ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 1 of 38
REQUEST FOR PROPOSAL
DESIGN, DEVELOPMENT, PROCUREMENT, SUPPLY, INTEGRATION, IMPLEMENTATION, OPERATION, MAINTENANCE, MANAGEMENT OF INTELLEGENT TRANSIT MANAGEMENT
SYSTEM (ITMS) FOR SURAT MUNICIPAL CORPORATION, SURAT ANSWER TO PRE-BID QUERIES AND CORRIGENDUM DOCUMENT -2
SEPTEMBER 2015
SURAT MUNICIPAL CORPORATION
GUJARAT. INDIA
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 2 of 38
SURAT MUNICIPAL CORPORATION
BRTS CELL
ANSWER TO PRE BID QUERIES AND CORRIGENDUM-2
Name of Work:- RFP for Design, Development, Procurement, Supply, Integration, Implementation, Operation, Maintenance
,Management of Intelligent Transit Management System (ITMS) for Surat Municipal Corporation, Surat
Reference:- Tender Notice (On line) No. City Engineer/BRTS/15/2015-16
Sub.:- Pre-bid points clarification and amendment/corrigendum if any.
Ref.:- Bidders posted their queries on E-mail address: [email protected]
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 3 of 38
Answer to Queries and Corrigendum if any Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
1. Tender Notice and
Point No 23 of Bid
Summary Section
D and Answer to
Pre Bid Queries
and Corrigendum
Document 1
(Answer to Query
no. 1)
Physical Submission of Bid comprising of ; (a) Eligibility and Qualification Submission (Technical Proposal). (b) Price Bid (c) RFP Document Fees. (d) EMD/Bid Documents Fees through Speed Post /RPAD
should be on or before
29/09/2015 upto 17:00hrs.
As arranging all the required documents and
collation of final is taking more time, we request
authority to extend the bid submission date by
at least 2-3 weeks.
The Bid Submission date is extended and hence relevant clauses specified in ender Notice and Point No 20, 23 and 24 of Bid Summary Section D stands revised as follows.
Start Date and Last Date of downloading of RFP Document
Starting Date of downloading : 03/08/2015 from website http://smc.nprocure.com Last Date for downloading of RFP Document: 07/10/2015 and Time: Upto 17:00 hrs.
Due Date of Bid Submission (the “Due Date of Submission”)
The Physical Hard copy of Technical Bid and Price Bid (i.e. Envelop 1, Envelope 2 and Envelope 3) should be submitted on or before 07/10/2015 by 17:00 hrs. at following address. The Chief Accountant’, Surat Municipal Corporation Main Office , Muglisara. Surat-395003, Gujarat, India” in sealed cover duly super scribed with name of work and tender notice no. By R.P.A.D./ Speed post only. Delivery through Hand delivery/ Courier shall not be accepted and Bids of such bidders shall not be taken in to evaluation and Summarily rejected.
Tentative Date and Time of Opening of Technical Bid
12:00 hrs on 08/10//2015 at followings Address: Office of Chief Fire Officer,
2. We confirm the receipt of “ANSWER TO PRE-BID
QUERIES AND CORRIGENDUM DOCUMENT”
and now actively working towards the bid
submission. Considering the major changes in the
Corrigendum document and the time required to
get the quotations from the OEMs for the revised
specifications, we request two [2] more week’s
extension from the current dead line.
3. We request extension for 3 more weeks
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 4 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
Ground Floor, Nr. Fire Station, Muglisara, Surat Municipal Corporation, Surat, Gujarat, India
4. point no 9 ( C) (a) & (b) of Bid Summary Section D answer to Pre Bid
Queries no 5.
Turnover Criteria for consortium
Here with we request to put generic clause (if suitable) in tender/clarification document to consider BRTS as an alternate to I.T business for Non-Lead member experience/turnover.
we request you to allow turnover of I.T sector OR BRTS project for eligibility for non-lead member.
General clarification of corrigendum 1 , point no.5 is also applied to point no.4 for Non-Lead member in case turnover.
5. Tender Notice ,
Point No 16 of Bid
Summary Section
D of RFP Part 1 ,
Answer to Pre Bid
Queries and
Corrigendum
Document -1
(Answer to Queries
no 25)
Bid Security/EMD EMD of 65 Lacs in the form
of BG issued by an
approved bank as per the list
provided in Appendix 6 .
Incase the Bank
Guarantee/Demand Draft is
issued by a foreign Bank
outside India, confirmation of
the same by an Approved
Bank of SMC is required.
