Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 1
Request for Proposal
RFP #Y-01
Project Director
For
Unemployment Insurance Systems Improvement (UISIm)
Issued on December 22, 2017
by
New York State Department of Labor
W. Averell Harriman State Office Building Campus
Building 12
Albany, NY 12240
Submission Deadline
January 17, 2018 @ 11:00 a.m. New York Time
Prepared By: New York State Department of Labor (NYSDOL)
The New York State Department of Labor is an Equal Opportunity Employer. Auxiliary
aids and services are available upon request to individuals with disabilities.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 2
Procurement Lobbying Act and Designated Contacts
This Request for Proposal (RFP) is being conducted in accordance with the
Procurement Lobbying Act (State Finance Law §§139-j and 139-k). For more
information regarding the Procurement Lobbying Act, please refer to the New York State
Office of General Services (OGS) website at:
https://online.ogs.ny.gov/legal/lobbyinglawfaq/viewall.asp
Pursuant to the Procurement Lobbying Act, this solicitation includes and imposes certain
restrictions on communications between the Department of Labor and a bidder during
the procurement process. Accordingly, designated contacts for questions related to
this procurement as of the date hereof, are:
Primary:
Darlene Powers
New York State Department of Labor
Purchase & Contracts
State Office Campus, Bldg. 12, Rm. 454
Albany, New York 12240
Tel: (518) 457-9395
Alternate:
Gay Townsend-Jones
New York State Department of Labor
Purchase & Contracts
State Office Campus, Bldg. 12, Rm. 454
Albany, New York 12240
Tel: (518) 457-1392
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 3
Table of Contents
Summary Statement……………………………………………………………………………5
Section 1 – Unemployment Insurance System Improvement (UISIm) Project
Background/Overview ………………………………………………………………………... 5
Section 2 - RFP Scope ………………………………………………………………………...6
2.1 Project Overview/Purpose……………………………………………………………..6
Chart 1…………………………………………………………………………..6
2.1.1 Contract Terms………………………………………………………………...7
2.2 Project Requirements…………………………………………………………………..7
2.2.1 Identification, Availability, and Worksite Requirements……………..……..7
2.2.2 Additional Requirements of NYSDOL…………………………………….....8
2.2.3 Project Director Replacement……............................................................9
2.2.4 Knowledge Transfer…………………………………………………………..11
2.3 Project Director Role -Tasks and Activities..........................................................11
2.3.1 Pre-DDI Contract Award Tasks………………………………….…………..12
2.3.2 Post-DDI Contract Award Tasks…………………………………………….12
2.4 Project Director Qualifications…………………………………….………………….17
2.4.1 Mandatory Qualifications…………………………………………….………17
2.4.2 Desired Qualifications………………………………………………………..18
Section 3 – Process for Proposal Submission………………………………………………19
3.1 Questions Concerning this RFP……………………………………………………...19
3.2 Notice of Intent to Bid………………………………………………………………….19
3.3 Proposal Due Date………………………………………………………………….....19
Section 4 - RFP Timetable…………………………………………………………………….20
Section 5 – Proposal Requirements – Format and Content……………………………….20
5.1 Proposal Forwarding Instructions and Format……………………………………..20
Section 6 – Selection Process and Criteria…………………………………………………22
6.1 Evaluation of Proposals………………………………………………………………22
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 4
6.2 Evaluation Process…………………………………………………………………...23
6.3 Evaluation Criteria…………………………………………………………………….23
6.4 Method of Selection………………………………………………………………......23
6.4.1 Tie-Breaker……………………………………………………………….…...24
Attachments…………………………………………………………………………………….25
Appendices……………………………………………………………………………………..26
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 5
Summary Statement:
This Request for Proposal (RFP) will refer to New York State Department of
Labor singularly as “NYSDOL”; New York State as “the State”; and New York
State Office of Information Technology Services as "ITS".
Additionally, the bidder of this Project Director RFP who is awarded the contract will be
referred to as “Contractor”; the bidder of the UISS RFP #V-17 RFP who is awarded the
contract will be referred to as “DDI Vendor”; and any contractor working on the UISIm
project, including the DDI Vendor will be referred to as a “Project Contractor”.
Section 1 – Unemployment Insurance System Improvement (UISIm) Project
Background/Overview
NYSDOL is the primary entity that administers Unemployment Insurance (UI) benefits,
contributions, appeals, and labor exchange systems to connect job seekers with
employers. Over the past decade, the State commenced a modernization effort known
as Unemployment Insurance System Improvement (UISIm) and has pursued various
initiatives to enhance its support and administration of these program areas. The State
has faced the pressing problem of maintaining, modifying, and extending outdated and
expensive mainframe-based UI benefits,contributions, and appeals systems that were
written in the 1970s and 1980s and remain constrained by the technology of that era.
All of these challenges have significantly hindered the delivery of UI benefits,
contributions, and appeals services in more efficient and streamlined ways to customers.
While the State has considerable experience and expertise in implementing initiatives
using a variety of technologies (web, client server, open source, etc.) and incorporating
re-engineering goals and principles in mission critical business areas, we recognize the
magnitude of developing an integrated and complete UI solution which includes benefits,
contributions, and appeals services. Based on substantial research, the State concluded
that there exist proven, vendor-based solutions and single state UI systems that have
been successfully implemented. Therefore, NYSDOL has started the UISIm project by
issuing Unemployment Insurance System Solution (UISS) RFP #V-17 to procure vendor
services for the design, development, and implementation (DDI) of an UI benefits,
contributions, and appeals case management system in the State of New York.
NYSDOL is issuing this RFP to seek proposals from qualified bidding entities or
individuals, (“bidders”), to provide the Project Director, (“PD”), who will oversee the
contracted services, business, and information technology aspects of the UISIm project.
