23
Uranium: Developer AEE.asx Speculative Buy Share Price Valuation $0.12 Price Target (12 month) $0.08 Brief Business Description: Hartleys Brief Investment Conclusion Chairman & MD Top Shareholders Techincal Investments 11.6% Australian Special Opportunity Fund 11.5% Company Address Suite 3 , Level 1, 19-23 Prospect St Box Hill, Vic, 3131 Issued Capital 274.5m - fully diluted Market Cap - fully diluted A$1.3m A$0.0m EV EV/Resource Mlb U3O8 EV/Reserve Mlb U3O8 Prelim. (A$m) FY16e FY17e FY18e Prod. (mlb U3O8) 0.0 0.0 0.0 Op Cash Flw -1.8 -2.5 -2.2 Norm NPAT -3.2 -4.0 -6.5 EPS (cps) -1.0 -0.7 -0.7 P/E -3.8 -5.4 -4.8 Div. Yield 0.0% 0.0% 0.0% Mt Grade Mlb Resources (M) 2416 160 850 Reserves (M) 0.0 nm 0.0 Trent Barnett Head of Research Ph: +61 8 9268 3052 E: [email protected] 313.9m nm A$9.9m A$11.3m A$8.6m $0.0101 Hartleys has provided corporate advice within the past 12 months and continues to provide corporate advice to Aura Energy Limited ("Aura") for which it has earned fees and continues to earn fees. Hartleys has a beneficial interest in 12.5 million options in Aura. Debt (31 Dec 14a) 24 Mar 2015 $0.036 Aura has two uranium projects. Mauritania (Tiris) is currently a small project that technical appears simple but has relatively high sovereign risk; Sweden (Haggan) is technically more complicated, but has lower sovereign risk and is a globally significant source of potential uranium supply. Both projects are low grade, but unconventional flowsheets suggest the economics of Tiris are compelling while Haggan offers bluesky potential. Peter Reeve (Executive Chairman & CEO) Cash (31 Dec 14a) AURA ENERGY LTD (AEE) Mauritania uranium project with a Swedish free option Aura Energy Ltd is an early stage uranium developer. It has two projects for which it has completed scoping studies and is now progressing to a DFS for Tiris, while a PFS is the next step for Häggån. Tiris (Mauritania) is the principle project, and forms the basis of our valuation and price target. We believe investors should focus on Tiris, and view the second project (Häggån) as a free option on uranium price. Tiris is unconventional and low grade, however due to the unique geology, appears viable based on the early study work (DFS due 2016). Tiris: Mauritania + beneficiation + low capex = ~0.7-1.0Mlb pa U 3 O 8 for ~15+ years Tiris has a low grade, predominantly inferred, resource of 66Mt @334 ppm U 3 O 8 . Study work suggests 420ppm uranium ore can be easily beneficiated through a trommel and screen to a ~2500ppm leach feed. Consequently, the expected economics are far better than the in-situ grade suggests. Given the project is at scoping study stage, we allow for working capital and further studies in our capital estimates. However, we assume a higher throughput than the scoping study. We assume start-up capex of ~US$57m (scoping capex US$45m) to achieve ~0.9Mlb of production at C1 cash costs of ~US$36/lb. We value Tiris at A$56m (NPV 12 , pre-tax, unfunded). The deposit is shallow, fast leaching and likely to grow, which makes it attractive. Häggån: Sweden + polymetallic + bacterial heap leach = ~8 Mlb pa U 3 O 8 for >25 years Häggån is a very large (2.35Bt) polymetallic (U, Ni, Mo, Zn, V) project located in Sweden. The Company explains that the size of the resource places it as one of the largest undeveloped uranium resources in the world (803Mlb), albeit very low grade (155ppm). We value Häggån today at A$125m (unrisked NPV 12 , pre-tax, unfunded) and using assumptions that are more conservative than the scoping study. However, we attribute little value in our risked AEE valuation given more work needs to be undertaken, in our view, and the initial capex estimate is high (US$537m for 30Mtpa). Initiate with Speculative Buy, 8cps price target We initiate coverage with a Speculative Buy recommendation. AEE offers early stage uranium exposure with a re-rating probable as the Tiris project is de-risked by further study work or exploration success. There is upside to our 12cps valuation if the project can be funded with more debt, rather than equity dilution, given the long mine life. If uranium prices rise significantly, then we believe the market will also begin to attribute value to Häggån, boosting the bull case price target potential for uranium bulls. Near term catalysts include air-core infill drilling, extensional drilling and greenfield exploration testing at Tiris. The Tiris DFS is due in CY16, although we expect updates throughout this year. Hartleys Limited ABN 33 104 195 057 (AFSL 230052) 141 St Georges Terrace, Perth, Western Australia, 6000 Hartleys does and seeks to do business with companies covered in its research reports. As a result, investors should be aware that the firm may have a conflict of interest that could affect the objectivity of this report. Investors should consider this report as only a single factor in making their investment decision. Further information concerning Hartleys’ regulatory disclosures can be found on Hartleys website www.hartleys.com.au 0.00 0.005 0.01 0.015 0.02 0.025 0.03 0.035 0.04 0.045 0.05 . .5 1. 1.5 2. 2.5 3. 3.5 4. 4.5 5. Mar-15 Nov-14 Aug-14 Apr-14 Volume - RHS AEE Shareprice - LHS Sector (S&P/ASX SMALL RESOURCES) - LHS A$ M Aura Energy Source: IRESS

AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Page 1 of 23

Aura Energy (AEE)

Ura

niu

m: D

evelo

per

AEE.asxSpeculative Buy

Share Price

Valuation $0.12

Price Target (12 month) $0.08

Brief Business Description:

Hartleys Brief Investment Conclusion

Chairman & MD

Top Shareholders

Techincal Investments 11.6%

Australian Special Opportunity Fund 11.5%

Company Address

Suite 3 , Level 1, 19-23 Prospect St

Box Hill, Vic, 3131

Issued Capital 274.5m

- fully diluted

Market Cap

- fully diluted

A$1.3m

A$0.0m

EV

EV/Resource Mlb U3O8

EV/Reserve Mlb U3O8

Prelim. (A$m) FY16e FY17e FY18e

Prod. (mlb U3O8) 0.0 0.0 0.0

Op Cash Flw -1.8 -2.5 -2.2

Norm NPAT -3.2 -4.0 -6.5

EPS (cps) -1.0 -0.7 -0.7

P/E -3.8 -5.4 -4.8

Div. Yield 0.0% 0.0% 0.0%

Mt Grade Mlb

Resources (M) 2416 160 850

Reserves (M) 0.0 nm 0.0

Trent Barnett

Head of Research

Ph: +61 8 9268 3052

E: [email protected]

313.9m

nm

A$9.9m

A$11.3m

A$8.6m

$0.0101

Hartleys has provided corporate advice within the past

12 months and continues to provide corporate advice

to Aura Energy Limited ("Aura") for which it has

earned fees and continues to earn fees. Hartleys has

a beneficial interest in 12.5 million options in Aura.

