Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
REPORT
TO
ESPERIA COURT PTY LTD
ON
PRELIMINARY GEOTECHNICAL SITE ASSESSMENT
FOR
PROPOSED MIXED USE DEVELOPMENT
AT
1 TO 9 THE BOULEVARDE, STRATHFIELD, NSW
18 August 2015
Ref: 28634Vrpt-Strathfield
JK Geotechnics GEOTECHNICAL & ENVIRONMENTAL ENGINEERS
PO Box 976, North Ryde BC NSW 1670 Tel: 02 9888 5000 Fax: 02 9888 5001 www.jkgeotechnics.com.au
Jeffery & Katauskas Pty Ltd, trading as JK Geotechnics ABN 17 003 550 801
28634Vrpt-Strathfield Page ii
Date: 18 August 2015 Report No: 28634Vrpt-Strathfield Revision No: 0
Report prepared by: Fernando Vega Senior Associate For and on behalf of
JK GEOTECHNICS
PO Box 976
NORTH RYDE BC NSW 1670
Document Copyright of JK Geotechnics.
This Report (which includes all attachments and annexures) has been prepared by JK Geotechnics (JK) for its Client, and is intended for the use only by that Client. This Report has been prepared pursuant to a contract between JK and its Client and is therefore subject to:
a) JK’s proposal in respect of the work covered by the Report;
b) the limitations defined in the Client’s brief to JK;
c) the terms of contract between JK and the Client, including terms limiting the liability of JK.
If the Client, or any person, provides a copy of this Report to any third party, such third party must not rely on this Report, except with the express written consent of JK which, if given, will be deemed to be upon the same terms, conditions, restrictions and limitations as apply by virtue of (a), (b), and (c) above. Any third party who seeks to rely on this Report without the express written consent of JK does so entirely at their own risk and to the fullest extent permitted by law, JK accepts no liability whatsoever, in respect of any loss or damage suffered by any such third party.
28634Vrpt-Strathfield Page iii
TABLE OF CONTENTS
1 INTRODUCTION 1
1.1 Proposed Development 1
2 PROCEDURE 2
3 RESULTS 2
3.2 Brief Site Description 2
3.3 General Geology and Inferred Subsurface Conditions 2
4 PRELIMINARY COMMENTS AND RECOMMENDATIONS 3
4.1 Summary of Findings and Main Geotechnical Issues 3
4.2 Detailed Geotechnical Investigations and Inspections 4
4.3 Preliminary Design Guidance and Geotechnical Parameters 5
4.4 Conclusions 7
5 GENERAL COMMENTS 7
VIBRATION EMISSION DESIGN GOALS
APPENDIX
SITE SURVEY PLAN
28634Vrpt-Strathfield Page 1
1 INTRODUCTION
JK Geotechnics have been commissioned by the architects Mr Andrew Elia and Ms Georgina Camp
of Integrated Design Group, on behalf of Esperia Court Pty Ltd (Mr Nick Soulos), to carry out a
preliminary geotechnical assessment, based on a desk study research, to assist with the
Development Application (DA) for a proposed mixed use development at 1 to 9 The Boulevarde
(corner Churchill Avenue), Strathfield, NSW. The work was completed in accordance to our fee
proposal, Ref: P40595V-Strathfield dated 1 June 2015.
A summary of the principal geotechnical issues, based on the findings of this desk study
research, is provided on Section 4.1.
This report presents the findings of the desk study research and goes on to make preliminary
recommendations on geotechnical aspects of the proposed development. We also provide
requirements for a detailed geotechnical subsurface investigation of the site. The recommendations
provided herein must be reviewed once further geotechnical work has been completed, after
demolition and at CC stage, and after the final development details such as footing system and
structural loads are decided upon and determined.
1.1 Proposed Development
The development was at DA stage. The proposed development involves demolition of the existing
structures and construction of a fifteen level building over three levels of basement car parking. The
basement level is proposed to cover most of the site area.
At this DA stage, preliminary architectural plans (by Integrated Design Group, Project No.
ESP13059) have been provided including development sections drawings (SK9200 Issue A 21 May
2015) and layout of basement (SK1001 Issue A 21 May 2015) with a proposed lowest (B3) floor
level at RL2.16m. Also provided was a site survey plan of the site which shows select adjoining
surface reduced levels (RL) (refer to the attached survey in the Appendix). Based on these levels,
it is estimated that excavations in the range of about 10m are likely to be required to achieve the
proposed lowest basement floor level. Structural loads had not been advised, but we have assumed
column loads in the moderate to high range will apply for the size of the building.
