Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Resource Assessment and Implementation of DLC Programs
for Large Customer
2003. 10. 21
Chang-Ho Rhee, KERI
KERI 1
Outlook for demand - Demand forecasting
Demand forecast and DSM projection– Increase by average 8.4% per year last decade – Consumption per person : 5,800kWh in 2002– DSM deduced 3,130MW of peak demand in 2002 – DSM projection reach 10% of system peak in 2015
< Demand Forecast (unit 10 MW) >
3,9293,0692,2041,642Net increase
5.3%8,5074.5%7,6473.6%6,7813.0%6,22020119.4%6,5597.5%6,1235.6%5,6844.1%5,3742006
---8.4%4,5772002---2,0441992
Annual increasing
ratePeak load
Annual increasing
ratePeak load
Annual increasing
ratePeak load
Annual increasin
g ratePeak load
Upper scenario(excluding DSM)
Upper scenario(including DSM)
Baseline demand (excluding DSM)
Baseline demand(including DSM)
Year
* Source : 1st power demand/supply baseline plan
KERI 2
Outlook for Supply Capacity expansion plan– New capacity Need : 35,000MW by 2015– New expected capacity : 25,250 MW by 2011 (base on
generator’s plan)– Generator’s plan classified by status– In case of capacity plan delayed, decrease in reserve margin
below 10% after 2008
< Long-term power demand/supply outlook>
24.9%7,9066393952,0442,3772,4526,220201117.8%6,5275564671,8641,8671,7725,3742006
15.3%5,3813884281,3991,5931,5724,5772002(actual)
TotalHydroOilLNGCoalNuclear
Reserve margin
capacity (10 MW)Demand (10MW)
KERI 3
DSM in Korea –Programs
Programs at present Peak cutting : Special rate and Remote A/C Energy efficiency : lighting, motor, inverter Load Shift : Cooling/heat storage, Vending machinePR and ME&V system development
Direction after deregulation (2001)Administration : Utility (KEPCO) → Government (MOCIE) Funding : Utility cost → Public Goods ChargePrograms : introduction of DLC, DR M&V : Resource Assessment, Monitoring, Verification etc.Investment : increase up to 1% of total revenue
KERI 4
DSM in Korea –DLC programs
Remote controlled A/C Program- start year : 2000 - subject : KEPCO - target customer : residential, small commercial- target measure : air conditioner (package type)
Direct Load Control Program- start year : 2002- subject : KEPCO, KEMCO - target customer : large customer of commercial & industrial- target measure : electric furnace, Pump, HVAC, etc.
KERI 5
Methodology for forecasting DLC Potential
Load Characteristics Approach
Energy Consumption Approach
Diffusion Model Approach
KERI 6
Load Characteristics Approach
estimating component ratio
Energy consumption
ratio by customer
Load curve by customer, end-use,
seasonal hourly
Hourly load factor by load
type
Load component ratio
KERI 7
Energy Consumption ApproachEstimating cooling demand through the load difference between system load by season
PowerConsumption
Cooling demandIn August Load at 15:00
Residential monthlyEnergy consumption
Residential daily loadPattern by month
Commercial monthlyEnergy consumption
Commercial coolingDemand in August
Commercial daily loadPattern by month
Estimation of whole load
ResidentialCooling demand
Service coolingdemand
Public coolingdemand
Industrial coolingdemand
Public monthly energyconsumption
Public cooling demandIn August
KERI 8
Energy Consumption Approach (cont’d)
30,000
32,000
34,000
36,000
38,000
40,000
42,000
3 4 5 6 7 8 9 10
8,100MW
(month)
(MW)
30,000
32,000
34,000
36,000
38,000
40,000
42,000
30,000
32,000
34,000
36,000
38,000
40,000
42,000
3 4 5 6 7 8 9 10(month)
(MW) (Year 2000)
32,000
34,000
36,000
38,000
40,000
42,000
44,000
3 4 5 6 7 8 9 10(month)
(MW)
32,000
34,000
36,000
38,000
40,000
42,000
44,000
32,000
34,000
36,000
38,000
40,000
42,000
44,000
3 4 5 6 7 8 9 10(month)
(MW)
8,500MW
(Year 2001)
Applicable to cooling load - the difference between peak load and base load - peak load : load at 15:00 in July, or August- base load : average load of April and October
KERI 9
DLC Resources
Available DLC Resources in Korea Cooling
Ventilating
Heating
Pumping
Electric Furnace, etc
KERI 10
DLC Potential estimation- commercial
Analysis 1 and 2 used top-down approach, but analysis 3 used bottom-up approachThere are some variations in results by approaches
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
(MW)
2002 2003 2004 2005 2006
Res identia l Cooling Demand
Alt.1Alt.2Alt.3
KERI 11
Incentive level in DLC program
- LOLP 1.0 day: 2,440 Won/kWh
- LOLP 0.7 day: 3,480 Won/kWh
• Fixed cost of GT (Capital + O&M Cost) : 58,000 won/kWh
• Setting the standard of LOLP: 0.7 -1 day
Alternative 2
- RIM 2.0: 2,615 Won/kWh
• Applying a compensation payment which satisfies RIM test.
• Estimating the level of incentive corresponding to basic B/C (applying basic B/C as 1.0 - 3.0)
Alternative 3
900 Won/kWh
• Estimating real time MCP when DLC starts
• Average SMP in Korea 45 won/kWh
• Spike rate when the supply was shortened : 20 times
Alternative 1
IncentivesProcessClassification
KERI 12
Goal and Subjects of DLC Program
Types of DLC Program- Normal load reduction- Emergency interruption Load- Secured system load- Peak load reduction- Demand Reserve
Objects of DLC Program- System Availability- Market Price Stability- System Security- Profit model
KERI 13
Conclusion
This Paper investigate three approaches to evaluate potential of DLC effectsDemand estimation should be added to reflect component ratio by consumerWe could apply market price or avoided cost in peak periods as criteria for incentive