77
Request for Tender Documents FOR SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF DWDM & NEXT GENERATION SDH (STM-64) EQUIPMENT THROUGHOUT NTC ON TURNKEY BASIS Tender Notice # NTC (Proc-Dte) /ADV- /09-10 Author: Chief Technology Officer HEADQUARTERS F-5/1 ISLAMABAD

Request For Proposal - Longhaul Backbone Project

Embed Size (px)

Citation preview

Request for Tender Documents

FOR

SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF DWDM & NEXT GENERATION SDH (STM-64) EQUIPMENT

THROUGHOUT NTC ON TURNKEY BASIS

Tender Notice # NTC (Proc-Dte) /ADV- /09-10

Author:Chief Technology Officer

HEADQUARTERS F-5/1 ISLAMABAD

PREFACE

Infrastructure represents “wheels” if not “engine” to economic activity. Since the major share of NTC’s revenue is associated with it, all investment decisions, allocations of funds and their efficient use – for the up gradation and expansion of infrastructure – assume great significance. Cumulative impact of deregulated telecom environment, privatization of PTCL, entrance of new market players, and government telecom policy, is a precursor of highly inadequate infrastructure on a national level. NTC’s predilection to make up for the infrastructure deficiencies is therefore a strategic compulsion.

During the previous years, NTC has given a good account of itself in pursuing infrastructure/ network expansion. Consequently – loading of Fiber Optic Cable, on main, alternate, spur – junction routes, installation and commissioning of NGN, IP core routers, Green Exchanges, GPON, data networking, execution of ‘Project Horizon’ etc have been completed. NTC is providing IT & Telecom services to the Government of Pakistan up to tehsil level.

NTC’s long haul digital media on main and alternate routes, runs parallel to PTCL, and is providing ‘stream level connectivity throughout the country. NTC has its independent network of local and transit exchanges. NTC is fully established to meet the requirement of GoP/ Defence through its network/ infrastructure.

Available capacity on the existing optical fiber backbone has been utilized to the optimum. The project is therefore directly linked with the capacity upgrade of the existing optical fiber backbone. Up-gradation of the existing countrywide SDH backbone (STM-4) to DWDM network is to meet the future bandwidth requirement of the government and semi government sector.

B r i g ® B a b a r A z i z B e gC h a i r m a n N T C

2

C O N T E N T S

PART ONECHAPTER 1 Infrastructure Up-gradation

1.1 Existing OFS Network of NTC ……………………………….……..………………………………....

1.2 NTC Existing Network diagram ……………………………….………………………………………..

1.3 Link Power Budget ……………………………………………………………………….

1.4 Up-gradation of Existing Infrastructure/Backbone…………………………………………….....

1.5 Design Parameters for DWDM / SDH System ………………………………………………….……………………

1.6 DWDM/SDH Network Plan ……………………………………………………………………......

1.7 DWDM/SDH Equipment Details ………………………………….……………………………………

1.8 Bandwidth Demand Matrix ( NTC ) ……………………………………….……………………………..

1.9 Implementation Phases of DWDM / SDH Platform …………………………………………………….………………

CHAPTER 2 Instructions to the bidders

2.1 General ……………………………………………………………………………..

2.2 Eligible Bidders ……………………………………………………………………………….

2.3 Cost of Tendering ………………………………………………………………………………

2.4 Clarification of Documents …………………………………………………….….…………………….

2.5 Amendment of Tender Documents ……………………………………………………………………………..

2.6 Country of Origin …………………………………………………………………………….

2.7 Preparation of Bid Documents …………………………………………………………………..………..

2.8 Price ……………………………………………………………………………

2.9 Tender Security/Earnest Money ……………………………………………………………………………

2.10 Validity of Bids ……………………………………………….………………………….

2.11 Deadline for Submission of Bids ……………………………………………………………..…………..

2.12 Modification & Withdrawal of Bids ……………………………………………………………………………

3

2.13 Opening of Bids ……………………………………………………………………………..

2.14 Clarification/Correction of Bids ………………………………………………………..…….…………….

2.15 Responsiveness of Bids ……………………………………………….………………..………….

2.16 Pre-Liminary Examination .……………………………………………………………………..…….

2.17 Evaluation of Bids …………………………………………………………………………..

2.18 Evaluation Criteria/Method …………………………………………………………………………..

2.19 Compliance Certificate ……………………………………………………………………………

2.20 Award Criteria & NTC’s Right ………………………………………………………………………..…

2.21 Pre-Bid Conference ………………………………………………………………………….

2.22 Clause By Clause Compliance Statement ……………………………………………………..…………….……

2.23 Engineering Survey & System Design …………………………………………………………………………..

CHAPTER 3 General Terms and Conditions of the contract

3.1 Performance Security/Bank Guarantee …………………………………………………….….….……………..

3.2 NTC’s Responsibilities ………………………………………………..…………..…….………

3.3 Contractor’s Responsibilities.................................................................................................................

3.4 Contractor’s Representativel …………………………………..…………………………………..…

3.5 workmanship, materials and equipment …………………………………………………………………………...

3.6 Insurance …………………………….……………………….…………………..…

3.7 Transportation/Packing ……………………………………………………………………….……

3.8 Time for completion …………………………………………………………………..…………

3.9 Warranty/Services ………………………………………………………………………….……

3.10 Provisional Acceptance Certificate ………………………………………………………..……………………

3.11 Terms of Payment ……………………….……………………………………………….……

3.12 Final Acceptance Certificate ……………………………………………………………….……………

3.13 Default by Contractor …………………………….…………………………………….………

3.14 Contractor’s Negligence …………………………………..………………………….……………

3.15 Progress Review Meeting ……………………….………………………………………..…………

3.16 Inspection & Tests ………………………………………………………………………..……

4

3.17 Force Majeure ………………………………………………………………………..……

3.18 Liquidated Damages …………………………..…………………………………………………

3.19 Termination for Insolvency ……………………………………………..………………………………

3.20 Termination for Convenience ……………………………….……………………………………………

3.21 Compliance with Regulations …………………………………………………..…………………………

3.22 Confidentiality ……………………………………………………………..………………

3.23 Liability for Damage ……………………………….………..………………..…….……………

3.24 Settlement of Dispute …………………..………………………………………….………………

5

PART TWO

CHAPTER 4 Testing & Commissioning

4.1 Acceptance Testing…………………………………………………………………………………..

4.2 Testing Requirements…………………………………………………………………………………….

4.3 Pre-Shipment Inspection & Testing…………………………………………………………………………………….

4.4 Local Acceptance Testing…………………………………………………………………………………….

CHAPTER 5 Training

5.1 Objective ………………………………………………………………...5.2 Types of Trainings

……………………………………………………………………5.3 Training Schedules & Courses

…………………………………………………………………………………..5.4 Training Cost

…………………………………………………………………………………..5.5 Other Requirements

……………………………………………………………………………………

CHAPTER 6 Spares

6.1 Spare Parts ………………………………………………………………………........

6.2 List of Spares …………………………………………………………………………..

CHAPTER 7 Miscellaneous Technical Requirements

7.1 Environmental Requirements ……………………………………………………………………………

7.2 Earthing Requirements …………………………………..………………………………..………

7.3 Mechanical requirements…………………………………..……………………………………...

7.4 Labeling requirements…………………………………………………………..………………

7.5 Electrostatic discharge requirements ………………………………………………………………………….

7.6 Susceptibility to Electromagnetic radiation requirements ………………………………………………………………………….

7.7 Surge protection requirements ………………………………………………………………………….

7.8 Technical requirements

6

………………………………………………………………………….7.9 Reliability and Availability requirements

………………………………………………………………………….7.10 Test and measuring facilities requirements

………………………………………………………………………….7.11 Alarm requirements

…………………………………………………………………………..7.12 Protection requirements against accidental conditions

………………………………………………………………………….7.13 Power supply requirements

…………………………………………………………………………..7.14 Acoustic noise and Electromagnetic Radiation requirements

…………………………………………………………………………

PART THREECHAPTER 8 Glossary

8.1 Glossaries ………………………………………………………………………….

8.2 Frequently Used Terms ………….………………………………………………………………..

CHAPTER 9 Conclusions

Annexures:

1. Annex-A Existing NTC SDH Network Diagram2. Annex-B NTC Link Power Budget3. Annex-C Proposed DWDM/SDH Network Diagram4. Annex-D BOQ5. Annex-E NTC Bandwidth Matrix (Existing & Demand)6. Annex-F Format of Bank Guarantee for Earnest Money7. Annex-G Clause by Clause Compliance Certificate8. Annex-H Format of Bank Guarantee for Performance Security9. Annex-I Technical Specifications of DWDM System10. Annex-J Technical Specifications of SDH (STM-64) System11. Annex-K Technical Specifications of Optical Power Meter12. Annex-L Technical Specifications of Optical Laser Source13. Annex-M Technical Specifications of Visual Fault Locator14. Annex-N Technical Specifications of Fusion Splicer15. Annex-O Technical Specifications of OTDR

7

PART ONE

8

INFRASTRUCTURE UP-GRADATION

1.1 Existing OFS Network of NTCNTC’s Optical Fiber pair on main alternate and spur routes has been equipped with 622 Mbps SDH system (Siemens SMA1/4) on the following alignments:

1.1.1 Main Route (on eastern bank of river Indus)

Karachi – Hyderabad – Sukkur – Multan – Rawalpindi – Peshawar.

1.1.2 Alternate Route (on western bank of river Indus)

Karachi – Thatta – Dadu – Larkana – Shikarpur – D.G. Khan – Bannu - Peshawar.

1.1.3 Spur Routes

Gujranwala – Daska – Sialkot / Sargodha – Joharabad-KCP / Sargodha-Iqbal Town/Taxila – Haripur – Abbottabad / Nowshera – Mardan / Kamra – Attock / Sahiwal – Arifwala .

1.1.4 Junction Routes

Islamabad Junction network, Lahore Junction network, Karachi Junction network.

1.1.5 Both main and alternate routes start from Peshawar and end up in Karachi. Main and alternate route / cables join (on one system) at Peshawar Cantt and Pak Capital exchanges – forming three major self healing ring configuration and four sub ring configuration within above rings, thus provisioning of interruption free telecom services are ensured. Average distance between regeneration sites is 50 km. Number of ‘regeneration sites’ and ‘add/drop multiplexer sites’ are ‘40’ and ‘58’, respectively.

1.1.6 Spur routes are basically extensions of the Main and Alternate route cables. For example, Taxila to Abbottabad is a spur route covering Haripur, Havelian and Abbottabad. Taxila is a point where main route cable has been extended towards Abbottabad. SDH system at Taxila is common for main and spur route.

1.1.7 NTC has its own Optical Junction networks in three main cities of Pakistan, i.e. in Islamabad, Lahore and Karachi. These networks are in ring configuration with self healing provision, currently these are working on SDH STM-4 level in Lahore & Karachi where as in Islamabad the junction network is SDH STM-16 based.

1.1.8 In addition, Coastal communication link between Jiwani – Karachi has been recently established. This transmission link has been equipped with STM-16 (2.5 Gbit) system and will be connected with NTC SDH backbone for the provision of connectivity with dry ports, air ports and business centers of the country. This expansion will facilitate mobility / exploitation of resources and would enhance business opportunities.

9

1CHAPTER

1.2 NTC Existing Network Diagram

Existing network diagram is attached as Annex-A of tender documents.

1.3 Link power Budget

Link power budget is attached as Annex-B of tender documents.

1.4 Up gradation of Existing Infrastructure/ Backbone

Information/ data compiled in the following pages will assist the vendors in the process of his decision making. Technical requirements / specifications of the project are outlined under the following headings;

1.4.1 Design parameters – DWDM/SDH System

1.4.2 DWDM/SDH Network Plan

1.4.3 DWDM/SDH Equipment Details/ BOQs

1.4.4 Bandwidth Demand Matrix ( NTC )

1.4.5 Power Budget Analysis of Long Haul network (worked out in 2008)

1.4.6 Technical Requirements / Specifications.

1.5 Design Parameters of optical fiber cable for DWDM/SDH System

1.5.1 Fiber Loss ≤ 0.25 dB / Km

1.5.2 Splicing Loss ≤ 0.05 dB / Km

1.5.3 Connector Loss ≤ 0.5 dB / Connector

1.5.4 Section Loss Margin ≥ 3.5 dB / Span

1.5.5 Ageing Factor ≥ 0.035 dB / Km

1.5.6 Chromatic Dispersion (CD) = 20 ps / nm. Km

1.5.7 Polarization Mode Dispersion (PMD) = 0.5 - 1 ps / Km

10

1.6 DWDM/SDH Network Plan

DWDM/SDH Network Plan is attached as Annex-C of tender documents.

1.7 DWDM/SDH Equipment Details

DWDM/SDH Equipment Details along with complete BOQ is attached as Annex-D of tender documents.

1.8 Bandwidth Demand Matrix (NTC)

Bandwidth Demand Matrix (NTC) is attached as Annex-E of tender documents.

1.9 Implementation Phases of DWDM/SDH Platform

1.9.1 Phase-I (Ring 1)

1.9.2 Phase-II (Ring 2)

1.9.3 Phase-III (Ring 3)

-- End of Chapter One –

11

INSTRUCTIONS TO THE BIDDERS

2.1 GENERAL2.1.1 INTRODUCTION

National Telecommunication Corporation was established in 1996 under Telecommunication Re-Organization Act. NTC has a definite mandate to provide basic telecommunication services to its designated customers, which include Federal and Provincial Governments, their departments, autonomous organizations and defense services throughout the country. In addition NTC commissioned a countrywide Multi-Services data network based on state of the art technologies of ATM & PoS (Packet over SONET), one each at Islamabad, Lahore, Peshawar, Karachi and Faisalabad from the primary core network for Multi-Services.

2.1.2 SCOPE OF WORK

2.1.2.1 Supply, Installation, testing, Commissioning & Traffic shifting from old system (SDH STM-4) to new system of DWDM/SDH equipment throughout NTC on turnkey basis at given sites as per plan at annex-C, D & E and as per technical specifications/requirements.

2.1.2.2 For the execution of the work the bidder shall undertake to supply all hardware and software including equipment, installation material, PCM cables/power cables, patching cords & accessories etc, as detailed in annexes which shall be necessary for a complete functioning of an entity. Any other fittings or accessories under scope of work which may not have specifically been mentioned in the BOQ, but which are necessary to meet the Specifications , site requirements ,connectivity and for fully functioning of the system/links shall be provided by the bidder without any extra charges to NTC. These responsibilities may include but are not limited to following items required for the project.

2.1.2.2.1 Hardware2.1.2.2.2 Software2.1.2.2.3 Electrical Power cabling (both AC & DC) along with Circuit

breakers at AC (single/three phase) mains side2.1.2.2.4 Installation materials/accessories (i.e PCM/co-axial cables,

DDF racks with tag blocks, optical patch cords etc.)2.1.2.2.5 Services (Engineering, Installation, Integration, interfacing,

network connectivity, testing, commissioning & traffic/load shifting, Support, etc.)

