13
Rescue Mine Expansion Project Page 1 Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative is based on the proposed Plan of Operations submitted to the Forest Service on June 4, 2010 by Shoshone Silver/Gold Mining Company for the Rescue Mine. The proposed plan would allow Shoshone Silver/Gold Mining Company to conduct mining and milling operations at the Rescue Mine. Figure 1 The Rescue Mine is an underground gold mine located approximately one half mile southeast of Warren, Idaho in Section 11, T22N R6E, Boise Meridian (Figure 1). The project area encompasses approximately 170 acres and is located adjacent to Warren Creek which eventually drains into the Salmon River approximately 15 miles

Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 1

Rescue Mine Expansion Project

Details of the Proposed Action

Proposed Action

This alternative is based on the proposed Plan of Operations submitted to the Forest Service on June 4, 2010 by

Shoshone Silver/Gold Mining Company for the Rescue Mine. The proposed plan would allow Shoshone

Silver/Gold Mining Company to conduct mining and milling operations at the Rescue Mine.

Figure 1

The Rescue Mine is an underground gold mine located approximately one half mile southeast of Warren, Idaho in

Section 11, T22N R6E, Boise Meridian (Figure 1). The project area encompasses approximately 170 acres and is

located adjacent to Warren Creek which eventually drains into the Salmon River approximately 15 miles

Page 2: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 2

downstream. The project area includes the Rescue Mine Millsite, waste rock and tailings disposal areas, and

temporary access and exploration roads. The mine site is accessed from Forest Road #50340 (Figure 2).

Figure 2

The mine site currently has an access road, exploration roads, various ditches and pipelines, three drill pads, a

main adit, three abandoned adits, one new adit/portal under construction, a mill building, a makeup water tank, a

generator/shop building, various ancillary buildings, a primary settling pond, a secondary overflow pond, a

tailings pond, and a stormwater/streamflow infiltration pond (Figure 3).

Page 3: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 3

Figure 3

In addition to reauthorizing continuing use of the existing infrastructure along with the personnel and equipment

needed to maintain and operate the existing mine, the proposed action would:

Increase the capacity of the existing tailings pond in two phases.

Construct a new waste rock dump.

Clear a flat pad on which two makeup water tanks would be installed.

Fix a leak on the existing primary process water infiltration pond by installing a bentonite seal.

Authorize the construction of three new water infiltration basins.

Create a process water management system for ore milling.

Create a stormwater management system that utilizes overland flow to infiltrate water and/or infiltrates

water using a stormwater infiltration pond.

Authorize temporary road construction and maintenance necessary to facilitate the proposed activities.

Conduct exploratory core drilling and/or trenching.

The layout of the mine site under the proposed expansion is shown in Figure 4 and a detailed description of new

facilities is provided below.

Page 4: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 4

Figure 4

Tailings Pond

The existing tailings pond is full and of insufficient volume to handle the amount of tailings expected to be

generated as the mine returns to production over the next few years. Two new tailings ponds would be

constructed in phases. Both would be located where the existing tailings pond is located with each phase

excavating a consecutively larger footprint.

The phase one tailings pond would be constructed by clearing the trees and topsoil for future reclamation and

excavating material from the existing pond to create the pond’s containment berm. Figure 5 shows an

approximation of the phase one configuration. A temporary access road (#503400840) would be constructed to

encircle the pond by creating approximately a ten foot wide crest on the pond berm. The first phase pond would

have a capacity of approximately 6,000 cubic yards, it would be lined with 40 mil EPDM liner (or equivalent),

and have a lined, armored overflow channel on the northwest end leading to the adjacent stormwater pond. A

decant tower and perforated pipe would be installed to capture drainage water from the tailings. This would act as

a sump from which to pump recycled tailings water to the makeup water tanks or pond.

Page 5: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 5

Figure 5

The construction of the second phase tailings pond is optional and implementation would depend upon whether

sustained future production at the mine requires more tailings storage volume. Construction would consist of

building a second pond on top of the first phase pond after it is filled with tailings. Figures 6 and 7 display an

approximation of the phase two construction. The phase two pond would cover approximately the same area as

the first and extend southwestward from the phase one development. The temporary road around the first phase

pond would be abandoned and relocated around the second phase pond. The same type of liner and decant system

as described above for phase one would be used in the phase two pond.

