Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
nf{k.kh
fnYyh uxj fu
xe
REPORT OF THE CHIEF AUDITOR
2011-2012
MUNICIPAL CORPORATION OF DELHI (Part relating to South Delhi Municipal Corporation)
P RE FA C E This report for the financial year 2011-12 in respect of South Delhi Municipal
Corporation has been prepared for submission to the Standing Committee, SDMC in
accordance with Section 206(3) of the Delhi Municipal Corporation Act, 1957 as
amended by the Delhi Municipal Corporation (Amendment) Act, 2011. The Annual
Audit Report presents the significant audit findings of test check conducted by the
Office of the Chief Auditor on such transactions of the Erstwhile Municipal
Corporation of Delhi for the year 2011-12 which now either fall within the
jurisdiction of South Delhi Municipal Corporation or are relevant to the South Delhi
Municipal Corporation also. Matters relating to earlier years and later years
wherever deemed necessary have also been included.
It is worth mentioning that audit of transactions pertaining to a financial year
is conducted during the succeeding financial year. The departments are informed of
the preliminary audit observations through Audit Memorandum/Half Margin. This is
followed by Inspection Reports issued after completion of each audit. The
irregularities which are likely to be included in the Audit Report are brought to the
notice of the Commissioner through Draft Audit Paragraphs. The departments are
requested to confirm the facts & figures stated in the Draft Audit Paragraphs and
offer their comments within four weeks of their receipt. On receipt of satisfactory
reply from the department, the Draft Audit Paragraph is settled and in case the
reply is not found satisfactory, the same is suitably incorporated in Audit Para.
Accordingly the audit of transactions pertaining to the financial year 2011-12 was
conducted during 2012-13 and process of issue of draft paras and finalization of
Audit Report commenced during 2013-14.
The Report includes financial irregularities to the extent of ` 5010.18 lakh.
Major cases include “Loss due to non-allotment of rights for display of
advertisements through kiosks (` 103.20 lakh)”, “Loss due to non-recovery of
annual permission fee (` 103.71 lakh)”, “Short recovery of compounding fee due to
incorrect application of land rates (` 66.85 lakh)”, “Payment of Ready Mix Concrete
without delivery challans and computerized delivery challans/batching mix slips
(` 252.11 lakh)”, “Irregularities in the execution of work ‘Construction of Grade
Separator at Dabri intersection of Pankha Road” (` 65.06 lakh)”, “Review of
Ayurvedic Panchkarma Hospital, Kalu Saria, S.D.M.C.”, “Review of New Pension
Scheme, S.D.M.C. (` 1610.72 lakh) and “Outstanding temporary advances
(` 2262.48 lakh)”.
The Annual Audit Report has been prepared on the basis of
records/information furnished and made available by the auditees units. The Office
of the Chief Auditor disclaims any responsibility for any mis-information or non-
information on the part of the departments.
(Nand Kishore) Dated: Chief Auditor
South Delhi Municipal Corporation
C O N T E N T S Financial
implications (` in lakh)
Page No.
OVER VIEW iv PART-I’A’ Non submission of Monthly Accounts 1 PART-I’B’ Non submission of Annual Accounts 2 PART-II Non submission of Annual Appropriation
Accounts 3
PART-III FINANCIAL IRREGULARITIES A RECEIPTS AUDIT (a) Property Tax Audit 1. Non-recovery of dues against
dishonoured cheques. 105.09 4
2. Loss due to non-allotment of rights for display of Advertisements through Kiosks.
103.20 6
3. Loss due to non-recovery of license fee.
15.62 9
4. Loss due to non-recovery of license fee.
11.05 12
(b) Building 5. Outstanding demolition charges. 121.59 15 6. Loss due to non-recovery of annual
permission fee. 103.71 17
7. Short/non deposit of Parking Charges 79.65 19 8. Short recovery of compounding fee
due to incorrect application of land rates.
66.85 21
9. Short recovery of compounding fee due to incorrect application of land rates.
48.99 23
10. Short recovery of compounding fee due to incorrect application of land rates/non recovery of mixed land use charges.
14.28 25
11. Non-recovery of demolition charges. 12.91 27 12. Non deposit of conversion charges &
Car parking charges. 7.82 28
13. Non-deposit/short deposit of mixed land use charges.
5.78 30
14. Loss due to non deposit of one time car parking charges
5.56 31
ii
B WORKS MANAGEMENT AUDIT (a) Engineering 15. Payment of Ready Mix Concrete
without delivery challans and computerized delivery challans/batching mix slips.
252.11 32
16. Irregularities in the execution of work- “Construction of Grade Separator at Dabri intersection of Pankha Road”.
65.06 34
17. Non-enforcement of revised provisions in regard to Quality Assurance Audit/Third Party Testing Charges of CPWD Manual for implementation in erstwhile MCD resulting into irregular re-imbursement of Quality assurance audit/Third party testing charges to contractors.
30.65 41
18. Excess payment due to non deduction on account of decrease in price of Steel Re-inforcement bars under Clause 10 CA.
24.77 43
19. (A). Overpayment due to incorrect computation of quantity of BM and AC Mix
(B). Overpayment on account of less use of bitumen
15.35
4.24
46
20. Irregularities in testing of Ready Mix Concrete samples.
11.32 49
21. Payment of Ready Mix Concrete without verifying challans.
9.53 51
22. Excess payment due to non deduction on account of decrease in price of bitumen under Clause 10 CA.
3.21 53
23. Overpayment towards laying Water Bound Macadam.
2.83 55
24. Overpayment towards providing & laying Ready Mix Concrete.
2.36
57
(b) D.E.M.S. 25. Irregular payment to the contractors
towards hiring of tractor trolleys. 6.25 59
26. Irregular payment to the contractor towards hiring of Bajaj GC Max (LMV small).
3.41 61
iii
C HEALTH 27. Review of Ayurvedic Panchkarma
Hospital, Kalu Sarai, S.D.M.C.
64
D HORTICULTURE 28. Wasteful expenditure due to non–
planting the plants 3.79 69
E ACCOUNTS 29. Review of New Pension Scheme,
S.D.M.C. 1610.72 71
30. Outstanding temporary advances 2262.48 77 F MISCELLANEOUS 31. Outstanding Audit Reports, Inspection
Reports and Audit Objections. - 80
Annexure- A - 86 Annexure- B1 - 89 Annexure- B2 - 91 Annexure- C - 95 Annexure- D - 97
iv
O V E R V I E W
I. Non-recovery of dues against dishonoured cheques- ` 105.09 lakh.
The department is yet to recover dues amounting to ` 1,05,08,860 in
respect of 897 cheques tendered towards payment of property tax in Central
Zone which were dishonoured.
(Para 1)
II. Loss due to non-allotment of rights for display of advertisements through kiosks- `.103.20 lakh.
Inaction of the department for not awarding the contract to the second
highest bidder, M/s Pisces Communications Pvt. Ltd., despite knowing that the
highest bidder, M/s Adwel Advertising Service had not cleared outstanding dues
amounting to ` 11.97 crores, caused loss to the Corporation amounting to
` 1,03,20,000 in respect of Najafgarh Zone for the period from December, 2008
to November,2010.
(Para 2)
III. Outstanding demolition charges - ` 121.59 lakh. The Building departments, South Zone & West Zone are yet to recover
dues amounting to ` 1,21,59,096 in respect of 1310 cases towards demolition
charges.
(Para 5)
IV. Loss due to non-recovery of annual permission fee- ` 103.71 lakh.
Two property occupiers/owners applied for grant of permission to run
Banks in their premises under mixed land use in June, 2000 & February, 2002,
but the Building department did not grant any permission to them. Resultantly
they did not pay annual permission fee for the period 2000-01 to 2012-13 which
amounted to ` 1,03,71,173 but continued to run the Banks in their premises.
(Para 6)
v
V. Short/non deposit of Parking charges- ` 79.65 lakh.
Out of 14 property owners of West Zone, 13 property owners short
deposited the parking charges while one property owner did not deposit the
parking charges. This has resulted into short/non deposit of parking charges
amounting to ` 79,64,674.
(Para 7) VI. Short recovery of compounding fee due to incorrect application of
land rates- ` 66.85 lakh.
In 9 cases compounding fee amounting to ` 66,84,893 was
recovered short due to incorrect application of land rates.
(Para 8)
VII. Payment of Ready Mix Concrete without delivery challans and
computerized delivery challans/batching mix slips- ` 252.11 lakh. Payments amounting to ` 2,52,10,688 were released to the contractors for
providing & laying R.M.C. without delivery challans and computerized delivery
challans.
(Para 15)
VIII. Irregularities in the execution of work- “Construction of Grade
Separator at Dabri intersection of Pankha Road”- ` 65.06 lakh.
1. Non effecting of recovery of balance amount of Secured Advance and
incorrect calculation of escalation amount has resulted in excess
payment of escalation amount of ` 37,00,690.
2. Incorrect application of labour rates under Clause 10 CC resulted in
excess payment of ` 22,69,746.
3. Undue/extra payment of ` 5,35,867 was made by wrongly including the
items of centering shuttering separately in the bill of quantities.
(Para 16)
vi
IX. Non-enforcement of revised provisions in regard to Quality Assurance Audit/Third Party Testing charges of CPWD Manual for implementation in erstwhile M.C.D. resulting into irregular re-imbursement of Quality Assurance Audit/Third Party Testing charges to contractors - ` 30.65 lakh.
Irregular re-imbursement of Quality Assurance Audit/Third Party Testing
charges to contractors amounting to ` 30,65,313 due to non-enforcement of
revised provisions in regard to Quality Assurance Audit/Third Party Testing
charges of CPWD Works Manual 2010 for implementation in erstwhile M.C.D.
(Para 17)
X. Review of Ayurvedic Panchkarma Hospital, Kalu Sarai, S.D.M.C.
Ayurvedic Panchkarma Hospital, Kalu Sarai though evoked good response
during 2008-09 but thereafter because practically dormant in giving panchkarma
treatment/therapy to the patients/people residing in its catchment area. The
hospital has also been losing its appeal for general ayurvedic treatment. There
is a need to take a serious call on improving the utilization of doctors/staff of this
hospital.
(Para 27)
XI. Review of New Pension Scheme, S.D.M.C.
Non-remittance of NPS contributions with the concerned Trustee Bank
(Bank of India) and in the relevant accounts of Subscribers resulted into over
burdening of Municipal exchequer on account of interest of ` 4,81,07,703 and
Non-claming of Employer’s contribution of New Pension Scheme amounting to
` 11,29,64,265 in respect of Employees/Teachers of Education department from
Govt. of NCT, Delhi, while seeking reimbursement of 70% of expenditure incurred
on Education under different schemes of Non-Plan (Education).
(Para 29)
XII. Outstanding temporary advances- ` 2262.48 lakh.
Temporary advances amounting to ` 2262.48 lakh drawn by the drawing &
disbursing officers of different departments of the zones during the years
1998-99 to 2011-12 have not been adjusted so far.
(Para 30)
PART-I ‘A’
Non-submission of Monthly Accounts of erstwhile Municipal Corporation of Delhi
Section 205(i) of the D.M.C. Act, 1957 provides the Municipal Chief Auditor
shall conduct a monthly examination and audit of Municipal accounts and shall
report thereon to the Standing Committee who shall publish monthly an abstract of
receipts and expenditure of the month last preceding signed by not less than two
members of the Standing Committee and by the Municipal Chief Auditor.
Regulation 5 of Delhi Municipal Corporation (Maintenance of Accounts
Regulations, 1959) provides that at the end of each month a monthly abstract shall
be drawn up of the General Account and after the signature of Commissioner shall
be forwarded to the Municipal Chief Auditor for his monthly examination and report
to the Standing Committee. The abstract shall be forwarded to Municipal Chief
Auditor by 15th of the second month following the month to which the accounts
relate. Accordingly Monthly Accounts of erstwhile Municipal Corporation of Delhi
upto the year 2011-12 which have become due for submission as per the following
schedule have not been received so far (October, 2013).
(i) 2004-05 Due during 15th June, 2004 to 15th May, 2005,
(ii) 2005-06 Due during 15th June, 2005 to 15th May, 2006,
(iii) 2006-07 Due during 15th June, 2006 to 15th May, 2007,
(iv) 2007-08 Due during 15th June, 2007 to 15th May, 2008,
(v) 2008-09 Due during 15th June, 2008 to 15th May, 2009,
(vi) 2009-10 Due during 15th June, 2009 to 15th May, 2010,
(vii) 2010-11 Due during 15th June, 2010 to 15th May, 2011,
(viii) 2011-12 Due during 15th June, 2011 to 15th May, 2012.
Above position is brought to the knowledge of Standing Committee, South
Delhi Municipal Corporation for kind information.
2
Non-submission of Monthly Account by South Delhi Municipal Corporation
Monthly Account of S.D.M.C. for the month of March, 2013 which has become
due for submission by 15th May, 2013 has also not been received so far (October,
2013).
This is brought to the kind knowledge of the Standing Committee for issue of
such direction as may be deemed appropriate in the matter.
PART-I ‘B’
Non-submission of Annual Accounts
of erstwhile Municipal Corporation of Delhi
In accordance with Regulation 6 of Delhi Municipal Corporation (Maintenance
of Accounts Regulations, 1959), the Annual Account of erstwhile Municipal
Corporation of Delhi for the year 2011-12 was due to be submitted to audit by 15th
June, 2012 whereas this account has not been submitted so far (October, 2013).
Besides above, Annual Accounts of erstwhile Municipal Corporation of Delhi
for the seven preceding years i.e. 2004-05 to 2010-11 which became due for
submission to audit during the period 15th June, 2005 to 15th June, 2011 have also
not been submitted so far (October, 2013).
Above position is brought to the knowledge of Standing Committee, South
Delhi Municipal Corporation for kind information.
Non-submission of Annual Account by South Delhi Municipal Corporation
Annual Account of S.D.M.C. for the year 2012-13 became due for submission
by 15th June, 2013 but is yet to be submitted to audit (October, 2013).
This is brought to the kind knowledge of the Standing Committee for issue of
such direction as may be deemed appropriate in the matter.
3
PART-II
Non-submission of Annual Appropriation Accounts of erstwhile Municipal Corporation of Delhi
In accordance with Regulation 16 of Delhi Municipal Corporation
(Maintenance of Accounts Regulations, 1959), the Appropriation Account of
erstwhile Municipal Corporation of Delhi for the year 2011-12 was due to be
submitted to audit after submission of Annual Account by 15th June, 2012 whereas
this account has not been submitted so far (October, 2013).
In fact Annual Appropriation Accounts of erstwhile Municipal Corporation of
Delhi for the preceding nine years i.e. 2002-03 to 2010-11 which became due for
submission to audit have also not been submitted so far (October, 2013).
Above position is brought to the knowledge of Standing Committee, South
Delhi Municipal Corporation for kind information.
Non-submission of Annual Appropriation Account
by South Delhi Municipal Corporation
Annual Appropriation Account of S.D.M.C. for the year 2012-13 became due
for submission by 15th June, 2013 but is yet to be submitted to audit (October,
2013).
This is brought to the kind knowledge of the Standing Committee for issue of
such direction as may be deemed appropriate in the matter.
4
1. Non-recovery of dues against dishonoured cheques- ` 105.09 lakh.
The department is yet to recover dues amounting to ` 1,05,08,860 in respect of 897 cheques tendered towards payment of property tax in Central Zone which were dishonoured.
As per instructions issued from time to time from the office of the Chief
Accountant, following procedure is to be followed for the accountal and
re-adjustment of dishonoured cheques.
a- When a dishonoured cheque is returned by the bank, the reconciliating clerk
in the Accounts department, would trace from the dates on reverse of
cheques, the daily return received from the department and take necessary
action for passing reverse entries of original credits to revenue. He should
return the cheque to the department concerned for claiming amount from the
parties.
b- The amount of dishonoured cheques would immediately be debited in the
cash book to the head of account against which the credit was originally
given. The Zonal A.C.As. would maintain chronologically a register of
dishonoured cheques received from A.O. (H.Q.) and also watch their
clearance.
c- The department concerned shall ensure quick recovery of the dues from the
defaulting parties alongwith penalty wherever it is leviable.
d- The Zonal A.C.As. shall ensure that the registers for watching adjustment of
dishonoured cheques are invariably maintained in their respective offices.
They should also furnish a certificate regarding minus entry in Demand and
Collection registers or recovery action from the department concerned of the
zones.
A review of Dishonoured Cheque register maintained in Assessment &
Collection branch of Central Zone disclosed that the department received 1024
dishonoured cheques from A & C Head Quarter during the years 2009-10 &
2010-11, out of which it recovered property tax dues in 127 cases. However, in
remaing 897 cases, the department neither took write back action nor did it recover
5
the dues. Out of 897 cases, in 119 cases, cheque No. & G-8 No. were not
mentioned in the dishonoured cheque register. Thus dues amounting to
` 1,05,08,860 remained unrecovered in 897 cases.
The matter was brought to the notice of the department in April, 2012, but no
reply has been received so far (October, 2013).
(MCA/RS/DP-27(S)/2011-12)
6
2. Loss due to non-allotment of rights for display of advertisements through kiosks- `.103.20 lakh.
Inaction of the department for not awarding the contract to the second highest bidder, M/s Pisces Communications Pvt. Ltd., despite knowing that the highest bidder, M/s Adwel Advertising Service had not cleared outstanding dues amounting to ` 11.97 crores, caused loss to the Corporation amounting to ` 1,03,20,000 in respect of Najafgarh Zone for the period from December, 2008 to November,2010.
Condition No. 5 of notice for auction & condition 3(c) of terms & conditions for
allotment of rights for display of advertisements through kiosks in respect of Zones
provides that:-
“Only those highest bidders will be eligible for being declared as successful
highest bidders for the contract for which they quote the highest rates, who have
cleared all past dues against their previous contracts, if any, allotted to them by the
department. In case previous dues are not cleared by such highest bidders, the
particular contract shall be offered to the second highest bidder.”
The Advertisement department of the erstwhile Municipal Corporation of
Delhi issued Notice for Auction vide No.ADC (Advtt.)/unipoles/2008-09/1075 dated
21.10.2008 for display of advertisement(illuminated or non-illuminated) through
kiosks of the size 50” X 30” on streetlight poles existing only on the roads
maintained by the MCD in respect of Najafgarh Zone for a period of two years. Open
auction was held on 31.10.2008 and M/s Adwel Advertising Services offered the
highest bid for Rs. 4,35,000 p.m. while M/s Pisces Communications Pvt. Ltd. offered
the second highest bid for ` 4,30,000 p.m. The Auction Committee (31.10.2008)
recommended to allot contract to M/s Adwel Advertising Services, the highest
bidder, subject to clearance of all past dues, deposit of security amount equivalent
to three month’s licence fee, one month’s advance licence fee, advertisement tax
and completion of other requisite formalities. The Advertisement department
(3.11.2008) requested M/s Adwel Advertising Services to deposit past dues of
` 11,97,12,324 and 25% of the amount offered by him in respect of this contract
latest by 5.11.2008. In case the dues are not cleared and 25% of the offered
amount is not deposited by the stipulated date, the firm shall not be eligible for
7
being declared as “successful highest bidder” and the bid shall be cancelled and
earnest money deposited shall be forfeited.
Instead of complying with the requirements of letter dated 3.11.2008, the
firm approached the High Court, which vide order dated 4.11.2008 restrained the
MCD from awarding this contract to any other person till the next date of hearing
i.e. 2.12.2008. The department neither took any action to get the stay order
vacated from the Court nor to get the dues from the firm. However after 4 months,
the department informed the firm on 25.3.2009 that various cheques submitted
towards the outstanding dues and 25% of the amount offered for the contract were
rejected by the bankers and their offer shall be withdrawn.
Instead of withdrawing the contract of the firm and awarding the contract to
second highest bidder M/s Pisces Communication Pvt. Ltd. for ` 4,30,000 p.m., the
department allotted the contract for display of advertisement (illuminated/non-
illuminated) through kiosks on street light poles on M.C.D. roads for the period
ending 31.3.2011 in r/o Najafgarh Zone at a monthly licence fee of ` 4,35,000 vide
No.ADC/Advt./2009/D-238 dated 26.5.2009 without receiving past dues.
M/s Adwel Advertising Service did not pay the licence fee right from the date
of allotment and the department issued Show Cause Notice on 18.8.2009 to the firm
asking them as to why the contract be not cancelled and security forfeited for not
paying licence fee amounting to ` 8,96,100.
Consequent upon dismissal of suit(19.01.10) filed by M/s Adwel Advertising
Service in the High Court on 4.11.2008, and non-payment of outstanding dues
amounting to ` 19,90,23,374 in respect of South, Central, City, Najafgarh and
Shahdara North Zones, the department cancelled the contract for pole kiosks in
respect of these Zones vide No. OSD(Advtt.)/2009/D-1593 dated 25.1.2010.
Since M/s Adwel Advertising Service, being the highest bidder, had not
cleared their previous dues amounting to ` 11,97,12,324, the department should
not have considered this firm for awarding the contract and should have awarded
the contract to M/s Pisces Communications Pvt. Ltd. being the second highest
8
bidder for ` 4,30,000 in terms of condition No.5 of notice for auction & condition
3 (c) of terms & conditions for allotment of rights for display of advertisements
through kiosks in respect of zone.
