Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
URS ^^yw.^̂GX $' R0cd ̂
Ar.i \i -*i IVERO
RELEASE ABATEMENT MEASURE PLAN
RTN 1-14205
ELECTRIC POWER RESEARCH INSTITUTE LENOX, MASSACHUSETTS
April 11,2002
Prepared for:
GENERAL ELECTRIC COMPANY SCHENECTADY, NEW YORK
Prepared by:
URS CORPORATION 646 PLANK ROAD, SUITE. 202 CLIFTON PARK, NY 12065
CO o 3 CO
o o
o o o Kl
URS
April 11, 2002
Department of Environmental Protection Western Regional Office Bureau of Waste Site Cleanup 436 Dwight Street, 5th Floor Springfield, Massachusetts 01103
RE: Vault Area Release Abatement Measure Plan Electric Power Research Institute 115 East New Lenox Road Lenox, Massachusetts RTN 1-14205
Dear Sir or Madam:
On behalf of our client, General Electric Power Systems (GEPS), URS Corporation (URS) submits one copy of the Vault Area Release Abatement Measure Plan (RAM Plan), dated April 11, 2002 as required by Massachusetts Contingency Plan (MCP) regulations (310 CMR 40.0000). The appropriate fee, established in 310 CMR 4.00, has been sent to the DEP Lock Box.
Any questions may be directed to Mr. Edward Jamison of GEPS at (518) 385-7979.
Very truly yours, URS Corporation
Eriko Fujita Project Manager
Don Porterfield, P.E. Manager - Clifton Park
cc: Edward F. Jamison, GEPS Kevin Mooney, GE CEP Kimberly McMorrow, Esq. - Wilson, Sonsini, Goodrich & Rosati Thomas P. Woodard, LSP - URS Corporation Thomas J. Nunno, P.E., LSP - Roux Associates
URS Corporation 646 Plank Road, Suite 202 Clifton Park, NV 12065 Tel 518 688 0015 GE-EPRI/Apnl 11, 2002 Fax 5186880022 1 91-28171712/L605 lldep doc
Massachusetts Department of Environmental Protectio BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking MEASURE (RAM & URAM) TRANSMITTAL FORM
1 4 2 0 5 ] Pursuant to 310 CMR 40.0444 - 0446 and 310 CMR 40.0462 - 0465 (Subpart D)
A. SITE LOCATION:
Site Name: Rlppt-.rig PQWPT- R^gparnh
Street: 11S reaat-- NP»W T.pnnv Rnad Legation Aid: Formp-rTy 1000. NPW T.pnnx Rnad
CityfTown: T.pnnx ZIP 01340-2216
| | Check here if a Tier Classification Submittal has been provided to DEP for this Release Tracking Number.
Related Release Tracking Numbers That This RAM or URAM
B. THIS FORM IS BEING USED TO: (check all that apply)
! Submit a RAM Plan (complete Sections A, B. C, D, E, F, J, K, L and M).
D Check here it this RAM Plan Is an update or modification ot a previously approved written RAM Date Submitted: Plan. | | Submit a RAM Status Report (complete Sections A, B, C, E, J, K, L and M).
| | Submit a RAM Completion Statement (complete Sections A, B, C, D, E, G, J, K, L and M).
| | Confirm or Provide URAM Notification (complete Sections A, B, H, K, L and M).
| | Submit a URAM Status Report (complete Sections A, B, C, E, J, K, L and M).
| | Submit a URAM Completion Statement (complete Sections A, B, C, D, E, I, J, K, L and M).
You must attach all supporting documentation required for each use of form Indicated, Including copies of any Legal Notices and Notices to Public Officials required by 310 CMR 40.1400.
C. SITE CONDITIONS:
] Check here if the source of the Release or Threat of Release is known.
If yes, check all sources that apply: | | LIST | | Pipe/Hose/Line | | AST | | Drums | | Transformer Boat
0] otner sPecifyQJ Tanker Truck [~1 Vehicle Siihaii-rf anp vaiill-.q
Identify Media and Receptors Affected: (check all that I I Air I I Groundwater I 1 Surface Water I I Sediments C7I Soil =r,r,lw\ '-' '-' '-' '-' L5U
[J Wetlands Q Storm Drain D Private Well Q Public Water Supply Q Zone 2 [^] Residence
j—| acnoo r—| Unknown other Specify: ___
Identify Release and/or Threat of Release Conditions at Site: (check all that apply)
| | 2 and 72 Hour Reporting Condition(s) f^jT) 120 Day Reporting Condition(s) Other Condition(s)
Describe
D
RAMs may be conducted concurrently with an IRA only with written DEP approval URAMs may not be conducted if any 2 or 72 Hour conditions exist at the site.
unionnatea Identify Oils and Hazardous Materials Released: (check all that Oils | | Heavy Metals QrJwantc
| | Others Specify:
D. DESCRIPTION OF RESPONSE ACTIONS: (check all that apply)
D uepioymem 01 Aosoroant or uoruainmem | | Assessment and/or Monitoring Only Matarialc 21 Excavation of Contaminated Soils | | Temporary Covers or Caps
| | Re-use, Recycling or Treatment | | Btoremediation
O On Site 0 Off Site Est. Vol.:_ cubic yards [ [ Soil Vapor Extraction
Describe: | | Structure Venting System
D Kroouci or INAM_ Store ^ On Site Off Site Est. Vol.: _ _________ cubic yards Rorrtworv SECTION D IS CONTINUED ON THE NEXT PAGE.
Revised 2/24/95 Supersedes Forms BWSC-007, 008, 009 and 010 (in part) Page 1 of 4 Do Not Alter This Form
Massachusetts Department of Environmental Protection BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking MEASURE (RAM & URAM) TRANSMITTAL FORM Pursuant to 310 CMR 40.0444 - 0446 and 310 CMR 40.0462 - 0465 (Subpart D)
D. DESCRIPTION OF RESPONSE ACTIONS (continued): varounowaier ireatment
QH Landfill Q Cover O Disposal EsL Vol.: 15_ . cubic yards I—I
] Removal of Drums, Tanks or Containers | | Air Sparging
Describe: .qiibstirfar-P Vanlt-.n | | Temporary Water Supplies
Removal of Other Contaminated Media | | Temporary Evacuation or Relocation of Residents
Specify Type and [ | Fencing and Sign Posting
Other Response Actions Describe
See 310 CMR 40.0442 for limitations on the scope and type of RAMs. See 310 CMR 40.0464 for performance standards for URAMs.
| | Check here if this RAM or URAM Involves the use of Innovative Technologies. DEP is interested in using this information to aid in creating an Innovative Technologies Clearinghouse.
Describe
E. TRANSPORT OF REMEDIATION WASTE: (If Remediation Waste has been sent to an off-site facility, answer the following
Name of
Town and State:.
Quantity of Remediation Waste Transported to
F. RAM PLAN:
| | Check here if this RAM Plan received previous oral approval from DEP as a continuation of a Limited Removal Action (LRA).
Date of Oral
| | If a RAM Compliance Fee is required, check here to certify that the fee has been submitted. You MUST attach a photocopy of the payment. See 310 CMR 40.0444(2) to learn when a fee is not required.
| | Check here If the RAM Plan is proposed for a Transition Site. If this is the case, you may need to attach an LSP Evaluation Opinion prior to undertaking the RAM, if not previously provided. See 310 CMR 40.0600 for further information about Transition Sites.
G. RAM COMPLETION STATEMENT:
If a RAM Compliance Fee is required in connection with submission of the RAM Completion Statement, check here to certify that the fee has been submitted. You MUST attach a photocopy of the payment. You owe this fee when submitting a RAM Completion Statement if you received oral approval of a RAM that continued an LRA, and have NOT previously submitted a RAM Plan and accompanying fee.
If any Remediation Waste will be stored, treated, managed, recycled or reused at the site following submission of the RAM Completion Statement, you must submit a Phase IV Remedy Implementation Plan, along with the appropriate transmlttal form, as an attachment to the
RAM Completion Statement.
H. URAM NOTIFICATION:
Identify Location Type: (check all that apply) Q Public Right of Way \^\ Utility Easement Private Property
Identify Utility Type: (check all that | | ^^^Jane \ I Water Natural Gas
| | Telephone | | Steam Lines | | Telecommunications | | Electric | | Other Specify: I—I onecK nere n you proviaea utr wnn previous oral nouncaiion 01 mis Date of O al
[~~| Check here if the property owner was NOT contacted prior to initiation of the URAM. If this is the case, you must attach an explanation of why the owner was not contacted, including the date and time when contact ultimately occurred. Check here if this URAM will occur In connection with the construction of new public utilities. If this is the case, document the nature
I and extent of encountered contamination, the scope and expense of necessary mitigation and the benefits amd limitations of project alternatives.
With the exception stated below, the person undertaking the URAM must provide the name and license number of an LSP engaged or employed in connection with the URAM:
LSP Name: LSP License Number:.
LSP information is not required if the URAM is limited to the excavation and/or handling of not rnore than 100 cubic yards of soil contaminated by Oil, or not more than 20 cubic yards of soil contaminated either by a Hazardous Material or a mixture of a Hazardous
Revised 2/24/95 Supersedes Forms BWSC-007, 008, 009 and 010 (in part) Page 2 of 4 Do Not Alter This Form
I
I
Massachusetts Department of Environmental Protection BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking MEASURE (RAM & URAM) TRANSMITTAL FORM Pursuant to 310 CMR 40.0444 - 0446 and 310 CMR 40.0462- 0465 (Subpart D)
I. URAM COMPLETION STATEMENT:
| Check here if this URAM was limited to the excavation and/or handling of not more than 100 cubic yards of soil contaminated by Oil. or not more than 20 cubic yards of soil contaminated by either a Hazardous Material or a mixture of a Hazardous Material and Oil.
