Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
REPUBLIC OF KENYA
LAKE VICTORIA NORTH WATER SERVICES
BOARD
WATER AND SANITATION SERVICES
IMPROVEMENT PROJECT
(WaSSIP)
REHABILITATION AND AUGMENTATION
OF BUTERE, MUSANDA AND
NAVAKHOLO WATER SUPPLY SYSTEMS
ENVIRONMENTAL IMPACT ASSESSMENT
(EIA) AND ENVIRONMENTAL
MANAGEMENT PLAN (EMP)
Client / Employer:
CHIEF EXECUTIVE OFFICER LAKE VICTORIA NORTH WATER SERVICES BOARD
P.O. BOX 673 - 50100
KAKAMEGA
KENYA
Consulting Engineers:
CES / MANGAT, I.B. PATEL & PARTNERS JV CONSULTING ENGINEERS P.O. BOX 48674, 00100 – GPO
NAIROBI, KENYA
TEL.: +254-20-2710500 / 1, FAX: +254-20-2710549
EMAIL: [email protected]
MARCH 2011
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV i
TABLE OF CONTENTS
1 GENERAL INFORMATION....................................................................................................1
1.1 INTRODUCTION .................................................................................................................1
1.2 NAME AND ADDRESS OF PROJECT PROPONENT ................................................................1
1.3 TITLE OF PROJECT............................................................................................................2
1.4 OVERALL OBJECTIVE OF PROJECT....................................................................................2
1.5 PROJECT DEVELOPMENT ..................................................................................................2
1.6 LOCATION OF PROJECT.....................................................................................................2
1.7 PROJECT MANAGER..........................................................................................................2
1.8 PROJECT MANAGER’S REPRESENTATIVE ..........................................................................2
1.9 CONTRACTOR ...................................................................................................................2
1.10 PROJECT COST ................................................................................................................2
1.11 PUBLIC CONSULTATIONS ..................................................................................................3
1.12 RELEVANT BANK OPERATIONAL POLICIES .........................................................................3
1.13 ENVIRONMENTAL HEALTH AND SAFETY (EHS) GUIDELINES ..............................................4
2 BASELINE SURVEY..............................................................................................................1
2.1 PROJECT AREA.................................................................................................................1
2.1.1 Administrative Description ..........................................................................................1
2.1.2 Socio Economic Infrastructure....................................................................................1
2.2 ENVIRONMENTAL BASELINE ..............................................................................................2
2.2.1 Butere Town and Musanda Trading Centre - Butere/Mumias District.......................2
2.2.2 Navakholo Trading Centre - Kakamega District.........................................................3
2.2.3 Water Resources ........................................................................................................4
2.3 POPULATION AND WATER DEMAND ...................................................................................6
2.4 ENVIRONMENTAL AUDIT OF EXISTING FOR BUTERE, MUSANDA AND NAVAKHOLO WATER
SUPPLY SYSTEMS.........................................................................................................................7
3 PROJECT DESCRIPTION .....................................................................................................1
3.1 SCOPE OF PROJECT .........................................................................................................1
3.1.1 Butere Works ..............................................................................................................1
3.1.2 Musanda and Navakholo Works.................................................................................1
4 POSSIBLE ENVIRONMENTAL IMPACTS & MITIGATION MEASURES ...........................1
4.1 MAJOR ELEMENTS OF THE SURROUNDING ENVIRONMENT.................................................1
4.2 MEASURES TO MINIMIZE ENVIRONMENTAL IMPACTS..........................................................1
4.3 POSSIBLE SEVERITY, DISTRIBUTION AND DURATION OF ENVIRONMENTAL EFFECTS ..........1
4.4 POTENTIAL NEGATIVE IMPACTS AND MITIGATION MEASURES ............................................1
5 THE NO-PROJECT OPTION .................................................................................................1
6 ENVIRONMENTAL MANAGEMENT PLAN (EMP) ..............................................................1
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV i
ANNEX 1 - MINUTES OF STAKEHOLDERS MEETING
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 1
GENERAL INFORMATION
Introduction
The Government of the Republic of Kenya (GoK) has mainstreamed its National Water Policy to envisage 100% access to safe water for the Country’s population by 2030. To achieve this target, the GoK has been implementing a far reaching sector reform program since 2002 aimed at harmonizing the Management of Water Resources and Water Supply and Sanitation (WSS) throughout the Country. This reform has been propelled by the Water Act (2002), which aims at harmonizing the Management of Water Resources and Water Supply and Sanitation Services. The World Bank has been supporting the GoK in its Water Sector Reforms through financing of programmes towards improvement of Water and Sanitation Services in the Country. In this regard, the (GoK) and World Bank, through the International Development Association (IDA), have agreed on the implementation of the Water and Sanitation Services Improvement Project (WaSSIP). This Project aims at supporting the Water Sector Reform effort by achieving the following three objectives namely: (i) Increase access to reliable, affordable and sustainable Water Supply and
Sanitation Services. (ii) Improve the Water and Wastewater Services.
(iii) Institutional Strengthening and capacity building of Water Service Providers,
within the Lake Victoria North Water Services Board (LVNWSB) area of jurisdiction.
One of the activities identified under Component (3) is – Rehabilitation and Augmentation of Butere, Musanda and Navakholo Water Supply Systems. LVNWSB has undertaken Detailed Designs and prepared Tender Documents and Drawings for the Works. LVNWSB is in the process of procuring a Contractor for the Implementation of these Works. The present Water Services in Butere, Musanda and Navakholo are under extreme pressure due to the high population increase, development and growth over the last decade. In addition, sections of the system are either dilapidated or require urgent rehabilitation due to normal wear, tear and age. The problems are at times compounded by interference with the existing infrastructure such as damage to appurtenances etc. The suppressed water supply in some areas affects the well being and living standards of the population in these areas.
Name and Address of Project Proponent
Chief Executive Officer Lake Victoria North Water Services Board (LVNWSB) Off Kakamega – Kisumu Road P.O. Box 673 – 50100 KAKAMEGA, Kenya Tel.: +254-56-30795 / 31552 ; Fax: +254-56-31506 E-mail: [email protected]
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 2
Title of Project Rehabilitation and Augmentation of Butere, Musanda and Navakholo Water Supply Systems Contract No. NC / PH III / LOT 6 / Butere, Musanda and Navakholo (C)
Overall Objective of Project The overall objective of the Project is to expand treated water output and transmit the same to supply Butere, Musanda and Navakholo Towns and part of their environs.
Project Development The following Reports have been prepared as part of Project Development:
• Inception Report
• Final Design Report
• Tender (Bid) Documents for Implementation of Works
Location of Project
The Project Location Plan is shown in Figure 1.1 on page 1-5.
Project Manager
Chief Executive Officer Lake Victoria North Water Services Board (LVNWSB) Off Kakamega – Kisumu Road P.O. Box 673 – 50100 KAKAMEGA, KENYA Tel.: +254-56-30795 / 31552 Fax: +254-56-31506 E-mail: [email protected]
Project Manager’s Representative
(To be appointed)
Contractor
(To be appointed)
Project Cost
The Contract Price based on Final Design (Exclusive of Contingencies) for the Works is Kshs 107,406,658.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 3
Public Consultations Pursuant to Legislative Requirements, a Stakeholders’ Meeting was held on 21st July 2010 in Butere for Stakeholders interested in the Project to allow for their active interaction for the Project to move to Construction Stage. Minutes of the Stakeholders’ Meeting are given in this Report as Annex 1.
Relevant Bank Operational Policies
The following are the relevant World Bank Operational Policies that have been taken into account in this Environmental Impact Assessment (EIA) / Environmental Management Plan (EMP).
1. OP/BP 4.01 Environmental Assessment (January 1999) Environmental Assessment is one of the 10 safeguard policies of the World Bank.
The objective of the World Bank Environment and Social Safeguard Policies is to improve decision making, to ensure that project options under consideration are sound and sustainable, and that project affected people have been properly consulted.
The World Bank's environmental assessment policy and recommended processing
are described in Operational Policy (OP)/Bank Procedure (BP) 4.01. The World Bank system assigns a project to one of three project categories, as defined below:
Category A: An EIA is normally required because the project may have diverse
significant impacts (projects in this category are forestry, large industrial plants, irrigation and drainage, mineral development (including oil and gas), pipelines (oil, gas, and water), resettlement, rural roads, tourism, urban development, large transmission lines, etc.).
Category B: A limited environmental analysis is appropriate, as the project may have specific environmental impacts. Projects in this category include agro-industries (small scale), aquaculture & marine culture, small industries, mini-hydropower station, public facilities (hospitals, schools, housing complexes, rural electrification, telecommunications, small-scale tourism, rural water supply, etc.)
Category C: Environmental analysis is normally unnecessary, as the project is unlikely to have significant environmental impacts. Projects in this category include education, family planning, nutrition, institutional development, technical assistance, etc.
This Project has been assigned to Category B as it is a rural water supply project involving some construction works and use of chemicals for water treatment.
2. OP/BP 4.04 Natural Habitats (June 2001)
Supports the conservation of natural habitats and the maintenance of ecological functions as a basis for sustainable development. The Bank does not support projects that involve the significant conversion or degradation of critical natural habitats.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 4
3. OP 4.36 Forests (November 2002) Aims to reduce deforestation and enhance, through sustainable economic development, the environmental and social contribution of forests. The Bank does not support projects which involve significant conversion or degradation of critical forest areas or related critical natural habitats.
4. World Bank Policy on Access to Information
The World Bank Policy on Access to Information sets out the policy of the World Bank on public access to information in its possession. This Policy supersedes the World Bank Policy on Disclosure of Information, and took effect on July 1, 2010. This Policy is based on five principles:
• Maximizing access to information.
• Setting out a clear list of expectations
• Safeguarding the deliberative process
• Providing clear procedures for making information available
• Recognizing requester’s right to an appeals process. In disclosing information related to member countries / borrowers in the case of documents prepared or commissioned by a member country / borrower (in this instance, safeguards assessments and plans related to environment and resettlement - OP / BP 4.01, Environmental Assessments, and OP / BP 4.12 Involuntary Resettlement), the Bank takes the approach that the Country / Borrower provides such documents to the Bank with the understanding that the Bank will make them available to the public.
Environmental Health and Safety (EHS) Guidelines
The relevant Environmental Health and Safety (EHS) Guidelines that have been taken into account in this Environmental Impact Assessment (EIA) / Environmental Management Plan (EMP) are the World Bank EHS General Guidelines and the EHS Guidelines for Water and Sanitation. The World Bank Environmental Health and Safety (EHS) Guidelines can be found at www.ifc.org/EHSGuidelines 2007
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 5
Fig
ure
1.1
– P
roje
ct
Lo
cati
on
Pla
n
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 1
BASELINE SURVEY
Project Area
Administrative Description Butere Town and Musanda Trading Centre Butere Town and Musanda Trading Centre lie within Butere/Mumias District, one of the eight districts that make up Western Province. It was curved out of the larger Kakamega District on 2nd March 1998. It covers a total area of 939.3km2. The district borders Busia and Bungoma Districts to the west, Siaya and Vihiga Districts to the south and Kakamega District to the north. The District lies between Longitudes 34o 21” East and 34o 41’ East and Latitudes 0o 15’ North and 0o 29’ North of the equator.