Thus inaction of the department for not awarding the contract to the second
highest bidder, M/s Pisces Communications Pvt. Ltd., despite knowing that M/s
Adwel Advertising Service had to pay outstanding dues amounting to ` 11.97 crores,
caused loss to the Corporation amounting to ` 1,03,20,000 (` 4,30,000 X 24
months) in respect of Najafgarh Zone for the period from December, 2008 to
November,2010.
The irregularity was brought to the notice of the department in February,
2011, but no reply has been received so far (October, 2013).
(MCA/RS/DP-3(S)/2011-12)
9
3. Loss due to non-recovery of license fee - ` 15.62 lakh.
Non invoking the condition No.13 of terms & conditions for the grant of permission for display of advertisement through wall wrap M/s Adcom Network continuously defaulted in payment of licence fee ab-initio, which resulted into accumulation of dues and consequential loss of revenue amounting to ` 15,62,170.
Condition No. 2 & 3 of terms & conditions for the grant of permission for
display of advertisements through wall wrap provide that the advertiser will submit
the proposal/apply for the grant of permission for display of advertisements through
wall wrap on private properties and shall deposit with the M.C.D. advance monthly
fee @ ` 115 per sq.ft. of the display area by 10th of each calendar month failing
which a penalty/interest will be leviable @ 2% per month on the unpaid amount.
The permission will be subject to satisfactory performance at the end of each year
and enhancement of fee by 10% each year.
Condition No.13 further provides that in case of breach of any terms &
conditions or contraventions of any of the provisions of the DMC Act, Advertisement
Bye-laws or in any case any fee, charge, tax or any other amount is not paid, the
Municipal Corporation of Delhi shall take appropriate action against the advertiser
for recovery of the dues of MCD and/or for cancellation of the contract, as and when
such default is reported by the MCD. In any case, dues of the MCD shall be the first
charge on the forfeited security/guarantee retained by the Corporation while
granting the permission and they shall immediately release such dues of the MCD.
In such an eventuality, the MCD shall be at liberty to withdraw the permission.
M/s Adcom Network submitted proposal in December, 2008 for display of
advertisements through one Wall Wrap of the size 40’x6’ at B-87, Defence Colony,
New Delhi. The firm was asked (20.1.2009) to deposit security money of
` 82,800 equivalent to three months licence fee, one month’s advance licence fee of
` 27,600 (` 115x240 sq.ft.) and advertisement tax of ` 864 for the year 2008-09
alongwith requisite affidavit and an agreement duly signed. The firm deposited
security money of ` 82,800 vide G-8 No. 991046 dated 19.2.2009, one month
advance licence fee of ` 27,600 vide G-8 No. 991030 dated 19.2.2009 and
advertisement tax alongwith duly signed agreement & affidavit executed on
10
27.1.2009. The Advertisement department granted permission/No Objection
Certificate to M/s Adcom Network vide letter No.ADC(Advtt.)/2009/D-1615 dated
4.2.2009/16.2.2009 for display of advertisements through one wall wrap of the size
40’x6’ with a total display area of 240 sq.ft. at B-87, Defence colony. New Delhi
(Central Zone).
M/s Adcom Network (20.8.2009)requested the Advertisement department to
grant permission to increase the size of wall wrap from 40’x6’ to 35’x15’. The
department granted the permission to the firm vide letter No. ADC (Advtt.)/2009/
D-965 dated 25.9.2009 for increasing the size of wall wrap from 40’x6’ (240sq.ft.) to
30’x15’ (525 sq.ft.) subject to deposit of security amount of `98,325 and licence fee
for the period 16.2.2009 to 30.9.2009 amounting to ` 3,11,363 and advertisement
tax of ` 800 for the increased size by way of 3 separate pay orders. The firm vide
letters dated 26.10.2009 & 11.5.2011 requested the department to amend the
increased size of wall wrap 30’x15’(525 sq.ft.) to 30’x15’ (450sqft.)the permission of
which was granted on 25.9.2009. The department vide letter No. Co(Advtt.)/2011/
D-1002413 dated 7.6.2011 again granted permission for increasing the size of wall
wrap from 40’x6’ to 30’x15’ as per duly approved rate of licence fee and terms &
conditions of NOC. However, since the wall wrap of the size 30’x15’ = 450 Sqft. was
already being put up at site the licence fee was payable with retrospective effect
i.e. 16.2.2009.
On 19.7.2011, M/s Adcom Network requested the Advertisement department
to alter the approved size of wall wrap 30’x15’ (450 sqft.) to 34’x17’ (578 sqft). The
department granted the permission vide letter No. Co(Advtt.)/2011/D-1005519
dated 16.8.2011 subject to deposit of additional security amount of ` 44,160 addl.,
advertisement tax of ` 1,512 and monthly licence fee @ ` 66,470 w.e.f. 1.7.2011 as
the wall wrap of the increased size was already in existence at site. As the firm did
not deposit requisite payments and complete other formalities, the department
issued ‘Show Cause Notice’ vide No. Co(Advtt.)/2011/D-1006728 dated 16.9.2011 to
the firm asking them to show cause as to why the offer given to them vide letter
dated 16.8.2011 be not withdrawn, NOC dated 4.2.2009 cancelled and security
amount forfeited. As the firm defaulted in the payment of licence fee as per
11
approved terms & conditions, the department issued a ‘Demand Notice’ (BWP
07756431)vide No. Co(Advtt.)/2013/D-1002 dated 1.3.2013 to the firm directing
them to deposit outstanding dues of ` 15,62,170 accumulated upon the company
upto February, 2013. The firm did not deposit the said dues.
Audit observed that condition No.13 of the terms & conditions which clearly
provided that in case any fee, charge, tax or any other amount is not paid, the
Corporation shall take appropriate action against the advertiser for recovery of the
dues of MCD and/or for cancellation of the contract as and when such default is
reported by the MCD. Since M/s Adcom Network continuously defaulted in payment
of licence fee ab-initio, the department should have invoked this condition. But this
was not done so and resulted into accumulation of dues and consequential loss of
revenue amounting to ` 15,62,170.
The matter was brought to the notice of the department in February, 2011,
but no reply has been received so far (October, 2013).
(MCA/RS/DP-22(S)/2011-12)
12
4. Loss due to non-recovery of licence fee - ` 11.05 lakh.
Non invoking the condition No.13 of terms & conditions for the grant of permission for display of advertisements through wall wrap resulted into loss due to non-recovery of licence fee ` 11,05,104.
Condition No. 2 & 3 of terms & conditions for the grant of permission for
display of advertisements through wall wrap provide that the advertiser will submit
the proposal/apply for the grant of permission for display of advertisements through
wall wrap on private properties and shall deposit with the M.C.D. advance monthly
fee @ ` 115 per sqt. of the display area by 10th of each calendar month failing which
a penalty/interest will be leviable @ 2% per month on the unpaid amount. The
permission will be subject to satisfactory performance at the end of each year and
enhancement of fee by 10% each year.
Condition No.13 further provides that in case of breach of any terms &
conditions or contraventions of any of the provisions of the DMC Act, Advertisement
Bye-laws or in any case any fee, charge, tax or any other amount is not paid, the
Municipal Corporation of Delhi shall take appropriate action against the advertiser
for recovery of the dues of MCD and/or for cancellation of the contract, as and when
such default is reported by the MCD. In any case, dues of the MCD shall be the first
charge on the forfeited security/guarantee retained by the Corporation, while
granting the permission and they shall immediately release such dues of the MCD.
In such an eventuality, the MCD shall be at liberty to withdraw the permission.
M/s Asian Trading Company submitted proposal in September, 2008 for
display of advertisements through one No. of Wall Wrap of the size 60’x14’ at
79-80, Satkar Building, Nehru Place, New Delhi. The firm was asked (22.9.2008) to
deposit security money of ` 2,89,800 equivalent to three months licence fee, one
month’s advance licence fee of ` 96,600 (` 115x840 sq.ft.) and advertisement tax of
` 2,110 for the year 2008-09 with an agreement duly signed. The firm vide letter
dated 7.10.2008 enclosed 3 pay orders for ` 2,89,800, ` 96,600 and ` 2,110
alongwith duly signed agreement executed on 26.9.2008. The Advertisement
13
department granted permission/No Objection Certificate to M/s Asian Trading
Company vide letter No.ADC(Advtt.)/2008/D-1220 dated 26.11.2008 for display of
advertisements through one wall wrap of the size 60’x14’ with a total display area
of 840 sq.ft. at 79-80, Satkar Building, Nehru Place, New Delhi.
M/s Asian Trading Company further deposited ` 1,98,996 vide letter dated
5.3.2009 towards monthly licence fee and after that the firm did not deposit licence
fee. The department issued ‘Show Cause Notice’ to the firm on 15.6.2009 after
noticing on 12.6.2009 that the firm had displayed the wall wrap at the roof-top/
terrace of the property in excess of the permitted size, in utter violation of the
provisions of DMC Act, terms & conditions of NOC/permission and called upon to
show cause as to why NOC / permission given to them be not cancelled and security
deposited forfeited. The Advertisement department then cancelled No Objection
Certificates for display of advertisements through wall wrap at Satkar Building,
Nehru Place, Delhi vide No. CO(Advtt./2010/D-364 dated 20.4.2010 together with
other 5 permissions granted to the firm as the dues amounting to ` 28,37,140 had
accumulated against these NOCs/ permissions which included the outstanding dues
of ` 15,53,630 against the said building/permission for wall wrap. The firm
deposited ` 5 lakh as part payment of outstanding dues of ` 28.37 lakh lying against
6 contracts vide G-8 No. AH 20035 dated 14.5.2010.
Audit observed that condition No.13 of the terms & conditions had clearly
provided that in case any fee, charge, tax or any other amount is not paid, the
Corporation shall take appropriate action against the advertiser for recovery of the
dues of MCD and/or for cancellation of the contract as and when such default is
reported. But the department instead of invoking this condition remained silent and
on 20.4.2010 cancelled the permission/NOC thereby giving undue opportunities to
the firm to keep on displaying the advertisements through wall wrap. This resulted
into accumulation of the arrears to ` 15.53 lakh.
14
Thus non-recovery of licence fee has resulted in loss of revenue of
` 11,05,104 as detailed below
S.N. Period No. of months
Rate of Licence fee (`)
Loss of licence fee
(`) 1. 26.11.2008
to 25.11.2009
12
(840 x 115 = 96,600) 96,600
11,59,200
2. 26.11.2009 to
20.4.2010
5
(96,600 + 10%) = 1,06,260
5,31,300
Less amount paid by the firm 16,90,500 (-) 5,85,396
11,05,104
The irregularity was brought to the notice of the department in March, 2012,
but no reply has been received so far (October, 2013).
(MCA/RS/DP-20(S)/2011-12)
15
5. Outstanding demolition charges- ` 121.59 lakh.
The Building departments, South Zone & West Zone are yet to recover dues amounting to ` 1,21,59,096 in respect of 1310 cases towards demolition charges.
Section 343 of D.M.C. Act, 1957, provides that where the erection of any
building or execution of any work has been commenced or is being carried out or
has been completed without proper sanction or contrary to any condition, such
building shall be demolished within such period not exceeding 15 days or as may be
specified in the order by person concerned failing which the Commissioner may
himself cause the erection or the work to be demolished and the expenditure of
such demolition shall be recovered from such person as an arrear of tax.
A review of Demolition Charges register for the years 2010-11 to 2011-12 of
Executive Engineer (Building), South Zone & West Zone disclosed the position of
demand raised on account of demolition charges and recoveries made thereagainst
during the said years as under :-
It would be seen from the above table that out of the total demand on
account of demolition charges of ` 1,42,94,494 the department has effected the
S.N
Years No of properties
demolished
Demand Raised
(`)
Demolition Charges
recovered from
property owners
(number of properties)
Amount Recovered
& % age of Recovery
(`)
Demolition Charges
could not be recovered
from property owners
(number of properties)
Outstanding Amount
& its % age
(`)
Executive Engineer (Building), South Zone 1 2010-11 126 10,17,375 22 1,24,400
(12.23%) 104 8,92,975
(87.77%) 2 2011-12 1134 88,64,921 195 12,41,898
(14.01%) 939 76,23,023
(85.99%) Executive Engineer (Building), West Zone
3 Jan., 2011 to March, 2012
338 44,12,198 71 7,69,100 (17.43%)
267 36,43,098 (82.57%)
TOTAL 1598 1,42,94,494 288 21,35,398 (14.94%)
1310 1,21,59,096 (85.06%)
16
recovery of ` 21,35,398 which works out to 14.94%. This indicates lack of effective
monitoring by the departments towards recovering the demolition charges.
The irregularity was brought to the notice of the departments in August, 2012
& February, 2013, but no reply has been received so far (October, 2013).
(MCA/RS/DP-16(S) & 28(S)/2011-12)
17
6. Loss due to non-recovery of annual permission fee- ` 103.71 lakh.
Two property occupiers/owners applied for grant of permission to run Banks in their premises under mixed land use in June, 2000 & February, 2002, but the Building department did not grant any permission to them. Resultantly they did not pay annual permission fee for the period 2000-01 to 2012-13 which amounted to ` 1,03,71,173 but continued to run the Banks in their premises.
The Corporation vide Circular No.D/1155/Addl.Comm.(E)/99 dated 10.6.1999
issued guidelines for allowing mixed land use namely Nursing Homes, Guest Houses
and Banks in residential areas. According to these guidelines, annual permission
fee @ 10% for Banks and Nursing Homes and 2.5% for Guest Houses of the
difference between current commercial rates and current residential rates of land
(as approved by the ministry) were to be adopted for charging annual permission
fee from owner based on the actual floor area utilized for such non-residential
purposes.
A test check of two case files of properties located at Hauz Khas, New Delhi
(South Zone) disclosed that the respective property occupiers/owners applied for
grant of permission to run Banks in their premises under mixed land use in June,
2000 & February, 2002 but the Building department did not grant any permission to
them. Resultantly they have not been paying annual permission fee for the period
2000-01 to 2012-2013 but possibly are continuing to run the Banks in their
premises.
Thus failure on the part of the department to grant permission for carrying
out commercial activities despite being applied for by the respective
property occupiers/owners resulted in loss to the Corporation amounting to
` 1,03,71,173 as detailed below:-
S. N.
Property No.
Area used by Bank (sqm)
Diff. between comm. rates-
residential rate
(`)
Annual permission fee.(Area in use x 10% of
the difference in rates) and Area in use x rate of A&B category
of colony (`383) (`)
Period
Amount of annual
permission fee
(`) 1 2 kaushlya
park Hauz Khas, New
Delhi
253 syndicate
Bank
(24,150-11,550) =12,600
-
(253x1260) =3,18,780
(253x383) =96,899
2000-01 to
2005-06 2006-07
to 2012-13
6years
7years
19,12,680
6,78,293
18
25,90,973 - 15,295
(already deposited)
25,75,678 2 A-27 Hauz
Khas New Delhi
1021 Canara Bank
(24,150-11,550) =12,600
-
(1021x1260) =12,86,460
(1021x383) =3,91,043
2002-03 to
2005-06
2006-07 to
2012-03
4 years
7 yeras
51,45,840
27,37,301
78,83,141 - 87,646 (already
deposited) 77,95,495 Total 1,03,71,173
The matter was brought to the notice of the department in August 2012 but no
reply has been so far.
(MCA/RS/DP-26(S)/2011-12)
19
7. Short/non deposit of Parking charges - ` 79.65 lakh.
Out of 14 property owners of West Zone 13 property owners short deposited the parking charges while one property owner did not deposit the parking charges. This has resulted into short/non deposit of parking charges amounting to ` 79,64,674.
In terms of Public Notice issued by Municipal Corporation of Delhi regarding
mixed land use as per MPD–2021 and payment of mixed land use charges, the
owner/allottee/resident/user of the plot/dwelling unit under the mixed land use shall
be liable to pay one time charges for development of parking at such rate for one
E.C.S. per 50 sqm of plot area as under:-
‘A’ & ‘B’ Category of colonies ` 2,10,500
‘C’ & ‘D’ Category of colonies ` 1,49,750
‘E’, ‘F’ & ‘G’ Category of colonies ` 66,500
Out of the total one time charges for development of parking, 1/3rd was to be
paid on or before 30.6.2007 and the remaining 2/3rd by 31.3.2008.
A test check of applications vide which 14 property owners of West Zone
deposited conversion charges and parking charges disclosed that 13 property owners
short deposited the parking charges while one property owner did not deposit the
parking charges. This has resulted into short/non deposit of parking charges
amounting to ` 79,64,674 as detailed below:-
S.N. Property No. Category of
colony Area of
the plot in sqm.
Development of Parking charges
deposited by the owner
(`)
Development of Parking Charges
should have been deposited by the
owner (`)
(@ ̀1,49,750 per 50 Sqm- D Category)
(@ ` 66,500 per 50 Sqm-
F Category)
Parking Charges
short deposited
(`)
1 E- 107, Mansarovar Garden
D 257 3,84,875 7,69,715 3,84,840
2 D-9, Rajouri Garden
D 313.55 4,50,000 9,39,082 4,89,082
3 WZ-491, MS Block Hari Nagar
F 307 66,500 4,08,310 3,41,810
20
4 C – 596, Vikas Puri
D 324 2,99,500 9,70,380 6,70,880
5 A- 40, Vishal Enclave
D 334.45 4,06,980 10,01,678 5,94,698
6 A – 37, Vishal Enclave
D 334 4,44,652 10,00,330 5,55,678
7 C – 368, Vikas Puri
D 320 95,391 9,58,400 8,63,009
8 C-6/1, Mansarovar Garden
D 300 1,49,750 8,98,500
7,48,750
9 J- 13/41, Rajouri Garden
D 167.22 99,833 5,00,823 4,00,990
10 A – 1/166, Janak Puri
D 250 2,05,000 7,48,750 5,43,750
11 A – 21, Vishal Enclave
D 239.50 4,07,320 7,17,302 3,09,982
12 A – 42, Vishal Enclave
D 334.45 - 10,01,678 10,01,678
13 A – 30, Vishal Enclave
D 334.45 4,06,980 10,01,678 5,94,698
14 A – 31, Vishal Enclave
D 334.45 5,36,849 10,01,678 4,64,829
Total 79,64,674
The irregularity was brought to the notice of the department in February,
2013, but no reply has been received so far (October, 2013).
(MCA/RS/DP-18(S)/2011-12)
21
8. Short recovery of compounding fee due to incorrect application of land rates- ` 66.85 lakh.
In 9 cases compounding fee amounting to ` 66,84,893 was recovered short due to incorrect application of land rates.
A test check of record of Executive Engineer (Building), Central Zone
disclosed that 9 occupancy certificates/completion certificates were issued during
the period March, 2011 to February, 2012 with levy of compounding fee applicable
for permissible/compoundable deviations. The department worked out and
recovered the compounding fee based on land rates notified by the L&DO for the
period 1.4.1998 to 31.3.2000 as against the Circle rates which had been notified by
the Special Inspector General (Regulation) GNCTD, vide letter No.F.1(281)Regn.Br./
HQ/Div.Com./09/45 dated 4.2.2011.
Thus incorrect application of land rates has resulted into short recovery of
compounding fee amounting to ̀ 66,84,893 in 9 cases as detailed below:-
S. N.
Property No. & Category of Colony
C.C. issue No. & date
Area in sq.mtr.
Compounded on land rate
sq.mtr.
Land rate charged
per sq.mtr. (`)
Land rate should have
been charged per sq.mtr.
(`)
Amount recovered
short
(`) 1 D-1048, New Friends Colony
‘A’ 362/B/CC/CZ/11 dated 27.12.11
4.82 11,550 86,000 3,58,849
2 D-138, Defence Colony ‘B’ 354/B/CC/CZ/11 dated 23.11.11
10.17 11,550 68,200 5,76,130
3 D-140, Defence Colony ‘B’ 367/B/CC/CZ/11 dated 30.12.11
11.09 11,550 68,200 6,28,248
4 D-103, Defence Colony ‘B’ 318/B/CC/CZ/11 dated 23.3.11
6.10 11,550 68,200 3,45,565
5 D1-A, South Extn.-2 ‘A’ (Commercial)
350/B/CC/CZ/11 dated 25.10.11
8.25 26,680 86,000x3= 2,58,000
19,08,390
6 C-27, Pampose Enclave ‘B’ 375/B/CC/CZ/12 dated 21.2.12
12.84 11,550 68,200 7,27,386
7 A-24/8, Mohan Co-op. Ind. Estate, Mathura Road ‘D’
(Commercial)
8/B/CC/CZ/12 dated 6.2.12
11.47 18,480 43,600x3= 1,30,800
12,88,310
8 W-100, Creater Kailash-I ‘B’ 376/B/CC/CZ/12 dated 21.2.12
12.65 11,550 68,200 7,16,622
9 C-340, Defence Colony ‘B’ 359/B/CC/CZ/11 dated 27.12.11
2.39 11,550 68,200 1,35,393
Total 66,84,893 The irregularity was brought to the notice of the department in November,
2012. Executive Engineer (Building), Central Zone replied (24.5.2013) that
compounding fee are calculated on the basis of office order bearing
No.8/EE(B)HQ/92 dated 8.12.1992 issued under the signature of Commissioner of
22
erstwhile M.C.D. now S.D.M.C. categorically lays down as “Equivalent to the land
rates prevailing at the time of compounding. The prevailing rates shall be the
official notified rates of land in the area by the L & D O from time to time.