If any Remediation Waste will be stored, treated, managed, recycled or reused at the site following submission of the URAM Completion Statement, you must submit either a Release Abatement Measure (RAM) Plan or a Phase IV Remedy Implementation Plan, along with the
appropriate transmittal form, as an attachment to the URAM Completion Statement
J. LSP OPINION:
I attest under the pains and penalties of perjury that I have personally examined and am familiar with this transmittal form, including any and all documents accompanying this submittal. In my professional opinion and judgment based upon application of (I) the standard of care in 309 CMR 4.02(1), (ii) the applicable provisions of 309 CMR 4.02(2) and (3), and (iii) the provisions of 309 CMR 4.03(5), to the best of my knowledge, information and belief,
> if Section B of this form Indicates that a Release Abatement Measure Plan Is being submitted, the response actlon(s) that Is (are) the subject of this submittal (I) has (have) been developed in accordance with the applicable provisions of M.G.L. c. 21E and 310 CMR 40.0000, (II) Is (are) appropriate and reasonable to accomplish the purposes of such response action(s) as set forth in the applicable provisions of M.G.L. c. 21E and 310 CMR 40.0000 and (HI) complles(y) with the identified provisions of all orders, permits, and approvals identified In this submittal;
> if Section B of this form indicates that a Release Abatement Measure Status Report or a Utility-Related Abatement Measure Status Report is being submitted, the response action(s) that Is (are) the subject of this submittal (i) Is (are) being implemented in accordance with the applicable provisions of M.G.L. c. 21E and 310 CMR 40.0000, (ii) is (are) appropriate and reasonable to accomplish the purposes of such response actlon(s) as sei forth in the applicable provisions of M.G.L. c. 21E and 310 CMR 40.0000 and (iii) complies(y) with the identified provisions of all orders, permits, and approvals Identified in this submittal;
> if Section B of this form indicates that a Release Abatement Measure Completion Statement or a Utility-Related Abatement Measure Completion Statement is being submitted, the response action(s) that is (are) the subject of this submittal (i) has (have) been developed and implemented in accordance with the applicable provisions of M.G.L. c. 21E and 310 CMR 40.0000, (ii) is (are) appropriate and reasonable to accomplish the purposes of such response action(s) as set forth in the applicable provisions of M.G.L. c. 21E and 310 CMR 40.0000 and (iii) complies(y) with the identified provisions of all orders, permits, and approvals Identified in this submittal;
I am aware that significant penalties may result, Including, but not limited to, possible fines and imprisonment, if I submit information which I know to be false, inaccurate or materially incomplete.
| | Check here if the Response Action(s) on which this opinion is based, if any, are (were) subject to any order(s), permit(s) and/or approval(s) issued by DEP or EPA. If the box is checked, you MUST attach a statement identifying the applicable pro
LSP Name: Thomas P. Wnndard LSP #: 141Q Stamp:
Telephone: 207-879-7686
FAX: (optional) ?r)7-fl7q-7fif l THOMAS P. WfX-f.ARD
Signature:
Date: 2-,
An LSP Opinion Is not required for a Utility-Related Abatement Measure Notification.
An LSP Opinion Is not required for a URAM Completion Statement If the URAM Is limited to the excavation and/or handling of not more than 100 cubic yards of soil contaminated by Oil, or not more than 20 cubic yards of soil contaminated either by Hazardous Material or
a mixture of Hazardous Material and Oil.
K. PERSON UNDERTAKING RAM OR URAM:
Name of Qpnpral Kl pr!hri r Pnwpr Systems
Name of RdwarH .Tanri Title: F.HS af.i nn Manager
Street: One Rivpr 4^ ,_ Bnnm 237...
City/Town: _S State: NY ZIP Code: 1 3 ^ 4 5 - 0 0 0 0
Telephone: Ri R - T R 5 - 7 9 7 9 Ext.: FAX:
Check here if there has been a change in person undertaking the RAM or URAM.
Revised 2/24/95 Supersedes Forms BWSC-007, 008, 009 and 010 (in part) Page 3 of 4 Do Not Alter This Form
Massachusetts Department of Environmental Protection BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking
MEASURE (RAM & URAM) TRANSMITTAL FORM Pursuant to 310 CMR 40.0444 - 0446 and 310 CMR 40.0462 - 0465 (Subpart D)
RELATIONSHIP TO SITE OF PERSON UNDERTAKING RAM or URAM: (check one)
] RP or PRP Specify: Q Owner Q Operator Q Generator Q Transporter Other RP or PRP: Former Owner
] Fiduciary, Secured Lender or Municipality with Exempt Status (as defined by M.G.L. c. 21E, s. 2)
] Agency or Public Utility on a Right of Way (as defined by M.G.L. c. 21E, a. 50))
~~j Any Other Person Undertaking RAM or URAM Specify
M. CERTIFICATION OF PERSON UNDERTAKING RAM OR URAM:
Jami gnn , attest under the pains and penalties of perjury (I) that I have personally examined and am familiar with the information contained In this submittal, Including any and all documents accompanying this transmittal form, (II) that, based on my inquiry of those Individuals Immediately responsible for obtaining the information, the material information contained in this submittal is, to the best of my knowledge and belief, true, accurate and complete, and (ill) that I am fully authorized to make this attestation on behalf of the entity legally responsible for this submittal. I/the person or entity on whose behalf this submittal Is made am/Is aware that there are significant penalties, including, but not limited to, possible fines and Imprisonment, for willfully submitting false, Inaccurate, or incomplete information.
,60n«&()£rt£By: fl/Wn?S.^/ "•>_>js*— ') . V " '_; " ~> V\ '„•>£ p'ri/> y, Title: _EHS_
nature)
Rlent-.-rir! Pnwpr Date: (print name of person or entity recorded in Section K)
Enter address of person providing certification, if different from address recorded in Section
Street: _ __
City/Town: ___ State: ZIP Code:
Telephone: Ext.: FAX: (optional)
YOU MUST COMPLETE ALL RELEVANT SECTIONS OF THIS FORM OR DEP MAY RETURN THE DOCUMENT AS INCOMPLETE. IF YOU SUBMIT AN INCOMPLETE FORM, YOU MAY BE PENALIZED FOR MISSING
A REQUIRED DEADLINE.
Revised 2/24/95 Supersedes Forms BWSC-007, 008, 009 and 010 (in part) Page 4 of 4 Do Not Alter This Form
TABLE OF CONTENTS
1.0 INTRODUCTION 1 2.0 PERSON ASSUMING RESPONSIBILITY FOR RAM 2 3.0 CURRENT SITE CONDITIONS 3 4.0 DESCRIPTION OF RELEASE 6 5.0 SURROUNDING RECEPTORS 10 6.0 RELEASE ABATEMENT MEASURE 11
6.1 OBJECTIVES 11 6.2 STRATEGY 11 6.3 SCOPE OF WORK 12
6.3.1 Task 1 -Notifications 13 6.3.2 Task 2 - Remove and Dispose Contents of Each Vault 13 6.3.3 Task 3 - Excavate and Dispose Selected Vaults and Surrounding Soil 14 6.3.4 Task 4-Restoration of the Area 15 6.3.5 Task 5 -Submit Response Action Outcome Statement 15
7.0 MANAGEMENT OF REMEDIATION WASTE 16 8.0 ENVIRONMENTAL MONITORING PLAN 17 9.0 SCHEDULE 18 10.0 SEAL AND SIGNATURE OF LSP 19
TABLES
Table 1 Summary of Extractable Petroleum Hydrocarbon Results - Soil Sample Table 2 Summary of Polychlorinated Biphenyl Results - Soil Samples Table 3 Summary of Extractable Petroleum Hydrocarbons Results - Water Samples Table 4 Summary of Polychlorinated Biphenyl Results - Water Samples
FIGURES
Figure 1 Site Location Figure 2 Site Map Figure 3 Vault Area Figure 4 Generalized Potentiometric Surface Map, January 17, 2001 Figure 5 Massachusetts GIS Site Scoring Map Figure 6 Vault Investigation
APPENDIX
Appendix A Release & Utility-Related Abatement Measure (RAM & URAM) Transmittal form (BWSC-106)
Appendix B Permit and WPA Form 5 - Order of Conditions Appendix C Boring Logs
GEPS-EPRI URS 91-28171712.007L6051R-rev.doc April 11,2002
1.0 INTRODUCTION
On behalf of GE Power Systems (GEPS), URS has prepared this Release Abatement Measure
Plan (RAM Plan) for submittal to the Massachusetts Department of Environmental Protection
(DEP). The RAM Plan summarizes how GEPS will decommission 13 out-of-service
underground vaults at the Electric Power Research Institute (EPRI) High Voltage Transmission
Research Center (HVTRC) in Lenox, Massachusetts. An original Release & Utility-Related
Abatement Measure Transmittal Form (BWSC-106) is included with this RAM Plan, and a copy
of the form is included in Appendix A.
The location of the EPRI site is shown on Figure 1, and a generalized site map showing the
buildings and features on the property is included as Figure 2. The vault area is shown on Figure
3. The underground vaults are reported to have been used historically at the site for the
research/development and evaluation of various types of electrical equipment (apparently
including transformers). In November 2000, samples of the materials present in all 13 vaults
were collected and submitted for laboratory analysis. The laboratory analytical data indicated
the presence of polychlorinated biphenyls (PCBs) and extractable petroleum hydrocarbons
(EPH) compounds at concentrations that exceeded Reportable Concentrations (RCS-2). On
January 28, 2001, GEPS was notified of these exceedances by EPRI's legal counsel. On May 5,
2001 GEPS submitted the Release Notification Form (RNF) to the DEP regarding the vault
findings. The RTN 1-14205 was assigned to the release associated with the vaults by DEP in its
Notice of Responsibility letter dated December 13, 2001. The vaults are not associated with the
original release notification (RTN 1-1083) provided to the DEP in relation to a former kerosene
release. There are no other RTNs associated with the EPRI site.
This RAM Plan includes the required elements set forth in 310 CMR 40.0444. This RAM Plan is
being submitted prior to Tier Classification of the site. The appropriate fee established in 310
CMR 4.00 has been sent to the DEP Lock Box concurrently with this RAM Plan. GEPS will not
implement this RAM Plan until the DEP has issued a written approval of the RAM Plan, or the
DEP does not issue written approval or denial of the RAM Plan within 21 days of its receipt, in
which approval shall be presumed.
GEPS-EPRI 1 URS 91-28171712.00/L6051R-rev.doc April 11,2002
2.0 PERSON ASSUMING RESPONSIBILITY FOR RAM
The person assuming responsibility for the RAM on behalf of GEPS is:
Mr. Edward F. Jamison, P.G. GE Power Systems One River Road Building 43, Room 237 Schenectady, NY 12345 (518)385-7979 EHS Project Manager - Remediation
Mr. Jamison is a project manager for investigative and remedial projects at GEPS sites in the
United States and abroad.