As a Japanese MNC we bank with The Bank of
Tokyo Mitsubishi UFJ, New Delhi branch. This
comes under scheduled bank category as per
RBI. For EMD we plan to submit BG issued by
New Delhi branch of this bank which would be
encash able at New Delhi only. We don’t have
any arrangement with any of the bank in your
approved list. Therefore we request you to
please accept above BG as EMD & oblige. Look
forward to your positive response & confirmation
ASAP.
Clause 2.5 (b) of section E specifies that Incase the Bank Guarantee/Demand Draft is issued by a foreign Bank outside India, confirmation of the same by an Approved Bank of SMC is required. The Bank Guarantee should be encashable the in Surat branch of such Approved bank . No Change.
6. Annexure-2 ,
Section C of
Answer to Pre Bid
queries and
Corrigendum -1
Page no 46
Service Charges for O&M of
Control Center
Please clarify whether we need to provide call
centre operators also for 15 seater call centre in
this. If yes, we request authority to add a
separate line item with quantity for this cost so
that it is common & binding for all bidders.
Yes . Operation and Management of call center
is in scope of the Service Provider and included
under the line item (3) of Price Bid Format (c ) of
Annexure-2, Price Bid format. (of Answer to Pre
Bid and Corrigendum-1” Document) i.e
“Service Charges for Operation and
Management of Central Control Center”
Bidders are required to give complete break up
of all cost items including Call center operation
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 5 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
and management under the above line item (c ),
of Price Bid Format (c ) of Annexure-2.
First two lines (heading) of column 3 of Price
Bid Format (c ) of Annexure-2, of Answer to Pre
Bid queries and Corrigendum -1 is read and
replaced as follows.
“Quoted Annual Cost of O&M which the Bidder expects to receive from SMC during the Contract Period ( Amount in INR) “.
7. Annexure-2 ,
Section A of
Answer to Pre Bid
queries and
Corrigendum -1
Price Bid Format for
Hardware Units: City Bus
Shelter PIS Display Unit
(LED based) and
Communication units
General Clarification Pricing Format for Hardware
The Quantities of City Bus Shelters PIS Display
units and Communication units are changed as
follows;
“Point No 11 :
City Bus Shelter PIS Display Unit (LED based) quantities 800. Point No 12 :
Communication Unit for City Bus Shelters. Quantities 800.
8. Annexure-2 , Line
Item 4 of Section C
of Answer to Pre
Bid queries and
Corrigendum -1
Page no 46
Price Bid Format for O&M :
Communication Cost
General Clarification Bidder’s to quote for communication cost for
City Buses , BRT Bus stations, City Bus Shelters, Control Center, SMC Vehicles. Detailed break up of communication cost for each of above items shall be provided.
9. Clause no 10.3 (e) Tentative Phasing for General Clarification The table for Tentative Phasing for
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 6 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
of Draft Service
Provider
Agreement
implementation implementation for guidance of the Service
Provider provided in clause 10.3 (e) of Draft
Service Provider Agreement is revised and
placed in Annexure-1 of this document.
It may be emphasized that this phasing is
indicative and not binding.
10. Point No 2 of Bid
Summary Section
RFP Part-1 and
Answer to Pre Bid
queries and
Corrigendum -1
Location Details With reference to your response to pre bid queries and corrigendum, please provide the below information required for planning of connectivity and network infrastructure in the project.
List of 119 BRT Bus Stations Locations
List of 4 Depot Locations
The Location map and list are attached as
Annexure-2 of this document.
11. Annexure-2 ,
Section C of
Answer to Pre Bid
queries and
Corrigendum -1
Page no 46 and
Scope of Services
and Technical
Specification
Document -RFP
Part-2
Tracking Units Please provide detailed specifications of
Tracking Unit for SMC vehicles 535 units asked
in hardware price bid. It is not mentioned
anywhere in technical specifications document
in RFP.
Please refer specifications provided in clause
5.13.35 of RFP Part 2 document. The
Specifications of GPS based On-board unit for
City Bus is similar to tracking units for SMC
Vehicle.
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 7 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
12. Clause 5.3 , RFP
Part-2
Depot Management System Please confirm if fuel management system is also required in Depot Management System.
Yes
13. Clause 5.11.10 of
RFP Part-2
Helpdesk Management
Content of RFP requiring
Clarification
It must support remote
management for end-user &
allow analysts to do the
desktop sharing for any
system located anywhere,
just connected to internet.