The reply furnished by the department is not acceptable in audit as it reflects
the perception and understanding of the Executive Engineer (Building) and may not
necessarily reflect the official stand of the department/Commissioner/S.D.M.C. As
such, the department was requested to get the reply duly vetted/approved by the
competent authority so as to reflect the official view of the department. But no final
reply has been received so far (October, 2013)
(MCA/RS/DP-4(S)/2011-12)
23
9. Short recovery of compounding fee due to incorrect application of land rates- ` 48.99 lakh.
In 9 cases compounding fee amounting to ` 48,99,350 was recovered short due to incorrect application of land rates.
The Executive Engineer (Building), West Zone issued 4 occupancy
certificates/completion certificates and regularized 5 plans of additional structure in
properties in terms of Notification dated 22.9.2006 relating to ‘levy/charges for
Residential Plotted Development Regulations, 2006’during the period July, 2009 to
July, 2012 with levy of compounding fee applicable for permissible/ compoundable
deviations. The record disclosed that the department worked out and recovered the
compounding fee based on land rates notified by the L&DO for the period 1.4.1998
to 31.3.2000 as against the Circle rates which had been notified by the Joint
Secretary (Revenue), GNCTD dated 18.7.2007 and subsequently revised from time
to time.
Thus incorrect application of land rates has resulted into short recovery of
compounding fee amounting to ̀ 48,99,350 in 9 cases as detailed below:-
(A) S. N.
Property No. & Category of Colony
C.C. issue No. & date
Area in sq.mtr.
Compounded on land
rate sq.mtr.
Land rate charged
per sq.mtr.
(`)
Land rate should have
been charged per sq.mtr.
(`)
Amount of compounding
fee recovered
short (`)
1 P.No.35 Road No. 44, West Punjabi Bagh, ‘C’
07/CC/B/WZ/ 2011/I Dt. 1.7.11
12.45 6,930 54,600 5,93,491
2 J-40, Vikas Puri, ‘D’ 02/CC/B/WZ/ 2011/ II Dt. 10.2.11
12.3 6,930 43,600 4,51,041
3 D-1 Vikas Puri, ‘D’ 04/CC/B/WZ/ 2012/ 17/II Dt. 25.5.12
9.85 6,930 87,200 7,90,659
4 Nursery School at C- Block, Janak Puri, ‘D’ (Commercial)
04/CC/B/WZ/ 09/ll Dt.17.7.09
12.60 14,490 (7,245X2)
21,800X2 = 43,600
3,66,786
Total 22,01,977
(B) S. N.
Property No. & Category of Colony
Date of application for regularization
Area in sq.mtr.
Compounded on land rate
sq.mtr.
Land rate charged
per sq.mtr. (`)
Land rate should have
been charged per sq.mtr.
(`)
Amount of compounding
fee recovered
short (`)
1 T-29 Rajouri Garden, ‘D’ 17.05.2012 3.00 6930 87200 2,40,810
24
2 9/62 Rajouri Garden, ‘D’ 23.05.2012 13.40 6930 87200 10,75,618
3 23/64 AB Tilak Nagar ‘E’ 20.06.2012 11.96 6930 47840 4,89,284
4 C-85 Shivaji Park ‘F’ 12.09.2011 13.43 6930 32200 3,39,376
5 8/5 Subhash Nagar ‘E’ 23.07.2012 13.50 6930 47840 5,52,285
Total 26,97,373
The irregularity was brought to the notice of the department in February,
2013, but no reply has been received so far (October, 2013).
(MCA/RS/DP-23(S)/2011-12)
25
10. Short recovery of compounding fee due to incorrect application of land rates/non recovery of mixed land use charges- ` 14.28 lakh.
Compounding fee amounting to ` 2,68,898 was recovered short from the owner due to incorrect application of land rates. The owner also did not deposit the mixed land use charges for the subsequent years 2010-11 & 2011-12 which has further resulted into non recovery of mixed land use charges amounting to ` 11,59,380.
A test check of record of Executive Engineer (Building), Central Zone
disclosed that M/s Faridabad Implements Pvt. Ltd. applied for regularization of their
premises under Mixed Land Use Regulation, 2006 for running Guest House activities
in respect of property No.C-18 Friends Colony (East), New Delhi vide file
No.182/B/UCR/CZ/2009 dated 29.9.2009. The department granted the permission
on 27.10.2009 with the levy of (i) compounding fee applicable for permissible/
compoundable deviations and (ii) mixed land use charges. The department worked
out and recovered the compounding fee based on land rates @ ` 11,550 per sqm
notified by L.& D.O. for the period 1.4.1998 to 31.3.2000 as against the Circle rates
@ ` 43,000 per sqm which had been notified by the Joint Secretary (Revenue)
GNCDT vide letter No. F-2(12)/ Fin(E-l)/part file/vol-l(ii)/3548 dated 18.7.2007. This
has resulted into short recovery of compounding fee amounting to ` 2,68,898
(8.55 sqm x ` 43,000 - ` 11,550).
The record further, disclosed that the owner did not deposit the mixed land
use charges for the subsequent years 2010-11 & 2011-12 which has further resulted
into non recovery of mixed land use charges amounting to ` 11,59,380 (5,79,690x2
years).
Thus the total amount on account of short recovery of compounding fee and
non recovery of mixed land use charges works out to ` 14,28,278.
The irregularity was brought to the notice of the department in September
2012. Executive Engineer (Building), Central Zone replied (14.5.2013) that
compounding fee are calculated on the basis of office order bearing
No.8/EE(B)HQ/92 dated 8.12.1992 issued under the signature of Commissioner of
erstwhile M.C.D. now S.D.M.C. categorically lays down as “Equivalent to the land
26
rates prevailing at the time of compounding. The prevailing rates shall be the
official notified rates of land in the area by the L & D O from time to time.
The reply furnished by the department is not acceptable in audit as it reflects
the perception and understanding of the Executive Engineer (Building) and may not
necessarily reflect the official stand of the department/Commissioner/S.D.M.C. As
such, the department was requested to get the reply duly vetted/approved by the
competent authority so as to reflect the official view of the department. But no final
reply has been received so far (October, 2013).
(MCA/RS/DP-2(S)/2011-12)
27
11. Non-recovery of demolition charges- ` 12.91 lakh.
An amount of ` 12,91,120 was outstanding against 83 property owners in Central Zone whose unauthorised buildings/portions of buildings were demolished during the year 2011-12.
Section 343 of D.M.C. Act, 1957 provides that where the erection of any
building or execution of any work had been commenced or is being carried out or
had been completed without proper sanction or contrary to any condition, shall be
demolished within such period not exceeding 15 days or as may be specified in the
order by person concerned, failing which, the Commissioner may himself cause the
erection of work to be demolished and expenditure of such demolition shall be
recovered from such person as arrears of tax.
A review of Demolition Charges register of Building department, Central Zone
for the year 2011-12 disclosed that an amount of ` 12,91,120 as detailed in
Annexure ‘A’ was outstanding against 83 property owners whose unauthorised
buildings/portions of buildings were demolished during the year 2011-12.
Though the Building department sent notices to the Property Tax department
of the Zone for recovery of demolition charges as arrears of tax but the outstanding
amount of ` 12.91 lakh remained un-recovered.
The matter was brought to the notice of the department in November, 2012,
but no reply has been received so far (October, 2013).
(MCA/RS/DP-24(S)/2011-12)
28
12. Non deposit of conversion charges & car parking charges - ` 7.82 lakh.
In 14 cases, the owners/users of the premises applied for regularization under Mixed Land Use Regulations and deposited registration charges only but did not deposit the conversion charges and development charges for car parking as required. This has resulted into non deposit of conversion charges and development charges for car parking amounting to ̀ 7,82,258.
In terms of provisions regarding Mixed Land Use Regulations envisaged in the
Master Plan-2021 and notified by the D.D.A. vide its notification dated 22nd of June,
2007, the owners/users of the premises are liable to pay the mixed land use
charges/conversion charges and one time car parking development charges of their
premises before the 30th of June every year. However, the Urban Development
Ministry, Government of India vide its notification dated 12th of August, 2008
allowed to pay one time registration charges and annual conversion charges for the
year 2006-07 and 2007-08 for such properties without any penalty under clause
15.9 (V) for mixed land use on or before 30.6.2009.
During the course of audit on the accounts of Executive Engineer (Bldg.),
Najafgarh Zone it was noticed that in 14 cases, the owners/users of the premises
applied for regularization of their premises under Mixed Land Use Regulations and
deposited registration charges only but did not deposit the conversion charges and
development charges for car parking as required. This has resulted into non deposit
of conversion charges and development charges for car parking amounting to
` 7,82,258 as detailed below.
S.N. Premises No.
and name of the locality
Nature of trade/type of
use of the premises
Built up area of the
comme-rcial
premises
(sqm)
Amount of registration
charges deposited by
the trader
(`)
G-8 No. & date vide
which registration
charges deposited
Conversion charges
payable for E, F or G
category @ ` 192 per
sqm
Car Parking Charges payable
for E,F,G Category @
`66,500/- per ECS(Equivalent car space + 50
sq.mtr. (`)
1 B-25, Nanhe Park, Matiala Bindapur Road, Near Matiala, Uttam Nagar (Category-G)
General Store 17 1,000 476088/ 3.8.2009
3,264 Not leviable being less than 20 sqm area
2 B-25, Nanhe Park, Matiala Bindapur Road, Near Matiala, Uttam Nagar (Category-G)
General Store 15 1,000 476096/ 3.8.2009
2,880 Not leviable being less than 20 sqm area
29
3 B-25, Nanhe Park, Matiala Bindapur Road, Near Matiala, Uttam Nagar (Category-G)
Office 15 1,000 476094/ 3.8.2009
2,880 Not leviable being less than 20 sqm area
4 B-25, Nanhe Park, Matiala Bindapur Road, Near Matiala, Uttam Nagar (Category-G)
Furniture Store
17 1,000 476087/ 3.8.2009
3,264 Not leviable being less than 20 sqm area
5 16A, Kh. No.11/17/1, Hari Vihar, Phase-III, Kakrola
Retail Shop 30 1,000 496079/ 7.9.2009
5,760 66,500
6 G-107, Kh. No. 32/9/10/2, Harijan Basti, Palam Extn.
Magic Car Accessories
156 1,000 905004/ 25.6.2009
29,952 2,07,480
7 RZ-H-707, Raj Nagar –II, Palam Colony
Hemant Jewellers
10 1,000 922048/ 10.7.2009
1,920 Not leviable being less than 20 sqm area
8 B-25, Nanhe Park, Near Matiala, Utam Nagar
Photography Shop
17 1,000 476095/ 3.8.2009
3,264 Not leviable being less than 20 sqm area
9 B-25, Nanhe Park, Near Matiala, Utam Nagar
Cyber Café 17 1,000 476092/ 3.8.2009
3,264 Not leviable being less than 20 sqm area
10 B-25, Nanhe Park, Near Matiala, Utam Nagar
Office 17 1,000 476093/ 3.8.2009
3,264 Not leviable being less than 20 sqm area
11 RZF 905/22, GF/FF, Raj Nagar-II, Palam
Chand Medical
216 1,000 490018/31.7.2009
41,472 2,87,280
12 C-73, J.J. Colony, Camp No.2, Nangloi
M/s Arora Foot- Wear
9½ 1,000 36048/ 30.9.2008
1,824 Not leviable being less than 20 sqm area
13 1354/A, HC Road, Najafgarh Phirni Road
Maana Mega Mart
75 1,000 482026/ 29.7.2009
14,400 99,750
14 K-2/510, Mata Chowk, Mahipal Pur
Plywood Shop
20 1,000 55120/ 8.3.2010
3,840 Not leviable being less than 20 sqm area
1,21,248 6,61,010
The irregularity was brought to the notice of the department in July, 2010, but
no reply has been received so far (October, 2013).
(MCA/RS/DP-1(S)/2011-12)
30
13. Non-deposit/short deposit of mixed land use charges - `. 5.78 lakh.
In two cases the property owners have short deposited mixed land use charges amounting to ` 5,77,536.
In terms of Public Notice regarding ‘Mixed Land Use as per MPD-2021 and
payment of mixed land use charges’, issued by Municipal Corporation of Delhi, the
owner/allottee/resident/user of the plot/dwelling unit under the mixed land use shall
be liable to pay mixed land use charges to the authority before 30th June every year
based on rates fixed for different categories of colonies according to type of mixed
land use as under:-
A test check of applications and G-8 receipts vide which the property owners
have deposited the parking charges/mixed land use charges with the Building
department West Zone, disclosed that in two cases, the property owners short
deposited mixed land use charges amounting to ̀ 5,77,536 as detailed below:-
S.N.
Property No. Area of the plot
Area under mixed
land use
Year Mixed land use charges paid by the
owner@ (`) 192/Sqm.
(`)
Mixed land use charges should have been paid @ ` 511/Sqm.
(Category – ‘D‘) (`)
Mixed land use
charges short
deposited (`)
1 C-1 (Part -D) Rajouri Garden, Delhi
251 Sqm 223.14 Sqm
2007-08 13,000 1,14,024 1,01,024
2008-09 to
2011-12 (4 years)
- (1,14,024x4) 4,56,096
4,56,096
2 J- 66, Rajouri Garden, Delhi
240 Sqm 32 Sqm (G.F.)
2010-11 & 2011-12 (2 year)
12,288 (6144 x 2)
32,704 (16,352 x 2)
20,416
Total 5,77,536
The irregularity was brought to the notice of the department in February,
2013, but no reply has been received so far (October, 2013).
(MCA/RS/DP-9(S)/2011-12)
S. N.
Type of mixed land use
A & B Category of Colony
(` per Sq. Mtr.)
C & D Category of Colony
(` per Sq. Mtr.)
E, F & G Category of Colony
(` per Sq. Mtr.) 1 Retail Shops 767 511 192 2 Other Activities 383 256 96 3 Professional
Activities 192 128 48
31
14. Loss due to non-deposit of one time car parking charges - ` 5.56 lakh.
The owner deposited the conversion charges for the period from 2007-08 to 2011-12, but he did not deposit one time charges for development of parking amounting to ` 5,55,940.
In terms of Public Notice regarding “Mixed Land Use as per MPD- 2021 and
payment of mixed land use charges” issued by Municipal Corporation of Delhi, the
owner/allottee/resident/user of the plot/dwelling unit under the mixed land use shall
be liable to pay one time charges for development of parking @ ` 66,500 for ‘E’, ‘F’
& ‘G’ Categories for one E.C.S. per 50 sqm of plot area in addition to annual mixed
land use charges/conversion charges. Out of the total one time charges for
development of parking 1/3rd were payable on or before 30.6.2007 and the
remaining 2/3rd by 31.3.2008.
A test check of application vide which the property owner of the premises
B-94, Jain Park, Main Matiala Road, Uttam Nagar, Delhi having plot area of 418 sqm
disclosed that the owner deposited the conversion charges (mixed land use
charges) for the period from 2007-08 to 2011-12, but he did not deposit one time
charges for development of parking as required. This has resulted in loss due to
non-deposit of car parking charges amounting to ̀ 5,55,940 (418sqm/50 x` 66,500).
The irregularity was brought to the notice of the department in July, 2012, but
no reply has been received so far (October, 2013).
(MCA/RS/DP-12(S)/2011-12)
32
15. Payment of Ready Mix Concrete without delivery challans and computerized delivery Challans/batching mix slips- ` 252.11 lakh.
Payments amounting to ` 2,52,10,688 were released to the contractors for providing & laying R.M.C. without delivery Challans and computerized delivery challans.
(A) Para 5.8.8.9.4 & 5 of C.P.W.D. specifications 2002 for cement mortar, cement
concrete and RCC works inter-alia provides that RMC manufacturers/ suppliers shall
along with each batch of concrete delivered to the placement contractor, give him a
concrete delivery tickets to the Engineer-in-Charge for his record and also get
duplicate copies of each delivery tickets duly received and signed from the
contractor. Further R.M.C. as supplied by the manufacturer and as placed by the
contractor shall in no way be different from the specifications of concrete as
approved by the Engineer-in-Charge.
It was noticed that three Engineering divisions released payments amounting
to ` 93,78,908 as detailed in Annexure ‘B1’ to the contractors during 2008-09 to
2011-12 against 32 work orders towards providing and laying Ready Mix Concrete
without production of delivery tickets/challans of R.M.C. manufacturers which is
violation of ibid provisions. In the absence of delivery tickets/challans authenticity of
quantity of R.M.C procured from the R.M.C. manufacturers and provided and laid on
works could not be verified in Audit. The Division-wise detail is as under:
Division No. of cases
Amount (`)
M-I, Central Zone 4 10,37,123 M-II, Central Zone 23 72,43,100 M-III, Central Zone 5 10,98,685 32 93,78,908
(B) Further in terms of Section 10.5 of CPWD Works Manual-2007 in case of
works where R.M.C is stipulated to be used from an approved
sources/manufacturers, the computerized dispatch slip that are sent with each
dispatch of R.M.C shall be kept on record.
33
It was further noticed that above Divisions released payments amounting to
` 1,58,31,780 to the contractors against 51 work orders who produced manual
delivery challans instead of computerized delivery challans/batching mix slips in
contravention of ibid provision. This has resulted in irregular payment as detailed in
Annexure ‘B2’. The Division-wise break up is as under: -
Division No. of
cases Amount
(`) M-I, Central Zone 18 57,02,603 M-II, Central Zone 13 38,02,116 M-III, Central Zone 20 63,27,061 51 1,58,31,780
The irregularity was brought to the notice of the department during May,
2012 to April, 2013, but no reply has been received so far (October, 2013).
(MCA/RS/DP-13(S)/2011-12)
34
16. Irregularities in the execution of work- “Construction of Grade Separator at Dabri intersection of Pankha Road”- ` 65.06 lakh.
1. Non effecting of recovery of balance amount of Secured Advance and
incorrect calculation of escalation amount has resulted in excess payment of escalation amount of ` 37,00,690.
2. Incorrect application of labour rates under clause 10 CC resulted in excess payment of ` 22,69,746.
3. Undue/extra payment of ` 5,35,867 was made by wrongly including the items of centering shuttering separately in the bill of quantities.
The Executive Engineer (Project) West-I awarded work “Construction of Grade
Separator at Dabri intersection of Pankha Road and Road leading to Dwarka near
Janakpuri, Delhi” to M/s DRA- Brahamputra Consortium Ltd. (J.V.) at a contractual
cost of ` 109.838 crore with completion period of 30 months vide work order
No.EE(PR)West-I/2007-08/46 dated 31.1.2008. The scope of work included
construction of flyovers, remodeling & covering of Pankha Road Drain and surface
level development works. The work was started on 20.2.2008 and required to be
completed on 19.8.2010, but as per 41st Running Account Bill for ` 85,82,60,041
passed for payment in February, 2013, the work was shown ‘In Progress’.
A review of Running Account Bills and Escalation Bills vide which the
payments were released to the contractor disclosed the following irregularities.
1. Undue and excess payment on account of price escalation under clause 10 CC- ` 37 lakh.
Section 32.10 on Clause 10 CC of Forms No. 7 & 8 of CPWD Works Manual,
2007 provides that:
1. Variation in contract amount due to variations in price of materials, POL
and/or wages of Labour required for execution of work (not for the
materials supplied or services rendered at fixed price in accordance with
Clause 10 and 34), subject to certain conditions.
2. It will be applicable in contracts where the stipulation period of contract is
more than 18 months.
35
3. Payment under this clause is applicable for work done during the
stipulated period of the contract including the justified period extended
under the provision of Clause 5 of the contract without any action under
Clause 2.
4. The contractor shall prepare the statements of escalation or de-escalation
at the end of every three months. The first statement of escalation shall
be prepared at the end of three months, excluding the month in which the
work was awarded. For subsequent statements, cost of work done during
every quarter shall be taken into account.
5. According to Para 32.10.2 of CPWD Works Manual 2007 which deal with
the calculation of cost of work for which escalation/de-escalation is
applicable, the cost of work is computed as per the following formula/
guidelines :-
a- Gross value of work done upto this quarter. ……………………………….(A)
b- Gross value of work done upto the last quarter. ………………………….(B)
c- Gross value of work done since previous quarter (A – B). ………………(C)
d- Full assessed value of secured advance fresh paid in this quarter…. .(D)
e- Full assessed value of secured advance recovered in this quarter….. (E)
f- Full assessed value of secured advance for which escalation is payable in this quarter (D – E). … .…………… ………………………………………….(F)
g- Advance payment made during the quarter. ………………………………(G)
h- Advance payment recovered during the quarter. ………………………..(H)
i- Advance payment for which escalation is payable in this quarter (G –H)..(I)
j- Extra items/deviated quantities of agreement items paid as per clause 12 based on prevailing market rate during this quarter…………………(J)
M= C + F + I – J
N= 0.85 M
k- Less cost of materials supplied by the department as per clause 10 & recovered during the quarter…………………………………………………...(K)
l- Less cost of services tendered at fixed charges as per clause 34 & recovered during the quarter……………………………………………………(L)
36
m- Cost of work for which escalation/de-escalation is applicable
W= N – (K + L)…………………………………………………………………….(M)
Further clause 10 B of N.I.T. condition which deals with “Secured Advance on
Non-Perishable Materials” provides that when materials on account of which an
advance has been made under this sub-clause are incorporated in the work, the
amount of such advance shall be recovered/deducted from the next payment made
under any of the clause or clauses of this contract.