Coordination of the overall UISIm project will be managed by the PD. The PD will be
working closely with the DDI vendor to manage the project master schedule and to
ensure that the DDI vendor adheres to the project budget. The PD will be the main, but
not the only, liaison between the Project Steering Committee (PSC) and the Project
Management Office (PMO).
Bidders must review the UISS RFP #V-17 for more details about the UISIm project.
https://labor.ny.gov/agencyinfo/contracts/contract-bid-grant-opportunities.shtm. The PD
is responsible for all project management requirements stated in the UISS RFP #V-17.
The bidder for this RFP, and their proposed PD, must affirm, on Attachment D, having
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 6
reviewed UISS RFP #V-17 and affirm that the proposed PD has the required skill set
and the ability to direct the project management requirements stated in the UISS RFP
#V-17.
Section 2 – RFP Scope
2.1 Project Overview/Purpose
NYSDOL is seeking a PD to oversee the modernization efforts to replace the existing
information technology (IT) legacy UI system in its entirety. NYSDOL envisions the PMO
to be led by the PD, the NYSDOL Project Managers, and the DDI vendor’s Project
Manager. As described in UISS RFP #V-17 governance structure, the PD reports to the
PSC (See Chart 1).
Chart 1
The primary focus of the PD is to ensure that project activities are optimally delivered
through cost effective measures that include the best combination of State and 3rd party
vendors to deliver a quality product, meeting all agreed-to requirements on budget and
schedule. The PD will be in charge of coordination between both the business and IT
aspects of the project and will oversee the project contractors in an efficient and
professional manner, promoting a team-oriented approach. The PD will manage the
overall UISIm project. The PD will ensure that the products developed, prescribed
processes, and the deliverables of the UISIm project contractors meet the State’s
expections and specified standards and are consistent with the DDI vendor contract
documents and deliverables.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 7
The PD will be the main, but not the only, liaison between the PSC and the PMO. The
PD will update and provide advice to the PSC throughout the period of performance on
the status of the project deliverables, enhancements, and the quality of the product to
meet the requirements, specifications, and standards set forth in the corresponding
contract documents. The PD will ensure that the PSC is fully informed on the budget,
schedule, and quality of deliverables. Disputes that cannot be resolved between the PD
and other project contractors or State staff shall be raised through a prescribed process
to the PSC for resolution.
2.1.1 Contract Terms
This contract shall commence after approval by the New York Office of the State
Comptroller and shall be in effect for five (5) years, with the State’s sole option to extend
for a period not to exceed one (1) year. Notwithstanding the termination of this contract
pursuant to the above-stated term, the terms and conditions hereof shall be effective and
binding throughout the life of the executed contract, including the optional 1-year
extension period.
2.2 Project Requirements
2.2.1 Identification, Availability, and Worksite Requirements:
The following requirements are mandatory. For identification and availability purposes,
the bidder must ascertain and validate on Attachment D that the proposed PD is either a
United States (U.S.) Citizen or non-U.S. citizen.
A. Where the proposed PD is a U.S. citizen, the bidder must identify the individual
with, at a minimum, the first and last name of the proposed PD as it appears on
his/her Driver’s License, Non-Drivers Identification Card, or other accepted forms
of government identification. A copy must be submitted with the proposal.
B. Where the proposed PD is not a U.S. citizen, the bidder shall identify such to
NYSDOL.
C. Where the proposed PD is not a U.S. citizen, the bidder must identify the
individual with, at a minimum, the first and last name of the proposed PD as it
appears on his/her Visa and/or Passport. No other names or derivations may be
used. A copy must be submitted with the proposal.
D. The bidder must retain all necessary paperwork throughout the length of the
proposed PD’s engagement with NYSDOL.
E. The bidder is responsible for ensuring the proposed PD retains the authorization
to legally work in the United States throughout the term of the engagement based
on the length of term identified in the contract resulting from this RFP.
F. The bidder must identify if the proposed PD will be working under an H1-B or
other visa during the time of the placement. The bidder will provide the visa
expiration date for the individual engaged in the project and shall make
commercially and legally reasonable attempts, as determined solely by NYSDOL,
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 8
to extend the work visa until the proposed end dates of this contract. On
Attachment D the bidder must indicate if the proposed PD will be working under
an H1-B or other visa and the expiration date.
G. The Federal Immigration Reform and Control Act, as amended, (8 USC section
1324a et al) obligates employers, such as the bidder, to verify that all its
employees are legally entitled to work in the United States. In order to verify that
an individual is not an unauthorized alien, NYSDOL reserves the right to request
legally-mandated, contractor-held documentation attesting to the legal
entitlement to work in the United States for the PD assigned work under this
contract. In accordance with such law, NYSDOL does not discriminate on the
basis of national origin or citizenship.
H. For quality assurance purposes, the vendor who is awarded the contract for
NYSDOL RFP #V-17 – Unemployment Insurance System Solution – cannot
receive the award for NYSDOL RFP #Y-01.
I. The proposed PD must be a full-time employee of the bidder (subcontractors,
temporary staff, or 1099 contractors do not qualify) and a dedicated resource and
must agree to work on site in Building 12, State Office Campus, Albany, NY
throughout the life of the project. NYSDOL will provide hardware and software
tools as appropriate.
J. The bidder shall identify any dates, in excess of ten annual vacation days, in
which the proposed PD will be unavailable during the duration of the proposed
engagement. This includes, but is not limited to, absences related to work visas.
Dates in which the proposed PD will be unavailable must be indicated on
Attachment D.
K. The bidder will provide a minimum of two (2) and a maximum of four (4)
references for the individual who is being recommended for the PD position. The
bidder must complete Attachment E for each reference provided. The references
must be from prior customers (see Attachment E-1) and must provide first-hand
knowledge of the proposed PD’s ability to perform the type of services requested
in this RFP. References provided must be available to be contacted by
NYSDOL. There will be reference checks. We strongly encourage the bidder
to notify each reference that his/her contact information has been given to
NYSDOL and that NYSDOL will be contacting him/her to verify the
proposed PD’s work experience as it pertains to the project scope and
Sections 2.4.1 and 2.4.2 of this RFP. Failure to pass a reference check may
result in the proposal being disqualified from further consideration.
