PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
Request for Determination of Applicability
June 23, 2020
Subject Property
National Grid
Commercial Point
220 Victory Road
Boston, Massachusetts
Applicant
Boston Gas Company d/b/a National Grid
New England South Division
100 East Ashland Street
Brockton, MA 02302
LEC Environmental Consultants, Inc.
100 Grove Street
Suite 302
Worcester, MA 01609
508-753-3077
508-753-3177 fax
www.lecenvironmental.com
June 23, 2020
Federal Express and Email ([email protected])
Boston Conservation Commission
City Hall
1 City Hall Square, Room 709
Boston, MA 02201
RE: Request for Determination of Applicability [LEC File #: PALInc\15-153.04]
Operations and Service Center Decommissioning
National Grid
Commercial Point
220 Victory Road
Boston, Massachusetts
Dear Members of the Commission:
On behalf of Boston Gas Company d/b/a National Grid (Applicant), LEC Environmental Consultants,
Inc. (LEC) respectfully submits the enclosed Request for Determination of Applicability (RDA) for work
associated with the decommissioning of the Operations and Service Center at National Grid’s
Commercial Point facility located at 220 Victory Road in the Dorchester neighborhood of Boston,
Massachusetts. This filing is submitted pursuant to the Massachusetts Wetlands Protection Act (Act,
M.G.L.c.131 § 40) and its implementing Regulations (Act Regulations, 310 CMR 10.00), and the City of Boston Wetlands Protection and Climate Change Adaptation Ordinance (Chapter 7-1.4, Ordinance).
The project area is located within the previously developed/disturbed 100-foot Buffer Zone and 25-foot
Waterfront Area to Coastal Beach/Coastal Bank, and/or Land Subject to Coastal Storm Flowage (Zone
VE) associated with the Neponset River. The Applicant proposes to implement an erosion control
program to protect the adjacent wetland resource areas during demolition activities, and the site will be
stabilized and restored to pre-existing conditions following said activities.
As required, enclosed are 2 copies of the RDA submission package:
DEP WPA Form 1-Request for Determination of Applicability and Abutter Notification
Documents (Appendix A);
USGS Topographic Map (Appendix B, Figure 1);
MassGIS Orthophoto & NHESP Estimated Habitat Map (Appendix B, Figure 2);
FEMA Flood Insurance Rate Map (Appendix B, Figure 3);
Site Photographs (Appendix B); and
Site Plan entitled, Site Demolition and Erosion Control Plan, National Grid, Commercial Point,
220 Victory Road, Boston, MA, prepared by Nitsch Engineering, Inc., June 24, 2020 (Appendix
C).
PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
It is our understanding that the Conservation Commission will legally post the RDA application and
required public meeting so as to appear on the Conservation Commission’s July 8, 2020 agenda.
In conclusion, the proposed project fully complies with the governing regulations such that we
respectfully request the Commission to issue a Negative Determination of Applicability allowing the
work to proceed as described herein.
We trust that the information included herein is sufficient to facilitate your review. Should you have any
questions regarding this RDA or require additional information, please do not hesitate to contact me at
508-753-3077 or at [email protected]. Thank you for your consideration of this RDA, and
we look forward to the remote meeting with the Commission on July 8, 2020.
Sincerely,
LEC Environmental Consultants, Inc.
Andrea Kendall
Senior Environmental Scientist
cc: DEP, Northeast Region
Deborah Blanch, National Grid
Request for Determination of Applicability
National Grid – Commercial Point
220 Victory Road
Boston, Massachusetts
June 23, 2020
PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
Request for Determination of Applicability National Grid-Commercial Point
220 Victory Road
Boston, Massachusetts
Page 1 of 5
PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
1. Introduction
On behalf of the Applicant, Boston Gas Company d/b/a National Grid, LEC
Environmental Consultants, Inc. (LEC) is filing the enclosed Request for Determination
of Applicability (RDA) with the Boston Conservation Commission to decommission the
former Operations and Service Center located at National Grid’s Commercial Point
Facility located at 220 Victory Road in the Dorchester neighborhood of Boston,
Massachusetts. The project will occur, in part, within the previously developed/disturbed
100-foot Buffer Zone and 25-Waterfront Area to Coastal Beach/Coastal Bank, and/or Land Subject to Coastal Storm Flowage (Zone VE). These Wetland Resource Areas are
jurisdictional under the Massachusetts Wetlands Protection Act
(M.G.L. c. 131, s. 40, the Act) and implementing Regulations (310 CMR 10.00,
Regulations), and the City of Boston Wetlands Protection and Climate Adaptation
Ordinance (Chapter 7-1.4, Ordinance). Following decommissioning activities, existing
conditions (i.e., vegetation, crushed stone, and pre-existing elevations) will be restored
and the site will be stabilized.