The district has two Local Authorities namely Mumias Municipal Council and Butere/Mumias County Council. Butere/Mumias County Council has nineteen Electoral Wards.
Butere Town is the Administrative Headquarters of Butere/Mumias District. It is located 13 kilometers south of Mumias Town on the South Western part of the Western Province.
Navakholo Trading Centre Navakholo Town lies within Kakamega District in Western Province. The district borders Butere/Mumias and Bungoma Districts to the west, Nandi District to the east, Vihiga District to the south and Lugari District to the north. The District lies between Latitudes 0o 07’30” North and 0o 15” North and Longitudes 34o 32” East and 34o 57’ 30” East. The District covers a total area of 1,395km2.
The Trading Centre is located approximately 25km from Kakamega Town, the administrative headquarters of both Kakamega District and Western Province.
Socio Economic Infrastructure
Butere Town With a population growth rate of 2.5% per annum, Butere Township Location has a population of 11,352 including an urban population of approximately 2,212. There is no established industry in the area. The informal sector is dominated by commercial facilities such as retail shops, catering services, butcheries, tailoring, dispensing chemists, posho mills and bars.
The area is served with good all weather murram roads, which connects the District headquarters at Butere Town to Mumias which is 13km to the North. Yala and Luanda towns are connected via the Ekero-Luanda road at Sabatia Market. It is also well connected to Kakamega Provincial Headquarters via Mumias Town or through Bukura Market to Sigalagala trading center on the Kisumu – Kakamega road.
Butere Town has both Electricity and Telephone facilities. Postal services are available at Butere Post Office in Town.
The Town has 5No. mixed Government Primary Schools, 1No. Private Primary School and 5No. Secondary Schools. It also has 6 public health institutions (Butere District Hospital, Kakamega Highway Nursing Home and 4No. Private Clinics).
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 2
Musanda Trading Centre Musanda Trading Centre and its environs has a population of 2,928. Main commercial activities include operation of wholesale and retail shops, selling of new and second hand clothes (mitumba), hardware, catering services, education, health and social welfare. At present, there are 40 shops, 11 restaurants, 4 bars and 3 butcheries within Musanda Trading Centre. There are no industrial activities within the Trading Centre. The area is served with a good all weather murram road to Mumias Town in the North, Butere Town to the East and Unguja to the West. Postal and wireless network mobile phone services are available at Musanda. It is served with electricity from the National Grid.
Musanda Trading Centre and its immediate environs has 4 health centres, 1 financial institution, 3 Non-Governmental Organizations (NGOs), 3 Primary Schools, 3 Secondary Schools and 1 tertiary institution (Bangani Village Youth Polytechnic). All the three NGOs are involved in caring of orphans.
Navakholo Trading Centre Navakholo Trading Centre and its environs has a population of 9,743. Main commercial activities include selling of new and second hand clothes (mitumba), hardware, education, health and social welfare. The Trading Centre is located approximately 25Km from Kakamega Town. Presently, there are approximately 40 shops, 11 restaurants, 4 bars and 1 butchery within Navakholo Trading Centre. There are no industrial activities within the Trading Centre. The area is served with a murram road, which connects the Trading Centre with Kakamega and Malava Towns. Navakholo Trading Centre is the headquarters of Navakholo Division. The Trading Centre has both Electricity and Telephone facilities.
Environmental Baseline
Butere Town and Musanda Trading Centre - Butere/Mumias District
Topography: The district has a varying topography with a few hills and valleys dissected by a number of small streams. The district has an extensive undulating peneplain that dips southwards from about 1,641m to 1,500m above mean sea level to a further 1,250m to the west. The lowest part of the district stands at about 1,240m above sea level.
Geological profile: Granitic rocks cover more than half of the district roughly north of the Bukura-Butere road. On the other hand, Meta-sedimentary rocks of the Kavirondian system cover most of the southern part of the area, but with narrow strips of Nyanzian system volcanic rocks such as basalts and andesites. Large deposits of sand and some clay also occur in various parts of the district.
Soils: The district has a variety of soils. Most parts of Mumias, Matungu and South Wanga Divisions have predominantly loamy soils. There are also a few areas in the southern part of Matungu with black cotton soils. Butere division on the other hand has soils ranging from sandy loam, clay loams and well darained loam soils. Khwisero division has predominantly shallow sandy loams that are highly eroded. The eastern parts of Khwiero have red soils. The loamy soils do support various crops such as sugarcane, pulses and cereals as is evident in Mumias, Matungu, South Wanga and
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 3
parts of Butere Division. The good and well-developed soils in Mumias, Butere, South Wanga and Matungu Division have led to farmers devoting almost 68% at their arable land on cane production. The poor soils in Khwisero Division have led to poor crop development hence higher levels of poverty.
Rivers: The district is dissected by a number of streams and rivers giving it ample surface water resources. The major rivers include River Nzoia, Yala, Lusumu, Lairi, Viratsi and their tributaries. The rivers flow all year round.
Butere Town is situated midway between two tributaries of the Viratsi River. A confluence of the two tributaries is located about 3 kilometers west of Town. One of the tributaries flows in Southeast-Northwest, while the second one flows Northeast –Southwest direction, which is also the direction of the Viratsi River. The Viratsi is at upper course stage, flowing on rocky bed.
Climate: The district has high rainfall almost all year round. However, the rainfall is less in intensity between December and February. The annual rainfall ranges from 1,597 – 2,873mm per year. The district has an almost uniform rainfall distribution. It has high
temperatures all the year round. The mean maximum is about 29°C. The high temperatures and rainfall allow for crop development all year round, enabling farmers to have two cropping seasons district-wide.
Navakholo Trading Centre - Kakamega District
Topography: The district has a varying topography with altitudes ranging from 1,250 meters to 2,000 meters above sea level. Kakamega Town lies on the altitude 1500 meters above sea level. The district can be divided into two main physiographic units, namely the southern hills made up of rugged granites rising to 1,950 meters above sea level, and the peneplain with remnants of denudation at Kakamega and Kambiri. The Nandi Escarpment forms a prominent feature on the district’s eastern border with its main scarp rising from the general elevation of 1,600 to 2,000metres.
Climate: There are two rainy seasons in the district, the long rains and the short rains. The long rains start in March and end in June with the peak in May. The short rains commence in July and end in September and peaks in August. The driest months are December, January and February. Generally rainfall varies from 1,000mm per annum in northern parts of the district to 2,400mm per annum in southern parts. Most rainfall received in the district comes in the form of heavy afternoon showers with occasional thunderstorms.
The district has high temperatures all year round with slight variations in mean maximum and minimum ranges of 28oC to 32oC and 11oC to 13oC respectively. Low temperatures are usually recorded at night while the very high temperatures are recorded during the day. The mean annual evaporation ranges from 1,600mm to 2,100mm with high humidity and low evaporation rates. It is only a few low lying parts of the district that receive annual average evaporation of more than 1,800mm.
Agriculture: The heavy rainfall that Kakamega receives makes the soils vulnerable to erosion and this tends to reduce the agricultural productivity of farms in the district. 70 per cent of the area in Kakamega is under maize cultivation with cash crops, mainly sugarcane, in Lurambi, Navakholo, and Kabras Divisions. Tea is grown on a small scale in Shinyalu and Ikolomani Divisions. Livestock rearing is another dominant land use in the district. The flat topography in the southern part of the district coupled with heavy rainfall makes the area suitable for sugarcane growing.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 4
The well-drained soils and flat topography also provides a good potential for irrigation, though this potential has not been tapped. However, the flat and swampy soil leads to regular water logging and flooding.
Drainage: One of the main rivers found in the district is River Yala, which originates from the Nandi Hills, east of Kakamega District. It flows westwards through Kakamega Forest and the southern part of the district. The Nandi Escarpment forms the catchment zone for streams such as the Shitiya, Kabkalet and Nurungo, which flow westward to join the River Nzoia.
The Kakamega area is drained towards Lake Victoria by River Isiukhu. The River Isiukhu is a tributary of Nzoia River. It originates from the Nandi Escarpment and flows through Kakamega Forest before reaching Kakamega Town.
Several small streams form tributaries to these main rivers, exhibiting dendritic drainage patterns dissecting the peneplain surface often with steep erosional valleys. Only the northwestern part of the district to the north of Mumias is swampy due to low gradients and poor drainage. The area is well suited for sugarcane growing.
Geology: The general geology of the district consists of intrusive (mainly granites), Nyanzian Volcanics and the Kavirondian sediments. However, the granites cover most parts of the district.
Water Resources
a) Existing Water Supply Situation in Butere Town Butere Town is primarily served by groundwater supply system. The system consists of 4 Nr boreholes located within the Town. The 4 Nr. Boreholes were drilled in 1960, 1968, 1988, and 2004 respectively. Two boreholes are located at Ministry of Agriculture compound, 1 at Ministry of Water & Irrigation yard and 1 at Butere Girls’ High School.
The present average water production is 420m3/day whereas the present demand is 1,348m3/day. The present average production is therefore 31% of the total demand. This creates a scarcity of water and as a result alternative water sources have been developed. These are described below:
• Shallow Wells – The rural communities have shallow wells installed with hand pumps. Most are fitted with concrete covers and a few are open.
• Protected Springs – 4Nr. existing springs that were protected by Kenya-Finland Western Water Supply Programme (KEFINCO). The water quality is good though the yields are low (0.5 – 1.2m3/hr).
• Unprotected springs – Majority of the people in rural and peri-urban areas collect water from Unprotected Springs that are polluted.
• Roof Catchments – Some of the residents have constructed tanks and harvest water from the roofs during the rainy season.
• Boreholes: Community-managed boreholes drilled by KEFINCO and KWAHO (Kenya Water for Health Organization)
• Amukowa Borehole Community Water Supply in Sabatia market supplies water to about 50Nr. households.
There is no existing Sewerage System in Butere Town. Most of the residential areas are served by pit latrines. A few institutions have septic tanks such as the District
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 5
Hospital, Kakamega Highway Nursing Home and Eshimuli Guest house. Most Secondary Schools have VIP latrines.
b) Existing Water Supply Situation in Musanda Trading Centre
Musanda Trading Centre is presently served by groundwater supply system. The system consists of 2Nr Boreholes located at Musanda Primary School and the Market Centre respectively. At present only one Borehole (C5715) is operational and is located at Musanda Primary School with a yield of 1.83m3/hr. This Borehole is privately owned by the School. The second Borehole (C6989) that is not operational and has a yield of 1.36m3/hr. The combined present yield of the two Boreholes is 75m3/day. The Water Supply System is managed by the Local Community.
Water from the School Borehole is pumped to an elevated plastic ‘Kentainer’ tank (capacity 5m3) located within the school compound and supplied to 4Nr water kiosks and 30nr individual consumers without disinfection. The tank is also owned by the School. At present, only two water kiosks are in operation. Consumers purchase water from these water kiosks at a fee of Kshs.5 per 20 litre container of water.
The water kiosks are owned and operated by the local community. The community pays the School a monthly sum as electricity and pump maintenance charges.