L. Bidders who do not submit proposals by January 17, 2018 @ 11:00 a.m. New
York Time will be eliminated from consideration.
2.2.2 Additional Requirements of NYSDOL
A. NYSDOL will require background checks to be conducted by the bidder, at the expense of NYSDOL, including, but not limited to, finger-printing. The results of the background check are to be provided to NYSDOL. Upon contract award,
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 9
NYSDOL will also require the signing of a NYSDOL provided confidentiality statement and/or a non-disclosure agreement.
B. NYSDOL may also conduct its own background checks at its own expense,
including, but not limited to, fingerprinting.
C. NYSDOL may require the PD to provide photo identification such as a NYS
Driver’s License, Non-Drivers Identification Card, Passport, etc. in order to
receive a State or other applicable identification card used for entrance into
NYSDOL’s buildings and/or facilities.
D. NYSDOL may require the PD to attend training required by State law or in
accordance with the policy of NYSDOL. If required by NYSDOL, attendance at
training sessions will be mandatory. For trainings requiring a fee, NYSDOL shall
pay for the PD’s attendance. NYSDOL shall also be billed by the contractor for
the time the PD spends at such training. It is not intended to provide the PD with
the skills originally specified by this RFP.
E. NYSDOL may specify the manner and method by which the PD shall participate
in knowledge transfer at the time of placement or at any time during the PD’s
engagement.
F. The PD may be required to travel to NYSDOL offices and other locations in New
York State that are outside of the immediate Albany, NY area. In such cases,
with the prior written approval of NYSDOL, the PD shall be reimbursed for
mileage, lodging, and meals to the extent authorized by the NYS Office of the
State Comptroller as further set forth at:
http://www.osc.state.ny.us/agencies/travel/reimbrate.htm. The PD is responsible
for keeping adequate records (including hard copy receipts) to substantiate any
claims for reimbursement for travel in performance of the services under the
executed contract resulting from this RFP. In addition, the PD may, at NYSDOL’s
discretion and cost, be required to travel to other state locations where the DDI
vendor either is or has implemented solutions similar to the proposed DDI
solution.
2.2.3 Project Director Replacement
NYSDOL considers the continuous performance of the initially assigned PD to be critical
to the success of the project. In the event of a vacancy, the vacancy must be filled.
Replacement of the PD will not be grounds for an increase in the Hourly Wage Rate or
Markup, or an extension of the time for completion of the engagement outlined in 2.1.1.
Any replacement candidate must meet or exceed all requirements as set forth by
NYSDOL in this RFP. The contractor can only substitute due to sudden termination,
resignation, approved leave due to an Extraordinary Personnel Event (see below), or
death. To qualify for such replacement, the contractor must demonstrate to NYSDOL’s
satisfaction the event necessitating replacement and that the proposed replacement PD
is an actual full-time employee of the contractor (subcontractors, temporary staff, or
1099 contractors do not qualify). Proposed replacements shall have equal or better skill
level, qualifications, and experience, as determined solely by NYSDOL. Proposed
replacements deemed by NYSDOL to be less qualified than the originally proposed PD
may be grounds for pre-award disqualification or post-award termination.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 10
NYSDOL retains the right to cancel any contract resulting from this RFP for convenience
upon at least thirty (30) calendar days written notice to contractor without penalty or
other early termination charge. This provision should not be understood as waiving the
State’s right to terminate the contract for cause or stop work immediately for
unsatisfactory work, but is supplementary to that provision. If the contract is cancelled
pursuant to this section, NYSDOL shall remain liable for all accrued but unpaid charges
incurred through the date of cancellation.
The following definitions apply:
Extraordinary Personnel Event: means leave under the Family Medical Leave Act (29
U.S.C. §2601 et. seq.); or an incapacitating injury or incapacitating illness; or other
circumstances that in the sole discretion of NYSDOL warrant an extended leave of
absence, such as extended jury duty or extended military service that precludes the
individual from performing his/her job duties under the contract.
Incapacitating: means any health circumstance that substantially impairs the ability of
the PD to perform the job duties described in this RFP or the contract.
A. General Provisions
1) The contractor shall provide the NYSDOL PSC with a replacement request
that shall include:
a. A detailed explanation of the reason(s) for the replacement request;
b. The resume of the proposed replacement, signed by the replacement and
his/her formal supervisor;
c. The official resume of the current PD for comparison purposes;
d. Evidence of any required educational, professional and travel credentials;
and
e. A detailed explanation of the project knowledge transfer plan. Where
possible, the plan shall include confirmation that the replacement PD shall
work with outgoing personnel for at least two weeks (80 hours), at no cost
to NYSDOL during this transition period.
2) The NYSDOL PSC may request additional information concerning the
proposed replacement. In addition, the NYSDOL PSC and/or other
appropriate NYSDOL personnel involved with the Contract may interview the
proposed replacement PD prior to deciding whether to approve the
replacement request.
3) The NYSDOL PSC will notify the contractor in writing of: (i) the acceptance or
denial, or (ii) contingent or temporary approval for a specified time limit, of the
requested substitution. The NYSDOL PSC will not unreasonably withhold
approval of a proposed PD replacement. PD replacements are subject to the
provisions of 2.2.1, 2.2.2 and 2.4.1.
4) If the NYSDOL PSC denies the proposed replacement, the contractor will
propose an additional replacement for consideration until a satisfactory PD
replacement is deemed suitable and accepted by the NYSDOL PSC. The
contractor shall identify a suitable replacement within fifteen (15) days of the
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 11
actual vacancy occurrence or from when the contractor first knew or should
have known that the vacancy would be occurring, whichever is earlier.