2. General Site Conditions
National Grid’s Commercial Point Facility (Facility) is located within the southeastern
portion of Dorchester on the north side of Victory Road. The Facility is bound by Route
93 to the west, Morrissey Boulevard to the north, and the Neponset River to the east and
south (Appendix B, Figure 1). The Facility contains photovoltaic solar arrays,
operational buildings, a liquefied natural gas (LNG) tank, and associated infrastructure.
The Project Area is located within the southeast portion of the Facility, at the eastern
terminus of Victory Road, and includes the former Operations and Service Center; a
single-story modular office building, an outdoor gravel parking area, and a vehicle and
equipment storage area. The Project Area is level, contains paved, gravel, and vegetated
surfaces, and is bound by an 8-foot tall chain link security fence.
In 2019, the Operations and Service Center was relocated to another National Grid
facility. While various storage units, supplies, and vehicles were removed, miscellaneous
features remain, including, for example, the modular office building, a 10-foot wide
Request for Determination of Applicability National Grid-Commercial Point
220 Victory Road
Boston, Massachusetts
Page 2 of 5
PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
2.1
2.2
Conex storage box, wooden shed, steel plates, and concrete blocks (Appendix B, Site
Photographs).
The Project Area is located, in part, within the previously developed/disturbed 100-foot
Buffer Zone and 25-foot Waterfront Area to Coastal Beach/Coastal Bank and Land
Subject to Coastal Storm Flowage (Zone VE) associated with the Neponset River.
Natural Heritage and Endangered Species Program Designation
According to the 14th edition of the Massachusetts Natural Heritage Atlas (effective
August 1, 2017) published by Natural Heritage & Endangered Species Program (NHESP)
and the MassGIS data layer, the Project Area is not located within areas of Estimated
Habitat of Rare Wildlife or Priority Habitat of Rare Species. In addition, no Certified
Vernal Pools (CVP) or Potential Vernal Pools (PVP) occur on or within the vicinity of
the Site (Appendix B, Figure 2).
Federal Emergency Management Agency Floodplain Designation
According to the Preliminary March 16, 2016 Federal Emergency Management Agency
Flood Insurance Rate Map for Suffolk County, Massachusetts (Community Panel
25025C0091J), no portion of the Project Area is contained within a Special Flood Hazard
Areas Subject to Inundation by the 1% Annual Chance Flood Zone AE, base flood areas
determined (NAVD 88’, EL 13’) –Area subject to flooding by the 1% annual chance
flood. The Project Area is located within Coastal High Hazard Area Zone VE, base flood
determined (NAVD ’88, EL 14’) - Areas along coasts subject to inundation by the 1-
percent-annual chance flood event with additional hazards due to storm-induced velocity
wave action. The remaining portion of the Project Area located above elevation 14’ is
located within Zone X-Areas determined to be outside the 0.2% annual chance flood.
(Appendix B, Figure 3).
3. Proposed Conditions
National Grid proposes to decommission the Operations and Service Center Facility by
removing all structures, storage units, and miscellaneous features (e.g., remnant fence
posts), disconnecting utilities, and conducting a general surficial clean-up of debris from
within the Project Area.
Request for Determination of Applicability National Grid-Commercial Point
220 Victory Road
Boston, Massachusetts
Page 3 of 5
PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
Building Demolition and Removal of Storage Units
The modular office building will be dismantled in place and removed. Since the building
is elevated on concrete cinder blocks sitting on the ground surface, no excavations of
footings or foundations will be required and ground disturbing activities will thus be
minimized. It is anticipated that demolition and removal of the modular office building
will take roughly four (4) days. Following removal, dense-grade gravel will be placed
within the footprint of the building in order to provide a stable and uniform ground cover
consistent with the adjacent gravel parking area. The staging area for demolition
activities includes the existing gravel parking area. Any disturbed areas within the gravel
parking area resulting from tracked construction vehicles will be restored to existing
conditions.
