55
1 SPF-001 (Rev.D1) DOCUMENT RELEASE AND CHANGE FORM Prepared For the U.S. Department of Energy, Assistant Secretary for Environmental Management By Washington River Protection Solutions, LLC., PO Box 850, Richland, WA 99352 Contractor For U.S. Department of Energy, Office of River Protection, under Contract DE-AC27-08RV14800 TRADEMARK DISCLAIMER: Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof or its contractors or subcontractors. Printed in the United States of America. Release Stamp 1. Doc No: RPP-SPEC-63856 Rev. 00 2. Title: Procurement Specification - Condensers for ETF Steam Strippers 3. Project Number: OP185 N/A 4. Design Verification Required: Yes No 5. USQ Number: N/A RPP-27195 6. PrHA Number Rev. N/A Clearance Review Restriction Type: undefined 7. Approvals Title Name Signature Date Design Authority Melvin, Max A Checker Hall, Richard B Hall, Richard B 12/10/2020 Environmental Protection Beam, Tom Engineering Discipline Lead-Civil/Structural Mackey, Tom Engineering Discipline Lead-Electrical Rambo, Charles L Engineering Discipline Lead-Mechanical Goessmann, Glen E Engineering Discipline Lead-Ventilation Khabir, Sharok Originator Quam, Paul R Quam, Paul R 12/10/2020 Other Approver Young, Natalie M Other Approver Russell, Rose M Other Approver Marks, Jeff Other Approver Thompson, Tyler J Responsible Engineering Manager Lehrman, Scott D Welding Engineer Berkey, James 8. Description of Change and Justification Initial Release. 9. TBDs or Holds N/A 10. Related Structures, Systems, and Components a. Related Building/Facilities N/A b. Related Systems N/A c. Related Equipment ID Nos. (EIN) N/A ETF FACILITIES ETF-60K 60K-CND-001 60K-CND-201 11. Impacted Documents – Engineering N/A Document Number Rev. Title 12. Impacted Documents (Outside SPF): N/A 13. Related Documents N/A Document Number Rev. Title RPP-SPEC-64264 00 Procurement Specification - Pump Skids for ETF Steam Stripper 14. Distribution Name Organization Beam, Tom ENVIRONMENTAL PROTECTION Cassinelli, Andrew T COMMISSIONING Corbett, John E COMMISSIONING Domnoske, Lisa A ETF ENGINEERING Filip, Jeff WFD PROJECTS Garrett Reed, Tara L WFD PROJECTS Halgren, Dale L ETF ENGINEERING Lehrman, Scott D ETF PROJECTS ENGINEERING McFerran, Brandon E 242-A/AW/ETF OPERATIONS Melvin, Max A ETF PROJECTS ENGINEERING Russell, Rose M ETF ENGINEERING Rutherford, Wally PROD OPERATIONS ENGINEERING Severson, Brian D ETF PROJECTS ENGINEERING Thompson, Tyler J PROCUREMENT QA Yarger, David J ETF ENGINEERING RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 1 of 55

Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

1 SPF-001 (Rev.D1)

DOCUMENT RELEASE AND CHANGE FORMPrepared For the U.S. Department of Energy, Assistant Secretary for Environmental ManagementBy Washington River Protection Solutions, LLC., PO Box 850, Richland, WA 99352Contractor For U.S. Department of Energy, Office of River Protection, under Contract DE-AC27-08RV14800

TRADEMARK DISCLAIMER: Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof or its contractors or subcontractors. Printed in the United States of America.

Release Stamp

1. Doc No: RPP-SPEC-63856 Rev. 00

2. Title:Procurement Specification - Condensers for ETF Steam Strippers

3. Project Number:OP185

☐N/A 4. Design Verification Required:

☐Yes ☒No

5. USQ Number: ☒ N/ARPP-27195

6. PrHA Number Rev. ☒ N/A

Clearance Review Restriction Type:undefined

7. Approvals

Title Name Signature DateDesign Authority Melvin, Max AChecker Hall, Richard B Hall, Richard B 12/10/2020Environmental Protection Beam, TomEngineering Discipline Lead-Civil/Structural Mackey, TomEngineering Discipline Lead-Electrical Rambo, Charles LEngineering Discipline Lead-Mechanical Goessmann, Glen EEngineering Discipline Lead-Ventilation Khabir, SharokOriginator Quam, Paul R Quam, Paul R 12/10/2020Other Approver Young, Natalie MOther Approver Russell, Rose MOther Approver Marks, JeffOther Approver Thompson, Tyler JResponsible Engineering Manager Lehrman, Scott DWelding Engineer Berkey, James

8. Description of Change and Justification

Initial Release.

9. TBDs or Holds ☒N/A

10. Related Structures, Systems, and Components

a. Related Building/Facilities ☐N/A b. Related Systems ☐N/A c. Related Equipment ID Nos. (EIN) ☐N/A

ETF FACILITIES ETF-60K 60K-CND-00160K-CND-201

11. Impacted Documents – Engineering ☐N/A

Document Number Rev. Title

12. Impacted Documents (Outside SPF):

N/A

13. Related Documents ☐N/A

Document Number Rev. TitleRPP-SPEC-64264 00 Procurement Specification - Pump Skids for ETF Steam Stripper

14. Distribution

Name OrganizationBeam, Tom ENVIRONMENTAL PROTECTIONCassinelli, Andrew T COMMISSIONINGCorbett, John E COMMISSIONINGDomnoske, Lisa A ETF ENGINEERINGFilip, Jeff WFD PROJECTSGarrett Reed, Tara L WFD PROJECTSHalgren, Dale L ETF ENGINEERINGLehrman, Scott D ETF PROJECTS ENGINEERINGMcFerran, Brandon E 242-A/AW/ETF OPERATIONSMelvin, Max A ETF PROJECTS ENGINEERINGRussell, Rose M ETF ENGINEERINGRutherford, Wally PROD OPERATIONS ENGINEERINGSeverson, Brian D ETF PROJECTS ENGINEERINGThompson, Tyler J PROCUREMENT QAYarger, David J ETF ENGINEERING

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 1 of 55

Page 2: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

DOCUMENT RELEASE AND CHANGE FORM Doc No: RPP-SPEC-63856 Rev. 00

2 SPF-001 (Rev.D1)

14. Distribution

Name OrganizationYoung, Natalie M ETF PROJECTS ENGINEERING

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 2 of 55

Page 3: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP.-SPEC-63 856

Revision 0

Procurement Specification - Condensersfor ETF Steam Strippers

Prepared by

P.R. QuamSargent & Lundy for Washington River Protection Solutions, LLC

Date PublishedDecember 2020

11s1r?D1i!.'r.JNh1(.1lJ

Prepared for the U.S. Department of EnergyOffice of River Protection

Contract No. DE-AC27-08RV14800

B. -

siI/ 1<

o

A-6007-23 1 (REV-O)

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 3 of 55

Page 4: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-2

TABLE OF CONTENTS

1.0 SCOPE ............................................................................................................................. 1-7

1.1 DESCRIPTION ............................................................................................................. 1-7

1.2 DOCUMENT OVERVIEW .......................................................................................... 1-7

1.2.1 Definitions.............................................................................................................. 1-8

1.3 BACKGROUND ........................................................................................................... 1-8

1.4 TRADEMARK DISCLAIMER .................................................................................... 1-9

1.5 ABBREVIATIONS AND ACRONYMS ..................................................................... 1-9

1.6 UNITS ......................................................................................................................... 1-10

2.0 APPLICABLE DOCUMENTS ..................................................................................... 2-11

2.1 GOVERNMENT DOCUMENTS ............................................................................... 2-11

2.2 NON-GOVERNMENT DOCUMENTS ..................................................................... 2-12

2.3 NON-GOVERNMENT NON-CODE OF RECORD DOCUMENTS ........................ 2-13

2.4 HIERARCHY OF CODE............................................................................................ 2-14

3.0 STRUCTURES, SYSTEMS, AND COMPONENTS CHARACTERISTICS AND

REQUIREMENTS ..................................................................................................................... 3-15

3.1 STRUCTURES, SYSTEMS, AND COMPONENTS FUNCTIONS AND

FUNCTIONAL PERFORMANCE REQUIREMENTS ........................................................ 3-15

3.1.1 Mechanical Design............................................................................................... 3-15

3.1.2 Nozzles and Reinforcing Pads ............................................................................. 3-15

3.1.3 Shells and Shell Covers ....................................................................................... 3-16

3.1.4 Tubes, Tubesheets, and Tube End Fixing ............................................................ 3-16

3.1.5 Handling Devices ................................................................................................. 3-16

3.1.6 Shell Supports and Attachments .......................................................................... 3-16

3.1.7 Work Not Included .............................................................................................. 3-17

3.2 STRUCTURES, SYSTEMS, AND COMPONENTS INTERFACES ....................... 3-17

3.2.1 External Interfaces ............................................................................................... 3-17

3.2.2 Piping Interface .................................................................................................... 3-18

3.3 STRUCTURES, SYSTEMS, AND COMPONENTS CHARACTERISTICS ........... 3-18

3.3.1 Functional Characteristics .................................................................................... 3-18

3.3.1.1 Design Pressure ............................................................................................ 3-18

3.3.1.2 Design Temperature ..................................................................................... 3-18

3.3.1.3 Corrosion Allowance .................................................................................... 3-18

3.3.1.4 System Design Life ...................................................................................... 3-18

3.3.1.5 Performance Requirements........................................................................... 3-18

3.3.1.6 Environmental Conditions ............................................................................ 3-19

3.3.1.7 Design Loads ................................................................................................ 3-19

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 4 of 55

Page 5: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-3

3.3.2 Packaging, Storage, Shipping, and Handling ....................................................... 3-19

3.3.2.1 Transportability and Storage ........................................................................ 3-20

3.3.2.2 Hoisting and Rigging .................................................................................... 3-20

3.3.2.3 Equipment Handling ..................................................................................... 3-20

3.4 DESIGN AND CONSTRUCTION REQUIREMENTS ............................................. 3-20

3.4.1 Materials .............................................................................................................. 3-20

3.4.2 Bolting.................................................................................................................. 3-21

3.4.3 Welding ................................................................................................................ 3-22

3.4.4 Gaskets ................................................................................................................. 3-22

3.4.5 Nameplates and Product Marketing ..................................................................... 3-22

3.4.6 Human Factors Engineering ................................................................................ 3-22

3.5 SYSTEM RELIABILITY AND MAINTAINABILITY REQUIREMENTS ............ 3-22

3.5.1 Reliability ............................................................................................................. 3-23

3.5.2 Maintainability ..................................................................................................... 3-23

4.0 FABRICATION REQUIREMENTS ............................................................................. 4-24

4.1 WELDING REQUIREMENTS .................................................................................. 4-24

4.1.1 Structural Welding ............................................................................................... 4-24

4.1.2 Weld Materials ..................................................................................................... 4-24

4.1.3 Welding Procedures and Qualifications............................................................... 4-25

4.1.4 Weld Inspection Requirements ............................................................................ 4-25

4.1.5 Additional Welding Requirements ...................................................................... 4-26

4.2 WORKMANSHIP ....................................................................................................... 4-26

4.3 CLEANLINESS .......................................................................................................... 4-26

4.3.1 Material Contamination Control .......................................................................... 4-27

4.3.2 Surfaces ................................................................................................................ 4-27

4.3.3 Cleaning ............................................................................................................... 4-27

4.4 TOLERANCES ........................................................................................................... 4-28

4.5 PLATE LAYOUT AND FORMING .......................................................................... 4-28

4.6 LIFTING ATTACHMENTS....................................................................................... 4-28

4.7 TUBES-TO-TUBESHEET JOINTS ........................................................................... 4-28

5.0 PRODUCTION INSPECTION AND TESTING REQUIREMENTS .......................... 5-29

5.1 QUALIFICATIONS TESTING REQUIREMENTS .................................................. 5-29

5.2 INSPECTION.............................................................................................................. 5-29

5.2.1 General ................................................................................................................. 5-29

5.3 EXAMINATION ........................................................................................................ 5-30

5.3.1 Condenser ............................................................................................................ 5-30

5.3.2 Structural .............................................................................................................. 5-30

5.3.3 Lifting Attachments ............................................................................................. 5-30

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 5 of 55

Page 6: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-4

5.4 TESTING .................................................................................................................... 5-30

5.4.1 General ................................................................................................................. 5-30

6.0 DELIVERY, STORAGE, AND HANDLING .............................................................. 6-32

6.1 DELIVERY, STORAGE, & LOAD HANDLING ..................................................... 6-32

6.1.1 General ................................................................................................................. 6-32

6.1.2 Transportability .................................................................................................... 6-32

6.1.3 Packaging ............................................................................................................. 6-32

6.1.3.1 Levels of Packaging ...................................................................................... 6-32

6.1.3.2 Cleaning Plan ................................................................................................ 6-33