Other sources of water for the residents of Musanda are:
• Protected springs – 2Nr located within the vicinity of the Trading Centre. One of the springs was developed under the KEFINCO programme.
• Shallow wells – 2Nr hand-dug wells are located within the area.
• Roof catchment – Most residents have constructed tanks and harvest water from the roofs during the rainy season.
There is no existing Sewerage System in Musanda Trading Centre. Most households rely on on-plot sanitation facilities, predominantly pit latrines. The pit latrines are generally around 6m deep.
c) Existing Water Supply Situation in Navakholo Trading Centre
Navakholo Trading Centre is presently served by groundwater supply system. The system consists of 2Nr Boreholes located next to the Buheri-Kasisi junction. At present only one Borehole is operational with a yield of 58m3/hr (C-9232). The second Borehole which is not currently operational has a yield of 29m3/hr (C-9243). The combined present yield of the two Boreholes is 2,088m3/day. The Water Supply System is managed by the Local Community. Water from the Boreholes is pumped to a masonry tank (capacity 225m3) located at Emuhuni Hill and distributed to consumers without disinfection or any mode of treatment. Navakholo Sub-District Hospital has its own Borehole and an Elevated Steel Storage Tank (capacity 30m3). Presently, the hospital’s Borehole is not in operation due to siltation and is not equipped with a pump. The hospital is currently served by the community-managed water supply system via a 50mm dia. pipe tapped from the raw water pumping main to Emuhuni Hill Storage Tank.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 6
The Water Supply System is presently operating below its design capacity due to technical and operational deficiencies. The average recorded production as at end of July 2006 was 146m3/d, which is 7% of the design capacity of the system. There is no existing Sewerage System in Navakholo Trading Centre. Most households rely on on-plot sanitation facilities, predominantly pit latrines. The pit latrines are generally around 6m deep.
Population and Water Demand
The Population and Water Demand for Butere, Musanda and Navakholo was established in a Feasibility Study undertaken by CES/GFA/MIBP Consulting Engineers under the Water Supply and Sanitation Programme for the Nzoia Cluster in 2007. The Populations and Water Demand are as follows, projected to Year 2025:
Table 2.1: Summary of Population and Overall Water Demands for Butere Town
Year 2005 2010 2015 2020 2025
Population 11,352 12,864 14,577 16,517 18,717
Domestic Water Demand 777 945 1,071 1,214 1,376
Health/ Education/ Institution 172 212 241 273 309
Commercial/ Industrial 10% 78 95 107 121 138
Unaccounted for Water - 25% 25% 257 313 355 402 456
Treatment Works Losses - 5% 5% 64 78 89 100 114
Total Water Demand 1,348 1,644 1,862 2,110 2,391
Table 2.2: Summary of Population and Overall Water Demands for Musanda Trading Centre
Year 2006 2010 2015 2020 2025
Population 2,928 3,167 3,496 3,861 4,267
Domestic Water Demand 132 143 157 174 192
Health/ Education 20 22 24 27 30
Institutional/Administration 6 6 7 8 9
Commercial 1 2 2 2 2
Livestock 8% 11 11 13 14 15
Unaccounted for Water - 25% 25% 43 46 51 56 62
Treatment Works Losses - 1% 1% 2 2 3 3 3
Total Water Demand (m
3/day) 215 232 256 283 313
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 7
Table 2.3: Summary of Population and Overall Water Demands for Navakholo Trading Centre
Year 2006 2010 2015 2020 2025
Population 9,743 10,522 11,590 12,773 14,087
Domestic Water Demand 438 473 522 575 634
Health/ Education 68 74 81 89 99
Institutional/Administration 19 21 23 26 28
Commercial 5 5 6 6 7
Livestock 8% 35 38 42 46 51
Unaccounted for Water - 25% 25% 142 153 168 186 205
Treatment Works Losses - 1% 1% 7 8 8 9 10
Total Water Demand (m3/day) 715 772 850 937 1,033
Source: Feasibility Report - Rural Water and Sanitation Schemes prepared by CES/GFA/MIBP Consulting Engineers. February 2007)
Environmental Audit of Existing for Butere, Musanda and Navakholo Water Supply Systems
An Environmental Audit has been carried out for the Butere, Musanda and Navakholo Water Supply Systems. The Environmental Audit is detailed in the following Tables.
Table 2.4 - Environmental Audit for Existing Butere Water Supply System
Facility/Activity Description
Observation Environmental Impact Mitigation measures
Ministry of Water and Irrigation (MoWI) Compound
- Signboard: present at gate - Fence: Chainlink fence. - Lighting: 9No Security lights
present. Only 2 Working. - Cleanliness: Site well
maintained. Grass cut. - Sanitation facility: 1No pit
latrine, septic tank and bathroom present. All in good and operational condition.
- Fire fighting equipment: None.
- First aid equipment: None. - Security: Site manned by
1No. staff living within compound.
- Communication equipment: Fixed landline telephone available.
- Incidents: None.
- Inadequate lighting
may pose safety and security hazards during nightime operation.
- Lack of first aid equipment and fire fighting equipment at the works is risky.
- Lack of security guards could expose fittings within the compound to vandalism.
- Faulty security
lights to be replaced.
- Fire extinguisher (appropriate number, size and type) to be provided.
- Well-equipped first aid box to be provided and training offered on first aid procedures.
- Security guards to be placed at the compound.
BOREHOLE No. 1
Borehole No. 1 (C-8534)
- Borehole chamber: Good. - Cover: Missing; 620 x
620mm. - Pump lifting gantry: Firmly in
place. - Chamber cleanliness: Soil,
stones and debris in chamber.
- Missing cover
poses a safety hazard.
- Untidy chamber poses a safety hazard during routine maintenance.
- Replace missing
cover and install a locking mechanism.
- Chamber to be cleaned.
- Install wire gauze on vents of
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 8
Facility/Activity Description
Observation Environmental Impact Mitigation measures
- 3nr vent holes on walls of chamber do not have a protective mesh.
- Flow Meter: Available, ELSTER KENT, SNo. 517732-08; in good working condition.
- Fencing: Chainlink fence all round MoWI compound.
- Site: Well maintained. General remarks: - Located at MoWI compound - Constructed in 1968 - Pump run for 24hours.
- Open vents without mesh pose a safety hazard.
borehole chamber.
BOREHOLE No. 2
1) Borehole
No. 2 (C-5322)
- Borehole chamber: In good
structural condition. Stones and soil inside.
- 3nr vent holes on walls of chamber do not have a protective mesh.
- Pump lifting gantry: Firmly in place.
- Flow Meter: 40mm dia flow meter available, working.
- Fencing: Isolation fence not available.
General remarks: - Located at Butere Girls’ High
School Compound. - Constructed in 1988 - Pump run for 24hours.
- Untidy chamber
poses a safety hazard during routine maintenance.
- Open vents without mesh pose a safety hazard.
- Chamber to be
cleaned. - Install wire gauze
on vents of borehole chamber.
2) Valve
Chambers
- Some are broken. - Covers: Some are missing. - Cleanliness: Soil, stones
and debris in chambers.
- Broken and
uncovered chambers are a safety hazard
- Untidy chamber poses a safety hazard during routine maintenance.
- Replace missing
covers to chambers.
- Reconstruct broken chambers.
- Chambers to be cleaned.
3) Control
building and Panel
- Location: Within Butere
Girl’s Secondary School compound.
- Controls pumps for Borehole No. 2.
- Building: In good structural condition.
- Windows: 2 No. glazing broken.
- Lights: Both internal and external lights are not working.
- Room cleanliness: Not wept; dusty.
- Control Panel: Some hour meters are not working.
- Broken window
glazing a safety hazard.
- Lack of working lights a safety hazard during nightime operations.
- Dusty room poses a health hazard.
- Replace broken
window glazings. - All lights to be in
good working order.
- Room to be regularly cleaned.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 9
Facility/Activity Description
Observation Environmental Impact Mitigation measures
BOREHOLE No. 3 Borehole No. 3 (C-8537)
- Borehole chamber: Section
of wall is broken. Stones and soil in chamber.
- Cover: Metal cover available with locking mechanism.
- Pump lifting gantry: Firmly in place.
- Flow Meter: Missing. - Fencing: Existing fence is
broken. - Site: Maize planted within
borehole site. Site is generally bushy.
General remarks: - Located at Ministry of
Agriculture Compound. - Constructed in 1999 - Pump run for 24hours.
- Untidy and broken
chamber poses a safety hazard during routine maintenance.
- Bushy site a safety hazard.
- Repair broken
section of chamber.
- Clean chamber. - Install flow meter - Grass to be cut
and site to be properly maintained.
BOREHOLE No. 4
Borehole No. 4
- Borehole chamber: In good
structural condition. Stones and soil in chamber.
- Electrical switch box dangerously hanging on wall of chamber.
- Cover: Concrete cover available but fittings are prone to vandalism.
- Pump lifting gantry: Firmly in place.
- Flow Meter: Missing. - Fencing: Chainlink isolation
fence in place. - Site: Very bushy. General remarks: - Located at Ministry of
Agriculture Compound. - Constructed in 2004 - Pump run for 24hours.
- Untidy chamber
poses a safety hazard during routine maintenance.
- Loosely hanging electrical switch box is a safety hazard.
- Bushy site a safety hazard.
- Provide a metal
cover with locking mechanism.
- Clean chamber. - Install flow meter. - Safely clamp the
electrical switch box to wall of chamber.
- Grass to be cut and site to be properly maintained.
STORAGE TANKS
124m
3 Elevated
Steel Tank
- Located at Ministry of Water
and Irrigation Compound. - Tank: Some panels are
rusted. - Tank access: Access to tank
by fixed metal ladder. - Access Chamber: 1No.
Cover missing. - Vent pipe: Protective mesh
missing. - Cleaning of tank: Irregular.
Not cleaned for over a year.
- Rusted metal
panels a safety hazard.
- Water may be contaminated through unlocked access chamber and unclean tank.
- Access chambers
to be covered and locked.
- Tank to be regularly cleaned.
41m
3 Elevated
Steel Tank
- Located next to Borehole
No. 2 at Butere Girls’ High School compound.
- Rusted metal
panels a safety hazard.
- Access chambers
to be covered and locked.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 10
Facility/Activity Description
Observation Environmental Impact Mitigation measures
School compound. - Tank: Some panels are
rusted. - Walkways: Steel panels are
rusted. - Tank access: Access to tank
by fixed metal ladder. - Access Chamber: In good
condition but not cover locked.
- Vent pipe: Protective mesh missing.
- Cleaning of tank: Irregular.
hazard. - Water may be
contaminated through unlocked access chamber and unclean tank.
locked. - Tank to be
regularly cleaned.
DISTRIBUTION SYSTEM
1) 6.5 Km of
water pipeline
- Material: uPVC, GMS - Air valves: Several are
faulty. - Marker posts: Several
missing
- Lack of fire
hydrants in the network a safety hazard.
- Faulty air valves leads to formation of air locks in the distribution system and subsequently bursts.
- Replace faulty air
valves. - Install marker
posts.
2) Chambers:
- Chambers: Some are
broken. - Chamber Covers: Some
broken while some are missing.
