Upload
chacha420
View
217
Download
0
Embed Size (px)
Citation preview
8/13/2019 Rental Power Projects
1/19
FACTS & FIGURES BEHIND THE
SCANDAL
BILAL IFTIKHAR ERP# 05854
RENTAL POWER PROJECTS
8/13/2019 Rental Power Projects
2/19
PRESENTATION OUTLINE What is RPP?
What was the need of RPP in Pakistan?
Brief history of the contracts &procedure
Corruption in RPP,,, Truth or Lie!!!!!
Verdict by Supreme court Conclusion
Q & A
8/13/2019 Rental Power Projects
3/19
INTRODUCTION TO RPP RPPs are used to meet short term
energy requirements. They are mostlyused as temporary energy source
providers. They are typically commissioned on
4~6 moths basis based on availabletechnology.
Rental periods are normally installedfor 5 ~ 7 years depending upon thecountry requirement.
8/13/2019 Rental Power Projects
4/19
INTRODUCTIONTO RPP The rental power business has been
around for decades, but it has gainedlarger publicity in the midst and
aftermath of the power shortages andtransmission problems that plaguedCalifornia in USA and other places, Asianand African Block including South WestAsia (India and Pakistan) during 2002
onwards. Utilities scrambled forsupplemental power to compensate forinadequate transmission capacity,inadequate power generation capacity,and during severe weather conditions.
8/13/2019 Rental Power Projects
5/19
INTRODUCTION TO RPP Rental power plants have been set up in
the US, UK, India, Bangladesh, Kuwait,
Sri Lanka, Turkey, UAE, Saudi Arabia,Iraq and Palestine & now in Pakistan as
well.
The concept was introduced in Pakistan
in 2007 when two projects were awarded
to GE and APR, both from the US for
150MW and 136MW each.
8/13/2019 Rental Power Projects
6/19
WHATWAS THE NEED??? Severe Energy Crisis : Electricity Crisis in Pakistan is one of the
severe challenges the country is facing today.
Electricity is essential part of our daily life andits shortage has severely affected the economy
and overall living of ours. Pakistan is currently
facing up to 18 hours of electricity outage a day,
is expected to face more if not dealt with intime.
Current Energy Annual Shortfall goes even up to
6,000 MW. Annual Increase in Energy Demand:
8-12%. Peak Demand: 13,000 18,000 MW.
8/13/2019 Rental Power Projects
7/19
ADVANTAGES OF RPP Short Term solution for emergency requirement
accepted internationally.
No long duration commitments as in the case of
IPPs. Quick delivery of power due to short construction
period.
Services acquired without buying the equipment.
High availability matching that of new IPPs.
Supplemental power to compensate forinadequate transmission capacity.
Installation in a much smaller area, thus could beinstalled at choice stations.
8/13/2019 Rental Power Projects
8/19
INCEPTION OF RPPS IN P KIST N In 2006, when the energy short fall was 1000 MW,
the GOP decided to overcome this with RPP & twoagreements of 150 MW & 136 MW were made.
Process for Award of GE Energy and Alstom PowerRentals:
Two Rental Power Proposals received on13.07.2006 from GE & Alstom.
GE and APR proposals summarized below
150 MW GE Energy Rentals: 10% Advance Payment against Advance Bank
Guarantee. Monthly Advance Payment of 1% forfirst 4 rental months. Balance 86% in 36 equalMonthly Rental Services Fee. Confirmed andirrevocable Drawdown Letter of Credit.
8/13/2019 Rental Power Projects
9/19
INCEPTION OF RPP IN PAKISTAN136 MW Alstom Power Rentals:
7% Advance Payment against AdvanceBank Guarantee. Balance 93% in 36 equal
Monthly Rental Services Fee. Confirmedand irrevocable Stand By Letter of Credit
ECC approved the proposals on16.08.2006 as an emergency measure.
Subsequent to WAPDA approval,Contracts signed on 18.09.2006 withAlstom and on 23.09.2009 with GE.
NEPRA approved the Rental Tariff for thetwo projects on 15.12.2006.
8/13/2019 Rental Power Projects
10/19
PROCEDURE FOR CCQUIRING RPPS
Advertisements in leading newspapers of the country.
Registration and issuance of Request for Proposal (RFP)
Pre-bid meeting(s)
Bid Receipts
Opening of Qualification and Technical Bids (Envelope-1)
Evaluation of Qualification and Technical Bids.
Final Notification of Responsive Bidders.
Opening of Financial and Tariff Bids (Envelope-II) of responsivebidders.
Approval of Evaluation Report by GoP. Notification of Qualified Bidders.
Issuance of LoA.
Subsequent to issuance of LoA the concerned GENCO finalizes
8/13/2019 Rental Power Projects
11/19
RPPS TH T H VE BEEN INST LLED
8/13/2019 Rental Power Projects
12/19
ONGOING PROJECTS
8/13/2019 Rental Power Projects
13/19
CORRUPTION IN RPPS Favoritism in the awarding of contracts.
220 Mln scam was recorded by transparencyinternational in RPPs(Karkey).
Karkey was allowed to leave Pakistan withoutthe payment of money which it received asdown payment. It came into operation 9 monthlate then the original date adding only 60MW outof 232 MW.
Huge loss caused to national treasure byincreasing down payment from 7% to 14 % .
Extremely expensive then all other energysources.
8/13/2019 Rental Power Projects
14/19
CORRUPTION IN RPPS Duty on the import of these machines & equipment
was completely waived off. This caused huge lossto the national treasure.
Double payment of down payment because of thesite shift in Nodairo Welfare power international.This money was later on recovered.
In 2006, WAPDA officials offered sponsors forproduction of energy illegally by breaking rules, &
national treasure had to face loss due to this. No RPP met the production efficiency requirement,
but their licenses were not cancelled.
Changes were made in the LC in terms &conditions at the eleventh hour.
8/13/2019 Rental Power Projects
15/19
CORRUPTION IN RPP For one plant machinery was bought once
but charged twice similarly no one went
to audit the equipment imported at one of
the RPP hence the equipment was
declared faulty and new ones had to be
bought again.
ADB disapproved this projects stating
that this will result in an increase of 31-45% of electricity charges and will be
burdensome to foreign exchange
reserves but still these plants were
imported.
8/13/2019 Rental Power Projects
16/19
VERDICT BY SC Issue was taken to SC by Faisal Saleh Hayat
&Khawaja M Asif, then SC took suo motto action
as fundamental right of people was being
violated. Chief justice along with other justice heard the
case & ordered the cancellation of contracts of
RPPsbecause of the fraud in this matter.
SC held Wapda, Genco & Pepco & financeministry responsible for loss to national treasure
because they increased down payment &
ordered them to recover the down payment &
loses with interest.
8/13/2019 Rental Power Projects
17/19
VERDICT BY SC SC held the ministers & secretaries of
the duration (2006~2008) which wereinvolved in corruption responsible &
ordered to take action against themaccording to NAB Ordinance 1999.
SC further ordered chairman NAB that allofficers which took financial benefits ,
action shall be taken against themaccording to law & a report shall besubmitted for the courts review twice amonth.
8/13/2019 Rental Power Projects
18/19
CONCLUSION SUGGESTIONS In the light of all the facts & figures
presented above, it is evident thathuge corruption has been found in
RPP case. SC has given its verdict, now itsthe
duty of GOP to punish these corruptpeople.
Now the GOP should look forcheaper & more practicalsubstitutes for energy production &should find a long term alternative.
8/13/2019 Rental Power Projects
19/19
Q & A