42
Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan 1 REPORT ON THE EFFECTS OF THE BASE GROUTING / DCM ON DEEP FOUNDATION BORED PILES AT MARINA BAY BUSINESS FINANCIAL CENTRE A Report Presented to the TUCSS for the THE HULME PRIZE 2012 COMPETITION 31 July 2012 Report Submitted by: - - - - - - - - - - - - - - - - - - - - Er. KEE CHING GUAN IC: S7975339D P.Eng. (S'pore), Grad.Eng. (M'sia), MIES, MSSSS-StEr, Grad.IEM, B.Eng. (Hons, NTU, S'pore), M.Sc. (Geot. Eng., NTU, S'pore)

REPORT ON THE EFFECTS OF THE BASE GROUTING / DCM ON … · MBFC, i.e. 2 numbers for dia 1500mm piles, 1 number for dia 1000mm pile and 3 numbers for dia 1200mm piles. The load transfer

Embed Size (px)

Citation preview

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

1

REPORT ON THE EFFECTS OF THE

BASE GROUTING / DCM ON

DEEP FOUNDATION BORED PILES

AT

MARINA BAY

BUSINESS FINANCIAL CENTRE

A Report Presented to the TUCSS for the

THE HULME PRIZE 2012 COMPETITION

31 July 2012

Report Submitted by: - - - - - - - - - - - - - - - - - - - - Er. KEE CHING GUAN IC: S7975339D P.Eng. (S'pore), Grad.Eng. (M'sia), MIES, MSSSS-StEr, Grad.IEM, B.Eng. (Hons, NTU, S'pore), M.Sc. (Geot. Eng., NTU, S'pore)

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

2

ABSTRACT

The author would like to submit his report on one of the project involved in his

engineering life. The project is at Marina Bay Business Financial Centre. The

author would describe his involvement in this project. The focus of this report

would describe the author’s analysis on the instrumented test piles results for the

deep foundation bored piles. The effects of base grouting and Deep Cement Mixing

(DCM) on the pile performance would be described. Encouraging results are

presented and the outcome of the analysis could help in the improvement of the

deep foundation Bored Pile design in Singapore.

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

3

ABSTRACT 2

CONTENT 3

EFFECT S OF BASE GROUTING ON PILES AT

MARINA BAY BUSINESS AND FINANCIAL CENTRE 4

Introduction of Project 4

Problem Analysis 5

Design and Development of Solutions 11

Back analysis and interpretation of the ultimate load tests rests 16

- Effects of base grouting 16

- Effects of improved soil layer 21

- Effects of construction method 23

Quality control & quality assurance for construction of bored piles 25

- Verification of pile performance of working piles 28

Evaluation of Outcomes and Impacts 33

Responsibility for Decisions 34

Managing Engineering Activities 34

Exercising Sound Judgement 41

Communication 41

CONCLUSION 42

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

4

EFFECT S OF BASE GROUTING ON PILES AT

MARINA BAY BUSINESS AND FINANCIAL CENTRE

Introduction of Project

Marina Bay Business and Financial Centre (MBFC) is one of the most iconic

project in Singapore. The author was very grateful that he was able to involve in

this large scale civil engineering works. The author was assigned as a Senior Civil

Engineer with the reputable civil engineering contractor, Tiong Seng Contractors

(Pte) Ltd (TSC). The scope of the construction works, which cost S$100 millions

and undertaken by TSC are:

Deep foundation works (bored piles)

Retaining walls (contiguous bored piles & secant piles)

Soil improvement (deep cement mixing and jet grouting piles)

Geotechnical instrumentation

A&A to the existing Common Services Tunnel

The project involves residential development and commercial development.

Residential development which include 3 high rise tower blocks and 2 podiums.

The author was the Engineer-In-Charge and he has to manage the site execution of

the engineering works and to handle technical issues together with the consultants

and authorities. Design and confirmation of the founding depths for the foundation

bored piles were also his major duty in this project. The author has to work together

with the six geotechnical engineers, who were reported to him.

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

5

Problem Analysis

The proposed site is located at the marina bay area, which has one of the most

difficult geological formations in Singapore. In this project, about 85 numbers of

soil investigation bore holes had been carried out by the SI company, Moh &

Associates as shown. Generally, the formation comprises reclaimed sand/hydraulic

sand fill, upper marine clay, fluvial layer, lower marine clay and old alluvium. Part

of the Tower 2 is located within the area of existing seawalls. The site is next to the

Marina Bay Basin and surrounded by the existing Common Services Tunnel (CST).

The existing MRT North-South Line (NSL) is also passing through Tower 2 and

Phase 3. Both the geological formation and the strategic location determine the

challenges and difficulties for the project.

Generally, the construction sequences are:

Stage 1: Installed geotechnical instruments, such as inclinometers, water

stand pipes, piezometers, vibration meters, prisms and ground settlement

markers.

Stage 2: Installed DCM (If there is, all areas have DCM except R1 &

Podium block at Residential Development).

Stage 3: Coring for grouted DCM layers after 28 days.

Stage 4: Installed bored piles and retaining wall (secant piles & contiguous

bored piles).

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

6

Layout plan for MBFC

Report for TU

CSS TH

E HU

LME 2012 C

ompetition by Er. K

ee Ching G

uan

7

Organisation chart for T

SC at M

BFC

Report for TU

CSS TH

E HU

LME 2012 C

ompetition by Er. K

ee Ching G

uan

8

Soil investigation bore holes location at MB

FC

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

9

General geological formation for MBFC

Thickness ~ 10 to 25m, N≤30

EGL ~ RL 103.500m

Layer 1 - Fill material, Very loose to medium dense hydraulic sand fill

Layer 2A - Very soft to soft marine clay (upper marine clay)

Thickness ~ 10 to 15m, N≤4

Layer 3 - Loose to medium dense silty sand / clay (Fluvial material)

Thickness ~ 5m, N≤4

Layer 2B - Soft to stiff marine clay (lower marine clay)

Thickness ~ 5m, N≤15

Layer 4 - Medium dense clayey to silty sand and stiff to very stiff silty

to sandy clay (Old Alluvium)

Thickness ~ 0 to 10m, 10≤N≤30

Layer 5A - Dense, silty sand and hard, silty to sand clay with some

gravels (Old Alluvium)

Thickness ~ 0 to 10m, 30<N≤50

Layer 5B - Very dense, clayey to silty sand and hard, silty to sandy

clay (Old Alluvium)

Thickness ~ 5 to 15m, 50<N≤100

Layer 6 - Very dense, silty sand and very hard, silty to sandy clay and

sandy silt (Old Alluvium)

Thickness (>>40m)N>100

Dep

th (m

)

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

10

In this report, bored piles were only discussed. Bored piles were the first

engineering works commenced in this project at Residential Development since

there was no basement and no soil improvement was required in this area. In this

project, the geotechnical design for the bored piles is the responsibility of TSC. This

was clearly stated in the contract specifications as “The contractor shall be solely

responsible for the geotechnical design and installation of working piles which

shall support the specified loads with appropriate factor of safety”. Therefore, it

was important to come out the design calculations with the reasonable and

agreeable parameters.