- Broken chambers a
safety hazard. - Missing/broken
covers is a safety hazard.
- Re-construct
broken chambers. - Broken covers to
be replaced.
3) Marker
posts:
- Several are missing.
- Replace missing
marker posts.
Table 2.5 - Environmental Audit for Existing Musanda Water Supply System
Facility/Activity Description
Observation Environmental Impact Mitigation measures
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 11
Facility/Activity Description
Observation Environmental Impact Mitigation measures
General Remarks: - Water supply system consists of 2nr boreholes C-5715 (yield 1.83m
3/hr) and C-6989 (yield 1.36m
3/hr).
- Water from the boreholes is distributed to consumers without disinfection. BOREHOLES
Borehole No. 1 (C-5715)
- Location: Musanda Primary
School compound. - Depth: 51m - Drilled in 1990. - Borehole chamber: Good. - Cover: Concrete cover
available. However sections of roof slab concrete is damaged.
- Pump lifting gantry: Firmly in place.
- Chamber cleanliness: Stones, soil, grass, sticks inside the chamber.
- Electrical installations: Switch box is loosely tied onto the rising main.
- Pipe fittings: In good condition, no leakages observed.
- Fencing: None. - Site: Grass is cut and site
generally well maintained. - Control switch: The control
switch and cables have been dangerously mounted on the wall of the School’s administration block next to the staircase. School children have free access to them.
General remarks: - There is free access of
school children accessing the borehole.
- Damaged sections
of roof slab pose a safety hazard.
- Safety hazard to attendants working in chambers with stones, soil and grass.
- Loosely attached electric switchbox may lead to electrical shocks.
- Lack of fence may give way to unauthorized persons.
- Repair damaged
sections of concrete roof slab.
- Chamber to be cleaned.
- Safely clamp the switchbox on the wall of chamber.
- Provide fence with lockable gate at the borehole site.
Borehole No. 2 (C-6989)
- The borehole had been fitted
with a handpump that has since been vandalized.
- Location: Next to Musanda Market, in private land.
- Depth: 50m - Drilled in 1990. - Pump: None. - Electrical installations: None. - Pipe fittings: None. - Fencing: None. - Site maintenance: Site is
bushy with twigs, soil and rubbish over the pump platform.
General remarks: - There is free access of local
residents and domestic animals to the borehole.
- Lack of fence may
give way to unauthorized persons.
- Overgrown grass and may form a habitat for dangerous snakes.
- Provide fence with
lockable gate at the borehole site.
- Grass and bush to be cut and proper site maintenance observed.
PUMPING MAIN
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 12
Facility/Activity Description
Observation Environmental Impact Mitigation measures
(1) Pipeline - Material: GMS. - Size: 50mm diameter. - Length: 107m. - Age: Laid in 1990. - Valves and Fittings: Flow
meter not operational. - Pipeline: In good condition.
- Replace faulty flow meter.
(2) Chambers - Number: 1nr. - Chamber Covers: Broken. - Chambers structure: Walls
are broken. - Cleanliness of chambers:
Dirty with soil, stones and rubbish.
- Broken cover and chamber a safety hazard.
- Safety hazard to attendants working in chambers with stones, soil and grass.
- Broken cover to be replaced.
- Broken chamber to be repaired/reconstructed.
- Meter chamber should always be kept clean, locked and structure well maintained.
(3) Marker posts - None - Install marker posts.
STORAGE TANK
(1) Plastic elevated tank on a steel tower and timber platform. Capacity: 23m
3
Height of tower: 6.6m
- Location: Musanda Primary School.
- Fence: None. - Structure: Plastic tank in
good condition. - Tank roof access: Steel
ladder is provided. - Access chambers: Covered
with a plastic lid. - Washwater disposal:
Opening washout valve. Discharge to roadside drain.
- Tank cleanliness: Tank is not regularly cleaned.
- Platform: Some timber pieces are rotten and broken.
- Steel structure: In good condition.
- Valves and fittings: 1nr gate valve is not working.
- Damaged platform a safety hazard.
- Lack of fence and gate gives way to unauthorized entry.
- Dirty tank may lead to contamination of the stored water.
- Replace broken timber pieces and rehabilitate the tank’s platform.
- Fence with lockable gate to be provided.
- Tank to be regularly cleaned and regular maintenance observed.
- Replace faulty gate valve.
(2) Incidents:
- Past Occurrence: None. - Records: None. - Type of Record Books Kept:
None. - First aid equipment: None. - Warning sign: None.
- Lack of record books hampers the monitoring of activities and people accessing tank sites.
- Record books to be kept.
- Warning sign to be installed for trespassers.
DISTRIBUTION NETWORK
(1) Pipeline - Material: uPVC and Galvanized Mild Steel.
- Size: 25 to 50mm diameter. - Age: Laid in 1990. - Total length: Approx. 4km. - Valves and Fittings: Several
are leaking. - Pipeline: Some sections are
exposed, making them prone to vandalism.
- Exposed pipes make them prone to vandalism and subsequent contamination of disinfected water.
- Faulty valves to be replaced.
- Provide cover to exposed pipes by re-laying and backfilling in trenches.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 13
Facility/Activity Description
Observation Environmental Impact Mitigation measures
(2) Chambers - Number: 1nr within the network.
- Chamber Cover: Concrete cover is broken.
- Chamber structure: The chamber walls are broken.
- Cleanliness of chambers: Dirty with soil, stones and rubbish.
- Broken cover and chamber a safety hazard.
- Safety hazard to attendants working in chambers with stones, soil and grass.
- Broken cover to be replaced.
- Broken chamber to be repaired/reconstructed.
- Meter chamber should always be kept clean, locked and structure well maintained.
(3) Marker posts - None - Install marker posts.
(4) Water Kiosks - Number: 4nr. - Structure: Masonry structure
with corrugated iron sheets roof. Roofs are leaking.
- Cleanliness: Floors are wet and slippery.
- Doors: Wooden doors are present.
- Windows: Wooden windows are present.
- Usage: None of the water kiosks is presently in use.
- Pipes and fittings: Several are leaking.
- Leaking roofs, broken/missing doors and windows, untidy water kiosks pose safety and health hazards.
- Water kiosks to be rehabilitated.
- Repair/replace leaking pipes and fittings.
Table 2.6 - Environmental Audit for Existing Navakholo Water Supply System
Facility/Activity Description
Observation Environmental Impact Mitigation measures
General Remarks: - Water supply system consists of 2nr boreholes C-9232 (yield 58m
3/hr) and C-9243 (yield 29m
3/hr)
- Average volume of water produced per month was reported to be 7,000m3.
- Location: Next to Buheri-Kasisi junction in Nambacha Sub-location. - Water from the boreholes is distributed to consumers without disinfection.
BOREHOLES, CONTROL BUILDING & CONTROL PANEL Borehole No. 1 (C-9232)
- Depth: 66.3m - Drilled on 27
th November 1990.
- Borehole chamber: Good. - Cover: Metal cover available,
locked, though rusted. However sections of roof slab concrete is damaged.
- Pump lifting gantry: Firmly in place.
- Chamber cleanliness: Spare electrical cable kept haphazardly inside the chamber.
- Electrical installations: Switch box is detached from the wall of the chamber.
- Flow Meter: Available, 75mm diameter in good condition.
- Pipe fittings: In good condition, no leakages observed.
- Fencing: None. - Site: Grass is cut and site
- Rusted metal cover
and damaged roof slab pose a safety hazard.
- Untidy chamber poses a safety hazard during regular operation and routine maintenance.
- Detached electric switchbox may lead to electrical shocks.
- Lack of fence may give way to unauthorized persons.
- Clean and paint
rusted metal cover.
- Repair damaged sections of concrete roof slab.
- Chamber to be cleaned and spare electric cable to be stored at appropriate goods store.
- Safely clamp the detached switchbox on the wall of chamber.
- Provide fence with lockable gate at the borehole site.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 14
Facility/Activity Description
Observation Environmental Impact Mitigation measures
generally well maintained. General remarks: - The borehole is within the same
site with 1nr break pressure tank, old test borehole (abandoned) and the pumps control building.
Borehole No. 2 (C-9243)
- Depth: 68.9m - Drilled on 22
nd January 1990.
- Borehole chamber: Good. - Cover: Metal cover available,
locked, though rusted. However sections of roof slab concrete is damaged.
- Pump lifting gantry: Firmly in place.
- Chamber cleanliness: Dirty with soil, timber and grass inside the chamber.
- Electrical installations: Switch box safely clamped to wall.
- Flow Meter: Available, 75mm diameter in good condition.
- Pipe fittings: In good condition, no leakages observed.
- Fencing: None. - Site: Site is bushy with
overgrown grass and weeds. General remarks: - The borehole is located 110m
from Borehole No. 1.
- Rusted metal cover
and damaged roof slab pose a safety hazard.
- Untidy chamber poses a safety hazard during regular operation and routine maintenance.
- Lack of fence may give way to unauthorized persons.
- Overgrown grass and weeds may form a habitat for dangerous snakes.
- Clean and paint
rusted metal cover.
- Repair damaged sections of concrete roof slab.
- Chamber to be cleaned.
- Provide fence with lockable gate at the borehole site.
- Grass and weeds to be cut and proper site maintenance observed.
Control Building and Panel
- Location: Within the same
compound with Borehole No. 1. - Usage: Building houses the
control panel for both borehole pumps.
- Control Panel: Hour meters not working. Electrical short circuit for BH No. 2 as the switch trips whenever it’s switched on. Books stored on top of the panel and posters have been stuck on the panel.
- Building: Masonry structure with several sections of floor slab concrete detached, cracks on walls and leaking roof.
- Windows: 1nr metallic. - Door: 1nr metal door. - Lighting: 1nr fluorescent tube,
working. - Room cleanliness: Untidy;
Jembe, broom, shoes, chairs, tins haphazardly kept in the room.
- Warning sign: Sticker available on the door of the control panel.
- First aid equipment: None. - Fire fighting equipment: None. General remarks: - At time of visit power supply
- Short circuiting in
the control panel may cause a fire.
- Storage of books and sticking of posters on the control panel a safety hazard.
- Damaged sections of floor slab, leaking roof, cracks on walls of building are safety hazards.
- Haphazard storage of items on floor of building poses a safety hazard.
- No first aid equipment available in case of accidents.
- Lack of fire fighting equipment a safety hazard.
- Rehabilitate
pumps control panel.
- Books and posters should be removed from the control panel.
- Rehabilitate the control building to seal off cracks, leaking roof, etc.
- Room to be regularly cleaned and items kept on floor transferred to an appropriate storage facility.
- Well-equipped first aid box to be provided.
- Fire extinguisher (appropriate type and size) to be provided in the control building.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 15
Facility/Activity Description
Observation Environmental Impact Mitigation measures
had been disconnected by KPLC due to unpaid bills.
PUMPING MAIN
(1) Pipeline - Material: uPVC and GMS. - Size: 80 and 150mm diameter. - Length: 2.9km. - Age: Laid in 1990. - Valves and Fittings: Several are
not operational. - Fire hydrants: None. - Pipeline: Some sections are
exposed, making them prone to vandalism.
