  • SageRider, Inc

    Reservoir Monitoring Services Overview

    *

  • Introduction

    SageRider, Inc founded in 2008Started based on a need, recognized through consulting, to advance a new monitoring concept into a viable field development technologyFounding management team has background as pioneers in the tubing conveyed perforating industrySageRider positioned with two primary business segmentsSubsurface Surveillance - includes SageWatch, external casing or internal casing real-time P/T monitoring, and Fiber Optic cable installation for DTS and DAS monitoring.Completion Systems includes EasyRider multi-zone external casing gun system with ball drop actuation, propellant systems used for cased hole and open hole stimulation, and Tubing Conveyed Perforating.

    *

  • SageRider Working Areas - USA

    *

  • Why SageRider?

    *

  • Turnkey Approach to entire project Dedicated project manager on each job Source and ensure compatibility of all aspects of the installation Work closely with all services providers on project from start to finish Supply all aspects of the project with single supplier. Project planning Manufacturing of all components including gauges Field Deployment Integration of data for real-time access Experience Safety is of upmost importance Quarterly Bonus is linked to safety.

    *

  • SageWatch

    Subsurface Surveillance System

    *

  • Pressure/Temperature Gauges deployed outside or inside the casing in a multi-drop format to allow multiple, isolated measurements along the length of the wellbore.These measurements can be reservoir only, wellbore activity only, or both.System is powered from surface to collect real-time data, continuously.Data sample rates are programmable from surface, can be transmitted to Operator office, or downloaded locally at the data collection unit.

    What are we talking about ?

    *

  • All equipment is integral to the casing stringAll monitoring equipment is outside the casingNo change to casing ID dimensionCement Isolates each WatchStation Perforate to connect to the reservoir

    External SageWatch System

    *

  • Straight Vane Eccentric Centralizer

    Gauge Carrier with 1.25 Pressure Temperature Gauge

    Perforating Gun

    Y-Block with Rupture Disk and RA Tag

    Firing Head

    Straight Vane Eccentric Centralizer

    Pressure Transmission Line

    Overall Length 24.75

    Layout External System

    *

  • Frac monitoring of offset wellsFrac monitoring of host wellIdentify frac communication between layersIdentify unstimulated zonesIdentify communication between wellsIdentify completion system efficiency

    Applications / Benefits

    *

  • *

  • Internal SageWatch System

    All monitoring equipment is conveyed on tubing inside the casingHydraulic set Packers isolate monitoring pointsCan utilize existing wellsEquipment can be retrieved from the well, redressed, and reinstalled into another well

    *

  • Layout Tubing Deployed

    Gauge Carrier with inset for 1.25 Pressure /Temperature Gauge

    Rigid Steel Gauge Clamps

    Transfer Sub

    Retrievable Hydraulic Packer

    Transfer Sub

    Power/Data Transmission Cable

    Overall Length 27.25

    *

  • *

  • Data Collection

    Specifications

    *

  • Data Collection Specifications

    Electronic Pressure & Temperature Gauges with Quartz Pressure TransducerPressure Rating = 0 -16,000 psi working pressure Temperature Rating = 392 deg F / 200 deg CData Polling = up to 1 Sample / Second / GaugePressure Resolution = .01 psi Temperature Resolution = .01 deg FPressure Accuracy = +/- .02% within calibrated range Temperature Accuracy = +/- 0.9 deg F within calibrated range Dual in-line cable heads with internal electrical feed-through, no Y-blocks

    *

  • Data Collection Specifications

    SageRider specification introduced Fault Protection to multi-drop permanent gauge installationsDual built in current limiting assures no single gauge can draw excessive current and upstream communication is still available with a downstream line fault.Double redundancy for all current limiting circuit components ensures against loss of communication with downstream gauges in case of component failureSageRider purchased all permanent gauge manufacturing and IP from gauge provider and re-branded as Ranger Gauge Systems in April, 2011.

    *

  • *

  • *

  • Wellbore Construction Dimensions External Installation

    Desired Casing SizeMaximum System OD, inPossible Hole Size, inClearance, in2-7/8"5.1306.1250.9956.0000.8703-1/2"7.5007.8750.375Upset8.5001.0003-1/2"6.0006.5000.500Non-Upset6.7500.7504-1/2"6.7507.5000.7507.8751.1255"7.2507.8750.6258.2501.0005-1/2"7.7508.2500.5008.7501.0007"9.2509.8750.62510.6251.3757-5/8"9.87510.6250.75011.0001.1259-5/8"11.87512.2500.37514.7502.875

    *

  • Why ?

