PROJECT :
Causes , Prevention And Repair
Of Crack In Building
Project Member : Supervisor :
JHANGIR KHAN Engr: Qaiser Jamal
MUHAMMAD RAHIM
SALMAN LATIF
MUJAHID NAZEEF
8/13/2019 repair of crack
2/6
2
Scheme of presentation
Introduction Purpose Classification of crack Causes of crack Prevention of crack Repair of crack Conclusion
8/13/2019 repair of crack
3/6
3
INTRODUCTION :
CRACK:
A crack is a complete or incomplete separation of
concrete into two or more parts, produced by breaking or
fracturing.
Purpose:
The main purpose of this project is to increase life
period of building , to improve aesthetic and architecture
appearance of building.
CLASSIFICATIONOFCRACKS:
A. Structural Cracks:
1.Due to incorrect design2.Faulty construction3.Overloading
B. Non-Structural Cracks:
1.Moisture changes2.Thermal movement
8/13/2019 repair of crack
4/6
4
3.Elastic deformation4.Creep5.Chemical reaction6..Foundation movement and settlement of soil7.Vegetation
CAUSES OF CRACK:
1.Chemical reaction in construction material.2. Temperature and shrinkage effects.3.Settlement of ground.4. Faulty workman ship and poor construction practice .5. Environmental stresses.
6. Bad quality material.
Prevention of Crack:
1. Drainage arrangement should be made around the
building to minimize water entry in the foundation.
2. Avoid construction of wall on filled up soil.
8/13/2019 repair of crack
5/6
5
3. Avoid trees grows too close to building and compound
wall.
4. Good selection of material.
5. Specification for mortar and concrete.
6. Good construction practices.
7. Due consideration to Weather effect.
Repairofcrack:
The repair for cracks may be undertaken after ascertaining
the reasons for the appearance of the crack. A few basic
principles if followed will be more effective
1. Rendering of minor crack less that 1m wide may be done
after observing the crack for some time and then sealing it
with weak mortar of cement, lime and sand.
2. Cracks where width change with season should be filled
up with elastic fillers like silicon etc.
3. Where sheer crack are observed shear keys made of RCC
concrete with at least 1.5 percent steel vein forcemeat may
be provided at 1 to 1.5m intervals.
4. If cracks are due to movement of soil in black cotton once,
prevention of moisture penetration in the surrounding areas
has to be ensured by providing a waterproof blanket around
8/13/2019 repair of crack
6/6
6
the plinth. The masonry wall below ground level should also
be separated from the adjoining soil by replacing the existing
soil with coarse grain material.
Conclusion :
1.The individual cracks in members are unique by
themselves.
2.They are versatile diagnostic devices, clearly indicating the
specific problem in concerned members. In addition they
also indicate the degree of seriousness of the problem.
3. The crack throw light on the discipline in the associated
structural designs and quality .
4. The corrective measures to be implemented are clearly
indicated by these cracks.
THANKS