Debt (31 Dec 14a)

24 Mar 2015

$0.036

Aura has two uranium projects. Mauritania (Tiris) is

currently a small project that technical appears simple

but has relatively high sovereign risk; Sweden

(Haggan) is technically more complicated, but has

lower sovereign risk and is a globally significant

source of potential uranium supply.

Both projects are low grade, but unconventional

flowsheets suggest the economics of Tiris are

compelling while Haggan offers bluesky potential.

Peter Reeve (Executive Chairman & CEO)

Cash (31 Dec 14a)

AURA ENERGY LTD (AEE)

Mauritania uranium project with a Swedish free option Aura Energy Ltd is an early stage uranium developer. It has two projects for

which it has completed scoping studies and is now progressing to a DFS for

Tiris, while a PFS is the next step for Häggån.

Tiris (Mauritania) is the principle project, and forms the basis of our

valuation and price target. We believe investors should focus on Tiris, and

view the second project (Häggån) as a free option on uranium price. Tiris is

unconventional and low grade, however due to the unique geology, appears

viable based on the early study work (DFS due 2016).

Tiris: Mauritania + beneficiation + low capex = ~0.7-1.0Mlb pa

U3O8 for ~15+ years Tiris has a low grade, predominantly inferred, resource of 66Mt @334 ppm

U3O8. Study work suggests 420ppm uranium ore can be easily beneficiated

through a trommel and screen to a ~2500ppm leach feed. Consequently,

the expected economics are far better than the in-situ grade suggests.

Given the project is at scoping study stage, we allow for working capital and

further studies in our capital estimates. However, we assume a higher

throughput than the scoping study.

We assume start-up capex of ~US$57m (scoping capex US$45m) to

achieve ~0.9Mlb of production at C1 cash costs of ~US$36/lb. We value

Tiris at A$56m (NPV12, pre-tax, unfunded). The deposit is shallow, fast

leaching and likely to grow, which makes it attractive.

Häggån: Sweden + polymetallic + bacterial heap leach = ~8

Mlb pa U3O8 for >25 years Häggån is a very large (2.35Bt) polymetallic (U, Ni, Mo, Zn, V) project

located in Sweden. The Company explains that the size of the resource

places it as one of the largest undeveloped uranium resources in the world

(803Mlb), albeit very low grade (155ppm). We value Häggån today at

A$125m (unrisked NPV12, pre-tax, unfunded) and using assumptions that

are more conservative than the scoping study. However, we attribute little

value in our risked AEE valuation given more work needs to be undertaken,

in our view, and the initial capex estimate is high (US$537m for 30Mtpa).

Initiate with Speculative Buy, 8cps price target We initiate coverage with a Speculative Buy recommendation.

AEE offers early stage uranium exposure with a re-rating probable as the

Tiris project is de-risked by further study work or exploration success. There

is upside to our 12cps valuation if the project can be funded with more debt,

rather than equity dilution, given the long mine life. If uranium prices rise

significantly, then we believe the market will also begin to attribute value to

Häggån, boosting the bull case price target potential for uranium bulls.

Near term catalysts include air-core infill drilling, extensional drilling and

greenfield exploration testing at Tiris. The Tiris DFS is due in CY16,

although we expect updates throughout this year.

Hartleys Limited ABN 33 104 195 057 (AFSL 230052) 141 St Georges Terrace, Perth, Western Australia, 6000

Hartleys does and seeks to do business with companies covered in its research reports. As a result, investors should be aware that the

firm may have a conflict of interest that could affect the objectivity of this report. Investors should consider this report as only a single

factor in making their investment decision. Further information concerning Hartleys’ regulatory disclosures can be found on Hartleys

website www.hartleys.com.au

0.00

0.005

0.01

0.015

0.02

0.025

0.03

0.035

0.04

0.045

0.05

.

.5

1.

1.5

2.

2.5

3.

3.5

4.

4.5

5.

Mar-15Nov-14Aug-14Apr-14

Volume - RHS

AEE Shareprice - LHS

Sector (S&P/ASX SMALL RESOURCES) - LHS

A$ M

Aura Energy

Source: IRESS

Page 2: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 2 of 23

Aura Energy Share Price

AEE $0.036 Speculative Buy

Key Market Information Directors Company Information

Share Price $0.036 Peter Reeve (Executive Chairman & CEO) Suite 3 , Level 1, 19-23 Prospect St

Market Capitalisation - ordinary A$10m Robert (Bob) Beeson (Non-exec) Box Hill, Vic, 3131

Net Debt (cash) -$1m Brett Fraser (Non-exec) +61 3 9890 1744

Market Capitalisation - fully diluted A$11m Julian Perkins (Non-exec) +61 3 9890 3411

EV A$9m

Issued Capital 274.5m www.auraenergy.com.au

Options 39.5m Top Shareholders % ord

Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6%

Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian Special Opportunity Fund 31.50 11.5%

Valuation $0.12 1

12month price target $0.08 2 Reserves & Resources Cutoff Mt ppm Mlb

3 TOTAL RESOURCE 100 2,416 160 850

P&L Unit 30 Jun 18 30 Jun 19 30 Jun 20 30 Jun 21 4 Tiris - Total 100 66 334 49

Net Revenue A$m 0.0 53.0 72.1 58.9 5 Meas. & Ind. 100 2 300 2

Total Costs A$m -3.7 -29.9 -38.7 -37.6 6 Inferred 100 64 335 47

EBITDA A$m -3.7 23.1 33.4 21.4 7 Reserve 100 - nm -

- margin - 44% 46% 36% 8 Haggan - Total 100 2,350 155 801

Depreciation/Amort A$m -4.0 -7.3 -8.4 -8.6 9 Meas. & Ind. 100 - nm -

EBIT A$m -7.6 15.8 25.0 12.8 Inferred 100 2,350 155 801

Net Interest A$m 1.5 0.8 0.9 1.4 10 Reserve 100 - nm -

Pre-Tax Profit A$m -6.2 16.6 25.9 14.2

Tax Expense A$m 0.0 -0.8 -2.6 -2.1 Reguibat Production Summary Unit Jun 18 Jun 19 Jun 20 Jun 21

Normalised NPAT A$m -6.5 15.8 23.3 12.1 Ore to be beneficiated MT 0.0 0.8 1.0 1.0

Abnormal Items A$m 0.3 0.0 0.0 0.0 Beneficiated ore throughput MT 0.0 0.2 0.2 0.2