28634Vrpt-Strathfield Page 2
2 PROCEDURE
This preliminary desk study assessment included the research and review of relevant geotechnical
and geological information contained in our database for the site itself (test boreholes drilled at 4
Churchill Avenue in 1996 for other clients) and at nearby sites, and the Sydney geological map. No
current subsurface investigation on the site itself has been carried out as part of this preliminary
assessment.
3 RESULTS
3.2 Brief Site Description
The site is identified as Lot 1 in DP 173685, Lot 1 in DP 172769 and Lot 1 in DP173763 (or 1-9 The
Boulevard, corner Churchill Avenue). The attached Survey Plan (in the Appendix) shows the site
location and includes some select adjoining surface reduced levels and other site details including
some neighbouring information.
The site is located on the corner of The Boulevarde and Churchill Avenue extension, on the
southern side of Strathfield Square. The prevailing ground slope of the site falls slightly from around
RL12.2m-Rl12.5m in the south-east to around RL11.6m-RL11.9m in the north-west corner. The site
is almost entirely covered by commercial and retail buildings of two storey, brick construction. The
neighbouring properties to the south and west contain multi-level building with basements.
3.3 General Geology and Inferred Subsurface Conditions
Our site observations and research of available information, including a search of our in-house
database, has disclosed the following data on the geology and geotechnical conditions of the site:
1. The 1:100,000 geological map of Sydney indicates that the site is underlain by Ashfield
Shale of the Wianamatta Group, which typically consists of shale and laminite. This
geological profile does not take into account the residual soils derived from in-situ
weathering of the bedrock or earthworks (e.g. probable fill under tennis court area) that may
have previously been undertaken at the site.
2. Review of geotechnical information in the form of geotechnical boreholes discovered for
part of the site itself, which were drilled in 1996 at the rear of No. 4 Churchill Avenue,
confirmed the presence of shale bedrock at a depth of 5.4m below surface; the shale was
assessed in current terminology to be distinctly weathered and of medium strength. At
nearby sites to the west and south of the site, the shale was found a shallower depths of
2.8m-2.9m, but the rock was extremely weathered and extremely weak with residual clay
28634Vrpt-Strathfield Page 3
layers; medium or greater strength shale bedrock was encountered at greater depths of 4m
to 5m, which is similar to conditions encountered at 4 Churchill Avenue.
3. Above the bedrock there was limited depth of fill and residual silty clays of medium to high
plasticity and variable strengths (stiff to hard). The residual clays were estimated have a
moderate potential for shrink/swell reactive behaviour with changes in moisture content.
4. Groundwater was encountered at very shallow depths (0.3m-1m) in one of the boreholes
drilled in 1996 at 4 Churchill Avenue; it is considered very likely that these water levels might
be an anomaly or perched levels. However, groundwater should be expected below the site
since at nearby sites groundwater levels were measured in boreholes at depths in the range
of 3.7m to 4.4m.
4 PRELIMINARY COMMENTS AND RECOMMENDATIONS
4.1 Summary of Findings and Main Geotechnical Issues
Based on the results of our desktop study research, discussed in more specific detail in Section
3.2, we infer that the subsurface profile at the site most likely comprise some fill underlain by
residual clays grading into shale bedrock at general depths of around 3m-6m, based on nearby site
as well as geotechnical information on part of the site itself. The upper layers of shale might be of
an extremely low to very low strength nature, but improving with depth (probably around 5m-6m) to
at least medium strength. Groundwater levels are likely to be encountered within the depth of the
proposed three level basement excavation, since groundwater levels at nearby sites were at depths
of around 4m.
The above inferred subsurface profile must be confirmed by detailed geotechnical subsurface
investigations (refer to Section 4.2) involving cored boreholes, and standpipe wells for groundwater
monitoring, carried out prior to final structural design and issue of the Construction Certificate (CC)
and by geotechnical inspections of exposed rock during construction work.
Overall, it is considered that construction of the proposed development is viable and practicable,
provided detailed geotechnical borehole investigation is carried out prior to detailed final design
together with review of the preliminary recommendations provided in this report.