6.1.3.3 Cleaning Records .......................................................................................... 6-33

6.1.3.4 Packaging Type ............................................................................................ 6-33

6.1.3.5 Packaging Materials ..................................................................................... 6-33

6.1.3.6 Packaging Materials Contacting Stainless Steel and Nickel Alloy .............. 6-33

6.1.3.7 Seal Openings ............................................................................................... 6-34

6.1.3.8 Protection from Corrosion ............................................................................ 6-34

6.1.3.9 Unprotected Steel ......................................................................................... 6-34

6.1.3.10 Shipment Load Protection ............................................................................ 6-34

6.1.3.11 Protection from Shock and Vibration ........................................................... 6-34

6.1.3.12 Other Protection ............................................................................................ 6-34

6.1.3.13 Protection of Machined Surfaces .................................................................. 6-35

6.1.3.14 Packaging Inspection .................................................................................... 6-35

6.1.4 Handling ............................................................................................................... 6-35

6.1.4.1 Lift and Rigging Plan ................................................................................... 6-35

6.1.4.2 Lift Point Marking ........................................................................................ 6-35

6.1.4.3 Rated Temperature for Custom Lifting Devices .......................................... 6-35

6.1.4.4 Contact with Different Metals ...................................................................... 6-35

6.1.4.5 Critical Welds ............................................................................................... 6-35

6.1.4.6 Shipping and Handling Drawing .................................................................. 6-35

6.1.4.7 Unpacking and Assembly Drawing .............................................................. 6-36

6.1.4.8 Special Lifting Devices ................................................................................ 6-36

6.1.4.9 Below-the-Hook Device Marking ................................................................ 6-36

6.1.4.10 Offloading ..................................................................................................... 6-36

6.1.5 Storage ................................................................................................................. 6-36

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 6 of 55

Page 7: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-5

6.1.5.1 Level of Storage ............................................................................................ 6-36

6.1.5.2 Storage Areas ................................................................................................ 6-37

6.1.5.3 Storage Methods ........................................................................................... 6-37

6.1.5.4 Control of Items in Storage .......................................................................... 6-37

6.1.5.4.1 Inspections ................................................................................................ 6-38

6.1.5.4.2 Care of Items ............................................................................................ 6-38

6.1.5.4.3 Post-Fire Evaluations ............................................................................... 6-38

6.1.5.5 Removal of Items from Storage.................................................................... 6-38

6.1.5.6 Storage Records ............................................................................................ 6-39

6.1.5.7 Additional Storage Requirements ................................................................. 6-39

6.1.5.8 Environmental Storage Requirements .......................................................... 6-39

6.1.6 Delivery................................................................................................................ 6-39

6.1.7 Marking for Shipment .......................................................................................... 6-39

6.2 QUALITY ASSURANCE .......................................................................................... 6-40

6.3 SITE CONDITIONS ................................................................................................... 6-40

7.0 PROJECT MANAGEMENT ......................................................................................... 7-41

7.1 WORK PLAN ............................................................................................................. 7-41

7.2 SUBMITTALS ............................................................................................................ 7-41

7.2.1 Submittals Required with Proposal ...................................................................... 7-41

7.2.2 Submittals Required After Receipt of Order ....................................................... 7-42

7.2.3 Submittals Required Prior to Fabrication ............................................................ 7-42

7.2.4 Submittals Required Prior to Shipping ................................................................ 7-43

7.2.5 Request for Information ....................................................................................... 7-45

7.3 QUALITY ASSURANCE PROGRAM ..................................................................... 7-45

7.3.1 Non-Conformance Reports .................................................................................. 7-46

7.3.2 Inspection/Examination ....................................................................................... 7-46

7.3.3 Suspect/Counterfeit Items .................................................................................... 7-46

7.3.4 Certificate of Conformance.................................................................................. 7-46

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 7 of 55

Page 8: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-6

APPENDICES

Appendix A ………………………………………………………..Heat Exchanger Data Sheets

Appendix B ………………………………………………………… Large Condenser Drawing

Appendix C ………………………………………………………… Small Condenser Drawing

LIST OF TABLES

Table 2-1. Government Documents. ......................................................................................... 2-11

Table 2-2. Non-Government Documents (2 pages). ................................................................. 2-12 Table 2-3. Non-Government Non-Code of Record Documents (2 pages). .............................. 2-13 Table 7-1. Submittals Required with Proposal. ........................................................................ 7-41

Table 7-2. Submittals Required After Receipt of Order. .......................................................... 7-42 Table 7-3. Submittals Required Prior to Fabrication (2 Pages). ............................................... 7-42 Table 7-4. Submittals Required Prior to Shipping (2 pages). ................................................... 7-44

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55

Page 9: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-7

1.0 SCOPE

This Procurement Specification (hereafter referred to as Specification) provides baseline

requirements for design and procurement of two (2) Condensers (one large and one small), shell

and tube style, for the Effluent Treatment Facility (ETF) Steam Strippers. This Specification

establishes the functions, interfaces, function performance requirements, applicable codes and

standards, and requirements for the thermal design, mechanical design, materials, fabrication,

assembly, inspecting, testing, quality oversight, documentation, packaging, transportation, and

delivery of the two Condensers for the ETF Steam Strippers. The Condensers shall be shell and

tube heat exchangers constructed in accordance with Section VIII, Division 1 of the American

Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (B&PVC) (hereafter

simply referred to as the Code) including stamping with the Code “U” symbol.

1.1 DESCRIPTION

Washington River Protection Solutions, LLC (WRPS), is the U.S. Department of Energy (DOE),

Office of River Protection (ORP) Tank Farm Operations Contract (TOC). WRPS is contracted

to provide safe, compliant, cost-effective, and energy-efficient services to further the DOE-ORP

River Protection Project (RPP) Mission. In order to safely complete the RPP Mission, various

permanent or temporary systems and associated components are required.

This Specification identifies and communicates the common inputs, requirements, and criteria

for the design and procurement of two Condensers for the ETF Steam Strippers. The functions

of the Condensers are to condense all of the acetonitrile containing distillate from the top of the

Steam Stripper and Steam Concentrator.

The two shell and tube Condensers procured by this specification are different sizes and are

specified in detail herein. The first and larger Condenser, 60K-CND-001, will be installed to

condense acetonitrile containing water following its removal from the main Steam Stripper

Column, 60K-CO-001, as shown on H-2-839035. The second and smaller Condenser, 60K-

CND-201, will be installed to condense concentrated acetonitrile containing water following its

removal from the Concentrator Column, 60K-CO-201, as shown on H-2-839038. See Appendix

A, Appendix B, and Appendix C for further details differentiating the two Condensers, including

the Condenser data sheets.

1.2 DOCUMENT OVERVIEW

This Specification is a "design-build" specification, delineating the required functions and

requirements to which the VENDOR (SELLER) shall adhere to providing the finished

products/services to the BUYER. Where specific make and model of equipment and/or systems

are called out in this Specification, BUYER-approved equivalents will be considered.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 9 of 55

Page 10: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-8

The equipment being procured via this Specification shall interface with BUYER-provided

equipment and systems per Section 3.1.7.

Specific to this document, the following requirements and definitions are applicable.

1.2.1 Definitions

• DEVIATION – Any departure from the requirements contained in the purchase order and

specification, which SELLER proposes to incorporate if approved by BUYER.

• PRODUCT DATA – Printed information including, but not limited to, catalog cuts, color

charts, illustrations, diagrams, templates, performance curves, brochures, and other forms

of Product literature.

• RATED LOAD – The maximum load that can be lifted by the device.

• Shall/Must – Denotes project requirements, compliance is required

• Should – Denotes recommendation or expectation, compliance is expected. If a “should”

recommendation cannot be satisfied, justification of an alternative design solution shall

be submitted to the BUYER for approval.

• Will – Denotes a statement of fact.

• May – Denotes a “permissive” for a stated action, or denotes a possible outcome

depending on the context of the verbiage.

• BUYER – The TOC responsible for managing the design, procurement, and construction

of the procured item.

• SELLER – Contracted fabricator, vendor, or subcontractor performing work to the

contract Drawings, procurement Data Sheets, and technical specifications.

• Substitution – Any change or deviation from issued approved Drawings, designs,

methods, or contract terms and conditions. Changes in products, materials, equipment,

methods of construction, and test criteria required by the Contract Documents proposed

by the SELLER after award of the Contract are considered requests for substitution.

• WITNESS POINT – An inspection activity beyond which work shall not proceed until an

inspector and/or BUYER is notified and (1) the inspection is performed and released, or

(2) the inspection is deferred and can be completed at a later time, or (3) a written waiver

is issued by the organization who established the witness point.

1.3 BACKGROUND

The Hanford Site located in Washington State contains the largest quantity of legacy tank waste

in the DOE complex. Most of these nuclear wastes, resulting from the processing operations of

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 10 of 55

Page 11: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-9

defense nuclear materials, are stored in 177 underground storage tanks. The tanks contain an

estimated 56 million gallons of hazardous and radioactive liquids, sludge, and salt cake with

approximately 175 million curies of radioactivity. These tanks are located on the Central Plateau

of the Hanford Site in 200 East and 200 West Areas.

The ETF treats secondary liquid waste generated from waste streams at the Hanford Site. This

Specification is prepared to detail requirements associated with the new ETF Acetonitrile Steam

Stripper system, which will remove acetonitrile from the waste treatment plant effluent stream,

prior to delisting.

1.4 TRADEMARK DISCLAIMER

Reference herein to any specific commercial product, process, or service by trade name,

trademark, SELLER, or otherwise, does not necessarily constitute or imply endorsement,

recommendation, or favoring by the United States Government or any agency thereof or its

contractors or subcontractors.

1.5 ABBREVIATIONS AND ACRONYMS

ABBREVIATIONS AND ACRONYMS (2 Sheets)

AISC American Institute of Steel Construction

ASME American Society of Mechanical Engineers

ASNT American Society for Non-Destructive Testing

ASTM American Society for Testing and Materials

AWS American Welding Society

B&PVC Boiler and Pressure Vessel Code

BTH Below-the-Hook Lifting

CFR Code of Federal Regulations

CMTR Certified Material Test Report

COR Code of Record

DOE Department of Energy

ETF Effluent Treatment Facility

FIT Fabrication, Inspection, and Test

NDE Non-Destructive Examination

ORP Office of River Protection

PSSH Packaging, Storage, Shipping, and Load Handling

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 11 of 55

Page 12: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

1-10

QA Quality Assurance

QAP Quality Assurance Program

RFI Request for Information

RPP River Protection project

SSC Structures, Systems, and Components

TOC Tank Farm operations Contractor

WRPS Washington River Protection Solutions, LLC.

1.6 UNITS

°F degrees Fahrenheit

ft feet

gpm gallons per minute

hr hour

in. inch

kW kilowatt

psi Pound-force per square inch

psig Pounds-force per square inch gauge

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 12 of 55

Page 13: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

2-11

2.0 APPLICABLE DOCUMENTS

The following tables serve as the set of requirements that are used to design, construct, operate,

and decommission a nuclear facility or a mission critical, non-nuclear facility (or their structures,

systems, and components [SSCs]) over its lifespan. When specifying requirements for

procurement, the Design Authority/Subject Matter Expert shall ensure that the specific

codes/standard and regulation references selected for the design of the item are included in the

Code of Record (COR) according to TFC-ENG-DESIGN-C-57, “Development and Maintenance

of Code of Record.”

The following documents may not be an all-inclusive list and considerations for the design for

specific farms, facilities, and projects must be taken into consideration. In the event of a conflict

between the documents referenced herein and the requirements of this Specification, the

requirements of this Specification shall take precedence over requirements in documents listed in

Table 2-1 through Table 2-3 only when the Specification requirements are more stringent or

conservative.

2.1 GOVERNMENT DOCUMENTS

The following documents, of the exact issue shown in Table 2-1 through Table 2-3, form a part

of this Specification to the extent specified herein and establish of the Code of Record. Unless

otherwise shown or noted, the latest edition and addenda are applicable.

Table 2-1. Government Documents.

Document Number Title

Code of Federal Regulations (CFR)

10 CFR 830 “Nuclear Safety Management”

U.S. Department of Energy (DOE)

DOE G 414.1-3 “Suspect/Counterfeit Items Guide for Use with 10 CFR 830

Subpart A, Quality Assurance Requirements, and DOE O 414.1B,

Quality Assurance”

DOE-RL-92-36 “Hanford Site Hoisting and Rigging Manual”

Washington Administrative Code (WAC)

WAC 246-247 “Radiation Protection – Air Emissions”

WAC 173-303 “Dangerous Waste”

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 13 of 55

Page 14: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

2-12

2.2 NON-GOVERNMENT DOCUMENTS

The following documents establish the Code of Record, or basis of design of the new ETF

Condensers. Unless otherwise shown or noted, the latest edition and addenda are applicable.

Table 2-2. Non-Government Documents (2 pages).