A hazardous material building assessment was conducted by Tighe & Bond in March
2020 for the modular office building. Sampled materials (e.g., shingle, caulking,
insulation, wallboard, flooring, tile, adhesive) were negative for asbestos and as such, no
special management will be required. Universal waste items, such as mercury containing
light bulbs, batteries, light fixtures, fire extinguisher, heat/air conditioning units, etc. will
be removed by hand prior to demo activities.
The existing wooden sheds will be dismantled and removed. In addition, the metal
Conex box will be removed.
Utility Disconnection
Utilities, including water, sewer, gas, electric, and telecommunications, have been or will
be disconnected. The water service was terminated within the LNG Facility but the
terminus of the existing water line at the office building will be cut and capped flush to
grade. The sewer service will be terminated and capped at the existing belowground
sewer ejection pump housed within a 4’x4’x3’ wooden box located at the northwest
corner of the building. The wooden box will be removed and following the sewer cap,
the area will be filled with crushed stone to grade. Gas service will be terminated west of
the building within the LNG facility and will include a temporary excavation to access
and terminate the service. Excavated material will be replaced and surface stabilized
with asphalt to restore ground conditions. Overhead electric lines will be terminated on
the west side of the building and existing PVC surficial conduits extending from the
office building to the storage yard will be removed. Finally, telecommunication lines,
Request for Determination of Applicability National Grid-Commercial Point
220 Victory Road
Boston, Massachusetts
Page 4 of 5
PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
located within belowground conduits and overhead attached to utility poles, will be
terminated. Access to belowground fibers will be made from existing manholes such that
no ground disturbing activities will be required.
Miscellaneous
Miscellaneous items will be removed from the site. Dilapidated chain link fence
segments and posts located within a vegetated area will be removed. As needed, holes
resulting from removal of fence posts will be leveled and area seeded. Concrete blocks
and other items will be removed. Finally, the area will be hand-cleaned of surficial
debris.
The southeast corner of the modular office building is located within the 100-foot Buffer
Zone while the staging area is located, in part, within the previously developed/disturbed
100-foot Buffer Zone, 25-foot Waterfront Area, and Land Subject to Coastal Storm
Flowage. Once activities are complete, pre-existing conditions (i.e., vegetation,
pavement, gravel, elevation and grades, etc.) will be restored and the site will be
stabilized. Following seeding of disturbed areas, straw mulch will be applied to conserve
moisture and minimize erosion.
Construction is targeted to start this August following procurement of all permits.
4. Mitigation Measures
The Applicant intends to implement erosion controls during construction activities, in
accordance with National Grid’s Environmental Guidance Document (EG303), to
mitigate for any potential impacts to Wetland Resource Areas during construction.
National Grid’s EG303 provides specifications on environmental procedures and best
management practices (BMPs) to be followed by National Grid personnel, consultants,
and contractors. A description of these mitigating measures is provided below.
4.1 Erosion and Sedimentation Control
The Applicant proposes to implement an erosion control program to protect the adjacent
Neponset River from sedimentation during construction activities. The plan for the
control of potential impacts to the adjacent Wetland Resource Area will be comprised of
erosion control barriers (e.g., silt soxx located on the eastern perimeter of the gravel
Request for Determination of Applicability National Grid-Commercial Point
220 Victory Road
Boston, Massachusetts
Page 5 of 5
PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH
parking area, Appendix D) and best management practices (e.g., site housekeeping).
Construction material storage and construction vehicles/activity will be confined to
within paved or gravel areas. All erosion control barriers will remain in place until
disturbed areas are stabilized by vegetation, gravel, and/or pavement. Finally, if required,
vehicle refueling will be located beyond the 100-foot Buffer Zone. As a result of these
construction level BMPs, the Neponset River and associated Coastal Beach/Coastal Bank
will be protected.
