 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
J6 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J7 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J8 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
ACIDA 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
COMMU 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
C2REC 3.40 2.11 1.0000 0.000 20.000 EXTERNAL
6.12 3.79 1.0000 0.000 20.000 EXTERNAL
SEAWA 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
4THAR 13.60 8.43 1.0000 0.000 20.000 EXTERNAL
ASU 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
17.00 10.54 1.0000 0.000 20.000 EXTERNAL
9THOL 20.40 12.64 1.0000 0.000 20.000 EXTERNAL
AU1400 0.09 0.05 1.0000 0.000 0.400 AU1
AU16KV 0.85 0.53 1.0000 0.000 6.000 AU1
AU2400 0.09 0.05 1.0000 0.000 0.400 AU2
AU36KV 0.85 0.53 1.0000 0.000 6.000 AU3
AU3400 0.09 0.05 1.0000 0.000 0.400 AU3
AU4400 0.09 0.05 1.0000 0.000 0.400 AU4
9 0.05 1.0000 0.000 0.400 AU5
AU66KV 0.85 0.53 1.0000 0.000 6.000 AU6
AU6400 0.09 0.05 1.0000 0.000 0.400 AU6
GRID132 0.00 0.00 1.0000 0.000 132.000 GRID
.0000 0.000 230.000 GRID
JGRID 0.00 0.00 1.0000 0.000 20.000 GRID
GRID20 0.00 0.00 1.0000 0.000 20.000 GRID
GRIDG 0.00 0.00 1.0000 0.000 230.000 GRID
0 33.000 ALL
J0 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
PH678 17.00 10.54 1.0000 0.000 33.000 EXTERNAL
STEQU1 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
33.000 GASEQUAL
STEQU2 2.75 3.06 1.0000 0.000 33.000 GASEQUAL
DYEQU2 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
DEQSM1 0.00 0.00 1.0000 0.000 33.000 GASEQUAL
.000 33.000 GASEQUAL
09 0.00 0.00 1.0000 0.000 33.000 RELAY
REL1 0.00 0.00 1.0000 0.000 33.000 RELAY
08 0.00 0.00 1.0000 0.000 33.000 RELAY
RELAY SETTING
(CT2000:5)
1600-0004
)
1.0000 0.000 132.000 EXTERNAL
J2 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J3 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J4 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
J6 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J7 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
J8 0.00 0.00 1.0000 0.000 132.000 EXTERNAL
0.00 1.0000 0.000 132.000 EXTERNAL
ACIDA 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
COMMU 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
C2REC 3.40 2.11 1.0000 0.000 20.000 EXTERNAL
6.12 3.79 1.0000 0.000 20.000 EXTERNAL
SEAWA 10.71 6.64 1.0000 0.000 20.000 EXTERNAL
4THAR 13.60 8.43 1.0000 0.000 20.000 EXTERNAL
ASU 17.00 10.54 1.0000 0.000 20.000 EXTERNAL
17.00 10.54 1.0000 0.000 20.000 EXTERNAL
9THOL 20.40 12.64 1.0000 0.000 20.000 EXTERNAL
J0 0.00 0.00 1.0000 0.000 132.000