Clarification required
Remote Management Support is typically
included in Desktop/Client Management
Solution. Including this spec in Helpdesk
favours one or two vendors who have this
feature bundled in Helpdesk. Remote desktop
Connection can also be done by RDP solution
bundled with Windows.
The specifications given in the document are
generic, bidders shall be required to provide
solution approach to meeting the end use
requirement.
14. Clause 5.11.11 of
RFP Part-2
Detailed Specifications for IT
Asset Management
Content of RFP requiring
Clarification
The proposed solution shall
provide inventory of
hardware and software
applications on end-user
desktops including
information on processor,
memory, operating system,
Clarification required
The Proposed solution should not limit inventory
to Desktops only. It should discover and keep
an inventory of desktop, laptops, servers,
network and any IP enabled device. To ensure
that all IT Environment is covered. The IT asset
Register should be comprehensive and should
not fous only on desktop. There are important
software’s installed on servers as well Inventory
solution should cover server environment as
well for hardware as well as software inventory
The inventory management is for all IT assets
within implementation.
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 8 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
mouse, key board of
desktops etc. through agents
installed on them.
15. Clause 5.11.11 of
RFP Part-2
Detailed Specifications for IT
Asset Management
Content of RFP requiring
Clarification
It shall provide Software
Inventory features.
Clarification required
Department should focus not just on Software
inventory but full Software compliance including
cost compliance as well
Agreed
16. Clause 5.11.11 of
RFP Part-2
End-User Experience
Management System
Content of RFP requiring
Clarification
The solution should be
deployable as an appliance-
based system acting as a
passive listener on the
network thus inducing zero
overhead on the network
and application layer.
Clarification required
Not all vendors have appliance based system.
However, will comply to requirement of passive
listener on the network. Request department to
remove appliance based system
Agreed
17. Clause 5.11.11 of
RFP Part-2
End-User Experience
Management System
Content of RFP requiring
Clarification
The proposed system must
Clarification required
Solution should provide capability to take error
snapshot as well as user session replay
Agreed.
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 9 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
be able to provide the ability
to detect and alert when
users experience HTTP
error codes such as 404
errors or errors coming from
the web application.
18.
Clause 5.11.9 of
RFP Part-2
Web-Application
Performance Monitoring
Content of RFP requiring
Clarification
The proposed solution must
support any combination of
operating platforms that
support JDKs higher than
1.2 or Application Server (or
.NET v1.1 and above) with a
single methodology.
Clarification required
Recent and relevant version of JDK and .Net
versions should be supported
Agreed
19.
Clause 5.11.9 of
RFP Part-2
Web-Application
Performance Monitoring
Content of RFP requiring
Clarification
The proposed solution must
provide a real-time
application topology map to
triage and quickly pinpoint
the component causing a
performance bottleneck in
Clarification required
Real time dependencies mapping
Example: Identify UDP based business critical
application dependencies
Transient dependencies detection
Example: Threshold based automated backup
These dependencies should also be used for
Agreed
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 10 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
the end-to-end transaction
flow.
event correlation in common dashboard
20.
Clause 5.11.12 of
RFP Part-2
Enterprise Network
Monitoring and Management
Solution – Other Key
Requirements
Content of RFP requiring
Clarification
The Solution should provide
all the modules to monitor
Networks, Servers and
Applications in the same
appliance.
Clarification required
This seems to favor a specific vendor as these
are very different applications covering different
domains and areas. This can lead to
performance and scalability issues. Hence,
these components are deployed separately
Appliance based removed
21.
Clause 5.11.11 of
RFP Part-2
Detailed Specifications for IT
Asset Management
Content of RFP requiring
Clarification
It shall support software
Package Creation using
Generic scripts. The
software delivery software
should provide a Wizard for
auto script builder.
Clarification required
Does this refer to only Desktop and laptops or it
covers Server Environment as well. These
activities are critical for Servers as well. Full
Server Automation can also save time, ensure
policy enforcement and improve compliance
All IT Assets.
22.
Clause 5.13.2 of
RFP Part-2
Non-Functional
Requirements
Content of RFP requiring
Clarification required
How to achieve scalability support. Should use
Scalability in terms of solution expansion should
be provided.
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 11 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
Clarification
Shall support scalability both
vertically (scale-up) and
horizontally (scale-out)
across architecture tiers.
some automation tool to exercise the activities.