    *

  • Identify Optimum SpacingIdentify per Layer Drainage RadiusIdentify System Complexity between LayersCalibrate Reservoir Model

    Applications - Field Development

    Gauges

    Reservoir Layer Pressure

    *

  • Applications - Frac Monitoring

    Identify Frac Communication between LayersIdentify Non-Stimulated AreasIdentify Communication between WellsIdentify Completion System Efficiency

    Gauges

    Real-Time Monitoring During Offset Frac

    *

  • Applications - Frac Monitoring

    Identify Frac Communication between LayersIdentify Non-Stimulated AreasIdentify Communication between WellsIdentify Completion System EfficiencyInternal Casing Pressure Monitoring during Frac

    Gauges

    Gauges

    Real-Time Monitoring During Frac

    *

  • Applications - Production Monitoring

    Identify Contributing ZonesIdentify Contribution Change over TimeIdentify CrossflowOpen Wellbore AvailablePost Completion Custom Installations

    Gauges

    Hydrocarbons

    Is this the profile?

    *

  • Applications - Production Monitoring

    Identify Contributing ZonesIdentify Contribution Change over TimeIdentify CrossflowOpen Wellbore AvailablePost Completion Custom Internal Installations

    Gauges

    Hydrocarbons

    Or is this the profile?

    *

  • Applications - Production Monitoring

    Identify Contributing ZonesIdentify Contribution Change over TimeIdentify CrossflowOpen Wellbore AvailablePost Completion Custom Internal Installations

    Is this the profile?

    Gauges

    Hydrocarbons

    Or is this the profile?

    *

  • Fiber Optic Systems

    *

  • The fiber is the sensor

    Standard multi- or single-mode optical fiber

    T1 T2 T3 T4 .

    Measurement along a 10km fiber = 10,000 sensors

    Distributed Fiber Sensing

    1-10m pulse of light

    Backscattered light provides

    measurement point every 1m

    T9,999

    T9,998

    T9,997

    *

    2.unknown
  • Distributed Acoustics

    Production Monitoring inflow allocation Monitor flow regimes (slugging, bubble) Monitor induced fracturing and fluid placement Changes in proppant concentration Injection and stimulation profiles Sand detection in boreholes and flow lines Completion integrity problems and leaks

    Applications

    Distributed Temperature

    Zonal flow contribution Production monitoring below ESP Injection performance monitoring Stimulation profile verification Identification of gas breakthrough Gas Lift Valves & ESP monitoring Flow behind casing identification Inter-well connectivity Tubing & packer integrity

    *

  • SageRider - Permanent Installation

    Surface Cabling

    to EXiiUS

    DTS system

    Stainless Steel fiber conduit

    installed behind casing

    Continuous / Real-time Monitoring

    Cement Cure

    Frac monitoring

    Well Clean-up

    Production

    Declining

    *

  • Surface Components

    *

  • Frac Temperature Map - Warmback

    Time

    Depth

    1

    2

    4

    3

    8

    9

    10

    11

    12

    5

    6

    7

    *

  • Cluster 1: 15,804 Feet

    Cluster 2: 15,968 Feet

    Cluster 3: 16,131 Feet

    Cluster 4: 16,294 Feet

    Cement breakdown

    Acoustic Data Shows Poor Hydraulic Isolation

    Depth

    Time

    *

  • Temperature Interference from Offset Frac

    Note very small temperature changes

    detected while fracing the offset well

    Data provides a measurement of fluid movement

    related to the location of the intersecting fracture

    *

  • Track Record

    *

  • As of November, 2014

    109 well installations within the last 4 years 45 External installations 64 Internal installations Total of 366 WatchStations (Gauges) installed Success rate based on 4 years functionality for < 350 deg F = 98% Over 5 Million Hours of data collected since 2010 Areas Installed - Bakken, Eagle Ford, Barnett, Haynesville, Marcellus, Niobrara, Uinta Basin, Pinedale Anticline, CanaOne well installed in New Zealand for Shell / Todd (16 Watch Stations).

    *

  • Questions?

    *

    Core

    125m Cladding

    165m Polyamide

    Coating

    Carbon layer