Document Number Title

American Society of Civil Engineers (ASCE)

ASCE 7-10 “Minimum Design Loads for Buildings and Other Structures”

American Institute of Steel Construction (AISC)

AISC 325 “Steel Construction Manual”

American Petroleum Institute

API 660 “Shell and Tube Heat Exchangers”

American Society of Mechanical Engineers (ASME)

Required Code year at

time of contract

ASME Boiler and Pressure Vessel Code (B&PVC)

ASME Section II “Materials”

ASME Section V “Nondestructive Examination”

ASME Section VIII, Division 1 “Pressure Vessels”

ASME Section IX “Welding and Brazing Qualifications”

ASME BTH-1 “Design of Below-The-Hook (BTH) Lifting Devices”

ASME B16.5 “Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24

Metric/ Inch Standard”

ASME B30.20 “Below the Hook Lifting Devices”

ASME B31.3, 2016 “Process Piping”

American Society for Nondestructive Testing (ASNT)

ASNT SNT-TC-1A “Recommended Practice for Personal Qualification and

Certification in Nondestructive Testing”

American Society for Testing and Materials (ASTM)

A193 “Standard Specification for Alloy-Steel and Stainless Steel Bolting

for High Temperature or High Pressure Service and Other Special

Purpose Applications”

A194 Standard Specification for Carbon Steel, Alloy Steel, and Stainless

Steel Nuts for Bolts for High Pressure or High Temperature

Service, or Both

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 14 of 55

Page 15: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

2-13

Table 2-2. Non-Government Documents (2 pages).

Document Number Title

American Welding Society (AWS)

AWS D1.6/D1.6M “Structural Welding Code – Stainless Steel”

AWS D14.1 “Specification for Welding of Industrial and Mill Cranes and Other

Material Handling Equipment”

AWS B2.1/B2.1M-BMG “Base Metal Grouping for Welding Procedure and Performance

Qualification”

AWS QC1 “Standard for AWS Certification of Welding Inspectors”

International Code Council / International Building Code (ICC / IBC)

ICC IBC “International Building Code”

Military Standards (MIL)

MIL-STD-889C “Dissimilar Metals”

Tubular Exchanger Manufacturers Association (TEMA)

TEMA - 2007 Standards of the Tubular Exchanger Manufacturers Association

(TEMA)

Other

L.P. Zick Method Stresses in Large Cylindrical pressure Vessels on Two Saddle

Supports, L.P. Zick, Pressure Vessels and Piping: Design and

Analysis, A Decade of Progress, Vol. 2, 1972

2.3 NON-GOVERNMENT NON-CODE OF RECORD DOCUMENTS

The SELLER shall draft a Request for Information (RFI) to inquire about specific TOC

standards, procedures, and documents. The following documents are utilized or referenced by

this Specification but are not considered part of the COR. Unless otherwise shown or noted, the

latest edition and addenda are applicable.

Table 2-3. Non-Government Non-Code of Record Documents (2 pages).

Document Number Title

Washington River Protection Solutions, LLC (WRPS)

H-2-839035, Sheet 1 “ETF Steam Stripper P&ID Large Condenser and Pump Skid”

H-2-839038, Sheet 1 “ETF Steam Stripper P&ID Small Condenser and Pump Skid”

H-2-839039, Sheet 1 “ETF Steam Stripper P&ID Below Grade Lines”

H-2-839054, Sheet 1 “ETF Steam Stripper Mechanical Equipment Location Plan

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 15 of 55

Page 16: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

2-14

Table 2-3. Non-Government Non-Code of Record Documents (2 pages).

Document Number Title

MT-50529, Rev. 0 “Effluent Treatment Facility Acetonitrile Steam Stripping

System”

QA-AVS-APPENDIX “Procurement Quality Clauses”

RPP-8360, Rev. 6 “Lifting Attachment and Lifted Item Evaluation”

RPP-SPEC-64264 “Procurement Specification – Pump Skids for the ETF Steam

Stripper”

TFC-BSM-IRM_DC-C-02 “Records Management”

TFC-BSM-IRM_DC-C-07 “Vendor Processes”

TFC-ENG-DESIGN-C-10 “Calculation Format and Preparation Instructions"

TFC-ENG-DESIGN-C-57 “Development and Maintenance of Code of Record”

TFC-ENG-FACSUP-C-25 “Hoisting and Rigging”

TFC-ENG-STD-06 “Design Loads for Tank Farm Facilities”

TFC-ENG-STD-52 “Subcontractor Welding Standard”

TFC-ESHQ-Q_C-C-03 “Control of Suspect/Counterfeit Items”

2.4 HIERARCHY OF CODE

Except in those instances where Washington State has been granted regulatory authority by the

Federal Government, the hierarchical relationship among requirements specified in Section 2.0 is

as follows:

• Federal requirements (e.g., Code of Federal Regulations)

• Washington State requirements (e.g., Washington Administrative Code)

• Local ordinances

• U.S. Department of Energy Orders and Standards

• National consensus codes and standards

• Hanford Site-specific codes and standards

This hierarchy establishes the order of precedence of requirements levied in this Specification.

In the event of a conflict between two requirements, the SELLER shall submit an RFI for

clarifications prior to use.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 16 of 55

Page 17: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-15

3.0 STRUCTURES, SYSTEMS, AND COMPONENTS CHARACTERISTICS AND

REQUIREMENTS

This section addresses the following Structures, Systems, and Components (SSC) characteristics

and requirements:

• SSC functions and functional performance requirements are covered in Section 3.1,

• SSC interfaces are covered in Section 3.2,

• SSC characteristics are covered in Section 3.3,

• Design and construction requirements are covered in Section 3.4, and

• Reliability and maintainability requirements are covered in Section 3.5.

3.1 STRUCTURES, SYSTEMS, AND COMPONENTS FUNCTIONS AND

FUNCTIONAL PERFORMANCE REQUIREMENTS

3.1.1 Mechanical Design

a. The Condensers shall be designed and fabricated in accordance with ASME Boiler and

Pressure Vessel Code (B&PVC) Section VIII, Division 1 and Tubular Exchanger

Manufacturers Association (TEMA), TEMA Class B and any additional requirements of

this Specification and the referenced Drawings. Condensers shall be ASME U stamped

and a completed, signed and registered Form U-1 shall be provided for each condenser.

b. Components subject to both shell and tube side fluids (e.g., tubes, tube sheets, floating

heads) shall be designed for the most severe combination of pressure and temperature

that can apply.

c. The Condensers shall meet the requirements of the Heat Exchanger Data Sheet (see

Appendix A).

d. To provide operational margin. As noted in the remarks of both data sheets within

Appendix A, the SELLER is to design for a 20% excess area not counting U-portion of

the tubes.

e. Cooling water temperature rise shall be no more than 10 °F from inlet to outlet.

f. Manufacturer shall demonstrate successful installation for similar equipment that has

been in operation for at least 5 years.

3.1.2 Nozzles and Reinforcing Pads

a. All nozzles shall be set-in type or through type with full penetration welds. Nozzles with

internal projection shall have an additional fillet weld between the internal projection and

the inside surface of the shell or head.

b. All inside nozzle neck edges shall be rounded to 1/8 in. minimum radius. Nozzles shall

be flush with the inside wall.

c. Nozzles shall not be located on weld seams.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 17 of 55

Page 18: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-16

d. All connections shall be 3000# NPT, or Class 150 or Class 300 raised face, weld neck

flanges as depicted in Appendix A, Appendix B, and Appendix C in accordance with

ASME B16.11 and B16.5 (including vent and drain connections).

e. If required, nozzle reinforcing pads shall be external and, when constructed in segments,

shall have the segments joined with full penetration butt welds, the location of which

shall be at least 45 degrees from the longitudinal axis of the vessel. Each pad segment

shall have one American Standard Taper Pipe Thread (NPT) 1/4-in. tell-tale hole for

testing purposes.

f. Nozzle reinforcing pads and all attachment pads, if not circular, shall have rounded

corners of 2-in. minimum radius.

g. Length of nozzle projections shall provide a minimum clearance between the back of the

flange and the outside of the vessel insulation equal to the length of the flange bolts

(studs) plus 1 in.

h. Allowable nozzle forces shall be per API 660 Table 2.

3.1.3 Shells and Shell Covers

a. The shell diameter shall be left to the discretion of the SELLER within the TEMA

Class B Mechanical Standards.

b. The minimum shell thickness shall be determined by the Code design formulas, including

corrosion allowance, but in no case shall the nominal thickness of the shell be less than

shown in TEMA Class B.

3.1.4 Tubes, Tubesheets, and Tube End Fixing

a. Tubing shall be seamless.

b. Each U-tube shall be formed from a single length and shall have no circumferential

welds.

c. Total leak tightness is required for this service; therefore, tube-to-tubesheet joint shall be

strength-welded.

3.1.5 Handling Devices

a. Provision for lifting shall be included for all channels, bonnets, and covers.

b. For bundle pulling, tapped holes for pulling eyes shall be provided. They shall be

designed for a load of 1.5 times the bundle weight and fitted with a plug for operation.

3.1.6 Shell Supports and Attachments

a. Condenser lifting attachments (lugs) shall be designed by the SELLER. A minimum

factor of safety of two applied to the maximum permissible load shall be used to design

all Condenser lifting lugs.

b. Lifting lugs shall be a weld-on lug provided with a hole not less than 1 1/2 in. in diameter

and be designed and attached in a manner that will not damage/distort the Condensers.

c. The lug(s) shall be located at the top of the component, above its center of gravity.

d. The projection of the lug shall be designed to accommodate the thickness of the

insulation, such that placement of a shackle will not require removal of insulation.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 18 of 55

Page 19: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-17

e. The SELLER is responsible for determining the size and quantity of anchor bolts and the

design of the support saddle for horizontal installation.

f. Horizontal Condensers shall be designed for two saddle supports attached by welding.

Design of saddle supports and calculation of localized shell stress may be determined by

the SELLER in accordance with the L.P. Zick method, or equivalent method approved

by the BUYER.

g. One of the saddles shall be designated as the fixed saddle in which holes shall be

provided to receive the anchor bolts. The other saddle shall be designated as the sliding

saddle in which slotted holes shall be provided.

h. The bearing surface of the saddles shall be at least one-third of the circumference of the

shell.

i. Grounding Lugs: A grounding lug shall be provided on each vessel.

j. External attachments shall be of the same grade of material as the pressure shell, unless

agreed otherwise by the BUYER.

3.1.7 Work Not Included

The scope of supply of the SELLER shall exclude the following:

a. Condenser off-loading at the Site

b. Installation of Condensers on BUYER skid

c. Piping to/from Condenser

d. Start-up and commissioning Site work

e. Insulation and jacketing of the Condenser

3.2 STRUCTURES, SYSTEMS, AND COMPONENTS INTERFACES

The assembled Condensers will be bolted to the structural steel skids by the BUYER (reference

RPP-SPEC-64264).

3.2.1 External Interfaces

The Condensers shall fit within the maximum footprint requirements found in Appendix B and

Appendix C. If the overall dimensional size of the Condensers or the nozzle locations differ than

as shown in Appendix B and Appendix C, then approval for deviation is required by the

BUYER. See dimensional tolerances for nozzle locations as shown in Appendix B and

Appendix C for assurance of proper fit-up during installation.

The assembled Condensers will be bolted to the structural steel skid of the BUYER. For proper

anchorage to the structural steel skid of the BUYER, the SELLER shall provide saddle supports

with anchor bolt holes as dimensioned and depicted in Appendix B and Appendix C. See

dimensional tolerances as shown in Appendix B and Appendix C for assurance of proper fit-up

during installation. The information in Section 3.3.1.7 shall be used to design the supports.

SELLER shall provide equipment weight, size, and center of gravity for BUYER to determine

anchorage requirements.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 19 of 55

Page 20: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-18

SELLER shall provide maintenance clearances for each side of the Condensers.

3.2.2 Piping Interface

The Condenser units shall each be configured with inlet and outlet nozzles as depicted in

Appendix A. Flanges shall be two-hole oriented with the long axis of the vessel.

3.3 STRUCTURES, SYSTEMS, AND COMPONENTS CHARACTERISTICS

3.3.1 Functional Characteristics

This section provides requirements for the functional characteristics of each Condenser unit.

3.3.1.1 Design Pressure

The design pressure specified on the Condenser data sheets (see Appendix A) shall be taken to

be the top of the vessel. The pressure used in calculations shall be the design pressure plus the

static head pressure of the contents (assuming shell is full of water) making due allowance of the

specific gravity.

A pressure safety valve will be located on the piping connected to the tube side, upstream of both

Condensers as depicted in H-2-839039. The pressure safety valves will be sized, installed by

Others, and are not the responsibility of the SELLER. Note that the shell size is open to the

Steam Stripper vessels which are also protected by pressure safety valves (H-2-839034 and H-2-

839037).

3.3.1.2 Design Temperature

Design temperatures for the shell and tube sides are specified on the Condenser data sheets (see

Appendix A).

3.3.1.3 Corrosion Allowance

The corrosion allowance for internal surfaces (for the specified design life) applies to pressure

retaining parts and non-pressure parts (e.g., tray supports, clips), shall be 0.06-inch for stainless

material (0.002 mpy). The corrosion allowance is to be applied per wetted surface. .