GEPS-EPRI 2 URS 91-28171712.00/L6051R-rev.doc April 11,2002
3.0 CURRENT SITE CONDITIONS
This section describes the current site conditions including the location, site features, nearby
natural resource areas, and geology and hydrogeology.
Site Location and Features
The EPRI property is at 115 East New Lenox Road in Berkshire County, in Lenox,
Massachusetts. A small area at the northern end of the property lies within the corporate
boundary of Pittsfield, Massachusetts. The property comprises about 33 acres and is
approximately seven miles north of the Massachusetts Turnpike. The Universal Transverse
Mercator coordinates of the EPRI site are 4,695,576.7 meters north and 64,514.6 meters east.
The latitude and longitude of the EPRI site are N 42° 24' 3.6" and W 73° 14' 3.4". The location
of the EPRI property is illustrated in Figure 1.
EPRI HVTRC conducts research on high voltage electrical transmission equipment at the site.
In 1958, GEPS acquired the property and built the HVTRC. In 1985, GEPS gifted the property
to EPRI. GEPS continued to operate the facility for EPRI, until late 1994. The site was operated
by J.A. Jones Power Delivery Inc., of Charlotte, North Carolina, from January 1995 to December
1998, when EPRI assumed operational responsibilities. Currently, the HVTRC tests insulator
performance, flashover prevention, corona phenomena, and electrical and magnetic fields.
Historically, tests on transformers were conducted in the vaults.
Figure 2 is a generalized site map of the EPRI property east of the Housatonic River. As shown
in Figure 2, EPRI's property includes six buildings: the headquarters building, the UHV Building
(also known as the salt fog contamination chamber), the EHV Building (also known as the aging
chamber), a garage, a storage building, and the EPRI office building. As shown in Figures 2 and
3, the vaults are west of the EHV Building and adjacent to an ox-bow of the Housatonic River.
The property is listed as Parcel No. 1 in the Lenox Tax Assessor's Map 34. The property is
zoned residential 20-30-40. Properties adjacent to the site are zoned agricultural, residential, or
GEPS-EPRI 3 URS 91-28171712.00/L6051R-rev.doc April 11,2002
State Wildlife Management area. Potable water is supplied to the EPRI site from the City of
Pittsfield. Domestic sewage is collected in a septic tank that drains to an onsite leach field.
Access to EPRI's property is restricted by a chain-link fence topped with barbed wire. The
entrance to the site is an access road on East New Lenox Road. Access to the vault area is via an
existing road on EPRI's property near the northwest fence line. Therefore, the potential for
unauthorized access to the site is low. Soil categories S-2 and S-3 are appropriate for the site.
Topography
The topography of the site east of the Housatonic River slopes gently westward, from elevations
of approximately 985 to 950 feet above the National Geodetic Vertical Datum (NGVD). The
highest elevation near the site is the summit of Sykes Mountain, approximately one mile east-
northeast of the site. The elevation of Sykes Mountain is approximately 1,700 feet NGVD. The
vault area is at an elevation of approximately 953 feet msl and is within a relatively level area
adjacent to the ox-bow of the Housatonic River.
Geology and Hydrogeology
The overburden deposits at the EPRI site are comprised of glacio-fluvial sediments of the
Housatonic River valley, consisting of poorly sorted, fine- to coarse-grained silts and sands, with
a trace of gravel.
According to the United States Geological Survey's Bedrock Geological Map of Massachusetts
(1983), the bedrock underlying the site is the Dalton Formation, a Cambrian muscovite
microcline quartzite and feldspathic quartzite, and the overlying Stockbridge Formation, a
quartzose calcite and dolomite marble (Zen, 1983). The steep topography east of the site marks
where large-scale Taconic-aged faulting thrust the Proterozoic Tyringham Gneiss and the
Cambrian Cheshire Quartzite over the younger Dalton Formation that underlies the site (Zen,
1983). The depth to bedrock beneath the site is uncertain. Bedrock has not been encountered in
drilling conducted to date at the site.
GEPS-EPRI 4 URS 91-28171712.007L6051R-rev.doc April 11,2002
At present, there are 12 groundwater monitoring wells at the EPRI property (associated primarily
with RTN 1-1083). The locations of the wells are shown on Figure 4, which is a potentiometric
contour map for overburden groundwater at EPRI's property on January 17, 2001. As shown,
the nearest groundwater monitoring wells to the vault area are wells MW-8 and MW-4.
Groundwater beneath EPRI's property, east of the Housatonic River flows toward the southwest.
The groundwater under the EPRI site is classified as category GW-2 and GW-3 within the
Massachusetts Contingency Plan (MCP) regulations regarding risk characterization. Category
GW-2 groundwater represents a potential source of vapors of oil or hazardous material to indoor
air. Category GW-3 groundwater represents a potential source of discharge to surface water.
Natural Resource Areas
As shown in Figures 1 and 2, the Housatonic River flows along the western border of the EPRI
property. As shown on Figure 3, the vault area is within a Bordering Vegetative Wetland
(BVW). Much of the property and the vault area are within the 100-year floodplain of the
Housatonic River. Four oxbows of the river are within 500 feet of the site. The river is not
considered a Class A surface water body. An unnamed stream flows westward from Sykes
Mountain and passes approximately 500 feet from the site.
The DEP Bureau of Waste Site Cleanup Geographic Information Systems Site Scoring Map
(GIS Map) of the EPRI property is included as Figure 5. As shown on Figure 5, there are no
approved Zone II Interim Wellhead Protection Areas or public surface water supply areas within
one-half mile of the site. There are two protected open space areas within one-half mile of the
site. These areas appear to be associated with the Housatonic River Valley State Wildlife
Management Area shown on Figure 1. The first area is approximately 0.2 miles north of the site.
The second area appears to border the southwestern portion of the site. The southern part of
EPRI's property includes fresh water wetlands, as well as, National Heritage and Endangered
Species Program (NHESP) Wetlands Habitat. Finally, the adjacent Housatonic River is a fish
habitat area.
GEPS-EPRI 5 URS 91-28171712.00/L6051R-rev.doc April 11,2002
4.0 DESCRIPTION OF RELEASE
Thirteen unused concrete vaults are the subject of this RAM Plan. The location of the vaults is
shown in Figure 3. The series of vaults are located along an approximate north-to-south trend
adjacent to an oxbow of the Housatonic River in the northwest area of the EPRI property. Vault
1 (V-l) (located at the south end) is a 6 feet by 12 feet by 7 feet deep rectangular shaped concrete
vault with a solid bottom. The remaining vaults (V-2 through V-l3) are 3 feet diameter by 6 feet
deep cylindrically-shaped concrete vaults. The nature of the construction of the 12 cylindrically-
shaped vaults is not fully understood, but investigations performed to date suggests that the bases
of some of the cylindrically-shaped vaults is not solid concrete, but rather is gravel. All 13
vaults have removable metal grate covers.
On November 29, 2000, EPRI's consultant, Roux Associates (Roux), evaluated the
environmental condition of the vault contents. Roux sampled solid media (e.g., soil) present in
the 13 vaults and collected water samples from four of the vaults. A total of 14 solid samples
and five water samples were analyzed for polychlorinated biphenyl (PCB) via EPA Method 8082
and extractable petroleum hydrocarbon (EPH) compounds via MADEP Method 98-1. On
January 28, 2001, GEPS received a copy of a letter report prepared by Roux from EPRI's legal
counsel summarizing the results of sampling activities. The analytical data for the soil samples
are summarized in Tables 1 and 2. The soil sampling results indicated the presence of EPH
compounds in some soil samples at relatively low concentrations, with detections above
applicable Massachusetts Contingency Plan (MCP) Reportable Concentrations in only a couple
instances (Table 1). The soil sampling results showed the presence of PCBs in some of the
vaults at concentrations above applicable MCP Reportable Concentrations RCS-2 (Table 2). The
analytical results for the water samples are summarized in Table 3 and 4. These results
document the absence of PCBs in water samples and show the presence of EPH compounds in
only two samples below MCP Reportable Concentrations.
On February 22, 2001, on GEPS's behalf, URS conducted an inspection of the vaults to
investigate whether the vaults appeared to have solid (e.g., concrete, etc.,) bases. The inspection
suggested that the 12 cylindrical vaults have solid cross members across a portion of their bases;
GEPS-EPRI 6 URS 91-28171712.00/L6051R-rev.doc April 11,2002
however, other areas within the vaults did not appear to be solid. The base of the one rectangular
vault appeared to be concrete.
On May 5, 2001, GEPS submitted a Release Notification Form (RNF) to the DEP regarding the
vault findings reported by Roux. The DEP assigned RTN 1-14205 to the vault area in its Notice
of Responsibility letter to GEPS, dated December 13, 2001.
Following review and approval by EPRI, GEPS finalized a vault investigation work plan, dated
May 11, 2001. The objective of the work plan was to gather additional data to further evaluate
subsurface conditions near the vaults in order to develop a plan to close the vaults. The first task
of the work plan was to conduct a wetland survey to evaluate if the vaults were located within a
wetland or wetland buffer zone. On June 11, 2001, Beaver Brook Environmental Consultants,
LLC conducted the wetland survey, which confirmed that the vaults are within a bordering
vegetative wetland (BVW). The delineation of the BVW is shown on Figure 3.
In order to proceed with the vault investigation on behalf of GEPS, URS filed a Notice of Intent
(NOI) application package with the Lenox Conservation Commission (LCC) on October 18,
2001. On November 1, 2001, the LCC approved the NOI application at a public meeting, and on
November 26, 2001 the LCC issued permit number 198-186 (provided by DEP) and an Order of
Conditions to GEPS. A copy of the permit and Order of Conditions is provided in Appendix B.