2.1.2.2.6 Training 2.1.2.2.7 Documentation (Technical, Operation & Maintenance,

troubleshooting)12

2CHAPTER

2.1.3 SYSTEM RELIABILITY

2.1.3.1 The bidder shall furnish reliability calculations of the system depending upon the failure rates of various components, using backup and duplication philosophy and the degree of perfection of the software.

2.1.3.2 Based on the bidder’s previous experience, the following items shall be indicated:

2.1.3.2.1 Complete system failure (To be indicated on one year basis)2.1.3.2.2 Total hardware failure rate (To be indicated on one year basis)2.1.3.2.4 Mean active repair time (To be indicated in hours)2.1.3.2.5 Mean time between failures (To be indicated on one year basis)

2.1.4 MAINTENANCE SUPPORT AND AVAILABILITY OF SPARES

2.1.4.1 The bidder shall recommend the type of routine corrective & preventive maintenance tests and their duration, giving the test set ups and their procedures.

2.1.4.2 The bidder will clearly indicate the point of presence in Pakistan for maintenance purpose and will mention the cost of repair for each level of maintenance for hardware and software separately.

2.1.4.3 The bidder will specify briefly first, second and third line of maintenance support along with down time.

2.1.4.4 The successful bidder will maintain sufficient quantity of spares at the bidder's point of presence in Pakistan during and after the warranty period for at least 10 years. In case of failure of a component or whole system the equipment will be replaced within 24 hrs with a new one with out any extra cost. At the time of bid submission the bidder shall also furnish an affidavit on Rs 100/- legal paper ensuring the maintainability & availability of all kind of spares for at least 10 x years at the price mentioned in BOQ of RFT.

2.1.4.5 The bidder shall ensure that the production line is in operations for the quoted model of DWDM & SDH (STM-64) for ten years.

2.1.4.6 The backup support for up-gradation from 2x s(Two Lambdas) toג16x s(Sixteen Lambdas) is mandatory and bidder shall ensure thatגthe up-gradation shall be possible any time during ten years including Add & Drop at required site(s).

2.1.4.7 The bidder shall furnish the following:

2.1.4.7.1 Complete list of spares with unit prices separately for each of their equipment along with exact type and nomenclature.

2.1.4.7.2 List of recommended spares with quantities and item wise unit price separately for each equipment.

13

2.1.4.7.3 Per year Maintenance Cost for maintenance of complete network/system for ten years after completion of warranty period. This will include provision of spares, services etc.

2.1.5 LOCAL TRAINING:

The bidders will provide local training of 40 x NTC personnel for 06 weeks for configuration, troubleshooting and maintenance at Islamabad free of cost. Successful bidder will arrange tutor, training venue, training manuals & all allied accessories etc at its own cost. Project Director in consultation with Director (Procurement) will nominate the NTC personnel for training as per advice of Chief Technology Officer NTC.

2.1.6 FOREIGN TRAINING:

The bidders will provide foreign training to 15 x NTC personnel for 6x weeks for configuration, troubleshooting and maintenance of equipment free of cost. Successful bidder will arrange tutor, training venue, training manuals and all allied accessories etc at its own cost. Project Director in consultation with Director (Procurement) will nominate the NTC personnel for training as per advice of Chief Technology Officer NTC.

2.1.7 PRE-SHIPMENT VISIT

The Bidder will arrange pre-shipment visit of 04 NTC personnel for 01 week at its own expenses. All the testing/inspection tools, test equipment & preparation of test bed shall be arranged by the bidder. Boarding/lodging, air fare, subsistence allowance etc shall be arranged by successful bidder at its own expenses.

2.2 ELIGIBLE BIDDERS

Tendering is open to all suppliers who meet following criteria:

2.2.1 Have minimum 05 years relevant experience in supply, installation, testing and commissioning of such equipment and must have installed at least 03 DWDM/SDH (STM-64) long haul networks/systems throughout world. Bidders shall provide the record of their previous installation along with the project worth & contact information of the concerned person for verifications. NTC may ask for the inspection / demonstration of already installed equipment by the bidder during the bid evaluation process.

2.2.2 Registered with income tax and sales tax departments of Pakistan. Bidder shall also furnish the incorporation certificate from SECP.

2.2.3 Never been black listed from any government organization and will submit certificate to this effect in the form of affidavit on Rs.100/- legal paper.

14

2.2.4 Duly authorized from the principal firm (original equipment manufacturer/vendor) & will submit the authorization certificate issued by the principal firm at the time of bid submission.

2.2.5 Equipments or any of its unit/parts quoted by bidders must not be manufactured in Israel or India. Furthermore the Bidder/Principle supplier must not have any linkage with Israel or India regarding ownership, sponsoring, financing & manufacturing. (Bidders shall submit an affidavit on Rs.100/- legal paper with this respect).

Note: Bidder must submit documentary proof against all eligibly criteria mentioned in para.2.2.1 to 2.2.5. Fulfillment of all conditions of “Eligible criteria” is mandatory for a successful bidder along with other mandatory conditions set in tender documents.

2.3 COST OF TENDERING

The bidder shall bear all costs associated with the preparation and submission of its bid and the NTC will in no case be responsible or liable for these costs, regardless of the conduct or outcome of the tendering process.

2.4 CLARIFICATIONS OF TENDER DOCUMENTS

A prospective bidder requiring any clarification(s) regarding any matter (i.e. technical, financial) may notify to Project Manager (DWDM) NTC HQs and DE Procurement NTC HQs. The concerned NTC officer will respond to any query for clarification, which receives well before (approximate 05 working days or more) the deadline for the submission of bids.

Contact Information:• Project Manager (DWDM) NTC HQs

Email: [email protected]

• DE Procurement NTC HQs Email: [email protected]

2.5 AMENDMENT OF TENDER DOCUMENTS

2.5.1 At any time prior to the deadline for submission of bids, the NTC may, for any reason, whether at his own initiative or in response to a clarification requested by a prospective bidder, modify the tender documents by issuing addendum/amendment.

15

2.5.2 Any addendum thus issued shall be part of the tender documents. To afford bidders reasonable time in which to take an addendum into account in preparing their bids & depending on the nature of amendment, NTC may at its discretion extend the deadline for submission of bids.

2.6 COUNTRY OF ORIGIN

The bidder shall clearly mention the country of origin of the offered equipment. Equipment or any unit/part offered by the bidder must not be manufactured in India & Israel.

2.7 PREPARATION OF BID DOCUMENTS

2.7.1 The bid should be prepared considering Single Stage Two Envelope procedures. The envelope shall be clearly marked as “FINANCIAL PROPOSAL” and “TECHNICAL PROPOSAL” in bold and legible letters to avoid confusion.

2.7.2 Bid documents and all correspondence shall be in English language.2.7.3 The bid should have a covering letter on printed letter pad of the firm. The

original and all copies of the bid shall be typed or written in indelible ink and shall be signed by the bidder or a person or persons duly authorized from their company/firm. All pages of the bid, except for un-amended printed literature shall be initialed by the person or persons signing the bid. The bid shall contain no inter lineation, erasures or over writing at any page except as necessary to correct errors made by the bidder in which case such corrections shall be initialed by the person or persons signing the bid

2.7.4 The bidder shall prepare three copies of the bid, clearly marking one of them as “ORIGINAL BID” and the remaining for marked “COPY” duly numbered besides soft copy of technical proposal in the shape of CD. In the event of any discrepancy between them, the original shall govern.

2.8 PRICE

2.8.1 Prices should be quoted in Pak Rupees on FOR at destination sites basis.

2.8.2 The price quoted should be firm, final, and clearly written/typed without any ambiguity.

2.8.3 The price should include all the government taxes (including GST if applicable), duties, freight charges, delivery and installation charges etc.

2.8.4 The rates / prices shall be entered against each item in the Bill of Quantity (BOQ). Any item against which no rate or price is entered and left blank by the bidder shall be deemed covered by the rates / prices for other items in the BOQ.

2.8.5 The bidder shall be deemed to have obtained all information as to all the requirements thereto which may affect the bid price.

16

2.9 TENDER SECURITY / EARNEST MONEY

2.9.1 The bidder shall furnish a tender security/ earnest money equivalent to 2% of the total value of bid in the form of Deposit at Call, Bank Draft or a Bank guarantee issued by a scheduled bank of Pakistan / First class foreign bank in favor of Chairman NTC valid for a period of 60 days beyond the bid validity date as per annexure F.

2.9.2 Any bid not accompanied by an acceptable tender security shall be rejected by the NTC as non-responsive.

2.9.3 The tender securities / earnest money of the unsuccessful bidders will be returned upon award of contract to the successful bidder or on expiry of validity of tender security whichever is earlier.

2.9.4 The tender security of the successful bidder will be returned when the bidder has furnished the required Performance Security and signed contract agreement.

2.9.5 The tender security may be forfeited:2.9.5.1 If a bidder withdraws his bid during the period of bid validity.2.9.5.2 In the case of successful bidder, if he fails to oblige any of the

Following: 2.9.5.2.1 Submission of performance bond 2.9.5.2.2 Signing of contract 2.9.5.2.3 Non-compliance of contractual scope of work

2.10 VALIDITY OF BIDS

Bid shall remain valid for a period of 120 days from the date of tender opening.

2.11 DEADLINE FOR SUBMISSION OF BID

2.11.1 The bid shall be delivered in person or sent by the registered mail which should reach the NTC HQ, F-5/1 Islamabad on or before 1130 hours on

,2009.

2.11.2 Sealed bid should be put in the tender box placed at the reception gate of NTC HQ on or before the prescribed time on given date.

2.11.3 Bid should be submitted in sealed envelope having necessary information regarding tender notice and warning message “DO NOT OPEN BEFORE 1130 hours on , 2009”.

2.11.4 No open, e-mailed or faxed bid will be accepted.

2.11.5 Any bid received by the NTC concerned officer after the date and time of tender opening will not be accepted.

17

2.12 MODIFICATION & WITHDRAWAL OF BID

2.12.1. Any bidder may modify or withdraw his bid after bid submission provided that written notice of the modification or with-drawl is received by the concerned officer prior to the deadline for submission of bids.

2.12.2 No bid may be modified or withdrawn by a bidder after the deadline for submission of bids.

2.13 OPENING OF BID

2.13.1 The NTC tender committee will open the bids on , 2009 at 1200 hours in the presence of bidders representatives who desire to attend, at NTC HQ F-5/1 Islamabad.

2.13.2 The bidder’s name, bid prices, any discount, the presence or absence of tender security, and such other details as the committee at its discretion may consider appropriate, will be announced at the tender opening.

2.13.3 The tender committee will resolve any issue raised by the bidders, on the spot.

2.13.4 The tender committee reserves the right to reject any one or all bids without assigning any reason.

2.14 CLARIFICATIONS / CORRECTIONS OF BID

2.14.1 To assist in the examination, evaluation and comparison of the bids the committee may ask the bidder for a clarification of its bid.

2.14.2 Arithmetical errors will be rectified on the following basis:

2.14.2.1 If there is a discrepancy between unit price and total price that is obtained by multiplying the unit price and quantity, the unit price shall prevail and total price shall be corrected. If there is a discrepancy between the words and figures the amount in words shall prevail. If there is a mistake in addition / totaling that can be corrected & same may be taken as final.

2.14.2.2 If the bidder does not accept the corrected amount of bid, his bid will be rejected and his tender security forfeited.

2.15 RESPONSIVENESS OF BIDS

2.15.1 The valid bid security is submitted2.15.2 The bid is valid till required period2.15.3 The bid prices are firm during its validity and inclusive of all taxes, duties

etc18

2.15.4 Completion period offered is within specified limits2.15.5 The bidder is eligible to tender and possesses the requisite experience2.15.6 The bid does not deviate from basic technical requirements2.15.7 The bid is generally in order etc.2.15.8 The bidder complies all the terms & conditions of RFT by furnishing compliance certificate.2.15.8 All the bid documents have been properly signed & any computational

error has been clarified/corrected.

2.16 PRELIMINARY EXAMINATION

2.161 Prior to the detailed evaluation, NTC will determine the responsiveness of each bid to the bidding documents as per clause # 2.15. A responsive bid is one which conforms to the terms and conditions of the bidding documents without material deviations. NTC’s determination of a bid’s responsiveness is to be based on the contents of the bid itself.

2.16.2 A bid determined as non-responsive will be rejected by NTC and may not subsequently be made responsive by the bidder correction of the non-conformity.

2.16.3 NTC may waive any minor informality or non-conformity or deviation, provided such waiver does not prejudice or affect the relative ranking of any bidder.

2.17 EVALUATION OF BIDS

2.17.1 Technical evaluationIt will be examined in detail whether the system/works offered by the bidder complies with the technical specifications of the tender documents. For this purpose, the bidder’s data submitted with the bid will be compared with the technical features/criteria of systems/works detailed in the technical specifications

2.17.2 Commercial Evaluation: It will be examined in detail whether the bids comply with the commercial / contractual conditions of the tender documents. It is expected that no major deviation/stipulation shall be taken by the bidders.

2.18 EVALUATION CRITERIA / METHOD

2.18.1 The technical proposal & “conditions of Eligible bidders” shall be evaluated first. The bidder shall qualify for opening of financial bid only if it meets the technical specifications/requirement of NTC. Threshold marks for technical qualification shall be 75 %. Total score obtained by bidders shall be calculated in such a way that 60% weight age shall be taken from technical score and 40% weight age shall be taken from financial score and the contract will be awarded to the highest scoring bidder. The formula for calculating total score is as follows:

19

Technical Evaluation

Marks obtained x 0.6 = “X” Total marks

Financial Evaluation

Lowest value in PKR. among the offered bids (after loading , if required) ) x 0.4 = “Y” Value of bid in PKR. of respective bidder (after loading, if required)

Total Score (Z) = X+Y

Contract will be awarded to highest scoring bidder

2.18.2 Price adjustment for Commercial Compliance:2.18.2.1 The cost of making good and deficiency resulting from technical compliance will be added to the corrected total bid price for comparison purpose only. The adjustments will be applied taking the highest price quoted by the other bidders being evaluated in detail in their original bids for corresponding item. However lowest price shall be considered for the contract. In case of non-availability of price from other bidders, the price will be estimated by the tender evaluation committee.

2.18.3 No bidder shall contact NTC on any matter relating to its tender from the time of opening to the time of contract is awarded.

2.18.4 Any effort by a bidder to influence NTC in the tender evaluation, bid comparison or order award decision may result in the rejection of his bid.

2.19 COMPLIANCE CERTIFICATE

The bidder will furnish a compliance certificate with the bid as per enclosed format. (Annexure G)

2.20 AWARD CRITERIA & NTC’S RIGHT

2.20.1 The contract will be awarded to responsive lowest evaluated bidder, provided that such bidder has been determined to be technically qualified to satisfactorily perform the order.