Reported Profit A$m -6.2 15.8 23.3 12.1 Mined grade ppm 450 450 371

Minority A$m 0.0 0.0 0.0 0.0 Uranium mlb 0.7 0.9 0.7

Profit Attrib A$m -6.2 15.8 23.3 12.1 Uranium Equiv mlb 0.7 0.9 0.7

Balance Sheet Unit 30 Jun 18 30 Jun 19 30 Jun 20 30 Jun 21 Assumed mining inventory Mt 35.8 35.3 34.3 33.3

Cash A$m 28.8 18.5 43.5 65.4 Assumed mining inventory ppm 330 328 325 322

Other Current Assets A$m 0.9 20.5 27.3 23.8 Assumed mining inventory mlb 26.0 25.5 24.5 23.6

Total Current Assets A$m 29.7 38.9 70.8 89.2 Mine Life yr 24.50 24.50 23.50 22.50

Property, Plant & Equip. A$m 57.0 70.0 63.7 57.1 Costs Unit Jun 18 Jun 19 Jun 20 Jun 21

Exploration A$m 14.7 14.7 14.7 14.7 Cost per tonne mined $A/t 39.8 38.7 37.6

Investments/other A$m 0.0 0.0 0.0 0.0 EBITDA / tonne milled ore $A/t 30.8 33.4 21.4

Tot Non-Curr. Assets A$m 71.6 84.7 78.3 71.8 Total cash costs $A/lb 44.6 43.4 51.0

Total Assets A$m 101.4 123.6 149.1 160.9 Total cash costs US$/lb 35.5 34.4 41.3

C1: Operating Cash Cost = (a) $A/lb 34.9 34.8 41.2

Short Term Borrowings A$m - - - - (a) + Royalty = (b) $A/lb 38.9 38.9 45.2

Other A$m 0.9 7.4 9.5 9.3 C2: (a) + depreciation & amortisation = (c) $A/lb 45.8 44.2 52.9

Total Curr. Liabilities A$m 0.9 7.4 9.5 9.3 (a) + actual cash for development = (d) $A/lb 65.3 37.1 44.0

Long Term Borrowings A$m -2.9 -2.9 -2.9 -2.9 C3: (c) + Royalty $A/lb 49.8 48.2 56.9

Other A$m - - - - (d) + Royalty $A/lb 69.3 41.1 48.0

Total Non-Curr. Liabil. A$m -2.9 -2.9 -2.9 -2.9 Price Assumptions Unit Jun 18 Jun 19 Jun 20 Jun 21

Total Liabilities A$m -2.0 4.4 6.6 6.3 AUDEUR 0.69 0.67 0.65 0.65

Net Assets A$m 103.4 119.2 142.5 154.6 AUDUSD 0.79 0.80 0.79 0.81

Net Debt A$m -31.7 -21.4 -46.4 -68.3 Uranium US$/lb 58 62 64 64

nd / nd + e % -44.3% -21.9% -48.3% -79.1% Hedging Jun 18 Jun 19 Jun 20 Jun 21

Cashflow Unit 30 Jun 18 30 Jun 19 30 Jun 20 30 Jun 21 Hedges maturing? No No No No

Operating Cashflow A$m -3.7 10.1 28.7 24.6 Sensitivity Analysis

Income Tax Paid A$m 0.0 -0.8 -2.6 -2.1 Valuation FY19 NPAT

Interest & Other A$m 1.5 0.8 0.9 1.4 Base Case 0.12 15.8

Operating Activities A$m -2.2 10.0 27.0 23.9 Spot Prices -0.03 (-125.3%) -15.4 (-197.7%)

Spot AUD/USD 0.78, Uranium $39/lb.

Property, Plant & Equip. A$m -53.1 -20.4 -2.0 -2.0 Contract prices 0.00 (-100.0%) -4.5 (-128.8%)

Exploration and Devel. A$m 0.0 0.0 0.0 0.0 AUDUSD +/--10% 0.116 / 0.116 (0.0% / 0.0%) 13.8 / 18.3 (-12.6% / 15.6%)

Other A$m 0.0 0.0 0.0 0.0 Uranium +/--10% 0.182 / 0.046 (56.8% / -60.4%) 21.3 / 10.4 (34.7% / -34.0%)

Investment Activities A$m -53.1 -20.4 -2.0 -2.0 Molybdenum +/--10% 0.116 / 0.116 (0.0% / 0.0%) 15.8 / 15.8 (0.0% / 0.0%)

Nickel +/--10% 0.116 / 0.116 (0.0% / 0.0%) 15.8 / 15.8 (0.0% / 0.0%)

Borrowings A$m 0.0 0.0 0.0 0.0 Production +/--10% 0.186 / 0.042 (59.7% / -63.6%) 21.6 / 10.1 (36.5% / -35.7%)

Equity or "tbc capital" A$m 0.0 0.0 0.0 0.0 Operating Costs +/--10% 0.075 / 0.155 (-35.4% / 33.5%) 13.2 / 18.4 (-16.5% / 16.6%)

Dividends Paid A$m 0.0 0.0 0.0 0.0

Financing Activities A$m 0.0 0.0 0.0 0.0 Unpaid Capital

Year Expires No. (m) $m Avg price % ord

Net Cashflow A$m -55.3 -10.3 25.0 21.9 30-Jun-15 1.0 0.2 0.20 0%

30-Jun-16 29.0 2.3 0.08 11%

Shares Unit 30 Jun 18 30 Jun 19 30 Jun 20 30 Jun 21 30-Jun-17 9.4 1.5 0.16 3%

Ordinary Shares - End m 825 825 825 825 30-Jun-18 0.0 0.0 0.00 0%

Ordinary Shares - Weighted m 825 825 825 825 30-Jun-19 0.0 0.0 0.00 0%

Diluted Shares - Weighted m 825 825 825 825 30-Jun-20 0.0 0.0 0.00 0%

TOTAL 39.5 4.0 0.10 14%

Ratio Analysis Unit 30 Jun 18 30 Jun 19 30 Jun 20 30 Jun 21 Share Price Valuation (NAV) Risked Est. A$m A$/share

Cashflow Per Share A$ cps -0.3 1.2 3.3 2.9 100% Tiris (pre-tax NAV at disc. rate of 12%) 125 0.152

Cashflow Multiple x -13.4 3.0 1.1 1.2 100% Haggan (unfunded pre-tax NPV, risked by 100%) 0 0.000

Earnings Per Share A$ cps -0.7 1.9 2.8 1.5 Forwards 0 0.000

Price to Earnings Ratio x -4.8 1.9 1.3 2.5 Corporate Overheads -32 -0.039

Dividends Per Share AUD - - - - Net Cash (Debt) 1 0.002

Dividend Yield % 0.0% 0.0% 0.0% 0.0% Tax (NPV future liability) -9 -0.011

Net Debt / Net Debt + Equity % -44% -22% -48% -79% Options & Other Equity 3 0.004

Interest Cover X 5.2 na na na Total 96 0.12

Return on Equity % na 13% 16% 8%

Analyst: Trent Barnett Last updated:

+61 8 9268 3052

"tbc capital" could be equity or debt. Our valuation is risk-adjusted for how this may be obtained.