The total numbers of the bored piles in this project. Dia 1800mm bored piles are

designed for the tower blocks and dia 800mm to dia 1200mm are used for the

podium blocks and basement carparks. An appropriate method to construct the deep

foundation with quality control and quality assurance is also very crucial to ensure

that the piles are safe to support the skyscrapers and to complete the project on time.

Area Dia 1800mm

bored piles

800 to 1200 mm

bored piles

Total

R1 & Podium 112 120 232

Tower 1 & 4A Podium 107 95 202

Tower 2 & 4B Podium 207 115 322

3A & 3B Basement Carparks 0 269 269

Parcel A7 UPN 0 30 30

Total 426 629 1055

Numbers of foundation bored piles at MBFC

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

11

Design and Development of Solutions

In order to handle such large extent of the bored piling works at MBFC, a

systematic approach in the design and construction was required to be established

prior commencement of works.

Firstly, design equations and assumed design parameters have been discussed and

agreed with the C&S Consultant, Meinhardt (Singapore) Pte Ltd (MSPL), and

specialist contractors, Resource Piling Pte Ltd (RPPL) and KH Foges Pte Ltd (KH).

In this project, the author was very grateful to work with the following professional

personnel.

MSPL: Er. Kam Mun Wai, Dr. Junied Qureshi (Qualified Person’s

representatives)

TSC: Prof. Harry Tan (TSC’s specialist consultant), Er. Lim Kim Chai & Er.

Dr. Indra ( TSC’s consultants)

RPPL: Er. Foo Hee Kang (Professional Engineer from the specialist

contractor)

KH: Er. Dr. IH Wong (KH’s specialist consultant)

The geotechnical design for the bored pile is:

Case 1: 0.20.2

, ssultsp

AfQQ =≥

Case 2: 5.25.2

,, ppssultpultsp

AfAfQQQ

+=

+≥

Case 3: )5.1

()5.1

( ,,,,

,,

psfsnsfspsfspsfs

nsfspsfs

p AfAf

QQ

Q ηη −=−≥

Where Qp = working capacity the pile;

Qs,ult = ultimate skin resistance (kN)

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

12

fs = ultimate skin friction (kN/m2)

As = Circumference area (m2)

Qp,ult = ultimate base resistance (kN)

fp = ultimate end bearing (kN/m2)

Qs, psf = positive skin resistance below the neutral point (kN)

Qs,nsf = downdrag forces or negative skin friction (kN)

η = mobilisation factor for downdrag forces

The bored piles depth has to be designed to satisfy all the three cases. The assumed

design parameters are shown below:

Ultimate skin friction, fs = 2N for soil with SPT N <100 and fs = 300kN/m2

for soil with SPT N>100;

Ultimate end bearing, fp = 7000kN/m2;

Negative skin friction, fs,nsf = β x σv', where β = 0.35 for sand and β = 0.22

for marine clay.

In order to verify and confirm the design parameters are reasonably correct and

reliable. Six numbers of instrumented ultimate load tests had been conducted in

MBFC, i.e. 2 numbers for dia 1500mm piles, 1 number for dia 1000mm pile and 3

numbers for dia 1200mm piles. The load transfer curves for all the six ultimate load

tests are shown. The summaries of results of the instrumented pile loading tests are

tabulated.

Report for TU

CSS TH

E HU

LME 2012 C

ompetition by Er. K

ee Ching G

uan

13

Ultim

ate load tests plan at MB

FC

A4-UTP01, Dia

A4-UTP01 (Additional), Dia 1200mm

A2-UTP01, Dia

A2-UTP03, Dia

A2-UTP02, Dia

R1-UTP01, Dia

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

14

Fig. 1 Load transfer curves for the ultimate load tests at MBFC

Load Transfer Curves for Ultimate Load Test Piles at Marina Bay Financial Centre

0

5

10

15

20

25

30

35

40

45

50

55

60

65

0 5000 10000 15000 20000 25000 30000 35000 40000

Load (kN)

Dep

th (m

)

R1 - UTP01 (Dia 1500mm,base grouted)

A2-UTP01 (Dia 1200mm,base grouted)

A2-UTP02 (Dia 1000mm,base grouted)

A2-UTP03 (Dia 1500mm,non-base grouted)

A4-UTP01 (Dia 1200mm,non-base grouted)

A4-UTP01 (Additional, Dia1200mm, non-base grouted)

DCM Layer

DCM contribute 7000kN or 1.3WL

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

15

Summaries of results of the instrumented pile loading tests and interpreted results for MBFC

Date of Testing

Sequence of Testing Pile Ref.

Pile Length

(m)

Pile Dimension

(mm)

Pile Working

Load (kN)

Maximum Test Load

( kN / x WL)

Pile Construction Stabilising Fluid

Base Grouting

Within improved soil layer (DCM)

Pile Top Settlement

(mm) at 2 x WL , % of Pile

Dimension

Pile Top Settlement

(mm) at maximum

load , % of Pile

Dimension

Residual Settlement

(mm)

Elastic Shortening

(mm)

Elastic Shortening /

Pile Top Settlement

Pile Toe Settlement

(mm)Stratum

Maximum Mobilised

Skin Friction, fs

(kN/m2)

Mean SPT N-Value

Mean Effective Stress, σv' (kN/m2)

fs/Nβ =

fs/σv'

Undrained Shear

Strength, cu

(kN/m2)

α = fs/cu

Mobilised End

Bearing, fp

(kN/m2)

Remarks

34780 21.63 30.63 Layer 5B, very dense silty sand with SPT N ~ 50 to 100 45 65 470.00 0.69 0.10 NA NA NA

2.62 1.4% 2.0% Layer 6, hard silty sand with SPT N >100 556 100 564.00 5.56 0.99 NA NA 2829.00