2.20.2 The NTC reserves the right to accept or reject any bid, and to annul the tendering process and reject all bids, at any time prior to award of order,

20

without thereby incurring any liability to the affected bidders or any obligation to inform the affected bidders of the grounds for the NTC’s action.

2.21 PRE-BID CONFERENCE

In order to clarify the NTC requirements/technical specifications of the equipment, a pre-bid conference shall be arranged at NTC HQs on , at 1100 Hrs. Bidders may forward their technical queries at least 10 days prior to this conference so that answers to their queries may be given to them.

2.22 TECHNICAL COMPLIANCE STATEMENT

The Bidder shall furnish a Clause-by-Clause compliance for each and every clause of technical specification. As far as possible, the bidder shall provide the detailed technical description for each compliance statement.

2.22.1 "Fully Compliant", if the systems and functions offered fully meet the technical requirement.

2.22.2 "Partially compliant", if the systems and functions offered meet the technical requirement partially, the bidder shall state the reason why the offer is partially compliant. However, if the bidder is able to fulfill the specified requirement later, the time schedule for this shall be stated. In such cases, the bidder shall clearly mention the extent to which other requirements or specifications are affected.

2.22.3 “Non Compliant”, if systems and functions cannot meet the requirements, the bidder shall also state the reasons for it.

2.22.4 In case of absence or unclear statements of compliance for any specified requirement, NTC will interpret that particular requirements being "Non Compliant".

Note: The bidder shall include in his proposal the detailed technical information, drawings and functional descriptions of the offered equipment to support the Compliance to the technical requirements.

2.23 ENGINEERING SURVEY & SYSTEM DESIGN

2.23.1 The bidder shall carry out survey for each site at its own cost for installation of equipment, rectifiers, battery banks, DDF racks, PCM cables including accessories & power / telecom earthing etc to find out exact space / cable lengths for the system & connectivity upto exchange side.

2.23.2 On award of work the contractor shall submit detail survey report, complete system design including system performance to meet the Technical requirements & cutover plan at its own cost.

21

-- End of Chapter Two --

22

GENERAL TERMS & CONDITIONS OF CONTRACT

3.1 PERFORMANCE SECURITY / BANK GUARANTEE

3.1.1 The successful bidder shall furnish to NTC a performance security equivalent to 10% of the total ordered/contractual value, in the shape of bank guarantee valid for a period of 18xmonths (as per annexure “H”) at the time of signing of contract.

3.1.2 The performance security / bank guarantee shall be further extended at the consent of NTC if delivery or commissioning is delayed.

3.1.3 Failure of the successful bidder to furnish acceptable performance security for required validity period shall constitute sufficient grounds for the annulment of the award and forfeiture of the tender security.

3.1.4 All the correspondence regarding release of performance guarantee shall be made with Director (Procurement) NTC HQ.

3.1.5 The performance guarantee will be released after issuance of FAC by Project Director.

3.2 NTC’s RESPONSIBILITIES

3.2.1 NTC shall provide suitable space for the DWDM/SDH equipment and related power equipment to be installed at specified locations suitable in accordance with the engineering survey.

3.2.2 NTC shall provide earthing point (telecom & power), electrical AC (Single/Three Phase) power point in the AC distribution panel, as per the engineering survey report.

3.2.3 NTC shall provide room air conditioning, fire extinguisher & fire fighting system.

3.3 CONTRACTORS RESPONSIBILITIES

3.3.1 The contractor shall supply the equipment in accordance with the BOQ of

contract / purchase order.

3.3.2 The contractor shall not subcontract the whole of the works. The contractor shall not subcontract any part of the works without the consent of the NTC.

3.3.3 The contractor shall install & commission the equipment as per standards.3.3.4 The contractor will be responsible for connectivity of tributary signals (E1s

& E3s) & also FE/GE interfaces upto termination points of exchange/data eqpt through PCM cables /co-axial cables and accordingly will quote for these accessories on the basis of engineering survey.

3.3.5 The contractor will ensure termination of all the cabling on DDF.

23

3

3.3.6 The contractor will be responsible for shifting of all the traffic (E1s & E3s) from old system to new system ensuring minimum breakdown.

3.4 CONTRACTOR’s REPRESENTATIVE

3.4.1 Project Manager of the Contractor

3.4.1.1 The Contractor shall appoint one full time Residential Project Manager and necessary staff in Pakistan to implement the whole project. The Manager shall be proficient in English language and experienced in the installation, operation and maintenance of equipment and materials supplied.

3.4.1.2 The Manager shall be available one (1) month prior to commencement of installation work and be involved in the project work till the hand-over of the system to NTC.

3.4.1.3 NTC reserves the right to demand the replacement of the Project Manager, Assistant Project Manager, engineers, technicians or labor dispatched by supplier for the execution of the project, if NTC considers that he / she is not suitable to do his / her work.

3.4.2 Reporting to NTC

The contractor shall be required to submit monthly progress report to NTC. Every fault discovered during installation and testing must be documented by the contractor and a copy shall be submitted to each of the following officers of NTC.

3.4.2.1 Chief Technology Officer.

3.4.2.2 Project Director

3.4.2.3 Project Manager

3.4.3 The contractor shall ensure all personnel employed for the execution of the works under the contract are adequately qualified, skilled and suited in health and temperament for the conditions and environment in which work is to be undertaken. All relevant personnel should be able to converse fluently and discuss technical matters in English/Urdu.

3.4.4 The Contractor shall appoint one or more than one competent representative(s) whose name(s) shall have previously been communicated in writing to NTC by the contractor.

“The said representative, or if more than one shall be appointed then one of such representatives, shall be present on the site during working hours or as per the instructions which NTC or its representative may give to the said representative of the contractor”.

3.4.5 NTC shall be at liberty by notice in writing to the contractor to object to any representative or person employed by the contractor in the execution of or otherwise about the works who shall, in the opinion of NTC misconduct or be incompetent or negligent, and the Contractor shall remove such person from the work with a proper replacement.

3.4.6 The Contractor shall make his own arrangements and shall be responsible for the engagement of all personnel and labor local or otherwise and for

24

their legal status, visas, taxes, duties, transport, accommodation, feeding, working conditions, any other fringe benefit and payment thereof.

3.4.7 The Contractor shall keep NTC fully indemnified against any claim and dispute raised by the Contractor’s person and / or the third party with respect to engagement of the Contractor’s personnel.

3.5 WORKMANSHIP, MATERIALS & EQUIPMENT

3.5.1 The contractor shall execute the works according to the specifications, terms and conditions set out in the tender documents herein, decisions, instructions and orders given, from time to time, by NTC or their representatives on the site in writing or confirmed afterwards in writing, and to the satisfaction of NTC.

3.5.2 The contractor before starting the work has to ensure availability of sufficient tools, transport and labor etc., for execution of the work. The competent authority reserves the right to cancel the contract at any stage if such sources are found insufficient with the contractor for execution of work. Materials, tools and equipment to be supplied and / or provided by the contractor shall be of such quality, quantity and capability as to ensure the safe and satisfactory execution of the works. Complying with the relevant specifications, approved by NTC and subject to the inspection by NTC at Site. Should they be found not complying with the specifications or defective, insufficient or inadequate, then NTC shall have the right to direct the Contactor to replace improve and / or supplement them without any cost to NTC. The situation, if not improved by the contractor to the satisfaction of NTC may also result in the cancellation of contract. Any inspection of the above referred materials, tools and equipment followed by the approval from NTC shall not in any way relieve the contractor from his responsibility for supplying / providing the proper and necessary materials, tools and equipment and executing the works in compliance with the terms, conditions and specifications of the contract.

3.5.3 NTC shall have free use of the contractor’s equipment, materials, tools or other items as may be necessary on the site in connection with the works without being responsible to the contractor for fare, wear and tear thereof.

3.6 INSURANCE

3.6.1 Insurance for the following items shall be affected by and at the cost of the contractor:

3.6.1.1 Workmen’s compensation liability for the contractor’s personnel.

3.6.1.2 Vehicles, tools and test equipment provided and used by the Contractor.

3.6.1.3 Social insurance.

3.6.2 Any loss and / or damage which or any part of which is not covered by the insurance shall be borne or compensated by the contractor if such losses and / or damages are attributable to the Contractor.

25

3.7 TRANSPORTATION / PACKING

All types of transportation for delivery of equipment at final destination will be the responsibility of the contractor. Contractor shall ensure proper / international packing of equipment to avoid deterioration of equipment etc.

3.8 TIME FOR COMPLETION

3.8.1 The contractor shall supply, install and commission the equipment including load shifting from old system to newly installed system within 06 months from the date of signing of contract.

3.8.2 load shifting will be executed in three phases: Phase –I: Load Shifting in Ring –I including sub ring I-A & spurs. Phase-II: Load Shifting in Ring-II. Phase-III: Load Shifting in Ring-III including spurs.

3.8.2 Late completion

If the contractor fails to supply, install and commission the equipment within the time for completion, the contractor’s only liability to the NTC for such failure shall be to pay an amount equivalent to 0.5% per week maximum to 10% value for which he fails to complete the works.

3.9 WARRANTY / SERVICES

3.9.1 The contractor will warrant that the equipment supplied under the contract are new, un-used, and incorporates all recent improvements in design and materials and of good quality. The warranty shall remain valid for a minimum period of 12 months after the goods have been delivered, installed, commissioned at the final destination & stabilization period is ended as enunciated in clause 3.10.1. NTC shall promptly notify the supplier in writing of any claims arising under this warranty and the supplier will repair / replace the defective stores at reasonable speed without any cost effect.

3.9.2 The bidder, for technical assistance at the highest level shall provide high- level support/technical assistance at sites on 24 × 7 ×365 basis, during the warranty period, free of cost.

3.9.3 The contractor will sign O&M agreement with NTC after completion of warranty period. The duration of this agreement will be decided later on.

3.10 PROVISIONAL ACCEPTANCE CERTIFICATE

After successful and complete installation, testing and commissioning the contractor may notify to the NTC concerned officer when he considers that the works are complete. Upon such notification from contractor, the NTC

26

concerned officer will arrange inspection and issue provisional acceptance certificate, however issuance of PAC is subject to satisfactory completion of stabilization period enunciated below in favor of contractor as per requirement of contract. Alternatively the NTC concerned officer will notify the contractor that the work is not fully complete and contractor will rectify the discrepancies.

3.10.1 Stabilization Period

3.10.1.1 In case of any deficiency during provisional acceptance testing, it will be recorded and acknowledged by both the NTC and the Bidder. The Bidder will remove / rectify such faults and defects and again carry out the tests to the satisfaction of NTC.

3.10.1.2 After successful completion of provisional Acceptance Testing, & load shifting NTC shall monitor the total system for a period of three (3) months for checking the stability of the system.

3.10.1.3 During this stabilization period, if any major problems/faults are noticed, the Bidder shall be notified for rectification of such faults/problems. In such case the stabilization will begin again for a period of three months after the rectification of such faults and so forth. NTC reserves the right to replace the faulty node if found suitable.

3.10.1.4 NTC will issue provisional acceptance certificate after Two (2) Months of successful completion of stabilization period for whole of the network. Consequently warranty period will start from the date of issuance of PAC.

3.11 TERMS OF PAYMENT

Payment of contract price shall be made in the following manners:

3.11.1 Fifteen percent (15%) advance payment/mobilization advance shall be payable to the contractor against the Bank Guarantee of equivalent amount, submitted by the contractor & issued by any scheduled bank of Pakistan.

3.11.2 Twenty Five Percent (25%) of the contract price shall be payable to the contractor upon successful delivery of equipment at destination sites. The ultimate consignee will confirm the delivery of equipment. The contractor will furnish invoice of 40% of total contract price that will include the adjustment of 15% advance payment also.

3.11.3 Twenty Five Percent (25%) of the contract price will be payable to the contractor in three equal installments after the load shifting & completion of stabilization period of each optical ring of the network as the whole network is divided in three optical rings & activity of commissioning/load shifting will be carried out in three phases.

27

3.11.4 Remaining twenty five percent (25%) of the contract price will be payable to the contractor after issuance of PAC which is subject to the conditions enunciated in clause # 3.10.1. Project Director will issue PAC of whole of the network.

3.11.5 Ten percent (10%) balance payment shall be payable on removal of minor discrepancies occurring during the warranty period & subject to issuance of FAC by Project Director.

3.11.6 All the payments shall be made through cross cheque in the Pak Rupees.

3.11.7 Taxes will be deducted as per government rules at the time of payment.

3.12 FINAL ACCEPANCE CERTIFICATEThe contractor may notify the NTC concerned officer at-least 15 days before the expiry of warranty period for the issuance of final acceptance certificate. Upon such notification from contractor, the NTC concerned officer will issue Final Acceptance Certificate in favour of contractor subject to satisfactory completion of warranty period as per requirement of contract. Alternatively the NTC concerned officer will notify the contractor for the discrepancies that still remain un-resolved and contractor will rectify the discrepancies.

3.13 DEFAULT BY CONTRACTOR

The contractor will be declared as defaulter under following conditions:

3.13.1 If the contractor fails to supply the equipment, refuses or fails to comply with a valid instruction of the NTC, then NTC may give notice and stating the default.

3.13.2 If the contractor has not taken all practicable steps to remedy the default within 14 days after receipt of NTC notice, the NTC may by a second notice cancel the order and performance security will be confiscated.

3.13.3 If the contractor fails to deposit within 10 days of the issuance of letter of intent by NTC, the security equivalent to 10% of the contract price.

3.13.4 If the contractor has abandoned the contract.

3.13.5 Without reasonable excuse contractor have failed to commence the works or have suspended the progress of the works for ten (10) days after receiving from NTC written notice to proceed.

3.13.6 Gives the monthly progress equivalent to only 60% of the approved work progress.

3.13.7 Failure within a period of 30 days (or such longer period as NTC may authorize in writing) after receipt of the default notice from NTC.

3.13.8 Despite previous warnings by NTC in writing, not be executing the works in accordance with the contract, or be neglecting to carry out his obligations under the contractor, cancel the contract and may procure upon such terms and

28

in such manner as it deems appropriate, goods and services, similar to those undelivered and the Contractor shall be liable to NTC for any excess costs for such similar goods and services.

Note: “ If NTC cancels the contract under the above clause, it shall not be liable to pay the contractor any money on account of the contract. Moreover the security deposited by the contractor shall also be confiscated by the NTC under such circumstances”.

3.14 CONTRACTOR’s NEGLIGENCE

The contactor shall be responsible in respect of all activities, suites claims, demands, charges and expenses arising in connection herewith which shall be caused by negligence or breach of statutory duty of the contractor or any of his sub-contractor.

3.15 PROGRESS RRVIEW MEETINGS

Progress review meetings will be held as follows:

3.15.1 Fortnightly meeting will be held in the O/o Project Manager (DWDM).

3.15.2 Monthly meeting will be held in the o/o Project Director.

The contractor or his authorized representative will be present during the above mentioned meetings. The contractor will take necessary measures, as a result of the above meetings, to make the work progress as decided by the NTC, in conformity with Implementation Schedule.