5) If contractor becomes aware that any PD provided under this contract poses
an unacceptable risk to the State, or has been arrested for a felony or
misdemeanor offense that may disqualify such PD from operating, or having
access to NYSDOL systems and data, the contractor shall immediately notify
the NYSDOL PSC. Should NYSDOL decide that the PD must be replaced,
the contractor shall immediately remove the staff member and propose a
qualified replacement.
6) In the event it becomes necessary to replace the PD prior to completion of
one month (160 hours) of work, due to PD termination, sickness, or other
similar material change in the employment circumstance of the PD, the
contractor shall provide NYSDOL with five (5) business days prior written
notification describing the circumstances of the need for replacement.
7) In the event it becomes necessary to replace the PD after completion of one
month (160 hours) of work, due to PD termination, sickness, or other similar
material change in the employment circumstance of the PD, the contractor
shall provide NYSDOL with twenty (20) business days prior written
notification describing the circumstances of the need for replacement.
8) The contractor shall also identify a replacement of equal or better
qualifications, as determined solely by NYSDOL, within ten (10) business
days. NYSDOL reserves the right to do one of the following:
a. Allow the contractor to provide a replacement PD. The contractor
acknowledges that the failure to provide a PD for the duration of the
engagement constitutes a breach of contract and that as a liquidated
damage, NYSDOL has the right to receive up to two working weeks (80
hours) of work from the replacement PD, at no cost to NYSDOL, during a
transition/ramp-up period. This liquidated damage may be waived in
whole or in part, at NYSDOL’s sole discretion, if it is determined that the
need to replace the PD was beyond the control of the contractor, or
b. Terminate the contract if a replacement is required.
2.2.4 Knowledge Transfer
The PD must develop a final written internal executive summary of all work completed
on all tasks, associated metrics, and provide a presentation for executive staff identifying
operational recommendations that NYSDOL can undertake. A final written internal
executive summary and presentation for executive staff is required in the event of a PD’s
departure before project closeout.
2.3 Project Director Role – Tasks and Activities
The PD will conduct a timely and comprehensive review of the DDI draft contracts to
ensure, that from their perspective as the PD, all aspects of RFP #V-17, including all
NYSDOL requirements and deliverables, are included. The PD must also review the PD
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 12
contract to affirm that the duties and responsibilities described in the contract are
understood and will be accomplished.
2.3.1 Pre-DDI Contract Award Tasks
To the extent necessary and appropriate as determined by NYSDOL, the PD may assist
NYSDOL in the selection of the DDI vendor. The PD may be performing pre-DDI
contract award efforts which may include but are not limited to the following:
Task Activities:
A. DDI Vendor Contract Negotiation:
1) Provide guidance and information in support of contract negotiations for a
DDI vendor.
2) Document the DDI vendor/system development contract negotiation process.
B. Project Documentation:
1) Create reference documents and artifacts of project management standards based on the NYS ITS standards found in: https://its.ny.gov/nys-project-management-guidebook-release-2.
2) Document suggestions and recommendations based on DDI vendor
demonstrations in a clear and understandable manner.
2.3.2 Post-DDI Contract Award Tasks
The PD will perform project management services to complete the development, testing,
and implementation of the UISIm project. This will involve coordination and collaboration
with all project stakeholders, including NYSDOL, ITS, all project contractors and sub-
contractors. The PD will work with the UISIm project team to define the knowledge
transfer plan to allow state staff to oversee the continued operation and support of the UI
benefits, contributions, and appeals programs. The PD will also complete the formal
project closeout process to confirm that the UISIm project has been successfully
completed and NYSDOL expectations have been met. The PD will be responsible for the
following major activities, but will not be limited to:
Task Activities:
A. Project Management
1) Oversee and manage the project activities to successfully transition from DDI
contract award to start of the project.
a. Create a “DDI Vendor Onboarding” Transition Plan including all
assessment reports and updates;
b. Coordinate and conduct arrangements to on-board the DDI vendor
personnel;
c. Coordinate arrangements for onboarding NYSDOL’s UISIm project staff;
and
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 13
d. Ensure all project staff have signed all confidentiality and security
agreements and have taken all confidentiality trainings before the start of
the project.
2) Review and approve the DDI vendor’s project plan for project initiation.
a. Review the UISIm project plan submitted by the DDI vendor and develop
assessment reports as necessary;
b. Assess the UISIm project plan’s ability to outline how the project will be
structured and how it will be successfully implemented;
c. Produce assessment reports as required by the PSC;
d. Update the UISIm project plan with NYSDOL staff outlining the roles and
responsibilities of all project participants;
e. Review and approve updates to the project plan with the DDI vendor; and
f. Liaise with PSC to review and approve the DDI vendor’s project plan.
3) Review and approve the DDI vendor’s project initiation plan.
a. Assess and update the UISIm project initiation plan including producing
assessment reports;
b. Review changes/updates to the project initiation plan with the DDI vendor;
and
c. Execute the UISIm project initiation plan.
4) Manage the UISIm project scope, schedule, and budget.
a. Prepare and submit clear, understandable, and accurate monthly project
status reports;
b. Work with the UISIm project team coordinators with an emphasis on
addressing schedule and resource management issues as they arise;
c. Prepare and obtain approval for each project phase;
d. Compile status from work group leads and project contractors to update
the project schedule;
e. Update status and publish a monthly update to the project plan;
f. Complete periodic consultation to discuss project progress and potential
enhancements to improve execution;
g. Ensure the UISIm project meets or exceeds budget and financial
objectives; and
h. Report budgeting concerns to the PSC proactively and offer suggestions
for corrective action.
5) Oversee and manage the system change management process.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 14
a. Confirm that all system change management items are documented,
including cost, schedule, and resource impacts with project contractors;
b. Coordinate the review and approval of system change requests with the
PMO and PSC through a defined process and PSC approval; and
c. Track the progress and completion of all system change management
items.