Based on the above inferred subsurface conditions and description of the proposed development
(refer to Section 1.1), the following are considered to be principal geotechnical issues for the
proposed development:
28634Vrpt-Strathfield Page 4
1. Prior to any demolition or excavation taking place at the site, we recommend that
dilapidation surveys of adjoining buildings, walls and pavements be carried out.
2. Maintaining stability of the adjoining land, buildings, stormwater services and any other
boundary structures during excavations. During the excavation, every care should be taken
to not undermine or render unstable the footings of any adjoining structure.
3. The basement excavation is likely to be carried through a variable profile of fill, residual clay,
and weathered shale. The excavation will, therefore, require support by shoring/retention
pile walls with rock anchors (e.g. soldier or contiguous or secant piles).
4. The shale excavation is likely to require assistance with rock excavation equipment, which
may transmit vibrations through the rock mass that could affect adjoining buildings. Vibration
effects (associated with general excavation but more critically rock excavation) on adjoining
structures must be considered.
5. Spread or pile footings may be embedded below the basement level and these are expected
to be founded in shale.
6. Groundwater seepage is likely to be an issue for the proposed three level deep basement
excavation.
7. Contamination or environmental investigations are likely to be required in order to classify
the material to be excavated for waste disposal purposes in accordance with the NSW DEC
(formerly EPA) guidelines as inert, solid, industrial or hazardous waste.
Further comments on these issues and preliminary design parameters are provided in the
subsequent sections of this report.
4.2 Detailed Geotechnical Investigations and Inspections
Detailed geotechnical subsurface investigation must be carried out after demolition is complete to
allow site access for truck mounted drilling rigs. The subsurface investigation must also be
completed and analysed prior to final structural design and issue of the Construction Certificate
(CC) to determine the site specific subsurface profile and geotechnical parameters for the design
of the retention systems and footings.
To complete final design on the basis of the geotechnical information provided from this desk study
research and preliminary report is not endorsed.
The geotechnical investigations should involve at least five boreholes drilled to depths below the
proposed excavations and the depth of influence of the proposed footings (estimated borehole
depths: 13m). The bedrock should be drilled with coring methods to allow strength testing of rock
28634Vrpt-Strathfield Page 5
core and examination of defects. Standpipe wells should be installed in select boreholes to allow
monitoring of groundwater levels. Pump out test should be completed to estimate seepage rates
and volumes.
Furthermore, it will be essential during earthworks and construction that regular geotechnical
inspections and testing be commissioned to check initial assumptions about excavation and
foundation conditions and likely variations that may occur between borehole locations and to
provide further relevant geotechnical advice. Irregular or ‘milestone’ inspections by a geotechnical
engineer are often not adequate for excavation and foundation works. It is recommended that the
Client be made aware of the need to commission a geotechnical engineer for inspections.
4.3 Preliminary Design Guidance and Geotechnical Parameters
The following are comments and recommendations on the geotechnical issues identified as
probable for the proposed development. These should be considered only for the preliminary
planning, design and construction assessment of the development. We have also included
approximate estimates of likely geotechnical parameters that may be used for preliminary design
purposes only. To complete final design on the basis of the geotechnical information provided from
this desk study research and preliminary report is not endorsed.
1. Dilapidation surveys should be carried out on the adjoining buildings that fall within the
influence zone of the excavation, which can be defined as a horizontal distance back from
the edge of the excavation of at least twice the excavation depth. During the excavation,
every care should be taken to not undermine or render unstable the footings of any
adjoining structure.
2. Excavations to achieve the basement levels are approximately estimated to have to be
carried down to depths of around 10m below existing site surface levels. Such excavations
are inferred to encounter fill and residual clays and the shale bedrock. Excavation of the
soils are expected to be achievable using conventional earthmoving equipment, such as
hydraulic excavators. The extremely weathered shale may also be removed using the latter
equipment. However, the presence of stronger or less weathered bedrock below inferred
depths of around 5m-6m is likely to require the use of rock excavation equipment for more
effective removal. The use of such equipment may result in transmission of vibrations
through the rock mass that could affect adjoining buildings. Vibration effects (associated
with general excavation but more critically rock excavation) on adjoining structures must
be considered. We recommend that the initial excavation in rock be commenced away from
likely critical areas, e.g. boundaries with adjoining buildings, with instrumental vibration
28634Vrpt-Strathfield Page 6
monitoring undertaken. Guideline levels of vibration velocity for evaluating the effects of
vibration in structures are given in the attached Vibration Emission Design Goals sheet. If
it is found that transmitted vibrations are unacceptable, then it may then be necessary to
change to a smaller excavator with a smaller rock hammer, or to a rotary rock grinder and/or
rock saws.