3.16 INSPECTION & TESTS

3.16.1 If independent inspection is required by NTC they will appoint and inform the Contractor of such appointment of an inspector, NTC’s authorized inspector shall have the authority to reject any supplies or lots of supplies or portion of supplies which are found to be defective in material or workmanship or otherwise not in conformity with the requirements of the contract.

3.16.2 In the event, NTC’s inspector rejects any supplies; the Contractor shall furnish additional quantities for inspection / approval in lieu of the supplies rejected.

3.16.3 NTC’s independent inspection shall not relieve the Contractor from his responsibility to furnish supplies in conformity with contract requirements and free of all defects.

3.16.4 In the event of any irregularity in test reports, specifications as found by NTC’s authorized inspector, the Contractor shall immediately upon the inspector’s notification make necessary modifications, repairs, etc.

3.16.5 NTC staff may visit the site periodically or occasionally in order to supervise the progress and quality of installation work. Contractor shall co-operate fully with such supervisory staff.

29

3.16.6 Contractor shall keep the work and storage areas clean and shall daily remove rubbish and dirty things etc. from inside and near buildings and plants.

3.16.7 Upon completion of installation work of each site to the satisfaction of NTC, contractor shall remove from the site as early as possible all tools, appliances, packing cases and plants not constituting part of the contract.

3.17 FORCE MAJEURE

3.17.1 The Contractor shall not be liable for forfeiture of its performance security, liquidated damages or termination for default, if and to the extent that, it’s delay in performance or other failure to perform its obligations under the contract is the result of an event of Force Majeure.

3.17.2 For the purpose of this clause, Force Majeure means an event beyond the control of the Contractor and not involving the contactor’s fault or negligence. Such event may include, but are not restricted to, unforeseen natural disasters (floods, fire, earthquake etc.), public strikes, wars, revolutions, epidemics, quarantine restrictions and delay in freight embargoes.

3.17.3 If a Force Majeure situation arises, the contractor shall promptly notify NTC in writing of such conditions and the cause thereof. Unless otherwise directed by NTC in writing, the contractor shall continue to perform its obligations under the contract as far as is reasonably practicable, and shall seek all reasonable alternative means for performance not prevented by the Fore Majeure event.

3.18 LIQUIADATED DAMAGES

The contractor fails to deliver any or all of the goods or perform the services within the time period specified in the contract, NTC shall without prejudice to its other remedies under the contract deduct from the contract price as like liquidated damages, a sum equivalent to 0.5% of the delivered price of the delayed goods or unperformed services for each week of delay until actual delivery or performance. However the maximum deduction shall not exceed 10% of the total contract cost.

3.19 TERMINATION FOR INSOLVENCY

NTC may at any time terminate the contract by giving written notice to the contractor without compensation to the contractor, if the contractor becomes bankrupt or otherwise insolvent, provided that such termination will not prejudice or affect any right of action or remedy which has accrued or will accrue thereafter to NTC.

3.20 TERMINATION FOR CONVENIENCE

3.20.1 NTC may, by written notice sent to the contractor, terminate the contract, in whole or in part at any time for its convenience. The notice of

30

termination shall specify that termination is for NTC’s convenience, the extent to which performance of work under the contract is terminated, and the date upon which such termination becomes effective.

3.20.2 The goods that are complete and have reached at work site shall be purchased by NTC at contract terms and prices. For the remaining goods, NTC may select:

3.20.2.1 To have any portion completed and delivered at the contract terms and prices; and

3.20.2.2 The Contractor may be reimbursed for any expenses incurred for partially completed goods and material and parts already ordered.

3.21 COMPLIANCE WITH REGULATIONS

3.21.1 The Contractor shall, in all matters arising in the performance of the Contract, conform in all respects with the provisions of any Ordinance or Law or Regulations of Pakistan or By-laws of any local or other duly constituted authority that shall affect the Contractor in the performance of his obligations under the Contract and shall keep NTC indemnified against all penalties and liabilities due to the Contractor by every kind for breach by the Contractor and his personnel of any such ordinance, Law, Regulation or By-law.

3.22 CONFIDENTIALITY

3.22.1 The Contractor shall not disclose to any third party or make public the contents of NTC and any technical and commercial matters of NTC which are given to him or which he comes to know through execution of the Contract, without prior written consent of NTC, except the matters which have been already published by NTC or by the third party and except the case required by Laws and Regulations.

3.22.2 Any documents, other than the contract itself shall remain the property of NTC and shall be returned (in all copies) to NTC on completion of the contractor’s performance under the contract if so required by NTC.

3.23 LIABILITY FOR DAMAGE

3.23.1 Contractor shall repair, at his own expense and to the satisfaction of NTC, all damages to the system, building and plants etc. caused by supplier, his sub-contractor(s), or his employee during the period of installation and commissioning.

3.23.2 The contractor shall take special and full care not to cause damage to the cables, accessories, other materials and equipment supplied by NTC whether before/ during/after installation thereof, till the issuance of acceptance certificate by NTC

3.23.3 During execution of the Works, the contractor shall take full care and precautions not to cause any damage to the existing installations, facilities,

31

services, whether underground or on ground, and persons and property of the third party/NTC. Should any such damage be caused by the contractor, the contractor shall be responsible for rectifying and compensation for the said damage, if required so, and all the cost thereof shall be borne by the contractor except amount covered by the insurance. The contractor shall keep NTC indemnified against any claim from the third party with respect to such damage caused by and attributable to the contractor.

3.24 SETTLEMENT OF DISPUTE

3.24.1 All disputes and differences arising out of or in connection with the contract and its performance which can not amicably be settled between the parties, shall, within 30 (thirty) days from the date that either party informs the other in writing that such differences, dispute or question exists, be referred at the first stage to the Project Director, if the dispute/difference prevails even after resorting to the office of the Project Director then the matter will be brought to the office of Chief Technology Officer NTC whose decision will be final and shall not be challengeable in any court of law.

32

Annexure “F”

FORMAT OF BANK GUARANTEEFOR BID SECURITY

Bank Guarantee No.-----------Dated at Islamabad, the ----------

Amount___________Validity _________________

To,

THE CHAIRMAN,NATIONAL TELECOMMUNICATION CORPORATIONHEAD QUARTERS F-5/1ISLAMABAD.

Dear Sir,

WHEREAS M/S _____________ (hereinafter called the Tenderer) have requested us through ___________ Bank Ltd., to furnish Bid Security by way of Bank Guarantee in your favour in the sum of __________________ (IN FIGURE) ___________ (IN WORDS) against your Tender Notice No. ____________ dated ____________for supply / installation of_______________________________.

WE HEREBY AGREE AND UNDERTAKE:

i. To make unconditional payment _________ to you on demand without further question or reference to the Tenderer in case of withdrawal or modification of bid or any default or non-execution of the Contract or refusal to accept order by the Tenderer from the date of opening of bids until the expiry of the validity of their offer,

iii. To keep this guarantee in full force from (date) _________ upto _____________ (date) _______ the date until which the Tenderer’s offer is valid.

iii. To extend the period of guarantee if such extension be necessary beyond the date stated in para (ii) and as so desired by the tenderer.

Any claim arising out of this guarantee must be lodged with this Bank within the period the guarantee is valid and before the date of its expiry. After this date the guarantee will be considered null and void and should be returned to us.

Yours faithfully,

Name of the Bank:_______________Authorized officer’s Signature & Seal:______________________

33

Annex-GCOMPLIANCE SHEET

Clause. # Description CompliedNot

Complied

Partially complied

(give details)

Page # of bid, where

compliance available

1 General2 Eligible Bidders3 Cost of tendering4 Clarifications of Tender Documents5 Amendment of Tender Documents6 Country of Origin7 Preparation of bid documents 8 Price9 Tender Security / Earnest Money10 Validity of Bids11 Deadline for submission of bids12 Modification & Withdrawal of bid13 Opening of Bid14 Clarifications/correction of bid15 Responsiveness of Bids16 Pre-liminary Examination17 Evaluation of bids18 Evaluation Criteria / Method19 Compliance Certificate20 Award Criteria & NTC’s Right21 Pre-Bid Conference

22 Clause by Clause Compliance Statement

23Engineering Survey & System Design

Contract Conditions

1Performance Security / Bank Guarantee

2 NTC responsibilities

3 Contractor’s responsibilities

4 Contractror’s representative

5 Workmanship materials & equipment

6 Insurance

7 Transportation/Packing

8 Time for completion

9 Warranty/services

10 Provisional Acceptance Certificate1112

Terms of Payment

12 Final Acceptance Certificate

34

13 Default by contractor

14 Contractors negligence

15 Progress Review Meeting

16 Inspection & tests

17 Force Majuere

18 Liquidity Damages

19 Termination for insolvency

20 Termination for convenience

21 Compliance with regulations

22 Confidentiality

23 Liability for damages

23 Settlement of dispute

35

Annexure “H”

BANK GUARANTEE FOR PERFORMANCE BONDBank Guarantee No.-----------

Date of Issue -------------Valid upto ----------------Value (Rs.) ----------------

FROM: _______________________________________________________________

TO,THE CHAIRMAN,NATIONAL TELECOMMUNICATION CORPORATIONHEAD QUARTERS F-5/1ISLAMABAD..

SUBJECT: B/G AND DATE FOR _______________ ON BEHALF OF __________FOR DUE AND FAITHFUL PERFORMANCE ORDER NO. ________________ DATED_______________.

Whereas M/s______________________(hereinafter called the Supplier) have requested us to furnish a Bank Guarantee in your favour in the sum_____________(IN WORDS) _________________________as performance security against order No.._____________dated____________to be concluded between the Supplier and National Telecommunication Corporation HQs F-5/1 Islamabad.

WE HEREBY AGREE:1). To make an un-conditional payment of __________ to you on demand without

any further question or reference to the Supplier upon failure of the Supplier to perform the Order for which you will be the sole judge.

2). To keep this guarantee valid in full force from this date upto the time of the due and faithful completion of the Order under reference (the schedule of implementation shall be as described in the Purchase order and its subsequent amendments) or till___________ whichever date is later. The faithful completion of the order by the Supplier will be intimated by the NTC.

3). To extend the period of the enforceability of this guarantee if such extension be necessary or desired by you of us. All claims there under must be submitted to the Bank of________ on or before the expiry date mentioned in this guarantee are the date mentioned in its extensions issued from time to time, after which this guarantee will become null and void and should be returned to us. Irrespective of its return, we shall consider ourselves fully discharged from any obligation there under after the said expiry date.

Dated This Day ofAuthorized Signature:________________________& Seal of bank

Witness: ______________________ _____________________________ Sworn & Sign before me this day of…. …....

by.______________________

-- End of Chapter Three --36

PART TWO

37

TESTING & COMMISSIONING

4.1 ACCEPTANCE TESTING

The acceptance testing of system shall be carried out in the following two stages:

4.1.1 Pre-shipment inspection & testing

4.1.2 Installation Testing & Provisional Acceptance Testing

4.2 TESTING REQUIREMENTS

4.2.1 The Equipment Supplier shall carry out the factory tests, prior to shipment and provisional acceptance test in the presence of NTC's Inspecting Officer (hereafter called Inspector). Inspector may, at his discretion, reject the whole or any part of the equipment & cable or materials that, in his opinion, does not comply with terms of contract.

4.2.2 The Equipment Supplier shall submit to NTC for approval the schedules, inspection procedures, items, objectives and test procedures including recording forms at least one (1) month before the scheduled starting date of the tests.

4.2.3 The test for final confirmation for the system will be carried out by NTC one (1) month before the expiry of the warranty period for issuance of Final Acceptance Certificate. If the inspection results are not acceptable, The Equipment Supplier shall replace or repair the equipment concerned free of charge. In case of disagreement, the Equipment Supplier shall have an option to witness the inspection in question.

4.3 PRE-SHIPMENT INSPECTION & TESTING

Factory test and inspection of all the equipment and materials including spare units shall be carried out at manufacturer's factories before shipment to ensure that the equipment are complete in all respects and will comply with the terms of the contract.

4.3.1 Inspection by NTC

NTC shall send four inspectors for the factory inspection of whole system for a period of one (1) week. All cost for the inspection such as economy class airfares, boarding, lodging, daily allowance and local travel facility, etc. at the manufacturer's home country shall be borne by the Equipment Supplier.

4.3.1.1 The Equipment Supplier shall state the proposed acceptance tests and inspection plans which consist of test items and implementation schedule, for approval from NTC.

4.3.1.2 The Equipment Supplier shall submit the manufacturer’s own test data to the inspectors.

38

CHAPTER 4

4.3.1.3 Inspection & Testing items shall comprise at least the following items:

4.3.1.3.1 Numerical inspection of the whole equipment and materials.

4.3.1.3.2 Visual inspection for appearance and workmanship of the whole equipment and materials.

4.3.1.3.3 Inspection for mechanical composition of equipment and materials on sampling basis.

4.3.1.3.4 Performance inspection and test of main equipment and materials on sampling basis.

4.3.1.3.5 Factory Environmental Tests

4.3.1.4 The Equipment Supplier shall provide all the facilities, test equipment, tools and personnel necessary for testing and inspection at the factory.

4.3.1.5 No equipment shall be packed before the specified factory inspections and tests have been completed and certified by the inspector.

4.3.1.6 Two copies of the data of factory inspections and tests shall be submitted to NTC within one week after the completion of the respective tests.

4.3.1.7 The data shall also include the manufacturer's own test data of equipment and materials.

4.4 LOCAL ACCEPTANCE TESTING

4.4.1 Provisional Acceptance Testing

The provisional acceptance testing shall be conducted by NTC after completion of the installation. The set of tests and test procedure for the provisional testing in respect of SDH Optical Fiber equipment and associated Power Plant shall be approved by NTC

4.4.1.1 The testing will start when the following confirmations have been met:

4.4.1.1.1 That the installation work and testing have been completed.

4.4.1.1.2 That the system is suitable for service.

4.4.1.1.3 That spare units, tools and test units have been supplied.

4.4.1.1.4 That all the manuals, drawings and documents have been supplied.

4.4.1.2 The provisional acceptance testing shall include at least the following:

4.4.1.2.1 Visual inspection for proper installation.

4.4.1.2.2 Check that the delivered number is correct and installed (or stored as spares).

4.4.1.2.3 BER characteristic for all routes.

4.4.1.2.4 Performance tests for all equipment.

4.4.1.2.5 LASER related tests.

4.4.1.2.6 Cross connection accuracy.

4.4.1.2.7 Path protection switching functionality test for ring topology.

39

4.4.1.2.8 Overall function test of alarm indication, remote control / supervision and monitoring.

4.4.1.2.9 Receive level.

4.4.1.2.10 Performance testing at interfaces.

4.4.1.2.11 NMS (Network Management System) & TMN (Telecommunication Management Network).

4.4.1.2.12 Network Synchronization.

4.4.1.2.13 Order wire and data channels.

4.4 1.2.14 Synchronization test of clocks External/Internal.