Sources: IRESS, Company Information, Hartleys Research

24 Mar 2015

24 March 2015

Page 3: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 3 of 23

BUSINESS OVERVIEW Aura Energy is an Australian based uranium company that has two scoping study

level projects with large resources close to the surface in Europe and Africa. Aura

holds a total of 860Mlb uranium in inferred resources. Its two main projects are: the

Tiris Project (formerly known as Reguibat) in Mauritania and the Häggån Project

located in Sweden’s Alum Shale Province, one of the largest depositories of uranium

in the world.

Fig. 1: Tiris (Mauritania) Resource

Source: AEE

Fig. 2: Häggån (Sweden) Resource

Source: AEE

Fig. 3: Tiris is located in a flat desert

Source: AEE

U3O8

cutoff Mt ppm Mlbs

Tiris 100 66 334 49

Meas. & Ind. 100 2 300 1.6

Inferred 100 64 335 47

Reserve 100 - nm -

U3O8

cutoff Mt ppm Mlbs % Mlbs % Mlbs % Mlbs % Mlbs

Haggan 100 2,350 155 803 0.0207% 1,072 0.1519% 7,868 0.0316% 1,637 0.0431% 2,232

Meas. & Ind. 100 - nm - nm - nm - nm - nm -

Inferred 100 2,350 155 803 0.0207% 1,072 0.1519% 7,868 0.0316% 1,637 0.0431% 2,232

Reserve 100 0 nm - nm - nm - nm - nm -

Ni ZnU3O8 Mo V

Aura Energy is an

Austral ian based

uranium company that

has completed

scoping studies for

two projects in Europe

and Afr ica

Page 4: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 4 of 23

TIRIS 50 MLBS – MAURITANIA (100%)

Fig. 4: Tiris Resource

Source: AEE

The Hippolyte deposit at Tiris is a shallow (<4m) uranium project in north east

Mauritania. The project is low grade in-situ but studies suggest it can be upgraded

via a beneficiation (up to 7x) to high-grade leach feed, resulting in low upfront capex

and low operating costs. The Hippolyte resource, currently predominantly inferred,

is 66Mt @334 ppm for 49Mlb U3O8. The Company is confident of further exploration

success (the Company released a non-JORC exploration target for an additional

50Mlbs on 16 July 2014). To account for the considerable potential, we assume a

longer mine life than the scoping study. The Company is currently undertaking a drill

program to increase the M&I proportion (spacing to reduced from 100 x 200m to 50 x

50m) and hopefully increase the resource.

The resource is owned 100% by AEE, but it also has a JV (70/30) on certain

exploration permits with Ghazal Minerals Ltd.

The beneficiation test work suggests a straightforward wash and screen of the ore.

The uranium found at Tiris occurs as carnotite-type calcrete mineralisation within

unconsolidated coarser gravels and sands. The fine grained carnotite easily

separates from the coarse weathered granite. Testing to date suggests a low work

index, and the feed requires a simple trommel and screen (it does not require a

grinding mill). Work to date suggests that that 89% of the mineralisation could be

rejected to waste while retaining 86% of the uranium. Preliminary leach testwork

completed in late 2013 achieved 94% uranium extraction in four hours due to fine

grained nature of the carnotite.

Mining should be straightforward, as the majority of mineralisation occurs as a single

sheet with little cover. Testing to date suggests the material is largely unconsolidated

and can be excavated, with an anticipated low strip ratio of 0.25:1.

The beneficiated ore will go to standard alkaline leaching followed by ion exchange

in a NIMCIX reactor. Uranium will then be stripped from the NIMCIX resin to

generate a pregnant solution for precipitation as ammonium diuranate (ADU). After a

dewatering step in a centrifuge the precipitate will be calcined and dried to uranium

oxide (“yellowcake”) for transport to customers. All of these process steps are

standard and proven in the industry.

The total estimated initial cost for the project is US$45m (our model assumes

higher). The life of mine unit operating cost for Tiris is estimated to be US$30.3/lb of

U3O8.

The Company expects the mine will produce ~1.0Mlbs of U3O8 per year in Years 1

and 2, followed by ~650,000lbs in Years 3-10. Production rates are forecast to

increase in Years 11-15 due to higher grades (Zones I, J or C) to 710,000lbs,

however, cost of production also increases as the cost of ore transportation rises.

Total uranium produced (under these assumptions) is 10.7Mlbs over the 15 year

mine life. In our model we assume an expansion that increases mine life to 25 years

and doubles production in later years. This only has a modest impact on our NPV as

U3O8

cutoff Mt ppm Mlbs

Tiris 100 66 334 49

Meas. & Ind. 100 2 300 1.6

Inferred 100 64 335 47

Reserve 100 - nm -

Fig. 1: Tiris calcrete

deposit

Source: Aura Energy

Ore expected to be

benef ic iated

Page 5: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 5 of 23

we load up the additional capex and we use a 12% discount rate. However, the long

mine life means that our valuation is more leveraged to high long term uranium price

scenarios. The long mine life also provides investors with a longer dated call option

on a future uranium price spike.

Despite the remote location, the potential for significant mine flexibility (deposit is

shallow so does not require a mine plan that commits to a large pre-strip) suggests

risks are lower than some other developments.

Fig. 5: Estimated initial costs at Tiris (scoping study July 2014)

Cost (US$m)

Mining 1.12

Process Plant 22.07

Infrastructure 9.03

EPCM 3.19

Owner’s cost 1.58

Contingencies 8.05

Total Capital Cost US$45m

Source: Aura Energy

Fig. 6: Estimated summary of costs (scoping study)

US$ per Tonne of Ore Mined % of Total

Mining 2.59 8.9%

Processing 11.77 55.0%

Services 3.00 14.0%

G&A 4.08 19.0%

Total Cost US$21.42/tonne

Source: Aura Energy

Fig. 7: Map of the Tiris Project

Source: Aura Energy

Despite the remote

location, the potentia l

for s ignif icant mine

f lexibi l i ty (deposit is

shal low so does not

require a mine plan

that commits to a

large pre-str ip)

suggests r isks are

lower than some other

developments

Page 6: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 6 of 23

Fig. 8: Schematic of Geology at the Tiris Project

Source: Aura Energy Limited

Fig. 9: Photomicrograph showing the very fine grain size of the greenish

coloured carnotite grains (note the 50 micron scale)

Source: Aura Energy

Page 7: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 7 of 23

Fig. 10: Tiris Benefication Flow Sheet

Source: Aura Energy

Page 8: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 8 of 23

Exploration at Tiris The Company is currently undertaking a 4,000 metre drilling campaign to upgrade

resources to Measured / Indicated status, extend or expand the existing resource

and test several strongly anomalous targets. We understand that regional

prospectivity is high.