26710 20.75 38.63 Layer 5B, very dense silty sand with SPT N ~ 50 to 100 175 70 478.00 2.50 0.37 NA NA NA

3.16 1.7% 3.2% Layer 6, very dense and hard sandy clay with SPT N >100 924 100 541.00 9.24 1.71 NA NA 5684.00

DCM Layer within existing sand fill layer (Marine Clay

start from 16m onwards)375 NA NA NA NA 350.00 0.93 NA

Layer 5B, very dense silty sand with SPT N ~ 50 to 100 38 50 380.00 0.75 0.10 NA NA NA

3.25 0.5% 1.1% Layer 6, very dense silty sand with SPT N >100 214 100 450.00 2.14 0.48 NA NA 335.00

33130 32.25 53.75 Layer 5B, very dense silty sand with SPT N ~ 50 to 100 176 60 434.00 2.933 0.41 NA NA NA

2.50 2.2% 3.6% Layer 6, very dense silty sand with SPT N >100 314 100 525.00 3.14 0.60 NA NA 2829.00

21930 46.5 66.63 Layer 5B, very dense silty sand with SPT N ~ 50 to 100 30 70 430.00 0.429 0.07 NA NA NA

2.60 3.9% 5.6% Layer 6, very dense silty sand with SPT N >100 229 100 528.80 2.29 0.43 NA NA 8860.00

26150 24.25 73.75 Layer 5B, very dense silty sand with SPT N ~ 50 to 100 233 73 430.00 3.192 0.54 NA NA NA

3.09 2.0% 6.1% Layer 6, very dense silty sand with SPT N >100 286 100 537.00 2.856 0.53 NA NA 3713.00

18680

Yes

Yes

Polymer

Constructed with 23.5m long temporary casing to protect the loose and medium dense

sand, boring bucket and cleaning bucket under water.

0.00

13.29

7.46

65.6%

60.8R1-UTP01

A2-UTP01 54.7 8450

Constructed with 31.5m long temporary casing to protect the loose and medium dense

sand, boring bucket and cleaning bucket under water.

Polymer

1500

1200

13250 75.7%23.17

No 25.34

Constructed with 11.3m short casing, using bentonite slurry to stabilise the loose and medium dense sand,

boring bucket and cleaning bucket under water.

No 9.00

12.75

Polymer No

Yes (from 9m to 16m below EGL)

No

Bentonite Yes

No

A2-UTP02 49.9 1000 5750

A2-UTP03 59.3 1500 13250

Constructed with 26.8m long temporary casing to protect the loose and medium dense

sand, boring bucket and cleaning bucket under water.

8450

Constructed with 12.0m short casing, using bentonite slurry to stabilise the loose and medium dense sand,

boring bucket and cleaning bucket under water.

Bentonite No

100.0%11.250.88

35.25 17.15 31.9%

October-06

November-06

July-07

January-07

March-07

June-07A4-UTP01 (Additional

)58.3

A4-UTP01 57.5

36.60

1200 8450

Constructed with 15.0m short casing, using bentonite slurry to stabilise the loose and medium dense sand,

boring bucket and cleaning bucket under water.

Bentonite

50.00 16.21 24.3%

20.17

1200

No No 54.50

Skin friction fully mobilised. End bearing

slightly mobilised.

Skin friction fully mobilised. End bearing substantially mobilised.

DCM layer contributed about 7000kN or 40% of the test load (1.3 times WL). Therefore, skin friction at the lower

layers, Layer 5B & Layer 6 have not mobilised. End bearing has not

mobilised.

Skin friction fully mobilised. End bearing

slightly mobilised.

Skin fricion fully mobilised. End bering fully mobilised. Low

skin friction may due to bentonite filter cake

issue.

Skin friction fully mobilised. End bearing substantially mobilised.

50.42

5.375

27.3% 53.58

1

2

5

3

4

6

11.25

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

16

Back analysis and interpretation of the ultimate load tests results

The skin friction for the six load tests had been fully mobilised or substantially

mobilised at a relative displacement between the pile and soil of about 1.5% to 2%

pile diameter at maximum test loads, except for A2-UTP02. Generally, end bearing

for the test piles was not substantially / fully mobilised due to the fact that the piles

are rather long, from 49m to 60m. It was noted that substantial pile toe settlement of

about 0.5% to 4.5% pile diameter was required in order to slightly or substantially

mobilise the end bearing of the piles from about 2829kN/m2 to 8860kN/m2. It is

also to note that A4-UTP01 (Additional) was compensated and conducted at 6m

away from the A4-UTP01. This was because the pile performance for A4-UTP01

was not satisfactory and did not comply to the contract specifications.

The test results indicate a complex and erratic distribution of the relative pile soil

settlements, mobilised skin friction and mobilised end bearing. Various factors

would have contributed to the test results, such as base grouting, improved soil

layer (DCM) and construction method (different stabilising fluids). In the following

sections, factors affecting the test results would be discussed.

Effects of base grouting

Base grouting was required for all the foundation bored piles as specified in the

contract specifications. It involves installation of a grouting device (dia 32mm TAM

pipe) at the bottom of the steel cages or pile toe. Grouting hoses are attached to the

grouting device for preparation of three stages of post grouting after the pile has

been cast.

R1-UTP01, A2-UTP01 and A2-UTP02 had been base grouted at least 7days before

commencement of the load tests. Refer to Fig. 2, the pile toe settlement of R1-

UTP01 was 7.46mm or 0.49% pile diameter, when the end bearing had been

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

17

mobilised to 2829kN/m2. For A2-UTP01, the pile toe settlement was 13.29mm or

1.1% pile diameter for 5684kN/m2 of end bearing. The other three piles, which did

not base grouted, required 2.44% to 4.5% pile diameter to mobilise 2829kN/m2 to

8860kN/m2 of end bearing. The above results show that effects of base grouting on

pile toe settlements are huge. Base grouted piles required little pile toe movement to

mobilise end bearing compared with non-base grouted piles as shown below.

However, it was suggested that the base grouted pile would not contribute better

end bearing since the cement grout strength is much lesser than the compressive

strength of the pile base material. For A2-UTP02, the end bearing was only slightly

mobilised at 335kN/m2 with zero pile toe movement. The reason for such minimal

mobilisation was due to improved soil layer (DCM).