A test check of 34th Running Account Bill/7th Escalation Bill revealed the
following irregularities.
1- The payments of Secured Advance made to the contractor and recoveries
made thereagainst during the execution of work upto 34th Running Account
Bill/7th Escation Bill is as follows:-
Qtr. Period of escalation
Secured Advance paid (̀ )
Secured Advance recovered (`)
Secured Advance balance (`)
1st 2/08 to 4/08 - - -
2nd 5/08 to 7/08 - - -
3rd 1st Escalation
8/08 to 10/08
29,83,000
(IVth R.A.Bill)
- 29,83,000
4th 2nd Escalation
11/08 to 1/09
1,34,38,400
(7th R.A.Bill)
39,44,500 1,24,76,900
5th 3rd Escalation
2/09 to 4/09
4,39,20,617
(XIVth R.A.Bill)
4,51,67,809 1,12,29,708
6th 4th Escalation
5/09 to 7/09
3,52,02,000
(XVIth R.A.Bill)
3,51,66,376 1,12,65,332
7th 5th Escalation
8/09 to 10/09
6,04,88,200
(XIXth R.A.Bill)
3,31,31,200 3,86,22,332
8th
9th
6th Escalation
11/09 to 4/10
4,06,20,830
(XXIIIth R.A.Bill)
2,47,75,800 5,44,67,362
(to be recovered in Xth Qtr.)
19,66,53,047 14,21,85,685 5,44,67,362
10th 7th Escalation
May/10 to Aug/10
2,57,60,000
(34th R.A.Bill)
4,06,20,830
37
It would be seen from the above table that Secured Advance amounting to
` 5,44,67,362 was outstanding for want of recovery upto XXIII Running Account Bill/
6th Escation Bill passed for payment on 27.7.2010.
In the 7th Escalation Bill processed/passed for payment on 24.2.2012, the
department made the recovery of Secured Advance of ` 4,06,20,830 as against
` 5,44,67,362 which was to be actually effected in terms of the ibid provisions of
C.P.W.D. Manual.
2- Further, as per Section 32.10.2.3, the escalation amount should be calculated
on the formula given below.
M = C + F + I – J
N = 0.85 M
According to this, the escalation was payable @ .85 (or 85%) of cost of work
done. But the department did not apply this formula and released @ 1.00 (or
100%) of cost of work done to the contractor.
Thus non effecting of recovery of balance amount of Secured Advance of
` 5,44,67,362 and incorrect calculation of escalation amount (i.e. 1.00 instead of
0.85 or 100/85% of cost of work) has resulted in excess payment of escalation
amount of ` 37,00,690 as worked out below:-
All figures are in (`)
Cost of work on which escalation
Particulars Paid to be paid
A Gross Value of work done upto this quarter (upto25th R.A. Bill)
46,86,60,620 46,86,60,620
B Gross Value of work done upto last quarter (upto21st R.A. Bill)
41,86,10,724 41,86,10,724
C Gross Value of work done since previous quarter (A-B)
5,00,49,896 5,00,49,896
D Full value of Secured Advance fresh paid in 10th quarter (25th R.A. Bill)
2,57,60,000 2,57,60,000
E Full value of Secured Advance recovered in 10th quarter
4,06,20,830 5,44,67,362
38
F Full value of Secured Advance for which escalation is payable (D-E)
(-) 1,48,60,830 (-)2,87,07,362
G Less value of items paid on Market Rates (-) 52,000 (-) 52,000
H Total Value (C+F+G) 3,51,37,066 2,12,90,534
I 85% Cost of work on which escalation was payable (Hx.85)
3,51,37,066 1,80,96,954
Amount of escalation paid/was to be paid components wise is as under
All figures are in (`)
Components Factor (on ‘I’ above)
Escalation paid (worked out by the department
based on ` 3,51,37,060)
Was to be paid (worked out
proportionately based on
` 1,80,96,954)
A Cement 0.15 34,303 17,667
B Steel 0.25 9,26,290 4,77,075
C Material 0.21 15,51,755 7,99,214
D POL 0.05 2,78,072 1,43,218
E Bitumen 0.04 6,27,473 3,23,173
F Plant & Machinery 0.10 5,50,537 2,83,548
G Labour 0.20 36,62,469 18,86,314
H Total 76,30,899 39,30,209
I Escalation excess paid-` (76,30,899-39,30,209)
37,00,690
2. Incorrect application of labour rates under clause 10 CC resulted in excess payment to contractor- ` 22.70 lakh.
Item No.vii (b) given below the item No. vi for computation of escalation
amount on account of labour under clause 10 CC as given in tender document and
general conditions of contract provides that the escalation for labour also shall be
paid at the same quarterly interval when escalation due to increase in cost of
material and/or POL is paid under this clause. If such revision of minimum wages of
an unskilled male mazdoor takes place during any such quarterly intervals, the
escalation compensation shall be payable at revised rates only for work done in
subsequent quarters.
39
The department while calculating the escalation amount on account of labour
for the 7th quarter (August, 2009 to October, 2009) applied the rates of labour
prevalent during 7th Qr. itself instead of previous Qr. (i.e. 6th). Similarly, while
calculating the escalation of 8th & 9th Qr. (November, 2009 to April, 2010) as
combined quarter, the department applied the rates of labour prevalent during the
9th Qr. itself instead of previous Qr. (i.e. 7th). This has resulted in undue and excess
payment of ̀ 22,69,746 as detailed below:
Base Index of labour at the time of N.I.T.- ` 133.45
S.N. Qtr.No. Period of Qtr. 85% amount taken for
computation of escalation on
all items including
advances & overhead in 10
CC bill
(`)
Labour index/rate
paid on amount in Col.No.4
(`)
Amount of escalation
paid on value of Col.4 on
account of labour
(`)
Labour index/rate
due on amount in Col.No.4
(`)
Amount of escalation
due on value of Col.4 on
account of labour
(`)
Excess amount paid on
account of incorrect
application of labour
rate
(`)
1 2 3 4 5 6 7 8 9
1 7 Aug.,2009 to Oct., 2009
8,61,26,236 152.00 23,94,367 151 (6th Qr.)
22,65,291 1,29,076
2 8 & 9 Nov.,2009 to Apr.,2010
5,60,14,216 177.50 36,97,903 152 (7th Qr.)
15,57,233 21,40,670
22,69,746
3. Undue/extra payment towards centering, shuttering cost- ` 5.36 lakh.
In case, estimates are prepared on D.S.R. based, then items for –Centering
Shuttering are included therein, and if estimates are prepared on MORTH based
then the cost of Centering Shuttering stands included in the composite cost of
R.C.C./P.C.C./R.M.C. itself at various percentage rates depending upon the nature of
work in the shape of ‘Form Work’ and no separate items for centering shuttering are
taken therein.
It was noticed that various items of concrete works were found taken from
MORTH Data Book in the schedule of quantities which inter-alia included the
component/cost of centering shuttering in the cost of concrete itself, but the
department wrongly included the items of centering shuttering separately in the bill
of quantities based on D.S.R. 2007 which were not required. This has resulted in
40
undue/extra payment to the contractor amounting to ` 5,35,867 upto 41st Running
Account Bill passed for payment on 15.2.2013 as detailed below:-
S.N. Item of work executed Quantity
(Sqm.) Rate per sqm.
(`) Amount
(`)
1. Centering Shuttering in Walls
885.73 270 2,39,147
2. Centering Shuttering in suspended floor
945 240 2,26,800
3. Centering Shuttering in foundation footings
384.14 240 92,194
4. Centering Shuttering in Colums, Pillars, Piers
64.48 270 17,410
5,75,551
Rebate @ 6.895% (-) 39,684
Net Amount 5,35,867
The matter was brought to the notice of the department in April, 2013 but no
reply has been received so far (October, 2013).
(MCA/RS/DP-21(S)/2011-12)
41
17. Non-enforcement of revised provisions in regard to Quality Assurance Audit/Third Party Testing charges of CPWD Manual for implementation in erstwhile M.C.D. resulting into irregular re-imbursement of Quality Assurance Audit/Third Party Testing charges to contractors - ` 30.65 lakh.
Irregular re-imbursement of Quality Assurance Audit/Third Party Testing charges to contractors amounting to ` 30,65,313 due to non-enforcement of revised provisions in regard to Quality Assurance Audit/Third Party Testing charges of CPWD Works Manual 2010 for implementation in erstwhile M.C.D.
With a view to improving the quality of works, it had been decided by erstwhile
Corporation vide Resolution No. 573 dated 13.2.2003 that hence forth, in all the works
of MCD, quality assurance/audit would be carried out by selected organizations. The
name of selected agencies/organizations were circulated, vide Circular No. D-131/
DIR(T)/03 dated 8.5.2003 with the direction to incorporate this condition in NITs. Later
on vide Circular No. D/EE(P)-III/410 dated 27.7.2005 it was clarified that (i) 1%
weightage for testing charges was to be added while working out the justification.,& (ii)
Testing charges alongwith Service Tax charged, if any, was to be paid by the
Contractor. The rates of testing charges to be added in working out the justification
were further revised and circulated with name of some new agencies vide Circular
No.SE/QC/06-07/D-2816 & 2817 dated 20.2.2007 each for implementation in MCD.
As per Section 20.4.3.1 of CPWD Works Manual, 2010 though the contractor’s
profit and overheads were increased to 15% from earlier 10%, no change has been
made in contractor’s profit which remains @7.5% as applicable earlier whereas the
contractor’s overheads have been increased from 2.5% to 7.5% on account of seven
factors, mentioned therein. One of these factors at S.No. 4 thereof states about “Cost
of Quality Assurance set up enhancing testing lab.” Before enhancement of overhead
charges from 2.50% to 7.5%, a weightage for expenditure to be incurred by contractor
on account of Testing Charges/Third Party Audit was being considered/ added up in the
justification. But after enhancement of overhead charges an inclusion of these
stipulations in Section 20.4.3.1 of CPWD Works Manual 2010, the consideration of
weightage for testing charges in justification was stopped and since then no weightage
for Testing Charges is being given in justification and the expenditure of Third Party
Audit is to be borne by the Contractor. But no such Order/Circular for stoppage of
giving weightage in justification or for re-imbursement of testing charges in cases where
it was not considered in justification, was issued to date as a result of which the
42
contractors were quoting their rates as per the NIT conditions prevailing since 8.5.2003
and getting the re-imbursement of Quality assurance Audit/Third Party testing charges
as if the element on this account was not added up in computing the justification of
rates.
The Executive Engineer (M-III)/Najafgarh Zone and Executive Engineer (M-I)/West
Zone awarded 9 work orders relating to construction of re-modeling of outfall drain,
providing CC payment, Improvement and Strengthening of Road etc. to 4 contractors
during March, 2011 to February, 2012. A scrutiny of the record disclosed that the
department computed the justification of rates in respect of these works in consonance
with the revised provisions contained in Section 20.4.3.1 of CPWD Works Manual, 2010
and accordingly added 15% towards contractor’s profit & overheads. The department
did not add element on account of Quality Assurance audit/third party testing charges
and rightly so since these charges were deemed to be included in the 15% allowed
towards contractor’s profits and overheads. However, the department had allowed/
re-imbursed the amount of IIIrd party quality assurance fee amounting to ` 30,65,313 to
the contractors by obtaining the orders from Engineer-in-Chief, SDMC. This has resulted
in irregular re-imbursement of Quality Assurance Audit/Third party testing charges to
contractors amounting to ` 30,65,313 as detailed below:-
S. N. Work Order No. & Date Name of contractor Amount (`)
EE(M)-III/NGZ 1 54/25.4.2011 Naresh Kumar 3,52,563 2 55/25.4.2011 Esssco Traders 1,70,928 3 56/25.4.2011 Naresh Kumar 4,43,927 4 66/26.4.2011 Naresh Kumar 2,07,019 5 312/22.3.2011 Essco Traders 4,29,779 Total 16,04,216
EE(M)-I/WZ 6 730/31.3.2011 Essco Traders 1,92,737 7 731/31.3.2011 Dabas Const. Co. 1,84,597 8 1105/1.2.2012 R.P.Singhal, & Co. 1,72,432 9 1022/24.1.2012 R.P.Singhal, & Co. 9,11,331 Total 14,61,097 Grand Total 30,65,313
The matter was brought to be notice the department in March, 2013 and in
April, 2013, but no reply has been received so far (October, 2013).
(MCA/RS/DP-19(S)/2011-12)
43
18. Excess payment due to non deduction on account of decrease in price of steel re-inforcement bars under clause 10 CA- ` 24.77 lakh.
No recovery on account of decrease in price of steel re-inforcement bars during the period of completion of work, was made from the bills of the contractors.
In terms of clause 10 (CA) regulating payment due to increase/decrease in
prices of cement, steel re-inforcement bars and bitumen incorporated in the N.I.T. in
pursuance of Planning department’s letter No.D/EE(P)-III/27/2006-07 dated
19.5.2006, if after submission of the tender, the prices of bitumen, cement & steel
re-inforcement bars incorporated in the work (not being a material supplied from
MCD Store) increase (s) beyond the price (s) prevailing at the time of the last
stipulated date for receipt of tender for the work, then the amount of contract shall
accordingly be varied and provided further that any such increase shall not be
payable if such increase has become operative after the stipulated date of
completion of work (including extension, if any) in question.
In the event, the prices of bitumen, cement & steel re-inforcement bars
required for execution of work decrease, the M.C.D. shall in respect of the quantity
of bitumen, cement & steel re-inforcement bars incorporated in the work be entitled
to deduct from the dues of the contractor, such amount as shall be equaling to the
amount worked out on the basis of decrease in ex-refinery price of bitumen (basic
cost + excise + sales tax) and whole sale price index of cement & steel
re-inforcement bars as published by Economic Advisor to Government of India,
Ministry of Commerce & Industry and base price of cement and/or steel
re-inforcement bars prevailing as on the last stipulated date of receipt of tender and
for the period under consideration.
The Executive Engineer (Project-II), West Zone, awarded 3 works relating to
construction of Community Halls/Pucca School Buildings at M.C. Primary Schools. It
was noticed that though the rates/Whole Sale Price Index of steel reinforcement
bars used in the execution of the respective works were found lower during the
period of completion of work as compared to the rates applied by the department at
the time of working out the justification for the award of work in each case but the
44
department did not effect recovery on this account while passing the bills for
payment. Thus an amount of ` 24,77,488.05 remained un-recovered from the
contractors as per details given below:-
Bill-wise Qty. of reinforcement (MD Bar) used
(kg.)
Price of steel bar
taken in JOR
(per Kg.)
(`)
Price Index Difference (per Kg.)
(`)
Amount recoverable on account of price
de-escalation at the time
of hash submission
at the time of execution
Qty. X Rate X diff. / Price Index
(Hash sub.)
(`)
W.O. No.1/23.4.2009 14.11.2008
Ist R.A. Bill 131728.86 Dt. 30.6.2009 IInd R.A. Bill 28511.44 Dt. 30.7.2009
IIIrd R.A. Bill 67414.39 Dt. 30.9.2009
IVth R.A. Bill 112479.60 Dt.30.11.2009
Vth R.A. Bill 36968.98 Dt. 14.1.2010
VIth R.A. Bill 16520.91 Dt. 29.3.2010
VIIth R.A. Bill 3228.67 Dt. 25.5.2011
40.50
40.50
40.50
40.50
40.50
40.50
40.50
326.10
326.10
326.10
326.10
326.10
326.10
326.10
June 2009 282.00
July 2009 282.00
Sep2009 302.20
Nov 2009 302.20
Jan 2010 302.20
Average Rate 1/10 to 3/10
302.80
March, 2011 383.23
44.10
44.10
23.90
23.90
23.90
23.30
-57.13
7,21,479.09
1,56,157.18
2,00,103.52
3,33,868.84
1,09,733.59
47,807.28
-22,908.26
15,46,241.24
W.O. No.45/2.12.2008 29.8.2008
Ist R.A. Bill 22874.60 Dt. 27.2.2009
IInd R.A. Bill 23122.22 Dt. 30.3.2009
IIIrd R.A. Bill 36984.16 Dt. 25.5.2009
IVth R.A. Bill 3541.86 Dt. 29.6.2009
Vth R.A. Bill 9767.86 Dt. 30.9.2009
VIth R.A. Bill 148.18 Dt. 22.2.2010 VIIth Final Bill Nil Dt. 27.8.2010
43.50
43.50
43.50
43.50
43.50
43.50
43.50
335.80
335.80
335.80
335.80
335.80
335.80
335.80
Average Rate Dec/08 to Feb/09
303.03
Mar 2009 282.00
May 2009 282.00
June 2009 282.00
Average Rate 7/09 to 9/09
295.46
Feb 2010 302.20
--
32.77
53.80
53.80
53.80
40.34
33.60
--
97,104.31
1,61,146.30
2,57,754.70
24,684.38
51,043.90
644.97
--
5,92,378.56
45
W.O. No.10/25.5.2009 29.12.2008 Ist R.A. Bill 44334.87 Dt. 30.9.2009 IInd R.A. Bill 49543.92 Dt. 31.12.2009 IIIrd R.A. Bill 0.00 Dt. 29.1.2010 IVth R.A. Bill 17763.14 Dt. 26.5.2010
Vth R.A. Bill 2388.07 Dt. 27.9.2010
40.50
40.50
40.50
40.50
40.50
326.10
326.10
326.10
326.10
326.10
Average Rate 6/09 to 9/09
292.10 Dec 2009
302.20
0.00 Average Rate 2/10 to 5/10 322.00
Average Rate 6/10 to 9/10
341.09
34.00
23.90
326.10
4.10
-14.99
1,87,209.80
1,47,059.30
0.00
9,044.98
-4,445.83
3,38,868.25 Grand Total 24,77,488.05 The irregularity was brought to the notice of the department in September,
2012. The Executive Engineer (Project-II), West Zone intimated (15.5.2013) that an
amount of ` 19,26,467 has been recovered from the contractors against work order
Nos. 1 dated 23.4.2009 and 10 dated 25.5.2009 vide vouchers No.1 dated
11.12.2012 (` 15,99,134) and 34 dated 16.9.2011 (` 3,60,333). As regards
remaining recovery of ` 5,92,380 against work order No.45 dated 2.12.2008, the
same has also been made from security release bill passed on 14.5.2013 against
another work order No.55 dated 6.1.2010 of the same firm (M/s Rakesh Kumar
Gupta). Voucher No. will be intimated after release of security from Head Quarter.
But voucher No. has not been intimated so far (October, 2013).
(MCA/RS/DP-5(S)/2011-12)
46
19. (A). Overpayment due to incorrect computation of quantity of BM and AC mix ` 15.35 lakh.
(B). Overpayment on account of less use of bitumen ̀ 4.24 lakh.
(A). In four cases incorrect computation of quantities of BM & AC mix due to wrong application of yield density resulted in overpayment to the contractors amounting to ` 15,34,941
(B). No recovery for less use of bitumen was made from the contractor which resulted into overpayment of ̀ 4,24,262.
(A) Ministry of Road Transport and Highways (MORT&H) has revised
“Specifications for Road and Bridge Work-Fourth Revision 2001”, due to which
additional conditions for Dense Carpet works in MCD were also circulated for
immediate implementation vide Circular No.250/EE/P-III dated 15.7.2003.
Conditions No. 7,9,13,15 & 21 of additional conditions for dense carpet works
provide that :-
7. The job Mix shall be got designed by the Contractor from Municipal Laboratory
or as per direction of Engineer-in-Charge from CRRI etc. at his own cost. The
mix shall be designed in such a proportion that lab density of 2.2MT/cum. for
BM and 2.3MT/cum. for AC is achieved. Lab density will be defined in the job
Mix.
9. The bituminous work of BM and AC will be acceptable within variation of plus
minus 0.3% of the bitumen required as per JMF. Recovery for less use of
bitumen required as per JMF upto 0.3% than the theoretical consumption shall
be made at the prevailing Market Rate.
13. Measurement: Before applying the tack coat, the existing levels of the road
surface shall be taken jointly by the Engineer-in-Charge or his representative
and contractor at 3 metre intervals both ways or closer as directed by the
Engineer-In-Charge. These levels shall be recorded in the level book as well as
on the plan and the record shall be signed by the contractor. Levels of the
consolidated bituminous course shall again be taken and recorded in the level
book as well as on plan. The unit for measurement shall be cubic metre for
asphaltic concrete and bituminous macadam mix and consolidated quantity
shall be computed on the basis of daily tonnage laid and the field density as
47
well as levels and payment shall be restricted to the lower of the two
quantities. The necessary arrangement for taking levels will be made by the
contractor at his own cost.
15. Material will be tested from Municipal Laboratory or CRRI by the Contractor and
the results will be binding on the Contractor.