4.4.1.2.15 DC supply voltages and power consumption.

4.4.1.2.16 Additional checks & measurements proposed by the Equipment Supplier.

4.4.1.3 Provisional Acceptance Tests for Switch Mode Rectifiers

4.4.1.3.1 Appearance & Wiring.

4.4.1.3.2 AC Input Voltage.

4.4.1.3.3 DC Output Voltage.

4.4.1.3.4 Testing under no load condition.

4.4.1.3.5 Tests for current sharing.

4.4.1.3.6 Central Control verification test.

4.4.1.3.7 Testing the software configuration.

4.4.1.3.8 Capacity test.

4.4.1.3.9 Additional checks & Measurements proposed by the Equipment Supplier.

4.4.1.4 Acceptance Tests for Batteries

4.4.1.4.1 Measurement of individual cell voltages.

4.4.1.4.2 Test for the batteries back-up time.

4.4.1.4.3 Additional checks & measurements proposed by the Equipment Supplier operator.

4.4.1.5 The bidder shall provide the testing environment including all the testing & measuring equipment required to carry out provisional acceptance test according to approved procedure by (N&SE). The bidder shall arrange at its own cost and no liability on NTC 03xsets of test instrument for field acceptance & testing , however if nay equipment is available with NTC that can be used for testing.

4.4.2 Stabilization Period

4.4.2.1 In case of any deficiency during provisional acceptance testing, it will be recorded and acknowledged by both the NTC and the Equipment Supplier. The Equipment Supplier will remove / rectify such faults and defects and again carry out the tests to the satisfaction of NTC.

4.4.2.2 After successful completion of provisional Acceptance Testing, NTC shall monitor the total system for a period of three months for checking the stability of the system.

40

4.4.2.3 During this stabilization period, if any major problems/faults are noticed, the Equipment Supplier shall be notified for rectification of such faults/problems. In such case the stabilization will begin again for a period of three months after the rectification of such faults and so forth. NTC reserves the right to replace the faulty node if found suitable.

4.4.3 Provisional Acceptance Certificate

NTC will issue provisional acceptance certificate after Two (2) months of successful completion of the stabilization period.

4.4.5 Warranty Period

The date of completion of the stabilization period will signify the beginning of Warranty period .

4.4.6 Final Acceptance Certificate

On successful completion of the warranty period, Final Acceptance Certificate will be issued to the Equipment Supplier.

4.4.7 Documentation

4.4.7.1 General Requirements For Documentation

4.4.7.1.1Standard

Documentation shall be prepared in accordance with usual Telecommunication Industry Standards. Terms, marks and abbreviations shall be those adopted by ITU-T and those that are printed on parts and panels in equipment.

4.4.7.1.2Size & Binding

Each document shall be on A-4 size paper except for drawings and figures. The drawings and figures shall be folded to accommodate in A4 size. Handbooks shall be bounded with a hard durable cover and paper shall be strong to allow repeated use. When opened, the pages of the handbook shall lie flat.

4.4.7.1.3Copy of Handbook

NTC reserves the right to reproduce the Equipment Supplier’s documentation either in total or in part. The reproduced documentation will only be used within NTC for its own purposes.

4.4.7.1.4Number of Copies

The Equipment Supplier shall supply the following handbooks in English:

4.4.7.1.4.1 Planning Document 04 sets

4.4.7.1.4.2 System handbook (one for each station) 21 sets

4.4.7.1.4.3 Installation handbook11 sets

4.4.7.1.4.4. Measuring equipment handbook for 03 sets each measuring equipment

Tool Handbook (04 sets)

4.4.7.2 Planning Document

41

These shall include all the materials for planning of the system including information, charts, graphs & tables, interfacing plan etc.

4.4.7.3 System Handbook

4.4.7.3.1 System handbook shall deal with the detailed technical description of the system including detailed information on the operation of the system and facilities of every device used, system construction, adjustment, control etc. Explanation shall be in detail so that system operation and maintenance can be carried out with the help of system handbook.

4.4.7.3.2 System handbook shall at least include the following:

4.4.7.3.2.1 Detailed Technical Description.

4.4.7.3.2.2 Block diagrams, Schematic diagram and Circuit Diagrams.

4.4.7.3.2.3 List of equipment and parts.

4.4.7.3.2.4 Remote control and supervisory system arrangement.

4.4.7.3.2.5 Periodical test items and measuring method.

4.4.7.3.2.6 Recording forms for test, operation and maintenance.

4.4.7.3.2.7 Station wiring drawings in respect of equipment and power as per actual status of each station.

4.4.7.3.2.8 Others.

4.4.7.4 Installation Handbook

4.4.7.4.1 Drawings and explanation of procedure for equipment installation, equipment fixing, cable clamping and supporting, principle of wiring etc.

4.4.7.4.2 List of devices and materials for equipment installation.

4.4.7.4.3 Precautions in handling equipment.

4.4.7.4.4 Dimensions of materials shall be specified in all drawings. Explanation shall be distinctive and concrete so that the installation work can be carried out with the help of installation handbook.

4.4.7.5 Measuring Equipment Handbook

4.4.7.5.1 Measuring equipment handbook shall deal with equipment adjustment, test and operation and maintenance. Explanation shall be in detail so that equipment can be maintained in a stable manner.

4.4.7.5.2 Measuring equipment handbook shall include the following:

4.4.7.5.3 Detailed circuit diagram

4.4.7.5.4 Explanation of symbols, abbreviations and terminology used.

4.4.7.5.5 Step by step adjustment and testing procedures.

4.4.7.5.6 Electrical and mechanical specification by drawings and / or photograph indicating location of panels or parts.

4.4.7.5.7 Cause and appearance of each trouble.

4.4.7.5.8 Procedures for replacement of units and parts in the equipment specifications of each part, unit and / or sub-assembly including; type, identification code number, current and voltage, inductance, capacitance, resistance ratings and manufacturer’s name.

4.4.7.5.9 Detailed calibration procedure.42

4.4.7.6 Tool Handbook

These shall cover the operation procedures of all the important tools used to install and maintain the equipment.

4.4.7.7 Electronic Documentation

All the above documents should be in form of CD’s so that each could be loaded at server station and each client station. All the laptops will be fully installed with these electronic documentations.

4.4.7.8 System Simulators

System simulators will also be provided so that off-line knowledge about the system could be transferred for new system supervisors.

43

-- End of Chapter Four --

TRAINING

5.1 OBJECTIVEThe objective of the training program is to enable the NTC personnel to acquire the expertise concerning system design, installation, operation & maintenance, trouble-shooting & repair and detailed concept of all equipment under this project. The training program shall enable NTC personnel to acquire:

5.1.1 Independence in maintenance of the system

5.1.2 System design capability that allows NTC to undertake future expansion of the network independently

5.1.3 Network modeling and simulation skills

5.2 TYPES OF TRAININGThe training is divided into two types.

11.2.3.1.1.1 Type of Training No. of Trainees

Training Period

Qualification Required

11.2.3.1.1.2System Training in Manufacturer’s Premises

15 06x weeks Qualified Engineers

11.2.3.1.1.3Local Training in Islamabad in Supplier’s Premises.

40 06 xweeks Experienced Supervisors and

Technicians.

5.3 TRAINING COURSE & SCHEDULE The Equipment Supplier shall furnish the training courses and schedule as

described below. However, the Equipment Supplier can propose his own training course & schedule, but the schedule must meet the duration and general training requirements of NTC. NTC has the right to change the duration, number of trainees and training course at the time of negotiations.

5.3.1 System Training in Manufacturer’s Premises

The detailed system training shall be carried out in Training Center of the Manufacturer (not the Equipment Supplier) in the country of origin of the supplied equipment. The course plan & Training schedule shall be in the following order:

S # Training Course Period

44

CHAPTER 5

(a)

Introduction to Optical Fiber Transmission (SDH/DWDM)

Two weeks

(b)

Detailed technical training on the offered equipment including Installation, testing, commissioning procedures:

Six weeks

(c)

Preventive and corrective Maintenance Procedures & Operation of test instruments:

Two weeks

(d)

NMS, TMN, & Network Synchronization: one Week

(e)

System Design, Network Modeling & Simulation:

One week

5.3.2 Local Training[

For the local training, the Equipment Supplier shall supply a complete training solution covering all supplied equipment for such turnkey projects. Such training shall be conducted in Pakistan in the Equipment Supplier’s Premises or any other place, if approved by NTC. The training will be conducted in two batches each of 20 trainees detailed as under:-

5.3.2.1 Theoretical Training in Supplier’s Premises (12 weeks)

The training will be conducted for the all trainees either in the ‘Equipment Supplier’s Premises as per the requirement of NTC or any other place that is approved by NTC. The local training will be furnished as follows:-

S # Training Course Period

(a)

Introduction to Optical Fiber Transmission (SDH/DWDM)

One week

(b)

Installation Procedures One week

45

(c)

Testing Procedures One week

(d)

Commissioning of the Network One week

(e)

Preventive and corrective Maintenance Procedures & Operation of test instruments

One week

(f)

Network Management System, TMN, & Management of Centralized Spare Pool:

One week

5.3.2.2 On the Job Training at the installation site (Two Weeks)

This training shall be conducted to the same personnel during the installation of the system at the installation sites under the supervision of the ‘Equipment Supplier’s technical staff. This training shall include installation, testing and commissioning of system at the installation sites.

5.4 TRAINING COST5.4.1 For SDH/ DWDM System Training in Manufacturer’s Premises:

All costs such as economy class air fares (to and from), boarding, lodging; daily allowance and local travel facilities at the manufacturer’s home country shall be borne by the Equipment Supplier.

5.4.2 For Local Training:

For all the theoretical and on-the job trainings, the cost of traveling, boarding, and lodging will also be borne by Equipment Supplier.

5.5 OTHER REQUIREMENTS5.51 All the instructors shall possess high technical ability to impart training. They shall have a high command on English language.

5.5.2 Sufficient diagrams and explanatory material shall be prepared by the Equipment Supplier and distributed to the trainees during the training sessions.

5.5.3 The Equipment Supplier shall prepare necessary textbooks for trainees. All the text books shall be written in English and be described to show the actual system of this Project, not for general system or other project.

5.5.4 The objective of the training program is to enable the personnel to acquire the expertise concerning system installation,operation , maintenance,troubleshooting repair and detailed concept of all equipment. The training program shall enable personnel to acquire:

46

5.5.4.1 Independence in mtce of system

5.5.4.2 Specialist level mtce of the system

5.5.4.3 System installation capability that allows personnel to undertake future expansion of the network independently.

5.5.5 The training must be completed before the commencement of installation of tendered equipment.5.5.6 The efficiency of the training program conducted by the bidder will be under close scrutiny and it will have to be repeated by the bidder without extra cost to NTC if the training given is found to be ineffective , deficient and un-satisfactory . However, NTC has to communicate it’s dissatisfaction (if any) during the training period for improvement and not afterwards.

-- End of Chapter Five --

SPARES

6.1 SPARE PARTS

6.1.1 Requirements

The general requirements of the spare parts shall be evolved considering the following:

6.1.1.1 A modular replacement concept shall be employed wherever practicable to facilitate restoration and installation (e.g. plug-in Printed Circuit Boards).

6.1.1.2 Spare parts, components and modules shall be identified in the equipment block diagrams, schematic diagrams and assembly drawings.

6.1.1.3 All spare parts shall be supplied with clear labeling and marking for ease of identification.

6.1.1.4 The spare parts shall be shipped in a pre-tested condition according to the supplier’s normal standard practices for equipment.

6.1.1.5 The spare parts shall be supplied in suitable weather, vibration, dust and electrostatic discharge protection containers or bags, as applicable.

47

CHAPTER 6

6.1.1.6 Spare pools for hardware and software shall be available at the local support right from the beginning.

6.1.1.7 The Equipment Supplier shall guarantee an availability of hardware spares for a period of at least 15 years from the date of final acceptance of the completed system. In the event that any spare parts becomes discontinued, obsolete or unavailable in the original form during this period, then an equivalent spare part, fully compatible with the previous type and giving the same or superior performance, shall be made available.

6.1.1.8 The spare parts shall be supplied within four months from the placement of the order.

6.1.1.9 The spare parts shall also be tested at the time of making over.

6.2 LIST OF SPARES6.2.1 Main Spares (To be quoted for the purpose of evaluation)

The following spares shall be quoted and shall be considered for evaluation. The actual spares requirement will be decided at the time of negotiation with the successful Equipment Supplier, keeping in consideration mean time between failure (MTBF), mean time to restore (MTTR) and availability criteria.

6.2.1.1 For equipment units (Modular plug-in units, Cards or Boards)

For all Modular plug-in units, Cards or Boards, the Equipment Supplier shall sum up all similar types from all stations and 15% (Roundup number) of that number shall be provided for every type of Modular plug-in unit, Card or Board. For example, the total number of STM-1: L-1.2 interface boards installed at all the stations is 51, then the spare quoted shall be 7.65, rounded up to 8 numbers. This spares concept shall be applied to all modular plug-in units or cards or boards of all the supplied system including SDH systems & NMS. This shall not cover spares for tools, mechanical structures and accessories.

6.2.1.2 Power System Supply

The Equipment Supplier shall provide 10 numbers of each power supply related items like MCB Board (Fuse Box), PSA Unit etc.

[

6.2.1.3 Mechanical Structures for SDH System

The Equipment Supplier shall provide 3 pieces for each unit of all mechanical parts like racks, sub-racks, assembly and sub-assembly of SDH systems. This requirement is not applicable for NMS.

6.2.2 Optional Spares (Not Considered For Evaluation)[[

The following spares shall be quoted and shall not be considered for evaluation. The actual spares requirement will be decided at the time of negotiation with the successful Equipment Supplier, keeping in consideration mean time between failure (MTBF), mean time to restore (MTTR) and availability criteria.

6.2.2.1 The Equipment Supplier shall suggest and list the spare provisioning for equipment, tools, measuring equipment, consumable materials, cable and cable accessories for three years after the completion of the warranty period. These spares shall not be considered for evaluation but, according to these spares list, the actual requirement will be decided. A good spare philosophy, which allows

48

for defective equipment to be quickly restored, is essential for maintaining a high availability figure for the system.

6.2.2.2 The Equipment Supplier shall follow the following guide-lines for optional spares.

6.2.2.2.1 Visualizing the overall system, the application of spares shall be equalized over the entire system so as to obtain a balanced availability figure, which shall be consistent with the overall availability requirement of the station.

6.2.2.2.2 In the proposal, the Equipment Supplier shall outline the proposed philosophy substantiated with availability calculations.

6.2.2.2.3 The lists shall contain the quantity, description and numbering consistent with system drawings and the associated unit price.