Fig 2. Pile toe settlement versus mobilised end bearing due to base grouting

Pile toe settlement vs mobilised end bearing

2829, 0.49%

5684, 1.10%

335, 0.00%

2829, 2.44%

8860, 4.20%3713, 4.47%

0.00%

0.50%

1.00%

1.50%

2.00%

2.50%

3.00%

3.50%

4.00%

4.50%

5.00%

0 2000 4000 6000 8000 10000

End bearing (kN/m2)

Pile

toe

settl

emen

t in

per

cent

age

of p

ile d

iam

eter

(% D

)

R1-UTP01 (base grouted)

A2-UTP01 (base grouted)

A2-UTP02 (base grouted)

A2-UTP03 (non-base grouted)

A4-UTP01 (non-base grouted)

A4-UTP01 (non-base grouted)

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

18

Base grouting was not only help to reduce the pile toe movement. It was also help

to enhance tremendously on the skin friction above the pile toe. For R1-UTP01, the

mobilised skin friction increased rapidly from 54m to 60.77m (4.5D from the pile

toe, where D is the pile diameter) and the skin friction was about 626kN/m2 as

shown in Fig. 1. The mobilised skin friction was 924kN/m2 from 52m to 54.7m

(2.25D from the pile toe) for A2-UTP01. However, the mobilised skin friction at the

pile base location was only 229 kN/m2 to 314 kN/m2, for piles without base

grouting. Fig. 3 and Fig. 4 show the relationship between maximum mobilised skin

friction and mean SPT N-value, and maximum mobilised skin friction and mean

vertical effective stress, respectively. The difference between base grouted and non-

base grouted piles are shown clearly in the figures and Table. For example, the

factor of fs/N for layer 6 in R1-UTP01 is 5.6 and for layer 5B is only 0.69; For A2-

UTP01, factors for layer 6 and layer 5B are 9.25 and 2.5, respectively. Based on the

test results, it was concluded that skin friction for base grouted pile shaft at 2D to

4D from toe level would increased from (2.5~3) N to about (6~9) N or from

(0.43~0.6) to (0.99~1.71) for the β-values when comparing with piles without base

grouting. The relationship between beta value and effective stress is shown below.

′×= vsf σβ

δβ tan×= sK

where Ks = lateral earth pressure coefficient

δ = interface friction angle in degrees

σv’ = average effective vertical stress along the pile shaft

Report for TU

CSS TH

E HU

LME 2012 C

ompetition by Er. K

ee Ching G

uan

19

Pile toe settlement vs mobilised end bearing

5684, 1.10%

2829, 2.44%

8860, 4.20%3713, 4.47%

2829, 0.49%335, 0.00%0.00%

0.50%

1.00%

1.50%

2.00%

2.50%

3.00%

3.50%

4.00%

4.50%

5.00%

0 2000 4000 6000 8000 10000

End bearing (kPa)

Pile

toe

settl

emen

t in

per

cent

age

of p

ile d

iam

eter

(% D

)R1-UTP01 (base grouted)

A2-UTP01 (base grouted)

A2-UTP02 (base grouted)

A2-UTP03 (non-base grouted)

A4-UTP01 (non-base grouted)

A4-UTP01 (non-base grouted)

fs/N = 0.5

fs/N = 1.0

fs/N = 1.5

fs/N = 2.0

fs/N = 2.5

fs/N = 3.0

fs/N = 3.5

fs/N = 4.0

fs/N = 5.0

fs/N = 7.0fs/N = 8.0fs/N = 9.0

fs/N=6.0

0

100

200

300

400

500

600

700

800

900

1000

0 50 100 150SPT-N value (N)

Mob

ilise

d sk

in fr

ictio

n (k

N/m

2 )

Fig. 3 Relationship between maximum mobilised skin friction and mean SPT N-value for ultimate test piles at MBFC

Report for TU

CSS TH

E HU

LME 2012 C

ompetition by Er. K

ee Ching G

uan

20

Pile toe settlement vs mobilised end bearing

5684, 1.10%

2829, 2.44%

8860, 4.20%3713, 4.47%

2829, 0.49%335, 0.00%0.00%

0.50%

1.00%

1.50%

2.00%

2.50%

3.00%

3.50%

4.00%

4.50%

5.00%

0 2000 4000 6000 8000 10000

End bearing (kPa)

Pile

toe

settl

emen

t in

per

cent

age

of p

ile d

iam

eter

(% D

)R1-UTP01 (base grouted)

A2-UTP01 (base grouted)

A2-UTP02 (base grouted)

A2-UTP03 (non-base grouted)

A4-UTP01 (non-base grouted)

A4-UTP01 (non-base grouted)

Fig.

β = 0.05 β = 0.1β = 0.2β = 0.3β = 0.4β = 0.5β = 0.6β = 0.7

β = 0.8

β = 1.0

β = 1.5

β = 2.0

β = 0.9

0

100

200

300

400

500

600

700

800

900

1000

0 100 200 300 400 500 600

Effective vertical stress, σv' (kN/m2)

Mob

ilise

d sk

in fr

ictio

n (k

N/m

2 )

Fig. 4 Relationship between maximum mobilised skin friction and mean vertical effective stress for ultimate test piles at MBFC

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

21

Effects of improved soil layer

The 5th ultimate load test pile, A2-UTP02, was installed on 9 June 2007 at 4B

Podium after the DCM had been completed at that area. The improved soil layer

was from RL 94.000m to RL 87.000m (7m thick) or about 9m to 16m from EGL.

The geological profile of the pile is as shown below:

Layer 1, 0 to 15.2m (EGL at RL 103.000m): Loose sand fill;

Layer 2A, 15.2 to 24.6m: Soft marine clay (upper);

Layer 3, 24.6 to 27.6m: Medium stiff silty clay;

Layer 2B, 27.6 to 31.4m: Soft marine clay (lower);

Layer 5A, 31.4 to 35.8m: Very stiff silty clay;

Layer 5B, 35.8 to 39.4m: Hard silty clay and dense silty sand;

Layer 6, 40 to 49.6m: Very dense silty sand.

For this pile, majority of the DCM layer was located within the loose sand layer.

The behaviour of the pile was totally different from the other five piles. The

mobilised skin friction for pile shaft at DCM layer was 375kN/m2, which is as good

as skin friction at soil with SPT N-value greater 100 (refer to Fig. 1 and the Table

above). The DCM layer had contributed about 7000kN skin resistance to the pile

load, which is about 1.3 times of the working load of the pile. Therefore, the skin

friction at the lower layers, such as Layer 5 and Layer 6, had not been substantially

mobilised. The mobilised pile bearing capacity was also minimal, at 355kN/m2.