5. Summary
On behalf of the Applicant, Boston Gas Company d/b/a National Grid, LEC
Environmental Consultants, Inc. is filing this Request for Determination of Applicability
with the Boston Conservation Commission to decommission the former Operations and
Service Center at the Commercial Point Facility in Boston, Massachusetts. The project
will occur, in part, within the previously developed/disturbed 100-foot Buffer Zone and
25-foot Waterfront Area to Coastal Beach/Coastal Bank, and Land Subject to Coastal
Storm Flowage (Zone VE) associated with the Neponset River. In an effort to mitigate
for the proposed construction related activities, erosion control measures and best
management practices will be followed to protect adjacent Wetland Resource Areas.
The Applicant respectfully requests that the Commission issue a negative Determination
of Applicability allowing the work to proceed as described.
Appendix A
DEP WPA Form 1-Request for Determination of Applicability
Affidavit of Service
Abutter Letter
Abutter Notification
Abutters List
wpaform1.doc
Page 1 of 4
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 1- Request for Determination of Applicability Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 City of Boston Wetlands Protection and Climate Adaptation Ordinance
Boston City/Town
A. General Information
Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use the return key.
1. Applicant:
Boston Gas Company Name
[email protected] E-Mail Address
19 Phillips Road Mailing Address
Hanover City/Town
MA State
02339 Zip Code
617-908-8881 Phone Number
Fax Number (if applicable)
2. Representative (if any):
LEC Environmental Consultants, Inc. Firm
Andrea Kendall Contact Name
[email protected] E-Mail Address
100 Grove Street, Suite 302 Mailing Address
Worcester City/Town
MA State
01605 Zip Code
508-753-3077 Phone Number
508-753-3177 Fax Number (if applicable)
B. Determinations 1. I request the Boston
Conservation Commission make the following determination(s). Check any that apply:
a. whether the area depicted on plan(s) and/or map(s) referenced below is an area subject to
jurisdiction of the Wetlands Protection Act.
b. whether the boundaries of resource area(s) depicted on plan(s) and/or map(s) referenced below are accurately delineated.
c. whether the work depicted on plan(s) referenced below is subject to the Wetlands Protection Act.
d. whether the area and/or work depicted on plan(s) referenced below is subject to the jurisdiction
of any municipal wetlands ordinance or bylaw of:
Boston Name of Municipality
e. whether the following scope of alternatives is adequate for work in the Riverfront Area as depicted on referenced plan(s).
wpaform1.doc
Page 2 of 4
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 1- Request for Determination of Applicability Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 City of Boston Wetlands Protection and Climate Adaptation Ordinance
Boston City/Town
C. Project Description 1. a. Project Location (use maps and plans to identify the location of the area subject to this request):
220 Victory Road Street Address
Boston City/Town
Parcel ID: 1600230000 Assessors Map/Plat Number
Parcel/Lot Number
b. Area Description (use additional paper, if necessary):
National Grid’s Commercial Point Facility is located within the southeastern portion of Dorchester on the north side of Victory Road. The Site is bound by Route 93 to the west, Morrissey Boulevard to the north, and the Neponset River to the east and south. The National Grid Commercial Point Facility contains photovoltaic solar arrays, operational buildings, a liquefied natural gas tank, and associated infrastructure. The Project Area is located within the southeast portion of the Facility, at the eastern terminus of Victory Road, and includes the former Operations and Service Center; a single-story modular office building, an outdoor gravel parking area, and a vehicle and equipment storage area. The Project Area is level, contains paved, gravel, and vegetated surfaces, and is bound by an 8-foot tall chain link security fence. In 2019, the Operations and Service Center was relocated to another National Grid facility. While various storage units, supplies, and vehicles were removed, miscellaneous features remain, including, for example, the modular office building, a 10-foot wide Conex storage box, wooden shed, and concrete blocks The project area is located within the previously disturbed/developed 100-foot Buffer Zone and 25-foot Waterfront Area to Coastal Beach/Coastal Bank and Land Subject to Coastal Storm Flowage (Zone VE) associated with the Neponset River.
c. Plan and/or Map Reference(s):
Site Demolition & Erosion Control Plan, National Grid, Commercial Point, 220 Victory Road, Boston, MA, prepared by Nitsch Engineering Title
June 24, 2020 Date
Title
Date
Title
Date
2. a. Work Description (use additional paper and/or provide plan(s) of work, if necessary):
National Grid proposes to decommission the Operations and Service Center Facility by removing all structures, storage units, and miscellaneous features (e.g., remnant fence posts), disconnecting utilities, and conducting a general surficial clean-up of debris from within the Project Area.