3. Hydrogeological (groundwater) Considerations: Groundwater inflow should be
expected into the basement excavation. However, we do not know what seepage rates are
to be expected. Hence, as part of the site specific subsurface testing work, we recommend
that pump out tests be completed in the standpipe wells recommended for installation in
Section 4.2. Notwithstanding, at this very preliminary stage, our suggestion is that the
basement be designed as an undrained, water-tight structure and designed against the
effects of groundwater pressures, in the short and long term, e.g. lowest basement floor
slab will be subjected to uplift pressures from the high groundwater level, which may require
additional slab mass or ground anchors. It is also important to note that in some cases that
local Council has advised in the past that continual pump-out and seepage into the street
gutter will not be accepted.
4. Retention systems should be installed prior to commencement of any vertical
excavations. The excavation sides should be supported by appropriate shoring/retention
systems, preferably, a closed, rigid system of secant or contiguous pile walls, with rock
anchors, which forms the perimeter cut-off to reduce the inferred groundwater inflow. We
do not prefer the use of a more open system of semi-contiguous or soldier pile walls with
shortcrete panels because we infer that there might be groundwater seepage issues.
Additional lateral support or restraint, if necessary, may be provided by rock anchors or by
internal props. Approval from neighbouring landowners will be required prior to installation
of anchors into their property. Some of the adjoining buildings have basements and hence,
their details should be determined to assess the feasibility and impacts of rock anchors
along some site boundaries.
5. Lateral Pressures: a high coefficient of lateral pressure, K, should be employed for
retention design within fill and residual soils and extremely weathered shale rock, to assist
in reduction of excavation induced movements. K values can be estimated once the results
of the geotechnical borehole tests has been completed and processed.
6. All applicable surcharge loadings (e.g. adjacent footings) should be taken into account in
the retaining system design. All retaining systems should incorporate permanent drainage
provisions and be designed to withstand some hydrostatic pressuresguidelines for design
of shoring/retention systems are provided herein. The presence of adjoining footings must
be taken into consideration in the assessment of lateral pressures.
28634Vrpt-Strathfield Page 7
7. Footings: the proposed building should be supported on footings (e.g. strip/pads or piles)
founded within the shale of at least very low strength; these footings may be designed on
a preliminary basis for an allowable bearing pressure of 700kPa. Higher bearing pressures
for shale of at least medium strength (e.g. 1500kPa-3500kPa) may be applicable below
say 5m-6m if this is proven by completing and testing the recommended boreholes on the
site itself.
8. Foundation Inspections: footing excavations and exposed foundation strata should be
inspected and correlated to nearest borehole test information by a geotechnical engineer
to ascertain that the recommended foundation material has been reached and to check
initial assumptions about foundation conditions and possible variations that may occur
between borehole test locations.
4.4 Conclusions
Overall, it is considered that construction of the proposed development is viable and practicable,
provided detailed geotechnical borehole investigation is carried out prior to detailed final design
together with review of the preliminary recommendations provided in this report. The proposed
development is similar to other developments in nearby sites with similar geotechnical and
geological conditions, which have been successfully constructed.
5 GENERAL COMMENTS
The comments and preliminary recommendations made in this report are based on geotechnical
information recovered from this desk study. The client should be aware that the subsurface
conditions can change over short distances and the recommendations made in this report may be
substantially altered as a result of site specific geotechnical investigations. The preliminary
recommendations may need to be changed substantially if the depth of soil cover is found to be
much deeper than assumed.
The text and recommendations of this report are not intended to directly form a Contract Document
or Specification. Such documents should be prepared only after the detailed geotechnical
investigations as recommended in this report. There may be design features we are not aware of
or have not commented on for a variety of reasons. The designers should satisfy themselves that
all the necessary advice has been obtained.
The recommendations presented in this report include specific issues to be addressed during a
later stage of the project. In the event that any of the construction phase recommendations
28634Vrpt-Strathfield Page 8
presented in this report are not implemented, the general recommendations may become
inapplicable and JK Geotechnics accept no responsibility whatsoever for the performance of the
structure where recommendations are not implemented in full and properly tested, inspected and
documented.
If there is any change in the proposed development described in this report then all
recommendations should be reviewed.