Our Suggestions
The non functional activities should generate
reports for multiple architecture with detailed
ties wise. This should pin point the application
issues.
23.
Clause 5.13.2 of
RFP Part-2
Performance Requirements
Content of RFP requiring
Clarification
Shall deliver the project
providing measurable and
acceptable performance
targets for various internal
user groups, external
transactions and connectivity
bandwidths.
Clarification required
Should the solution handle all types of
acceptable targets with external user access?
Need to use the performance testing tool.
Our Suggestions
The performance testing tool should allow to
configure the various scenarios to achieve.
1. Shall provide an optimal and high
performance solution satisfying response time
for Internet and WAN connections with various
bandwidth.
2. The sizing exercise shall be based on
defining user profiles of the various applications
and systems, and running simulation to
determine the required hardware and software
configurations.
3. Shall ensure that frequent stress testing
exercises to be performed on the testing
hardware environment including the server to
Bidder to decide.
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 12 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
confirm sizing results.
24.
Clause 5.13.2 of
RFP Part-2
Performance Requirements
Content of RFP requiring
Clarification
Shall conduct a formal sizing
exercise to determine
bandwidth requirements for
all connectivity (MPLS,
internet, 3G/4G/LTE, etc.
Clarification required
Request to share the plan for achieving 3G,4G
performance analysis and network
virtualization/simulation.
Our Suggestions
Request you to consider for network
virtualization tool to analyze the network with
performance testing scenarios. This will help to
meet the performance analysis requirement in
3G, 4G and widely used networks.
Bidder to suggest and decide on appropriate
methodology.
25.
Clause 5.13.2 of
RFP Part-2
Performance Requirements
Content of RFP requiring
Clarification
1. Shall support around
500,000 registered users.
2. Shall support 5,000
concurrent users at peak
hours
Clarification required
Request to share the plan for executing the
5000 concurrent test during the peak load. This
will need hard ware in test environment.
Our Suggestions
Request you to consider for test automation tool
which allow executing the 5000 concurrent user
test and helping for sizing on upcoming
business growth for server sizing.
Bidder to demonstrate and decide.
26.
Clause 5.13.16 of
RFP Part-2
WAN Routers
Shall provide scalable
throughput and performance
Clarification required
Please define the throughput. We
recommended 500kpps performance throughput
No change
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 13 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
27.
Clause 5.13.16 of
RFP Part-2
WAN Routers
Shall support IPv4 and IPv6
standard internal and
external routing protocols
and WAN services
such as virtual routing and
forwarding (VRF),
multiprotocol border gateway
routing protocol extensions
(MPBGP), multiprotocol
label switching (MPLS) and
multiprotocol label switching
virtual private networks
(MPLS VPNs), tunneling and
encryption, quality of service
(QoS), congestion
management and bandwidth
optimization, multicasting
and protocol independent
multicasting (PIM)
Clarification required
Please remove the Bandwidth optimization
Our Router Support Traffic policing which helps
assign network resources (including bandwidth)
and increase network performance. For
example, you can configure a flow to use only
the resources committed to it in a certain time
range. This avoids network congestion caused
by burst traffic.
Traffic policing, Generic Traffic Shaping (GTS),
and rate limit control the traffic rate and
resource usage according to traffic
specifications. You can use token buckets for
evaluating traffic specifications.
A typical application of traffic policing is to
supervise the specification of traffic entering a
network and limit it within a reasonable range.
Another application is to "discipline" the extra
traffic to prevent aggressive use of network
resources by an application. For example, you
can limit bandwidth for HTTP packets to less
than 50% of the total. If the traffic of a session
exceeds the limit, traffic policing can drop the
packets or reset the IP precedence of the
packets.
Bidder to decide on output requirement of the
Project
28.
Clause 5.13.14 of
RFP Part-2
DMZ Switches
Support redundant power
supplies for high availability
Clarification required
Most of the 1U Switch is having 1+1
redundancy and in DMZ switch based on the
Agreed
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 14 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
(N+1 mode). port density 1U switch will be required, so
please change it to 1+1 redundancy
29.
Clause 5.13.14 of
RFP Part-2
DMZ Switches
Support logical and physical
redundancy mechanisms.
Clarification required
Please clarify the Logical Redundancy
Redundancy mechanism to be provided
30.
Clause 5.13.14 of
RFP Part-2
DMZ Switches
Support for integrated
service modules for
integrated services.
Clarification required
Integrated service modules for integrated
services is not required in DMZ switch because
the firewall and IPS device is asked separately
in the tender document, so please remove this
point
Agreed
31.