December 2001 Investigation
On December 7, 2001, immediately following receipt of the permit and Order of Conditions,
URS conducted an investigation to evaluate subsurface conditions near the vaults. Seven soil
borings (SB-113 through SB-119) were advanced to depths of 8 to 12 feet below ground surface
(bgs) using a Geoprobe. The soil boring locations are shown on Figure 6. The boring logs are
provided in Appendix C. A 4- to 5-foot thick layer of gray silty sand, which overlies a one-foot
thick gravel layer, was encountered coincident with the total depth of the vaults at the soil
borings advanced between the vaults (SB-113 through SB-116). A fine to coarse sand was
GEPS-EPRI 7 URS 91-28171712.00/L6051R-rev.doc April 11,2002
generally encountered beneath the gravel. The gravel layer was thin or absent at soil borings SB
117 through SB-119, which were advanced approximately one-foot on either side of the vaults.
URS collected eight soil samples for laboratory analysis from the seven soil borings advanced
adjacent to the vaults. The soil samples were analyzed for PCBs (EPA Method 8082) and EPH
compounds (MADEP Method 98-1). A grain size analysis was also conducted on the material
collected from 0 to 4 feet bgs from boring SB-117 and it was determined to be sandy silt with
trace clay. The analytical results from these soil borings are presented in Tables 1 and 2. The
analytical data indicates that EPH compounds were not detected above MCP Method 1 S-2 Soil
and GW-2/GW-3 Standards in any of the seven soil samples. PCBs were encountered above the
Method 1 risk standards at SB-114 between Vaults V-3 and V-4. PCBs were not detected above
the Method 1 risk standards at the other five borings.
As part of the December 7, 2001 field investigation, URS conducted additional probing to assess
whether the vaults have solid or soft bases. The solid bottom at vault V-l was measured at 6.8
feet bgs. However, observations suggested that the cylindrically-shaped vaults do not have solid
bottoms. Based on the data from these soil samples, GEPS has elected to advance additional soil
borings to further characterize the condition of soil surrounding the vaults. This information will
be used to determine the appropriate degree and extent of the corrective action efforts during
implementation of the RAM Plan.
March 2002 Investigation
The scope of the additional characterization work included the advancement of 23 soil borings to
a minimum depth of 14 feet bgs between and within the Vaults V-2 through V-l3 to complete
the characterization of the materials in the vault area. The objective of the borings was to
delineate the extent of impacted materials in the vault area and develop sufficient data about
subsurface conditions to be able to evaluate potential risks.
On March 27 and 28, 2002, the 23 soil borings were advanced using a Geoprobe. The soil
boring locations are shown on Figure 6. Soil boring SB-121 was advanced at former boring
GEPS-EPRI 8 URS 91-28171712.007L6051R-rev.doc April 11, 2002
location SB-114 to confirm the December 2001 analytical results and delineate the depth of
impacted materials. Soil borings SB-120 through SB-128 were advanced between the vaults.
Soil borings VSB-2 through VSB-13 were advanced within vaults V-2 through V-13. Because
Vault V-l has a concrete bottom at approximately 6.8 feet bgs, a soil boring was not advanced
within Vault V-l. The boring logs are provided in Appendix C
Soil samples were collected from beneath the horizon of the gravel layer that was previously
encountered within and between certain vaults. Based on observations made by URS in
February 2001 and the soil borings advanced in the vault area in December 2001, the gravel
layer within and between the vaults is at a depth of approximately 5.5 to 7 feet bgs. The soil
samples from directly beneath the gravel layer were collected between 7 to 10 feet bgs at 22 of
the 23 soil borings. The soil sample from soil boring VSB-2 was collected from 10 to 12 feet
bgs, because the gravel layer at Vault V-2 extended to 10 feet bgs. Two additional soil samples
each boring were collected (e.g., 10 to 12 feet bgs, and 12 to 14 feet bgs) and archived for
possible analysis.
The soil samples collected from beneath the gravel layer from each boring were analyzed for
PCBs (Method 8082). Selected soil samples were also analyzed for EPH compounds (MADEP
98-1). The analytical results from these soil borings are presented in Tables 1 and 2. PCBs were
not detected above 2 mg/kg in the 24 soil samples collected in March 2002. EPH compounds
were not detected above laboratory detection limits in the seven soil samples collected in March
2002. Based on the results of these soil samples, no additional soil samples were analyzed.
GEPS-EPRI 9 URS 91-28171712.007L6051R-rev.doc April 11, 2002
5.0 SURROUNDING RECEPTORS
Potential human receptors at the EPRI site who may come into contact with the potentially-
impacted soils within and near the vaults include the adult employees and trespassers. However,
the vaults are subsurface structures with heavy covers, so the potential for access to the contents
and surrounding soils is extremely limited. Potential offsite human receptors, such as the
residents of abutting properties and workers, are even more unlikely to ingest, inhale, or contact
the vaults contents and potentially impacted subsurface soils.
Receptors that may be affected by potentially contaminated water include humans and
environmental receptors such as benthic and aquatic organisms in the Housatonic River. There
are no public or private water supply wells near the EPRI site.
GEPS-EPRJ 10 URS 91-28171712.00/L6051R-rev.doc April 11,2002
6.0 RELEASE ABATEMENT MEASURE
This section provides the objective, strategy, and scope of work for this RAM Plan.
6.1 OBJECTIVES
The objective of the Vault RAM is to:
Remove, if appropriate based on risk, and properly dispose of the contents and contaminated soil
near the vaults to mitigate any significant risk posed to human health or the environment.
6.2 STRATEGY
The strategy for addressing the vaults relies on using analytical data from the characterization
work to guide the degree and extent of any removal/excavation during implementation of the
RAM Plan. The characterization work, which was conducted prior to implementing the RAM,
includes the advancement of soil borings and collection of soil samples for laboratory analysis.
The analytical results from the various phases of investigation provide a detailed environmental
quality database documenting the degree and extent of compounds of concern in the subsurface
surrounding the vaults. These data will be used to develop the nature and scope for any
excavation/removal activities to be performed to address any excess risk posed by the
compounds of concern. Specifically, these data will be used to determine the corrective action
approach and the vertical/lateral extent of any soil excavation. The degree of any excavation will
extend to sufficient degree to ensure that any impact surpassing the cleanup criteria will be
removed to mitigate any excess risk. This approach, which essentially involved the collection of
characterization samples, which are equivalent to post-excavation samples, prior to the actual
soil removal effort, has been developed to facilitate the following:
• Lessens the overall amount of physical disturbance in the vault area, which is in a wetland
area.
GEPS-EPRJ 11 URS 91-28171712.007L6051R-rev.doc April 11,2002
• Eliminates the need to keep the excavation area open pending receipt of analytical results
since post-excavation samples will not be collected. Thus, we will be able to backfill any
excavations after we reach the target excavation depths (which will be defined based on pre
excavation sampling results).
• Diminishes the risk of harm to onsite workers or potential trespassers from falling into an
open excavation.
• Diminishes the risk of harm to the local animal population from falling into an open
excavation.
• Lessens concern over potential flooding or collapse and undermining of the excavation area
in the wetland.
• Avoids potential problems associated with collecting representative post-excavation samples
recognizing that any excavations will extend below the water table.
• Diminishes the potential need to dewater the area during implementation of the RAM, which
could limit access to the available work area with the placement of temporary water holding
tanks nearby. This also reduces the potential of disturbing the wetland by trucks needed to
unload/load the holding tanks and other associated equipment (hoses).
• Less risk of transporting contamination downward from the impacted areas by dewatering.
As described in Section 4.0, prior to the implementation of the Vault RAM, an additional
investigation was conducted to complete the characterization of release from the vaults. The
additional investigation work was conducted on March 27 and 28, 2002. The results of this
additional investigation will be used, in conjunction with the currently available analytical data,
to define the extent of removal actions and serve to delineate the excavation during the Vault
RAM.
6.3 SCOPE OF WORK
The RAM will comprise these five tasks that URS and its subcontractors will implement on
GEPS' behalf:
Task 1 - Notifications;
GEPS-EPRI 12 URS 91-28171712.00/L6051R-rev.doc April 11,2002
Task 2 - Remove and Dispose the Contents of Each Vault;
Task 3 - Excavate and Dispose Selected Vaults and Surrounding Soil;
Task 4 - Restoration of the Area; and
Task 5 — Submit Response Action Outcome Statement.
6.3.1 Task 1 - Notifications
URS will provide notification that the Vault RAM will be implemented to the Chief Municipal
Officer, the Board of Health, and the Fire Department of the Town of Lenox. The written
notification will be submitted to these agencies immediately after the RAM Plan is filed with the
DEP, and the work will not commence until seven days after the notification is received by the
Town agencies. The Lenox Conservation Commission (LCC) will also be notified of the Vault
RAM implementation schedule. Note that the Order of Conditions, which was previously issued
by the LCC, covers the activities associated with this RAM.
6.3.2 Task 2 - Remove and Dispose Contents of Each Vault
Depending upon evaluation of the results of the findings of the investigations near the vaults, it
may be necessary to remove impacted materials from the vault area in accordance with Permit
198-186 and the Order of Conditions, issued by the LCC on November 26, 2001. Prior to the
start of field activities, the condition of the silt fence, which was installed in December 2001,
will be assessed. If the condition of the silt fence has deteriorated, it will be repaired or replaced.
Based on the investigation findings, the materials from within the vaults will be removed. A
vacuum truck will be used to remove the material from within each vault to the depth determined
from the soil boring/sampling program. The interior of each vault will be inspected. Based on
the inspections, GEPS may elect to collect samples, if appropriate, to evaluate whether treatment,
isolation, or removal of any vault is warranted. If the removal depth extends beyond the
accessibility of the vacuum truck, the vault and associated materials will be excavated (See
Task 3).
GEPS-EPRI 13 URS 91-28171712.00/L6051R-rev.doc April 11,2002
6.3.3 Task 3 - Excavate and Dispose Selected Vaults and Surrounding Soil
Depending upon evaluation of the findings of the results of the investigations near the vaults, it
may be necessary to excavate and remove vaults and surrounding soils to sufficiently remove
soil impacted with compounds at levels of concern. The analytical results for the soil samples
collected during the additional characterization work and the previously collected data will be
used to establish the degree and extent of any vault or soil removal during the RAM. Wastes
generated during any vault or soil removal efforts will be placed into rolloff container(s) or
vacuum truck that will be staged onsite pending waste-characterization analysis and off-site
disposal at a properly licensed facility.