3.3.1.4 System Design Life

Condensers will have a design life of 30 years.

3.3.1.5 Performance Requirements

The Condensers shall be capable of performing to the specifications in Appendix A.

A thermal performance and vibration report shall be provided.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 20 of 55

Page 21: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-19

3.3.1.6 Environmental Conditions

The Condensers will be installed indoors at the Hanford Site located in Washington State. The

expected environmental conditions during operation are shown below.

Relative Humidity: Up to 100%

Ground Elevation: 672 ft (above sea level)

Environment: Indoor

Minimum ambient temperature: 70°F

Maximum ambient temperature: 78°F

3.3.1.7 Design Loads

Design loads shall comply with TFC-ENG-STD-06.

a. Seismic

1. Natural Phenomena Design Requirements shall be in accordance with

TFC-ENG-STD-06.

2. Seismic Design Category shall be SDC-1, Limit State B, the NPH Design

Category is NDC-2.

3. Seismic Performance: Equipment shall withstand the effects of earthquake

motions determined according to TFC-ENG-STD-06.

4. The term "withstand" means "the unit will remain in place without separation of

any parts when subjected to the seismic forces specified and may be subject to

only moderate permanent deformation (Limit State B).”

5. Component Importance Factor: 1.5.

6. An amplification factor of 3 shall be applied to account for the potential

amplification of the steel frame which each of the Condensers will sit atop. This

amplification factor is incorporated into ASCE 7-2010, Equation 13.3-1

(1+2 x z/h) with z/h being equal to 1.

b. Thermal Insulation

1. The Condensers will be insulated and jacketed by Others. The density of the

insulation and jacketing will be: 6 lb/ft³.

2. Thermal insulation and jacketing will be 2-in. thick.

3.3.2 Packaging, Storage, Shipping, and Handling

When the SELLER has requirements for packaging, storage, shipping, and load handling

(PSSH), the PSSH requirements of the SELLER must be approved by the BUYER. Otherwise,

the SELLER shall use the requirements in Section 6.1 for those specified below for the

Condensers.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 21 of 55

Page 22: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-20

3.3.2.1 Transportability and Storage

ASME NQA-1 Part 1 Requirement 13 shall be used in PSSH of Condensers while considering

the following requirements:

a. Condensers shall be individually packed to protect from damage during shipping. A

packaging and shipping plan shall be submitted, see Section 6.1.

b. One copy of the storage procedure shall be attached to the equipment or crate at the time

of shipment. The storage procedure shall cover both short term and long term (over six

months) storage maintenance programs.

UNLESS approved by the BUYER, the SELLER shall meet the transportability and storage in

Section 6.1.

3.3.2.2 Hoisting and Rigging

UNLESS approved by the BUYER, the SELLER shall meet the hoisting and rigging

requirements in Section 6.1.

3.3.2.3 Equipment Handling

UNLESS approved by the BUYER, the SELLER shall meet the equipment handling

requirements in Section 6.0.

3.4 DESIGN AND CONSTRUCTION REQUIREMENTS

Design and assembly activities shall be conducted in accordance with the codes listed in Section

2.0, to the extent evoked by this Specification. The SELLER shall meet or exceed the structural

loads listed in Section 3.3.1.7.

3.4.1 Materials

a. Materials for Condensers shall comply with the requirements of ASME B&PVC,

Section II and VIII, and as specified on the Data Sheets in Appendix A.

b. The Condensers shall be fabricated from 300 Series stainless steel for corrosion

resistance to acetonitrile steam service.

c. All major pressure boundary parts shall be furnished to ASTM material specifications,

and be provided with Certified Material Test Reports (CMTRs) showing compliance with

physical and chemical requirements.

d. Materials used for other parts shall be clearly identified on the Bill of Materials as to

material type and grade; however, CMTRs are not required. Materials shall be

non-asbestos, non-absorbent, and suitable for the chemical and radiation environment in

which they are used.

e. No substitutions shall be allowed unless written approval is provided by the BUYER.

f. No suspect/counterfeit materials shall be used per QA-AVS B76.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 22 of 55

Page 23: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-21

g. Metallic parts shall be of corrosion-resistant metal, or suitably finished to resist corrosion,

except temporary connection material (e.g., connecting ductwork and condensate piping

that can be easily replaced).

h. All other materials used in construction of the Condensers shall be provided with a

Certificate of Conformance/Compliance. Certificates of Conformance/Compliance shall

be traceable to the material used in the fabrication and conform to the requirements in

Section 7.3.4.

i. When specified, only stainless steel that is labeled with a heat number traceable to a

CMTR may be used in the construction of the pressure boundary. SELLER shall verify

that the contents of the CMTR demonstrate compliance with the appropriate ASTM or

ASME material specifications.

j. When the material is subdivided, the SELLER shall transfer the heat number to the part

and remnants using a certified low corrosion marker that has less than 200 ppm total

halogens, less than 200 ppm sulfur, and less than 300 ppm total low melting metals.

SELLER shall provide traceability of the certified marker to the BUYER. This will

ensure that all parts of the original stock piece are traceable. Small parts, such as

couplings, flanges, etc., may be kept in boxes that are labeled with heat numbers. Heat

numbers may be removed from parts or covered when the parts are assembled.

k. Materials shall be free from any defects or imperfections that may affect performance as

verified through qualification and production inspection tests in Section 4.3.1. The

SELLER shall not incorporate any rebuilt or refurbished parts into this assembly.

l. Bronze, copper, lead, zinc, tin, antimony, cadmium, or other low-melting point metals,

their alloys, or materials containing such metals as their basic constituents or

molybdenum, and halogens shall not be used in direct contact with stainless steel, with

the exception or materials used by the SELLER in handling, assembly, and storage of

stainless-steel parts.

m. The SELLER shall submit to the BUYER, for review, all high-strength materials to be

incorporated, and applicable heat treatments.

n. Materials for all structural members may be selected in accordance with AISC Manual as

applicable.

o. Dissimilar metals, such as those defined by MIL-STD-889C, “Dissimilar Metals,” that

have active electrolytic corrosion properties, shall not be used in direct contact.

3.4.2 Bolting

a. Unless otherwise specified, all bolting shall be ASTM A193 GR B7 studs with

ASTM A194-2H heavy hex nuts.

b. Stud bolting shall be one diameter longer than the normal nut engagement.

c. Any fasteners supplied with head marks matching those displayed in Appendix I,

Suspect/Counterfeit Fastener Head Mark List, or facsimiles thereof, shall be deemed

unacceptable under the terms of this Purchase Order/Contract Order.

(Ref. DOE G 414.1-3)

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 23 of 55

Page 24: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-22

3.4.3 Welding

The SELLER shall maintain a complete record of welding materials, including heat number, lot

number, flux and electrode manufacturer used, and shall be made available to the BUYER upon

request.

3.4.4 Gaskets

a. All elastomers used shall be approved by the BUYER. Chemical and physical properties

of the elastomers shall be suitable for the chemical and radiation environment in which

they are used.

b. Gaskets shall be of one-piece construction.

c. Spares: Ship one new and unused gasket per nozzle to be used as spares.

3.4.5 Nameplates and Product Marketing

Each Condenser shall have a legibly marked nameplate permanently attached in accordance with

UG-116 of ASME B&PVC, Section VIII, Division 1.

a. The nameplate shall be 300 Series stainless steel and shall be seal-welded to a 300 Series

stainless steel nameplate bracket.

b. The Condensers shall be Code stamped in accordance with ASME B&PVC, Section VIII,

Division 1.

A supplemental nameplate shall be provided in order to accommodate BUYER-required

information, in addition to Code information, as follows:

a. Manufacturer

b. Date of manufacture

c. Purchase order number of the BUYER

d. Specification number and revision of the BUYER

e. Serial identification number

f. Item Number: 60K-CND-001 or 60K-CND-201, as applicable

g. Differential pressure design

h. Tube material, number, and size of tubes, Birmingham Wire Gauge (BWG) minimum or

average wall, length, and square feet of surface area

i. Minimum design metal temperature and specified vacuum service and temperature

3.4.6 Human Factors Engineering

The SELLER shall design the Condensers for ease of operation and access for maintenance.

3.5 SYSTEM RELIABILITY AND MAINTAINABILITY REQUIREMENTS

This section specifies reliability and maintainability requirements.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 24 of 55

Page 25: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

3-23

3.5.1 Reliability

The Condensers shall be designed for continuous operation for more than 30 years.

3.5.2 Maintainability

Critical equipment, instrumentation, or high maintenance items shall be accessible for ease of

inspection and removal or replacement.

a. The system shall be designed to facilitate maintenance with commercially available tools,

wherever possible.

b. The SELLER shall furnish all special tools unique to the equipment of the SELLER that

are necessary for installation, start-up, operation, maintenance, and adjustment of the

equipment and accessories furnished by the SELLER.

c. The SELLER is to supply spare parts if they require special tooling. SELLER is to

recommend spare parts as part of submittal based on the design life per clause

QA-AVS B82.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 25 of 55

Page 26: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

4-24

4.0 FABRICATION REQUIREMENTS

The fabrication includes equipment procurement, component fabrication, assembly, and

fabrication inspection. The SELLER shall be responsible for the manpower, facilities, and

equipment to complete purchasing, fabrication, assembly, and delivery of the equipment. The

SELLER shall also manage the fabrication activities, which include creating and maintaining

production schedule. The SELLER shall provide all special tools and calibrated equipment

necessary for assembly, operation, and maintenance.

4.1 WELDING REQUIREMENTS

Welding qualifications shall be in accordance with applicable fabrication standards or as

specified by the BUYER. ASME B&PVC Section IX, “Welding and Brazing Qualifications,”

may be used in lieu of these requirements. Weld size and type shall be selected by the Moisture

Separator manufacturer based on applicable loads and system pressure requirements established

within this Specification, and must meet all applicable codes. The SELLER shall adhere to

welding requirements documented in TFC-ENG-,,.

Special care shall be taken to limit contamination of stainless steel components with halides,

which are common to adhesive products. When specified, stainless steel components shall be

cleaned with neutral detergent and water. Equipment shall have a name plate permanently

attached to the top or side of the case.

All weld joints and seams, along the pressure boundaries, shall be 100% continuously welded.

Weld joints and seams shall be wire brushed or buffed after final Nondestructive

Examination (NDE) and inspections as required to remove heat discoloration, oxidation, all

burrs, and sharp edges. For stainless steel material, the wire brush shall not be made of carbon

steel elements or a stainless brush previously used on carbon steel.

4.1.1 Structural Welding

All structural welding shall meet the requirements of the following codes, as applicable and all

welds will be visually inspected per statically loaded American Welding Society (AWS) criteria:

AWS D1.6/D1.6M, “Structural Welding Code – Stainless Steel,” for structural stainless

steel and stainless steel to carbon steel

4.1.2 Weld Materials

All welding filler metals and fluxes used in the fabrication and repair of components shall be in

accordance with the requirements of ASME B&PVC, Sect. II, Part C, “Specifications for

Welding Rods, Electrodes, and Filler Metals” and/or AWS B2.1/B2.1M-BMG, “Base Metal

Grouping for Welding Procedure and Performance Qualification”. Legible CMTRs for all weld

materials shall be submitted to the BUYER.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 26 of 55

Page 27: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

4-25

4.1.3 Welding Procedures and Qualifications

All Welding Procedures and Qualification shall meet the requirements set forth in the applicable

fabrication code.

SELLER shall prepare written Welding Procedures. Welding procedures and performance

qualification shall be in accordance with the codes listed in Section 2.0.

SELLER shall submit copies of all Welding Procedures, Procedure Qualification Records, and

Welder Procedure Qualification Records to be employed in the performance of this

Specification. SELLER shall provide records to indicate that welder/operator is qualified.

The quality control procedures of the SELLER shall include the requirement that no welders

shall have, in their possession, more than one type of filler metal at any one time. An exception

is that welders may have both bare wire and covered electrodes that deposit weld metal of the

same A-number class. The filler metal control procedure of the SELLER shall be submitted and

approved.

All welding performed by the housing manufacturer shall be based on published consensus

standards, such as AWS D1.6/D1.6M and/or ASME B&PV Code, Section IX, or ASME B31.3.

Welder Performance Qualification Records shall be submitted for all personnel performing

welding, including tacking. Welders shall be qualified in accordance with the applicable

fabrication code.