6) Execute the project communication management plan.
a. Implement a project communication process that facilitates
communication of clear, understandable, and accurate information, to the
intended individuals, at the right time;
b. Communicate clear, understandable and accurate project updates
proactively to the PSC and the PMO by preparing meeting agendas,
facilitating meetings, documenting minutes, and action items;
c. Communicate all changes to the UISIm project to all project participants
as appropriate;
d. Develop and distribute strategic communications reports; and
e. Perform periodic review and updates to the project communication
management plan.
7) Execute the project change management plan.
a. Maintain a log of all system change requests identified by the UISIm
project team and submitted by the project contractors;
b. Facilitate the review and approval process for all system change
requests;
c. Document and monitor the system change management process; and
d. Track and manage the system change management costs versus budget.
8) Oversee organizational change management.
a. Working with the DDI vendor, ensure the organizational change
management methodology and process are developed and approved by
the PSC;
b. Ensure organizational change management risks are integrated into the
project risk management plan;
c. Ensure organizational change management activities are included in the
project plan and user training.
9) Execute the project risk management plan.
a. Maintain a log of all project risks identified by the work group leaders and
project contractors;
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 15
b. Develop, update, and maintain the project work plan (i.e. Gantt Chart); in
a format approved by the PSC;
c. Evaluate and assign risk probability and impact scores;
d. Rank the identified risks and focus mitigation efforts on the highest
evaluated risks;
e. Prepare risk mitigation plans;
f. Present risks and mitigation plans to the PMO and the PSC;
g. Review and respond clearly and understandably to the Quality Assurance
(QA) Contractor’s findings and coordinate efforts for remedies with the
other project contractors; and
h. Implement agreed upon mitigation plans.
10) Manage UISIm project team.
a. Provide the PSC with clear and understandable recommendations for
optimal level of project staffing and reporting structure for UISIm as the
project evolves and changes;
b. Provide clear guidance to the UISIm project team leaders;
c. Oversee the UISIm project team work plans;
d. Manage dependencies between UISIm work groups;
e. Lead and manage activities of the UISIm project team; and
f. Coordinate reviews, approvals, and documentation needed for the project
review processes to ensure continued process improvements.
B. Project Contractors’ Management
1) Oversee and coordinate project contractors’ work.
a. Manage the project management process with the project contractors;
b. Assess and update all project documents submitted by the DDI vendor;
c. Review findings and recommendations provided by project contractors
and incorporate into the project plans;
d. In consultation with ITS, coordinate and oversee the IT technical work
scope for project contractors;
e. Provide project coordination for work tasks assigned to project
contractors;
f. Provide technical oversight and direction to project contractors;
g. Review and approve in collaboration with the PSC, any system changes
made by the DDI vendor to features or functions in order to resolve defect
issues with the PSC;
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 16
h. Manage and assign tasks to project contractors;
i. Facilitate meetings to monitor and respond to deficiencies in the project
contractors’ requirements and deliverables;
j. Oversee and manage the DDI vendor’s finalization of system
requirements;
k. Monitor deliverables database and define requirements for revision
control;
l. Give final approval over all requirements resulting from progressive
elaboration during the finalization of system requirements;
m. Give approval for DDI vendor’s base code set, framework, commercial-
off-the-shelf (COTS) product(s), or any technical base proposed by the
DDI vendor to be used to determine finalized requirements;
n. Ensure all materials for requirement design workshop sessions conducted
by the DDI vendor are made available to NYSDOL attendees;
o. Oversee and manage all milestones of all project contractors to ensure
compliance with NYSDOL requirements, as detailed in the UISS RFP #V-
17 – See Section 2.30.1: Contractor Invoicing Schedule Milestones and
Deliverables Required prior to Invoicing,
p. Oversee and approve DDI vendor project deliverables that are in
compliance with NYSDOL requirements, as detailed in the UISS RFP #V-
17 – See Section 2.30.3, Table 8: Deliverables List for more details;
q. Provide formal written notice to the DDI vendor for project deliverables as
required, according to the UISS RFP #V-17;
r. Review and verify project contractors’ invoices based on project
deliverables; and
s. Verify time and budget requests of project contractors prior to NYSDOL
approval (if applicable).
C. Training Management
1) Execute the DDI vendor’s Knowledge Transfer Plan (See UISS RFP #V-17
Section 2.27).
a. Ensure the DDI vendor’s Knowledge Transfer Plan meets the project
objectives;
b. The plan should document, instruct, and fully prepare a provider for
operating, monitoring, and maintaining system activity and performance;
and
c. Review and comment on the DDI vendor’s Knowledge Transfer Plan.
2) Execute the training plan.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 17
a. Work with the DDI vendor to finalize a training plan in accordance with
provisions of UISS RFP #V-17 Section 2.28 Solution Training to
successfully transition NYSDOL staff and public users to the new
Solution;
b. Work closely with the training team and ensure the training plan is
followed and executed as designed;
c. Review and approve DDI vendor developed training plans and materials;
d. Review and oversee corrective action plans for any training sessions
reported to be ineffective; and
e. Regularly monitor DDI vendor’s timely completion and update of all
training materials, including meeting notes, work in progress, drafts, final
deliverables, run stream/job documentation, operator/user manuals, desk
guides, and error handling procedures, in NYSDOL’s SharePoint cloud
portal.
D. Project Closeout
1) Initiate, manage and oversee the project closeout process. Provide additional
documentation as determined by the PSC, which may include but may not be
limited to:
a. Outstanding work orders;
b. Documentation of DDI vendor Technical Knowledge Transfer (See UISS
RFP #V-17 Section 2.27);
c. Documentation of project lessons learned;
d. Documentation that the risk management plan was completed; and
e. Documentation of project actual expenses compared to budget.