6.2.2.2.4 The unit price of optional spare shall tally with that quoted for the bid.

6.2.2.2.5 Prior to contract signature, final quantity of spares shall be prepared and agreed

6.2.3 Warranty Spares (Not Considered For Evaluation)

Equivalent quantity of spares shall be handed over to NTC prior to issuance of the PAC for utilization as warranty spares which will be returned to supplier at end of warranty period or good units adjusted against the order of spares by NTC.

-- End of Chapter Six --

MISCELLANEOUS TECHNICAL REQUIREMENTS

7.1 ENVIRONMENTAL REQUIREMENTS

7.1.1 The equipment will be installed and operated in sub-tropical conditions. Therefore adequate measures must be taken to ensure maximum operational reliability under such conditions.

7.1.2 The equipment shall operate and meet the stated performance parameters without forced air-cooling applied at:

7.1.2.1 Ambient Temperature : -110C to +550C

7.1.2.2 Relative Humidity : up to 85% at 300C

Under the condition that ambient temperature varies from -110C to +550C, and relative humidity up to 95% at 311C the equipment shall continue to operate, with guaranteed performance.

7.1.3 The ‘Equipment Supplier’ shall list the equipment components employing active temperature control.

49

CHAPTER 7

7.1.4 The equipment shall not deteriorate or suffer any damage during transportation or storage under weather protected, nor temperature controlled locations at:

7.1.4.1 Ambient Temperature : -20°C to +65°C

7.1.4.2 Relative Humidity : up to 98% at 60°C

7.1.5 The equipment shall operate at full specification up to an altitude of 2200m.

7.1.6 Adequate measures shall be taken to protect the equipment against insects, fungus, dust and any other harmful effects during transportation, storage, installation and operation.

7.1.7 The equipment shall be able to endure vibrations during transportation and storage according to following:

7.1.7.1 11 shocks of 300 m /s 2 each with duration of 18ms.

7.1.7.2 Vibrations for 500 hours with a frequency range 5-70Hz and with a maximum acceleration of 5 m/s2.

7.1.7.3 The equipment shall be designed to safely operate at a guaranteed performance parameters for acceleration of 11 m/s2 with frequency range 11-110Hz.

7.2 EARTHING REQUIREMENTS

7.2.1 The equipment should have positive power earth and a separate signal earth. The signal earth shall not carry any power current. The supply power ground shall not be directly connected to the signal ground in the rack. The ‘Equipment Supplier’ shall include full details of the earthing arrangements of the equipment.

7.2.2 All racks cabinets and ironwork shall be connected to the earth system.

7.2.3 For all screw type terminations, the ‘Equipment Supplier’ shall state the proposed method to prevent slackening of the terminations due to vibration or other reasons.

7.2.4 All earthing conductors shall be of adequate cross section area to ensure minimum resistance.

7.2.5 Earth conductor insulation shall be colored Yellow-Green.

7.2.6 The ‘Equipment Supplier’ shall supply all the earthing accessories to ensure proper ground. The station earth terminal / plate will be provided by NTC in each existing station. For a new station, the ‘Equipment Supplier’ has to supply every material related to make the proper earthing.

7.3 MECHANICAL REQUIREMENTS

7.3.1 Racks shall be of metallic structure and of dimensions according to ETSI 19” standard.

7.3.2 Equipment shall be of modular construction for ease of operation and maintenance. Replacement of faulty units, parts etc. shall be done from the front of the rack. Similarly, additional units added to sub-equipped racks, shall he install from the front without causing any disturbance or interruption to units already installed.

7.3.4 Where rack, sub-rack, or assembly is only partially equipped, the unequipped portions shall be fitted with dust covers or dummy panels.

7.3.5 There shall be no swelling or sharp edges, which could constitute a safety hazard for personnel. There shall not be any connector, switch, etc. protruding from the rack or

50

module or sub-assembly that could be accidentally knocked and cause a partial or complete loss of traffic or interruption to the system.

7.3.6 All sub-racks, modules and units etc. shall have an impact resistance finish similar to the rack containing them.

7.3.7 All equipment units shall be "Plug-in" types and capable of being secured at the front to prevent accidental removal. No de-soldering shall be necessary for removal of a module or unit. The removal or insertion of the units while equipment is in operation shall not endanger or affect the reliability or performance of the equipment.

7.3.8 Low contact-resistance plugs and sockets shall be used. Particular care must take to minimize effects of corrosion. The ‘Equipment Supplier’ shall provide full details of such arrangements.

7.3.9 Loose wiring or cabling shall not be permitted. All wiring and cabling shall be secured in a neat and tidy manner and adequately protected against accidental damage or the possibility of damage during the removal or insertion of any unit.

7.3.10 Particular attention shall be paid to the sealing of sub-assemblies to prevent the ingress of moisture or fine dust particles.

7.3.11 All screws shall be provided in metric standard complete with all necessary washers and locking devices.

7.3.12 Special tools required for installation and maintenance shall be provided along with the equipment.

7.4 LABELLING REQUIREMENTS

7.4.1 Labeling shall be done in English, and symbols used shall be internationally recognized.

7.4.2 All units shall be labeled clearly so that identification is possible from the front of the rack.

7.4.3 In addition to unit / sub-unit identification labels, each discrete unit that is removable for first line maintenance shall have a manufacturer’s serial number, which will be used for identification at a repair center.

7.4.3 All test and measuring points shall be clearly labeled with same designations as those used in technical manuals.

7.4.4 The equipment shall be marked at relevant locations with warning signs against hazardous voltages and harmful laser radiation.

7.5 ELECTROSTATIC DISCHARGE REQUIREMENTThe system shall, without permanent damage or degradation of performance, withstand static discharge according to relevant ITU-T K series recommendation. The method and procedure to test the requirement be mentioned.

7.6 SUSCEBTIBILITY TO ELECTROMAGNETIC RADIATION REQUIREMENT

The system shall without degradation of performance, withstand the effects of an external electrostatic field according to relevant ITU-T K series recommendations. The method and procedure to test the requirement be mentioned.

7.7 SURGE PROTECTION REQUIREMENT

51

A fully equipped terminal sub-rack shall withstand, without permanent damage, the surges applied to all electrical inputs and outputs, according to relevant ITU-T K series recommendations. The method and procedure to test the requirement be mentioned.

7.8 TECHNOLOGICAL REQUIREMENT7.8.1 Only first grade components shall be used and no component shall be operated at or above the manufacturer’s rated maximum value.

7.8.2 All wire and cable insulation shall be of plastic type. The materials used shall be of ozone resistance quality and shall not deteriorate in the specified environment.

7.8.3 Organic materials liable to attack by fungus or mould shall be avoided. If their use is unavoidable, they shall be suitably treated.

7.8.4 No materials shall be used which will produce gases having harmful effect on contacts or personnel.

7.8.5 When one component with similar specifications replaces any component, the equipment shall still meet its specified performance.

7.9 RELIABILITY AND AVAILIBILTY REQUIREMENT7.9.1 The ‘Equipment Supplier’ shall submit, Mean Time Between Failure (MTBF) figures for the offered system and modules.

7.9.2 The method of derivation of these figures shall be explained and it shall be highlighted whether the derivation is based on past usage or mathematical model only.

7.9.3 The ‘Equipment Supplier’ shall submit a detailed calculation of availability for the proposed system. The tributary units of the input and output ADM’s of the traffic path may be taken as reference.

7.10 TEST AND MEASURING FACILITIES REQUIREMENT

7.10.1 In addition to the test and measuring features of NMS / LCT, it is preferable to have test & measuring ports in the system to measure performance parameters of each optical channel without interrupting the services (such as connecting spectrum analyzer to monitor optical signal).

7.10.2 Testing facilities for the sub-equipment / modules shall be incorporated without removing it from sub-rack.

7.11 ALARMS REQUIREMENT

7.11.1 The line terminal equipment shall contain at least the alarms as given in ITU-T Rec. G.958.

7.11.2 The offered equipment and systems shall be fitted with the necessary alarms to indicate changes in equipment or system status.

7.11.3 It shall be possible to simply define any alarm into “Urgent” or “Non-Urgent” or “Not applicable” (or equivalent) categories. The ‘Equipment Supplier’ shall state how this is achieved in the offered equipment.

7.11.4 The alarms for equipment fault and transmission-originated fault shall be clearly distinguishable.

7.11.5 Transmission alarms shall clearly indicate which system and which direction of transmission is affected.

52

7.11.6 Facilities shall be provided to suppress any alarm. When these facilities are operative, visual indication such as “Attention” shall be given.

7.11.7 Any local operation of switches or controls in a station, which causes the equipment to operate in an abnormal manner, shall cause a prominent visual indicator. This shall be illuminated until the station is restored to normal operating conditions.

7.11.8 The rack alarm shall be clearly visible to maintenance staff and have urgent, non-urgent, attention and remote (or equivalent) alarm indications.

7.11.9 Alarm Indication Signal (AIS), in compliance with relevant ITU-T Rec. such as G.703 shall be automatically inserted in the digital transmission path in the event of the fault. This is to prevent unnecessary alarm indications on equipment or stations down-stream from the fault.

7.12 PROTECTION REQUIREMENT AGAINST ACCIDENTALCONDITIONS

7.12.1 Power supply units shall be provided with an arrangement for protecting them from damage in case of overheating.

7.12.2 Protection circuits shall not cause false tripping. The equipment to be protected and the protection device shall be designed in such a way that there is a suitable margin between the normal working condition and the tripping condition, including any switching transient.

7.12.3 If any semiconductor is liable to be damaged due to mismatch, loosening of an interconnecting cable & plug-in unit removal etc. then the connectors shall have an easily visible warning sign, marked with a special color.

7.12.4 If a signal overload has caused protection circuits to operate, these circuits shall automatically be restored when the signal level is reduced to its normal value. The equipment shall thereafter continue to operate properly without any re-adjustment.

7.12.5 The equipment shall not be damaged by the battery voltage slowly decreasing to zero.

7.12.6 The ‘Equipment Supplier’ shall provide over-voltage-protection of semiconductors, used in the power supply unit.

7.12.7 It shall not be possible to insert a plug-in unit in an incorrect position, such that damage would occur to the unit or to the equipment

7.12.8 The insertion or removal of a unit while power is switched on to the equipment shall not cause any damage to the unit or equipment.

7.13 POWER SUPPLY REQUIREMENT

7.13.1 The requirement of the power for all equipment shall be as follows:

7.13.1.1 DC Power Requirement : -48 V DC to -60 V DC

7.13.2 The equipment shall maintain its guaranteed performance when the power input to the equipment varies from:

7.13.1.2 Variation in power input : -40 V to -75 V DC.

7.13.3 The ‘Equipment Supplier’ shall supply one Power Distribution Box (MCB Box) for each station. Power cable sufficient enough to terminate from central DC power distribution to the equipment shall also be supplied.

7.13.4 Each power supply unit of the equipment shall be fitted with automatic circuit breaker.

53

7.13.5 Under fault conditions a visual alarm shall be displayed on the front panel of the power unit.

7.13.6 The ‘Equipment Supplier’ shall state critical parameters, defining the level of performance degradation that may be expected.

7.13.7 Hazardous voltages (more than 75 V) shall be specially identified and separated from voltages below 75 V. The ‘Equipment Supplier’ shall indicate if such hazardous voltages exist in the offered equipment.

7.13.8 The DC – DC converter should be in twin form and distribution of power supply should inherently guarantee protection against single conductor failure.

7.13.9 Maximum power dissipation for NE shall be indicated.

7.14 ACOUSTIC NOISE AND ELECTROMAGNETICRADIATION REQUIREMENT

7.14.1 The acoustic noise generated from the equipment shall be such that the radiated sound power from the equipment shall not exceed: 60 DBA.

7.14.2 If the noise is of the impulse type, or contains audible tones, then, the radiated sound power from the equipment shall not exceed: 50 DBA.

7.14.3 The offered equipment shall be designed with sufficient screening, so that any electromagnetic radiation will have no adverse effect on any co-located equipment.

7.14.4 Under conditions where the equipment is operated temporarily with doors open & covers removed, no condition shall be created which may cause any hazard to staff through radio frequency emission, laser emitted light etc.

-- End of Chapter Seven --

PART THREE

54

GLOSSARY

Term Description

Absorption That portions of optical attenuation in optical fiber that results from converting optical power to heat. One cause of absorption is the impurities introduced in the fiber manufacturing process.

ADM

Add/drop multiplexer. Digital equipment that provides an interface between higher and lower rate signals. A SONET ADM is capable of extracting or inserting lower rate signals from a higher rate multiplexed signal without demultiplexing the entire signal.

Alternate Mark Inversion (AMI)

The line-coding format in transmission systems where successive ones (marks) are alternatively inverted (sent with polarity opposite that of the preceding mark)

American National Standards Institute (ANSI)

A membership organization that develops U.S. industry standards and coordinates U.S. participation in the International Standards Organization (ISO)

APS

Automatic Protection Switching. A switching mechanism that routes traffic from working lines to protect them from component failure or fiber cut. Automatic Protection Switching (APS) was standardized in SONET Phase II.

Asynchronous Transmission

Transmission of digital signals without a precise clock signal.

Asynchronous Transfer Mode (ATM)

International standard for cell relay in which multiple service types (such as voice, video, or data) are conveyed in fixed-length (53-byte) cells. Fixed-length cells allow cell processing to occur in hardware, thereby reducing transit delays. ATM is designed to take advantage of high-speed transmission technologies such as SONET.

55

8CHAPTER

Term Description

Attenuation

The decrease in signal strength along a fiber optic waveguide. Attenuation is caused by a combination of absorption and scattering and is usually expressed in decibels per kilometer (dB/km).

Backbone

The primary path in a network used for transporting traffic between network segments. Backbone can also refer to the physical connection or group of connections that forms a major transport pathway.

Bandwidth (BW)Information-carrying capacity of a communication channel; analog bandwidth is the range of signal frequencies that can be transmitted by a communication channel or network

Bit error rate (BER) The fraction of bits transmitted that are received incorrectly.

BidirectionalOperating in both directions; bidirectional APS allows protection switching to be initiated by either end of the line

Bit Error vs. Block Error

Error rate statistics play a key role in measuring the performance of a network; as errors increase, user payload (especially data) must be retransmitted; the end effect is creation of more (non-revenue)

Bit Interleaved Parity–8 (BIP–8)

A method of error checking in SONET that allows a full set of performance statistics to be generated; for example, a BIP–8 creates eight-bit (one-byte) groups, then does a parity check for each o

Bit StuffingIn asynchronous systems, a technique used to synchronize asynchronous signals to a common rate before multiplexing

Bit Synchronous

A way of mapping payload into VTs that synchronizes all inputs into the VTs, but does not capture any framing information or allow access to subrate channels carried in each input; for example, bit sy

Bits Per Second (BPS)The number of bits passing a point every second; the transmission rate for digital information

Bidirectional Line Switched Ring (BLSR)

A scheme used in SONET rings in which traffic is sent on both rings in opposite directions. If a fault occurs, all traffic switches over to use the other side of the ring. BLSR can also be implemented with four fibers, providing full redundancy.