With the combined effects of base grouting and improved soil layer, the pile toe

settlement is zero. As such, pile top settlement is same as the measured elastic

shortening.

It was noted that all the working piles would behave similar to A2-UTP02, since

DCM had to be completed prior installation of foundation bored piles. However, it

was also worthwhile to note that the rate of pile top settlement was increased

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

22

rapidly from 0.3233x10-3mm/kN to 0.3739x10-3mm/kN when the pile load went

beyond 7000kN/m2 due to the localised effects of high mobilised skin friction at

DCM layer as shown in Fig. 5.

Fig. 5. Rate of pile top settlement for A2-UTP02

0.2000

0.2500

0.3000

0.3500

0.4000

0.4500

0.5000

0.5500

0 2000 4000 6000 8000 10000 12000 14000 16000 18000 20000

Pile Load, P (kN)

Rat

e of

pile

top

sett

lem

ent,

Δ/P

(x 1

0-3 m

m/k

N)

Significant increase in rate of settlement beyond 7000kN

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

23

Effects of construction method

All the piles in MBFC were constructed under water instead of dry pile method due

to the geological formation of the site. The piles were deep, ranging from 50m to

80m and the construction time for one pile was long, boring and casting needed

ranging from about 18hours to 48hours.

Long temporary casings (20 to 30m depend on thickness of sand layer) were

required to protect the loose sand layer when polymer was used as stabilising fluid.

However, only short casing from 6 to 10m was required if bentonite was adopted to

stabilise the loose to medium dense sand layer, very soft to soft marine clay layer

and soft to medium stiff clay and sand layer. The reason that bentonite slurry can

stabilise and prevent the loose to medium dense layer (from toe of the temporary

casing up to the top of the very soft marine clay) from collapse during boring

operation is because the loose to medium dense sand layer is highly permeable.

Bentonite suspensions can seal the hole and provide the gel strength required to

move the solids out of the hole. In other words, it would form a filter cake on those

soil layers that are highly permeable to prevent loose to medium dense sand layer

from collapsing. Therefore, by adopting bentonite as stabilising fluid would have

the following advantages.

Short casing (6 to 10m) instead of long casing (20 to 30m) for polymer;

No joining and welding of casings are required for each individual piles;

Smaller machine / crane is needed;

No vibrator hammer or only smaller capacity of vibrator hammer (eg. 5tons

hammer) is needed for installation and extraction of casings;

Minimal vibration created (this is good for this site as MBFC is located at

LTA MRT railway reserves zone and URA CST 6m protection zone);

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

24

These were the main reasons that driven the ultimate load tests for A2-UTP02, A4-

UTP01 & A4-UTP01 (Additional) to be carried out using bentonite. All the 232

numbers of working piles at R1 & Podium were constructed using polymer and it

required lengthy construction time of four months from October 2006 to February

2007 to complete all the piles. The purpose of carrying out the three load tests using

bentonite was to prove to the Consultants that the piles performance would not be

compromised by adopting bentonite slurry. The successful of this approach would

ultimately shorten the construction period for the commercial development, i.e.

Tower 1, Tower 2, underground carparks and podiums. Total average duration

required to install a 70meter deep foundation bored piles of dia 1800mm with

polymer and bentonite slurry are shown below. It shows that the duration was about

30 percent shorter for piles constructed with bentonite slurry comparing with

polymer slurry.

Average duration required to construction a 70meter deep foundation bored

piles with polymer and bentonite suspensions

However, bentonite supensions do have disadvantage. The filter cake formed

around the pile shaft would affect the skin friction. This was proven in the ultimate

load test A4-UTP01. The fully mobilised skin frictions for this pile were only

Polymer 1 5 12 0.5 6 1.5 30.5 Longer time taken

Bentonite 1 0 12 0 6 0.5 24.0 about 30% faster

Total Remarks

Duration for each activity (hrs)

Lowering Steel Cages

Lowering Tremie Pipes

Extraction of Casings

1.5

1.5

3

3

Stabilising Fluid

1st Casing Installation (max 14m)

2nd Casing Installation (joining and

welding)

Boring Operation

Flushing through

tremie pipe to pile toe, if

sediments >200mm

Concreting

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

25

30kN/m2 for old alluvium (soil layers above layer 6) and 229kN/m2 for layer 6. It

was also need to note that the bore hole with bentonite suspensions was untouched

for at least 24hours when the boring was only few meters to reach the toe level.

This was due to boring rig faulty during the installation. It was concluded that the

thick filter cake was formed during the stoppage period and caused the lower

mobilised skin friction.

In order to verify this finding, another ultimate load test A4-UTP01 (Additional)

was installed and tested at 6m away from A4-UTP01. The pile was constructed in

continuous sequences without any disturbance. The mobilised skin friction for this

pile is much higher than the previous one. The mobilised skin frictions were

233kN/m2 and 286kN/m2 for layer 5 and layer 6, respectively.

Quality control & quality assurance for construction of bored piles

After the analysis and interpretation of the ultimate load tests results, the C&S

Consultant and TSC had decided to adopt the following design parameters for the

working piles. Conservatively, the effects of base grouting and improved soil layer

were not taken into the consideration.

Area Skin friction

(kN/m2) for soil

with SPT N-value

< 100 blows

Skin friction for

soil (kN/m2) with

SPT N-value

> 100 blows

End

bearing

(kN/m2)

R1 & Podium; Tower 1 & 4A

Podium; Tower 2 & 4B Podium;

Parcel A7 UPN

2 N 300 7000

3A & 3B Basement Carparks 2 N 280 4500

Design parameter adopted for working piles in MBFC

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

26

The quality control and quality assurance for the foundation bored piles must be in

placed in order to achieve the design. It was required to closely monitor the

progress of the foundation works due to the tight construction schedule.

Several forms had been created and implemented for the site supervisors and

geotechnical engineers to follow. The objective was to ensure that all the required

information was recorded, such as:

Setting out of the pile

Casing verticality

Time taken for each individual activities, such as casing installation, boring,

lower steel cages, tremie pipes and concreting

Quality of the bentonite / polymer suspensions (Strictly follow BS EN

1536:2000, Clause 6.5.2)

Bored out soil classifications

Ground level, casing level, pile penetration length, pay length and

reinforcement details

Concreting record to verify the wet concrete raising

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

27

Sequences of the bored piles construction

Casing installation

Collar casing

Inner casing

Casings had been installed Join & weld additional casing if required

Seawall removal if any Boring operation

Lowering steel cage with base grouting tubes

Tremie pipe installation Tremie concreting

Testing on bentonite/polymer qualities prior/during boring

and before casting

Sand content (for bentonite only)

PH value

Viscosity Mud balance

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

28

Verification of pile performance of working piles

Total 15 numbers of working load tests had been carried out on the working piles

for MBFC to verify the pile performance. It is noted that all the piles had been base

grouted prior the working load tests. In addition, all the piles are located within the

soil improvement layer except those piles at R1. Therefore, the performances of the

piles are expected to be very good as per the discussion early on the effects of base

grouting and effects of improved soil layer. The author has carried out back analysis

for the load tests on the working piles using Chin’s Stability Plot.

