Upload
dotruc
View
218
Download
0
Embed Size (px)
Citation preview
Response to NERSA Consultation Paper
06 May 2011
Strictly Confidential 1
Overview
NERSA‟s consultative approach is welcomed
This response pertains to wind energy projects seeking a PPA under REFIT
Feedback will be provided on assumptions made in the NERSA Consultation
Paper that are not in line with current industry practice and experience
We look forward to an appropriate tariff resulting which will correctly shape this
new industry in South Africa
1 AIIM, Umoya Energy & Hopefield Wind Farm
Umoya‟s Credentials
Umoya Energy (Pty) Ltd was established by African Infrastructure Investment Managers (Pty) Ltd (“AIIM”) as a SPV to develop the Hopefield Wind Farm in 2008
AIIM is an Infrastructure Equity Fund Manager established in 2000 by Old Mutual and Macquarie. AIIM & Kagiso have also established an Empowerment Fund
AIIM has circa R 8.7 billion (US $ 1 billion) of Equity funds under management through 4 investment funds
Funds are deployed as Equity in core infrastructure projects across Africa covering Toll Roads, Telecoms and Power
In RSA AIIM is the largest equity investor in private infrastructure projects – principally the three major Toll Roads and Kelvin Power Station
Renewable energy is a competing asset class and needs to yield returns commensurate to other infrastructure assets to attract equity investment
Umoya (and AIIM) support NERSA‟s objectives of REFIT tariffs that will yield 17% real IRR to Equity Investors
Hopefield Wind Farm
The Hopefield Wind Farm has been under development
since mid 2008, hence the project is very well understood
Significant investment has been made (>R10m) to prove the
resource, to understand the site, to achieve permitting, to
secure competitive EPC pricing, and to develop a bankable
finance model and project.
Infrastructure Equity Investors require certainty of the tariff
they will receive in 3-4 years time when the project will reach
financial close
Decisions to continue developing the Hopefield site were
based on:
April 2009 tariff of R1.25 per kWh plus full indexation
Equating to tariff in April 2011 terms of R1.35 per kWh
The NERSA revisions were a surprise and the proposed
tariff of R0.938/kWh plus partial indexation renders the
Hopefield Wind Farm un-bankable
Date Milestone
Sep 2008 Land secured
Dec 2008 Met mast installed
Sep 2009 Environmental Authorisation
received
Oct 2009 Local rezoning approval
received
Aug 2010 Provincial rezoning approval
received
Sep 2010 CAA approval and SAAF
approval received
Oct 2010 Tenders run for construction
works
Dec 2010 Lead arranger appointed
2 Review of NERSA proposal
Our Approach
Reviewed the impact of the proposed tariff and partial indexation in our detailed
bankable project finance model
Debt Service Coverage ratios were not met
Targeted equity return levels were not met
Created a replica levelised cost model to recalculate & understand the proposed
NERSA wind tariff based on the assumptions stated in the Consultation Paper
Studied the Electric Power Research Institute (“EPRI”) July 2010 report „Power
Generation Technology Data for Integrated Resource Plan of South Africa‟
“Backsolved” from the NERSA tariff to seek to understand the inputs
Compared the assumptions to those observed by Umoya in the South African
market and used in the bankable financial model
In Q4 2010 Umoya ran tenders for turbine supply, balance of plant electrical and
balance of plant civil works so has actual data on market prices for South African wind
farms
Umoya has interviewed lead arrangers and has made a selection, and hence has
accurate pricing on debt and foreign exchange hedging rates
Levelised Cost vs Project Finance Models
Levelised cost Project finance
Industry and Banks generally use a Project Finance Model to appraise projects
The NERSA REFIT tariffs, however derived, must be tested and found to deliver a
17% real IRR in a properly constructed Project Finance Model – a reality check
Assumes equity earns returns
alongside debt in early years – up to
40% of cash flows to equity
Timing of cash flows taken in to
account – equity earns only 20% of
cash flows in early years despite
investing 30% of capital required
Assumes debt is repaid over 20
year project life
Debt is repaid over 15 years in
preference to equity
Capital Cost – Real vs Assumed Inputs
Real market prices appropriate to project construction start date are an imperative
NERSA‟s assumed inputs appear incorrect – 25% too low
Umoya*
Cost
R/kW
NERSA*
Cost
R/kW
Umoya
%
NERSA
%
Overnight capital
cost15,407 15,150 80.5% 95%
Land 407 319 2.1% 2%
Project dev fees 909 - 4.7% 0%
Grid + Interest
during
construction
1,676 478 8.8% 3%
Debt Service
Reserve Account748 - 3.9% 0%
Total 19,147 15,947 100% 100%
*NERSA inputs from EPRI report and Consultation Paper para 6.7 and replica model; Umoya inputs from South African tender
process
Replica levelised cost model cannot
accommodate the proposed 6-10%
developer fee at R0.938 tariff
Interest during construction accounts
for 7% of Umoya‟s total cost, Grid
costs account for <2%
Funding a Debt Service Reserve
account has not been included in
NERSA‟s total project cost
EPRI figures are in Jan 2010 terms –
no inflation adjustment has been
made – cost are at lower end of
market prices seen by Umoya
Allowing for Dev fees closer to 10%, we suggest R20,000/kW = $2,700/kW
Approximately 60% of the capital cost of a wind farm is denominated in Forex
The Rand is a very volatile currency
Foreign Exchange
The current low rates may not be available 12 months from now at financial close -
Options to hedge this exposure have been priced at over R70m
Conservative FX assumptions are required to accommodate some adverse
movements – alternatively project costs must be increased to include hedging costs
Oct 2008 1 EUR = 14.0 Rand
Apr 2009 1 EUR = 12.0 Rand
Apr 2010 1 EUR = 10.0 Rand
Operating Costs – Slide 1 of 4
New industry - so it is difficult to assess the operating costs in years 10 - 20 with any certainty. The past 10 years show original estimates out by 4 to 5 X.