56

Term Description

Bragg Grating

A technique for building optical filtering functions directly into a piece of optical fiber based on interferometric techniques. Regions of higher and lower refractive indices in the fiber core are formed by exposing photosensitive fiber to deep UV light through a mask.

Broadband

A method of data transmission in which multiple signals share the bandwidth of a high-frequency carrier. Cable television, for example, uses broadband techniques to deliver many channels over one cable.

Services requiring 50–600 Mbps transport capacity

Broadband Integrated Services Digital network (BISDN)

A single ISDN that can handle voice, data, and eventually video services

Byte interleavedBytes from each STS–1 are placed in sequence in a multiplexed or concatenated STS–N signal; for example, for an STS–3, the sequence of bytes from contributing STS–1s is 1, 2, 3, 1,

Byte synchronous

A way of mapping payload into VTs that synchronizes all inputs into the VTs, captures framing information, and allows access to subrate channels carried in each input; for example, byte synchronous ma

Cable Used in reference to optical fibers, cable denotes one or more optical fibers enclosed within protective covering(s) and strength members.

Capacity

A measure of the amount of information a telecommunications facility can carry or process. For transmission lines, capacity is usually expressed in bits per second. For a device such as a switch, capacity might be expressed as the number of calls it can process or the aggregate bandwidth of the backplane.

Carrier A company that provides a communications circuit. Carriers are either public, such as AT&T and Sprint, or private.

CATV

Though this acronym correctly refers to community antenna television, it is commonly used to refer to cable TV. CATV is a television distribution method that receives, amplifies, and retransmits signals from different sources by coaxial, fiber cable, or microwave to subscribers.

57

Term Description

CCITT

The technical organs of the United Nations specialized agency for telecommunications, now the International Telecommunications Union–Telecommunications; they function through international commit

Center Wavelength Wavelength measured at the central point of a laser's effective optical power.

Channel

A communications path or the signal sent over that path. Using multiplexing, several channels can be transmitted over a single medium (copper or fiber). In wavelength division multiplexing (WDM) technology, a channel is assigned to a specific wavelength, or lambda.

Chromatic Dispersion A property of optical fiber whereby different wavelengths in an optical pulse travel at different speeds and arrive at different times, resulting in a smearing of the received signal.

CircuitA communications path or network; usually a pair of channels providing bidirectional communication

Circuit SwitchingBasic switching process whereby a circuit between two users is opened on demand and maintained for their exclusive use for the duration of the transmission

Cladding Material that surrounds the core of an optical fiber. The cladding has a lower index of refraction than the core and causes the transmitted light to travel down the core.

Competitive local exchange carrier (CLEC)

A local service provider, formerly a telephone company, that competes against incumbent local exchange carriers.

CO Central office. A common carrier switching center housing equipment that terminates users' lines.

Coating Protective material that surrounds the cladding of an optical fiber.

Coaxial Cable A medium used for electrical transmission composed of an insulated central conducting wire wrapped in another cylindrical conducting wire.

Coding Violation (CV)A transmission error detected by the difference between the transmitted and the locally calculated bit-interleaved parity

58

Term Description

ConcatenateThe linking together of various data structures—for example, two bandwidths joined to form a single bandwidth

Core The light-conducting central portion of an optical fiber. The core has a higher index of refraction than the cladding.

critical angle When traveling from an optically denser to optically less dense material, the angle of incidence at which light stops being refracted and is totally reflected.

Cyclic Redundancy Check (CRC)

A technique for using overhead bits to detect transmission errors

dark fiber An inactive optical fiber. Typically when fiber is laid some initially remains dark, or in reserve, for future use.

Data Communications Channels (DCC)

OAM&P channels in SONET that enable communications between intelligent controllers and individual network nodes as well as inter-node communications

Decibel (dB) Decibel. A logarithmic scale used as a measure of relative power. In optical signal transmission, attenuation (loss) is expressed as dB/km.

DefectA limited interruption in the ability of an item to perform a required function

Demultiplexing (DEMUX)

A process applied to a multiplex signal for recovering signals combined within it and for restoring the distinct individual channels of the signals

Distributed feedback laser (DFB)

An injection laser diode constructed with a Bragg reflection grating outside the active region to suppress multiple longitudinal modes and enhance a single longitudinal mode.

Dichromatic Filter An optical filter that transmits light according to wavelength; light that is not transmitted is reflected.

Dielectric A nonconducting or insulating substance that resists passage of electric current.

Diffraction Grating

A ray of fine, parallel equally spaced reflecting or transmitting lines that mutually enhance the effects of diffraction to concentrate the diffracted light in specific directions determined by the spacing of the lines and by the wavelength of the light.

59

Term Description

Digital Cross-Connect system (DCS)

An electronic cross-connect that has access to lower-rate channels in higher-rate multiplexed signals and can electronically rearrange (cross-connect) those channels

Digital SignalAn electrical or optical signal that varies in discrete steps; electrical signals are coded as voltages; optical signals are coded as pulses of light

Diode An electronic device that conducts electricity in one direction only. The simplest semiconductor devices are diodes.

Dispersion The temporal spreading of a light signal caused by light signals traveling at different speeds through an optical waveguide. Dispersion can be caused by modal or chromatic effects.

Dispersion-shifted fiber (DSF)

A type of single-mode fiber designed to have zero dispersion in the 1550-nm region. DSF works poorly for DWDM applications because of high nonlinearities at the zero dispersion point.

Digital Subscriber Line (DSL)

Public network technology that delivers high bandwidth over conventional copper wiring at limited distances.

Dense Wavelength Division Multiplexing (DWDM)

The transmission of multiple signals over closely spaced wavelengths in the 1550-nm region on a single fiber or fiber pair. See also WDM.

Erbium-Doped Fiber Amplifier (EDFA)

A device used to amplify optical signals. EDFAs, unlike regenerators, do not convert the signal back to electric before boosting it. In an EDFA, optical fibers are doped with the rare earth element erbium, which can amplify light in the 1550-nm region when pumped by an external laser. See also optical amplifier.

Enterprise System Connection (ESCON)

An IBM protocol used to link mainframes with peripherals and other mainframes at 11 to 17 MBps over fiber optic cable.

Ethernet

Baseband LAN specification invented by Xerox Corporation and developed jointly by Xerox, Intel, and Digital Equipment Corporation. Ethernet networks use CSMA/CD and run over a variety of cable types at 11 Mbps. The IEEE 802.3 series of standards is very similar. See also Fast Ethernet; Gigabit Ethernet.

60

Term Description

European Conference of Postal and Telecommunications Administrations (CEPT)

The CEPT format defines the 2.048–Mbps European E1 signal made up of 32 voice-frequency channels

Exchange Carrier Standards Association (ECSA)

An organization that specifies telecommunications standards for ANSI

FailureA termination of the ability of an item to perform a required function; a failure is caused by the persistence of a defect

Far End Block Error (FEBE)

A message sent back upstream that receiving network element is detecting errors, usually a coding violation

Far End Receive Failure (FERF)

A signal to indicate to the transmit site that a failure has occurred at the receive site

Fiber Distributed Data Interface (FDDI)

LAN standard, defined by ANSI X3T9.5, specifying a 110-Mbps token-passing network using fiber-optic cable, with transmission distances up to 2 km. FDDI uses a dual-ring architecture to provide redundancy.

Fast Ethernet (FE)

Based on an extension to the IEEE 802.3 specification, Fast Ethernet offers a speed of 110 Mbps over Cat-3 or UTP. It preserves many of the attributes of Ethernet, including frame format, MAC mechanisms, and MTU. See also Ethernet.

Fiber-Optic Cable A data transmission medium that uses glass or plastic fibers, rather than copper wire, to carry modulated pulses of light; also called optical fiber.

Fiber Channel

A technology for transmitting data between computer devices at data rates from 110 to 400 MBps over optical fiber or copper. Fiber channel is optimized for connecting servers to shared storage devices and for interconnecting storage controllers and drives.

Filter An arrangement of electronic components designed to pass signals in one or more frequency bands while attenuating signals in other frequency bands.

Fixed StuffA bit or byte whose function is reserved; fixed-stuff locations, sometimes called reserved locations, do not carry overhead or payload

61

Term Description

Floating Mode

A VT mode that allows the VT synchronous payload envelope to begin anywhere in the VT; pointers identify the starting location of the VT SPE; VT SPEs in different super-frames may begin at different lo

FramingMethod of distinguishing digital channels that have been multiplexed together

Frequency

The number of cycles of periodic activity that occur in a discrete amount of time.

The number of cycles per unit of time, denoted by Hertz (Hz). One Hz equals one cycle per second.

Four-Wave Miixing (FWM)

A nonlinearity that occurs in DWDM systems when multiple wavelengths mix together to form new wavelengths. Four-wave mixing is most prevalent near the zero-dispersion point and at close wavelength spacings.

Gigabit Ethernet (GE)

Standardized in IEEE 802.3z, Gigabit Ethernet (GE) is a backbone LAN technology offering data speeds up to 1100 Mbps. GE can use either a shared or switched medium. See also Ethernet.

Graded-Index Fiber Optical fiber in which the refractive index of the core decreases toward the cladding.

Grooming Consolidating or segregating traffic for efficiency

Hz Hertz (cycles per second).

Incumbent Local Exchange Carrier(ILEC)

Term used to describe the primary existing carriers, formerly known as Regional Bell Operating Companies (RBOCs); distinguished from new competitive carriers coming out of deregulation of the telecommunications industry.

Index Of Refraction The ratio of the velocity of light in free space to the velocity of light in a material. See also refractive index.

Insertion Loss The loss of power that results from inserting a component, such as a connector or splice, into a previously continuous path.

InterleaveThe ability of SONET to mix together and transport different types of input signals in an efficient manner, thus allowing higher transmission rates

62

Term Description

Internet protocol (IP)

Internet Protocol. Defined in RFC 791, the Internet Protocol (IP) is a network layer protocol in the TCP/IP stack offering a connectionless internetwork service. IP provides features for addressing, type-of-services specification, fragmentation and reassembly, and security.

A component of protocol for many computer links including the Internet

Intermediate reach(IR) Distance specification for optical systems that operate effectively from 3 to 20 km.

International Organization for Standardization (ISO)

International organization that is responsible for a wide range of standards, including those relevant to networking. ISO developed the OSI reference model.

IsochronousAll devices in the network derive their timing signal directly or indirectly from the same primary reference clock

International Telecommunication Union (ITU)

A specialized agency of the United Nations for telecommunications. The International Telecommunication Union Standardization Sector (ITU-T) is the successor to the CCITT (Consultative Committee for International Telegraph and Telephone).

ITU Grid ITU standard wavelength designation for lasers. It is based on 100 GHz spacing of optical frequency, with a center frequency of 193.1 THz (1552.52 nm).

Interexchange Carrier (IXC)

A long distance telecommunications carrier that offers a range of circuit switched, packet switched, leased line, and enhanced communications services; any provider of communications services between exchanges on a long-haul basis.

Jitter Small and rapid variations in the timing of a signal or waveform due to noise, changes in component characteristics, voltages, circuit synchronization, and so on.

lambda A data channel in a WDM or DWDM system assigned to a specific wavelength. Lambda and wavelength are sometimes used interchangeably.

Local Area Network (LAN)

A high-speed, low-error data network covering a relatively small geographic area. Ethernet, FDDI, and Token Ring are widely used LAN technologies. See also MAN; WAN.

63

Term Description

Laser Originally an acronym for light amplification by stimulated emission of radiation, laser is a light source that produces coherent, near monochromatic light.

Laser Diode A semiconductor device that emits coherent light when forward biased.

Local Exchange Carrier (LEC)

A local provider of primarily voice services to business and residential customers. A LEC provides intra-LATA (local access transport area) telecommunications services.

Light Emitting Diode (LED)

A semiconductor device that accepts electrical input and converts them to a signal in the form of incoherent light.

LineOne or more SONET sections, including network elements at each end, capable of accessing, generating, and processing line overhead

Line Alarm Indication Signal (AIS–L)

AIS–L is generated by section terminating equipment (STE) upon the detection of a loss of signal or loss of frame defect, on an equipment failure; AIS–L maintains operation of the downstream

Line Overhead (LOH)

18 bytes of overhead accessed, generated, and processed by line terminating equipment; this overhead supports functions such as locating the SPE in the frame, multiplexing or concatenating signals, performance monitoring, automatic protection switching and line maintenance.

Line Remote Defect Indication (RDI–L)

A signal returned to the transmitting line terminating equipment (LTE) upon detecting a loss of signal, loss of frame, or AIS–L defect; RDI–L was previously known as line FERF

Line Terminating Equipment (LTE)

Network elements such as add/drop multiplexers or digital cross-connect systems that can access, generate, and process line overhead

locked modeA VT mode that fixes the starting location of the VT SPE; locked mode has less pointer processing than floating mode

Loss Budget The amount of overall attenuation allowable in a system.

LR Long reach. Distance specification for optical systems that operate effectively from 20 to 110 km.

64

Term Description

MAN

Metropolitan area network. A network that covers an area larger than a LAN, usually a metropolitan area. MANs exist between and interconnect the long-haul and access segments of the global network. See also LAN; WAN.

MappingThe process of associating each bit transmitted by a service into the SONE/TSDH payload structure that carries the service.

Material Dispersion Dispersion resulting from the different velocities of each wavelength in a fiber medium.

MesochronousA network whereby all nodes are timed to a single clock source; thus, all timing is exactly the same (truly synchronous)

MM Fiber Multimode fiber. An optical fiber in which the core is large enough to propagate more than one mode of light. See also single-mode fiber.

Modal Dispersion Dispersion caused by the different transit lengths of different propagating modes in a multimode fiber and resulting in different arrival times. Also called multimode dispersion.

Modulation

The process of varying some characteristic of a carrier wave as the information to be transmitted on that carrier wave varies. Examples include amplitude modulation (AM), frequency modulation (FM), and pulse-coded modulation (PCM).

MPLS

MultiProtocol Label Switching. A set of IETF standards designed to allow packet flows to be switched on the basis of labels instead of the full destination address. MPLS is based on the concept of routing at the edge and switching in the core.

MTBF

Mean time between failure. Time at which 50% of the units of interest will have failed; used as a measure of the time a user might reasonably expect a device or system to work before a fault occurs.

Narrowband services requiring up to 1.5–Mbps transport capacity

Network attached storage (NAS)

Central data storage system that is attached to the network that it serves. See also SAN.

Non-dispersion-shifted fiber (NDSF)

A type of single-mode fiber designed to have zero dispersion in the 1311-nm region.

65

Term Description

Network Node Interface (NNI)

A defined interface between nodes in the public network

NonlinearityDeviation from linearity in an electronic circuit, electro-optic device, or fiber, that generates undesired components in a signal.