4.1.4 Weld Inspection Requirements

a. Personnel performing visual weld inspections shall be a Certified Welding Inspector

(Minimum Level II) in accordance with the requirements specified in AWS QC1,

“Standard for AWS Certification of Welding Inspectors.” The following documentation

shall be submitted prior to the start of fabrication per QA-AVS B25:

b. Welds shall meet the visual acceptance criteria of codes listed in Section 2.0.

c. NDE processes, required within this purchase order, shall require review and approval of

SELLER:

1. Personnel certification procedure,

2. The NDE operational procedures, and

3. Personnel certifications including current and valid visual acuity examination

(< 1year old). The examination must be performed annually by a certified

medical professional.

d. Per QA-AVS B31, the personnel certification procedure and certification package for

NDE personnel shall accurately reflect the requirements embodied in the applicable issue

of ASNT SNT-TC-1A, “Standard Topical Outlines for Qualification of Nondestructive

Testing Personnel,” plus any other requirements of the SELLER.

e. The NDE operational procedures shall contain all applicable requirements of the

documentation referenced in the purchase order including:

1. Reference standard or image quality indicator information,

2. Chemical purity requirements per QA-AVS B46,

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 27 of 55

Page 28: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

4-26

3. Calibration requirements per QA-AVS B58 and B61, and

4. Report forms, as a minimum per QA-AVS B52.

f. Data packages and changes thereto shall be submitted to the BUYER as identified in the

purchase order.

g. Personnel performing NDE (RT, PT, UT, ET, LT, AC or MT) shall be qualified/certified

to ASNT SNT-TC-1A (Minimum Level II) as identified in the codes listed in Section 2.0.

The recommended practices in ASNT SNT-TC-1A are mandatory requirements for this

purchase order per QA-AVS B31

h. The SELLER will maintain and submit weld history data for each weld per

QA-AVS B13.

4.1.5 Additional Welding Requirements

a. All tools used for stainless steel shall be kept separate from any tools previously used or

currently being used for cleaning carbon steel components. Tools for stainless steel shall

be used only on stainless steel surfaces. Similarly, appropriate controls shall be put into

place to ensure ferrous and non-ferrous material is properly segregated, and that tools

specifically used on non-ferrous material be designated.

b. All areas, from which temporary attachments have been removed, shall be examined by

the liquid penetrant method or magnetic particle method, as applicable, after the surface

has been restored.

c. Preparation for welds shall be by non-thermal methods, where practical.

d. Thermally cut surfaces shall be ground to provide slag-free metal and fit-up equivalent to

machining.

e. Where welding destroys protective plating on hardware items, the weld and surrounding

area shall be thoroughly cleaned, primed, and painted, as appropriate.

f. Where free iron contamination (shows up as rust streaks on stainless steel) is observed,

the surface area shall be cleaned prior to welding.

g. All external supports, support rings, pads, and structural brackets attached to the vessel

shall be seal-welded all around to prevent corrosion between the vessel and attachments.

h. All main seam welds (Category A and B joints) shall be full penetration and, where

possible, double sided.

i. All nozzle-to-shell or head welds (Category D joints) shall be full penetration.

4.2 WORKMANSHIP

Acceptable workmanship shall be based on satisfactory completion of all specified fabrication

inspections.

4.3 CLEANLINESS

All cleaning shall be in accordance with the codes listed in Section 2.0. Before assembly, all

parts shall be clean to the extent that extraneous materials are not present:

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 28 of 55

Page 29: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

4-27

• Combustible dust (shop dust), chips, and turnings,

• Abrasive particles,

• Rust and other loose corrosion products,

• Magnetic/liquid penetrant residues, dye check, etc.,

• Foreign material, such as paper, plastic, and wood,

• Cutting oils,

• Excess lubrication grease and oil,

• Marking dyes, and

• Adhesives.

4.3.1 Material Contamination Control

a. Machining or grinding of stainless steel shall be done with tools that have never come in

contact with materials other than stainless steel.

b. Material-handling devices used for machining, positioning, supporting, welding, etc.,

which come in contact with stainless steel, shall be made of stainless steel. If carbon

steel contamination is evident, the surface shall be ground, and the test shall be repeated

until the contamination is removed. This procedure shall be available at the facility of the

SELLER for the review of the BUYER.

c. When forming stainless plate, care shall be taken to prevent carbon pickup or

contamination of formed material.

4.3.2 Surfaces

a. All wetted surfaces shall be free of features that entrap solids. Sharp burrs or edges

resulting from cutting or machining operations shall be rounded or ground smooth.

b. All nicks and gouges less than or equal to 0.012-in. deep may be removed by blend

grinding. All nicks and gouges greater than 0.012-in. deep shall be filled with weld metal

and ground smooth.

c. If a thermal cutting process is used, the cut surface shall be ground smooth or machined

to remove all adhering slag, gouges, and discoloration, to produce a bright clean surface.

4.3.3 Cleaning

a. The Condenser shall be delivered to the Site clean and free of any oils, tape adhesives,

weld splatter, dirt, loose debris, and other contaminants.

b. Solvents and cleaning solutions used on stainless steels shall not exceed 50 ppm for

chlorides.

c. Mechanical cleaning tools used on stainless steel shall not have been previously used on

carbon steel or any other materials that would contaminate stainless steel surfaces.

1. Wire brushes used for cleaning stainless steel shall be stainless steel, free of dirt

and grease, and either new or only previously used on stainless steel or nickel

alloys, to clean between passes and on completed welds.

2. Grinding wheels used for cleaning shall be stainless steel, new or previously used

only on austenitic stainless steel or nickel alloys.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 29 of 55

Page 30: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

4-28

4.4 TOLERANCES

a. Standard tolerances, for the external dimensions of heat exchangers and for nozzles and

support locations, shall be in accordance with TEMA Standard Figure F-1.

b. Standard tolerances for tubesheets, partitions, covers, and girth flanges shall be in

accordance with TEMA Standard Figure F-2.

4.5 PLATE LAYOUT AND FORMING

a. Shell plates shall be rolled with plate manufacturer serial and heat numbers on the outside

of the vessel. All material shall be identified with the material manufacturer heat

numbers clearly visible during all stages of fabrication and testing.

b. Saddles shall be continuously welded to the shell. Longitudinal weld seams in the shell

shall not be located within 15 degrees of the horn of the saddle, since this is a location of

high stress.

c. Vessel parts that are being joined shall be fitted, aligned, and retained in position during

the welding operation, so that the permissible tolerances are not exceeded in the

completed assembly.

d. Longitudinal seams shall be staggered. Plate layouts shall be arranged so that, to the

maximum extent possible, longitudinal and circumferential weld seams clear all nozzles,

manways, and their reinforcing pads by 2-in. minimum, measured from weld edge to

weld edge.

e. When nozzles must penetrate welds seams, or when nozzle reinforcing pads must cover

weld seams, the seam shall be ground flush and radiographically examined before

welding the nozzle. The seam shall be radiographed per Code Paragraph UW-51.

4.6 LIFTING ATTACHMENTS

a. The welding of Condenser lifting attachments, lifting lugs, or bails shall be performed in

accordance with AWS D14.1.

b. Lifting attachment design shall consider the entire Condenser weight, i.e., including tube

bundle.

4.7 TUBES-TO-TUBESHEET JOINTS

Tube holes in tube sheets shall be deburred by chamfering 1/32-in. maximum on both sides of

the tubesheet.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 30 of 55

Page 31: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

5-29

5.0 PRODUCTION INSPECTION AND TESTING REQUIREMENTS

The entire Condenser assemblies shall be inspected and tested in accordance with the codes

listed in Section 2.0, or BUYER approved equivalent:

a. Test procedures, examinations, and inspections shall be certified, documented, and

submitted for review and approval.

b. The BUYER reserves the right to witness any testing.

5.1 QUALIFICATIONS TESTING REQUIREMENTS

The results of inspections shall be documented and submitted to the BUYER for review and

approval before acceptance.

5.2 INSPECTION

The SELLER shall develop a fabrication, inspection, and test (FIT) plan that sequences the

fabrication operations and denotes the inspection and test points of the SELLER. The FIT plan shall

be reviewed and approved by the BUYER prior to the start of fabrication. At the time of the review

of the FIT plan, the BUYER shall specify all applicable witness and hold points.

The BUYER reserves the right to witness all tests and inspections identified in the FIT plan, and

shall be given a minimum of ten working days written notice prior to each test or inspection date. It

should be noted that third party inspectors may be required to be present during testing/inspections as

the representative for the BUYER or an independent representative for the stakeholders of the

BUYER.

Prior to the performance of tests/inspections, the SELLER shall submit a procedure for each test to

the BUYER, for review and approval. Test/inspection information, recorded or calculated, shall be

documented and submitted to the BUYER.

5.2.1 General

a. The responsibility for inspection rests with the SELLER, and shall be in accordance with

Paragraph UG-90 of the Code and this Specification.

b. Prior to final inspection, the inside and outside of the vessel shall be thoroughly cleaned

and shall be free from all slag, scale, dirt, grit, weld splatter and pieces of metal, paint,

oil, etc. All welds shall be free of slag, oil, grease, paint and other foreign substances that

might prevent proper interpretation of the required tests.

c. The SELLER retains overall responsibility for ensuring, either directly or through

sub-suppliers, that the inspections necessary for conformance to the purchase

specifications are conducted. The performance of quality surveillance by the

representative of the BUYER does not relieve the SELLER or sub-suppliers of

responsibility for meeting the specification requirements.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 31 of 55

Page 32: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

5-30

5.3 EXAMINATION

5.3.1 Condenser

a. Radiographic examination of welded joints shall be performed when required by the

Code. Spot radiography, to obtain a joint efficiency of 85%, is the minimum

requirement.

b. Radiographic examination procedures and acceptance criteria shall be in accordance with

ASME B&PVC Section V, Article 2 and Section VIII, Division 1, Paragraphs UW-11

and UW-52.

c. All radiographs taken during fabrication shall be available for examination by the

BUYER or representative of the BUYER.

5.3.2 Structural

Structural-related items shall be visually inspected in accordance with AWS D1.6/D1.6M.

Acceptance criteria of welds shall be in accordance with requirements for statically loaded

structures in accordance with AWS D1.6/D1.6M, Section 6.29.

5.3.3 Lifting Attachments

Attachment welds as part of lifting lugs or bails, and welds on below-the-hook lifting devices

shall be visually examined in accordance with AWS D14.1, Paragraph 8.6. In addition, perform

either 1) radiographic examination in accordance with AWS D14.1, Paragraph 8.9, or

2) ultrasonic examination and magnetic particle examination in accordance with AWS D14.1,

Paragraphs 8.13 and 8.16, respectively. Document examinations.

5.4 TESTING

5.4.1 General

a. The BUYER reserves the right to witness all tests and shall be given a minimum of ten

working days written notice prior to each test date.

b. The Condensers shall be tested in the horizontal position with suitable support.

c. The gaskets and bolting, used on all flanged connections during pressure testing, shall be

identical to those for operation.

d. All welds shall be cleaned and free of scale prior to hydrostatic testing, to permit proper

examination for defects.

e. Water shall be used for the hydrostatic testing fluid. Water shall be tested for chlorides if

austenitic stainless steel wetted materials are present. The chloride content of the test

medium shall not exceed 20 ppm (by mass) for water temperatures of < 149°F.

f. Test Temperature: Before application of the test pressure, the test water and the vessel

material shall be allowed to equalize to approximately the same temperature.

g. After completion of the hydrostatic test, the vessel shall be drained, dried, and closed as

quickly as practicable.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 32 of 55

Page 33: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

5-31

h. Prior to the performance of testing, the SELLER shall submit the test procedures to the

BUYER for approval. The test procedures shall describe the method and set-up,

including instrumentation for the tests including acceptance criteria.

i. The shell side and the tube side of the Condensers shall be subjected to a pressure test, in

accordance with Paragraph UG-99 of the Code. See design/test pressures in the

datasheets in Appendix A. The test pressure shall be held for 30 minutes.

j. An independent hydrostatic test of the shell-side and the tube-side shall be performed.

k. The test pressure shall be measured at the high point of the vessel in the test position.

l. The final pressure test shall be held for a minimum of one hour.

m. If applicable, nozzle reinforcement pads shall be pneumatically tested at 25 psig.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 33 of 55

Page 34: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-32

6.0 DELIVERY, STORAGE, AND HANDLING

6.1 DELIVERY, STORAGE, & LOAD HANDLING

6.1.1 General

a. All hoisting, rigging, transport, and load handling activities shall comply with

DOE-RL-92-36, RPP-8360 “Lifting Attachment and Lifted Item Evaluation,” and

TFC-ENG-STD-06.

b. SELLER shall receive, clean, package, store, preserve, handle, and ship SSCs to protect

against physical damage, or any effect that would affect quality or cause deterioration, at

all times, while items are located on the premises of the SELLER. Items shall also meet

the requirements of ASME NQA-1-2008/2009A, “Quality Assurance Requirements for

Nuclear Facility Applications,” Part 1, Requirement 13. Classification and packaging will

follow the guidelines of ASME-NQA-1.

c. SELLER shall follow manufacturer recommendation for storage and handling of all

purchased items.

d. SELLER shall submit a PSSH Plan in accordance with QA-AVS B85. The PSSH plan

shall include all plans, procedures, and Drawings that address how items will be

packaged, stored, shipped, and handled in accordance with the requirements described

throughout this Specification, with the exception of topics covered by the Lift and

Rigging Plan described in Section 6.1.4.1

6.1.2 Transportability

All transport activities shall comply with DOE-RL-92-36, RPP-8360, “Lifting Attachment and

Lifted Item Evaluation,” and TFC-ENG-STD-06.