The Applicant proposes to implement an erosion control program to protect the adjacent Neponset River from sedimentation during demolition activities. The plan for the control of potential impacts to the adjacent Wetland Resource Area will be comprised of erosion control barriers (e.g., silt soxx located on the eastern perimeter of the gravel parking area) and best management practices (e.g., site housekeeping).
wpaform1.doc
Page 3 of 4
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 1- Request for Determination of Applicability Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 City of Boston Wetlands Protection and Climate Adaptation Ordinance
Boston City/Town
C. Project Description (cont.) b. Identify provisions of the Wetlands Protection Act or regulations which may exempt the applicant
from having to file a Notice of Intent for all or part of the described work (use additional paper, if necessary).
No exemption is noted, however, this filing is submitted in accordance with 310 CMR 10.02(2)(b)(3): Activities within the buffer zone (and riverfront area per 10.02(2)(a)(1)) which do not meet the requirements of 310 CMR 10.02(2)(b)(1). and 2. are subject to preconstruction review through the filing of a Determination of Applicability to clarify jurisdiction.
3. a. If this application is a Request for Determination of Scope of Alternatives for work in the Riverfront Area, indicate the one classification below that best describes the project.
Single family house on a lot recorded on or before 8/1/96 Single family house on a lot recorded after 8/1/96 Expansion of an existing structure on a lot recorded after 8/1/96 Project, other than a single family house or public project, where the applicant owned the lot
before 8/7/96 New agriculture or aquaculture project Public project where funds were appropriated prior to 8/7/96 Project on a lot shown on an approved, definitive subdivision plan where there is a recorded deed
restriction limiting total alteration of the Riverfront Area for the entire subdivision Residential subdivision; institutional, industrial, or commercial project Municipal project District, county, state, or federal government project Project required to evaluate off-site alternatives in more than one municipality in an
Environmental Impact Report under MEPA or in an alternatives analysis pursuant to an application for a 404 permit from the U.S. Army Corps of Engineers or 401 Water Quality Certification from the Department of Environmental Protection.
b. Provide evidence (e.g., record of date subdivision lot was recorded) supporting the classification above (use additional paper and/or attach appropriate documents, if necessary.)
wpaform1.doc
Page 4 of 4
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands WPA Form 1- Request for Determination of Applicability Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 City of Boston Wetlands Protection and Climate Adaptation Ordinance
Boston City/Town
D. Signatures and Submittal Requirements I hereby certify under the penalties of perjury that the foregoing Request for Determination of Applicability
and accompanying plans, documents, and supporting data are true and complete to the best of my knowledge. I further certify that the property owner, if different from the applicant, and the appropriate DEP Regional Office were sent a complete copy of this Request (including all appropriate documentation) simultaneously with the submittal of this Request to the Conservation Commission. Failure by the applicant to send copies in a timely manner may result in dismissal of the Request for Determination of Applicability.
Name and address of the property owner:
National Grid Energy Service Name
40 Sylvan Raod Mailing Address
Waltham City/Town
MA State
02451 Zip Code
Signatures: I also understand that notification of this Request will be placed in a local newspaper at my expense in accordance with Section 10.05(3)(b)(1) of the Wetlands Protection Act regulations.
Signature of Applicant Deborah Blanch, Boston Gas Company
June 23, 2020 Date
Signature of Representative (if any) Andrea Kendall, LEC Environmental
June 23, 2020 Date
Consultants, Inc.