- Lack of fire hydrants in the network a safety hazard.
- Exposed pipes make them prone to vandalism and subsequent contamination of disinfected water.
- Fire hydrants to be installed and frequent pressure tests conducted.
- Faulty valves to be replaced.
- Provide cover to exposed pipes by re-laying and backfilling in trenches.
(2) Chambers - Number: 11nr. - Chamber Covers: Some
missing/broken. - Chambers structure: Several
have broken walls. - Cleanliness of chambers:
Several are dirty with soil, stones and rubbish.
- Missing/broken covers is a safety hazard.
- Broken chambers a safety hazard.
- Safety hazard to attendants working in chambers with stones, soil and grass.
- Missing/broken covers to be replaced.
- Broken chambers to be repaired / reconstructed.
- All valve chambers should always be kept clean, locked and structure well maintained.
(3) Marker posts - General remarks: Several missing/broken.
- Missing/broken marker posts to be replaced.
STORAGE TANK
(1) Ground level masonry tank at Emuhuni Hill Capacity: 225m
3
- Location: Emuhuni hill on top of a rock.
- Fence: None. - Structure: Walls are cracked
and plaster is broken in several sections.
- Tank roof access: Metal cat ladder is provided.
- Access chambers: Metal ladder mounted on wall of tank. Metal cover in place; locked.
- Washwater disposal: Opening washout valve. Discharge to open surface on the foot of the rocky hill.
- Tank cleanliness: Tank is not regularly cleaned.
- Valve chambers: 2nr chambers with sections of roof slab damaged. Metal covers available; locked.
- Chambers cleanliness: Soil, stones, grass and rubbish inside the chamber.
- Valves and fittings: In good condition.
- The stored water could be contaminated through unprotected vent pipe.
- Damaged tank structure a safety hazard.
- Lack of fence and gate gives way to unauthorized entry.
- Dirty tank may lead to contamination of the stored water.
- Damaged sections of roof slab of valve chambers a safety hazard.
- Safety hazard to attendants working in chambers with stones, soil and grass.
- Leaking sections of tanks to be repaired and tank rehabilitated.
- All vent pipes to be fitted with protective mesh.
- Fence with lockable gate to be provided.
- Tank to be regularly cleaned and regular maintenance observed.
- Rehabilitate valve chambers.
- All valve chambers should always be kept clean, locked and structure well maintained.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 16
Facility/Activity Description
Observation Environmental Impact Mitigation measures
General remark: - Vent pipe not fitted with
protective mesh. - Tank is leaking.
(2) Incidents:
- Past Occurrence: None. - Records: None. - Type of Record Books Kept:
None. - First aid equipment: None. - Warning sign: None.
- Lack of record books hampers the monitoring of activities and people accessing tank sites.
- Record books to be kept.
- Warning sign to be installed for trespassers.
BREAK PRESSURE TANKS
General remarks: - 2nr break pressure tanks, each of capacity 10m
3.
- Tanks constructed in 1990
(1) Ground level masonry Break Pressure Tank at Borehole No. 1 Site. Capacity: 10m
3
- Location: Buheri-Kasisi road junction. Within the same site as BH No.1.
- Fence: None. - Structure: Walls are cracked
and plaster is broken in several sections.
- Tank roof access: Metal cat ladder is provided.
- Access chambers: Metal ladder mounted on wall of tank. Metal cover in place; locked although rusted.
- Washwater disposal: Opening washout valve. Discharge to roadside drain
- Tank cleanliness: Tank is not regularly cleaned.
- Valve chambers: 2nr chambers with sections of roof slab damaged. Metal covers available; locked but rusted.
- Chambers cleanliness: Soil, stones, grass and rubbish inside the chambers.
- Valves and fittings: Sluice valves not working.
General remark: - Vent pipe not fitted with
protective mesh. - Tank is leaking.
- The stored water could be contaminated through unprotected vent pipe.
- Damaged tank structure a safety hazard.
- Lack of fence and gate gives way to unauthorized entry.
- Dirty tank may lead to contamination of the stored water.
- Damaged sections of roof slab of valve chambers a safety hazard.
- Safety hazard to attendants working in chambers with stones, soil and grass.
- Leaking sections of tanks to be repaired and tank rehabilitated.
- All vent pipes to be fitted with protective mesh.
- Fence with lockable gate to be provided.
- Clean and paint rusted metal covers.
- Tank to be regularly cleaned and regular maintenance observed.
- Rehabilitate valve chambers.
- All valve chambers should always be kept clean, locked and structure well maintained.
(2) Ground level masonry Break Pressure Tank along Malaha Line Capacity: 10m
3
- Location: At Malaha-Ingotse road junction.
- Fence: None. - Structure: Walls are cracked
and plaster is broken in several sections.
- Tank roof access: Metal cat ladder is provided.
- Access chambers: Metal ladder mounted on wall of tank. Metal cover in place; locked although rusted.
- Washwater disposal: Opening washout valve. Discharge to roadside drain
- Tank cleanliness: Tank is not regularly cleaned.
- Valve chambers: 2nr chambers
- The stored water could be contaminated through unprotected vent pipe.
- Damaged tank structure a safety hazard.
- Lack of fence and gate gives way to unauthorized entry.
- Dirty tank may lead to contamination of the stored water.
- Damaged sections of roof slab of valve chambers a safety
- Leaking sections of tanks to be repaired and tank rehabilitated.
- All vent pipes to be fitted with protective mesh.
- Fence with lockable gate to be provided.
- Clean and paint rusted metal covers.
- Tank to be regularly cleaned and regular maintenance observed.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 17
Facility/Activity Description
Observation Environmental Impact Mitigation measures
with sections of roof slab damaged. Metal covers are missing.
- Chambers cleanliness: Soil, stones, grass and rubbish inside the chambers.
- Valves and fittings: Sluice valves are both working.
- Site maintenance: Site is bushy with overgrown grass and sugarcane grown around it.
General remark: - Vent pipe not fitted with
protective mesh. - Tank is leaking.
hazard. - Safety hazard to
attendants working in chambers with stones, soil and grass.
- Lack of covers to chambers a safety hazard.
- Overgrown grass and may form a habitat for dangerous snakes.
- Rehabilitate valve chambers.
- All valve chambers should always be kept clean, locked and structure well maintained.
- Missing covers to be replaced.
- Grass and weeds to be cut and proper site maintenance observed.
(3) Incidents:
- Past Occurrence: None. - Records: None. - Type of Record Books Kept:
None. - First aid equipment: None. - Warning sign: None.
- Lack of record books hampers the monitoring of activities and people accessing tank sites.
- Record books to be kept.
- Warning sign to be installed for trespassers.
DISTRIBUTION NETWORK
(1) Pipeline - Material: uPVC and Galvanized Mild Steel.
- Age: Laid in 1990. - Valves and Fittings: Several are
leaking. - Fire hydrants: None. - Pipeline: Some sections are
exposed, making them prone to vandalism.
- Lack of fire hydrants in the network a safety hazard.
- Exposed pipes make them prone to vandalism and subsequent contamination of disinfected water.
- Fire hydrants to be installed and frequent pressure tests conducted.
- Faulty valves to be replaced.
- Provide cover to exposed pipes by re-laying and backfilling in trenches.
(2) Chambers - Number: Approximately 40 within the network.
- Chamber Covers: Several are missing/broken.
- Chambers structure: Several chambers have broken walls.
- Cleanliness of chambers: Most are dirty with soil, stones and rubbish.
- Missing/broken covers is a safety hazard.
- Broken chambers a safety hazard.
- Safety hazard to attendants working in chambers with stones, soil and grass.
- Missing/broken covers to be replaced.
- Broken chambers to be repaired / reconstructed.
- All valve chambers should always be kept clean, locked and structure well maintained.
(3) Marker posts - General remarks: Several missing/broken.
- Missing/broken marker posts to be replaced.
(4) Water Kiosks - Number: 4nr. - Structure: Masonry structure
with asbestos roof tiles. Roofs are leaking through holes made by stones/vandals.
- Cleanliness: Floors and walls dirty.
- Doors: Wooden, many have been vandalized.
- Windows: Wooden, many have been vandalized.
- Usage: None of the water kiosks is presently in use.
- Leaking roofs, broken/missing doors and windows, untidy water kiosks pose safety and health hazards.
- Water kiosks to be rehabilitated.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 1
PROJECT DESCRIPTION
Scope of Project
The Final Design for Construction of New Water Supply System for Butere, Musanda and Navakholo Towns is based on the Feasibility Report - Rural Water and Sanitation Schemes prepared by CES/GFA/MIBP Consulting Engineers (February 2007).
The Works to be undertaken are as follows:
Butere Works
• Rehabilitation Works:
− Rehabilitation of existing 4 Nr Boreholes including cleaning and developing of Borehole and provision of suitable Control Panel,
− Rehabilitation of existing Transmission Main, Storage Tank and Distribution Network.
• New Works:
− Development of 4 Nr Production Boreholes, approximate depth 60m - 70m, each with estimated total yield of 29m3/hr, including installation of pumps, control panels, site and ancillary works etc.
− Borehole Manifold Pipeline – length 2.1km, 80mm dia., ferrous pipe
− Pumping Main from Borehole to Elevated Pre-Pressed Steel Tank– 50mm dia. ferrous pipe, total length approximately 100m
− 2no.Elevated Pre-Pressed, Steel Tank – total capacity 300m3
• On-Site Sanitation & Hygiene Campaigns
− Construction Programme to Build Ventilated Improved Pit Latrines
− Artisan Training Programme
− Hygiene and Community Awareness Campaigns A Schematic Layout Plan showing location of the Proposed Works including Boreholes, Transmission Mains and Storage Tanks is given in Figure 3.1 on Page 3-3. A Site Layout Plan of a Typical Borehole, Chlorination and Storage Tank Site is given in Figure 3.2 on Page 3-4.
Musanda and Navakholo Works
Under the Water and Sanitation Improvement Project (WaSSIP) only Rehabilitation of the Existing Water Supply systems for Musanda and Navakholo Trading Centres is to be carried out. The Objective is to Rehabilitate the Existing Water Supply Systems in these two areas to optimise supply.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 2
The Scope of the Rehabilitation Works is follows:
i) Musanda Trading Centre a) Borehole Site – Musanda Primary School Borehole
• Development and cleaning to original depth 43m
• Construction of Borehole Control Room
• Installation of Borehole Control Panel and Switchgear
• Ancillary Works e.g. fencing drainage, etc.
b) Distribution System
• Construction of Water Kiosk (1Nr.)
• Rehabilitation of existing Storage Tanks
• Rehabilitation of Appurtenances, gate valves, water meters, etc.
c) Chlorination Facility
• A provision has been allowed for 1Nr. Chlorination Facility at the Borehole Sites, however, implementation will depend on availability of funds
ii) Navakholo Trading Centre
a) Borehole Site – Bukhari Market
• Development and cleaning to original depth - 67m
• Construction of Borehole Control Room
• Installation of Borehole Control Panel and Switchgear
• Ancillary Works e.g. fencing drainage, etc.
b) Distribution System
• Construction of Water Kiosk (3Nr.)