2.4 Project Director Qualifications
2.4.1 Mandatory Qualifications
The PD must have:
A. A current Project Management Professional credential (“PMP”) from the Project
Management Institute. A copy of this certification must accompany the bidder’s
technical proposal (See Attachment B, “Proposal Checklist”).
B. Managed at least two (2) IT projects successfully, defined as a project that met
all of its stated objectives to the customer’s satisfaction, that:
1) had a budget of at least $10 million in IT “application development services”. ”Application development services” are defined as systems whose primary component is software for business processes. This software should have been developed and/or enhanced through coding as part of the referenced project.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 18
2) had complexities requiring coordination of work between multiple entities and
contractors; and
3) had similar scale and complexity to the UISIm project, and that must have
included the system development phases associated with design through
deployment and full client acceptance.
C. A minimum of ten (10) years of project management experience in the public or
private sector.
D. A minimum of ten (10) years of hands-on experience using project management
methodologies and associated tools and metrics.
E. A minimum of a bachelor’s degree from an accredited college or university. If the
degree has been obtained in another country, it is required that the degree or
coursework be evaluated for equivalency. The following is a link to a list of
agencies that provide evaluations of foreign education:
https://www.cs.ny.gov/jobseeker/degrees.cfm. We accept evaluations
performed by these companies or companies that are current National
Association of Credential Evaluation Services (NACES) members –
http://www.naces.org. The bidder is responsible for any evaluation fees.
2.4.2 Desired Qualifications
The Project Director should have:
A. Led four (4) or more projects that involved communication and customer
relationship management activities with both internal and external stakeholders.
B. Project management experience in two (2) or more of the following business
applications:
UI, Financial Accounting, Case Management, Government Revenue,
Insurance, or Claim Processing.
C. A minimum of ten (10) years of experience with iterative information system
development methodologies.
D. Written at least one (1) project guide or led at least one (1) project training which
communicated and translated technical terminology, concepts, and issues in
terms clear and understandable to technical and non-technical management and
staff.
E. A minimum of seven (7) years of experience defining and managing project
scope statements and development approach documents.
F. A minimum of seven (7) years of experience creating and maintaining project
schedules using project scheduling software.
G. A minimum of seven (7) years of experience coordinating project team member
activities according to approved project scope, development approach, and
project schedule.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 19
H. A minimum of seven (7) years of experience creating and maintaining project
risks and project issues logs.
I. A minimum of seven (7) years of experience managing the resolution of technical
or business issues raised by project stakeholders.
J. A minimum of seven (7) years of experience managing project artifacts, i.e.,
design documents, requirements, test plans, and program code, using
configuration management software.
K. A minimum of seven (7) years of experience developing regular project status
reports.
L. A minimum of seven (7) years of experience planning, developing agendas and
conducting regular project status meetings and working meetings with project
stakeholders.
M. Strong communication skills both written and verbal to demonstrate required
knowledge, skill sets and abilities to define and manage UI project scope and
development. A writing sample of the proposed PD will be required, see Section
5.1.B.1.d.
Section 3 – Process for Proposal Submission
3.1 Questions Concerning this RFP
Questions concerning this RFP shall be submitted via electronic mail attachment utilizing
Attachment H RFP #Y-01 Questions, to
[email protected]. Questions regarding the RFP will be
accepted until December 29, 2017 at 5:00pm NYT. No telephone inquiries will be
accepted. Answers to all questions received by this date will be returned to the bidders
in electronic format no later than the deadline as specified in the Calendar of Events.
The inquiry must cite the particular page, section, and paragraph number (where
applicable) and must be submitted on Attachment H. Bidders are encouraged to submit
questions as early and often as necessary during the Question and Answer period, but
no later than the deadline for submission of bidder’s questions specified in the Calendar
of Events. NYSDOL will make every effort to respond to questions as quickly as
possible.
3.2 Notice of Intent to Bid
Bidders intending to submit a proposal to this RFP should submit the “Notice of Intent to
Bid” form. This form and completion and forwarding instructions are included in
Attachment A – Notice of Intent to Bid. Forms should be received no later than
December 28, 2017 at 5:00pm NYT. Submission of this form is not a mandatory pre-
requisite for bidder eligibility.
3.3 Proposal Due Date
Proposals must be received no later than January 17, 2018 at 11:00AM NYT. Any
proposals or unsolicited amendments to proposals received after the due date and time
will not be considered in the review process. No “faxed” or “e-mailed” documents will be
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 20
accepted. NYSDOL takes no responsibility for any third-party error in the delivery of
proposals (e.g. U.S. Post Office, Federal Express, UPS, courier).
Section 4 – RFP Timetable
RFP Calendar of Events
RFP Event Date
RFP Release Date December 22, 2017
Deadline Date for Questions December 29, 2017 @ 5:00pm NYT
Responses to Questions January 8, 2018 @ 5:00pm NYT
Submission Date for the Notice of Intent to Bid (not
mandatory) December 28, 2017 @ 5:00pm NYT
Deadline Date for Proposal Submission January 17, 2018 @ 11:00am NYT
Anticipated Date of 1st Level Interviews Week of January 29, 2018
Anticipated Date of 2nd Level Interviews Week of February 5, 2018
Anticipated Date of Notification of Award February 15, 2018
Timeframe for Contract Negotiations 7 Business Days from Date of
Award Announcement
Anticipated Date of Execution of Contract Agreement
Approximately 45 days from
Contract Submission to NYS
Control Agencies
Anticipated Project Start Date April 30, 2018
Section 5 – Proposal Requirements – Format and Content
5.1. Proposal Forwarding Instructions and Format
A. Forward Proposal Packages to:
Darlene Powers
New York State Department of Labor
Purchase & Contracts
State Office Campus, Bldg. 12, Rm. 454
Albany, New York 12240
B. Proposal Format:
A submission may only include one individual as the proposed PD.