The anticipated criteria that will be used to define removal areas and depths are:
• If soil data from a boring between vaults are averaged with other data from soil that will
remain in place and the average residual concentration is found to exceed risk-based MCP
criteria, then the vaults on either side (except for Vault V-l) of the soil boring and the
impacted soil will be removed.
• If soil data from a boring from between vaults are averaged with other data from soil that will
remain in place and the average residual concentration is found to be below risk-based MCP
criteria, then this area will be left in place.
• If soil data collected from beneath a vault area averaged with other data from soil that will
remain in place and the average residual concentration is found to exceed risk-based MCP
criteria, then the impacted soils (and likely the vault) will be removed.
• If soil data collected from beneath a vault are averaged with other data from soil that will
remain in place and the average residual concentration is found to be below risk-based MCP
criteria, then the vault will not be removed. However, the contents of the vaults will be
removed for off-site disposal.
Pending evaluation of the soil data, GEPS may elect to modify these criteria so long as the
modifications are consistent with the goals of the RAM Plan. Either Method 1 or a Method 3
GEPS-EPRI 14 URS 91-28171712.00/L6051R-rev.doc April 11,2002
risk criteria characterization will be performed to ensure the extent of remediation is adequate to
protect human health and the environment, per MCP regulations.
6.3.4 Task 4 - Restoration of the Area
Following completion of the corrective action effort, URS' subcontractor will backfill the
excavations and restore the area. Clean fill with similar physical parameters (e.g., silty sand) as
the native materials at the site will be used to fill the vaults and replace soil that is removed from
the work area to approximate original grades. The area will then be seeded with the wetland
seed mixture and mulched as provided in the NOI.
6.3.5 Task 5 -Submit Response Action Outcome Statement
When the objectives of the RAM Plan have been met and the remedial actions are completed,
GEPS will submit a Response Action Outcome Statement (RAO) to the DEP. The RAO will
include the elements set forth in 310 CMR 40.1000. The report will be submitted to the DEP
within 60 days of the completion of the RAM or within 120 days of obtaining oral, written, or
presumed approval of the RAM Plan by DEP, whichever is sooner.
GEPS-EPRI 15 URS 91-28171712.00/L6051R-rev.doc April 11,2002
7.0 MANAGEMENT OF REMEDIATION WASTE
The remediation waste will be managed in accordance with the provisions set forth in 310 CMR
40.0030. Any excavated soil, vault materials, and solid vault contents will be staged in a rolloff
container pending proper offsite disposal. Fluids that may be removed during the RAM will be
either disposed of via the vacuum truck or temporarily stored in drums or a holding tank pending
proper off-site disposal.
GEPS-EPRI 16 URS 91-28l7I712.00/L6051R-rev.doc April 11,2002
8.0 ENVIRONMENTAL MONITORING PLAN
Air monitoring will be performed during the implementation of the Vault RAM according to
URS's site-specific Health and Safety Plan (HSP). Action levels and contingencies for air
monitoring results in the work area that are above background levels will be established in the
HSP. In addition, the remediation contractor selected for the project will be required to develop
and implement their own Health and Safety Plan, which must be at least as stringent as URS's
HSP. Access to the work area will be strictly limited to necessary personnel, thus limiting
potential exposure. If dusty conditions occur, dust control measures, such as water sprays, will
be implemented.
GEPS-EPRI 17 URS 91-28171712.007L6051R-rev.doc April 11,2002
9.0 SCHEDULE
GEPS will not initiate the Vault RAM until the DEP has issued a written approval of the RAM
Plan, or after 21 days following the DEP receipt of the RAM Plan, in which case approval shall
be presumed. Therefore, GEPS anticipates that it will begin implementing the Vault RAM on or
about 21 days after it is submitted to the DEP.
GEPS plans the following schedule for implementation of this RAM.
Task Weeks after RAM Plan Submittal
Immediately Task 1 - Notifications
Task 2 - Remove and Dispose the Contents of each 3 to 4 Vault Task 3 - Excavate and Dispose Selected Vaults and 3 to 4 Surrounding Soil
3 to 4 Task 4- Restore the Area
4 (May 11,2002) Task 5 - Submit Response Action Outcome Statement
GEPS-EPRI 18 URS 91-28171712.00/L6051R-rev.doc April 11,2002
10.0 SEAL AND SIGNATURE OF LSP
The seal and signature of the LSP is provided in Section J of the original Release and Utility-
Related Statement Measure Transmittal Form (BWSC-106), which has been submitted to DEP
with this report. A copy of Form BWSC-106 is included in Appendix A.
GEPS-EPRI 19 URS 91-28171712.00/L6051 R-rev.doc April 11, 2002
0 i | | o o o•4-1 o oo oo oo oo 00 00 00 00 oo oo 00 oo 00 OO oOs in in in m m in o m in m in 0CN CN î . C/3 tN
,> CM o o O O o o O O o O O o O O (V O SO V 7 V V V V 9 V V V V V V V V V V
O _̂ CQ ^o r~i o o r-- r- r-- r- r- r- r- oo i/i ^ ^ m in ^ 1/4 m in 00 OS în in in m m in vi in ^ r— m m m ^r— ^&>
CN •—' I—1 I—1 (~> 0 f> c-> SO V V V V V V V V £̂ ) V V V V ^ V V V VV V V V^
CQ •o oo Ô o•w 0O 0o M p p ro p fi m
in in P r- P r- r- r- P P P P^ li-i CN *—' Ĥ '—10 0o 0000000000000 00 V V V V V V V V V V V V V V V V V V V V E ^ i—< a. o"5 PC w
_l 1**H Os 00 O (N VO vo vo VO VO VO VO VO VO VO vo vo VO vo VO VO VO rH d o m(N O o O O O o O O O O O O O O O O PQ § 7 V 7 V V V V V V V V v V V V V V 9 V 00 00
S •*-• CQ
CU .̂ vo •o 00 0 VO VO VO VO VO VO vo VO VO VO VO VO vo VO VO VO VO o1-H v. j5 (N (N Q Q Q Q1 CN O 00 000 000O 0 ffl V v V V v V V V V V V V 4J CO QV V 7 V V£! (N5 V V O "p.
p- c/1 E tu E p CQ TT vo o vo VO oo VO vo VO VO VO 00 «0 5 § g &3 00 vo o O O ^o O O O O o ** o *-' O "1 V V V V V V V o z
r- O t~. o O 0§ O 0 »—« O o o o o o *"̂ *—H Oo in o 00 o o • ' c fN (N t—< 1—< fN
o o O 00o Or0o o o o 0—, r-l o in t—1 o 8 00in 8—i fN fN fN (N (N
B B u
u B
CO 1) u B
1 2-M
etb.
ylna
phth
alen
e
8 aJU u u u
& o"
Phen
anth
rene
**"!.
[Flu
oran
then
e | F
luor
ene
u1 cp, JJ JU
|Chr
ysen
e CO w o
OH •Ou CQ CQ a,
o 1
> vo ^
I J ^
M •S n U
'o
PH J» s
Com
poun
d
O O
5; S f-H
O
•M O en «s I
fM
U n fN
|C19
-C36
Ahp
hatic
s |C
ll-C
22A
rom
atic
s
U
8
lAce
naph
thyl
ene
1 s.
VO
^
§ m fN
0 o m (N
| Ant
hrac
ene
1
S
fOi—(i P3 C/3
01 .s o
1 oo
»S o t-C!ri
O •3T
C/3>
•*•*£ o T-H1 00
r)
oo JS
f>
o\ cX /->
7 •o oV
^o oV
SO 0 V
SO
? SO oV
SO 0 V
VO
?
so
?
SO
?
SO o V
SO 0 V
SO 0V
•o
? SO oV
VO oV
so
?
SO
? CJ
•3>% .0
11 0 !£>" >s tN
43 ~
7, CO
so fN
« co
Ol £ oo1t
n o r~rj ft
m
^7 fN mV
—i V
00
? 00 oV
oo O V
oo O V
oo
? oo o V
OO o V
oo oV
oo
? oo
? 00 O V
oo oV
00
? oo
? 00
? oo oV
OO oV
T3 flj
ft aC a
W*J
a 0
Q « o o
OH
Q o
CO CN O^ oo oo oo oo oo 00o m m in in in Os 5J q 0 q O t q o I/I "1 > ^ CD if D ^ CD CD o CD SO r-< V V V V 9 V ^
O OO oo 00 00 oo oo
ER
RE
SEA
RC
S o in in m in in 00 S 0 o q o , O o oo 00 M
ASS
AC
HU
S t> **• Os Os o o o o 0 CD SO £^ V V V V V V~
0 CN CN CN (N cs cs
OJ r- q q5^ o O O O 0 0f- .2 •CD O CD O CD CD f00 V V V V V V ^
« 1 OJ ,C
e. o S ^ CS CS CN cs cs CS3 o m in in m in q q ° g§ Q 15s q 0 o q o o t/5 C/J I/I C^ Q o o Q CD CD fN cs < >
\^ r"( v vV V V V V W^ 3 i O G.
o C£ ^ r- r-- >, a SO so so SO so q q^O «2 5s O o o O , o o ^ "° in c. o o o o CD CD fs o B^ ^ £Z «
t/3 t-^ V V V V V V OJ^ « fr o I-5 •*•* 0 8 Q
Cfl in in in in in m SO SO SO so SO s^. « O o o o CD so
Os O o O o o O SP U a£5 < > 00 00 • a - 2 ^ 0 0 0 o CD CD SC tj CQ ^ |5 ~J ?