AFFIDAVIT OF SERVICE
Under the Massachusetts Wetlands Protection Act
and Boston Wetlands Ordinance, City of Boston Code, Ordinances, Chapter 7-1.4
I, Sharon A. Sullivan, on behalf of Boston Gas Company d/b/a National Grid, hereby certify
under the pains and penalties of perjury that on June 24, 2020 I gave notification to abutters in
compliance with the second paragraph of Massachusetts General Laws Chapter 131, Section 40
and 310 CMR 10.05 (4) (a) and Boston Wetlands Ordinance, City of Boston Code, Ordinances,
Chapter 7-1.4 in connection with the following matter:
A Request for Determination of Applicability filed under the Massachusetts
Wetlands Protection Act and the City of Boston Wetlands Ordinance by LEC
Environmental Consultants, Inc. on behalf of the Applicant, Boston Gas Company
d/b/a National Grid, with the City of Boston Conservation Commission on June
24, 2020 for property located at 220 Victory Road (Assessor’s Parcel ID:
160023000) in Boston, Massachusetts.
The form of notification, and a list of the abutters to whom it was given and their addresses, are
attached to this Affidavit of Service.
_________________________________________ 6/24/2020
Sharon A. Sullivan Date
Permitting Technician
June 24, 2020
CERTIFICATE OF MAILING
«Name»
«Address»
«City», «State» «Zip»
Re: Notice of Intent Application [LEC File #: PALInc\15.153.04]
220 Victory Road
Assessor’s Parcel ID: 1600230000
Boston, Massachusetts
Dear Abutter:
On behalf of the Applicant, Boston Gas Company d/b/a National Grid, LEC Environmental Consultants,
Inc. (LEC) has filed a Request for Determination of Applicability for work associated with the
decommissioning of the Operations and Service Center at National Grid’s Commercial Point facility
located at 220 Victory Road in the Dorchester neighborhood of Boston. This filing is being submitted
pursuant to the Massachusetts Wetlands Protection Act (M.G.L. Ch. 131, s. 40, as amended) and its
implementing Regulations (310 CMR 10.00), and the Boston Wetlands Ordinance, City of Boston Code,
Ordinances, Chapter 7-14.
The Request for Determination of Applicability and accompanying plans are available for review by the
public at the Boston Conservation Commission. The Public Hearing will be held at the Boston City Hall,
1 City Hall Square, Piemonte Room, 5th Floor on July 8, 2020 beginning at 6:00 p.m., in accordance with
the provisions of the Massachusetts Wetlands Protection Act (M.G.L. Ch. 131, s. 40, as amended) and its
implementing Regulations (310 CMR 10.00), and the Boston Wetlands Ordinance, City of Boston Code,
Ordinances, Chapter 7-14. Further information regarding this application will be published at least five
(5) days in advance in The Boston Herald. Notice of the Public Hearing will also be posted at the Boston
City Hall at least 48 hours in advance. Confirmation of hearing date, time and agenda may be found at
https://boston.gov/public-notices.
Due to Governor Baker’s Covid-19 State of Emergency and further direction from the CDC, the Governor
has suspended certain provisions of the Massachusetts Open Meeting Law. Please check the
City/Conservation Commission website for information relative to remote viewing and/or participation in
the public hearing process.
Please do not hesitate to review the materials and/or attend the public hearing should you have questions
or concerns about the proposed project.
Sincerely,
LEC Environmental Consultants, Inc.
Andrea Kendall
Senior Environmental Scientist
Notification to Abutters Under the
Massachusetts Wetlands Protection Act
and the
City of Boston Code, Ordinances, Chapter 7-1.4
In accordance with the second paragraph of Massachusetts General Laws Chapter 131, Section 40, and
City of Boston Code, Ordinances, Chapter 7-1.4, you are hereby notified of the following:
A. The name of the Applicant is Boston Gas Company d/b/a National Grid, New England South
Division, 100 East Ashland Street, Brockton, Massachusetts.
B. The Applicant has filed a Request for Determination of Applicability with the Conservation
Commission for the municipality of Boston, Massachusetts for work associated with the
decommissioning of the Operations and Service Center pursuant to the Massachusetts Wetlands
Protection Act (General Laws Chapter 131, Section 40) and the City of Boston Wetlands Protection
and Climate Change Adaptation Ordinance (Chapter 7-1).
C. The activity is proposed on a lot located at 220 Victory Road (Assessor’s Parcel ID: 1600230000),
Boston, Massachusetts.