Fig. 11: Current drill campaign likely to increase resource

Source: Aura Energy

Fig. 12: Several greenfield targets to be tested

Source: Aura Energy

The Company is

current undertaking a

4,000 metres dr i l l ing

campaign to upgrade

resources to

Measured / Indicated

status, extend

resource and test

several strongly

anomalous targets.

We understand that

regional prospectiv ity

is h igh

Page 9: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 9 of 23

HÄGGÅN 800MLBS – SWEDEN (100%)

Fig. 13: Häggån Resource

Source: AEE

Häggån is a very large (2.35Bt) polymetalic project located in Sweden. The size of

the Häggån resource positions it as one of the largest undeveloped uranium

resources that are compliant with ASX or TSX requirements (30 September 2014).

The deposit is a near-flat-lying sheet of mineralisation averaging 108 metres in

thickness.

The Häggån Project forms part of a large uranium field where the uranium occurs

with molybdenum, nickel, vanadium and zinc in black shales. The first uranium

operation from the Alum Shale began at Kvarntorp in southern Sweden in 1965.

The nature of the mineralogy (normally require a fine grind) and relatively low grade

make it unviable using traditional acid or alkaline leach (the reagent use is too high).

However, test work has suggested that an acid generating bacterial heap leach will

work well, and improve the economics. Even still, the Häggån project requires

recovery of the by-product metals to be viable, in our view (we use higher operating

costs than the scoping study).

We attribute little value to Häggån in our valuation given it requires more work and

as a large project is unlikely to be attributed much value by the equity market unless

uranium prices have risen.

U3O8

cutoff ppm Mlbs % Mlbs % Mlbs % Mlbs % Mlbs

Haggan 100 155 803 0.0207% 1,072 0.1519% 7,868 0.0316% 1,637 0.0431% 2,232

Msr. & Ind. 100 nm - nm - nm - nm - nm -

Inferred 100 155 803 0.0207% 1,072 0.1519% 7,868 0.0316% 1,637 0.0431% 2,232

Reserve 100 nm - nm - nm - nm - nm -

Ni ZnU3O8 Mo V

Häggån is a very large

(2.35Bt) polymetal ic

project located in

Sweden.

We attr ibute l i t t le

value to Häggån in our

valuation given i t

requires more work

and as a large project

is unlikely to be

attr ibuted much value

by the equity market

unless uranium pr ices

have r isen.

Page 10: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 10 of 23

INDUSTRY EXPOSURE AEE is a uranium developer, and as such is exposed to global energy demand and

specifically the global nuclear power industry. Since the Fukushima disaster, the

uranium industry has been very focussed on the potential restart of the Japanese

nuclear reactors for a near term increase in demand. Medium and long term

forecasts tend to concentrate on the Chinese demand for nuclear power.

Fig. 14: Uranium Prices

Source: Bloomberg, Iress, Cameco

25

35

45

55

65

75

85

95 Spot Uranium (US$) Spot Uranium (US$) 5yr fwd

Long Term Contract Uranium (US$)

US$/lb

Market expectations ofmedium term U3O8 prices (Red)

are improving. Spot prices (Blue) and industry long term contract (Green).

Medium and long term

uranium forecasts

tend to concentrate on

the Chinese demand

for nuclear power.

Page 11: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 11 of 23

GEOGRAPHIC EXPOSURE Tiris is located in North East Mauritania in a military designated exclusion zone.

Access is possible all year round, although supplies are more difficult to source

during Ramadan.

Häggån is located in the Storsjön District of Sweden. Access is possible all year

round, although it is preferable to not plan to begin works in spring due to the thaw.

Mauritania The Islamic Republic of Mauritania is located in the Western part of the African

continent and currently has a stable and democratic elected government that

supports foreign investment. However, historically it is one of the world’s most coup-

prone states (last coup was 2008). The Country ranks among the top in Africa

according to the Fraser Institute Survey of Mining Companies, however,

infrastructure is poor and limited. Glencore, Kinross and First Quantum operate in

the country with significant investment. With mining income contributing to more

than a quarter of GDP, mining is generally viewed as a long term growth strategy for

the Country. The Transparency International Corruption Perceptions Index for 2014

gave Mauritania a score of 30 (perceived levels of corruption in the public sector on

a scale of 0:highly corrupt to 100:least corrupt) and was ranked 124th out of 175

countries.

The Mauritanian Parliament has recently undergone a number of mining reforms,

and the New Model Mining Convention Law provides a standard model based on

current mining codes as well as new provision on training, local recruitment,

technology transfers, environmental compliance, and infrastructure. The Mining

Code Amendment highlights that royalties which were previously fixed are now

floating based on international commodity prices and also specifies taxation regime

for capital gains arising from transfers of exploitation licenses. The reforms are

consistent with the Government of Mauritania intention of encouraging foreign

investment in mining. The country is a large iron ore exporter, although falling prices

have slowed that development recently.

The law exempts mining companies from customs duties for exploration equipment

during the first 5 years of production and permanently on fuel and spare parts.

Corporate income tax is 25% after a tax exemption for the first 3 years of production.

There is an additional 14% withholding tax on repatriated earnings and a 16% VAT.

Mauritania is prospective for oil & gas. The offshore Chinguetti field was discovered

in 2001, production is currently around 8,000bpd. The Banda field is estimated to

contain approximately 1.2 TCF of natural gas and the Tiof deposit is estimated to

contain 120 million barrels of oil with associated gas. Onshore, there is the

Taoudeni basin.

Sweden Sweden recently ranked second in the Fraser Institute Survey of Mining Companies’

most favourable mining countries. Domestic consumption of uranium is high, as

Sweden produces ~50% of its electricity from its 10 nuclear reactors.

Sweden does not impose a royalty on mining and lies within the lowest taxing

quartile with an effective tax rate of 28.6%.

The Transparency International Corruption Perceptions Index for 2014 gave Sweden

a score of 87 (perceived levels of corruption in the public sector on a scale of

0:highly corrupt to 100:least corrupt), and was ranked 4th out of 175 countries.

Glencore, Kinross and

First Quantum operate

in Mauritania with

signif icant investment.