^
^ £ £V V V V V o o ^ b "3 o"
'RO
M V
AU
L T
AR
EA
SO
IL
TA
BL
E 2
OF
PO
LY
CH
LO
RIN
AT
ED
5 °- o
oo
• s 3 §ro ro ro ro o C/5
x "& « « cs fN cs CN CS o tx
OH Eso 1 SO so SO O O'00 O O O O O
OO tn V V V V V II J ~ B;
1 - 3 8 0 CO fi (N (N CS fN m mro ro ro ro t— in •• •̂ s E > MT-J P3
OH
f E -= § £T3 — 00 I- "
it M- 8 "8 g ^ £ SO SO s SO SO „ t: t- ro Oin in o o O o 1 o o a o •«= — u
s in
s SO r o o O o o o § g- " V KV V V V V V o - J « u b S3 > M >
0 K U o ^ 3 S3 u ̂ 0
sc o o V
o o V
O V
o o V
' o o V
SO o o V ^
TT y,i!o
03^J o_
=" ~ <
& §" m5 M E? oo co >
Z —• cs ro Tt
oo i o
K =3 . • • ' 1 1 1 • CN
' 1 i 'o oo < « C
(. «j oo
'< a5 B
P
M
)H
O 1 . . • 1 . ' • fN
'o CO VI
X
cs
242/
1016
> d•o a cs (N oo o 2 Po (NCS ro fN fN CS fN oa. PQ OH J.
t C ) 0 O OH b o o O W r-o o o
WOU ~ rs g 0 oo u U U o o o 2 o o o o < <
M o cs cs (N cs (N en S o S O es 00oa o o O o Oi d doo en V V V V V
rs o 51 o o 1 O Io 05 o o o o o°p ^ CO r- en V V V V V "
on oTf VO Os OS o
1 o p ' o sIen en d d d d00i d dCO en V V V V V +j en rs cs cs cs cs o rr rf en 3 .2 o a. d d d d d C- t~* r~~ flj
00
co en V V V V V V VA
Os w en en en en 2* U 1-H V §-« a: 10 .. « 3rvl 1—1 is iO so o en CJ D 5 g ^ 00 09 »s o 0 o O o O o £ a, aJ CO 00 > CO V V V V V V V o
Z —• cs' en
en CO
O ' ' i 1 cs >̂ 2 1 ' • '
1 CO ? o
• •
o o o o o o oON ro ro 0 0 ' s 0 oS3 O oi0co
2 o o o o o O o 00 tN
V V V V V VV D ~
•̂ 00 oo oo oo oo oo oo oo ts ts ts (S ts ts o 'CO oGO • 0 0 o o o o
3/27
/02
3/27
/02
o o o o o o o V V V V V V V1
00
~z ffl
3/27
/02
o o 0 o o o o o o 0 oV V V V V 1oGO V
00
3/28
/02
3/28
/02 ON ON ON ON NO
ca ON s o ' o O S OI 00oCO o o o o O 0 3
V V V V V V O
<0
03
0
<0
03
3V) ca
ro rH ro O O O O• o O O O V V V V
00 00
o o o o
NOIt
oCO 1
00 3 O CX
1 CO
3/28
/02 1
o
o o O O ' roi o o O O o o O o
V o oV V V ^ OH
H •4-1 rl o a P oNO -
••
00 CN CaL O
on _1
CN oo en
VS
B-1
3
0 1
00 3/2
7/02
'
e« Tt oCO 00 00 oo o o •o
u Ot
Oo o - o ou o o o o O V V V V V o 0 oj p
H »J O- "o CN C? (Nw 1 O
s 00 « V V V V V V V
Y O
F PO
LY
CH
LO
RIN
AT
ED
FRO
M V
AU
L T
AR
EA
SO
IL
.EC
TR
IC P
OW
ER
RE
SE
AR
C
oi ta-J
LE
NO
X, M
ASS
AC
HU
S
5
"Q _ o
'S «N r
TABLE 3 SUMMARY OF EXTRACTABLE PETROLEUM HYDROCARBON RESULTS
FROM VAULT WATER SAMPLES
ELECTRIC POWER RESEARCH INSTITUTE LENOX, MASSACHUSETTS
MCP Groundwater Standard VI V2 Compound GW-1 11/29/00 11/29/00
C9-C18 Ahphatics 4000
TABLE 4 SUMMARY OF POLYCHLORINATED BIPHENYL RESULTS
FROM VAULT WATER SAMPLES
ELECTRIC POWER RESEARCH INSTITUTE LENOX, MASSACHUSETTS
Compound
Aroclor 1016 Aroclor 1221 Aroclor 1232 Aroclor 1242 Aroclor 1248 Aroclor 1254 Aroclor 1260 Total PCBs
MCP GW-1 Groundwater Standard
-------
0.5
VI 11/29/00
I ^
MOUNTAIN
r-olor J
0 250 500 750 1000
GRAPHIC SCALE (METERS)
QUADRANGLE LOCATION
FIGURE
1 SITE LOCATION MAP
NOTE CONTOUR INTERVAL = 6 METERS
EPRI SITE LENOX, MASSACHUSETTS
REFERENCE PITTSRELD EAST QUADRANGLE A998
THE CIRCLES DEPICTED ARE THE 1/2 MILE AND 1 MILE RADII FROM THE UHV BUILDING URS 646 PLANK ROAD SUITE 202 CLIFTON PARK, NEW YORK 12065
POWER PDLE
WETLAND DELINEATION LINE VAULT AREA
GENERAL ELECTRIC COMPANY Original includes color coding LENOX, MASSACHUSETTES
SOURCE! SITE PLAN PREPARED BY HILL ENGINEERS, ARCHITECTS, AND 46 I ANI ROAD SUML PLANNERS OF DALTON, MA DATED 06/15/01. I [| ION PARK NEW 0t
MA DEP - Bureau of Waste Site Cleanup SITE NAME: Site Scoring Map: 500 feet & 0.5 Mile Radii :PRI422404n 731403ewi Ib* rrtorTTUODfi thovn on tfui map [̂«L«^ol
• tta DMI jvajlatoit 21 tfw etas*
Site Location V^55^ a*1' "*> _»
MASSACHUSETTS GIS SITE SCORING MAP
EPRI SITE LENOX, MASSACHUSETTS
646 PLANK ROAD SUITE 202 URS CLIFTON PARK. NEW YORK 12065 Ftoedc Hns>«o.USS»««Stroa1>ri
CM *~ UJ *
l| §1aa v-
co LU
cox o
I
o:
a: UJ
5 o
CO UJ
O o C/3 O
O m xO O z
o z trO CD
-co- O CO
LU O LU m
CO
APPENDIX A
RELEASE & UTILITY-RELATED ABATEMENT MEASURE (RAM & URAM)
TRANSMITTAL FORM (BWSC-106)
IT) (O
CN
LU
Q<O
_LUO
w Z < LU •
10 111 IO
CD
a: LU
5 o
Ioi LU_l <OLL
Om
O o> o
I 00 X
hoo z
o a:z
O z LU O LU
O CO
CO CO
Massachusetts Department of Environmental Protection BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking MEASURE (RAM & URAM) TRANSMITTAL FORM
! 1 - 14205 Pursuant to 310 CMR 40 0444 - 0446 and 310 CMR 40 0462 - 0465 (Subpart D)
A. SITE LOCATION:
Site Name Electric Power .Research institute
Street 115. .East _New_Lenox_Raad _ - Location Aid .Formerly 1CLQQ New Lenox Road
City/Town T.pnny _ ZIP Q124Q-22UL
[ | Check here if a Tier Classification Submittal has been provided to DEP for this Release Tracking Number
Related Release Tracking Numbers That This RAM or URAM
B. THIS FORM IS BEING USED TO: (check all that apply)
) Submit a RAM Plan (complete Sections A, B, C. D. E, F, J, K. L and M)
I—I Check here it this RAM Plan is an update or modification ot a previously approved written RAM Date Submitt" Plan
| | Submit a RAM Status Report (complete Sections A, B, C. E, J, K, L and M)
| | Submit a RAM Completion Statement (complete Sections A, B, C, D, E, G, J, K, L and M)
(G Confirm or Provide URAM Notification (complete Sections A, B, H, K, L and M)
f ] Submit a URAM Status Report (complete Sections A, B, C, E, J. K, L and M)
| | Submit a URAM Completion Statement (complete Sections A, B, C, D, E, I, J. K, L and M)
You must attach all supporting documentation required for each use of form indicated, including copies of any Legal Notices and Notices to Public Officials required by 310 CMR 40.1400.
C. SITE CONDITIONS:
Uj Check here rf the source of the Release or Threat of Release is known
If yes, check all sources that apply | | UST Q] Pipe/Hose/Lme | | AST | | Drums F] Transformer J Boat
| | Tanker Truck {^} Vehicle ^J Other Specrfy Subsurface vaults
Identify Media and Receptors Affected (check all that I I Air I I Groundwater |~~1 Surface Water I I Sediments Lfl Soil ! L3LJ or,^U,\ ' ' ' ' ' ' '
Q Wetlands Q Storm Dram Q ™^0 D Private Well Q Public Water Supply Q| Zone 2 QJ Residence
G icnoo j—| Unknown r—j other Specrfy
Identify Release and/or Threat of Release Conditions at Site (check all that apply)
| | 2 and 72 Hour Reporting Condition(s) Qj 120 Day Reporting Condition(s) [_ ] Other Condition(s)
Descnbe
RAMs may be conducted concurrently with an IRA only with written DEP approval URAMs may not be conducted if any 2 or 72 Hour conditions exist at the site
Identify Oils and Hazardous Matenals Released (check all that j^j Oils [_ 1 ^™°""(tle° Heavy Metals
[~ ] Others Specify ._ _
D. DESCRIPTION OF RESPONSE ACTIONS: (check all that apply) uepioymem 01 Aosoroant or ^omainmem
[ | Assessment and/or Monitoring Only M atonalc
^f\ Excavation of Contaminated Soils I Temporary Covers or Caps
(~~| Re-use, Recycling or Treatment j Bioremediation
i ) On Site i Off Site Est Vol _ cubic yards [ J Soil Vapor Extraction
Describe _ [_ ] Structure Venting System
f j %™£™ NArL Store t j On Site Off Site Est Vol cubic yards
SECTION D IS CONTINUED ON THE NEXT PAGE.