Clause 5.13.14 of
RFP Part-2
DMZ Switches
Provide scalable throughput
and performance.
6. Support multiple interface
options such as 10 gigabit,
gigabit, and fast Ethernet.
Clarification required
In DMZ switch all the servers are either having
10G or 1G connectivity. Fast ethernet ports are
rarely used in DMZ. So please remove fast
Ethernet
Agreed
32.
Clause 5.13.17 of RFP Part-2
L2/L3 Switches Shall support redundant power supplies, operating in an N+1 mode.
Clarification required
Most of the 1U Switch is having 1+1
redundency and in L2/L3 switch based on the
port desity if 1U switch will be required thenn
we do not required N+1 redundancy, so please
change it to 1+1 redundancy
Agreed
33. Clause 5.13.17 of RFP Part-2
L2/L3 Switches
Clarification required Agreed
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 15 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
Support for integrated service modules for integrated services.
integrated service modules for integrated
services is not required in DMZ switch because
the firewall and IPS device is asked separately
in the tender document, so please remove this
point
34.
Clause 5.13.17 of RFP Part-2
L2/L3 Switches Shall support dynamic trunk configuration across all switch ports. Shall comply with 802.1q Trunking standard.
Clarification required
The Dynamic Trunking Protocol (DTP) is a
proprietary networking protocol developed by
Cisco Systems for the purpose of negotiating
trunking on a link between two VLAN-aware
switches, and for negotiating the type of
trunking encapsulation to be used. It works on
Layer 2 of the OSI model. VLAN trunks formed
using DTP may utilize either IEEE 802.1Q or
Cisco ISL trunking protocols.
Please change it to Dynamic LACP Trunking
DTP / LACP
35.
Clause 5.13.19 of RFP Part-2
Server Farm Switches Support logical and physical redundancy mechanisms
Clarification required
Please clarify the Logical redundancy.
Redundancy requirement
36.
Clause 5.13.7 of
RFP Part-2
Servers Requirements Clarification required
Blades chassis shall be supplied with switch
blades that include two controllers
Our Suggestions
Please remove this point as none of reputed
Blades chassis shall be supplied with switch
blades that include appropriate redundancy
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 16 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
OEM has this feature
37.
Clause 5.13.7 of
RFP Part-2
Servers Requirements Clarification required
Be SNMP manageable and support for
TACACS+ and RADIUS integration
Our Suggestions
It is proprietary specifications please remove it
Agreed
38.
Clause 5.13.7 of
RFP Part-2
Servers Requirements Clarification required
Support failover protocols (e.g. VRRP, HSRP)
Our Suggestions
It is proprietary specifications please remove it
Agreed
39.
Clause 5.13.21.1 of
RFP Part-2
Storage and Backup
Requirements
Service provider shall be
responsible for meeting or
exceeding the following
unified storage system
requirements:
Clarification required
Storage must be configuring with 32GB cache per controller without O/S overhead.
Our Suggestions
In the context of a SAN storage appliance, cache memory serves as a critical buffer or staging area to keep data flowing along its path between servers and disk storage. Servers process blocks of data in high speed memory, and then burst those data blocks in streams across the network at extremely high transfer rates to and from data stores residing on the SAN. A cache is a buffer of live, volatile memory designed to accept data blocks at maximum
Based on Operations requirement, bidder to
decide
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 17 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
speed and temporarily store them, releasing servers to move on to the next process while data blocks are queued to move from cache to or from hard disk. The bottom line is that cache memory has an enormous impact on the efficiency of data transfer because it compensates for the latency of spinning hard disks.
40.
Clause 5.13.21.1 of
RFP Part-2
Storage and Backup
Requirements
The system shall support
SAN, NAS, and Scale-out-
NAS, via IP-based and/or
FC-based.
Clarification required
The system shall support SAN functionality using 4*8Gbps FC frontend ports.
Our Suggestions
This is SAN environment and hence important to define SAN functionality along with no of FC ports to established connectivity with Host.
Bidder to decide based on end use requirement
41.