Page 12: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 12 of 23

Fig. 15: Tiris

v

Source: Nationsonline.org

Fig. 16: Häggån

v

Source: mapsoftheworld.com

Project location

(not to scale)

Zouerat

(mining city) Export port

General project

location

(not to scale)

Page 13: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 13 of 23

PEERS AND COMPETITORS Forte Energy (FTE.asx) as a uranium explorer in Mauritania (A238 prospect and the

Bir En Nar project), is the closest peer. Other operators in Mauritania include First

Quantum (Guelb Moghrein, copper/gold), Kinross (Tasiiast, gold), State of

Mauritania via SNIM (Guleb el Rhein, Kedia d’Idjill, M’Haoudat, iron ore), Xstrata

(Askaf and the Lebthania, iron ore), GRY.asx (gold exploration) and Drake

Resources (gold exploration). Oil & gas operators include Petronas, Tullow, Total,

Charoit and Kosmos.

Fig. 17: ASX listed uranium projects

Source: Hartleys Research

0

500

1000

1500

2000

2500

3000

3500

4000

0 100 200 300 400 500 600 700 800 900 1000

Uranium ProjectsGrade (ppm)

Mlb U3O8

Haggan (AEE)Tiris (AEE)

Bubble size is ore deposit size (Mt)

Etango (BMN)Kvanefjeld (GGG)

Wiluna (TOE)

Langer Heinrich (PDN)

Temrezli (AEK)

Tiris post benefication

Four Mile West (AGS)

Page 14: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 14 of 23

Fig. 18: Selected Mauritania Resource Operators

Source: Hartleys Research

KEY SUPPLIERS & CUSTOMERS Tiris is remote and hence the site will need to be self-sufficient. Power is expected

to be diesel generated (wind and solar may be eventual options in the future). Plant

construction is expected to be as modular as possible for simpler construction on

site. Road access already exists. Preliminary water studies suggest it can be

sourced locally (it is estimated that the project, as currently defined, will require 0.5-

1.0 gigalitres of water per year). It is anticipated that yellow cake can be trucked to

Zouerat and then trucked or railed to the export port at Nouadhibou (north west

Mauritania).

Häggån has good road access, although it requires two short waterway crossings via

punt ferries. The region is lightly populated, although the potential mine is located in

a commercial forest and hence land access is relatively easy and located far enough

away from the small population centres. It is anticipated that yellow cake can be

trucked/railed to customers in Europe, most likely in France.

Page 15: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 15 of 23

MANAGEMENT, DIRECTORS AND

MAJOR SHAREHOLDERS

Biographies are sourced from the Company website

Mr. Peter Reeve (Executive Chairman & CEO), has been involved in the

Australian resources industry for approximately 25 years and, as a professional

metallurgist, has held positions with Rio Tinto, Shell-Billiton, Newcrest Mining and

Normet Consulting. For seven years Peter worked at JB Were as a Resource

Specialist Fund Manager and a Resource Corporate Finance Director. He has been

a management consultant in South Africa and was involved in an African iron ore

start-up. Peter was Managing Director and Chief Executive Officer of Ivanhoe

Australia, which he co-founded with Robert Friedland, and was a Director of both

EXCO Resources and Emmerson Resources.

Dr. Bob Beeson (Non-Executive Director, former AEE CEO) is a professional

geologist with over 35 years of experience in mineral exploration and development.

He has held senior management positions with Billiton Australia, Acacia Resources,

North Limited and New Hampton Goldfields, and has extensive experience in

leading and managing teams in many regions of the world. we has been Managing

Director of Aura Energy Ltd since its listing in 2006 (resigned in 2014) and is a Non-

Executive Director of Drake Resources Limited (also operating in Mauritania).

Mr. Brett Fraser (Non-Executive Director) is qualified as an accountant and has

more than 25 years’ experience in the finance and securities industry. For many

years he was an analyst working in merchant banking focused on the mining

industry. He is a former owner and director of media group Redwave Media Limited

and has owned and operated businesses across mining, finance, wine, health and

media.

Mr Jules Perkins (Non-Executive Director) was Manager of Mining & Technology

(Australia) for AngloGoldAshanti Ltd, one of the world’s largest gold mining

companies, until 2006. His career includes underground mining engineering in South

Africa and management of metallurgic operations on the Zambian Copperbelt. He

led the mineral processing department of Shell Research in the Netherlands for

three years before moving into corporate management. He moved to Australia with

Shell in 1989, where he was involved in the management of mining and metallurgical

operations and technology. Similar roles followed with Acacia Resources Ltd and

AngloGold Ashanti.

Total

Economic

Exposure

Position millions rank

Directors

Peter Reeve Non-Executive Chairman and CEO 4,333,104 4,537,469 8,870,573 1

Robert Beeson Non-Executive Director 3,035,257 2,291,667 5,326,924 2

Brett Fraser Non-Executive Director 1,526,000 3,569,461 5,095,461 3

Julian Perkins Non-Executive Director 2,642,595 1,831,600 4,474,195 4

Source: AEE

Economic Exposure of Board and key management

Total Options Shares

Page 16: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 16 of 23

MAJOR SHAREHOLDERS There are two substantial shareholders:

Technical Investments Pty Ltd (11.6%)

Australian Special Opportunity Fund (11.5%)

OPTIONS AND UNPAID CAPITAL Management holds 11m of the options.

Fig. 19: Options

Expiry

Exercise Price Number

Unpaid capital (A$)

May-15 $0.20 1,000,000 200,000

Sep-15 $0.06 26,214,005 1,572,840

Jan-16 $0.20 2,250,000 450,000

Mar-16 $0.45 570,000 256,500

Jul-16 $0.20 6,625,000 1,325,000

Dec-16 $0.20 200,000 40,000

Mar-17 $0.05 2,600,000 125,320

TOTAL $0.11 46,084,005 $4,963,410

Source: AEE

Page 17: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 17 of 23

FINANCIALS

PRODUCTION We assume Tiris could be in production in late CY18.

We do not incorporate Häggån into our cashflow/earnings model.

CASH FLOW

Capex requirements We assume start-up capex for Tiris of A$72m (US$57m). To cover working capital

and to be conservative, we assume startup capital of A$87m (US$68m). Our startup

capital estimate is important for our dilution assumptions.

Free cash flow We don’t expect AEE to be cash flow positive for several years.

Dividends We don’t expect AEE to pay dividend for the foreseeable future.

EQUITY ISSUANCE We assume substantial equity dilution (~512m new shares) for Tiris to reach first

production.

SENSITIVITIES

FX exposure We model AEE in USD, although as the project progresses it is more likely that

Häggån should be modelled in EUR.

Interest Rate exposure AEE is not directly exposed to interest rates. However, low interest rates are likely

to help facilitate the financing of long mine life projects, in our view.