21. The field density of leveling course, wearing course shall not be less than 95%
of the laboratory density for leveling course and 98% for the wearing course
respectively.
Three Engineering divisions awarded 4 works relating to Improvement &
Strengthening of Roads to M/s C. Prakashan & Co., M/s. Vinod Kumar and M/s
Radheshyam in which the department did not make applicable the above
provisions. As a result, the department computed the laid quantity of BM and AC
mix based on actual yield density as against desired/required density as per Job Mix
Formula. Thus incorrect computation of quantities of BM & AC mix due to wrong
application of yield density resulted in overpayment to the contractors amounting to
` 15,34,941 as detailed below:-
S. N.
Work Order No. & Date
Item Qty. Laid (in MT)
Density to be
achieved as per JMF
Qty. payable (in cum)
(3/4)
Qty. paid (in cum.
3/4actual)
Excess Qty. paid in cum. (6-5)
Rate / cum
(`)
Amount
(`) EE(Proj.)-I/West Zone, SDMC 1 64/14.11.2011 BM 3384.02 2.257 1499.34 1522.26 22.92 6190 1,41,875 AC 5328.45 2.356 2261.65 2307.75 46.10 8190 3,77,559
Total 5,19,434 2 65/14.11.2011 BM 5923.87 2.257 2624.67 2678.28 53.61 6190 3,31,846 AC 4859.44 2.356 2062.58 2103.86 41.28 8190 3,38,083
Total 6,69,929 EE (Proj.)-II/West Zone, SDMC 3 80/23.1.2012 BM 2805.98 2.243 1251.00 1289.68 38.68 5930 2,29,372
EE (M)-I/West Zone, SDMC 4 500/5.8.2011 BM 554.44 2.235 248.07 258.69 10.62 5575 59,206 DBC 439.71 2.359 186.40 194.00 7.60 7500 57,000 Total 1,16,206
Grand Total 15,34,941
(B) Further, in two works (work order No. 64 & 65 dated 14.11.2011), though the
contactor used less bitumen than that of what required as per DSR but the
department did not make recovery for less use of bitumen in terms of additional
48
condition No. 9 mentioned above. This has further resulted in overpayment to the
contractor amounting to ` 4,24,262 as detailed below:
S. N.
Work Order No. & Date
Item Qty. of mix
brought (MT)
% age of bitumen
to be used as
per item/DSR
% age of bitumen actually used as
per average of samples
Qty. of bitumen as per item / DSR (MT)
Actual bitumen used as
per samples
(MT)
Less bitumen used as
per samples
(MT)
Rate / MT as per
10CA bill
(`)
Amount
(`)
1 64/
14.11.2011 BM 3384.02 3.5 3.410(1no) 118.440 115.395 3.045 43065 1,31,133
DBC 5328.45 5.5 5.473(3no) 293.064 291.626 1.438 43065 61,927 2 65/
14.11.2011 BM 5923.87 3.5 3.431(6no) 207.335 203.248 4.087 43606.66 1,78,220
DBC 4859.44 5.5 5.475(4no) 267.269 266.054 1.215 43606.66 52,982 Total 4,24,262
The irregularity was brought to the notice of the department during
September, 2012 to April, 2013, but no reply has been received so far (October,
2013).
(MCA/RS/DP-7(S)/2011-12)
49
20. Irregularities in testing of Ready Mix Concrete samples ` 11.32 lakh.
Payments amounting to ` 11,31,812 released to the contractors towards providing & laying RMC without examining the authenticity of delivery challans and testing results creates suspicion about the actual execution of this item of work (P/L/ RMC).
According to provisions contained in CPWD specifications for providing and
laying Ready Mix Concrete/Cement Concrete (RMC/CC), samples of C.C. cubes each
of size (15cmx15cmx15cm) for 25 cum or part thereof is required to be taken and
got tested from Laboratory. However, in M.C.D. this is being done for execution of
every 20 cum or part thereof. These samples are lifted on the very day of providing
and laying of Ready Mix Concrete/Cement Concrete and sent on its 7th day for 7
days testing which are got tested in the Municipal Laboratory on the very day of its
receipt. In case of failure of 7 days testing, repeated samples for 28 days testing
are sent on its 28 days and got tested in Laboratory on the very day of their receipt.
The Executive Engineer (M-I), Central Zone awarded three works for
development of roads by providing RMC during 2010-11. All three works were
completed and payments thereagainst released to the respective contractors as
detailed below.
Audit observed following glaring irregularities in the execution of works.
1. RMC challans issued by M/s NPEE Construction, Gurgaon against Work Order
No.135 dated 26.11.2010 were manual instead of computerized. Though
these challans were issued about 9 months before issue of work order, but
S.N Work Order No. & Date
Name of Contractor
Qty. of RMC provided and laid (M-20)
cum and Rate - `/cum + C.E.
Details of delivery Challans (RMC M-20)
Date of Amount
(`)
Sending sample
Testing of sample in Mpl.
Lab. (for 28 days)
1. 135/26.11.2010 M/s Usha Builders
94.46 4471.25 -10.10%
159,162,164,167,169,172,174, 175,195,197, dated 21.2.2010 199,201,203 dated 22.2.2010
28.2.2011 &
1.3.2011
28.2.2011 &
1.3.2011
3,79,696
2. 90/31.05.2011 M/s Manmeet Singh Khurana
84.58 4471.25 -2.22%
07 to 018 dated 20.5.2011 18.7.2011 18.7.2011 3,69,783
3. 183/28.02.2011 M/s Rajeev Enterprises
84.14 4544.01
180,181,183,187,189,190, 198,199 dated 22.3.2011
210,212,214 dated 28.3.2011
29.3.2011 &
5.4.2011
29.3.2011 &
5.4.2011
3,82,333
Total
11,31,812
50
the samples of C.C. cubes were sent on 28.2.2011 and 01.03.2011 and were
tested on the same day for 28 days testing i.e. after one year of procuring
RMC.
2. RMC challans issued by M/s Shiv Raj. Int. Pvt. Ltd. Faridabad against Work
Order No. 90 dated 31.05.2011 were computerized but these were also
issued 11 days before issue of work order. The samples of C.C. cubes were
sent for testing on 18.07.2011 for 28 days testing i.e. after two months of
procuring RMC.
3. The samples of RMC against Work Order No. 183 dated 28.02.2011 were sent
on 7th day (29.3.2011 & 5.4.2011) for 28 days testing rather these samples
should have been sent on 19.4.2011 & 25.4.2011 for 28 days testing.
Thus payments amounting to ` 11,31,812 released to the contractors towards
providing & laying RMC without examining the authenticity of delivery challans and
testing results creates suspicion about the actual execution of this item of work
(P/L/ RMC).
The irregularity was brought to the notice of the department in May, 2012,
but no final reply has been received so far.
(MCA/RS/DP-14(S)/2011-12)
51
21. Payment of Ready Mix Concrete without verifying challans- ` 9.53 lakh.
Payment amounting to ` 9,52,926 was released on the basis of manual delivery challans without verification as the challan Nos. of succeeding dates were found in descending order in comparison to challan Nos. of preceding dates.
Para 5.8.8.9.4 & 5 of C.P.W.D. specification 2002 for cement mortar, cement
concrete and R.C.C. works inter-alia provides that Ready Mix Concrete (R.M.C.)
manufacturer/supplier shall, alongwith each batch of concrete delivered to the
placement contractor, give him a concrete delivery ticket. The supplier shall give
copies of all such delivery tickets to the Engineer-in-Charge for his record and also
get duplicate copies of such delivery tickets duly received and signed from the
contractor. Further R.M.C. as supplied by the manufacture and as placed by the
contractor shall in no way be different from the specifications of concrete as
approved by the Engineer-in-charge.
Further in terms of Section 10.5 of C.P.W.D. Works Manual, 2007 in case of
works where R.M.C. is stipulated to be used from an approved sources/
manufacturers, the computerized dispatch slips that are sent with each dispatch of
R.M.C. shall be kept on record.
The Executive Engineer M-IV, West Zone & Executive Engineer (M-IV),
Central Zone awarded 10 work orders during 2008-09 to 2011-12 for improvement
of Roads/lanes by providing & laying R.M.C. The respective contractor procured the
R.M.C. from M/s Vikas Emark Infrastructure, J.P. Concrete, NPEE Construction & C.S.
Concrete Pvt. Ltd. and laid it on the roads/lanes. The manual delivery
challans/delivery tickets submitted by the contractors disclosed that challan No. of
succeeding dates were found in descending order in comparison to challan No. of
preceeding dates while challan No. 000701 to 000703 of C.S. Concrete Pvt. Ltd.
were shown used twice in two different works by recording different dates as per
52
the following:-
S.N. Work Order No. & Date
Quantity of R.M.C.-M-20 grade
provided & laid (M3)
Challan No. & Date vide which R.M.C. supplied
Rate + C.E. (Per cum)
(`)
Amount
(`)
Executive Engineer (M-IV) West Zone
RMC supplied by M/s Vikas Emark Infrastructure 1 209/21.09.2011 82.32 010698,010700, 702,
703,705,708,709,711,714, 715,717 719/ 23.12.2011
4160.25 (-) 14.50%
-
2 129/2.08.2011 29.55 010779 to 010783 22.12.2011
4160.25 (-) 15%
1,04,495
3 133/2.08.2011 70.89 010722 to 010724 010726 to 010727 730,732,735,738,739 & 010741/ 23.12.2011
4160.25 (-) 10%
-
4 130/2.08.2011 55.96 010771 to 010778/ 22.12.2011 4160.25 (-) 15%
1,97,886
Executive Engineer (M-IV) Central Zone
RMC supplied by M/s J.P. Concrete 5 278/22.03.2011 63.42 4266,4269,4270,4271,4273,4274,
4275/ 10.7.2011 4544.01
URM -
6 7/11.04.2011 89.16 2871,2872,2875,2876,2880,2883, 2884,2886,2889 dated 26.7.2011 2918,2920,2923,2924 dated 29.7.2011
4544.01 URM
4,05,144
RMC supplied by NPEE Construction
7 159/25.02.2009 75.89 4,7,11,17,31,34,35,38,40 & 41 Dated 27.07.2010
4323.95 (-) 5.55%
-
8 158/25.02.2009 21.00 47,50,52, dated 23.7.2010 4323.95 (-) 1.99%
88,996
RMC supplied by C.S. Concrete 9 13/11.04.2011 86.91 000701 to 000703, 000705 to
000708 / 31.10.2011 000715 to 000718, 000721 & 000722 / 1.11.2011
4544.01 URM
-
10 197/17.10.2011 34.42 000700 to 000703, (used twice) 000704 dated 11.11.2011
4544.01 URM
1,56,405
Total 9,52,926
As the challans Nos./tickets Nos. of succeeding dates cannot be in
descending order, and also use of same challans Nos. for two different works, the
veracity of execution of R.M.C. works aggregating to ` 9,52,926 puts a question
mark. Further acceptance of manual delivery challans instead of computerized
delivery challans was also in disregard of Section 10.5 of C.P.W.D. Works Manual.
The irregularity was brought to the notice of the department during October,
2012 to Jan, 2013 but no reply has been received so far (October, 2013).
(MCA/RS/DP-8(S)/2011-12)
53
22. Excess payment due to non deduction on account of decrease in price of bitumen under clause 10 CA- ` 3.21 lakh.
No recovery on account of decrease in price of bitumen under clause 10 CA during the period of completion of work, was made from the bills of the contractor.
In terms of clause 10 (CA) regulating payment due to increase/decrease in
prices of cement, steel re-inforcement bars and bitumen incorporated in the N.I.T. in
pursuance of Planning department’s letter No.D/EE(P)-III/27/2006-07 dated
19.5.2006, if after submission of the tender, the prices of bitumen, cement & steel
re-inforcement bars incorporated in the work (not being a material supplied from
MCD Store) increase (s) beyond the price (s) prevailing at the time of the last
stipulated date for receipt of tender for the work, then the amount of contract shall
accordingly be varied and provided further that any such increase shall not be
payable if such increase has become operative after the stipulated date of
completion of work (including extension, if any) in question.
In the event, the prices of bitumen, cement & steel re-inforcement bars
required for execution of work decrease, the M.C.D. shall in respect of the quantity
of bitumen, cement & steel re-inforcement bars incorporated in the work be entitled
to deduct from the dues of the contractor, such amount as shall be equaling to the
amount worked out on the basis of decrease in ex-refinery price of bitumen (basic
cost + excise + sales tax) and whole sale price index of cement & steel re-
inforcement bars as published by Economic Advisor to Government of India, Ministry
of Commerce & Industry and base price of cement and/or steel re-inforcement bars
prevailing as on the last stipulated date of receipt of tender and for the period under
consideration.
The Executive Engineer-(M)-I, West Zone awarded a work relating to
strengthening of road by providing dense carpeting in Punjabi Bagh/Shivaji Park,
West Zone vide work order No.EE(M-WZ)-I[EE-VII]/SYS/2011-12/1163 dated
15.2.2012 at a contractual amount of ` 75,04,421 with a completion period of 4
months. First R.A. bill amounting to ` 74,54,421 after withholding ` 50,000 was
passed for payment on 30.4.2012.
54
It was noticed that though the rates of bitumen used in the execution of the
work were found lower during the period of execution of work as compared to the
rates applied by the department at the time of working out the justification of rates
for the award of work but the department did not effect recovery on this account
while passing the bill for payment. Thus an amount of ` 3,21,108 remained
unrecovered from the contractor as per details given below:-
S. N. Rate of bitumen Difference in
rates
(`/PMT)
Quantity of bitumen used in the work
(MT)
Recoverable amount
(`)
as per justification of Rates excluding cartage ` 500
(`/PMT)
as per bill submitted by the contractor
(`/PMT)
1 45,802
43,992 1,810 14.830 26,842
2 45,802
43,607 2,195 13.840 30,379
3 45,802
43,607 2,195 14.140 31,037
4 45,802
43,607 2,195 14.250 31,279
5 45,802
43,233 2,569 14.075 36,159
6 45,802
43,233 2,569 14.340 36,839
7 45,802
43,233 2,569 12.910 33,166
8 45,802
43,233 2,569 7.4150 19,049
9 44,839
29,360 15,479 4.933 76,358
3,21,108
The irregularity was brought to the notice of the department in April, 2013,
but no reply has been received so far (October, 2013).
(MCA/RS/DP-25(S)/2011-12)
55
23. Overpayment towards laying Water Bound Macadam- ` 2.83 lakh.
Payment for laying of water bound macadam was made on the basis of net quantity of coarse aggregate supplied and stacked at site instead of taking 80% of the net quantity of coarse aggregate resulting in overpayment of ̀ 2,82,528.
Section 404.2.6 of Specifications for Road & Bridge works of Indian Road
Congress, Ministry of Shipping, Road Transport & highways lays down the
approximate quantities of coarse aggregate (90-45 mm, 63-45 mm and 53-22.4
mm) required to be stacked for 100 mm/75 mm compacted thickness of Water
Bound Macadam (W.B.M.) base coarse for 10 sqm area in TABLE 400-9. Based on
its average requirement and least requirement, the percentage of stone aggregate
that gets reduced during compaction/W.B.M is indicated against each as per details
given in following table.
S. N.
Size Range Required quantity
(M3)
Average quantity required
(M3)
Compacted thickness
(M)
Percentage of Stone Aggregate reduce during compaction/WBM
Based on average
requirement
Based on least
requirement 1 90 mm - 45 mm 1.21 to 1.43 1.32 100 24.24% 17.31% 2 63 mm - 45 mm 0.91 to 1.07 0.99 75 24.24% 17.58% 3 53 mm - 22.4 mm 0.91 to 1.07 0.99 75 24.24% 17.58%
It would be seen from the above analysis that the net quantity of supply &
stacking of stone aggregate (i.e. after allowing 7.5% on account of void) is reduced
by 24.24% based on average requirement and 17.31% to 17.58% based on least
requirement during the course of compaction/ W.B.M. Thus it can be reasonably
expected that compaction would be around (24.24% + 17.31% = 20.77%).
2
Further, in terms of DSR-2002 & 2007 and also as per the approved item
No.10 & 11 circulated by the Planning department vide their letter No.D-37/EE(P)III/
2003 dated 14.1.2003, the payment of laying WBM is made on cubic metre basis
(code 17.6 of DSR-2002 refers). Thus, the department is required to work out and
record in the measurement book the quantity of laid/consolidated/ compacted WBM.
56
The records disclosed that four Engineering divisions awarded 13 work orders
relating to metalling and premixing of road and made payments for laying of WBM
without working out the quantity of the laid/consolidated/compacted thickness of
WBM. The department had adopted the net quantity of coarse aggregate stacked
as the quantity of compacted W.B.M. instead of taking 80% of the net quantity of
coarse aggregate as the quantity of compacted WBM.
Thus making the payment for laying WBM on the basis of net quantity of
supply and stacking of coarse aggregate instead of 80% thereof resulted into an
overpayment of ` 2,82,528 to the respective contractors in 13 cases as
detailed in Annexure ‘C’. The division-wise detail is as under:-
S. N. Divisions No. of Cases Amount (`)
1 EE(Pr.)-I/South Zone 2 58,019 2 EE(Pr.)-II/ South Zone 5 29,640 3 EE(Pr.)/Najafgarh Zone 3 1,21,592 4 EE(M)-I/West Zone 3 73,277 13 2,82,528
The irregularity was brought to the notice of the department during July, 2012
to April, 2013, but no reply has been received so far (October, 2013).
(MCA/RS/DP-6(S)/2011-12)
57
24. Overpayment towards providing & laying Ready Mix Concrete- ` 2.36 lakh.
While framing the estimates for ‘Development/Improvement of road/lane/ gali’ the rate of the item – providing and laying Ready Mix Concrete M-25 & M-20 grade not requiring re-inforcement of steel bars should have been taken as ` 4369.25 per cum (M-25) and ` 4221.95 per cum (M-20) but actually adopted rates were ` 4471.25 per cum & ` 4323.95 per cum respectively. This resulted in overpayment of ` 2,35,994 to contractors.
A test check of record of two Engineering divisions (M-II, South Zone, & M-IV,
Central Zone) disclosed that in preparing the estimates for ‘Development/
Improvement of road/lane/gali’, the department had been inter-alia including an
item relating to providing and laying Ready Mix Concrete M-25 & M-20 @ ` 4,471.25
per cum and ` 4323.95 per cum respectively based on rate provided in D.S.R.-2007
(Item No.16.75 & 16.76). However, an analysis of the said rate as available in Delhi
Analysis of Rates-2007 disclosed that in the computation of the rate of ` 4,471.25
per cum, labour components on account of Mason, Beldar & Bhisti were included as
under which were applicable for R.M.C.- M-25 grade with re-inforcement for steel
bars (Item No.5.37).
(`) Mason 24.91 Beldar 270.50 Bhishti 124.60
420.01
Since, in the pavement of R.M.C. for road/lane/gali etc., the steel bars (viz.
re-inforcement for R.C.C. work) were not used, the department should have
recomputed the rate of this item by including the labour component on account of
Mason, Beldar & Bhisti which was applicable in respect of providing & laying in
position C.C. all work (Item No.4.1.1) as under:
(`) Mason 14.66 Beldar 220.46 Bhishti 96.92
332.04
Based on above, the rate of this item viz. R.M.C.-M-25 grade not requiring re-
inforcement of steel bars works out ` 4,369.25 per cum [4471.25 – 102 (` 420.01 –
58
` 332.04 = ` 87.97 + 1% W.C. + 15% C.P. on account of labour component)] &
` 4221.95 (` 4,369.25 deduct ` 147.30 for using M-20)] and this should have been
taken into account while framing the estimates for such works, but this was not
done. This has resulted in an overpayment of ` 2,35,994 in 27 work orders as
detailed in the Annexure ‘D’. The division-wise breakup is as under:-
S. N. Name of division No. of cases Amount (`)
1 Ex. Engg. M-lV, Central Zone 08 63,097
2 Ex. Engg. M-II, South Zone 19 1,72,897
27 2,35,994
The irregularity was brought to the notice of the department during October,
2012 & March, 2013 but no reply has been received so far (October, 2013).
(MCA/RS/DP-10(S)/2011-12)
59
25. Irregular payment to the contractors towards hiring of tractor trolleys - `. 6.25 lakh.
In 19 cases payment of ` 6,24,948 was irregularly made to the contractors despite deficiencies like non-mention of registration No. of tractor trolleys and name of the drivers & beldars in the Muster Rolls and non-maintenance of log books indicating date-wise work done in each colony.
During the course of audit of DEMS department, Najafgarh Zone, it was noticed
that for lifting of garbage in Ward No. 135 and 133, the department engaged tractor
trolleys with driver, oil and four beldars @ ` 1186 ` 1254 & ` 2000 per day during the
period from 16.9.2009 to 15.11.2010. The department issued muster rolls for
recording attendance of tractor trolley, driver & labours/beldars and payment thereof
to the contractor.
A scrutiny of records disclosed the following irregularities:-
(i) Registration No. of the tractor trolleys which were got engaged and which
received the payment were not found mentioned in the muster roll.
(ii) Name of the drivers & beldars got engaged with the tractor trolleys were not
found mentioned in the muster roll.
(iii) No Log Book indicating date-wise work done in each colony/locality/area and
also mileage covered was placed on record.