Clause 5.13.21.1 of
RFP Part-2
Storage and Backup
Requirements
The system shall support the
following minimum baseline
technical specifications:
a. Pre-configured with Fabric
operating software and web
based management tools
b. Support storage
expansion shelves (Fiber
Channel, SATA, NL-SAS,
SSD)
c. Supplied with direct fabric
Clarification required
The system shall support the following minimum baseline technical specifications:
a. Pre-configured with Fabric operating software and web based management tools
b. Support storage expansion shelves (SAS, NL-SAS, SSD) -
c. Supplied with direct fabric attached server operating system
d. Support high availability features and dynamic path rerouting in the event of a link
Bidder to decide based on end use requirement
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 18 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
attached server operating
system
d. Support high availability
features and dynamic path
rerouting in the event of a
link failure
e. Equipped with hot
pluggable and redundant
power supplies
failure
e. Equipped with hot pluggable and redundant power supplies
Our Suggestions
FC Disk is obsolete and not avail with reputed OEM for storage
42.
Clause 5.13.21.1 of
RFP Part-2
Storage and Backup
Requirements
The system shall have
minimum of fifteen (15)
Terabytes (TB) of usable
space on disk arrays.
However, the Service
Provider is required to verify
the size of usable disk space
specified here to ensure that
enough disk space is
available for data storage, to
meet the requirements of the
applications as detailed in
this RFP, also taking into
consideration future annual
growth of 20% for 5 years.
Clarification required
The system shall have minimum of fifteen (15) Terabytes (TB) of usable space on disk arrays. However, the Service Provider is required to verify the size of usable disk space specified here to ensure that enough disk space is available for data storage, to meet the requirements of the applications as detailed in this RFP, also taking into consideration future annual growth of 20% for 5 years. Offered storage must support minimum 200 or more disks using SAS, NL-SAS or SSD disks.
Our Suggestions
It's mandate to keep scalability so as to bring all OEM at par, else it will be difficult to evaluate and generate comparison model.
agreed
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 19 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
43.
Clause 5.13.21.1 of
RFP Part-2
Storage and Backup
Requirements
The unified storage disk
array shall be connected to
both primary and backup
fibre/ether switches through
redundant ports. The unified
storage disk array shall be
equipped with redundant
controllers and fibre/ether
switches.
Clarification required
The unified storage controllers shall be connected to both primary and backup fibre/ether switches through redundant paths. Offered storage must have symmetric active-active controllers and LUN must be shared by both controllers.
Our Suggestions
Symmetric active-active controllers allows LUN to be accessible from any of the controller, hence this features allows the any of the controller to read/write data on the LUN. This features encusres that all the controllers are at same utilization levels at any point of time there by maintaining steady performance
agreed
44.
Clause 5.13.21.1 of
RFP Part-2
Storage and Backup
Requirements
LUNs shall be configured for
each service. HDD assigned
to each LUN shall formulate
a RAID 6 that includes HDD
from different shelves to
enhance the solution
availability. Service
Providers are to suggest the
leading design for storage
RAID configuration taking
into consideration the
reliability, availability and
Clarification required
LUNs shall be configured for each service. HDD assigned to each LUN shall formulate a RAID 5 that includes HDD from different shelves to enhance the solution availability. Service Providers are to suggest the leading design for storage RAID configuration taking into consideration the reliability, availability and speed of the solution.
Our Suggestions
As per the industry best practice production environment is always configured in RAID5 and RAID would be consider in case NL-SAS Disk for non-production environment
Agreed
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 20 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
speed of the solution.
45.
Clause 5.13.21.1 of
RFP Part-2
Storage and Backup
Requirements
The system shall support
automated storage tiering
and movement of data within
different tiers including
SATA, NL-SAS and SSD
disks without requiring user
intervention.
Clarification required
The system shall be configured with automated storage tiering and movement of data within different tiers including SAS, NL-SAS and SSD disks without requiring user intervention.
Our Suggestions
This feature allows to control Tiering by allowing to move the data from one Tier to another Tier at different time intervals which can be user defined. This helps user to define different type of Tiering rules depending upon the application requirement.
Bidder to decide basis of above responses
46.
Clause 5.13.21.2 of
RFP Part-2
Virtual tape library
Service Providers shall be
responsible for meeting or
exceeding the following VTL
system requirements
Clarification required
The Service Provider shall design the VTL in order to achieve low cost per terabyte (TB), while meeting all performance parameters
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library. At present in RFP no technical specs mentioned, In order to bring all reputed OEM at same level need to incorporate generic specs (as spelled in left column).
Bidder to decide based on operations
requirements
47.