All the working load tests had been loaded to 2 times working load. The pile top

settlements for the four piles at R1, whereby the piles were located outside the

improved soil layer, were measured at 0.8% to 1.7% of pile dimension. Whereas,

the settlements for the 11 piles located within the improved soil layer had

experience lesser values, various from 0.4% to 0.8%. These results are comparable,

where 1.4% and 1.7% for R1-UTP01 and A2-UTP01 (with base grouting & outside

improved soil area) respectively & 0.5% of pile dimension for A2-UTP02 (with

based grouting & within improved soil area).

The estimated average ultimate skin frictions for the entire pile length based on

Chin’s Plot were also lesser, from 69 to 122kN/m2, for piles located outside the

improved soil area than the opposite with higher skin frictions from 101 to

252kN/m2. As mentioned earlier, all the piles had been base grouted before the load

tests. Generally, the skin frictions were only partially mobilised during the load tests

(2 x WL) and the end bearings were not mobilised or only slightly mobilised. The

factor of safeties for all the test piles, based on the estimate ultimate total resistance

and ultimate skin friction, are much higher than the design values of 2.5 and 2.0

respectively. These were shown clearly in the Chin’s Plots and the results on Table.

The results on the working test piles were agreeable with the previous on the effects

of improved soil layer and base grouting. Therefore, it could be concluded that

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

29

performance of the deep foundation in MBFC is extremely good and safe. However,

it also shows that the design of the bored piles was too conservative as resulted

from ignoring the both effects of base grouting and improved soil layer. In the

author’s opinion, the design should take into account on the effects of base grouting

and this would offer a more economical, safe and effective deep foundation system.

As for the other, the effects of improved soil layer shall not be considered in the

design as proposed by the author. The reasons are the effects of consolidation on the

piles would affect the contribution of improved soil layer and this would require

further study and research.

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

30

(a)

Chin’s Stability Plots for the working load tests at MBFC

R1 - WLT#1: R1-12-P35

y = 0.000043x + 0.000477

y = 0.000027x + 0.000649

0.000000

0.000200

0.000400

0.000600

0.000800

0.001000

0.001200

0.001400

0.0 5.0 10.0 15.0 20.0 25.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

R1 - WLT#2: R1-10-P57

y = 0.000070x + 0.000353

y = 0.000043x + 0.000468

0.0000000.000100

0.0002000.000300

0.0004000.000500

0.0006000.000700

0.0008000.000900

0.0 2.0 4.0 6.0 8.0 10.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

R1 - WLT#3: R1-18-T55

y = 0.000019x + 0.000197

y = 0.000010x + 0.000289

0.000000

0.000100

0.000200

0.000300

0.000400

0.000500

0.000600

0.0 5.0 10.0 15.0 20.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

R1 - WLT#4: R1-18-T106

y = 0.000017x + 0.000233

y = 0.000008x + 0.000337

0.000000

0.000100

0.000200

0.000300

0.000400

0.000500

0.000600

0.0 5.0 10.0 15.0 20.0 25.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Commercial - WLT#1: P4C-T18 at Tower 1

y = 0.000019x + 0.000124

y = 0.000014x + 0.000161

0.000000

0.000050

0.000100

0.000150

0.000200

0.000250

0.000300

0.000350

0.000400

0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Commercial - WLT#2: P4C-T99 at Tower 1

y = 0.000015x + 0.000167

y = 0.000010x + 0.000221

0.000000

0.000050

0.000100

0.000150

0.000200

0.000250

0.000300

0.000350

0.000400

0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Commercial - WLT#3: P2A-T126 at Tower 2

y = 0.000013x + 0.000170

0.000000

0.000050

0.000100

0.000150

0.000200

0.000250

0.000300

0.000350

0.0 2.0 4.0 6.0 8.0 10.0 12.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Commercial - WLT #4: P2A-T175A

y = 0.000020x + 0.000092

0.000000

0.000050

0.000100

0.000150

0.000200

0.000250

0.000300

0.0 2.0 4.0 6.0 8.0 10.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

31

(b)

Chin’s Stability Plots for the working load tests at MBFC

Commercial - WLT#5: P4A-P18 at Podium

y = 0.000048x + 0.000262

y = 0.000029x + 0.000348

0.000000

0.000100

0.000200

0.000300

0.000400

0.000500

0.000600

0.000700

0.0 2.0 4.0 6.0 8.0 10.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Commercial - WLT#6: P4A-P12 at Podium

y = 0.000037x + 0.000176

0.000000

0.000050

0.000100

0.000150

0.000200

0.000250

0.000300

0.000350

0.000400

0.0 1.0 2.0 3.0 4.0 5.0 6.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Commercial - WLT#7: P4B-P66 at Podium

y = 0.000042x + 0.000326

0.000000

0.000100

0.000200

0.000300

0.000400

0.000500

0.000600

0.000700

0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Basement Carpark, Parcel A4 - WLT#1: P3A-P71

y = 0.000018x + 0.000362

0.000000

0.000100

0.000200

0.000300

0.000400

0.000500

0.000600

0.0 2.0 4.0 6.0 8.0 10.0 12.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Basement Carpark, Parcel A4 - WLT#2: P3A-P131

y = 0.000013x + 0.000300

0.0000000.0000500.0001000.0001500.0002000.0002500.0003000.0003500.0004000.000450

0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Basement Carpark, Parcel A4 - WLT#3: P3A-P108

y = 0.000018x + 0.000214

0.000000

0.000050

0.000100

0.000150

0.000200

0.000250

0.000300

0.000350

0.000400

0.0 2.0 4.0 6.0 8.0 10.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Basement Carpark, Parcel A4 - WLT#4: P3A-P53

y = 0.000016x + 0.000263

0.000000

0.0000500.000100

0.000150

0.0002000.000250

0.000300

0.0003500.000400

0.000450

0.0 2.0 4.0 6.0 8.0 10.0

Δ, Settlement (mm)