• Rehabilitation of Storage Tanks
• Rehabilitation of Appurtenances, gate valves, water meters, etc.
c) Chlorination Facility
• A provision has been allowed for 1Nr. Chlorination Facility at the Borehole Sites, however, implementation will depend on availability of funds
.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 3
Fig
ure
3.1
– S
ch
em
ati
c L
ayo
ut
Pla
n o
f P
rop
osed
Bu
tere
Wate
r S
up
ply
Au
gm
en
tati
on
Wo
rks
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 4
Fig
ure
3.2
–
Sit
e L
ayo
ut
Pla
n o
f a T
yp
ical B
ore
ho
le, C
hlo
rin
ati
on
an
d S
tora
ge T
an
k S
ite
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 1
POSSIBLE ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
Major Elements of the Surrounding Environment There are no sensitive parts of the natural environment which may be adversely affected by the Project during construction or after completion of the Project. In fact, the proposed works will improve the natural environment considerably and bring it to acceptable levels as leaking appurtenances will be repaired, excavated areas backfilled and planted with natural growth in the area, etc.
Measures to Minimize Environmental Impacts In order to minimise the Project’s potential effects on the environment, efforts will be made to do the following:
• Disturb as little land as possible.
• Store construction materials sheltered from the weather in approved Contractor’s yards.
• Efficiently plan the logistical aspects of the work so as to minimise the pollution caused by transport vehicles. Watering of dirt roads wherever required.
• Minimise hauling of saturated excavated loads.
• Carry out the work in as precise and short time as possible.
• Leave the site as clean as or cleaner than the condition that it was initially found in.
• Keep the local residents informed, in advance, of works to be carried out in the area.
Possible Severity, Distribution and Duration of Environmental Effects Only a localised minor environmental effect is anticipated as a result of this part of the Project. The effects should be of a very short term as the local flora and fauna adjust to the new environment.
Potential Negative Impacts and Mitigation Measures The anticipated environmental impacts and their potential mitigation measures are given in Table 4.1 that follows.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 2
Table 4.1- Potential Impacts and Mitigation Measures
Potential Impact Mitigation Measure Scale of Impact /
Remark
Construction Impacts
• Minor destruction of
natural habitats, forests
wetlands, vegetation
cover, etc
• There are no protected or ecologically sensitive
natural habitats, forests, wetlands or protected
areas in the immediate vicinity of the works that
will be damaged or exploited by the project
construction or operation
• Any adjacent wetlands and streams shall be
protected from construction site runoff and
appropriate filtering and siltation prevention
measures shall be undertaken
• Landscaping to be done after construction works
to blend with the surrounding area
• Land to be rehabilitated by planting trees and
ornamental bush / flowers on disturbed areas
• Direct, temporary
• Vibration, noise, air
pollution and dust
generation by traffic
and machinery
• Strict control under construction contract to limit
these impacts to acceptable levels
• Watering to be enforced to keep dust levels low
• Use of approved construction plant during normal
working hours (daytime only)
• Cover to haul trucks carrying excavated material
• Construction plant and equipment Machinery to
be well maintained to prevent oil spillage, air
pollution, etc
• Workers to wear masks and ear muffs in
sensitive areas
• Control speed and operation of construction
vehicles
• Contractor to have a designated area where
maintenance will be carried out that is protected
from rain water that would carry oil to the river
• Prohibit idling of vehicles
• Direct, temporary
• Storage of construction
material, oil and
gasoline for machinery
• Strict control by Supervising Engineer to ensure
acceptable storage practices
• Contractor to have a designated storage area
that is protected from rain water
• All oil products to be stored and handled carefully
• Direct, temporary
• Dumping of excavated
material
• Earthworks have been designed such that cut
and fill balance will be maintained (zero mass
balance) to avoid disposal of or need for extra
material
• Dumping to be done at designated sites only
• During decommissioning stage land to be
• Direct, temporary
• Zero mass
balance will
reduce
construction
traffic from and to
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 3
Potential Impact Mitigation Measure Scale of Impact /
Remark
rehabilitated by removing unnecessary materials
that shall be covering the land and preventing the
natural biodiversity
construction site
significantly
• Soil erosion and
Compaction
• At decommissioning of Contractor’s Yard / other
Sites phase, land to be rehabilitated by loosening
the soil which would be compacted by the project
• Soil conservation structures to be provided over
areas prone to soil erosion mostly to reduce
impact by run-off
• Direct, temporary
• Disruption of normal
water supply and
wastage
• Entry of sediments and
pollutants in the
distribution system
• Provision of temporary make up pipe pieces and
fittings to maintain continuity of supply
• Execute flushing and disinfecting affected
sections
• Direct, temporary
• Solid Waste
Generation
• Construction of a central waste collection point
with bulk storage facilities
• The site will have waste receptacles at
convenient points to prevent littering during
occupation
• During operation phase, waste to be collected
and disposed off appropriately
• Indirect, Long
Term during
operation phase
• Work camp increases
pressure on
environment, e.g.
firewood cutting,
poaching, etc.
• Awareness workshop for workforces to be held
periodically
• Strict control under construction contract
• Direct, temporary
• Workforce accidents by
unsafe working
practices, e.g. work in
ditches, contact with
wastewater, fire
outbreak, etc
• Awareness workshop for workforces on safe
working practices, periodically
• Strict control by Supervising Engineer to limit
safety hazards
• First Aid Equipment to be provided during the
construction at reasonable places and sites for
providing care in case of accidents.
• Warning signs, lighting and backfilling trenches
as soon as works are completed
• Protection rails / warning signs at deep trenches
• Well maintained sanitary facilities for the workers
and visitors on site
• Proper signage to be put in place to notify those
• Direct, temporary
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 4
Potential Impact Mitigation Measure Scale of Impact /
Remark
within areas of Works of the activities and heavy
vehicles and to direct traffic
• Fire fighting drills to be carried out frequently
• Fire fighting emergency response plan to be in
place all the time
• Fire fighting equipment which is to be regularly
maintained, serviced and inspected to be in
place
• Fire hazard signs and directions to emergency
exit, route and assembly point to be indicated in
case of fire outbreak
Operational Impacts
• Pollution by Stored
Water Treatment
Chemicals – Chlorine
• Safe Storage facilities to be provided. Chemical
Storage areas to be constructed with hardened
cement screed floor finish with approved epoxy
floor coating. Chemical solutions pipes to raw
water tanks will be uPVC protective piping.
• Direct, long term
• Pollution by Disposal of
chemical sludges -
chlorine.
• Calcium hypochlorite residual waste to be kept in
Soak Pits, which will be constructed to drain
away from river / water courses.
• Water treatment will be done at a minimum
disinfection / chlorination.
• Sludge to be dried and sold or disposed in
dumps. Sludge is not expected to contain high
percentage of heavy metals as there are no
heavy industries in the vicinity. However testing
for trace metals to be undertaken regularly
before sale of sludge for agricultural use.
• Periodic monitoring to be undertaken to ensure
that suspended solids and biodegradable
organics in sludge discharges will not clog rivers
or result in unduly reduced oxygen levels
• Testing for heavy metals in dried sludge for sale
and in Disposal Pits to be carried out once a
year. Where wastewater is to be disposed in
rivers / water courses testing of water in the
receiving body to be carried out monthly.
• Direct, long term
• Pollution by
Wastewater
Generation and
disposal by workers
and visitors to
Disinfection Sites
• Septic Tank to be provided for sanitation • Direct, long term
Socio-Economic, Health and Safety Impacts
• Work camp increases • Provision of services for work camp, e.g. • Direct, temporary
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 5
Potential Impact Mitigation Measure Scale of Impact /
Remark
pressure on public
services e.g.
transportation, water
demand, etc.
transportation to town, on-site water supply etc
• Workforce
requirements might
lead to increased
immigration of people
from other areas into
the Town
• Employment of local people for most of the
workforce requirements. Imported staff limited to
skilled staff and permanent employees of
contractor
• Indirect, long
term
• Increase in sexually
transmitted diseases
e.g. AIDS
• Awareness workshop for workforces to be held
periodically
• Controlled access of outsiders to work camp
• Indirect, long
term
• Health risks and Injury
to workers on site
during construction
and operation
• All workers to be provided with full protective
gear i.e. working boots, overalls, helmets,
goggles, earmuffs, masks and gloves
• Well stocked First Aid Kits to be provided within
the Site and all construction vehicles. The kits to
be fully equipped at all times and managed by a
qualified person
• Contractor to have workmen’s compensation
which is to be compliant with Workmen’s
Compensation Act, as well as Ordinances,
Regulations and Unions Agreements
• Adequate sanitary facilities to be provided and
general cleanliness maintained
• Food handlers preparing food for the workers at
the site to be controlled and monitored to ensure
that food is hygienically prepared
• Security guards to be provided during
construction and operational phase
• Adequate lighting and alarm systems installed at
strategic points
• Safety equipment and fire extinguishers to be
provided on-site. To be provided and monitored
by LVNWSB
• Site to be fenced to prevent access by
unauthorised persons
• Septic tank provided for sanitation and potable
water provided to on-site workers from an
elevated tank (existing elevated tanks to be
rehabilitated by cleaning and rust-proofing). Staff
housing to be fenced off from rest of the Works.
• Indirect, long
term
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 1
THE NO-PROJECT OPTION
The No-Project Option is considered if the Project would not be implemented according to common EIA-Guidelines with regard to the assessment of benefits and impacts.
Generally, it can be stated that the minor adverse impacts caused by the Project construction activities such as impacts on soil, air and vegetation would not occur. During operation, no adverse impacts are foreseen.
The No-Project Option however would consequently result in a number of more important negative effects which refer to:
- The population of the Towns and their environs will go on suffering from
water shortages.
- Some population in informal settlements and rural areas will continue drinking water which is at present not treated or subjected to any disinfection processes, resulting in increase of water borne diseases.
- Institutions like Schools, Health Centres, etc. will keep on suffering from unreliable treated water supply giving rise to water borne diseases.
- The existing appurtenances will not be rehabilitated and will go on deteriorating with all associated environmental risks.
- Time used in search of water will not be saved for utilisation in economical activities.
- Employment opportunities connected with the Project implementation would not be available.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
CES/MIBP JV 1
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
As part of an EIA, the Environmental Management and Coordination Act, 1999, requires that an Environmental Management Plan (EMP) be provided. In the EMPs presented in this Chapter, key Impacts and mitigation measures as described in Chapter 4 are summarised. Parties responsible for the various actions and monitoring activities are identified and an indication of the cost involved is given, where possible.
Detailed EMPs are given in the following Tables.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
2
Table 6.1: EMP for Planning Phase of Project
Issue / Impact Management Strategy
Actions Performance Indicators
Monitoring Requirements
Responsibility Cost
Purchase of Land for: - Borehole Sites in
Butere
To ensure land owners are adequately compensated and the process complies with the laws of Kenya
• Land valuation to be undertaken and the sites to be purchased at current market values on basis of “willing seller, willing buyer”.
• Compensation of any existing crops and trees destroyed according to present crop valuation. Valuation to be undertaken by District Agricultural Officer
Lack of Complaints
Documentation LVNWSB and a series of private land owners
District Agricultural Officer
To be determined based on market land and crop values.