Packaging, Shipping, Receiving, Storage, and Handling shall consider the following

requirements:

a. Units shall be individually packed to protect from damage during shipping.

b. One copy of the storage procedure shall be attached to the equipment or crate at the time

of shipment. The storage procedure shall cover both short term and long term (over six

months) storage maintenance programs.

6.1.3 Packaging

6.1.3.1 Levels of Packaging

The packaging requirements shall be based on the protection that is necessary during shipping,

handling, and storage of the item. Level of packaging requirements shall be in accordance with

protection requirements of NQA-1-2008/2009A, Part 1, Requirement 13. Note: The supplier QA

program is not required to be compliant to NQA-1 and can be based on another nationally

recognized standard as long as it adequately addresses the requirements drawn from NQA-1,

2008 + 1a 2009 addenda.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 34 of 55

Page 35: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-33

6.1.3.2 Cleaning Plan

Prior to packaging an item, debris/contamination shall be removed using SELLER documented

and approved standard procedure, unless specified otherwise. Before delivery to the site, all

items shall be clean to the extent that extraneous materials, such as those listed below, are not

present:

• Metallic or other dusts (shop dust), chips, and turnings,

• Abrasive particles,

• Weld splatter,

• Rust and other loose corrosion products,

• Magnetic/liquid penetrant residues, dye check, etc.,

• Foreign material, such as paper, plastic, and wood,

• Cutting oils,

• Excess lubrication grease and oil,

• Marking dyes, and

• Fluid piping shall be flushed with inhibited water.

6.1.3.3 Cleaning Records

SELLER shall provide cleaning records showing the item has been cleaned, as appropriate, prior

to packaging.

6.1.3.4 Packaging Type

Package type shall provide the level of protection, as required, based on the equipment type.

Containers, crates, and skids shall be used as the foundation methodology for packaging.

6.1.3.5 Packaging Materials

Pressure sensitive tape should be used in lieu of adhesives in contact with bare metal.

6.1.3.6 Packaging Materials Contacting Stainless Steel and Nickel Alloy

Tapes, adhesives, desiccants, or any other packaging materials contacting austenitic stainless

steel and nickel alloy surfaces:

a. Shall not be compounded from, or treated with chemical compounds containing elements

in such quantities that harmful concentrations are leachable, or that they could be released

by breakdown under expected environmental conditions and could contribute to

intergranular cracking or stress corrosion cracking, such as those containing fluorides,

chlorides, sulfur, lead, zinc, copper, and mercury.

b. Paperbacked (masking) tape shall not be used.

c. Upon removal of tape, all residual adhesive shall be removed by wiping with a reagent

grade non-halogenated solvent (acetone, alcohol, or equal).

d. Starch, silicone, and epoxy tape material may be used for tape adhesive if the

requirements of this section are met.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 35 of 55

Page 36: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-34

6.1.3.7 Seal Openings

All equipment openings shall be capped, plugged, or sealed. Clear plastic closures shall not be

used. Activities shall be in accordance with NQA-1-2008/2009A Part 1, Requirement 13 to

prevent entry of foreign material and humidity and protected against corrosion and physical

damage. Note: The supplier QA program is not required to be compliant to NQA-1 and can be

based on another nationally recognized standard as long as it adequately addresses the

requirements drawn from NQA-1, 2008 + 1a 2009 addenda.

a. Flanged openings shall be provided with gasketed closures.

b. Threaded openings shall be provided with steel caps or steel plugs.

c. All tell-tale and vent holes shall be packed with grease, to prevent water infiltration.

Plugs are not permitted.

6.1.3.8 Protection from Corrosion

Items subject to deleterious corrosion shall be protected. Activities shall be in accordance with

NQA-1-2008/2009A Part 1, Requirement 13 (e.g. using either contact-preservatives, inert gas

blankets, or vapor-proof barriers with desiccants to absorb any moisture inside the container).

Note: The supplier QA program is not required to be compliant to NQA-1 and can be based on

another nationally recognized standard as long as it adequately addresses the requirements drawn

from NQA-1, 2008 + 1a 2009 addenda.

6.1.3.9 Unprotected Steel

Uncoated carbon steel (where applicable) and all stainless steel materials shall be wrapped to

prevent exposure during shipment and storage.

6.1.3.10 Shipment Load Protection

All activities shall comply with DOE-RL-92-36, RPP-8360, “Lifting Attachment and Lifted Item

Evaluation,”.

6.1.3.11 Protection from Shock and Vibration

Cushioning, blocking, bracing, and anchoring shall be used where protection from shock and

vibration is required. Activities shall be in accordance with NQA-1-2008/2009A Part 1,

Requirement 13. Note: The supplier QA program is not required to be compliant to NQA-1 and

can be based on another nationally recognized standard as long as it adequately addresses the

requirements drawn from NQA-1, 2008 + 1a 2009 addenda and the protection level as specified.

6.1.3.12 Other Protection

Protect equipment and finishes against impact, abrasion, and other damage

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 36 of 55

Page 37: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-35

6.1.3.13 Protection of Machined Surfaces

Apply a rust preventative coating to machined carbon steel surfaces prior to shipment.

6.1.3.14 Packaging Inspection

Prior to shipment from the facilities of the SELLER, BUYER shall be provided opportunities

(as appropriate) to inspect shipments to assure that products comply with all requirements,

quantities are correct, products are undamaged, and packages are ready for shipment.

6.1.4 Handling

6.1.4.1 Lift and Rigging Plan

All activities shall comply with DOE-RL-92-36, RPP-8360, “Lifting Attachment and Lifted Item

Evaluation,” and TFC-ENG-STD-06.

6.1.4.2 Lift Point Marking

Lift points shall be clearly identified on the equipment.

6.1.4.3 Rated Temperature for Custom Lifting Devices

All custom designed Hanford Site lifting devices shall be rated for cold weather temperature of

10°F or below.

6.1.4.4 Contact with Different Metals

Any item, containing or comprised of austenitic stainless steel or nickel based alloys, shall be

stored, handled, and constructed in a manner that prevents direct contact with materials such as

carbon steel, lead, zinc, copper, mercury, halogenated material, low melting elements, and any

chloride containing material.

6.1.4.5 Critical Welds

All critical welds shall be identified in the design media of the SELLER. For the purpose of this

requirement, critical welds are defined as those welds whose failure could result in loss of load,

or loss of load control.

• All critical welds on lifting devices should be full-penetration welds, if possible.

• Critical welds shall be verified in accordance with Section 4.1.4.

6.1.4.6 Shipping and Handling Drawing

Prior to shipment, the SELLER shall provide detailed handling instructions, including a

dimensioned Drawing for each equipment/assembly, indicating all dimensions and tools

necessary for support, lift, and shipment of the completed equipment. Tolerances for such

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 37 of 55

Page 38: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-36

dimensions shall be noted either on the specific dimension or in general notes. Dimensions

locating centers of gravity shall be generated by SELLER calculation, shall be noted on the

Drawing, and the calculations shall be submitted with the Drawings. These Drawings shall be

provided with the PSSH plan described in Section 6.1.1.

6.1.4.7 Unpacking and Assembly Drawing

SELLER shall provide a dimensioned Drawing that includes receiving instructions, offloading

and unpacking instructions, and on-site assembly instructions (if equipment is shipped in a

disassembled state). These Drawings shall be provided with the PSSH plan described in

Section 6.1.1.

6.1.4.8 Special Lifting Devices

Any special handling devices, needed for assembly or installation, shall be identified and

supplied with the equipment. SELLER provided structural and mechanical lifting devices, as

defined by ASME B30.20, shall conform to the requirements of ASME B30.20 and

ASME BTH-1. Below-the-Hook devices shall be load tested in accordance with ASME B30.20.

All custom designed lifting devices, for use on the Hanford Site, shall be rated in accordance

with environmental conditions of Section 3.3.1.6.

6.1.4.9 Below-the-Hook Device Marking

All activities shall comply with DOE-RL-92-36, RPP-8360, “Lifting Attachment and Lifted Item

Evaluation,” and TFC-ENG-STD-06.

6.1.4.10 Offloading

Offloading at BUYER designated delivery site will be performed by the BUYER or a BUYER

designated representative

6.1.5 Storage

This section contains requirements that shall be fulfilled by the organization responsible for

performing the storage items. These storage requirements only apply after item fabrication has

been completed. Levels and methods of storage are defined to minimize the possibility of

damage or lowering of quality due to corrosion, contamination, deterioration, or physical damage

from the time an item is stored upon receipt until the item is removed from storage and placed in

its final location, is consumed, or is removed for its intended use. Special storage instructions

from the manufacturer, if specified, shall be addressed as part of the storage process for both

short and long term storage of items. Protection level(s) shall be as specified.

6.1.5.1 Level of Storage

Environmental conditions for items shall satisfy protection requirements of NQA-1-2008/2009A

Part 1, Requirement 13. Note: The supplier QA program is not required to be compliant to NQA-

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 38 of 55

Page 39: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-37

1 and can be based on another nationally recognized standard as long as it adequately addresses

the requirements drawn from NQA-1, 2008 + 1a 2009 addenda.

6.1.5.2 Storage Areas

Periodic inspections shall be performed to ensure that storage areas are being maintained in

accordance with applicable requirements.

a. Access to Storage Areas: Access to storage areas for Levels A, B, and C items shall be

controlled and limited only to personnel designated by the responsible organization.

Access to storage areas involving Level D items shall be controlled, as designated, by the

responsible organization.

b. Cleanness and Housekeeping Practices: Cleanness and good housekeeping practices

shall be enforced at all times in the storage areas. The storage areas shall be cleaned, as

required, to avoid the accumulation of trash, discarded packaging materials, and other

detrimental soil.

c. Fire Protection: Fire Protection, commensurate with the type of storage area and the

material involved, shall be provided and maintained.

d. Storage of Food and Associated Items: The use or storage of food, drinks, and salt tablet

dispensers, in controlled storage areas, shall not be permitted

e. Measures to Prevent Entrance of Animals: Measures shall be taken to prevent the

entrance of rodents and other animals into indoor storage areas or equipment, to minimize

possible contamination and mechanical damage to stored material.

6.1.5.3 Storage Methods

a. Ready Access to Stored Items: All items shall be stored in such a manner as to permit

ready access for inspection or maintenance, without excessive handling, to minimize risk

of damage.

b. Arrangement of Items: Items stacked for storage shall be arranged so that racks,

cribbing, or crates are bearing the full weight without distortion of the item.

c. Storage of Hazardous Material: Hazardous chemicals, paints, solvents, and other

materials, of a like nature, shall be stored in well ventilated areas and not within the same

room as the equipment.

d. Identification: Items and their containers shall be plainly marked so that they are easily

identified without excessive handling or unnecessary opening of crates and boxes.

e. Coverings: Weatherproof coverings, when used for outdoor storage, shall be of flame

resistant type sheeting or tarpaulins. They shall be placed to provide drainage and to

ensure air circulation minimizing condensation. They shall be tied down to prevent

moisture from entering and to protect the coverings from wind damage.

f. Outdoor Storage: Items stored outdoors shall be positioned or covered to avoid trapping

moisture in pockets or internally. For example, valves shall be positioned such that water

does not collect under the bonnet, but drains from the valve packing area.

6.1.5.4 Control of Items in Storage

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 39 of 55

Page 40: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-38

6.1.5.4.1 Inspections

Inspections shall be performed and documented, on a periodic basis, to ensure that the integrity

of the item and its container, as provided for under Section 6.1.3 and Section 6.1.5, is being

maintained. Deficiencies noted shall be corrected and documented. The characteristics verified

during this inspection shall include such items as:

• Identification and marking,

• Protective covers and seals,

• Coatings and preservatives,

• Desiccants and inert gas blankets,

• Physical damage, and

• Cleanness.

6.1.5.4.2 Care of Items

Requirements for proper maintenance, during storage, shall be documented in storage records

described by the PSSH plan of the SELLER. Care of items, in storage (includes storage in

place), shall be exercised in accordance with the following:

a. Items in storage shall have all covers, caps, plugs, or other closures intact. Methods used

to seal openings shall be in accordance with Section 6.1.3.9. Covers removed for internal

access shall be immediately replaced and resealed after completion of the purpose for

removal.

b. Temporary preservatives shall be left intact during storage. Should reapplication of

preservatives be required at the site, only those previously approved shall be used.

c. Items pressurized with inert gas shall be monitored at such a frequency as to ensure that

the gas pressure is maintained within specified limits during storage. Desiccant humidity

indicators shall also be monitored, and desiccants shall be changed or reprocessed when

specified.

d. Other maintenance requirements, specified by the manufacturer instructions for the item,

shall be performed.