Clause 5.13.21.2 of
RFP Part-2
Virtual tape library
Service Providers shall be
responsible for meeting or
Clarification required
The system shall have capacity of 30TB usable data. The proposed system shall also meet the
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 21 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
exceeding the following VTL
system requirements
future growth requirements. The Service Provider is required to verify the size of usable disk space specified here to ensure that enough disk space is available for data backup, to meet the requirements of the applications as detailed in this RFP and backup policy, also taking into consideration future annual growth of 20% for 5 years
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library. At present in RFP no technical specs mentioned, In order to bring all reputed OEM at same level need to incorporate generic specs (as spelled in left column).
48.
Clause 5.13.21.2 of
RFP Part-2
Virtual tape library
Service Providers shall be
responsible for meeting or
exceeding the following VTL
system requirements
Clarification required
The system shall be used for storing user, systems, and applications data. The system shall interface with all server platforms and OSs as part of the solution
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library. At present in RFP no technical specs mentioned, In order to bring all reputed OEM at same level need to incorporate generic specs (as spelled in left column).
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 22 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
49.
Clause 5.13.21.2 of
RFP Part-2
Virtual tape library
Service Providers shall be
responsible for meeting or
exceeding the following VTL
system requirements
Clarification required
Redundant array controllers shall be provided for load balancing and failover
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library. At present in RFP no technical specs mentioned, In order to bring all reputed OEM at same level need to incorporate generic specs (as spelled in left column).
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 23 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
50.
Clause 5.13.21.2 of
RFP Part-2
Virtual tape library
Service Providers shall be
responsible for meeting or
exceeding the following VTL
system requirements
Clarification required
VTL system to support the following minimum baseline technical specifications:
a. Integration with different backup management utilities and applications
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 104 of 178
b. Ability to support disaster recover (DR) / remote site replication and expiration of backup copies
c. Supports features of bandwidth optimization required to achieve bandwidth consumption reduction
d. Modular storage architecture and scalable for storage expansion
e. Supports integrated high availability with backup management utility server
f. Supports as minimum the following protocols: NFS v3/v4 over TCP, pNFS, CIFS, NDMP v2/v3/v4, tape library, emulation (VTL) over Fibre Channel
g. Supports management through GUI, SNMP and command line management interface
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 24 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
h. Supports the configuration of QoS settings
i. Allows configuration of an unlimited number of virtual tape cartridges
j. Supports the configuration of capacity on demand and tape capacity settings
k. Supports multi-site tape consolidation
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library. At present in RFP no technical specs mentioned, In order to bring all reputed OEM at same level need to incorporate generic specs (as spelled in left column).
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 25 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
51.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
Service Providers shall be responsible for meeting or exceeding the following backup system requirements:
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
52.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The solution shall be supported with a backup utility that is required to be implemented on redundant server blades. Each server blade installed at both primary and backup blades chassis shall be connected to both primary and backup fibre/ether switches through redundant links
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
53.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The backup management utility shall be supplied with the required agent licenses in alignment with ITMS solution used databases
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 26 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
and operating systems, SAN and LAN based backups. Additionally, the utility shall support backup solution functionalities.
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
54.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The backup shall support backup of virtual servers
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
55.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The software shall support scheduled automated backup using policy-based management for all server and OS platforms of the solution environment
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 27 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
specifications it's difficult for bidder to frame up backup policy.
56.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The software shall support online backup and restore of any running solution applications and databases.
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
57.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The backup software shall be capable of having multiple backup sessions simultaneously.
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
58.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The backup software shall support different types of backup such as full backup, incremental backup, differential backup, selective backup, point in time backup and progressive incremental backup, and snapshot
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 28 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
59.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The backup software shall support different types of user interfaces (e.g. GUI, web-based interface). Tape library
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
60.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
Service Providers shall be responsible for meeting or exceeding the following tape library system requirements
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
61. Clause 5.13.21.3 of Backup software Clarification required Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 29 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
RFP Part-2 The tapes library shall support the following minimum baseline technical specifications:
a. Include multiple tape drives
b. Contain LTO based tape media slots (support LTO-6 with 8 Gbps interface)
c. Scalability for future expansion
d. Include a robotic system for the handling of media
e. Include built-in component level diagnostic capabilities and provide alerting capabilities via SNMP
f. The tape library shall be directly supported by different backup software packages
g. An internal fibre channel shall be included for direct SAN fabric connectivity
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
62.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The system shall meet current and future growth requirements.
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 30 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
63.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The Service Provider shall provide enough tape media to ensure that enough is available for data backup, to meet the requirements as detailed in this RFP and backup policy, also taking into consideration future annual growth of 20% for 5 years
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
64.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The system shall back up all critical information of the solution from all applications for long term archival purposes.