Selection of most suitable water supply source
Ensure sustainability of water supply source
• Water Resources Studies have been carried out which show the proposed source, supply from Boreholes, is the most economically viable.
• Hydrogeological Field Investigations carried out using Resistivity Sounding Technique established the sustainable yields from the 4 Nr Proposed Borehole Sites ranging between 3 -10 m
3/hr.
N/A Regular Test Pumping e.g. Annually
Consultants - CES/MIBP
To be determined at operations stage.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
3
Table 6.2: EMP for Construction Phase of Project
Issue / Impact Management Strategy
Actions Performance Indicators
Monitoring Requirements
Responsibility Cost
Habitat loss – construction will result in loss of some flora and fauna in: the Borehole / Chlorination / Storage Tank Sites and along transmission pipes routes
Provide measures to protect habitats for flora and fauna
• Habitat loss will be minimized and monitored.
• Where possible, no trees will be removed.
• Replanting with indigenous plants and trees to be implemented. e.g. indigenous tree seedlings to be planted along the transmission mains some metres away from the pipeline on either side of the pipeline where permissible.
• Presence of a good balance of flora and fauna
• Lack of flooding in project area
• Comparison between baseline habitat and current habitat
• Changes in local runoff characteristics
Contractor, monitored by the Supervising Engineer.
Cost of indigenous tree seedlings for length of transmission route estimated to be approx. KShs. 5,000.
Increased soil erosion – this may occur along trenches for water pipelines
Implement technical measures to prevent soil erosion
Soil erosion induced by excavation activities to be reduced by sowing of grass.
Shoring and support to be provided for Deep water pipeline trenches
• Sediment presence in storm channels and runoff
• Lack of complaints
Daily visual inspection of work sites and storm channels especially after heavy rainfall
Supervising Engineer. District Agricultural Officer District Environmental Officer
Cost of Preventive measures included in detailed Bills of Quantities No additional cost.
Deterioration of soil properties – the levelling of the Borehole / Chlorination / Storage Tank Sites and the excavation of trenches for water pipelines will result in disturbance of natural soil structure, mixing of layers and compaction.
Implement measures to protect natural soil properties
Top soil to be stockpiled separately from subsoil. After completion of works, the top soil to be spread over those areas which can be partially restored in order to facilitate natural regeneration of those areas. Compaction of soil to be minimized by careful stockpiling and separation of top and sub-soils. All excavated material to be carefully re-used, replaced and/or levelled and planted up with grass and other indigenous seedlings, as necessary.
• Regeneration and re-growth of vegetation
Monitoring 3 months, 6 months and 9 months after replacement of soil. If re-growth and regeneration of material has not taken place, Contractor to replant the area.
Supervising Engineer District Agricultural Officer District Environmental Officer
Included in the Bills of Quantities No additional cost.
Deterioration in air quality – activities such as site clearance and excavation at Borehole / Chlorination / Storage Tank Sites,
Implement measures to minimise air pollution
• A water bowser will be used to miminize dust generation on all murram (dirt) roads.
• Vehicle and equipment emissions to be kept within reasonable
Lack of complaints
Daily inspection of work sites
Contractor, monitored by Supervising Engineer
Compliance included in Bills of Quantities and Specifications. No additional cost.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
4
Issue / Impact Management Strategy
Actions Performance Indicators
Monitoring Requirements
Responsibility Cost
/ Storage Tank Sites, Pipeline trenches, and transportation of materials on unpaved roads will result in dust emissions
limits by maintaining equipment to manufacturer’s specification. In addition, Contractors to be encouraged to use unleaded petrol and low sulphur diesel (both now available in Kenya) for all vehicles and equipment.
Pollution of areas adjacent to construction sies by construction waste materials e.g. used lubricants, oil, paints and other construction materials
Effective management of the sites, contractors yards and storage yards
• Wastes to be properly contained in designated areas on the sites prior to disposal
• Wastes to be regularly cleared from site and disposed of in approved manner
• Staff to be regularly trained and sensitized on waste management
Absence of waste at sites except in designated locations Laboratory tests
Regular site inspections and Laboratory Tests
Supervising Engineer. District Water Officer.
Specified in the Bills of Quantities and Specifications with a penalty Clause for non-compliance. No additional cost.
Health and Safety of Contractor’s Team and Construction Work
Provide appropriate safety equipment and work conditions to reduce risk to workers
Ensure Contractor’s staff have undergone appropriate training and ensure appropriate signage and procedures are used. First Aid Equipment to be provided during the construction at reasonable places and sites for providing care in case of accidents.
Frequency of accidents / incidents
Daily inspection of work sites
Supervising Engineer. Included in the Bills of Quantities and Specifications No additional cost.
Table 6.3: EMP for Operation Phase of Project
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
5
Issue / Impact Management Strategy
Actions Performance Indicators
Monitoring Requirements
Responsibility Cost
Improved Water Supply to the Project Area
Ensure Project operation achieves intended objective i.e. improved water supply and sanitation for area residents
• Ensure all water connections are metered
• Minimise water losses.
• Develop Management Plans, Maintenance Plans, Evaluation and Monitoring Plans
• Set management performance targets
• Project technical and financial sustainability
• Unaccounted for Water levels (UFW)
• Customer feedback
Develop and implement an Evaluation and Monitoring Plan
LVNWSB Water Service Provider Council Water Officers Community Members
Cost is variable and primarily dependent on allocated budget form LVNWSB for checking water metering and losses.
Pollution by Water Treatment Chemicals Storage - Chlorine
Provide safe storage facilities according to health and safety regulations.
• Safe Storage facilities to be provided, with appropriate Personal and (Environment) Protective Equipment (PPE).
• Chemical Storage areas to be constructed with hardened cement screed floor finish with approved epoxy floor coating. Chemical solutions pipes to raw water tanks will be uPVC protective piping.
Frequency of accidents / incidents
Regular inspection of storage sites
LVNWSB / Water Service Provider
No additional cost.
Pollution of adjacent land and water courses by Disposal of Sludge from Chlorination Processes.
• Develop appropriate disposal practices
• Water Quality Testing to ensure that potable standards are maintained and that any effluent meets NEMA’s standards.
• Calcium hypochlorite, Alum and Soda Ash residual waste to be kept in Soak Pits, which will be constructed to drain away from river / water courses.
• Water treatment will be done using minimum amount of chemicals. Periodic laboratory tests on raw water to be done to determine minimum dosage of chemicals to be used – alum, soda ash, chlorine.
• Sludge to be dried and sold or disposed in dumps. Sludge is not expected to contain high percentage of heavy metals as there are no heavy industries in the vicinity. However testing for trace metals to be undertaken
Favourable environmental health
Regular Monitoring of soil condition of disposal sites / pits
LVNWSB / Water Service Provider
No additional cost.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
6
Issue / Impact Management Strategy
Actions Performance Indicators
Monitoring Requirements
Responsibility Cost
regularly before sale of sludge for agricultural use.
• Periodic monitoring to be undertaken to ensure that suspended solids and biodegradable organics in sludge discharges will not clog rivers or result in unduly reduced oxygen levels
• Testing for heavy metals in dried sludge for sale and in Disposal Pits to be carried out once a year. Where wastewater is to be disposed in rivers / water courses testing of water in the receiving body to be carried out monthly.
Health and Safety of operations staff
Provide training, appropriate safety equipment and work conditions to reduce risk to workers
• Awareness workshop for staff on safe working practices, periodically
• First Aid Equipment to be provided for providing care in case of accidents.
• Fire fighting drills to be carried out frequently and Fire fighting emergency response plan to be in place
• Fire hazard signs and directions to emergency exit, route and assembly point to be indicated in case of fire outbreak
• Adequate lighting and alarm systems installed at strategic points
• Safety equipment and fire extinguishers to be provided on-site and monitored by LVNWSB
• Site to be fenced to prevent access by unauthorised persons
• Staff housing to be rehabilitated, septic tank provided for sanitation and potable water provided to on-
Frequency of accidents / incidents
Daily inspection of work sites
LVNWSB / Water Service Provider
To be established at operations phase.
EIA / EMP BUTERE, MUSANDA & NAVAKHOLO
7
Issue / Impact Management Strategy
Actions Performance Indicators
Monitoring Requirements
Responsibility Cost
site workers from an elevated tank (existing elevated tanks to be rehabilitated by cleaning and rust-proofing). Staff housing to be fenced off from rest of the Works.
Continuing degradation and destruction of water catchment areas in the region.
Development of a catchment protection plan
Formation of a Catchment Protection Association (CPA) urgently required. This association should aim to:
• Design and execute public awareness campaigns to educate the population on the importance of the preservation of the forest and natural resources
• Establish a nursery and propagate indigenous and exotic species
• Systematically re-plant sections of the catchment
• Systematically encourage the surrounding communities to embrace farm forestry and plant a mix of indigenous and exotic trees on their farms. Set targets of, for example 10 trees per plot per year.
Improved and sustained river flow regime for rivers / ground water in the region
Develop and implement a Catchment Monitoring Plan
LVNWSB District Forest Officer District Water Officer District Environment Officer Key Community Members
To be established at operations phase.
ANNEX 1
MINUTES OF STAKEHOLDERS MEETING
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 1 of 7
WATER SUPPLY AND SANITATION SERVICES IMPROVEMENT PROJECT
(WASSIP)
Water Supply and Sanitation for the Nzoia Cluster Phase III, Step 1 and 2:
Rehabilitation and Augmentation of Butere, Musanda and Navakholo Water Supply
Systems
MINUTES OF STAKEHOLDER’S MEETING HELD ON 21st JULY, 2010 AT
ESHUMULI GUEST HOUSE, BUTERE FROM 11:00 HRS
PRESENT:
Nr. Name Designation/Organization
1. Mr. Peter Sewe Engineer, CES/MIBP JV
2. Mr. Paul Kogo Engineer, CES/MIBP JV
3. Mr. Bernard Mulele District Water Officer, Butere District.
4. Mr. B. K. Cheboswony District Water Officer, Mumias District.
5. Mr. Daniel C. Jakait District Water Officer, Khwisero District.
6. Mr. Enos Mwanza Deputy District Water Officer, Butere District.
7. Mr. Albert S. Kulundu Deputy District Water Officer, Kakamega Central District.
8. Mr. Protus Musawa District Environmental Officer, Butere/Mumias Districts.
9. Mr. Stanley K. Langat Provincial Administration /District Officer, South Wanga
District.
10. Mr. Jacob Mumia District Development Officer, Butere District.
11. Mr. Edward B. Wekesa Catchment Development Officer, Water Resources
Management Authority, Butere District.
12. Mr. Fredrick Opondo Deputy Public Health Officer, Butere District.
13. Mr. Harrison Mugera Boarding Master, Butere Boys Secondary School.
14. Mr. Julius Shireka Chairman, Musanda Community Piped Water Project.
15. Mr.Francis Mulama Caretaker Chairman, Musanda Community Piped Water
Project.