Δ/Q

(mm

/KN

)

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

32

Summaries of results for the working load tests and back analysis results for MBFC

(A) (B) = (C) - (A) (C) (D) = (A) / WL (E) = (C) / WL

S/N Date of Testing Area Pile Ref. Pile Length

(m)Pile Dimension

(mm)

Pile Working Load

(WL, kN)

Maximum Test Load ( kN / x WL)

Pile Construction Stabilising Fluid

Base Grouting

Within improved soil layer (DCM)

Max. Pile Top Settlement

(mm), % of Pile

Dimension

Residual Settlement

(mm), % of Pile Top

Settlement

Estimated ultimate skin friction based on Chin's Plot by

allowing 15% reduction (kN), % of total resistance

Estimated ultimate end bearing based on Chin's Plot by

allowing 15% reduction (kN),

% of total resistance

Estimated ultimate total

resistance based on

Chin's Plot (kN)

Estimated Average ultimate skin friction for entire pile length based on Chin's

Plot (kN/m2)

Estimated ultimate end

bearing at pile base

(kN/m2)

Factor of Safety (ultimate skin

friction)

Factor of Safety (ultimate total

resistance)Remarks

16900 20.75 4.88 19767 11714 31481

2.00 1.7% 23% 63% 37% 100%

9500 7.63 0.25 12143 7625 19767

2.00 0.8% 3% 61% 39% 100%

2.00 1.1% 24% 53% 47% 100%

38000 19.13 4.00 50000 56250 106250

2.00 1.1% 21% 47% 53% 100%

38000 13.25 3.75 44737 15977 60714

2.00 0.7% 28% 74% 26% 100%

38000 14.00 1.50 56667 28333 85000

2.00 0.8% 11% 93% 47% 140%

38000 13.00 1.75 65385 0 0

2.00 0.7% 13% 100% 0% 0%

28500 6.38 1.25 42500 0 0

1.50 0.4% 20% 100% 0% 0%

12220 6.75 1.00 17708 11602 29310

2.09 0.7% 15% 60% 40% 100%

12840 4.50 0.50 22973 0 0

2.19 0.5% 11% 100% 0% 0%

9810 5.75 1.00 20238 0 0

2.07 0.6% 17% 100% 0% 0%

14900 8.00 0.75 47222 0 0

2.10 0.7% 9% 100% 0% 0%

17600 6.75 0.00 65385 0 0

2.08 0.6% 0% 100% 0% 0%

23800 9.41 2.12 47222 0 0

2.07 0.7% 23% 100% 0% 0%

17600 6.50 0.25 53125 0 0

2.08 0.5% 4% 100% 0% 0%

2.98

3.44

6.29

6.65

7.74

4.11

3.03

3.93

4.26

2.24

122

130

160

174

NA

NA

NA

NA

NA

End bearing has not mobilised.

3.73

4.16

4.47

5.59

3.20

4.47

NA

NA

5.01

Bentonite Yes

Yes (from 6.0m to 16.0m

from EGL)

NA22163.8 1200 8450

Constructed with 11.5m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

15 22 Jan 2008

WLT #4 at Basement Carpark,

Parcel A4

P3A-P53

Yes

Yes (from 6.7m to 19.2m

from EGL)

NA End bearing has not mobilised. 164

End bearing has not mobilised.

14 7 Mar 2008

WLT #3 at Basement Carpark,

Parcel A4

P3A-P108 65.7 1400 11500

Constructed with 7.0m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

Bentonite

Bentonite Yes

Yes (from 5.7m to 19.7m

from EGL)

NA25268.9 1200 8450

Constructed with 8.0m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

13 22 Mar 2008

WLT #2 at Basement Carpark,

Parcel A4

P3A-P131

Yes

Yes (from 3.0m to 18.7m

from EGL)

NA End bearing has not mobilised. 216

End bearing has not mobilised.

12 15 Feb 2008

WLT #1 at Basement Carpark,

Parcel A4

P3A-P71 63.4 1100 7100

Constructed with 7.2m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

Bentonite

Bentonite Yes

Yes (from 3.0m to 13.0m

from EGL)

NA11661.6 900 4750

Constructed with 6.0m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

11 17 Dec 2007WLT #7 at

Commercial, Podium

P4B-P66

Yes

Yes (from 4.0m to 16.0m

from EGL)

NA End bearing has not mobilised. NA12510 26 Dec 2007

WLT #6 at Commercial,

PodiumP4A-P12 58.5 1000 5850

Constructed with 6.0m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

Polymer

Bentonite Yes

Yes (from 3.0m to 16.1m

from EGL)

1477210155.9 1000 5850

Constructed with 6.0m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

9 10 Nov 2007WLT #5 at

Commercial, Podium

P4A-P18

Yes

Yes (from 4.0m to 16.8m

from EGL)

NA End bearing has not mobilised. 104

End bearing has not mobilised.

8 14 Nov 2007WLT #4 at

Commercial, Tower 2

P2A-T175A 72.3 1800 19000

Constructed with 7.0m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

Polymer

Polymer Yes

Yes (from 2.5m to 16.8m

from EGL)

NA

11134

7 2 Oct 2007WLT #3 at

Commercial, Tower 2

P2A-T126 66.4 1800 19000

Constructed with 7.2m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

1

2

34.50

WLT #1 at Residential

WLT #2 at Residential

WLT #3 at Residential

19.00

8 Feb 2007

6 Mar 2007

10357

9708

15822

2.34

2.56

2.34

2.63

85000

99

69

110

4 17 Apr 2007 WLT #4 at Residential R1-18-T106

5 17 Sep 2007WLT #1 at

Commercial, Tower 1

P4C-T18

72.2 1800 19000

60.7 1800 19000

30 Mar 2007

Constructed with 28.8m long temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

Constructed with 7.0m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

44737R1-18-T55 71.6 1800 19000

Constructed with 25.0m long temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

38000 40263

Polymer Yes

Yes (from 4m to 16m

from EGL)

Polymer Yes No

NoPolymer Yes

22105

6279 2.35

6 2 Oct 2007WLT #2 at

Commercial, Tower 1

P4C-T99 Polymer Yes

Yes (from 3.5m to 15.6m

from EGL)

4750

Constructed with 16.8m long temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

Polymer

62.7 1800 19000

Constructed with 9.5m short temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

1200

1000

8450

Constructed with 21.7m long temporary casing to protect the loose and medium dense sand, boring bucket and cleaning

bucket under water.