Page 6: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 6

Figure 6

Figure 7

Page 7: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 7

Following the construction of each phase, the outside slopes of the pond berms would be revegetated with native

forbs and grasses, a six-foot high cyclone fence would be erected around the perimeter of the tailings pond berm

to restrict wildlife access, and the southeast end of the pond would be gently sloped.

Final reclamation of the tailings ponds would consist of dewatering, stabilizing with cement (if needed), placing a

two-foot thick lift of native fill material over the surface of the tailings, recontouring the outer berm to achieve 2:1

(H:V) slopes, and applying revegetation treatments (seed, fertilizer, mulch, and slash).

All tailings would be transported as a slurry from the mill building to the tailings pond via a plastic pipeline.

After the solid tailings are deposited in the pond the residual water would be pumped via another pipeline up to

the mill makeup water tanks or pond (Figure 4).

An alternative tailings disposal method that may be employed would be a sand or paste backfill system that

involves partially dewatering the tailings slurry, possibly adding binders such as cement, and pumping it back into

the mine to fill voids left by ore and waste rock removal.

Waste Rock Dump

The existing waste rock dump is expected to be filled when construction of the new decline (a downward sloping

mine tunnel) is completed. Further mine development would require additional space to dispose of approximately

4,600 cubic yards of waste rock. The new waste rock dump would be constructed in two phases. Figures 8

through 10 display an approximation of the waste rock dump. The first phase of the dump would consist of two

separate lifts of waste rock, each being approximately fifteen feet high. Phase 2 would have roughly three fifteen-

foot lifts. Trees, slash, root wads, and topsoil would be retained for future reclamation.

Less than 0.1 miles of new temporary road construction (#503400831 and #503400832) would provide access

across the bottom and top of the dump. All temporary roads would be insloped with a ditch discharging to a

buffered outlet on undisturbed ground on either side of the dump.

Dump reclamation would involve recontouring the dump so that all the slopes were at an approximately 2:1 (H:V)

angle. Stockpiled trees, slash, root wads, and topsoil would be redistributed on the area. The top of the dump

would be backsloped and crowned to direct stormwater away from the regraded dump face and onto undisturbed

ground on either side of the dump. All disturbed ground would be revegetated. The operator would reclaim each

lift prior to construction of the next.

Makeup Water Tanks

Two plastic water tanks of up to 5,000 gallons capacity each would be placed in a gently sloping area just off the

temporary road above the millsite (Figure 4). A 1,000 square foot area would be bladed flat to accommodate the

tanks. The tanks would provide water to the mill via a plastic pipeline. The tanks would receive water pumped

up from an underground sump in the mine and/or recycled decant water from the tailings pond or the makeup

pond.

Page 8: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 8

Figure 8

Figure 9

Page 9: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 9

Figure 10

Process Water Infiltration Areas

The mill process water would be disposed of by infiltration into the ground. Several locations have been

identified on the mine site where process water would be discharged (Figure 4). The existing primary infiltration

pond would serve as both the primary mill makeup water pond and the primary infiltration pond. This pond is

presently leaking water from a small seep on the outside of the berm lying between the pond and Warren Creek.

This leak would be repaired by temporarily dewatering the pond and constructing an impermeable barrier along

the streamside perimeter by excavating a slit trench and backfilling it with bentonite. Once the pond has been

dewatered, the fine clay material that has built up on the bottom of the pond would be removed and placed on the

waste rock dump in order to increase the vertical infiltration rate in the pond.

Three smaller infiltration basins ranging from 1,000 to 3,000 square feet in surface area would be constructed to

dispose of waste process water (Figure 4). The basins would each be excavated approximately five feet deep with

the excavated material bermed up around the perimeter to increase their capacity. Water levels in the three basins

would only be allowed to rise to within two feet of the top of the berm.

Page 10: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 10

Process Water Management

The primary source of mill water would be the 50 gallons/minute of water that is produced by the underground

workings of the mine. The operator currently holds a water right on this source. There would be no discharge of

process water to Warren Creek.

Approximately 120 gallons/minute of water is required to operate all of the gold recovery equipment in the mill.

When milling processes are occuring additional water from makeup water tanks or the makeup water/infiltration

pond would be used to make up the approximate 70 gallon/minute shortfall.