The above deficiencies put question mark on the veracity of actual
engagement of tractor-trolleys with oil, drivers & four beldars for lifting of garbage.
Thus this has resulted in irregular payment amounting to ` 6,24,948 to the
contractors as detailed below.
S. N.
Ward No.
Name of Contractor Period Rate of tractor trolley
per day (̀ )
Payment made
(`)
Vr. No. and date vide which
payment made
1 135 Dharam Pal S/o Sh. Tulsi Ram
16.09.2009 to 15.10.2009
1,186 30,836 153-D/11.11.2010
2 135 Dharam Pal S/o Sh. Tulsi Ram
16.10.2009 to 15.11.2009
1,186 30,836 154-D/11.11.2010
3 135 Dharam Pal S/o Sh. Tulsi Ram
16.11.2009 to 15.12.2009
1,186 30,836 155-D/11.11.2010
4 135 Dharam Pal S/o Sh. Tulsi Ram
16.12.2009 to 15.01.2010
1,186 32,022 162-D/11.11.2010
5 135 Dharam Pal S/o Sh. Tulsi Ram
16.01.2010 to 15.02.2010
1,186 30,836 163-D/11.11.2010
60
6 135 Dharam Pal S/o Sh. Tulsi Ram
16.02.2010 to 15.03.2010
1,186 28,464 164-D/11.11.2010
7 135 Dharam Pal S/o Sh. Tulsi Ram
16.07.2010 to 15.08.2010
1,186 30,836 243-D/14.3.2011
8 135 Dharam Pal S/o Sh. Tulsi Ram
16.08.2010 to 15.09.2010
1,186 32,022 246-D/14.3.2011
9 135 Ramesh Kumar S/o Sh. Prem Singh
16.12.2009 to 15.01.2010
1,186 32,022 156-D/11.11.2010
10 135 Ramesh Kumar S/o Sh. Prem Singh
16.01.2010 to 15.02.2010
1,186 30,836 157-D/11.11.2010
11 135 Ramesh Kumar S/o Sh. Prem Singh
16.02.2010 to 15.03.2010
1,186 28,464 158-D/11.11.2010
12 135 Ramesh Kumar S/o Sh. Prem Singh
16.09.2009 to 15.10.2009
1,254 32,611 159-D/11-11-2010
13 135 Ramesh Kumar S/o Sh. Prem Singh
16.10.2009 to 15.11.2009
1,254 32,611 160-D/11.11.2010
14 135 Ramesh Kumar S/o Sh. Prem Singh
16.11.2009 to 15.12.2009
1,186 30,836 161-D/11.11.2010
15 135 Ramesh Kumar S/o Sh. Prem Singh
16.03.2010 to 15.04.2010
1,186 32,022 235-D/14.3.2011
16 135 Ramesh Kumar S/o Sh. Prem Singh
16.07.2010 to 15.08.2010
1,186 30,836 244-D/14.3.2011
17 135 Ramesh Kumar S/o Sh. Prem Singh
16.08.2010 to 15.09.2010
1,186 32,022 245-D/14.3.2011
18 133 Radhey Shyam S/o Sh. Shiv Lal
16.10.2010 to 15.11.2010
2,000 48,000 230-D/14.3.2011
19 133 Raj Kumar S/o Sh. Chhattar Singh
16.10.2010 to 15.11.2010
2,000 48,000 231-D/14.3.2011
Total 6,24,948
The irregularity was brought to the notice of the department in March, 2012
but no reply has been received so far (October, 2013).
(MCA/RS/DP-11(S)/2011-12)
61
26. Irregular payment to the contractor towards hiring of Bajaj GC Max (LMV small)- ` 3.41 lakh.
In 16 cases payment of ` 3,40,611 was irregularly made to the contractors despite deficiencies like the name of the Agency/Contractor which/who was to supply the vehicles for removal of garbage and malba was neither mentioned in the approval nor in the Office Order issued by the S.S., Log Books of the vehicles were not maintained daily, fake reading of meter were shown in the log book etc.
The Chief Engineer-I, circulated the rates of hiring of machinery/equipment to
be used by various departments of MCD vide No. CE-I/2009/D/1300 dated 5.3.2009.
In compliance of this circular, Dy. Commissioner, Najafgarh Zone approved
(23.7.2009) the proposal of the DEMS department to engage 3 Bajaj, GC Max LMV
whose registration Nos were (i) DL-1L-L4800 (ii) DL 1L J9890 and (iii) DL 1L J9915
with two Beldars/Safai Karamcharies on hire charges basis @ ` 1100 per day and
extra charges for additional mileage/distance more than 40 km., for removal of
garbage/malba from ward No. 148, Madhu Vihar during the period 1.8.2009 to
31.3.2010. The DEMS department issued work order/office order on 28.7.2009 to
the contractor for engaging 3 Bajaj, GC Max (LMV small) with the condition to
maintain daily log book and get it authenticated by S.I. daily.
A scrutiny of records relating to payments made to the contractor – M/s
Virender Kashyap and log books of the vehicles disclosed the following
irregularities.
1. The name of the Agency/Contractor which/who was to supply the vehicles for
removal of garbage and malba was neither mentioned in the approval nor in
the Office Order issued by the S.S. for engagement/hiring of the vehicles.
2. Two No. Bajaj GC Max vehicles (bearing Regn. Nos.DL-1L-L4800 &
DL-1L-J9890) with two Beldars/Safai Karamchari were engaged/hired during
the period from 1.8.2009 to 31.3.2010. The payment of ` 3,40,611 was
released to the contractor for the period from 1.8.2009 to 31.1.2010. No bill
for the residual period from 1.2.2010 to 31.3.2010 was submitted by the
contractor for payment.
62
3. Log Books of both the vehicles were not maintained daily. It appeared that
Log Books of both the vehicles viz. vehicle No. D1-1L-L-4800 and DL-1L-J-
9890 were prepared in one go by two different officials on one occasion/same
date as is evident from the expressions of entries made in both the Log
Books, date of submission of bills by the Contractor as well as the date of
payment in respect of all the bills. The Log Books were also not
authenticated by S.I. daily as required in terms of office order dated
28.7.2009.
4. On several occasions during the period from 01.08.2009 to 31.03.2010, the
meter reading at the commencement of the trip and after the conclusion of
the trip was in consecutive order and did not show any gap of even a single
K.M. for many days. It shows that the vehicles did not leave the parking site
even for a single hour for many days for taking fuel/gas etc.
5. The reading of meter recorded in the Log Book in respect of vehicle No.
DL-1L-J-9890 at the commencement of work on 01.09.2009 at 7.00 A.M. was
2511 but after conclusion of trip on 01.09.2009 at 2.30 P.M., it was shown as
2251 instead of 2551. However, fake reading from 2251 to 2551 were again
shown in the Log Book for subsequent 7 more days resulting in bogus
payment for about 7 days amounting to ̀ 7,150.
6. Similarly, the reading of meter of the vehicle No. DL-1L-J-9890 after
conclusion of the work/trip on 17.09.2009 at 2.00 P.M. was 2806. But at the
commencement of the work/trip on next day i.e. 18.9.2009 at 6.30 A.M., it
was shown as 2608 instead of 2806 due to which fake reading was recorded
again for subsequent 5 days, resulting in bogus payment amounting to
` 5,500 for 5 more days.
7. The reading of meter of above vehicle at the commencement of trip/work on
25.03.2010 at 7.30 A.M. was 9087 and after the conclusion of trip at 3. P.M.
on the same day, it was recorded as 10,127 which shows a gap of 1040 kms.,
which is totally impracticable. However, this time this mistake was not
rectified on subsequent dates which shows fake maintenance of Log Book of
the vehicle.
63
The above deficiencies put question mark on the veracity of actual
engagement/hiring of vehicles with engagement of two beldars/safai Karamcharies
for removal of garbage and malba in Ward No. 148 during the period from 1.8.2009
to 31.3.2010. Thus, this has resulted in irregular payment amounting to ` 3,40,611
to the Contractor as detailed below:-
S.N Ward No.
Name of Contractor
Period Regn. No. of Vehicle shown engaged/hired
Rate of tractor trolley
per day (`)
Payment made (`)
1 148 Sh. Virender Kashyap
1.8.2009 to 31.8.2009 DL-1L-L-4800 1,100 27,628
2 148 Sh. Virender Kashyap
1.9.2009 to 30.9.2009 DL-1L-L-4800 1,100 27,279
3 148 Sh. Virender Kashyap
1.10.2009 to 31.10.2009 DL-1L-L-4800 1,100 29,736
4 148 Sh. Virender Kashyap
1.11.2009 to 30.11.2009 DL-1L-L-4800 1,100 27,540
5 148 Sh. Virender Kashyap
1.12.2009 to 31.12.2009 DL-1L-L-4800 1,100 28,600
6 148 Sh. Virender Kashyap
1.1.2010 to 31.1.2010 DL-1L-L-4800 1,100 29,716
7 148 Sh. Virender Kashyap
1.2.2010 to 27.2.2010 DL-1L-L-4800 1,100 No bill submitted by the Contractor for payment
8 148 Sh. Virender Kashyap
1.3.2010 to 31.3.2010 DL-1L-L-4800 1,100 No bill submitted by the Contractor for payment
9 148 Sh. Virender Kashyap
1.8.2009 to 31.8.2009 DL-1L-J-9890 1,100 27,388
10 148 Sh. Virender Kashyap
1.9.2009 to 30.9.2009 DL-1L-J-9890 1,100 27,284
11 148 Sh. Virender Kashyap
1.10.2009 to 31.10.2009 DL-1L-J-9890 1,100 29,784
12 148 Sh. Virender Kashyap
1.11.2009 to 30.11.2009 DL-1L-J-9890 1,100 27,600
13 148 Sh. Virender Kashyap
1.12.2009 to 31.12.2009 DL-1L-J-9890 1,100 29,456
14 148 Sh. Virender Kashyap
1.1.2010 to 30.1.2010 DL-1L-J-9890 1,100 28,600
15 148 Sh. Virender Kashyap
1.2.2010 to 27.2.2010 DL-1L-J-9890 1,100 No bill submitted by the Contractor for payment
16 148 Sh. Virender Kashyap
1.3.2010 to 31.3.2010 DL-1L-J-9890 1,100 No bill submitted by the Contractor for payment
Total 3,40,611
The irregularity was brought to the notice of the department in February,
2012. The department furnished the reply (28.3.2012) which was duly considered
and further audit observations made thereon were issued in April, 2012, but no final
reply has been received so far.
(MCA/RS/DP-15(S)/2011-12)
64
27. Review of Ayurvedic Panchkarma Hospital, Kalu Sarai, S.D.M.C.
Ayurvedic Panchkarma Hospital, Kalu Sarai though evoked good response during 2008-09 but thereafter because practically dormant in giving panchkarma treatment/therapy to the patients/people residing in its catchment area. The hospital has also been losing its appeal for general ayurvedic treatment. There is a need to take a serious call on improving the utilization of doctors/staff of this hospital.
Introduction
Panchkarma is one of the theraputic procedures in Ayurveda. It is aimed at
radical elimination of disease causing factors and maintains the equilibrium of body
tissues (dhatus) and humours (doshas) data. The five fold measures adopted for this
therapy for internal purification of body system are Vaman, Virechan, Anuvasana,
Asthapana & Nasya. Panchkarma therapy is believed to be very effective in the
management of autoimmune disorders, rheumatic arthritis, bronchial asthma, GIT
disorders & mental diseases.
Health department of MCD has been providing preventive, curative &
promotive health services to a large section of population in Delhi. The available
infrastructure is also being used for promoting the management of Panchkarma.
Before initiating proposal for opening of first Panchkarma Hospital in Prashant Vihar,
a team of 9 members went to make a physical study of Panchkarma Unit
functioning in Trivandrum, Kerala on 22.6.2001. The study report was not produced
to Audit.
MCD started with establishing a Panchkarma Hospital at Prashant Vihar,
Rohini under the name “Shri Madhav Rao Sadashiv Rao Golvalkar (Guruji) MCD
Panchkarma Therapy Hospital” during 2001-02 for which the Standing Committee/
Corporation vide Resolution No.260 dated: 27.8.2001 & 418 dated: 17.7.2002
approved the creation of posts in different categories like R.M.S./Officer Incharge,
Medical Officer, Staff Nurse, Compounder, Ward Boy, UDC, LDC etc. Thereafter, 6
more Ayurvedic Panchkarma Hospitals were also established one each in K.B.Zone,
South Zone, S.P.Zone & Shahdara(North) Zone and two in West Zone during
2005-06 to 2007-08.
65
The Standing Committee vide Resolution No. 338 dated 8.11.2006 and the
Corporation vide its Resolution No. 558 dated 11.12.2006 approved the proposal for
opening of an Ayurvedic Panchkarma Hospital, Kalu Sarai and creation of category
‘A’ & ‘C’ posts. A budget provision of ` 140 lakh was made under Plan Head of
Account for the expenditure on establishment, medicines, equipment, furniture,
instruments, equipment and miscellaneous items. This hospital was however
opened on 19.1.2008.
Scope of Audit
The main object of Audit is to review/analyse the performance of the hospital
with regard to effectiveness/utilization of doctors alongwith para-medical staff
posted in the hospital and equipments & other assets purchased/installed with
respect to number of patients treated/cured.
Audit Comments 1. Poor performance of the hospital with respect to strength of Doctors/ para-
medical staff and the patients treated /cured.
The Standing Committee vide Resolution No. 338 dated 8.11.2006 and
Corporation vide Resolution No. 558 dated 11.12.2006 approved the creation of
following posts for this hospital.
1. R.M.S Incharge One
2. Medical Officer (Ay.) Three
3. Compounder (Ay.) One
4. Masseurs Four (Panchkarma Tech.) 5. Staff Nurse Four
6. Ward Boy Four
7. Sweeper Three
The hospital started functioning on 19.1.2008 with the following staff:-
1. R.M.S One
2. M.O. Four
66
3. Compounder (Ay.) One
4. Staff Nurse Three
5. Ward (Aya) Two
6. Sweeper Two
7. Chowkidar One
Year-wise number of patients treated/ cured with respect to the strength of
doctors / para-medical staff is as under:-
Patients treated with Panchkarma Therapy
Year Doctors and Para-medical
Staff
Number of patients treated with Panchkarma
Therapy
Average of patients treated by one doctor
with Panchkarma Therapy per month
19.1.2008 to 31.3.2008 4/6 31 3 2008-09 4/6 156 3 2009-10 4/4 18 Less than one 2010-11 5/4 51 2 2011-12 5/4 29 1 2012-13 4/4 42 2
327
Patients treated with General Ayurvedic treatment
Year Doctors and Para-medical
Staff
Number of patients treated General
Ayurvedic treatment in one year
Average of No. of patients treated by one doctor with General Ayurvedic
treatment
Per month Per day 19.1.2008 to 31.3.2008
4/6 1007 104 4
2008-09 4/6 4096 85 3 2009-10 4/4 1515 32 1 2010-11 5/4 5855 98 4 2011-12 5/4 5958 99 4 2012-13 4/4 6222 130 5
24,653
From the position given in the table, it may be observed that
è Since the opening of the hospital on 19.1.2008 only 327 patients were
treated with Panchkarma therapy, while 24,653 patients were treated with
general Ayurvedic treatment, upto March, 2013.
67
This indicated that the Panchkarma Therapy at this hospital failed to appeal
to patients residing in its catchment area. Even in regard to general Ayurvedic
treatment there is question mark on the quality of service rendered by hospital
doctor/staff as even in 2012-13 average number of patients attended to each by
doctor per day remained were ‘5’.
2. Under utilization of services of Doctors
Thus, though the hospital was opened for giving Panchkarma Therapy to the
patients, but it gave therapy to only 327 patients during Jan, 2008 to 31.3.2013
through 4/5 Medical Officers and 4-6 para-medical staff without Masseurs.
However, the hospital treated 24,653 patients with general Ayurvedic treatment
during the period from 19.1.2008 to 31.3.2013. This indicates that the services of
medical and para-medical staff were only not being properly utilized for the purpose
of providing Panchkarma Therapy and general ayurvedic treatment. Some of the
probable reasons for poor appeal of this hospital to any patient for Panchkarma
Therapy could be as follows:
1. Masseurs, Staff Nurse, Ward Boy/Aya were not appointed/posted in the
hospital.
2. The health department failed to provide medicines and Panchkarma
technicians to this hospital and hospital failed to provide credible services
to the patients.
3. Underutilization of Instruments/Apparatus/Furniture - ` 12.45 lakh.
Instruments / Apparatus/ Furniture costing to ` 12,44,927 were purchased
during the years 2007-08 to 2009-10. The hospital stated that no Instruments/
Apparatus were lying unused in the hospital. However, since a very few patients
were given Panchkarma therapy, the equipment/apparatus meant for Panchkarma
therapy remained grossly under utilized.
4. Non production of records.
Following records/ information were not produced to Audit.
1. Purchase files of instruments, equipments, furniture and medicines.
68
2. Information regarding expenditure incurred on the construction/ renovation of building.
Audit Suggestion:-
Ayurvedic Panchkarma hospital has been loosing its appeal for both
Panchkarma Therapy and general ayurvedic treatment. There is need to take a
serious call on improving the utilization of services of doctors, and infrastructure.
Since the opening of the hospital on 19.1.2008 to 31.3.2013 a negligible number of
patients (327) were treated with Panchkarma therapeutic system. There is hardly
any point in letting the Panchkarma therapy related infrastructure/staff to remain
unused in the hospital. It is, therefore, recommended that the hospital be run as
fullfledged Ayurvedic hospital without the pretence of its being Panchkarma hospital
and may be strengthened accordingly.
(MCA/RS/DP-30(S)/2011-12)
69
28. Wasteful expenditure due to non planting the plants - `. 3.79 lakh.
The entire expenditure of ` 3,79,092 incurred by the department for complete plantations at internal roads through contractor without getting the plants planted in the holes dug for planting proved wasteful.
The Horticulture department, Najafgarh Zone prepared two estimates each of
` 1,89,546 for complete plantation work at internal roads in Madhu Vihar &
Sadh Nagar, Najafgarh Zone in September, 2011 which included following items of
work.
The quantity in respect of each item of work mentioned at S. N. 1 to 5 above
was worked out based on projected requirement of 130 numbers of plants to be
planted. The plants were to be provided by the department.
Two works were awarded vide work order Nos.DDH/NGZ/2011-12/139 dated
19.10.2011 and DDH/NGZ/2011-12/141 dated 19.10.2011 to M/s Archana
Enterprises at a contractual amount of ` 1,89,546 each. The Contractor started the
works on 24.10.2011 and completed them on 1.11.2011 at a total cost of ` 3,79,092
(` 1,89,546 x 2).
A scrutiny of Measurement books No. 11001 and 11003 disclosed that the
Contractor executed all the 5 items mentioned above, but item No. 6 – relating to
Providing/Planting the plants was not executed as the plants were neither issued by
the department to the Contractor for planting nor the department got planted the
plants in the holes dug for planting through departmental labour.
S. N. Description of work Quantity
1. Digging holes in ordinary soil…………. 130 Nos.
2. S/S of good earth …………….. 117 m3
3. S/S of dung manure …………. 58.5 m3
4. P/F of M S Circular type tree guards 130 Nos.
5. Mixing of good earth & manure 175.5 m3
6. Providing/Planting the plants (to be provided by the department)
130
70
Thus the entire expenditure of ` 3,79,092 incurred by the department for
executing the work (Item No. 1 to 5) through the Contractor without getting the
plants planted in the holes dug for planting proved wasteful and needs
investigation.
The irregularity was brought to the notice of the department in June, 2012,
but no reply has been received so far (October, 2013).
(MCA/RS/DP-17(S)/2011-12)
71
29. Review of New Pension Scheme, South Delhi Municipal Corporation.
Non-remittance of NPS Contributions with the concerned Trustee Bank (Bank of India) and in the relevant accounts of Subscribers resulted into over burdening of Municipal exchequer on account of interest of ` 4,81,07,703 and Non-claming of Employer’s Contribution of New Pension Scheme amounting to ` 11,29,64,265 in respect of Employees/Teachers of Education department from Govt. of NCT, Delhi, while seeking reimbursement of 70% of expenditure incurred on Education under different schemes of Non-Plan (Education).
Introduction
The Government of India, Ministry of Finance, vide Notification No. 5/7/2003-
ECB & PR, dated 22.12.2003 published in the Gazette of India, Extraordinary, Part-1,
dated 22.12.2003, introduced a new restructured defined contribution pension
system for new entrants to Central Government Service. The salient features of this
New Pension Scheme are as under:-
1. New pension Scheme is mandatory for all Government servants joining
service on or after 1.1.2004.
2. Government servant has to make contribution @ 10% of his basic pay plus
DA, which shall be deducted from his salary bills every month by the PAO
concerned. The Government shall make an equal matching contribution.
3. In order to implement the scheme, there shall be a Central Record Keeping
Agency and several Pension Fund Managers. An independent Pension Fund
Regulatory and Development Authority (PFRDA) shall regulate and develop
the pension market.
4. Till the regular Central Record Keeping Agency and Pension Fund Managers
are appointed and the accumulated balances under each individual account
is transferred to them, it has been decided that such contributions shall be
kept in the Public Account of India. This will be purely a temporary
arrangement.