Commodity price exposure AEE is primarily affected by uranium prices, but it could be argued that it is also

exposed to Ni and Mo prices given the polymetallic Häggån project.

We assume Tir is could

be in product ion in

late CY18.

We do not incorporate

Häggån into our

cashflow/earnings

model

Page 18: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 18 of 23

VALUATION CONSIDERATIONS

VALUATION We are more conservative than the scoping studies given experience has

demonstrated that, on average, subsequent studies generally exhibit a deterioration

in project economics. It is, of course, our hope that AEE subsequent studies

maintain (or perhaps even improve) on studies released to-date, and should that

occur we will need to increase our valuation.

Our valuation is based on Tiris only. We do not value Haggan in our AEE valuation

given we believe more studies need to be completed and the market should focus on

Tiris. We would change our view if uranium prices increased significantly such that

there was an urgent requirement for new large projects.

Fig. 20: Hartleys valuation assumptions

Source: Hartleys Research Estimates, AEE scoping study

Scoping

(16 July 2014)

Hartleys Difference

Mine Life Years 15 25 66.7%

Mining Inventory Mt 16 36 123.4%

- Grade U3O8 ppm 334 330 -1.1%

- Grade Ni ppm

- Grade MoO3 ppm

Pit Strip Ratio (x) x 0.25 0.25 0.0%

Pit Mill Feed (mt pa) Mt pa 1 1.43 43.0%

Cost/tonne ore US$/t 21.4 23.5 10.0%

Startup Capex US$m 45 57 26.7%

Total Capital US$m n/a 147

Operating Cost U3O8 credit US$/lb 30.3 36.0 18.7%

Recovery U3O8 % 95% 90% -5.3%

Payability U3O8 % 100% 100% 0.0%

U3O8 price US$/lb 65 63.9 -1.6%

Ni price US$/lb

MoO3 price US$/lb

Production U3O8 Mlb pa 0.75 0.9 24.9%

Production Ni Mlb pa

Production MoO3 Mlb pa

NPV10 at decision to mine US$m n/a

NPV12 at decision to mine A$m 75.8

Startup capex (for NPV) A$m 72.0

Startup capex (for NPV) US$m 57.0

Startup capital (for dilution) A$m 86.9

Startup capital (for dilution) US$m 68.7

Tiris

Our valuation is based

on Tir is only. We do

not value Haggan in

our AEE valuat ion

given we believe more

studies need to be

completed and the

market should focus

on Tir is. We would

change our v iew if

uranium pr ices increased signif icantly

such that there was an

urgent requirement for new large projects.

Page 19: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 19 of 23

Fig. 21: Hartleys valuation

Source: Hartleys Research Estimates

Fig. 22: Key assumptions and risks for valuation Assumption Risk of not realising

assumption Downside risk to

valuation if assumption is

incorrect

Comment

Rising uranium prices High High We assume consensus uranium price forecasts, which, by its nature, is not the most conservative

estimate in the market

Tiris first production in late CY18

High Meaningful We believe this is achievable

Tiris expansion in 2033 and mine life extension

High High We believe this is possible, although is greater than assumed in Company scoping studies

Tiris is predominantly equity funded

High Upside We assume substantial equity dilution to fund Tiris. If more debt funding can be acquired, then

the economics improve

Häggån has minimal value High Upside Given we place such a large discount on our Häggån valuation, it is immaterial to our base

case valuation

Conclusion We believe there is substantial risk in our assumptions, which could have a high impact on our valuation, and hence we believe that AEE is high risk

Source: Hartleys

Fig. 23: Commodity price assumptions

Source: Hartleys Estimates, IRESS

Unrisked Risked Risked

Corporate Valuation $m $m $/per shr

100% Tiris (pre-tax NAV at disc. rate of 12%) 125.2 125.2 0.15

100% Haggan (unfunded pre-tax NPV, risked by 100%) 123.7 0.0 0.00

Other Exploration 33.0 8.2 0.01

Forwards 0.0 0.0 0.00

Corporate Overheads -32.4 -32.4 -0.04

Net Cash (Debt) 1.3 1.3 0.00

Tax (NPV future liability) -9.3 -9.3 -0.01

Options & Other Equity 3.1 3.1 0.00

Hedges 0.0 0.0 0.00

Total 244.5 96.1 0.12

Current (today)

0

20

40

60

80

100

120

140

160

180

Hartleys Assumption for Valuations

Spot Uranium (US$)

Long Term Contract Uranium (US$)

US$/lb

0

20

40

60

80

100

120

140

160

180Hartleys Assumption for Valuations

Uranium (A$)

Uranium Long Term Contract (A$)

A$/lb

Page 20: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 20 of 23

PRICE TARGET Our price is a risk weighted average of potential scenarios.

Fig. 24: Price Target Methodology

Source: Hartleys

Price Target Methodology Weighting Spot 12 mth out

60% $0.12 $0.13

NPV base case at spot U3O8 (US$39/lb) and fx prices 5% $0.00 $0.00

NPV base case at spot forward contract U3O8 prices (US$49.6/lb) 25% $0.00 $0.00

NPV base case upper end estimated incentive prices (US$80/lb) 0.5% $0.30 $0.34

Net cash backing 10% $0.00 $0.00

Risk weighted composite $0.07

12 Months Price Target $0.08

Shareprice - Last $0.036

12 mth total return (% to 12mth target + dividend) 130%

NPV Tiris (base case)

Page 21: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 21 of 23

RECOMMENDATION & RISKS

INVESTMENT THESIS & RECOMMENDATION We initiate coverage with a Speculative Buy recommendation.

AEE offers early stage uranium exposure with a re-rating probable as the Tiris

project is de-risked with further study work or exploration success. There is upside

to our 12cps valuation if the project can be funded with debt, rather than equity

dilution, given the long mine life. If uranium prices rise significantly, then we believe

the market will also begin to attribute value to Häggån, boosting the bull case price

target potential for uranium bulls.

RISKS The risks for AEE are similar to most developers: attaining capital for development

studies and construction, the outcomes of more detailed studies, management key-

man risk, relevant government approvals, political risk, commodity prices,

commissioning success and the asset performance versus nameplate design.

SIMPLE S.W.O.T. TABLE Strengths Two uranium projects means diversification

Tiris realistic project, Häggån has blue-sky Tiris has a small start-up capital requirement Tiris is relatively short timeframe to development Häggån is a very large deposit

Weaknesses Tiris is located in remote Mauritania Tiris requires beneficiation (albeit simple) Häggån is polymetallic Häggån process is bacterial heap leach Both projects are low-grade

Opportunities More exploration success at Tiris More exploration success at Häggån Potential to divest Häggån to fund Tiris Potential to JV Häggån development studies

Threats Access to the remote Tiris project Securing ongoing financing for development studies Opportunistic takeover to secure Häggån

Source: Hartleys Research

AEE of fers early stage

uranium exposure wi th

a re-rat ing probable

as the Tir is project is

de-r isked with further

study work or

explorat ion success.