1) Technical Proposal:
a. On Attachment D, the bidder and the proposed PD must affirm that:
1) they have read and understand UISS RFP #V-17, 2) the proposed PD has the skill set and the ability to direct the project
management requirements as stated in UISS RFP #V-17, 3) they understand and agree to conform to the requirements set forth
in Sections 2.2 and 2.3 of this RFP; 4) the proposed PD is a US citizen. If not a US citizen, the type of visa
under which the proposed PD will be working and the expiration date must be indicated; and
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 21
5) the proposed PD is available for the duration of the proposed engagement with the exception of dates indicated in excess of ten annual vacation days.
b. The bidder shall provide a narrative that demonstrates that the individual
proposed as the PD meets the mandatory qualifications set forth in
Section 2.4.1 of this RFP and possesses some or all of the desired
qualifications set forth in Section 2.4.2 of this RFP. Copies of current
certifications are required.
c. Proposal narratives should be as succinct as possible, while adequately
covering all sections of this RFP, but should not exceed 30 pages, using
twelve (12) point Times New Roman font, with one (1) inch margins.
Supporting documents are not included in this limit. All pages must be
numbered.
d. The bidder shall provide a writing sample from the proposed PD. This
writing sample shall illustrate the PD’s vision of a vendor transition plan,
an assessment report, and a monthly status report.
e. The proposed PD is required to participate in an oral interview to clarify or
support representations made in the written Technical Proposal. The
purpose of the oral interview is to provide the Technical Review
Committee with a greater understanding of the proposed PD’s
qualifications and how past experience will serve to meet the mandatory
and desirable qualifications of this RFP. Presentations/demonstrations
will be conducted at NYSDOL offices at Building 12, State Office Building
Campus, Albany NY. NYSDOL reserves the right to reject the proposals
of bidders who fail to provide any required oral interview.
f. References for the proposed individual set forth in Section 2.2.1.K. must
be provided using Attachment E and E-1.
g. Copies of professional certifications, individual resumes, and Attachments
E and E-1 should be packaged with the Technical Proposal (Volume I).
h. Administrative Documents (this includes all mandatory documentation the
bidder is obligated to return with their proposal (e.g., copy of PMP
certificate, copy of Driver’s License, Non-Drivers Identification Card, visa,
passport, or other accepted forms of government identification) should be
packaged with the Technical Proposal (Volume I).
2) Financial Proposal
a. The Financial Proposal must be provided using Attachment F.
3) Bidders must submit proposals in three (3) separate packages:
A. Volume I - Technical Proposal/Administrative Documents
B. Volume II - Financial Proposal
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 22
C. Volume III – NY Legal and Regulatory Forms and Appendices
The three (3) volumes must be submitted simultaneously to the Procurement
Office (at the address listed in Section – 5.1.A. of this RFP and by the date
indicated in Section 4 – RFP Timetable). The bidder’s response to this RFP
shall be submitted as three (3) separately bound and identified proposals.
Each proposal must be marked with the title of the RFP, the Assigned Bid
Number, and the respondent’s name and address clearly displayed on the
exterior of each envelope. Volumes I, II, and III must be in separate
envelopes but should be in the same submission package.
Volume I - Technical Proposal/Administrative Documents
Volume I – Technical Proposal/Administrative Documents shall be submitted
as twelve (12) hard copies (printed and bound), one (1) of which must contain
original signatures. The bidder must also submit five (5) corresponding
searchable electronic media copies on USB 2 or 3 compliant flash drives
labelled “Vendor name UISIm PD RFP #Y-01 Technical,” saved as Microsoft
Word, Excel, and/or Adobe Acrobat format files.
Volume II – Financial Proposal
Volume II – Financial Proposal shall be submitted as five (5) hard copies
(printed), one (1) of which must contain original signatures. The bidder must
also submit five (5) corresponding searchable electronic media copies on
USB 2 or 3 compliant flash drives labelled “Vendor name UISIm PD RFP#Y-
01 Financial,” saved as Microsoft Word, Excel, and/or Adobe Acrobat format
files.
Volume III – NY Legal and Regulatory Forms and Appendices
Volume III – NY Legal and Regulatory Forms and Appendices shall be
submitted as five (5) hard copies (printed), one (1) of which must contain
original signatures. The bidder must also submit five (5) corresponding
searchable electronic media copies on USB 2 or 3 compliant flash drives
labelled “Vendor name UISIm PD RFP #Y-01 Legal-Regulatory,” saved as
Microsoft Word, Excel, and/or Adobe Acrobat format files.
Section 6 – Selection Process and Criteria
6.1 Evaluation of Proposals
All proposals received shall be subject to an evaluation by NYSDOL. A Technical
Review Committee, a Cost Review Committee, and the PSC will participate in the
evaluation of proposals. Members of the Technical Review Committee and the Financial
Review Committee will individually evaluate the technical and financial portions of the
proposals. The Financial Committee will not share their information with the Technical
Committee or the PSC at any time during the review of the proposals.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 23
6.2 Evaluation Process
The evaluation process will be conducted as follows:
A. Incomplete proposals will be disqualified.
B. All bidders that are determined not to be responsive or responsible will be
disqualified after completing a review.
C. Proposals that fail to meet the requirements and/or mandatory qualifications may
be disqualified after completing a full review.
D. Technical (which includes the written proposal and both first and second-level
oral interviews) and Financial proposals will be scored separately and then
combined to produce a final score based upon the weight given to each part.
E. The bidder which represents the total best value (the most points received in the
financial evaluation combined with the technical evaluation -which includes the
technical review as well as both first and second-level oral interviews ) will be
deemed the proposed winner of this RFP.
F. For quality assurance purposes, the vendor who is awarded the contract for
NYSDOL RFP #V-17 – Unemployment Insurance System Solution – cannot
receive the award for NYSDOL RFP #Y-01.