As per Ministry of Finance, Government of India, letter No. F. No.5 (31)/2005-
ECB & PR, dated 30.9.2005, accumulations at the credit of subscribers to the new
Pension Scheme shall carry interest @ 8% p.a. and calculation of interest on
72
subscriptions will be done on monthly basis as stipulated in GPF Rules. Ministry of
Finance, O.M. No. CGA, F. No.1 (7)/2003/TA/Part File/177, dated 23.6.2008 further
stated that consequent upon appointment of National Security Depository Limited
(NSDL) as the Central Record Keeping Agency and Pension Fund Managers, the
contributions will be passed on to the Trustee Bank for investment. CDDOs will be
responsible for registering themselves and their NCDDOs on new Pension Scheme
Contribution Accounting Network (NPSCAN) of NSDL and for the following functions:-
(i) Registration of new employees with NSDL as well as notifying NSDL about
changes.
(ii) Preparation and passing of monthly salary bills and bills for the Government
contributions in respect of the Government servant covered under the NPS.
(iii) Remittance of employees and Government contribution to the Trustee bank
preferably by RTGS/NEFT.
(iv) Intimation/uploading of subscriber-wise remittance details to NSDL online and
(v) Maintenance of detailed ledger account
As per Circular No.AO/P/2008-09/D/17,dated 27-08-2008 issued by the Chief
Accountant–cum-Financial Advisor of erstwhile MCD, the deductions of employees
contributions were to be started from the salary for the month of August paid in
September, 2008. The Zonal DCAs were directed to send the amount of deductions
of employees contributions of NPS and matching employer’s contribution of the
same month itself to the HQ by way of ECS in favour of “Commissioner, MCD, A/c-
New Contributory Pension Scheme,2004(1)”, Bank Account No.30385204809, State
Bank of India, Chandni Chowk, Delhi. Further as per Circular No.
DCA/FP/2010/D/103, dated Nil, issued by the Chief Accountant–cum-Financial
Advisor of erstwhile MCD, the deductions of employees will be done through PRAN
(issued by NSDL) and no deductions will be made through PPAN from the month of
November, 2010 onwards.
73
Audit reviewed the system of New Pension Scheme introduced in Accounts
departments of three Zones (viz. West Zone, Central Zone & Najafgarh Zone) of
South Delhi Municipal Corporation for the year 2008-09 to 2011-12 and noticed as
follows.
Para 1 Accumulation of interest due to non- remittance of contributions of New Pension Scheme into Trustee Bank thereby over burdening of Municipal Exchequer- ` 481.08 lakh.
In terms of Chief Accountant-cum-Financial Advisor’s Circular No.
F/DCA/FP/2010/D/103 dated nil following officers were required to be registered with
National Securities Depository Limited, being the Central Record Keeping Agency
under the New Contributory Pension Scheme.
• Principal Accounts Office (Pr. AO)- DCA/Final Payment
• Pay and Accounts Office (PAO)- ACAs of Zones & Hospitals
• Drawing and Disbursing Offices (DDO)- All DDOs
All the employees covered under NPS have to obtain PRAN from NSDL for
implementation of the scheme irrespective of whether they have obtained PPAN or
not. PRAN can be obtained by the DDO/PAO from the facilitation centers of NSDL in
Delhi by submitting duly filled in form ST of the subscribers.
As per the Guidelines laid down for PAOs, the following records are required
to be maintained by them in their offices:-
1. Index Register- for allotment of 16 digit unique code, i.e. PPAN.
2. Ledger Folio- for posting the credits of contributions in the Detailed Ledger
Account of the individual.
3. Broadsheet- for posting of contributions done in ledger shall also be done in
Broadsheet and tallied with accounts figures as being done in the case of GPF
for pre 1.1.2004.
4. Consolidated Information in Floppy- for forwarding the information received
from DDOs in Annexure-III and IV to Principal Accounts Office by PAO.
5. Transfer Cases- The PAO will not transfer any balance to any other PAO.
74
6. Reconciliation after close of each Financial Year- After close of each financial
year, CPAO shall have to report the details of balance PAO wise to each Pr.
AO, who shall forward the information to each PAO for the purpose of
reconciliation. The PAO will reconcile the figure of contributions posted in the
ledger account of the individuals as per their ledger with figures as per the
books of CPAO.
7. Accounting Heads in the books of PAO- For classification of recoveries from
the individual and the Govt. matching contributions as credits.
A review of records i.e. Cash Books, Vouchers and Expenditure Control
Register (ECR) in respect of New Pension Scheme (NPS), maintained in Accounts
Department of three Zones (viz. West Zone, Central Zone & Najafgarh Zone) for the
years 2008-09 to 2011-12 revealed that the Assistant Chief Accountants (PAO) of
the Zones did not remit the NPS contributions amounting to ` 30,27,94,284 to the
Trustee Bank(Bank of India). As per the entries in the Expenditure Control Register
(ECR), the said amount had been deposited in Current Account. The Accounts
Officer (NPS) of erstwhile MCD, requested Asstt. Chief Accountants to upload the
relevant information on CRA System immediately and remit this amount to the
Trustee Bank. i.e. Bank of India. There was nothing on record to show if the
aforesaid amount of subscribers contribution alongwith employer’s contribution of
NPS had been deposited in the concerned Trustee Bank after uploading the relevant
subscriber’s information on Central Record Keeping Agency (CRA) System as
requested by AO/NPS.
Non-remittance of NPS Contributions with the concerned Trustee Bank (Bank
of India) and in the relevant accounts of subscribers resulted into over burdening of
Municipal exchequer on account of interest of ` 4,81,07,703 as detailed below.
S. No.
Name of the Zone
NPS Contribution / not remitted
to Trustee Bank (`)
Interest
(`)
1. West Zone 12,26,91,730 2,50,11,150 2. Central Zone 2,97,29,726 52,97,738 3. Najafgarh Zone 15,03,72,828 1,77,98,815 Total 30,27,94,284 4,81,07,703
75
The P.A.Os of the departments also did not maintain above mentioned
records viz Index Register, Ledger Folio, Broadsheet, etc. and had not done any
reconciliation after the close of each financial year as required in terms of
Guidelines of the scheme. In the absence of which the exact position of
employees/employer’s contribution in respect of individual employee w.e.f.
1-1-2004 to 31-03-2012 and actual number of employees covered under NPS as on
31-3-2012 could not be checked in Audit.
Para 2 Non- claming of Employer’s Contribution of New Pension Scheme in respect of Employees/Teachers of Education Department from Govt. of NCT, Delhi, under Non-Plan (Education) Grant ` 1129.64 lakh.
The Expenditure incurred on Education is met out of Non-Plan Funds of the
erstwhile MCD. Thereafter 70% thereof is reimbursed by Govt. of NCT, Delhi.
It was noticed from the records maintained by Accounts department of West
Zone that during the years 2008-09 to 2011-12 different departments of the zone
had contributed an amount of ` 18,99,18,496 towards employer’s contribution
equivalent to 10% of pay of the employees/ subscribers covered under New Pension
Scheme (N.P.S). This amount of contribution was for the years 2008-09 to 2011-12.
The Accounts department of the zone had not bifurcated this amount between
Education department and other departments in its books of accounts i.e. Cash
Books, Monthly Accounts etc. As a result it could not prefer claim of the amount of
employer’s contributions in respect of the employees working in Education
department from Govt. of NCT, Delhi, while seeking reimbursement of 70%
expenditure incurred on education under different Schemes of Non-Plan
(Education). The expenditure incurred on account of employer’s contribution in
respect of the Education department as worked out in Audit amounts to
` 16,13,77,522.
Apart from this, while seeking re-imbursement of 70% of expenditure
incurred on Education under different schemes of Non-Plan (Education), the
department did not prefer claim of 70% of expenditure amounting to ` 11,29,64,265
towards employer’s contribution. Also no record relating to deduction of
76
contribution towards NPS has been maintained in Accounts departments. Thus this
had over burdened the Municipal exchequer by ` 11,29,64,265.
The matter was brought to the notice of the departments during July, 2013 to
Sept, 2013, but no reply has been received from the department so far.
(MCA/RS/DP-31(S)/2011-12)
77
30. Outstanding temporary advances - ` 2262.48 lakh.
Temporary advances amounting to ` 2262.48 lakh drawn by the drawing & disbursing officers of different departments of the zones during the years 1998-99 to 2011-12 have not been adjusted so far.
Rule 75 of General Financial Rules, 2005 provides that advances to
Government servants and others for special departmental purposes shall be
regulated by special orders issued by Government or an Administrator, as the case
may be. A Government servant who is granted advances from public funds shall be
responsible for its adjustment and/or repayment.
Further, in terms of Commissioner’s Circular No.CA/Adv./43/40/834 dated
16.8.1988, a temporary advance is required to be adjusted immediately after the
transaction for which it was given is over and in no case not later than one month
from the date of drawal of the advance. It will be the personal responsibility of the
Drawing & Disbursing Officer to clear the advance within prescribed time. In case
the adjustment is delayed, the salary of the officer against whom the advance is
outstanding will have to be withheld till proper accounts are rendered.
It was noticed from the Temporary Advance registers maintained in the
Accounts Offices of four Zones and Executive Engineer (E&M)-I that temporary
advances amounting to ` 22,62,48,156 drawn by the Drawing & Disbursing Officers
of different departments of the Zones, during the years 1998-99 to 2011-12 have
not been adjusted so far. The year wise breakup of these advances in respect of
four Zones and Executive Engineer (E&M)-I is as under:-
S.N. Name of Zone / Years Amount (`) 1. Central Zone 2003-04 to 2006-07 53,17,657 2007-08 1,50,64,255 2008-09 2,87,93,760 2009-10 3,05,56,955 2010-11 81,27,811 2011-12 64,58,861 9,43,19,299
2. South Zone 1998-99 53,803 1999-2000 6,12,736 2000-01 21,66,472
78
2001-02 9,28,852 2002-03 5,76,909 2003-04 47,76,437 2004-05 25,49,329 2006-07 3,78,027 2008-09 11,54,745 2009-10 1,33,41,022 2010-11 1,45,65,050 2011-12 5,37,08,298 9,48,11,680
3. Najafgarh Zone 2011-12 1,01,65,984
4. West Zone 2011-12 83,87,214
5. Ex. Engg.(E&M)I 2000-01 37,70,590 2001-02 5,13,447 2005-06 3,26,985 2006-07 57,305 2007-08 39,00,000 2008-09 92,592 2009-10 99,03,060 1,85,63,979 Grand Total 22,62,48,156
The department wise position of these advances in respect of four Zones and
Executive Engineer (E&M)-I is as under:-
S.N. Name of Zone / Name of Drawing & Disbursement Officer
Amount (̀ )
1. Central Zone Dy. Health Officer 29,893 Sanitation Superintendent 6,80,682 Asstt. Commissioner 25,000 Dy. Director (Horticulture) 2,27,256 Dy. Director (Education) 9,31,38,911 A.O. (I.T.) 2,17,557 Total 9,43,19,299
2. South Zone Dy. Health Officer & CAMO 93,896 Sanitation Superintendent 8,82,425 Asstt. Commissioner 80.000 Dy. Director (Horticulture) 5,09,300 Dy. Director (Education) 760,42,792 A.A. & C. 1,14,782 Executive Engineer, Division-I 1,64,19,230 Kasturba Hospital 3,34,255 Executive Engineer, Building-I 3,35,000 Total 9,48,11,680
79
3. Najafgarh Zone Sanitation Superintendent 35,984 Dy. Director (Horticulture) 4,92,600 Dy. Director (Education) 96,37,400 Total 1,01,65,984
4. West Zone Sanitation Superintendent 1,85,756 Dy. Director (Horticulture) 1,21,500 Dy. Director (Education) 80,79,958 Total 83,87,214
5. Ex. Engg. (E&M)-I 1,85,63,979 Grand Total 22,62,48,156
During the course of audit of different offices of the zone it was noticed that
most of the Drawing & Disbursement Officers had not maintained Temporary
Advance registers. As such they were requested to furnish the following
information.
1. Voucher No., date and amount of advance.
2. Head of account and Name of Scheme/Project Under/for which advance drawn.
3. Name of Agency/body for which drawn.
4. Expected date of completion of Project/Scheme/Purpose.
5. Actual date of Completion of Project/Scheme.
6. Whether the department pursued for adjustment of advances after
completion of Project/Scheme, if so, letter No. & date vide which pursed.
7. Whether the department reflects the above vital information in the register of
advances.
Above information were not furnished by the department. In the absence of
such register, the mechanism through which the department kept control over the
drawal as well as adjustments of these advances could not be ascertained.
The matter was brought to notice of the department in July, 2012, but no
reply has been received from the department so far.
(MCA/RS/DP-32(S)/2011-12)
80
31. Outstanding Audit Reports, Inspection Reports and Audit Objections.
The Para indicates the position of outstanding paras of Annual Audit Reports upto the year 2010-11 presented to the Standing Committee as well as the position of Inspection Reports/Audit Notes and objections included therein issued upto 31.3.2013. These Audit Objections and Audit Paras have not been settled in the absence of replies from various departments despite directions of the Corporation for furnishing replies in a fixed time schedule.
(a) Outstanding paras of Audit Reports.
There were 446 Audit Paras relating to financial irregularities commented
upon in the Audit Reports upto the year 2010-11 lying outstanding as on 31.8.2013.
Year-wise number of outstanding paras for the period 1963-64 to 2010-11 in
respect of South Delhi Municipal Corporation is as under:-
Year No. of outstanding paras Details of paras 1963-64 1 14(P) 1964-65 - - 1965-66 - - 1966-67 - - 1967-68 1 45 1968-69 - -
1969-70 1 58(P) 1970-71 - - 1971-72 3 14(P),15(P),16(P) 1972-73 2 9,39 1973-74 1 9(P) 1974-75 4 3(P),4(P),8(P),32 1975-76 8 3(P),4(P),7(P),20(P),
34,52,57,73 1976-77 12 1,2(P),4,5,6,10,18(P),
33(P),35,47, 64,101(P) 1977-78 9 4(P),5(P),9,10,
13,14,18,19,71 1978-79 6 1,3,5,13(P),36,37 1979-80 3 2(P),12(P),36 1980-81 4 16(P),18(P),19(P),20(P) 1981-82 1 2(P) 1982-85 - - 1985-86 2 3,12(P) 1986-87 8 2(P),3(P),5,6(P),
11(P),22,24,25 1987-88 5 3,11(P),22(P), 31(P),32(P)
81
1988-89 1 16(P) 1989-90 3 1(P),2(P),11 1990-91 6 2,4,5,6,8,13 1991-92 4 1(P),5,10,20(P) 1992-93 4 1(P),3(P),14(P),16 1993-94 6 2,4(P),9,10, 30(P),31(P) 1994-95 8 5,8,9,13,15(P), 20(P),22,23 1995-96 17 1(P),2,4,5,8,10,13,
14,15,16,21,23,24, 28(P),29(P),32(P),33(P)
1996-97 21 3,4,6,7,8,9,10,12, 13,14,16,19,22,23, 28,29,32(P),33(P), 37(P),46,55
1997-98 24 5(P),7,8,9,10,11, 12,14,15,16,17,19, 20,21,22,25,26,27, 29,30,32,35(P),47,62
1998-99 21 2(P),3,4,6,7,9,14,15,17, 18,19,25,26,27, 29, 30(P),32,36,38, 49,50(P)
1999-00 22 1(P),2(P),10,15,16,17,18,20,22,25,27,29,32,34,41,43,46,47(P),49(P), 50(P), 51,56
2000-01 28 3(P),4(P),5(P),9,14, 15,16, 17,18,19,20, 21, 23,24, 27,28,29, 32,34,35,36,37, 39, 40,41,43, 48,57(P)
2001-02 32 4,5,7(P),9(P),10(P),11,12(P),13,15,16,17,18,19,21,22,23,27, 28,29,30,31,32,33,37, 41(P),45,48,49,51,60,61,62
2002-03 25 1(P),2(P),3(P),4,6,9(P),14(P),15,19,20,22,23,26,28,29,30, 32,33,38,40,41,49(P)52, 54,56
2003-04 21 1(P),2(P),4(P),5,6,12, 13,15,16,17, 18,19, 24,25,30,38(P),39, 47(P),49,51,53(P)
2004-05 12 3,4,8,9,10,13, 19,29, 30,36, 42,48(P)
2005-06 18 4,8,9,10,11,12,13,14, 18,23(P),27(P),28,29, 30,31(P),33,34(P),39
2006-07 16 1(P),3,5(P),8(P),10,14(P), 15,16(P),21(P),22,23,24(P), 26,30, 31(P),33(P)
2007-08 18 2(P),4,6,11(P),14(P),15(P), 16,19,20,21,23(P),26,27, 29(P),33, 35(P),36(P),39
82
2008-09 24 5,7,9(P),12,14(P),15(P),17, 18(P),19(P),20(P),22(P), 23(P), 26,27(P),28,31,32, 33, 35(P),36(P),39,41, 42(P),43
2009-10 23 3,5(P),7,10,11,13(P),15(P), 17,21,23(P),24(P),25(P),26, 29, 30,31,32,33,37(P), 40,46(P),47(P),48
2010-11 21 1 to 21 Total 446
* P indicates that paragraph contains part observation relating to the SDMC
In addition to above 446 paragraphs there were 47 audit paras of different
Audit Reports which being related to Outstanding Audit Reports, Inspection Reports
& Audit objections, Recoveries made at the instance of audit were more or less
informative in nature.
(b) Outstanding Inspection Reports/Audit Notes & Vouching Notes.
The Corporation vide resolution No.32 dated 3.9.1959 has prescribed a time
limit of one week for disposal of Audit Objections by the departmental officers and
10 days in the case of disposal by the Commissioner.
There were 22,942 Audit Objections/Items, which could not be settled in the
absence of replies. Year-wise number of outstanding Reports and also department
wise outstanding Reports and objections for the period 1964-65 to 2011-12 as on
31.3.2013, is as under: -
Year to which Inspection Reports/ Audit Notes
relate
No. of outstanding Inspection Reports/Audit
Notes
No. of outstanding Items.
1964-65 1 5
1965-66 1 1
1966-67 1 5
1967-68 2 10
1968-69 2 10
1969-70 0 0
83
1970-71 4 23
1971-72 10 45
1972-73 12 72
1973-74 14 84
1974-75 18 119
1975-76 16 113
1976-77 19 160
1977-78 26 193
1978-79 93 549
1979-80 54 318
1980-81 56 321
1981-82 54 332
1982-83 66 407
1983-84 66 397
1984-85 65 444
1985-86 75 544
1986-87 75 570
1987-88 64 481
1988-89 61 557
1989-90 67 607
1990-91 68 651
1991-92 48 518
1992-93 42 478
1993-94 60 770
1994-95 64 755
1995-96 61 780
1996-97 60 775
1997-98 68 829
1998-99 70 966
1999-00 77 971
2000-01 63 855
2001-02 69 896
84
2002-03 76 947
2003-04 69 878
2004-05 63 626
2005-06 74 730
2006-07 91 838
2007-08 80 774
2008-09 71 643
2009-10 66 630
2010-11 81 714
2011-12 56 551
Total 2399 22942
The department wise break up is as under:-
Department No. of outstanding Inspection Reports/Audit Notes.
No. of Items
Engineering 688 8371
Health 583 4010
Accounts 200 1177
Asstt. Commissioner/ Addl. Dy. Commissioner
154 1505
Education 172 1764
Horticulture 147 1529
D.E.M.S. 217 1974
Assessment & Collection 169 2156
Miscellaneous 69 456
Total 2,399 22,942
The accumulation of Inspection Reports/Audit Notes and Audit Observations
to a good number of 2,399 and 22,942 respectively indicates that the departments
concerned have not been following the instructions regarding prompt and proper
disposal of audit objections and queries. They are required to furnish the necessary
explanation, information, documents, records and other particulars, as the case
may be within a week of the receipt of communication from Audit but Audit
Inspection Reports are being treated in a very casual manner by the Municipal
85
Officers who neither reply promptly to the Audit Objections nor discuss the
circumstances in which the irregularities etc. have been allowed to continue. The
primary responsibility for taking appropriate action and clearance of Audit
Objections is of the department concerned and it is obvious that casual treatment
of audit observations weakens the accountability-mechanism. Therefore it is
strongly recommended that the departments should put in place an effective
mechanism to monitor the compliance to audit observations and their settlement.