D. Copies of the Request for Determination of Applicability may be examined by contacting the Boston
Conservation Commission at (617) 635-3850.
For more information, call: LEC Environmental Consultants, Inc. (the applicant’s representative) at
(781) 245-2500.
E. Copies of the Request for Determination of Applicability may be obtained from LEC Environmental
Consultants, Inc. (the applicant’s representative) by calling (781) 245-2500 between the hours of 8:00
a.m. and 5:00 p.m., Monday through Friday. A fee may be charged for each copy requested.
F. Information regarding the public hearing may be obtained from the Boston Conservation Commission
(the regulatory agency) by calling (617) 635-3850 or at https://boston.gov/public-notices.
NOTE: Notice of the Public Hearing, including its date, time, and place, will be published at least five (5)
days in advance in The Boston Herald.
NOTE: Notice of the public hearing will also be posted at the Boston City Hall not less than 48 hours in
advance.
NOTE: You also may contact the nearest Department of Environmental Protection Regional Office for
more information about this application or the Wetlands Protection Act. To contact DEP, call:
Northeast Region: 978-694-3200
650 700 WM T MORRISSEY BL
EXPRESSWAY MOTORS LLC
700 MORRISSEY BLVD
DORCHESTER, MA 02122
FREEPORT ST
COMMONWLTH OF MASS
FREEPORT
DORCHESTER, MA 02122
201 VICTORY RD
COMM OF MASS MDC
201 VICTORY RD
DORCHESTER, MA 02122
229 VICTORY RD
CITY OF BOSTON
229 VICTORY RD
DORCHESTER, MA 02122
235 VICTORY RD
OLD COLONY YACHT CLUB THE
235 VICTORY RD
DORCHESTER, MA 02122
VICTORY RD
COMM OF MASS DPW
VICTORY RD
DORCHESTER, MA 02122
FREEPORT ST
COMMWLTH OF MASS
FREEPORT
DORCHESTER, MA 02122
FREEPORT ST
COMMWLTH OF MASS
FREEPORT
DORCHESTER, MA 02122
Appendix B
Locus Maps & Site Photographs
Figure 1: USGS Topographic Map
Figure 2: MassGIS Orthophoto & NHESP Estimated Habitat Map
Figure 3: FEMA Flood Insurance Rate Map
Site Photographs
<Double-click here to enter title>
Figure 1: USGS Topographic Map220 Victory RoadDorchester, MA
May 19, 2020
±0 500 Feet
Environmental Consultants, Inc.
Wakefield, MA
781.245.2500
www.lecenvironmental.com
Office of Geographic and Environmental Information(MassGIS), Commonwealth of Massachusetts
Executive Office of Environmental Affairs
1:25,000 USGS Topographic Images - April 2001
<Double-click here to enter title>
Figure 2: MassGIS Orthophoto & NHESP Map220 Victory RoadDorchester, MA
May 19, 2020
VICTORY R
OAD
±0 200 Feet
NHESP Certified Vernal Pool
NHESP Potential Vernal Pool
NHESP Estimated Habitatsof Rare Wildlife (2017)
NHESP Priority Habitatsof Rare Species (2017)
k
k
Legend
Environmental Consultants, Inc.
Wakefield, MA
781.245.2500
www.lecenvironmental.com
Office of Geographic and Environmental Information
(MassGIS), Commonwealth of Massachusetts,
Executive Office of Environmental Affairs
MassGIS USGS Ortho Imagery (2019)
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
Views of modular office building (front) to be demolished on site and removed and adjacent gravel parking area to be used as staging area.
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
View of modular office building sitting on concrete cinder blocks (no foundation). Dense graded crushed stone will be placed within the footprint of the building to provide a stable
and uniform ground cover consistent with the adjacent gravel parking area.
Southerly view of modular office building (rear) to be demolished on site and removed.
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
Existing Conex metal storage container and miscellaneous items adjacent to modular office building to be removed and area cleaned of surficial debris.
View of wooden storage shed and miscellaneous items to be removed.
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
Views of housing containing belowground sewer injection pump. Sewer line to be cut and capped in this location. Housing (and above fencing) to be removed and
area filled with crushed stone up to ground surface.