53.2R1-12-P35

R1-10-P57 56.1

Yes

Yes

Polymer No

No

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

33

Evaluation of Outcomes and Impacts

The project is situated at the Marina Bay, an artificial bay formed by reclamation,

which will be developed to further support Singapore’s continuing growth as a

major business and financial hub. Marina Bay Business Financial Centre is the first

few developments in this area. Future developments around Marina Bay would also

have the similarities as the current development, i.e. high rise buildings supported

by deep foundation and deep basements which required soil improvements works to

form the earth retaining or stabilising structure. Thus it was important to understand

the deep foundation and soil improvements behaviours and to develop more reliable

and economical in the design and construction methods in Marina Bay.

In this section, the author discussed the behaviour of the bored piles at MBFC. The

findings are useful and would have great impacts in the future projects if there are

adopted in the design and construction. The findings are summarised below:

Foundation bored piles

Effect of base grouting – Take into account of the contribution of base

grouting on the skin friction, i.e. base grouted pile shaft at 2D to 4D from

toe level, adopt 6~9N or 0.99 to 1.71 (β-value).

Impacts: Pile penetration depths would have been reduced by 10 to 30%,

that will save cost and construction duration.

Effect of DCM – Take into account of the contribution from the improved

soil layer, i.e. skin friction of 375kN/m2 for the pile shaft within the

improved soil layer.

Impacts: Pile penetration depths could be reduced.

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

34

Effect of construction methods – Excavation of bored pile under bentonite

suspension would be faster compared with polymer suspension in Marina

Bay area. This is because shorter temporary casing and smaller machinery

are only required under bentonite suspension.

Impacts: The construction duration for the deep foundation works could be

reduced by at least 30%.

Responsibility for Decisions

In this large scale engineering project, the author, as Senior Civil Engineer, was

responsible for the supervision of the Geotechnical Engineers, site supervisors and

sub-contractors to ensure all the engineering activities to be carried out safely and

smoothly. The author was also involving in the decisions on the various works

methods to solve the problems encountered at MBFC including getting approval

from the authorities, such as LTA, URA and BCA. The examples are:

To use Down-the-Hole method and Casing Oscillator method at the seawall

area to break through and clear off the seawall in preparation for the soil

improvement and bored piling works as shown below.

To carry out load tests adjacent to the excavation area and MRT reserve

zone (refer to the figure below)

The author took accountability and responsible for the decisions which he had made

during the project period. The author was pleasure that the project was able to hand

over satisfactory to the client.

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

35

Casing Oscillator was in operation to remove the existing seawall

Removal of existing seawalls using casing oscillator with hammer grab

Casing oscillator

Hammer grab

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

36

(a) Working load tests using Kentledge method adjacent to MRT line and

excavation area

Sketch showing Kentledge load test carried out near to existing MRT line (outside zone of influence, ie. 2nd reserve but located within 3rd reserve)

Sketch showing Kentledge load test carried out near to excavation area (10 m away from the edge of the excavation)

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

37

(b)

Working load tests using Kentledge method adjacent to

MRT line and excavation area

Photos showing 4200 tons Kentledge load test setup

Load cell reader Electrical pump

Hydraulic jacks with load cells and stacking steel plates

Inspection of the setup prior testing by the author and the supervisor

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

38

Managing Engineering Activities

This project involved a lot of engineering activities and all the activities would have

to be carried out closely and simultaneously. The engineering activities are:

Geotechnical instrumentation;

Deep cement mixing;

Jet grouting;

Bored piles;

Continuous bored piles;

Down-the-hole hammer;

Casing oscillator;

DCM coring tests.

The overall view of the site can be seen in the following. Some of the activities are

shown. The author had to plan the daily activities based on 24-hour a day basis. The

aim was to avoid unnecessary down time for all the heavy machineries and man

powers from the sub-contractors. Various considerations had to be taken care for

the planning purpose. Such as, bored piles can only be installed after DCM has been

completed; effects of jet grouting on completed bored piles need to be taken into

considerations; etc.

Site utilities plan was also a very important issue. This was because almost all the

engineering works located on the entire site. Allocation of utilities, such as water

pond, bentonite / polymer silos, cement silos, mixing plants, machineries, boring

tools, etc, was the great challenge in this particular site, whereby existing MRT line

and existing CST are located within the site boundary. Therefore, the site utilities

plan had to be cleared and approved by LTA & URA and to make sure that the

effects on the existing tunnels are minimal due to the additional loads created. The

site utilities plan is shown also.

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

39

An over view of the site showing various on-going activities

Phase 2, Tower 2 Area

Overview of the Site

Phase 3, Basement Carpark Area

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

40

Site utilities plan for MBFC for silos, batching plants, etc, located within the MRT 2nd & 3rd reserve zone and URA 6m reserve zone

Silos & batching plants for bentonite

& polymers suspensions

Batching plants for DCM & JGP works,

located directly on top of the existing URA

CST tunnel

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

41

Exercising Sound Judgement

The author had exercise sound judgement during his involvement in the project. He

worked together with all the professional personnel in the design and construction

of the deep foundation bored piles. He analysed the load tests results and confirmed

the design parameters with the fellow consultants for the construction of the

working piles. The design parameters were reasonably correct and all the load tests

on the working piles had passed according to the criteria. His analysis on the effects

of base grouting and DCM on the foundation bored piles could be continued with

the research and adopted in the future projects in Marina Bay area. By adopting this

approach, the design and construction of the deep foundation bored piles would be

more economical and safer. He was also exercised sound professional engineering

judgement for adopting of down-the-hole hammer and casing oscillator methods to

overcome the existing seawall problems in MBFC.

Communication

During the whole project period, the author communicated well with all range of

people, such as authorities, consultants, his colleagues at site, sub-contractors and

suppliers. He assisted his Project Manager in chairing the daily site meeting with all

the sub-contractors for all the site works. He also involved in the consultants’

progress and technical meetings to solve all the site issues. In addition, he played a

very proactive role in getting URA/LTA’s clearance for all the engineering works

within their protection zone.

Report for TUCSS THE HULME 2012 Competition by Er. Kee Ching Guan

42

CONCLUSION

The author describes his project involvement in the Project BFC. The effects of

base grouting on the deep foundation bored piles are heavily described. The impacts

of the outcome of the current analysis could have great impact in the future’s deep

foundation design in Singapore.

31 July 2012