Stormwater Management

There are three primary sources of stormwater runoff at the Rescue mine; the temporary roads, the mill site work

pads and waste rock dumps, and flow in an intermittent stream that is diverted around the mine site. Drainage

from these sources would either be dispersed overland or directed into infiltration basins.

Stormwater that falls on the mill site work pads and existing waste rock dump would run overland to the primary

infiltration pond. Temporary roads would have water either directed to the stormwater infiltration basin via

ditches or have waterbars that direct flows to fill side of the road.

The intermittent stream directly south of the main mine site runs for a couple of months during spring snowmelt

and into early summer. It flows directly into the main mine site where it is captured in a catchment basin and

piped and/or ditched to the stormwater infiltration basin. After the new tailings pond is constructed, the

reconstructed stormwater infiltration pond would have a storage capacity of approximately 90,000 gallons. This

may not be sufficient to contain the total streamflow during snowmelt. As such, an approximately 200 foot

existing overflow pipe would be capped and perforated or slotted in order to distribute the flow over a larger

section of ground for infiltration rather than have a single concentrated discharge at the end of the pipe.

Additionally, structures to divert all or part of the stream across the minesite to the makeup water / infiltration

pond would be installed. If water from the perforated overflow pipe consolidates into an overland flow, the

stream would be diverted to the degree needed to avert overland flow into Warren Creek.

Temporary Roads

Approximately 0.3 miles of temporary road would be newly constructed. New temporary road construction

would be needed in conjunction with the new waste rock dump, both phases of the tailings pond construction, and

the exploration drilling (Figure 11).

Road maintenance would occur throughout the project area on existing temporary roads. With the exception of

temporary road #503400830, maintenance activities would include; but is not limited to, routine blading, the

removal of slides/slumps, maintenance/installation of safety berms, maintenance/installation of waterbars,

cleaning of culverts, ditch cleaning, and clearing of brush/trees encroaching the roadway. Temporary road

#503400830 would include the installation of a culvert in addition to other activities described above. Table 1

describes the temporary roads associated with the proposed action.

Page 11: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 11

Figure 11

Page 12: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 12

Table 1. Proposed Temporary Road Construction and Maintenance

Road # Activity

Approximate

Mileage

503400800 Maintenance 0.3

503400810 Maintenance 0.8

503400811 Maintenance 0.3

503400812 Maintenance 0.5

503400813 New Construction and Maintenance 0.1

503400830 Maintenance and Culvert Installation 0.3

503400831 New Construction and Maintenance <0.1

503400832 New Construction and Maintenance <0.1

503400840 New Construction and Maintenance 0.1

Exploration Projects

Five drill pads would be constructed in the project area (Figure 12). Four drill pads would be constructed in or

adjacent to temporary roads already present on the landscape. One drill pad would require the construction of

approximately 0.1 miles of temporary road (#503400813) to access the pad. Drill pads would be constructed to

an approximate dimension of 15 feet by 30 feet to accommodate the drill rig and associated equipment.

Following drilling, erosion control measures (drainage and revegetation) would be implemented as temporary

reclamation. When there is no further use planned for a pad in the foreseeable future, it would be reclaimed by

restoring the pad and the access road to the original hillslope contour.

Trenching could occur anywhere within the cross-hatched area indicated in Figure 12. No new roads would be

constructed; a tracked excavator would travel overland to access trenching sites. Trenches would be no more than

12 feet wide, 5 feet deep, and 20 feet long. Rock samples and photographs would be taken of any vein exposures.

Trenches would be backfilled and reclaimed (seed, fertilizer, mulch, and slash) in the same operating season as

they were opened. Any trees and slash cut to provide overland access for machinery would be scattered back over

these routes.

Final Reclamation

The existing reclamation plan for the Rescue mine would be updated to reflect the additional reclamation tasks

associated with the proposed expansion. Removal and disposal of all structures, equipment, hazardous materials

and other debris would be required. Earthwork would be done to recontour the tailings ponds and waste rock

dumps to reduce slope angles in order to reduce erosion and promote revegetation. All roads would be fully

recontoured. All disturbed ground would be revegetated. Final approval and implementation of the Plan of

Operations would not occur until a bond has been posted to cover the costs of reclamation.

Page 13: Rescue Mine Expansion Projecta123.g.akamai.net/7/123/11558/abc123/forestservic... · Rescue Mine Expansion Project Details of the Proposed Action Proposed Action This alternative

Rescue Mine Expansion Project

Page 13

Figure 12