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up
Bidder to decide based on above responses
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 31 of 38
Sr.
No. Clause No RFP Reference
Queries/ suggestions provided by the
Bidders Response/ Corrigendum if any
backup policy.
65.
Clause 5.13.21.3 of
RFP Part-2
Backup software Clarification required
The Service Provider shall be responsible for developing a solution backup and recovery policy, and applying the policy to the backup system.
Our Suggestions
We request you to consider technical specifications for offered Virtual tape library, without mentioning backup software detail specifications it's difficult for bidder to frame up backup policy.
Bidder to decide based on above responses
In addition to the online tender published vide tender notice no. CE/BRTS/15/2015-16 with this, Addendum-2 is published and attached
herewith. Bidders are instructed that all Addendum shall be treated as a part of tender document and shall be submitted along with the
Tender Documents.
City Engineer
Surat Municipal Corporation
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 32 of 38
Annexure -1 Tentative Phasing
Separate Request Orders for BRTS, City Bus Services and SMC Vehicles shall be issued
Services Request Order
No
Approximate Time for
Request Order from
Successful Pilot
Demonstration
Scope/ Approximate Sizing Tentative Lead
Time .
BRTS
1 and 2 0-6 Months All Central Software at CCC
Call Center, Web Portal etc.
AVL, PIS in followings
o BRT Bus Stations :100
o BRT Buses : 110
Depot Management System in
Bhestan Depot.
6-8 months
3 and 4 6-10 Months Depot Management System in
Kosad Depot.
AVL, PIS in
o BRT Bus Stations :16
2- 3 months
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 33 of 38
5 11-24 Months Remaining BRT Buses and
remaining other quantities
2- 3 months
City Bus
Services
1 and 2 0-8 Months AVL and PIS in followings;
City Buses: 200
City Bus Shelters :528
6-8 months
3 and 4 9- 12 Months Depot Management System in
City Bus Depot-2
2-3 months
SMC
Emergency
Vehicle (Fire,
Health and
Security)
1 0-3 months AVL and Driver console on SMC
Emergency vehicles : 50
3 months
SMC Vehicle
1 and 2 3-6 months Tracking units on SMC Vehicles :
535
4 -6 months
3 10-24 months Remaining Quantities -
The above is a tentative schedule as envisaged at this point of time and the Authority retains the full right to make changes / additions
to this schedule.
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 34 of 38
Annexure -2 Location of BRT Bus Station, Bus Depot and City Bus Shelters
A. Location of BRT Bus Station and Bus Depot
BRTS is 72 KM network which has undertaken in Phases. Phase -1 of BRTS is already operational where as Phase-2 is in advance stage of completion. Network Details is summarized below.
Phase of BRT Project
Network Length (KM) No of BRT Bus Stations
Phase-1 30 52
Phase-2 42 64
Kaharwarnagar Bus Station is equivalent to 3 station
3
Total 72 119
BRT Network Details
Corridor Name
Corridor Length (KM) No of BRT Bus Stations in Specific Corridor
Average Distance Between BRT Bus Station
BRT Phase-1
Sachin GIDC to Udhana Darwaja Corridor
9.98 18 500 meter
Dumas Resort to Anuwrat Dwar 4.1 9 500 meter
ITMS FOR SURAT MUNICIPAL CORPORATION, GUJARAT, INDIA Page 35 of 38
Anuwrat Dwar to Kharwarnagar 4.2 8 500 meter
Kharwarnagar to Simada 7.8 13 500 meter
Simada to Sarthana 2.6 5 500 meter
BRT Phase-2
Adajan to Jahangirpura 4.1 8 500 meter
Adajan to PAL 3.5 6 500 meter
PAL to ONGC 5.8 10 500 meter
Anuvratdwar to Saint Thomas 1.75 3 500 meter
Saint Thomas to Dakasheshwar Mahadev Jn.
5 8 500 meter
Hirabaugh to Magob 3.25 5 500 meter
Hirabaugh to Kasanagar 3 4 500 meter
Gajera to Jahangirpura 4 8 500 meter
Katargam to Kosad 9.5 12 500 meter
Depot : BRT and City Bus Services shall have two Depot each. One BRT Depot is operational at Bhestan in Surat where another
BRT Bus Depot is under construction at Kosad in Surat. The locations of Depot of City Bus Services are yet to be decided .