A waste classification will need to be assigned to any soil excavated from the site prior to offsite
disposal. Subject to the appropriate testing, material can be classified as Virgin Excavated Natural
Material (VENM), General Solid, Restricted Solid or Hazardous Waste. If the natural soil has been
stockpiled, classification of this soil as Excavated Natural Material (ENM) can also be undertaken,
if requested. However, the criteria for ENM are more stringent and the cost associated with
attempting to meet these criteria may be significant. Analysis takes seven to 10 working days to
complete, therefore, an adequate allowance should be included in the construction program unless
testing is completed prior to construction. If contamination is encountered, then substantial further
testing (and associated delays) should be expected. We strongly recommend that this issue is
addressed prior to the commencement of excavation on site. If there is any change in the proposed
development described in this report then all recommendations should be reviewed.
This report has been prepared for the particular project described and no responsibility is accepted
for the use of any part of this report in any other context or for any other purpose. Copyright in this
report is the property of JK Geotechnics. We have used a degree of care, skill and diligence
normally exercised by consulting engineers in similar circumstances and locality. No other warranty
expressed or implied is made or intended. Subject to payment of all fees due for the investigation,
the client alone shall have a licence to use this report. The report shall not be reproduced except
in full.
JKG Vibrat
Germanevaluatrecogni
The DINlevels msumma
It shoulfrequenconditio
It shouleffects include enlargeload beit may b‘safe lima broad
Table 1
Group
1
2
3
Note: F
GEOTEC
tion Emission Des
n Standard ing the effesed to be co
N 4150 valumeasured i
arised in Tab
d be noted ncies may beon of the stru
ld also be nhas been oeven mino
ement of craearing walls.be attributedmits’ are pred guide.
1: DIN 4150
Type of S
Buildings upurposes, and buildin
Dwellings similar des
Structuresparticular do not corin Group 1intrinsic vaare under
For frequenci
HNICAL & ENVI
sign Goals Rev1 J
VI
DIN 4150 cts of vibratonservative.
ues (maximun (x) or (y
ble 1 below.
that peak ve quite ‘safeucture.
noted that thobserved foror non-strucacks already Should dam
d to other caesent, it does
– Structura
Structure
used for commindustrial buil
ngs of similar
and buildingssign and/or us
s that becausesensitivity to vrrespond to tho1 and 2 and haalue (eg. builda preservatio
es above 10
RONMENTAL E
July12
BRATION E
– Part 3: tion in struc
um levels my) horizonta
vibration veloe’, dependin
hese levels r the particuctural effecty present, amage be obauses. DIN 4s not necess
al Damage –
mercial ldings design.
of se.
e of their vibration, ose listed ave ings that n order).
0Hz, the hig
NGINEERS
EMISSION
1986 providctures. The l
easured in aal directions
ocities higheng on the fre
are ‘safe limlar class of ts such asnd the sepa
bserved at vi4150 also stsarily follow
– Safe Limi
Less than 10Hz
20
5
3
her values in
Jeffery & Katausk
DESIGN G
des guidelinlimits prese
any directio, in the pla
er than the mequency con
mits’, up to wbuilding. ‘D
s superficialaration of paibration levetates that wh that damag
its for Build
Peak Vib
At Foundatiat a Freque
10Hz 50Hz
20 to 4
5 to 1
3 to 8
n the 50Hz to
kas Pty Ltd, tradin
OALS
ne levels onted in this
n at the fouane of the
minimum figntent of the v
which no daDamage’ is d
cracking iartitions or iels lower thahen vibrationge will occur
ding Vibrati
bration Veloc
on Level ency of:
to z
5
40 4
5 1
8 8
o 100Hz colu
ng as JK Geotech
of vibration standard ar
ndation, ORuppermost
gures in Tabvibration an
amage due defined by Din cement intermediatean the ‘safe n levels highr. Values giv
ion
city in mm/s
50Hz to 100Hz
40 to 50
15 to 20
8 to 10
umn should b
nics ABN 17 003
Pag
velocity forre generally
R, maximumt floor), are
ble 1 for lowd the actual
to vibrationDIN 4150 torender, the
e walls fromlimits’, then
her than theven are only
Plane of Floof Uppermo
Storey
All Frequenc
40
15
8
be used.
550 801
ge 1 of 1
r y
m e
w l
n o e m n e y
oor ost
cies
28634Vrpt-Strathfield Page 9
APPENDIX
SITE SURVEY PLAN