Revised 2/24/95 Supersedes Forms BWSC-007, 008, 009 and 010 (in part) Page 1 of 4 Do Not Alter This Form
Massachusetts Department of Environmental Protection BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking MEASURE (RAM& URAM) TRANSMITTAL FORM
| 1 14205 Pursuant to 310 CMR 40 0444 - 0446 and 310 CMR 40 0462 - 0465 (Subpart D)
D. DESCRIPTION OF RESPONSE ACTIONS (continued)
0] Landfill Cj Cover < j Disposal Est Vol _15 cubic yards G ijrounowaier ireatmeni
Massachusetts Department of Environmental Protection BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking MEASURE (RAM & URAM) TRANSMITTAL FORM Pursuant to 310 CMR 40 0444 - 0446 and 310 CMR 40 0462 - 0465 (Subpart D)
I. URAM COMPLETION STATEMENT:
| | Check here if this URAM was limited to the excavation and/or handling of not more than 100 cubic yards of soil contaminated by Oil or not more than 20 cubic yards of soil contaminated by either a Hazardous Material or a mixture of a Hazardous Matenal and Oil
If any Remediation Waste will be stored, treated, managed, recycled or reused at the site following submission of the URAM Completion Statement, you must submit either a Release Abatement Measure (RAM) Plan or a Phase IV Remedy Implementation Plan, along with the
appropriate transmittal form, as an attachment to the URAM Completion Statement
J. LSP OPINION:
I attest under the pains and penalties of perjury that I have personally examined and am familiar with this transmittal form, including any and all documents accompanying this submittal In my professional opinion and judgment based upon application of (i) the standard of care in 309 CMR 4 02(1), (u) the applicable provisions of 309 CMR 4 02(2) and (3) and (in) the provisions of 309 CMR 4 03(5) to the best of my knowledge, information and belief,
> if Section B of this form indicates that a Release Abatement Measure Plan is being submitted, the response action(s) that is (are) the subject of this submittal (i) has (have) been developed in accordance with the applicable provisions of M G L c 21E and 310 CMR 40 0000, (u) is (are) appropnate and reasonable to accomplish the purposes of such response action(s) as set forth in the applicable provisions of M G L c 21E and 310 CMR 40 0000 and (in) complies(y) with the identified provisions of all orders, permits and approvals Identified in this submittal,
> if Section B of this form indicates that a Release Abatement Measure Status Report or a Utility-Related Abatement Measure Status Report is being submitted, the response action(s) that is (are) the subject of this submittal (i) is (are) being implemented in accordance with the applicable provisions o f M G L c 21E and 310 CMR 40 0000, (u) is (are) appropriate and reasonable to accomplish the purposes of such response action(s) as se forth in the applicable provisions of M G L c 21E and 310 CMR 40 0000 and (in) complies(y) with the identified provisions of all orders, permits and approvals Identified in this submittal,
> if Section B of this form indicates that a Release Abatement Measure Completion Statement or a Utility-Related Abatement Measure Completion Statement is being submitted, the response action(s) that is (are) the subject of this submittal (i) has (have) been developed and implemented in accordance with the applicable provisions of M G L c 21E and 310 CMR 40 0000, (ii) is (are) appropnate and reasonable to accomplish the purposes of such response action(s) as set forth in the applicable provisions of M G L c 21E and 310 CMR 40 0000 and (HI) complies(y) with the identified provisions of all orders, permits and approvals identified in this submittal
I am aware that significant penalties may result, including, but not limited to possible fines and impnsonment, if I submit information which I know to be false, inaccurate or matenally incomplete
| | Check here if the Response Action(s) on which this opinion is based if any, are (were) subject to any orderfsV permit(s) and/or approval(s) issued by DEP or EPA If the box is checked, you MUST attach a statement identifying the applicabl i pro1 * '"
LSP Name Thomas P Wondard Stamp
Telephone ?n7-R7Q-76f l f i
FAX (optional) ?n7- f l7Q- '
Signature
Date A r. An LSP Opinion Is not required for a Utility-Related Abatement Measure Notification.
An LSP Opinion Is not required for a URAM Completion Statement If the URAM Is limited to the excavation and/or handling of not more than 100 cubic yards of soil contaminated by OH, or not more than 20 cubic yards of soil contaminated either by Hazardous Material or
a mixture of Hazardous Material and Oil.
K. PERSON UNDERTAKING RAM OR URAM:
Name of npnpral R1 ert-.ri r Pnwpr Systems
Name of F.dwarri .Tami Rnn Title RHH Remp.rii at".i nn
Street Onp Rivpr Road, Building 43, Rnnm 237
City/Town firhpnpcl-ady State MY ZIP Code 12345-0.QOO
Telephone ^1 B-^ f tg -7q7q Ext FAX
| | Check here if there has been a change in person undertaking the RAM or URAM
Revised 2/24/95 Supersedes Forms BWSC-007. 008, 009 and 010 (in part) Page 3 of 4 Do Not Alter This Form
Massachusetts Department of Environmental Protection BWSC-106 Bureau of Waste Site Cleanup
RELEASE & UTILITY-RELATED ABATEMENT Release Tracking
MEASURE (RAM & URAM) TRANSMITTAL FORM r- , 1 142^5Pursuant to 31OCMR 40 0444 -0446 and 31OCMR 40 0462- 0465 (Subpart D) LL "L _ |
L. RELATIONSHIP TO SITE OF PERSON UNDERTAKING RAM or URAM: (check one)
^/\ RPorPRP Specify t'j* Owner O Operator' > Generator i~} Transporter Other RP or PRP Former Owner
| ] Fiduciary Secured Lender or Municipality with Exempt Status (as defined by M G L c 21E s 2)
Q] Agency or Public Utility on a Right of Way (as defined by M G L c 21E s 5(j))
I I Any Other Person Undertaking RAM or URAM Specify
M. CERTIFICATION OF PERSON UNDERTAKING RAM OR URAM:
.Tarrn .qnn_ , attest under the pains and penalties of perjury (I) that I have personally examined and am familiar with the information contained in this submittal, including any and all documents accompanying this transmittal form, (ii) that, based on my inquiry of those individuals immediately responsible for obtaining the information, the material information contained in this submittal is, to the best of my knowledge and belief, true, accurate and complete, and (in) that I am fully authorized to make this attestation on behalf of the entity legally responsible for this submittal I/the person or entity on whose behalf this submittal is made am/is aware that there are significant penalties, including, but not limited to, possible fines and impnsonment, for willfully submitting false inaccurate, or Incomplete information
ignature) L/
For_fieneraJ_ Elecriric Power Sysf.pms (print name of person or entity recorded in Section K)
Enter address of person providing certification, if different from address recorded in Section
Street ___
City/Town __ State _ ZIP Code
Telephone _ Ext _ FAX (optional)
YOU MUST COMPLETE ALL RELEVANT SECTIONS OF THIS FORM OR DEP MAY RETURN THE DOCUMENT AS INCOMPLETE. IF YOU SUBMIT AN INCOMPLETE FORM, YOU MAY BE PENALIZED FOR MISSING
A REQUIRED DEADLINE.
Revised 2/24/95 Supersedes Forms BWSC-007, 008. 009 and 010 (in part) Page 4 of 4 Do Wo( Alter This Form
APPENDIX B
PERMIT AND WPA FORM 5 - ORDER OF CONDITIONS
2 » '7'
COMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF ENVIRONMENTAL AFFAIRS DEPARTMENT OF ENVIRONMENTAL PROTECTION WESTERN R E G I O N A L OFFICE
JANE SWIFT ' *' I BOB 1)1 HAM)
Governor " U \L 'KEN \ MSP
RE NOTIFICATION OF FILE NUMBER DATE November 19 2001
WETLANDS/ LENOX (city/town) The Department of Environmental Protection has received a Notice of Intent filed in accordance with the Wetlands Protection Act (M G L c.131, §40)'
APPLICANT URS CORPORATION_ OWNER; ELECTRIC POWER RESEARCH INSTITUTE INC
ADDRESS 646 PLANK ROAD. SUITE 202_ ADDRESS: 115 EAST NEW LENOX ROAD
CLIFTON PARK, NY 12065_ LENOX. MA 01 240
PROJECT LOCATION: 115 EAST NEW LENOX ROAD
IF CHECKED, THE FOLLOWING ITEM(S) APPLY TO THIS NOTICE OF INTENT:
A. X This project has been assigned the following file # 198-1886 :
Although a file # is being issued, please note the following: Materials and equipment shall be stored in a manner and
'tion, which will minimize the compaction of soils and the concentration of runoff. Refueling of vehicles shall be
in an area outside the "Buffer Zone". If a spill occurs, contaminated soils shall be removed according to guidelines
established by the DEP Division of Hazardous Waste. The proposed work sequence, schedule and timing should
be clearly understood by the Conservation Commission prior to permitting.
ISSUANCE OF A FILE NUMBER INDICATES ONLY COMPLETENESS OF SUBMITTAL, NOT APPROVAL OF APPLICATION
B. No File # will be assigned to this project until the following missing information is sent to this office, to meet the minimum submittal requirements in accordance with the Wetlands Protection Regulations at 310 CMR 10.00:
_copy(s) of a completed Notice of Intent (WPA Form 3 or WPA Form 4, whichever is applicable) and a copy of the Fee Transmittal Form, with-a copy of the check for the State's share of the Notice of Intent filing fee
copy(s) of plans, calculations, and other documentation necessary to completely describe the proposed work and mitigating measures to protect resource areas.
copy(s) of a 8 V4" by 11" section of the USGS topographic map of the area (a legible photocopy) showing the site
Two (2) copy(s) of plans showing compliance with Title 5 of the State Environmental Code, 310 CMR 15.00
Proof that a copy of your Notice of Intent has been mailed or hand delivered to the Natural Heritage and Endangered Species Program
COMMENTS: - See page 2 for additional information
This information is available in alternate formal by calling our ADA Coordinator at (617) 574-6872.
Other Regulatory Jurisdiction
C Application has been forwarded to Waterways Regulatory Program to determine if a Chapter 91 License is required
D 401 Water Quality Certification (314 CMR 9 00) may be required See below for further details
( ) Based upon the information submitted in and with your Notice of Intent a separate 401 Water Quality Certification application form is not required. Provided that the project meets the following conditions, summarized below from 310 CMR 9.03 and 9.04, and the conditions under the Corps of Engineers Programmatic General Permit for Massachusetts (PGP), the project qualifies for 401 Certification as certified under the PGP:
a) activities are conducted in compliance with MGL c 131, §40 (the Wetlands Protection Act) and the Final Order of Conditions permitting the activities does not result in the loss of more than 5.000 square feet cumulatively of bordering and isolated vegetated wetlands ana Land Under Water and/or the dredging of more than 1CG cubic yards of Land Under Water,
b) the Final Order of Conditions requires at least 1:1 replacement of Bordering Vegetated Wetlands pursuant to 310 CMR 1055(4)(b),
c) The project is not listed in 314 CMR 9 04 (1) through (11) including discharge of dredged or fill material to any Outstanding Resource Waters, any part of a subdivision unless deed restricted, so long as the discharge is not to an Outstanding Resource Water see 314 CMR 9 04 (3), and,
d) The project does not include activities exempt from MGL c 131, s40 (except for normal maintenance and improvement of land in agricultural or aquacultural use), discharge of dredged or fill material to an isolated vegetated wetland designated as rare and endangered species habitat, loss of any salt marsh, activities subject to an individual 404 permit
Information and a copy of the PGP can be obtained from the Corps of Engineers at 1-800-362-4367 If impacts to resource areas or project size increased beyond that described in the Notice of Intent or there are discrepancies therein, you must notify the Department and request a determination that the critena of 310 CMR 9 03 have been met before the activity may begin.