(MCA/RS/DP-29(S)/2011-12)
86
ANNEXURE – A [Referred to in Para 11]
S.N. Ref. No. of Demolition Charges Register
Property No. Amount
1. 1180 1418/13, Govind puri 5,875/-
2. 1181 T-11, Chruch Road, Jungpura 15,750/-
3. 1183 RZ-2062-63/27, Tuglakabad Extn. 4,700/-
4. 1184 B-68, OIA – Ist 7,050/-
5. 1185 RZ-2514/c/127, Tuglakabad Extn. 5,875/- 4,700/-
6. 1186 RZ-1/4, Gali No. 4, Tuglakabad Extn. 2,350/-
7. 1187 S-357, G.K. Ist 21,000/-
8. 1189 1418/13, Govind puri 5,875/-
9. 1191 1318/8, Govind puri 10,500/-
10. 1193 1049 E/10, Govind puri 2,350/-
11. 1194 779, Sunlight Colony 3,525/-
12. 1195 S-290, G.K.-Ist 26,250/-
13. 1196 185 B, Jeevan Nagar 2,350/-
14. 1198 B-63, Lpn-Ist 34,125/-
15. 1199 B-272, GK-Ist 21,000/-
16. 1200 C-235, Sarita Vihar 7,050/-
17. 1201 E-287, Sarita Vihar 3,525/-
18. 1202 165-B, Jeevan Nagar 7,050/-
19. 1203 601, Sunlight Colony-I 8,225/-
20. 1204 7/7, 7/8, Nehru Nagar 5,825/-
21. 1205 7A, Church Road, Bhogal 8,225/-
22. 1206 B-126, Kalkaji 28,875/- 31,500/-
23. 1208 RZ-48/6, T.B. Extn. 4,700/-
24. 1210 RZ-9/12, Gali No. 11, T.B. Extn. 3,525/-
25. 1212 RZ-4/11, T.B. Extn. 4,700/-
87
26. 1213 RZ-9/16, Gali No. 11, T.B. Extn. 3,525/-
27. 1214 B-126, Kalkaji 1,78,500/-
28. 1215 C-471, Johrikunj Gali K.M. Pur 15,750/-
29. 1217 6/7, 6/8, Nehru Nagar 5,875/-
30. 1222 291/4, Gali No. 4, Govind Puri N. Delhi 11,750/-
31. 1223 C-8, Sanwal Nagar 63,000/-
32. 1224 D-52, O.D.S Lajpat Nagar-IV 21,000/-
33. 1226 349/, Slum Tenants DDA flat Kalkaji 25,100/-
34. 1227 N-192/B, Janta Flats, Sarita Vihar 4,700/-
35. 1228 E-8, Kailash Colony N.D. 33,300/-
36. 1229 1415, Gali No. 13 Govind Puri N. Delhi 5,250/-
37. 1230 1421, Gali No. 13, Govind Puri N. Delhi 7,875/-
38. 1232 1412, Gali No. 3, Govind Puri 15,750/-
39. 1235 RZ-2692/29, TKD Ext. 10,500/-
40. 1236 A-231, OIA Ph-I 5,875/-
41. 1237 95, Sarai Jullena, N.D. 10,500/-
42. 1238 D-1112, New Friends Colony, N.D. 5,250/-
43. 1240 53, Bharat Nagar NFC, N.D. 15,750/-
44. 1241 RZ-535/21, TKD Ext. 7,875/-
45. 1242 RZ-2677/28, TKD Ext. 13,125/-
46. 1243 RZ-2688/29, TKD Ext. 7,875/-
47. 1244 O-12, Sri Niwash Puri 10,500/-
48. 1245 136318, Govind puri 3,525/-
49. 1246 B-85/B (p.no. 126), Kalkaji 1,22,900/-
50. 1247 26, Masihgarh vill. 34,125/-
51. 1248 1359-C, Gali No. 8, Govind Puri 7,050/-
52. 1250 51, Kailash Kunj 18,070/-
53. 1251 New K.G. Khusla Malu Band main 25 feet Road, N.D. 11,750/-
54. 1252 198/32, Ramesh Market Garhi 11,750/-
55. 1253 TA-102 & 103, TKD. Ext. 21,000/-
88
56. 1255 6/5, Nehru Nagar 10,500/-
57. 1256 C-471, Johrikunj 26,250/-
58. 1261 C-118, DDA Flats, Kalkaji 4,200/-
59. 1262 K-1/102, CR Park, ND 21,000/-
60. 1264 B-24, GK-I 4,700/-
61. 1265 50, 11,750/-
62. 1266 Bhogal 136, Hari Nagar Ashram 7,050/-
63. 1268 RZ-176 A/15, TKD. Ext. 2,350/-
64. 1269 RZ-457, Gali No. 14 TKD. Ext. 8,225/-
65. 1270 F-14/10, Joga Bai Ext. 23,625/-
66. 1271 198/32, Ramesh Mkt. Garhi 4,700/-
67. 1272 2/6 Jungpura 10,500/-
68. 1273 P.N. 49 (New N.) 38 (old) church Road Bhogal 4,700/-
69. 1274 Plot No.1, Jungpura Lane, Bhogal 5,875/-
70. 1275 1/21 Double story Jungpura Ext. 23,625/-
71. 1276 Plot No. 1, Suman Bazar 7,850/-
72. 1277 P.N. 105 (num P.N. 107/1) Suman Bazar, Bhogal 7,875/-
73. 1278 C-53, Vishnu Kumar colony 26,500/-
74. 1279 H.N.-86, 8,250/-
75. 1280 23/34 Main Mkt. Badupr. 8,250/-
76. 1281 P.N. 6 Shop No. 2 Dhuruvihar mkt. Badupr. 15,750/-
77. 1282 A-222, Main Mkt. Badupr. 10,500/-
78. 1283 B-10, Main Road Tajpur Road Budpr. 4,125/-
79. 1284 P.N. 105, near P.n. (107/1) Suman Bazar Bhogal 7,875/-
80. 1285 J-64 private colony Sri Niwash puri 7,050/-
81. 1286 Plot No.1 Suman Bazar Bhogal 7,850/-
82. 1287 105, Suman Bazar Bhogal (near p.n. 107/1) 7,875/-
83. 1288 1018, Gali No. 2 Govind puri 7,050/-
Total 12,91,120/-
89
ANNEXURE – B 1 [Referred to in Para 15]
S. N.
W. O. No. & date Qty. of pdg. and laying RMC (M3)
Rate (`)
+ - % age
Amount (`)
E.E – (M-I) – Central Zone 1 364/02.03.2009 68.72 2364.15 (+) 39.86 % 2,27,223 2 362/02.03.2009 95.67 2364.15 (+) 53.88 % 3,48,043 3 137/29.10.2009 54.24 4471.25
-147.30 4323.95
(-) 3.40 % 2,26,557
4 363/02.03.2009 69.61 2364.15 (+) 42.98 % 2,35,300 Total 10,37,123 E.E – (M-II) – Central Zone 5 247/02.03.2009 118.95 2364.15 (+) 04.42 % 2,93,645
6 258/02.03.2009 118.62 2340 (+) 39.44 % 3,87,045 7 177/08.01.2010 75.89 4471.25
-147.30 4323.95
(+) 14.52 % 3,75,791
8 257/02.03.2009 71.64 2364.15 (+) 29.49 % 2,19,314 9 204/25.02.2009 111.60 2364.15 (+) 46.23 % 3,85,812 10 122/17.01.2008 50.60 3490.10 URM 1,76,599 11 205/25.02.2009 102.46 2364.15 (+) 46.00 % 3,53,657 12 24/26.05.2009 62.89 2364.15 (+) 49.00 % 2,21,535 13 48/02.06.2009 51.80 4471.25
-147.30 4323.95
(-) 08.61 % 2,04,696
14 246/02.03.2009 65.28 2364.15 (+) 26.89 % 1,95,832 15 63/16.06.2009 102.28 2364.15 (+) 45.90 % 3,52,794 16 210/25.02.2009 103.36 2364.15 (+) 45.95 % 3,56,641 17 14/21.05.2009 104.56 2364.15 (+) 45.53 % 3,59,744 18 203/25.02.2009 105.68 2364.15 (+) 46.52 % 3,66,071
90
19 200/25.02.2009 107.47 2364.15 (+) 48.52 % 3,77,352 20 218/25.02.2009 64.30 2364.15 (+) 57.02 % 2,38,694 21 216/26.02.2009 100.21 2364.15 (+) 46.52 % 3,47,123 22 208/25.02.2009 112.61 2364.15 (+) 46.23 % 3,89,304 23 43/28.05.2009 105.00 2364.15 (+) 45.00 % 3,59,942 24 207/25.02.2009 101.05 2364.15 (+) 45.90 % 3,48,551 25 79/27.07.2009 81.10 4471.25
-147.30 4323.95
(-) 17.41 % 2,89,620
26 20/26.05.2009 73.77 4471.25 -147.30 4323.95
(-) 17.36 % 2,63,603
27 206/25.02.2009 110 2364.15 (+) 46.02 % 3,79,735 Total 72,43,100 E.E – (M-III) – Central Zone 28 93/16.07.2010 52.77 4471.25
-147.30 4323.95
(-) 08.00 % 2,09,921
29 29/25.07.2009 71.96 4471.25 (+) 08.95 % 3,50,548 30 57/25.05.2011 69.45 4471.25
-147.30 4323.95
(+) 02.15 % 3,06,755
31 38/13.04.2010 26.94 4471.25 -147.30 4323.95
-------- 1,16,487
32 36/13.04.2010 26.59 4471.25 -147.30 4323.95
-------- 1,14,974
Total 10,98,685 Grand Total 93,78,908
91
ANNEXURE – B 2 [Referred to in Para 15]
S. N.
W. O. No. & date Qty. of pdg. and laying RMC (M3)
Rate (`)
+ - % age
Amount (`)
Remarks
E.E – (M-I) – Central Zone 1 140/29.10.2009 79.86 4471.25
-147.30 4323.95
(-) 3.62 % 3,32,810 No batch mix slip and address of RMC Plant .
2 277/15.01.2009 125.09 2364.15 (+) 67.00 % 4,93,872 No batch mix slip No form VAT 3D Haryana
3 240/17.12.2008 61.69 2364.15 (+) 45.05 % 2,11,547 No batch mix slip and address of RMC Plant .
4 224/22.12.2009 82.96 4323.95 (-) 3.265 % 3,47,003 No batch mix slip 5 328/25.02.2009 83.09 2364.15 (+) 51.45 % 2,97,504 No batch mix slip 6 233/22.12.2009 53.22 4323.95 (-) 3.92 % 2,21,100 No batch mix slip No form
VAT 3D Haryana 7 220/16.12.2008 96.29 2364.15 (+) 44.70 % 3,29,401 No batch mix slip No form
VAT 3D Haryana 8 290/29.01.2009 106.74 2364.15 (+) 63.09 % 4,11,557 No batch mix slip , TIN No and
25% fly ash, VAT 3D Haryana 9 219/16.12.2008 95.91 2364.15 (+) 47.00 % 3,33,316 -Do- 10 339/25.02.2009 44.49 2364.15 (+) 47.00 % 1,54,616 No batch mix slip 11 179/11.12.2008 88.55 2364.15 (+) 53.98 % 3,22,350 No batch mix slip 12 142/29.09.2008 70.10 2364.15 (+) 65.50 % 2,74,278 No batch mix slip
and address of RMC Plant . 13 68/26.04.2011 87.94 4544.01 URM 3,99,600 No batch mix slip 14 84/09.07.2009 71.79 2364.15 (+) 54.33 % 2,61,932 No batch mix slip, No form
VAT 3D Haryana 15 176/17.02.2011 106.56 4544.01 URM 4,84,210 No batch mix slip 16 312/03.02.2009 97.41 2364.15 (+) 39.00 % 3,20,106 No batch mix slip 17 181/11.11.2009 79.73 4323.95 (-) 5.76 % 3,24,891 No batch mix slip No form
VAT 3D Haryana and no TIN
92
18 350/26.02.2009 50.24 2364.15 (+) 53.66 % 1,82,510 No batch mix slip No form VAT 3D Haryana and no TIN
Total 57,02,603
E.E – (M-II) – Central Zone 19 173/21.11.2011 84.65 4680.10
136.09 4544.01
URM 3,84,650 No batch mix slip, No TIN and No form VAT 3D Haryana
20 41/28.05.2009 92.44 2364.15 (+) 34.91 % 2,94,835 No batch mix slip No form VAT 3D Haryana
21 36/28.05.2009 60.90 2364.15 (+) 34.91 % 1,94,239 No batch mix slip No form VAT 3D Haryana
22 33/28.08.2009 110.69 2364.15 (+) 49.91 % 3,92,296 No batch mix slip No form VAT 3D Haryana
23 17/05.05.2011 50.70 4471.25 -147.30 4323.95
(-) 6.90 % 2,04,098 No batch mix slip No form VAT 3D Haryana
24 35/19.05.2010 84.11 4471.25 -147.30 4323.95
(-) 05.08 % 3,45,212 No batch mix slip
25 23/26.05.2009 64.96 2364.15 (+) 49.00 % 2,28,827 No batch mix slip No form VAT 3D Haryana and no TIN
26 248/02.03.2009 68.30 2364.15 (+) 32.92 % 2,14,628 No batch mix slip No form VAT 3D Haryana
27 206/29.03.2011 84.46 4471.25 -147.30 4323.95
(-) 4.48 % 3,48,840 No batch mix slip No form VAT 3D Haryana and no TIN
28 184/23.02.2011 71.46 4471.25 -147.30 4323.95
(-) 15.15 % 2,62,178 No batch mix slip No form VAT 3D Haryana and no TIN
29 110/02.09.2011 57.45 4680.10 136.09
4544.01
URM 2,61,053 No form VAT 3D Haryana No batch mix slip
93
30 147/01.10.2011 80.12 4680.10 136.09
4544.01
URM 3,64,066 No batch mix slip No form VAT 3D Haryana
31 132/12.01.2010 92.45 2364.15 (+) 40.55 % 3,07,194 No batch mix slip No form VAT 3D Haryana
Total 38,02,116 E.E – (M-III) – Central Zone 32 133/18.07.2011 70.23 4471.25 (+) 07.89 % 3,38,792 No batch mix slip No form
VAT 3D Haryana 33 132/18.07.2011 79.68 4471.25
-147.30 4323.95
(+) 03.06 % 3,55,075 No batch mix slip and no address of Plant
34 143/02.08.2011 29.00 4680.10 URM 1,35,723 No batch mix slip No form VAT 3D Haryana
35 165/28.09.2011 70.42 4680.10 URM 3,29,573 No batch mix slip 36 132/22.02.2011 62.58 4680.10
136.09 4544.01
URM 2,84,364 No batch mix slip and no address of RMC Plant .
37 104/30.06.2011 88.27 4471.25 -147.30 4323.95
(+) 03.23 % 3,94,003 No batch mix slip and no address of RMC Plant .
38 251/29.12.2011 39.48 4680.10 URM 1,84,770 No batch mix slip and no address of RMC Plant .
39 50/25.05.2011 81.69 4471.25 -147.30 4323.95
(-) 1.38 % 3,48,349 No batch mix slip No form VAT 3D Haryana and no TIN
40 53/25.05.2011 83.83 4471.25 -147.30 4323.95
(-) 1.38 % 3,57,475 No batch mix slip No form VAT 3D Haryana and no TIN
41 155/24.08.2011 73.27 4471.25 -147.30 4323.95
(+) 4.16 % 3,29,995 No batch mix slip No form VAT 3D Haryana and no TIN
42 154/24.08.2011 77.18 4471.25 -147.30
(+) 4.24 % 3,47,872 No batch mix slip No form VAT 3D Haryana and no TIN
94
4323.95 43 127/28.01.2011 71.53 4680.10
136.09 4544.01
URM 3,25,033 No batch mix slip
44 97/18.10.2010 107.32 3785.39 URM 4,06,248 No batch mix slip and address of Plant
45 91/18.10.2010 117.29 3785.39 URM 4,43,988 No batch mix slip and no address of Plant
46 95/18.10.2010 111.26 3785.39 URM 4,21,162 No batch mix slip No form VAT 3D Haryana
47 90/18.10.2010 112.66 3785.39 URM 4,26,462 No batch mix slip and no address of Plant
48 126/28.01.2011 68.76 4680.10 136.09
4544.01
URM 3,12,446 No batch mix slip and no address of Plant
49 49/16.04.2010 80.50 4471.25 -147.30 4323.95
(-) 05.60 % 3,28,586 No batch mix slip and no address of Plant
50 66/01.07.2010 29.65 4471.25 -147.30 4323.95
------- 1,28,205 No batch mix slip and no address of Plant
51 67/01.07.2010 29.82 4471.25 -147.30 4323.95
------- 1,28,940 No batch mix slip and no address of Plant
Total 63,27,061 Grand Total 1,58,31,780
95
ANNEXURE – C [Referred to in Para 23]
S.N. Work Order No. & Date
Qty of stone aggregate supplied & stacked
Qty of laying of W.B.M.
taken as paid
Qty of laying of W.B.M. should be taken i.e. 80% of coarse aggregate
supplied
Qty of WBM excess taken
(20%)
Rate / C.E. Amount
m3 m3 m3 m3 (`) / (%) (`) Ex. Engg. (Proj. I) South Zone
1 144/28.8.2008 1144.68 (63mm-45mm= 766.17)
(53mm-22.4mm= 378.51)
1135.11 915.74 228.94 122 +73.15%
48,362
2 30/21.4.2010 226.64 (53mm-22.4mm)
226.64 181.31 45.33 192.55 +10.64%
9,657
Total 58,019 Ex. Engg. (Proj. II) South Zone
3 69/28.2.2011 54.67 (53 mm-22.4 mm)
54.67 43.74 10.93 220.24 URM
2,407
4 8/16.5.2011 48.37 (53 mm-22.4 mm)
48.37 38.70 9.67 220.24 URM
2,130
5 64/10.2.2011 75.76 (53 mm-22.4 mm)
75.76 60.61 15.15 220.24 URM
3,337
6 20/2.11.2011 255.88 (53 mm-22.4 mm)
255.82 204.70 51.16 192.55 +7.91%
10,631
7 21/2.11.2011 267.94 (53 mm-22.4 mm)
267.94 214.35 53.59 192.55 +7.91%
11,135
Total 29,640 Ex. Engg. (Proj.) Najafgarh Zone
8 56/24.5.2010 113.76 (53mm-22.4mm)
113.76 91.00 22.76 192.55 +16.90%
5,123
9 52/24.5.2010 847.64 (53mm-22.4mm)
847.64 678.11 169.53 192.55 +39.99%
45,697
10 89/22.12.2009 1865.74 (53mm-22.4mm= 1133.87)
(63mm-45mm= 731.87)
1865.70 1492.59 373.15 192.55 - 1.50%
70,772
Total 1,21,592
96
Ex. Engg. (M-I) West Zone 11 211/11.5.2011 214.87
(53mm-22.4mm) 214.87 171.90 42.97 192.55
+ 20.79% 9,994
12 517/26.8.2011 1139.66 (53mm-22.4mm= 572.22) (63mm-45mm= 567.44)
1139.66 911.73 227.93 192.55 + 11.70 %
49,023
13 836/31.3.2010 314.10 (53mm-22.4mm= 152.12) (63mm-45mm= 161.98)
314.11 251.28 62.82 192.55 +17.89%
14,260
Total 73,277 Grand Total 2,82,528
97
ANNEXURE – D [Referred to in Para 24]
S. N. Work Order No. & Date
Qty. of P/L cc pavement of mix RMC- M-25/M-20
(m3)
Difference in rates
(` 4471.25 - ` 4369.25) (` 4323.95 - ` 4221.95)
Contractor’s percentage on
tendered amount + - (%age)
Financial Implication
(`)
Ex. Engg. M-IV, Central Zone
1 8/12.04.2010 81.41 102 (-) 10.23 % 7,454
2 9/12.04.2010 84.38 102 (-) 10.10 % 7,737
3 31/13.04.2010 92.15 102 (-) 1.99 % 9,212
4 30/13.04.2010 92.10 102 (-) 1.99 % 9,207
5 151/25.02.2009 73.93 102 (-) 1.99 % 7391
6 158/25.02.2009 63.44 102 (-) 1.99 % 6,342
7 159/25.02.2009 75.89 102 (-) 5.55 % 7,311
8 247/13.12.2011 61.78 102 (+) 33.99 % 8,443
Total 63,097
Ex. Engg. M-II, South Zone
9 5/20.04.2012 37.22 102 (+) 13.78 % 4,320
10 113/18.03.2011 79.14 102 (+) 2.91 % 8,307
11 120/23.10.2009 79.27 102 (-) 11.01 % 7,195
12 68/15.06.2011 168.90 102 (-) 3.77 % 16,578
13 116/23.10.2009 76.65 102 (-) 8.58 % 7,147
14 75/15.07.2011 218.42 102 (+) 25.05 % 27,860
15 84/25.06.2009 103.26 102 (-) 5.09 % 9,996
16 23/05.06.2009 61.19 102 (-) 8.54 % 5,708
98
17 20/05.06.2009 85.20 102 (-) 2.54 % 8,470
18 22/05.06.2009 74.50 102 (-) 3.33 % 7,346
19 17/05.06.2009 86.64 102 (-) 3.43 % 8,534
20 79/22.06.2009 97.91 102 (-) 5 % 9,487
21 29/05.06.2009 77.13 102 (-) 2.63 % 7,660
22 148/26.11.2009 57.76 102 (+) 21.99 % 7,187
23 21/05.06.2009 70.11 102 (-) 8.43 % 6,548
24 56/08.06.2009 80.21 102 (-) 2 % 8,018
25 99/30.09.2009 59.62 102 (+) 16.16 % 7,064
26 12/20.04.2011 127.81 102 (-) 5.15 % 12,365
27 28/05.06.2009 31.08 102 (-) 2 % 3,107
Total 172897
Grand Total 2,35,994