RESOURCE LEVELING VS RESOURCE ALLOCATION
Resource Leveling: - How to smooth resource demands? - No problem with time or resources. - Strategy? - Method of moments? - Method of double moments? - Multi-Resources? - Desired (best) profiles?
Resource Profile:
Strategy: __________________________________________________________________________
Example: Two schedule alternatives have associated resource profiles as shown below, which alternative would you
choose and why? Also calculate the total worker-weeks needed for both cases:
Mx =
My =
R Start Delay 2 A 1 B 1 C 1 D 2 E
60
Resource Allocation: - Allocate limited resources to top-priority activities. - Strategy? - Heuristic rules - Inconsistency among existing software - Excel Implementation - EasyPlan Optimization
Floats? Resource limit = 2 / day Solution
Strategy: __________________________________________________________________________ Another Solution Priority Rules:
R 2 A 2 B 1 C 1 D 2 E
R Start Delay 2 A 2 B 1 C 1 D 2 E
R Start Delay 2 A 2 B 1 C 1 D 2 E
61
Resource Allocation Example:
Time
Eligible Activities
Resources (limit = 2)
Duration
Rule (ELS)
Decision
Finish Time
Microsoft Project Solution?
Case of Multi-Resources? Case of Multi-Resources Multi-Skills?
62
MEETING DEADLINE
- Activity time-cost relationship? Linear vs Discrete (Cheap & Slow versus Fast & Expensive)
- Cost Slope?
- Project time-cost relationship?
- Strategy to meet deadline? ________________________________
________________________________ ________________________________
Example 1: Durations and cost slopes are shown. We need to meet a 12-day deadline. Example 2: Normal and crash data for the tasks are shown. What is the optimum project duration?
How can the project be finished in 20 days?
A 5
D 5
B 5
C 4
100
200 200
50
________________________________
________________________________ ________________________________
_________________________________________________________________________
_________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________
________________________________
________________________________ ________________________________
63
CASH FLOW ANALYSIS
Factors Affecting Interest Payment: Credit from suppliers Reporting Periods (payment frequency) Interest rate Subcontracting Mobilization payment Better scheduling Hold back percentage Bid Unbalancing
Terms Used Every Period: - Cost = (Direct + Indirect) estimates - Expenses < = Cost (if suppliers can give you a credit) - Budget = Cost + Markup * Cost = Cost (1 + Markup) - Income = Owner payment = Budget – Holdback If Everything goes well: - Expenses < = Cost - Income = Budget - Profit = Cost * Markup
Cost ($)
Cumulative Expenses
Cumulative Income
Financing area (interest is charged)
Month