6.1.5.4.3 Post-Fire Evaluations

In the event that a fire should occur in the storage area at any time, each item, known to have

been heated to an ambient temperature of over 150°F (65°C) or subjected to smoke

contamination, shall be withheld from installation or use until it has been thoroughly examined.

The item must be verified to be in conformance with specified requirements

6.1.5.5 Removal of Items from Storage

Only items, that have been inspected and are considered acceptable for installation or use in

accordance with the associated receiving inspection procedure (if applicable), shall be removed

from storage for installation or use.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 40 of 55

Page 41: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-39

6.1.5.6 Storage Records

Preparation of written records shall include such pertinent information as storage location, results

of inspections, results of in-storage maintenance to include the results of configuration control

activities for the item while in storage, protection requirements, changes in item ownership

including (if applicable) certificates of conformance, and personnel authorized access to the

storage location(s).

6.1.5.7 Additional Storage Requirements

SELLER should refer to the approved PSSH plan for long term storage requirements (if

applicable).

6.1.5.8 Environmental Storage Requirements

SELLER shall specify any additional environmental storage requirements (e.g., temperature

range, humidity, range, protection from precipitation) and required maintenance during storage

(e.g., pump/rotor rotation schedule)

6.1.6 Delivery

All delivery activities shall comply with DOE-RL-92-36, RPP-8360, “Lifting Attachment and

Lifted Item Evaluation,” and TFC-ENG-STD-06.

a. The delivery address, for all equipment, will be designated by the BUYER and defined in

the procurement contract associated with the respective equipment.

6.1.7 Marking for Shipment

a. Marking of items for shipment shall follow the requirements of NQA-1-2008/2009A, Part

1, Requirement 13. Note: The supplier QA program is not required to be compliant to

NQA-1 and can be based on another nationally recognized standard as long as it

adequately addresses the requirements drawn from NQA-1, 2008 + 1a 2009 addenda.

b. All packages shall be clearly and suitably tagged, prior to shipment. All transport

activities shall comply with DOE-RL-92-36, RPP-8360, “Lifting Attachment and Lifted

Item Evaluation,” TFC-ENG-STD-06, and include the following:

1. Temporary marking of items for shipment not within a container, such as pipe,

tanks, and heat exchangers, shall exhibit the above specified information in a

location that is in plain unobstructed view. Marking may be applied directly to

bare metal surfaces, provided it has been established that the marking material is

not deleterious to the item. Stamping and etching are not allowed as temporary

marking methods.

2. If any hazardous chemicals are included with shipments, the transport vehicle

shall display the relevant Department of Transportation labels/placards.

c. For shipment packaging list requirements, refer to Section 6.1.3.

d. Package markings shall appear on a minimum of two sides of a container, preferably on

one side and one end.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 41 of 55

Page 42: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

6-40

e. Package markings shall be applied with waterproof ink or paint in characters that are

legible. When information relative to handling and special instructions is required, such

information shall be preceded by the word “CAUTION” in letters that are at least

1/2 in. (12.7 mm), as permitted by package size. Alternatively, if tags or labels are used,

they shall be affixed to the container using a waterproof adhesive, tacks where practical,

or a corrosion-resistant wire.

f. Temporary supports shall be marked (tagged or painted).

g. Clearly mark partial deliveries of component parts of equipment to identify equipment

and contents, permitting easy accumulation of parts and facilitating assembly.

6.2 QUALITY ASSURANCE

Quality Assurance (QA)requirements have been interspersed through this Specification, where

appropriate. Regarding “Delivery, Storage, and Handling,” QA-AVS B85 shall be invoked,

where appropriate. At a minimum, a hold point shall apply “Prior to Packaging/Shipping.” At a

minimum, Quality Level (QL-3) must be used for all hoisting and rigging procurements. The

SELLER shall provide required notifications of verification points, and shall not proceed past

required hold point without written authorization from the BUYER.

6.3 SITE CONDITIONS

a. Storage condition requirements are specified in Section 6.1.5.

b. During delivery, all equipment may be exposed to the outdoor/environmental conditions

specified in Section 3.3.1.6.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 42 of 55

Page 43: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

7-41

7.0 PROJECT MANAGEMENT

7.1 WORK PLAN

A work plan covering design, fabrication, testing, and submittal schedule dates shall be provided.

Any changes to the work plan will require written concurrence of the BUYER.

7.2 SUBMITTALS

Unless specified otherwise, submittals of the SELLER shall be per the following subsections.

All electronic submittals shall be in a suitable format per TFC-BSM-IRM_DC-C-02, “Records

Management,” and in compliance with TFC-BSM-IRM_DC-C-07, “Vendor Processes.”

Washington State Professional Engineering stamps are anticipated to be needed for several of the

design deliverables to support permitting. Stamped deliverables will be agreed on during the

kickoff meeting.

7.2.1 Submittals Required with Proposal

Table 7-1. Submittals Required with Proposal.

Item Title Description

1 Preliminary Drawing and

Documentation List

List of Drawings and documentation that will be

provided in completion of the contract.

2 Conceptual Layout

Drawings

The SELLER shall submit conceptual equipment

layout Drawings for the proposed Condenser units.

3 Preliminary System

Performance Analysis

The SELLER shall provide a preliminary system

performance evaluation, including equipment sizing

analysis, consistent with the performance

requirements identified in this specification.

4 Quality

Assurance Program

Copy of SELLER Quality Assurance Program.

5 Identification

of Subcontractors

List of all proposed subcontractors. The SELLER

shall flow down all requirements to subcontractors,

as applicable.

6 Preliminary Schedule Summary of activities required to design, fabricate,

test, and ship the Condensers.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 43 of 55

Page 44: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

7-42

7.2.2 Submittals Required After Receipt of Order

Table 7-2. Submittals Required After Receipt of Order.

Item Title Description

7 Configuration Drawing Drawings detailing all major components and

orientation:

• Preliminary cross-section Drawing showing the

details of the proposed equipment (bundle

details, baffle locations, number of passes, and

number of tubes), with Bill of Materials.

• Preliminary Condenser outline Drawing with

location, orientation, and size of nozzles, and

major dimensions of the unit.

• Preliminary saddle support concept and anchor

details.

8 Preliminary System

Performance Analysis

Preliminary performance evaluation, including

equipment sizing analysis and Condenser performance

data, shell-side and tube-side pressure drop, and heat

transfer.

9 Code Deviations All deviations to the codes specified within this

Specification shall be clearly identified and must be

approved with submittal.

10 Work Plan A work plan shall be submitted per Section 7.1.

11 Detailed Schedule A detailed schedule showing the activities required to

design, fabricate, test, and ship the Condensers including

submittals and major procurements (long lead items).

7.2.3 Submittals Required Prior to Fabrication

Table 7-3. Submittals Required Prior to Fabrication (2 Pages).

Item Title Description

12 Fabrication Drawings All fabrication and assembly Drawings, including

manufacturer standard details associated with the

fabrication and assembly Drawings, shall be submitted.

Drawings shall include dimensions, required

maintenance clearances, part number callouts, associated

ASTM standard, all connection sizing and locations,

welding, and operating weight.

13 Factory Test

Procedures

FIT Plan and Test procedures shall be submitted for

review and approval for all factory tests, per

QA-AVS B52.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 44 of 55

Page 45: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

7-43

Table 7-3. Submittals Required Prior to Fabrication (2 Pages).

Item Title Description

14 Vendor Data Sheets SELLER shall submit product data and rated

capacities/efficiencies of selected equipment and

accessories.

15 System Performance

Analysis. Stress and

Structural Analysis

Calculations

SELLER shall provide a system performance evaluation,

including equipment sizing analysis, indicating

compliance with the performance requirements identified

in this Specification.

16 Welding and NDE All Welding and NDE Procedures, as well as Procedure

Qualification Records, shall be submitted by the

SELLER in accordance with Section 4.1, per

QA-AVS B31, B25, and B28.

17 Authorization to Start

Fabrication

The SELLER shall not start fabrication until written

authorization has been received from the BUYER.

18 Packaging, Storage,

Shipping, and Load

Handling Plan

SELLER shall submit a PSSH Plan, for approval, by the

BUYER. The PSSH plan shall include all plans,

procedures, and Drawings that address how items will be

packaged, stored, shipped, and handled in accordance

with the requirements described throughout this

Specification. The plan shall be prepared per

Section 6.1.

19 Cleaning Records During/after fabrication and prior to packaging and

shipment, cleaning records must record cleaning

performed according to cleanliness level as specified in

Section 4.3 of this Specification.

20 Lifting and Rigging

Plan

SELLER shall provide a Lift and Rigging Plan to cover

the lifting and handling instructions for each lifted item

(entire package as well as individual items that are

uncrated). The plan shall describe the lift points, special

lifting devices, and/or hardware needs, and lift diagrams.

21 Site Assembly

Instructions

SELLER shall provide site assembly instructions,

including unpacking and installation Drawings.

22 Calculations Preliminary calculations shall be provided for review.

Calculations may include (but are not limited to)

structural calculations, lifting lug calculations, pressure

design, thermal design, and Condensers performance.

23 FIT Plan The SELLER shall submit a FIT Plan that sequences the

fabrication operations, inspections, and test points to the

BUYER for review and approval.

7.2.4 Submittals Required Prior to Shipping

The SELLER shall not ship the Condensers until all tests and inspections are performed and the

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 45 of 55

Page 46: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

7-44

documentation data package is complete and approved by the BUYER. The SELLER shall

notify the BUYER three weeks before the intended shipping date. The SELLER shall allow the

BUYER one week after receiving the package and before shipment to review the data package.

Table 7-4. Submittals Required Prior to Shipping (2 pages).

Item Title Description

24 As Built Drawings and

Specifications

The SELLER shall deliver, to the BUYER, one hard

copy and one electronic file in PDF format of the final

fabrication level as-built Drawings and specifications

accurately depicting the product delivered. Drawings

shall include dimensioned subassemblies, dimensioned

component details, material and fastener size, gasket

and insulation materials and thicknesses, descriptions,

weld symbols, center of gravity, references to

applicable ASTM/ASME Standard and Edition, and

notes. The designer name, responsible engineer name,

bill of materials, and Drawing number shall appear on

the index (cover sheet).

Drawings shall also include:

• Design pressure, test pressure design

temperature, minimum design metal

temperature, and any restriction on operation of

the heat exchanger.

• Interface connection details, including size, type

of connection and location, direction of flow,

and flange ratings.

• The dimensions, orientation, and location of

supports, including bolt holes and slots.

• Tube layout, number of tubes, number of baffles

dimensioned layouts.

25 Final Calculations Reviewed and approved calculations shall be legible

and prepared on 8 1/2 inch by 11 inch sheets with all

pages numbered and bound in a hard copy binder.

26 Inspection and Testing

Reports

Inspections, examinations, testing, and NDE activities

shall be documented and the documentation delivered

before shipment of the product. Inspection reports shall

provide actual inspection results, specifying what was

inspected, who inspected it, the characteristics that

were inspected, and the acceptance criteria. A thermal

performance and vibration report shall be submitted.

All test requirements called out in specification(s) and

fabricator Drawings shall be documented in the testing

reports.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 46 of 55

Page 47: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

7-45

Table 7-4. Submittals Required Prior to Shipping (2 pages).

Item Title Description

27 Certified Material Test

Reports

CMTRs shall be provided for the Condenser

assemblies, per QA-AVS B49.

28 Welding Inspection Welding documentation shall meet QA-AVS B28 and

submitted in accordance with the requirements of

Section 4.1.4, prior to shipping.

29 Procedures for Repair The SELLER shall submit the procedures for repairs

of rejected items or parts.

30 Spare Parts List The SELLER shall provide a list of all spare parts,

identifying each specific subassembly to which it

applies.

31 Certificate of Conformance The Certificate of Conformance shall identify the

contract requirements met per QA-AVS B79 and

include a Suspect/Counterfeit Items statement per QA-

AVS B76

32 Completed FIT Plan The SELLER shall provide a completed FIT Plan that

includes inspections, examinations, testing and NDE

activities and the documentation delivered before

shipment of the product. Inspection reports shall

provide actual inspection results, specifying what was

inspected, who inspected it, the characteristics that

were inspected, and the acceptance criteria. All test

requirements called out in specification(s) and

fabricator drawings shall be documented in the testing

reports.

33 Manufacturer’s Data

Reports

ASME Section VIII, Division 1 required

Manufacturer’s Data Report.

34 Warranty Information The SELLER shall provide their warranty offer.

7.2.5 Request for Information

Any changes shall be submitted per the RFI process requirements detailed in

TFC-BSM-IRM_DC-C-07, “Vendor Processes.”

7.3 QUALITY ASSURANCE PROGRAM

The BUYER reserves the right to verify the quality of work at the facility of the SELLER,

including any sub-tier facilities. Access to sub-tier facilities shall be requested through the

SELLER and verification may be performed jointly with the SELLER. Seller shall have a

documented and implemented Quality Assurance Program that has an ASME B&PVC U Stamp

Certification.