Non-zero dispersion-shifted fiber (NZ-DSF)

A dispersion-shifted SM fiber that has the zero dispersion point near the 1550-nm window, but outside the actual window used to transmit signals. NZ-DSF is designed to maximize bandwidth while minimizing fiber nonlinearities.

Optical amplifier (OA) A device that amplifies an input optical signal without converting it to electrical form. See also EDFA.

Optical add/drop multiplexer (OADM)

A multiplexer used in optical networks that can add and drop wavelengths into and out of an optical signal without converting it back to electrical form.

Optical Carrier (OC) A series of physical protocols (such as OC-1, OC-3, OC-12) defined for SONET optical signal transmission.

Operations System (OS)Sophisticated applications software that overlooks the entire network

Operations, Administration, Maintenance, and Provisioning (OA&M or OAM&P)

Provides the facilities and personnel required to manage a network

Optical Channel Spacing The separation, usually expressed as a frequency, between wavelengths of adjacent WDM or DWDM channels.

Optical Link Loss Budget

The range of optical loss over which a fiber optic link will operate and meet all specifications, expressed relative to the transmitter output power.

Order-wireA channel used by installers to expedite the provisioning of lines

OSI seven-layer model

A standard architecture for data communications; layers define hardware and software required for multi-vendor information-processing equipment to be mutually compatible; the seven layers from lowest t

66

Term Description

Optical time domain reflectometer (OTDR)

An instrument used in design and diagnostics that locates faults or infers attenuation in optical networks.

OverheadExtra bits in a digital stream used to carry information besides traffic signals; order-wire, for example, would be considered overhead information

Packet SwitchingAn efficient method for breaking down and handling high-volume traffic in a network; a transmission technique that segments and routes information into discrete units.

Parity Check

An error-checking scheme that examines the number of transmitted bits in a block that hold the value one; for even parity, an overhead parity bit is set to either one or zero to make the total number

PathA logical connection between a point where an STS or VT is multiplexed to the point where it is demultiplexed

Path Overhead (POH) A group of management communications facilities in SDH

Path Terminating Equipment (PTE)

Network elements, such as fiber-optic terminating systems, which can access, generate, and process POH

PayloadThe portion of the SDH signal available to carry service signals such as E1 and E3.

Payload PointerIndicates the beginning of the synchronous payload envelope (SPE)

Plesiochronous Digital Hierarchy (PDH)

Asynchronous multiplexing scheme in which multiple digital synchronous circuits run at different clock rates. See also SDH.

Photo Detector An optoelectronic transducer such as a PIN photodiode or avalanche photodiode.

Photodiode A semiconductor device that converts light to electrical current.

PhotonThe basic unit of light transmission used to define the lowest (physical) layer in the OSI seven-layer model

A quantum of electromagnetic energy; a particle of light.

Photonic A term used to describe communications using photons, analogous to electronic for electronic communications.

67

Term Description

Physical Layer First layer of the OSI reference model. All-optical technologies such as DWDM work at the physical layer.

PlesiochronousA network with nodes timed by separate clock sources with almost the same timing

Plesiochronous digital Hierarchy

The widely deployed transmission system which predates SDH

Polarization mode dispersion (PMD)

An inherent property of optical media, caused by the difference in the propagation velocities of light in the orthogonal principal polarization states of the transmission medium.

Point of Presence (POP)A point in the network where inter-exchange carrier facilities like DS–3 or OC–N meet with access facilities managed by telephone companies or other service providers

PointerA part of the SONET/SDH overhead that locates a floating payload structure.

PollAn individual control message from a central controller to an individual station on a multipoint network inviting that station to send

Packet over SONET (POS)

A technology in which IP packets are mapped into SONET frames with intervening use of an ATM layer.

Protocol Transparency Ability of systems to transport information without being aware of higher layer protocols. Such systems are also sometimes called protocol agnostic.

Public switched telephone network (PSTN)

Generic term for the collection of networks that provide public telephone switching service.

Rayleigh scattering The scattering of light that results from small inhomogeneities of material density or composition.

Receiver

A device at the destination end that includes a detector and signal processing electronics to perform optical-to-electrical conversion. A receiver has a maximum acceptable value of average received power (receiver overload) and a minimum acceptable value of received power (receiver sensitivity).

Refraction The changing of direction of a wavefront as it passes through a boundary between two dissimilar media.

68

Term Description

Refractive Index A property of optical materials that relates to the speed of light in the material. See also index of refraction.

Regenerator

A device that regenerates optical signals by converting incoming optical pulses to electrical pulses, cleaning up the electrical signal to eliminate noise, and reconverting them to optical pulses for output; also called a regenerative repeater.

Device that restores a degraded digital signal for continued transmission; also called a repeater

Remote Alarm Indication (RAI)

A code sent upstream in a DS–n network as a notification that a failure condition has been declared downstream; RAI signals were previously referred to as yellow signals

Remote Defect Indication (RDI)

A signal returned to the transmitting terminating equipment upon detecting a loss of signal, loss of frame, or AIS defect; RDI was previously known as FERF

Remote Error Indication (REI)

An indication returned to a transmitting node (source) that an errored block has been detected at the receiving node (sink); this indication was formerly known as far end block error (FEBE)

Remote Failure Indication (RFI)

A failure is a defect that persists beyond the maximum time allocated to the transmission system protection mechanisms; when this situation occurs, an RFI is sent to the far end and will initiate a pr

Storage area network (SAN)

A dedicated, centrally managed, secure information infrastructure that enables any-to-any interconnection of servers and storage systems. See also NAS.

Synchronous Digital hierarchy (SDH)

Synchronous Digital Hierarchy. European standard that defines a rate and format standards for transmission of optical signals over fiber using ATM and SONET. In contrast to PDH, SDH provides for a synchronous multiplexing scheme. See also PDH; SONET.

Section

The span between two SDH network elements capable of accessing, generating, and processing only SDH section overhead; this is the lowest layer of the SDH protocol stack with overhead

69

Term Description

Section Overhead

Nine bytes of overhead accessed, generated, and processed by section terminating equipment; this overhead supports functions such as framing the signal and performance monitoring.

A group of management communications facilities in SDH.

Section Terminating Equipment (STE)

Equipment that terminates the SDH section layer; STE interprets and modifies or creates the section overhead

SlipAn overflow (deletion) or underflow (repetition) of one frame of a signal in a receiving buffer

Single-mode fiber (SMF)A small-core optical fiber through which only one mode can propagate. See also multimode fiber.

Signal-to-noise ratio (SNR)

A measure of signal quality as the ratio of the total signal to the total noise. This effectively shows how much higher the signal level is than the noise level.

Synchronous Optical Network (SONET)

Synchronous Optical Network. An interface standard developed by Bellcore and widely used by the telecommunications industry for high-speed synchronous transport over optical fiber. See also SDH.

Short reach (SR) Distance specification for optical systems that operate effectively up to 3 km.

Step-Index Fiber Fiber that has a uniform index of refraction throughout the core.

Stratum Level of clock source used to categorize accuracy

Synchronous Transfer Module (STM)

An element of the SDH transmission hierarchy; STM–1 is SDH's base-level transmission rate equal to 155 Mbps; higher rates of STM–4, STM–16, and STM–48 are also defined

Synchronous Transport Signal Level 1 (STS–1)

The basic SONET building block signal transmitted at 51.84–Mbps data rate

T-Carrier

Generic designator for any of several digitally multiplexed telecommunications carrier systems. The two most common are T1, which transmits DS-1 formatted data at 1.544 Mbps, and T3, which transmits DS-3 formatted data at 44.736 Mbps.

70

Term Description

Time-Division Multiplexing (TDM)

Technique in which information from multiple channels can be allocated bandwidth on a single transmission medium based on assigned time slots. SONET is a TDM technology.

Transponder In a DWDM system, a module that receives an input signal and converts that signal to a wavelength to be optically multiplexed with other wavelengths.

Tributary Unit (TU)The basic unit of payload together with its management overheads and synchronization data

Unidirectional Path Switched Ring (UPSR)

A scheme used in SONET rings in which traffic is sent on one of the two rings and in one direction. The second ring is reserved for redundancy.

User-Network Interface (UNI)

A defined interface between the user and the public network

Virtual Container (VC)The basic unit of payload together with its management overheads

Wide Area Network (WAN)

A physical or logical network that serves users across a broad geographic area and often uses transmission devices provided by common carriers. See also LAN; MAN.

Wander Long-term variations in a waveform

Waveguide A material medium that confines and guides a propagating electromagnetic wave. An optical fiber is an example of a waveguide.

Waveguide Dispersion

A component of chromatic dispersion that occurs because of the different refractive indices of the core and the cladding of fiber, resulting in a propagation delay in one or more of the wavelengths relative to others.

Wavelength The distance between points of corresponding phase of two consecutive cycles of a wave. In DWDM systems, wavelength is often used interchangeably with lambda.

Wavelength Division Multiplexing (WDM)

The transmission of two or more signals over (relatively) widely spaced wavelengths, typically at 850 and 1311 nm or 1533 and 1577 nm, on a single fiber or fiber pair. See also DWDM.

Wideband Services requiring 1.5– to 50–Mbps transport capacity

71

12.2 Frequently Used Terminologies

Abbreviation Description

ADM Add/Drop Multiplexer

ALS Automatic Laser Shutdown

ANSI American National Standards Institute

APS Automatic Protection Switching

ATM Asynchronous Transfer Mode

AU Administrative Unit

AUG Administrative Unit Group

BER Bit Error Ratio

BISDN Broadband Integrated Services Digital Network

BLSR Bidirectional Self Healing Ring

BML Business Management Layer

BPON Broadband PON

CCITT Comité Consultif International Telegraphique Et Telephonique

CD Chromatic Dispersion

CMI Coded Mark Inversion

CMIP Common Management Information Protocol

CNR Carrier-To-Noise Ratio

CORBA Common Request Broker Architecture

CSO Composite Second-Order Distortion

DBA Dynamic Bandwidth Allocation

DCC Data Communications Channel

DCF Dispersion Compensating Fiber

DCN Data Communication Network

DCS Digital Cross-Connect

72

Abbreviation Description

DNI Dual Node Interconnection

DRA Distributed Raman Amplifier

DSF Dispersion Shifted Fiber

DSL Digital Subscriber Line

DWDM Dense Wavelength Division Multiplexing

DXC Digital Cross-Connect

ECC Embedded Communication Channel

EDF Erbium-Doped Fiber

EDFA Erbium-Doped Fiber Amplifier

EML Element Management Layer

EMS Equipment Management System

EOS Ethernet Over SDH

EOW Engineering Order-Wire

EPON Ethernet PON

ETSI European Telecommunications Standards Institute

FBG Fiber Bragg Grating

FDM Frequency Division Multiplexing

FTTC Fiber To the Curb

FTTH Fiber To The Home

FWM Four Wave Mixing

GFP Generic Framing Procedure

GMPLS Generalized MPLS

GUI Graphical User Interface

HO Higher Order

IEC Inter Exchange Carrier

IP Internet Protocol

IR Intermediate Reach

ITU–T International Telecommunications Union

IVD Inside Vapor Deposition

L Long Haul

LAN Local-Area Network; A Linked Group Of Computers

LAPD Link Access Procedure on D-channel

LCAS Link Capacity Adjustment Scheme

73

Abbreviation Description

LCT Local Craft Terminal

LEC Local Exchange Carrier

LO Lower Order

LR Long Reach

MAC Media Access Control

MAN Metropolitan-Area Network

MCVD Modified Chemical Vapor Deposition

MFD Mode-Field Diameter

MPLS Multiple Protocol Label Switching

MSOH Multiplex Section Overhead

MSP Multiplex Section Protection

MS-SPRing Multiplex Section Shared Protection Ring

MUX Multiplexer

NE Network Element

NGS Next Generation SDH Network

NMS Network Management System

NNI Network Node Interface

NZDSF Nonzero Dispersion-Shifted Fiber

OADM Optical Add Drop Multiplexer

OAM&P Operations, Administration, Maintenance, And Provisioning

OC Optical Carrier

O-E-O Optical-Electrical-Optical

OLA Optical Line Amplifier

OLT Optical Line Termination

ONU Optical Network Unit

OPS Optical Packet Switching

OS Operating System

OSI Open System Interconnection

OSNR Optical Signal-To-Noise Ratio

OSPF Open Shortest Path First

OTN Optical Transport Network

OW Order-Wire

OWAD Optical Wavelength Add/Drop

74

Abbreviation Description

OXC Optical Cross-Connect

PABX Private Automatic Branch Exchange

PCM Pulse Code Modulation

PDH Plesiochronous Digital Hierarchy

PDL Polarization Dispersion Loss

PMD Polarization Mode Dispersion

POH Path Overhead

PON Passive Optical Network

POP Point Of Presence

PPP Point to Point Protocol

PTR Pointer

QoS Quality of Service

REG Regenerator

RFL Raman Fiber Lasers

RIP Routing Information Protocol

ROADM Reconfigurable OADM

RPR Resilient Packet Ring

RSOH Regenerator Section Overhead

S Short Haul

SDH Synchronous Digital Hierarchy

SMS SDH Management Sub-network

SNCP Sub-Network Connection Protection

SOA Semiconductor Optical Amplifier

SOH Section Overhead

SONET Synchronous Optical Network

SPE Synchronous Payload Envelope

SPM Self Phase Modulation

SR Short Reach

SRS Stimulated Raman Scattering

SSMF Standard Single Mode Fiber

STM Synchronous Transport Mode

STS Synchronous Transport Signal

TDM Time Division Multiplexing

75

Abbreviation Description

TM Terminal Multiplexer

TMN Telecommunication Management Network

TS Time Slot

TSI Time Slot Interchange

TTL Time To Live

TU Tributary Unit

TUG Tributary Unit Group

TUG Tributary Unit Group

U Ultra Long Haul

V Very Long Haul

VC Virtual Container

VPN Virtual Private Network

VR Very Long Reach

VT Virtual Tributary

WDM Wavelength Division Multiplexing

XPM Cross-Phase Modulation

76

CONCLUSION

9.1 Faced with the multifaceted challenges of increased service needs, explosive demand of bandwidth, fiber exhaust, and layered bandwidth management, etc - service providers have become desperate to weigh conflicting options. Enhanced bandwidth requirement has been further compounded with the integration of switching and transmission in optical communication networks. One way to alleviate fiber exhaust is to lay more fiber, and, for those networks where the cost of laying new fiber is minimal, this will prove the most economical solution. However, laying new fiber will not necessary enable the service provider to provide new services or utilize the bandwidth management capability of a unified optical layer. Beginning with DWDM system, under the cover of NTC’s infrastructure up gradation project, service provider can establish a grow-as-you-go infrastructure, which allows him to add current and next generation systems for virtually endless capacity expansion. Because a DWDM infrastructure can deliver the necessary capacity expansion, laying a foundation based on this technology is viewed as the best place to start. Making investment for the infrastructure Up-gradation, as a strategic partner, would therefore be coup de maitre.

77

9CHAPTER