6.3 Evaluation Criteria
Technical Component = 70 points
The technical evaluation is comprised of three (3) components: written technical
evaluation, first-level oral interview (if bidder is susceptible to award), and second-level
oral interview (if bidder is still susceptible to award following the first-level oral interview).
A bidder who does not receive the pre-determined minimum number of written technical
evaluation points will not be considered for a first or second-level oral interview.
Financial Component = 30 points The financial proposal evaluation will be based on total cost of services. If a financial proposal is found to be non-responsive, that proposal may not receive a financial score and may be eliminated from consideration. The lowest cost bidder receives the maximum points. All other bidders are evaluated relative to the lowest bidder’s cost. The formula for the evaluation of other bidder’s cost will be: (lowest cost bidder / bidder cost) x maximum points.
6.4 Method of Selection
The method of selection will be based on a point system with the technical portion of the
rating criteria weighted at 70% of the total and financial being 30% of the total. NYSDOL
will select the bidders that provide the best value taking into consideration the most
beneficial combination of factors including qualifications, experience, and cost as
described herein. The scores from the written technical and financial portions of the
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 24
eligible bidders proposal will be combined and a ranking of bidders will be developed.
The next step will be the oral interview process. The proposed PD of all bidders
susceptible to award will be asked to participate in the first-level oral interview process.
The finalists will be notified of the date, time, and place of the interview. The purpose of
the interview will be for the proposed PD to demonstrate communication skills, the ability
to provide the requested services, to clarify representations from the written Technical
Proposal, and to provide the details as to how the proposed PD will accomplish the
requirements of the RFP. The interview will be evaluated on the basis of whether the
proposed PD substantiates the characteristics and attributes indicated in the proposal
and points will be awarded accordingly. NYSDOL reserves the right to reduce a written
technical score based upon information received during the first-level oral interview.
The first-level oral interview(s) will be conducted by members of the Technical
Evaluation Team. At the conclusion of the first-level oral interview(s), each interview
score will be combined with the bidder’s written technical score and the cost score to
create a new ranking of bidders. The proposed PD of all bidders still susceptible to
award after the first-step oral interview will be asked to participate in a second-level oral
interview.
The finalists moving onto the second-level oral interview will be notified of the date, time,
and place of the interview. The second-level oral interview(s) will be conducted by
representatives of the PSC. NYSDOL reserves the right to reduce a written technical
score based upon information received during the second-level oral interview. At the
conclusion of the second-level oral interview, each interview score will be combined with
the written technical score, the cost score, and the first-level oral interview score. The
bidder with the highest number of points at the conclusion of the written technical
evaluation, cost evaluation, first-level oral interview, and second-level oral interview will
be considered the bidder with the best value and the proposed winner of RFP #Y-01.
Note: For quality assurance purposes, the vendor who is awarded the contract for
NYSDOL RFP #V-17 – Unemployment Insurance System Solution – cannot receive the
award for NYSDOL RFP #Y-01. Should the bidder who represents the total best value
for RFP #Y-01 be from the #V-17 awarded vendor, the next highest ranked bidder will be
considered the proposed award winner for RFP #Y-01.
6.4.1 Tie-Breaker
In the event that bidders receive the same final score, the State will use the following tie breaking mechanisms, in the order listed, to determine final ranking:
• The bidder’s Financial Score.
• The bidder's Technical Score after Second-Level Interview.
• Determination by PSC.
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 25
Attachments
Attachment A Notice of Intent To Bid
Attachment B Proposal Checklist
Attachment C New York Legal and Regulatory Forms Cover Sheet
Attachment C-1 New York State and Federal Certifications
Attachment C-2 New York State Department of Labor Non-Disclosure Agreement
Attachment C-3 Contract Termination Provisions Pursuant to State Finance Law §139-k
Attachment C-4 Bidder’s Disclosure of Prior Non-Responsibility
Attachment C-5 Bidder’s Affirmation of Understanding and Agreement
Attachment C-6 ST-220-CA Contractor Certification to Covered Agency
Attachment C-7 ST-220-TD Contractor Certification to New York State Department
of Taxation and Finance
Attachment C-8 Form A: State Consultant Services – Contractor’s Planned
Employment
Attachment C-9 Form B: State Consultant Services – Contractor’s Annual
Employment Report
Attachment C-10 Contract Termination Provision Pursuant to Public Officers Law
§73 (4)
Attachment C-11 Bidder Certification of Compliance with Public Officers Law §73
(4)
Attachment C-12 Vendor’s Experience Certification
Attachment C-13 Vendor Responsibility Form
Attachment C-14 AC3237-S – NYS Office of the State Comptroller Substitute Form
W-9
Attachment C-15 No Conflict of Interest Attachment D Bidder and Proposed Project Director Affirmation Attachment E Project Director Resume and Reference Form
Attachment E-1 Proposed Project Director Mandatory Qualifications Summary
Attachment F Project Director Financial Response Form
Attachment G Terms and Conditions
Attachment H RFP #Y-01 Questions
Unemployment Insurance System Improvement Project Director RFP #Y-01 Page | 26
Appendices
Appendix A Standard Clauses for New York State Contracts
Appendix MWBE MWBE EEO Requirements and Procedures
Appendix MWBE-1 MWBE EEO Policy Statement
Appendix MWBE-2 EEO 100 Staffing Plan
Appendix MWBE-3 EEO 101 Workforce Utilization Report
Appendix MWBE-4 MWBE 100 MWBE Utilization Plan
Appendix MWBE-5 MWBE 101 Application for Waiver of MWBE Participation Goal
Appendix MWBE-6 MWBE 105 MWBE Quarterly Compliance Report
Appendix SDVOB SDVOB Requirements and Procedures
Appendix SDVOB-1 SDVOB 100 SDVOB Utilization Plan
Appendix SDVOB-2 SDVOB 101 SDVOB Monthly Compliance Report
Appendix SDVOB-3 SDVOB 200 Application for Waiver of SDVOB Participation Goal