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 47 of 55

Page 48: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

7-46

7.3.1 Non-Conformance Reports

Non-Conformance Reports identified at the facility of the SELLER or lower-tier subcontractor,

associated with this Procurement Specification, with a proposed disposition of “Accept as is” or

“Repair,” shall be submitted to and approved by WRPS Engineering and QA, before the

Subcontractor takes any corrective action on the nonconformance. Submittals must conform to

QA-AVS B22.

7.3.2 Inspection/Examination

The SELLER shall include the qualifications of the inspectors for all critical items or features

identified from the design.

7.3.3 Suspect/Counterfeit Items

Procurement of genuine, new, and unused parts shall conform to QA-AVS B76, “Procurement of

Potentially Suspect or Counterfeit Items.”

7.3.4 Certificate of Conformance

Objective evidence, in the form of a written document for all parts procured, shall be provided by

the SELLER. Documentation shall be in the form of a Certificate of Conformance or CMTR.

Certificates of Conformance shall be traceable to the material used in the fabrication, as required

by the codes listed in Section 2.0, and shall fulfill the requirements of NQA-1, Requirement 7,

and Paragraph 503, “Certificate of Conformance.” Note: The supplier QA program is not

required to be compliant to NQA-1 and can be based on another nationally recognized standard

as long as it adequately addresses the requirements drawn from NQA-1, 2008 + 1a 2009

addenda. Documentation shall conform to QA-AVS B79, “Certificate of Conformance.”

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 48 of 55

Page 49: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

A-47

APPENDIX A

HEAT EXCHANGER DATA SHEETS

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 49 of 55

Page 50: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

A-48

HEAT EXCHANGER SPECIFICATION SHEET

1 Project No.

2 Customer: Washington River Protection Solutions Reference No.

3 Address: Proposal No. Rev. 0

4 Plant Location Hanford, WA Date 12/10/2020

5 Service of Unit Stripper Overheads Condenser Item No. 60K-CND-001

6 Size: Type: S&T Vertical X Horiz. Connected In Parallel Series

7 Surf./Unit (Gross/Eff.) Sq Ft; Shells/U Surf/Shell (Gross) Sq Ft

8 PERFORMANCE OF ONE UNIT

9 Fluid Allocation Shell Side Tube Side

10 Fluid Name

11 Fluid Quantity, Total Lb/Hr

12 Vapor (In/Out)

13 Liquid (In/Out)

14 Steam (In/Out)

15 Water (In/Out)

16 Noncondensable (In/Out)

17 Temperature (In/Out) °F

18 Density @ Cond. Lb/Ft3

19 Viscosity, Vapor/Liquid Cp

20 Molecular Weight, Vapor/Liquid

21 Mol Wt, Noncondensable

22 Specif ic Heat, Vapor/Liquid BTU/Lb °F

23 Thermal Conductivity BTU/Ft/Hr Sq Ft°F

24 Latent Heat BTU/Lb @F

25 Inlet Pressure Psig

26 Velocity Ft/Sec

27 Pressure Drop, Allow /Calc Psi

28 Fouling Resistance (Min) Hr Sq Ft °F/BTU

29 Heat Exchanged BTU/Hr; MTD (Corrected) °F

30 Transfer Rate, Service Clean Actual BTU/Hr-Sq FT°F

31 CONSTRUCTION OF ONE SHELL Sketch (Bundle/Nozzle Orientation)

32 Shell Side Tube Side

33 Design/Test Pressure Psig 150 / 195 150 / 195

34 Design Temperature / C.E.T °F 400 / 400 /

35 No. Passes per Shell See Attached Sketch

36 Corrosion Allow ance In.

37 Connections In

38 Size Out

39 & Rating Non-condensible gas vent

40 Tube No. OD = In;Thk(Min/Av) 18ga min In.;Length Ft.;Pitch in. 30 60 90 45

41 Tube Type Finned Bare U-Tube Tube Material

42 Shell ID in. OD In. Shell Cover (Integ.)(Remov.)

43 Channel or Bonnet Channel Cover

44 Tubesheet-Stationary Tubesheet-Floating

45 Floating Head Cover Impingement Protection

46 Baffles-Cross Type % Cut (Diam) (Area) Spacing:c/c Inlet in.

47 Baffles- Long Seal Type

48 Supports-Tube U-Bend Type

49 Bypass Seal Arrangement Tube-Tubesheet Joint

50 Expansion Joint Type

51 r v2 - Inlet Nozzle Bundle Entrance Bundle Exit

52 Gaskets-Shell Side Tube Side

53 - Floating Head

54 Code requirements ASME Stamp TEMA Class B

55 Weights/Shell Filled w ith w ater Bundle Lb

56 Remarks:

57

58

59

60

61 304L stainless steel tubes and tube side components.

62 304L stainless steel construction balance of unit.

63 Commercial/industrial unit, mill f inish as-w elded.

64 1" 3000# NPT coupling shell vent connection.

65 Vendor to furnish or confirm data in lines 40 through 55.

DESIGNED BY: CHECKED BY: DATE

PRQ RBH 12/10/2020

60K-CND-001 is a total condenser. Condensed liquid temperature is an

estimate. Vendor to design for 20% excess area, not counting the

U-portion of the tubes.

10 /

0.0005

4,426,003

0.037

Minimum Design Internal Pressure is for a Full Vacuum.

1

6-in. / 300# / Flange

1.5-in. / 150# / Flange

6-in. / 150# / Flange

6-in. / 150# / Flange

1.0-in / 300# / Flange

0.06 inch

4,551

/

0.001

0.0123

0.451

0.0144

214

0

211

530,387

0.392

4,551

47

59.8

0.28

0.78

0.24

972

0.77

0.24

1.007

4,551 530,387

Stripper Overheads Cooling Water (50 vol% Eth. Glycol)

57

67

4.8

530,387

67

5.8

• U ----

T1 . E1 .1 UTr7

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 50 of 55

Page 51: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856

Revision 0

A-49

HEAT EXCHANGER SPECIFICATION SHEET

1 Project No.

2 Customer: Washington River Protection Solutions Reference No.

3 Address: Proposal No. Rev. 0

4 Plant Location Hanford, WA Date 12/10/2020

5 Service of Unit Concentrator Overheads Condenser Item No. 60K-CND-201

6 Size: Type: S&T Vertical X Horiz. Connected In Parallel Series

7 Surf./Unit (Gross/Eff.) Sq Ft; Shells/U Surf/Shell (Gross) Sq Ft

8 PERFORMANCE OF ONE UNIT

9 Fluid Allocation Shell Side Tube Side

10 Fluid Name

11 Fluid Quantity, Total Lb/Hr

12 Vapor (In/Out)

13 Liquid (In/Out)

14 Steam (In/Out)

15 Water (In/Out)

16 Noncondensable (In/Out)

17 Temperature (In/Out) °F

18 Density @ Cond. Lb/Ft3

19 Viscosity, Vapor/Liquid Cp

20 Molecular Weight, Vapor/Liquid

21 Mol Wt, Noncondensable

22 Specif ic Heat, Vapor/Liquid BTU/Lb °F

23 Thermal Conductivity BTU/Ft/Hr Sq Ft°F

24 Latent Heat BTU/Lb @F

25 Inlet Pressure Psig

26 Velocity Ft/Sec

27 Pressure Drop, Allow /Calc Psi

28 Fouling Resistance (Min) Hr Sq Ft °F/BTU

29 Heat Exchanged BTU/Hr; MTD (Corrected) °F

30 Transfer Rate, Service Clean BTU/Hr-Sq FT°F

31 CONSTRUCTION OF ONE SHELL Sketch (Bundle/Nozzle Orientation)

32 Shell Side Tube Side

33 Design/Test Pressure Psig 150 / 195 150 / 195

34 Design Temperature / C.E.T °F 400 / 400 /

35 No. Passes per Shell See Attached Sketch

36 Corrosion Allow ance In.

37 Connections In

38 Size Out

39 & Rating Non-condensible gas vent

40 Tube No. OD = In;Thk(Min/Av) 18ga min In.;Length Ft.;Pitch in. 30 60 90 45

41 Tube Type Finned Bare U-Tube Tube Material

42 Shell ID in. OD In. Shell Cover (Integ.)(Remov.)

43 Channel or Bonnet Channel Cover

44 Tubesheet-Stationary Tubesheet-Floating

45 Floating Head Cover Impingement Protection

46 Baffles-Cross Type % Cut (Diam) (Area) Spacing:c/c Inlet in.

47 Baffles- Long Seal Type

48 Supports-Tube U-Bend Type

49 Bypass Seal Arrangement Tube-Tubesheet Joint

50 Expansion Joint Type

51 r v2 - Inlet Nozzle Bundle Entrance Bundle Exit

52 Gaskets-Shell Side Tube Side

53 - Floating Head

54 Code requirements ASME Stamp TEMA Class B

55 Weights/Shell Filled w ith w ater Bundle Lb

56 Remarks:

57

58

59

60

61 304L stainless steel tubes and tube side components.

62 304L stainless steel construction balance of unit.

63 Commercial/industrial unit, mill f inish as-w elded.

64 1" 3000# NPT coupling shell vent connection.

65 Vendor to furnish or confirm data in lines 40 through 55.

DESIGNED BY: CHECKED BY: DATE

PRQ RBH 12/10/2020

60K-CND-201 is a total condenser. Condensed liquid temperature is an

estimate. Vendor to design for 20% excess area, not counting the

U-portion of the tubes.

96 10,747

Concentrator Overheads Cooling Water (50 vol% Eth. Glycol)

57

67

4.8

10,747

0.78

0.24

0.77

0.24

1.007

10,747

47

67

5.8

96

96

/

0.001

0.0121

0.446

0.014

213

0

211

0.039

Minimum Design Internal Pressure is for a Full Vacuum.

1

2-in. / 300# / Flange

1.5-in. / 150# / Flange

1.5-in. / CL3000 / NPT

1.5-in. / CL3000 / NPT

1.0-in / 300# / Flange

972

0.06 inch

0.392

59.8

0.28

10 /

0.0005

93,330

PciNo

II II I I

F

I I

. Lurdy

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 51 of 55

Page 52: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856 Revision 0

B-50

APPENDIX B

LARGE CONDENSER GENERAL ARRANGEMENT DRAWING 60K-CND-001

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 52 of 55

Page 53: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

LARGE CONDENSERSCALE: 1/4

LARGE CONDENSER SUPPORTSCALE: 1/4

A SKETCH PER RPP-SPEC-63856

NOZZLE SCHEDULENOZZLE QTY SIZE/INCHES RATING FUNCTION

N1 1 6 CL150 RF TUBE SIDE INLET

N2 1 6 CL150 RF TUBE SIDE OUTLET

N3 1 6 CL300 RF SHELL SIDE INLET

N4 1 1 1/2 CL150 RF SHELL SIDE OUTLET

N5 1 1 CL300 RF SHELL SIDE VENT

N1

N4

N3N2N2 N5 N3

N1 N4

NOTES:1. DIMENSIONS ARE IN INCHES, TOLERANCES SHALL BE ±1/16.

LARGE CONDENSER SUPPORTSEE DETAIL2 PL

6

(15 7/16)

20 15/16

28 9/16 20

68 15/16

75 7/16

N5

13

TYP

13 10 3/8

10

22

11

(6)

(4)

(2) 18

(1 3/4)

11/16 THRU2 PL

(ANGLE, 6 X 4 X 5/16ASTM A276)

RPP-SPEC-63856 Rev 0

B-51

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 53 of 55

Page 54: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

RPP-SPEC-63856 Revision 0

C-52

APPENDIX C

SMALL CONDENSER GENERAL ARRANGEMENT DRAWING 60K-CND-201

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 54 of 55

Page 55: Release Stamp DOCUMENT RELEASE AND CHANGE FORMRPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 8 of 55. RPP-SPEC-63856 Revision 0 1-7 1.0 SCOPE This Procurement Specification (hereafter

SMALL CONDENSERSCALE: 1/2

SECTION A-ASCALE: 1/2(TYP, 2 PL)

A A

A SKETCH PER RPP-SPEC-63856

NOZZLE SCHEDULENOZZLE QTY SIZE/INCHES RATING FUNCTION

N1 1 1 1/2 FNPT TUBE INLET

N2 1 1 1/2 FNPT TUBE OUTLET

N3 1 2 CL300 RF SHELL INLET

N4 1 1 1/2 CL150 RF SHELL OUTLET

N5 1 1 CL300 RF SHELL VENT

N5N3

N4

N5 N3

N4

NOTES:1. DIMENSIONS ARE IN INCHES, TOLERANCES SHALL BE ±1/16.

1 1/8

2 1/4

6 1/4

TYP

6 1/2

N2

N1

40

36 9/16

10 9/16 16 1/4

6 9/16

(2 1/16)

2 1/2

1 1/8

(3/4)

4 1/2

(6)

RPP-SPEC-63856 Rev 0

C-53

RPP-SPEC-63856 Rev.00 12/10/2020 - 12:40 PM 55 of 55