( ) Before the activity described in the Notice of Intent can commence, you must obtain a Water Quality Certification from this Regional Office. Please complete the enclosed 401 Water Quality Certification application form and file it with this Regional Office for Review. The applicant is advised to forward a copy of the application to the Army Corps of Engineers for review, at U.S Army Corps of Engineers, 696 Virginia Road, Concord, MA 01742-2751
( ) Your project involves dredging of greater than 100 cubic yards of Land Under Water. Please complete the enclosed 40 Water Quality Certification application form and submit to the Department of Environmental Protection, Wetlands and Waterways Program, One Winter Street, Boston, MA 02108. Call the Wetlands and Waterways Program at 617292-5695 with any questions. The applicant is advised to forward a copy of the application to Army Corps of Engineers for review, at U S. Army Corps of Engineers, 696 Virginia Road, Concord, MA 01742-2751.
For more information please contact: Timothy McKenna
cc: Conservation Commission
Property Owner as listed in Notice of Intent
Representative as listed in Notice of Intent
( ) Natural Heritage and Endangered Species Program
( ) U.S. Army Corps of Engineers
( ) DEP Waterways Regulation Program
( ) Other
DEP File Number Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands 198- I 86
Provided by DEP WPA Form 5- Order of Conditions Massachusetts Wetlands Protection Act M G L c 131, §40
A. General Information
Important When filling From
out forms on L e n o x the computer Conservation Commission use only the
This issuance if for (check one) tab key to move your
Q Order of Conditions cursor - do not use the return key D Amended Order of Conditions
To Applicant Property Owner (if different from applicant)
URS Corp on behalf of GF Power Systems F . P R T Name Name 646 Plank Road, Suite 202 1 1 5 E a s t N e w L e n o x R d . Mailing Address Mailing Address
C1 ^ f l -nn P a r k NY 1 906 S L e n o x MA 0 I 2 4 0 Crtyn"own State Zip Code City/Town State Zip Code
1 Project Location
I 15 East New Lenox Rd L e n o x MA Q I 2 4 0 Street Address City/Town
34 1 Assessors Map/Plat Number Parcel/Lot Number
2 Property recorded at the Registry of Deeds for
B e r k s h i r e M i d d l e D i s t r i c t County Book Page
Certrficate (if registered land)
3 Dates
10/ 18/200 1 I 1 / 2 6 / Q1 1 7 2 6 / O 1 Date Notice of Intent Filed Date Public Hearing Closed Date of Issuance
4 Final Approved Plans and Other Documents (attach additional plan references as needed)
Title Date
5 Final Plans and Documents Signed and Stamped by
Name
6 Total Fee
7 8 7 . 5 0 (from Appendix B Wetland Fee Transmrttal Form)
WPA Fom. 5 11 an
Massachusetts Department of Environmental Protection ' 9 8 I 8 f c Bureau of Resource Protection - Wetlands ~
WPA Form 5- Order of Conditions p^^v Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Findings
Findings pursuant to the Massachusetts Wetlands Protection Act
Following the review of the above-referenced Notice of Intent and based on the information provided in this application and presented at the public hearing, this Commission finds that the areas in which work is proposed is significant to the following interests of the Wetlands Protection Act Check all that apply
D Public Water Supply CD Land Containing Shellfish CH Prevention of Pollution
CH Private Water Supply O Fisheries D Protection of Wildlife Habitat
D Groundwater Supply n Storm Damage Prevention D Flood Control
Furthermore, this Commission hereby finds the project, as proposed, is (check one of the following boxes)
Approved subject to:
[7] the following conditions which are necessary, in accordance with the performance standards set forth in the wetlands regulations, to protect those interests checked above. This Commission orders that all work shall be performed in accordance with the Notice of Intent referenced above, the following General Conditions, and any other special conditions attached to this Order. To the extent that the following conditions modify or differ from the plans', specifications, or other proposals submitted with the Notice of Intent, these conditions shall control.
Denied because:
[~l the proposed work cannot be conditioned to meet the performance standards set forth in the wetland regulations to protect those interests checked above. Therefore, work on this project may not go forward unless and until a new Notice of Intent is submitted which provides measures which are adequate to protect these interests, and a final Order of Conditions is issued.
O the information submitted by the applicant is not sufficient to describe the site, the work, or the effect of the work on the interests identified in the Wetlands Protection Act. Therefore, work on this project may not go forward unless and until a revised Notice of Intent is submitted which provides sufficient information and includes measures which are adequate to protect the Act's interests, and a final Order of Conditions is issued. A description of the specific information which is lacking and why it is necessary is attached to this Order as per 310 CMR 10.05(6)(c).
General Conditions (only applicable to approved projects)
1. Failure to comply with all conditions stated herein, and with all related statutes and other regulatory measures, shall be deemed cause to revoke or modify this Order.
2. The Order does not grant any property rights or any exclusive privileges; it does not authorize any injury to private property or invasion of private rights.
3. This Order does not relieve the permittee or any other person of the necessity of complying with all other applicable federal, state, or local statutes, ordinances, bylaws, or regulations.
WPAFonnS P»g« 2
DEP Fie Number Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands 1 9 8 - 1 8 6
Provided by DEP WPA Form 5- Order of Conditions Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Findings (cont)
4 The work authorized hereunder shall be completed within three years from the date of this Order unless either of the following apply a the work is a maintenance dredging project as provided for in the Act, or b the time for completion has been extended to a specified date more than three years, but less
than five years, from the date of issuance If this Order is intended to be valid for more than three years, the extension date and the special circumstances warranting the extended time period are set forth as a special condition in this Order
5 This Order may be extended by the issuing authority for one or more penods of up to three years each upon application to the issuing authonty at least 30 days prior to the expiration date of the Order.
6 Any fill used in connection with this project shall be clean fill Any fill shall contain no trash, refuse, rubbish, or debris, including but not limited to lumber, bricks, plaster, wire, lath, paper, cardboard, pipe, tires, ashes, refrigerators, motor vehicles, or parts of any of the foregoing
7. This Order is not final until all administrative appeal periods from this Order have elapsed, or if such an appeal has been taken, until all proceedings before the Department have been completed.
8 No work shall be undertaken until the Order has become final and then has been recorded in the Registry of Deeds or the Land Court for the district in which the land is located, within the chain of title of the affected property. In the case of recorded land, the Final Order shall also be noted in the Registry's Grantor Index under the name of the owner of the land upon which "the proposed work is to be done In the case of the registered land, the Final Order shall ateo be noted on the Land Court Certificate of Title of the owner of the land upon which the proposed work is done The recording information shall be submitted to this Conservation Commission on the form at the end of this Order, which form must be stamped by the Registry of Deeds, prior to the commencement of work.
9 A sign shall be displayed at the site not less then two square feet or more than three square feet in size bearing the words,
"Massachusetts Department of Environmental Protection" [or, "MA DEP"]
"File Number 198- I 86
10. Where the Department of Environmental Protection is requested to issue a Superseding Order, the Conservation Commission shall be a party to all agency proceedings and hearings before DEP.
11. Upon completion of the work described herein, the applicant shall submit a Request for Certificate of Compliance (WPA Form 8A) to the Conservation Commission.
12. The work shall conform to the plans and special conditions referenced in this order.
13 Any change to the plans identified in Condition #12 above shall require the applicant to inquire of the Conservation Commission in writing whether the change is significant enough to require the filing of a new Notice of Intent.
14. The Agent or members of the Conservation Commission and the Department of Environmental Protection shall have the right to enter and inspect the area subject to this Order at reasonable hours to evaluate compliance with the conditions stated in this Order, and may require the submrttal of any data deemed necessary by the Conservation Commission or Department for that evaluation.
Massachusetts Department of Environmental Protection 'e Numb€r
Bureau of Resource Protection - Wetlands i 9 8 - 1 8 6 .
WPA Form 5 Order of Conditions prov.edbyoE Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Findings (cont)
15 This Order of Conditions shall apply to any successor in interest or successor in control of the property subject to this Order and to any contractor or other person performing work conditioned by this Order
16 Prior to the start of work, and if the project involves work adjacent to a Bordering Vegetated Wetland, the boundary of the wetland in the vicinity of the proposed work area shall be marked by wooden stakes or flagging Once in place, the wetland boundary markers shall be maintained until a Certificate of Compliance has been issued by the Conservation Commission
17 All sedimentation barriers shall be maintained in good repair until all disturbed areas have been fully stabilized with vegetation or other means At no time shall sediments be deposited in a wetland or water body During construction, the applicant or his/her designee shall inspect the erosion controls on a daily basis and shall remove accumulated sediments as needed The applicant shall immediately control any erosion problems that occur at the site and shall also immediately notify the Conservation Commission, which reserves the right to require additional erosion and/or damage prevention controls it may deem necessary. Sedimentation barriers shall serve as the limit of work unless another limit of work line has been approved by this Order.
Special Conditions (use additional paper, if necessary).
Materials and equipment shall be stored in a manner and l o c a t i which will minimize the comp a'C tion of -soils a-n d the concentration of runoff. Refueling of vehicles shall be in an area outside the Buffer Zone. If a spill occurs, contaminated soils shall be removed according to guidelines e stablished by the DEP Division of Hazardous Waste. T i h e proposed work sequence schedule and timing should be clearly understood by the Conservation Comm. prior to p e r m i t t i
Findings as to municipal bylaw or ordinance TRENCHED IN SILT FENCES TO BE US
Furthermore, the hereby finds (check one that applies): Conservation Commission
that the proposed work cannot be conditioned to meet the standards set forth in a munici