Key components fail << 20yr “design life” – e.g gearboxes = 8 years
NERSA‟s suggested R0.118 per kWh is low when compared to EPRI‟s recommendations, industry analysis from Wind Energy Update (EUR 0.019 per kWh) and Deloitte (EUR 0.016 - EUR 0.022 per kWh)
Operating costs – Slide 2 of 4
Developers can buy certainty for the first 10 years from OEM Vendors
The second 10 yrs is at large – Developers (Investors) must plan for
component replacement, e.g. Gearbox ($500k), Rotors ($200k) etc
RSA CPI does not adequately provide for FX movement 10 - 20 yrs ahead
and Developers (Investors) must hence take a view.
Operating Costs – Slide 3 of 4
What should NERSA / Developers / Investors assume for yrs 10 – 20 ?
Truth is, no one knows
The Wind Energy Update report suggests a material upward trend from E0.022/kWh
Operating Costs – Slide 4 of 4
Allowance made for major
component costs and
increased service costs in
years 11-20
Major components will be
priced in foreign currency -
allowance made for under-
recovery of ZAR depreciation
Unknown if service providers
will give „spare parts
inclusive‟ warranties after
year 10.
Will depend on size of future
market.
Umoya‟s View – As per below, average of R0.24/kWh before local overhead,
increased security and insurance costs, plus costs of energy forecasting
After adding in for the above we suggest not less than R0.30/kWh
Energy yield
The Consultation Paper uses an expected capacity factor of 27% from a typical
100MW wind farm in the calculations
This is slightly high for the country as whole but can be accepted for early projects
as the capacity factor predicted from the P50 energy yield assessment
Banks only evaluate project cash flows based on P90 energy yield expectations
(have a theoretical 90% chance of being achieved) - these are 15-20% lower than
the P50 predictions
Tariffs should therefore be set using P90 energy yield predictions (equating to a
capacity factor of around 23% from this typical farm) to ensure that projects are
able to meet their debt service and equity return targets
Debt Structure and Cost
Tenor Debt to be repaid over 15 years not 20 years as per NERSA
Gearing 70% debt funding and 30% equity funding is in line with
Umoya‟s experience
Cost of debt Despite current low JIBAR rates, the markets expect rates to
increase over the next 15 years
Cost of debt over the project life will be closer to the 15 year
interest rate swap rate rather than 3 month JIBAR
Debt margins are between 3-4% and will only be refined once
the risks in the PPA are assessed
Additional costs will be incurred to hedge interest rate
exposure
The cost of debt is significantly higher than
that proposed by NERSA
Umoya NERSA
Tenor 15 years 20 years
Gearing 70% 70%
Interest rate 8.46% 5.55%
Margin 3.50% 4.38%
Hedge costs 0.50% 0%
Total cost 12.46% 9.93%
Indexation
As equity returns are back-weighted until after debt is repaid indexation on the
full tariff is crucial to ensure that investor returns are not eroded by inflation
Without indexation of the full tariff, the starting tariff must be significantly
increased from those published in 2009
Indexation on the full tariff is recommended
Timing of Tariff Review
Whilst we agree the tariff should be reviewed periodically Investors need certainty to
make decisions about the viability of their projects through the development period
Tariffs should be fixed for at least 3 - 4 years to enable sites to be selected,
developed, financed and constructed before the tariff is changed
Recommend that tariff reviews speak to projects being implemented in 3 – 4 years
time – e.g set today for projects targeting financial close in 2014 (with mechanism to
cater for regulatory delays)
3 Conclusion
Conclusion
REFIT tariffs that yield real returns of 17% to Equity are supported
NERSA must ensure that their proposed REFIT tariff works within the financial models and
governance criteria used by the market – this is reality
NERSA must insure that all Capex costs are included for and are market related
NERSA must consider 20 year risk in determining the O&M component of the REFIT tariff
REFIT tariff revisions should apply to projects being implemented at least 3 – 4 years in the
future to enable investment decisions to be made with tariff certainty
Umoya is of the view that the REFIT tariff for wind energy should be reinstated to
where the market expected it to be, i.e. R1.35 plus full indexation in 2011 terms
Thank You
Thank You