16. Mr. Edwin Namayi Caretaker Clerk, Musanda Community Piped Water Project.
17. Ms. Melsa Khaoya Member, Water Action Group, Butere District.
18. Mr. Gerald M. Siambiri Chairman, Navakholo Water Supply.
19. Mr. Charles Juma
Wambongo
Secretary, Navakholo Water Supply.
20. Mr. Edward Wabwire
Wakhura
Executive Member, Navakholo Water Supply.
21. Mr. Francis Mapesa
Wakhura
Vice Chairman, Navakholo Water Supply.
22. Mr. Lazarus Kwabi
Baserecha
Vice Secretary, Navakholo Water Supply.
23. Mr. John Nambua O. Clerk, Navakholo Water Supply.
24. Mr. Faustino O. Shitabule Chairman, South Wanga Water Users Association.
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 2 of 7
1. INTRODUCTION
LVNWSB Representative welcomed all present and after self introduction of all present,
explained that the meeting had been convened to receive feedback on the proposed
Project - Rehabilitation and Augmentation of Butere, Musanda and Navakholo Water
Supply Systems.
LVNWSB Representative emphasized that participation of the stakeholders is vital in
ensuring success of the Project and asked all present to air their views freely. The agenda
of the meeting was set as follows;
1. Consultants Brief on the Proposed Project;
2. Participants’ Comments/Queries/Remarks and Responses by LVNWSB and
CES/MIBP JV;
3. Closing Remarks from LVNWSB;
4. Any Other Business.
2. CONSULTANT’S BRIEF ON THE PROPOSED PROJECT
CES/MIBP JV Representative gave a brief of the proposed project as follows:
A. WATER SUPPLY COMPONENTS
1. Butere Town
New Water Supply Facilities Comprising of 4Nr. New Boreholes, Pipelines and
Ancillary works will be constructed for Butere. The capacity of the New
Borehole System will be 570m3/day. The existing boreholes and pipelines will
also be rehabilitated.
Briefly, the Project Components are as follows:
• Development of 4Nr. Boreholes, approximate depth 60 – 70m, each with
estimated yield ranging from 3m3/hr to 8m
3/hr, including installation of
Pumps, Control Panels and Site & Ancillary Works at each Borehole Site.
• Borehole Manifold pipeline – length 2.1km, 80mm dia. ferrous pipe.
• 2Nr. 150m3 elevated Pressed Steel Storage Tank including 12m high tower,
associated pipework and fittings.
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 3 of 7
• 3Nr. Chlorination Buildings including equipping with mixing tanks, dosers,
mixers, dosing pumps, etc.
• Gravity Main – length 4.0km, 100mm dia. ferrous pipe.
• Minor Rehabilitation Works at 2nr. existing Boreholes Sites including
associated ancillary works.
2. Musanda and Navakholo Trading Centres
For Musanda and Navakholo Trading Centres, only Rehabilitation Works for
existing boreholes is proposed under the current phase of the Project. Extra funds
are being sourced by LVNWSB for Expansion Works.
The Rehabilitation Works involve rehabilitation of 1Nr. Existing Borehole in
each of the two Trading Centres, rehabilitation of existing Pipelines and Storage
Tanks and construction of Water Kiosks.
Briefly, the Project Components are as follows:
(i) Musanda Trading Centre
a) Borehole site - Musanda Primary School Borehole
• Development and clearing to original depth 43m;
• Construction of Borehole control Room;
• Installation of Borehole Control panel and switchgear;
• Ancillary works e.g. fencing, drainage, etc.
b) Distribution System
• Construction of Water Kiosk (1Nr.);
• Rehabilitation of existing Storage Tanks;
• Rehabilitation of Appurtenances; Gate Valves, Water Meters, etc.
c) Chlorination Facility.
• A provision has been made for construction of 1 Nr. Chlorination
Facility at the Borehole sites.
(ii) Navakholo Trading Centre
a) Borehole site – Bukhari Market
• Development and cleaning to original depth -67m;
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 4 of 7
• Construction of Borehole Control Room;
• Installation of Borehole Control Panel and Switchgear;
• Ancillary works e.g. fencing, drainage, etc.
b) Distribution System.
• Construction of Water Kiosks (3Nr.);
• Rehabilitation of Storage Tanks;
• Rehabilitation of Appurtenances; Gate Valves, Water Meters, etc.
c) Chlorination Facility
• A provision has been made for construction of 1nr. Chlorination
Facility at the Borehole sites.
B. ON-SITE SANITATION.
• Construction Programme to Build Ventilated Improved pit Latrines
• Artisan Training Programme
• Hygiene and community Awareness Campaigns.
3. PARTICIPANTS’ COMMENTS/QUERIES/REMARKS AND RESPONSES BY
LVNWSB AND CES/MIBP JV;
No NAME AND
DESIGNATION
QUESTION RESPONSE
1. Mr. Harrison
Mugera,
Boarding Master,
Butere Boys
Secondary
School.
What are the dangers posed
to consumers by supplying
un-chlorinated water while
using the existing system?
Although chlorination was not
being carried out, periodical tests
show that the level of
contamination has been negligible
and within acceptable limits.
However, there has been an
increase in rural to urban
migration. This has increased the
population of persons living in
town. Since there is no proper
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 5 of 7
No NAME AND
DESIGNATION
QUESTION RESPONSE
sewerage, there is likelihood that
level of contamination may go
high. That is why the Project has
undertaken to construct
chlorination units.
2. Mr. Fredrick
Opondo, Deputy
Public Health
Officer, Butere
District.
You have mentioned that
the project will carry out
Hygiene and Community
Awareness Campaigns as
well as Construction
programme to build
Ventilated Improved Pit
Latrines. What role will the
Public Health Office play?
The role of Public Health Office
will be to liaise with the Project
Team in carrying out Hygiene and
Community Awareness Campaigns
as well as identification of
locations for Construction of
Ventilated Improved Pit Latrines.
Has the project carried out
an Environmental Impact
Assessment for this
project?
Environmental Impact Assessment
for this project has been carried
out. However the Assessment will
not be deemed fully completed
before the views of all the affected
stakeholders is heard and
discussed. This meeting serves to
record all this views.
Are there any plans to
construct sewerage plants?
The scope of works does not
include construction of a sewerage
facility. The study carried out
shows that the construction of
Ventilated Improved Pit Latrines
will keep the hygiene situation at
manageable levels.
3. Mr. Edward B.
Wekesa,
Catchment
Development
Officer, WRMA,
Butere District.
What is the status of land
acquisition especially
where the Boreholes are
located?
LVNWSB is in the process of
acquiring any private land deemed
necessary prior to commencement
of the Project.
4 Mr. Gerald M.
Siambiri,
Chairman,
Navakholo Water
Supply.
Will the funding cater for
enough reservoir tanks
since we are encountering
a lot of leakage problems
on the existing tanks?
All the existing tanks will be
rehabilitated.
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 6 of 7
No NAME AND
DESIGNATION
QUESTION RESPONSE
How will the compensation
of the lands affected be
carried out?
All the procedures of compensation
shall be carried out based on
government procedures for land
acquisition.
What is the percentage of
funding between the towns
of Navakholo & Musanda?
How was it reached at?
The allocation of funds is based on
scope of works necessary to ensure
potable water provision to each
Town.
5. Mr. B. K.
Cheboswony,
District Water
Officer, Mumias
District.
Will the scope of work
include supply of steel
tanks to replace existing
PVC tanks which are
leaking?
Our scope of work only entails
rehabilitation. If however, some
tanks are beyond repair, supply of
equivalent tanks shall be
considered based on availability of
funds.
6. Mr. Albert S.
Kulundu, Deputy
District Water
Officer,
Kakamega
Central District.
Even when the Boreholes
in Navakholo are
rehabilitated, the cost of
power is too high.
Is there any possibility of
looking into other options
of power supply?
LVNWSB shall look into policies
and tariffs, so as to make water
affordable to consumers with
manageable cost of supply.
Other options of power supply are
wind energy and solar energy,
which were not considered because
of limited funding.
7. Mr. Gerald M.
Siambiri,
Chairman,
Navakholo Water
Supply.
We have done feasibility of
using solar energy on one
borehole in Navakholo and
we have drafted a KShs.
1.5 Million proposal.
We have presented this to
Lurambi CDF but they say
it is too high. Will the
board consider this
proposal?
The proposal should also be
submitted to the water Board to
consider.
8. Mr. Bernard
Mulele, District
Water Officer,
Butere District.
So as to avoid interruptions
in supply of water during
rehabilitation of the
existing 72m3 reservoir at
Butere, will the project
supply or build a new one
to be used during this
The contract will be asked to
include measures to ensure
continuous supply of water during
construction.
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 7 of 7
No NAME AND
DESIGNATION
QUESTION RESPONSE
construction period?
9. Mr. Jacob
Mumia, District
Development
Officer, Butere
District.
Why can’t we go for
gravity schemes with little
operation cost even with
the little money we have
rather than boreholes
which have high running
costs.
The capital cost of a gravity
scheme that can apply to this are is
much higher than the funds
available.
What Conservation
measures have been
planned to ensure that the
source of water for the
Project is sustainable?
Planting of trees and vegetation to
minimize surface run-off and thus
encourage recharge of underground
aquifer.
10. Mr. Protus
Musawa, District
Environmental
Officer,
Butere/Mumias
Districts.
Did the Project consider
other sources of supply?
If so what are the results of
Cost Benefit Analysis that
made the Consultant
choose the boreholes as
source of supply?
The Project is not a new water
supply system but rather is an
improvement of already existing
water supply systems. Majority of
the works is rehabilitation with
minor new works like Chlorination
Units.
4. CONCLUSION
The Stakeholders’ Meeting concluded by unanimous resolution of No Objection to
the implementation of the Proposed Project, Rehabilitation and Augmentation of
Malaba & Malakisi Water Supply Systems.
5. CLOSING REMARKS
LVNWSB Representative, Mr. Bernard Mulele, thanked all the participants for their
positive input during the discussions and assured that all concerns raised and recorded
will be addressed accordingly.
Mr. Mulele further notified that there being no objection to the commencement of the
construction phase of the Project, the Project is expected to commence before the end of
the year and take 12 months to complete.
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
Page 8 of 7
6. ANY OTHER BUSINESS
There being no other business the meeting concluded at 12:15 Hrs with prayers from Ms.
Melsa Khaoya.
Notes by Paul Kogo
CES / MIBP JV
Attachments:
1. Photographs
2. Signed Attendance Lists
3. Copies of Invitation Letters
JOINT VENTURE
WATER SUPPLY & SANITATION PROGRAMME NZOIA CLUSTER – PHASE III, STEPS 1 AND 2: Four (4) Towns: Butere, Malakisi, Mumias and Kimilili Three (3) Rural Water Supply and Sanitation Clusters and Nine (9) Independent Rural Water Supply and Sanitation Schemes
E29050EA0P126605740B0AFR0EA0P126637.doc Page 1 of 1
Consultant’s Representative, Mr. Sewe, gives
a Presentation on the Proposed Project.
Participants listen to the Consultant’s
Presentation
LVNWSB Representative, Mr. Bernard
Mulele, responds to Participants’ queries at the
Meeting
Some of the Participants at the Meeting
SIGNED ATTENDANCE LIST