Page 22: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Hartleys Limited Aura Energy Ltd (AEE) 24 March 2015

Page 22 of 23

EV/EBITDA BANDS

Fig. 25: Using Hartleys base case commodity forecasts

Source: Hartleys Estimates, IRESS

Fig. 26: Using spot commodity prices

Using spot commodity prices Using current contract commodity prices

Source: Hartleys Estimates, IRESS

.00

.05

.10

.15

.20

.25

.30

.35

.40

AEE Actual

Hartleys Target

8x EV/EBITDA

6x EV/EBITDA

4x EV/EBITDA

2x EV/EBITDA

1x EV/EBITDA

Shareprice

.00

.05

.10

.15

.20

.25

AEE Actual

8x EV/EBITDA

6x EV/EBITDA

4x EV/EBITDA

2x EV/EBITDA

1x EV/EBITDA

Shareprice

.00

.05

.10

.15

.20

.25

AEE Actual

8x EV/EBITDA

6x EV/EBITDA

4x EV/EBITDA

2x EV/EBITDA

1x EV/EBITDA

Shareprice

Page 23: AEE Reports/2015...Issued Capital (fully diluted inc. all options) 313.9m Techincal Investments 31.80 11.6% Issued Capital (fully diluted inc. all options and new capital) 826.0m Australian

Page 23 of 23

HARTLEYS CORPORATE DIRECTORY Research Trent Barnett Head of Research +61 8 9268 3052

Mike Millikan Resources Analyst +61 8 9268 2805

Scott Williamson Resources Analyst +61 8 9268 3045

Simon Andrew Energy Analyst +61 8 9268 3020

Janine Bell Research Assistant +61 8 9268 2831

Corporate Finance Grey Egerton-

Warburton

Director & Head of

Corp Fin.

+61 8 9268 2851

Richard Simpson Director +61 8 9268 2824

Paul Fryer Director +61 8 9268 2819

Dale Bryan Director +61 8 9268 2829

Ben Wale Associate Director +61 8 9268 3055

Ben Crossing Associate Director +61 8 9268 3047

Stephen Kite Associate Director +61 8 9268 3050

Scott Weir Associate Director +61 8 9268 2821

Registered Office

Level 6, 141 St Georges TcePostal Address:

PerthWA 6000 GPO Box 2777

Australia Perth WA 6001

PH:+61 8 9268 2888 FX: +61 8 9268 2800

www.hartleys.com.au [email protected]

Note: personal email addresses of company employees are

structured in the following

manner:[email protected]

Hartleys Recommendation Categories

Buy Share price appreciation anticipated.

Accumulate Share price appreciation anticipated but the risk/reward is

not as attractive as a “Buy”. Alternatively, for the share

price to rise it may be contingent on the outcome of an

uncertain or distant event. Analyst will often indicate a

price level at which it may become a “Buy”.

Neutral Take no action. Upside & downside risk/reward is evenly

balanced.

Reduce /

Take profits

It is anticipated to be unlikely that there will be gains over

the investment time horizon but there is a possibility of

some price weakness over that period.

Sell Significant price depreciation anticipated.

No Rating No recommendation.

Speculative

Buy

Share price could be volatile. While it is anticipated that,

on a risk/reward basis, an investment is attractive, there

is at least one identifiable risk that has a meaningful

possibility of occurring, which, if it did occur, could lead to

significant share price reduction. Consequently, the

investment is considered high risk.

Institutional Sales Carrick Ryan +61 8 9268 2864

Justin Stewart +61 8 9268 3062

Simon van den Berg +61 8 9268 2867

Chris Chong +61 8 9268 2817

Digby Gilmour +61 8 9268 2814

Veronika Tkacova +61 8 9268 3053

Wealth Management Nicola Bond +61 8 9268 2840

Bradley Booth +61 8 9268 2873

Adrian Brant +61 8 9268 3065

Nathan Bray +61 8 9268 2874

Sven Burrell +61 8 9268 2847

Simon Casey +61 8 9268 2875

Tony Chien +61 8 9268 2850

Tim Cottee +61 8 9268 3064

David Cross +61 8 9268 2860

Nicholas Draper +61 8 9268 2883

John Featherby +61 8 9268 2811

Ben Fleay +61 8 9268 2844

James Gatti +61 8 9268 3025

John Goodlad +61 8 9268 2890

Andrew Gribble +61 8 9268 2842

David Hainsworth +61 8 9268 3040

Neil Inglis +61 8 9268 2894

Murray Jacob +61 8 9268 2892

Gavin Lehmann +61 8 9268 2895

Shane Lehmann +61 8 9268 2897

Steven Loxley +61 8 9268 2857

Andrew Macnaughtan +61 8 9268 2898

Scott Metcalf +61 8 9268 2807

David Michael +61 8 9268 2835

Jamie Moullin +61 8 9268 2856

Chris Munro +61 8 9268 2858

Michael Munro +61 8 9268 2820

Ian Parker +61 8 9268 2810

Charlie Ransom

(CEO)

+61 8 9268 2868

Brenton Reynolds +61 8 9268 2866

Conlie Salvemini +61 8 9268 2833

David Smyth +61 8 9268 2839

Greg Soudure +61 8 9268 2834

Sonya Soudure +61 8 9268 2865

Dirk Vanderstruyf +61 8 9268 2855

Jayme Walsh +61 8 9268 2828

Samuel Williams +61 8 9268 3041

Disclaimer/Disclosure

The author of this publication, Hartleys Limited ABN 33 104 195 057 (“Hartleys”), its Directors and their Associates from time to time may hold

shares in the security/securities mentioned in this Research document and therefore may benefit from any increase in the price of those

securities. Hartleys and its Advisers may earn brokerage, fees, commissions, other benefits or advantages as a result of a transaction arising

from any advice mentioned in publications to clients.

Hartleys has provided corporate advice within the past 12 months and continues to provide corporate advice to Aura Energy Limited ("Aura") for

which it has earned fees and continues to earn fees. Hartleys has a beneficial interest in 12.5 million options in Aura.

Any financial product advice contained in this document is unsolicited general information only. Do not act on this advice without first consulting

your investment adviser to determine whether the advice is appropriate for your investment objectives, financial situation and particular needs.

Hartleys believes that any information or advice (including any financial product advice) contained in this document is accurate when issued.

Hartleys however, does not warrant its accuracy or reliability. Hartleys, its officers, agents and employees exclude all liability whatsoever, in

negligence or otherwise, for any loss or damage relating to this document to the full extent permitted by law.