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
Existing metal Conex storage container to be removed from within equipment and storage yard.
Overview former equipment and storage yard.
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
Views of PVC electric conduit to be removed. Electric service already terminated.
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
Views of miscellaneous items and debris to be removed from equipment and storage yard.
National Grid-Commercial Point 220 Victory Road
Boston, Massachusetts
Site Photographs
Views of concrete blocks and miscellaneous items and debris to be removed from equipment and storage yard. Fence posts (top) to be removed. Any disturbed
areas will be seeded.
Appendix C
Plans entitled:
Site Demolition & Erosion Control Plan, National Grid, Commercial Point, 220 Victory Road, Boston MA
prepared by Nitsch Engineering, Inc., dated June 24, 2020
VICTORY
ROAD
//
//
//
//
////
// // // // // //
//
SCALE:1" = 20'
20 10 0 20 40
FOR RDA PERMITTING ONLYNOT FOR CONSTRUCTION
NOTES
PREPARED FOR:
DRAFTED BY:
SCALE:
FILE:
NITSCH PROJECT #
DATE:
CHECKED BY:
PROJECT MANAGER:
SURVEYOR:
REV. COMMENTS
REVISIONS
DATE
8551.11
1"= 20'
JUNE 24, 2020
WRM
---
WRM
WRM
SITE DEMOLITION & EROSION CONTROL PLAN INATIONAL GRID, COMMERCIAL POINT
220 VICTORY ROAD, BOSTON, MASSACHUSETTS C-1SHEET: 1
OF 3 REV.
8551.11CLO.DWG
GENERAL NOTES:
ABBREVIATIONSPROPOSED LEGEND
//
//
//
//
//
//
//
SCALE:1" = 20'
20 10 0 20 40
PREPARED FOR:
DRAFTED BY:
SCALE:
FILE:
NITSCH PROJECT #
DATE:
CHECKED BY:
PROJECT MANAGER:
SURVEYOR:
REV. COMMENTS
REVISIONS
DATE
8551.11
1"= 20'
JUNE 24, 2020
WRM
---
WRM
WRM
SITE DEMOLITION & EROSION CONTROL PLAN IINATIONAL GRID, COMMERCIAL POINT
220 VICTORY ROAD, BOSTON, MASSACHUSETTS C-2SHEET: 2
OF 3 REV.
8551.11CLO.DWG
FOR RDA PERMITTING ONLYNOT FOR CONSTRUCTION
NOTES
CATCH BASIN W/ SILTATION SACKINLET PROTECTION
GRAVEL PARKING LOT DETAIL
··
COMPOST WATTLES - SLOPE PROTECTION DETAIL
SECTION PLAN
PREPARED FOR:
DRAFTED BY:
SCALE:
FILE:
NITSCH PROJECT #
DATE:
CHECKED BY:
PROJECT MANAGER:
SURVEYOR:
REV. COMMENTS
REVISIONS
DATE
2 Center Plaza, Suite 430Boston, MA 02108T: (617) 338-0063F: (617) 338-6472
Civil EngineeringLand SurveyingTransportation EngineeringStructural Engineering
PlanningGIS
Green Infrastructure
8551.11
AS NOTED
JUNE 24, 2020
WRM
---
WRM
WRM
EROSION CONTROL NOTES & DETAILSNATIONAL GRID, COMMERCIAL POINT
220 VICTORY ROAD, BOSTON, MASSACHUSETTS C-3SHEET: 3
OF 3 REV.
8551.11CDT.DWG
FOR RDA PERMITTING ONLYNOT FOR CONSTRUCTION
EROSION AND SEDIMENT CONTROL NOTES:
Appendix D
Silt Soxx
® ™
® ™
® SOXX™(12" TYPICAL)
™
® SOXX™ (12" TYPICAL)
ENVIRONMENTAL GUIDANCEDate
Doc. No. EG-303NE
08/08/12SUBJECT
Access, Maintenance and ConstructionBest Management Practices
ReferenceEP No. 3 - Natural ResourceProtection (Chapter 6)
BMP # 4SILT SOXX *
BMP DETAIL
BMP PICTURE
Page: 3-4 Rev. No. 0