Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Restoration Techniques forThree High Gradient Tributaries
in Karnowsky Creek, Oregon Coast Range
River Restoration Northwest SymposiumSkamania, WA
January 30 – February 2, 2006
Johan B. HogervorstHydrologist, Siuslaw National Forest
• General overview of the project
Karnowsky Creek Stream Restoration
• Techniques we’ve tried in twointermittent channels
• Lessons learned for each channel
2
KarnowskyWatershed
SiuslawEstuary
FlorenceMapleton
Karnowsky Creek,Lower Siuslaw Watershed
Karnowsky Valleypre-project condition
Siuslaw River
Duncan Inlet
PrivateUSFS
Head of Tide
OriginalHomestead
1932
Tidal Influenceon Private Land
Ditches
Drained pastureland
Deeply incised ditches
3
Karnowsky Creek Stream Restoration
Private
USFS
Head of Tide
OriginalHomestead
Aggraded Reach
Down cutDown cut
Flow
Main Stem Restoration Objectives
• Restore water table/wetland habitat
• Reconstruct a meandering channel that regularlyconnects with its flood plain
• Reestablish native vegetation• Create complex fish habitat through
addition of large wood
• Work with a collaborative partnership in the Siuslaw Basin
Karnowsky Creek Stream Restoration
1.5%
MaintainExistingSpawning
.65%
.1%
Lower Two Miles of Main Stem Channel
4
Fall, 2002Fall, 2003Spring, 2004
Channel
Wood
Floodplain
Hummocks
Karnowsky Creek Stream RestorationTributary Restoration Objectives
• Demonstrate results to private landowners
• Reestablish natural gravel transport
• Create additional fish spawning areas
• Reduce/eliminate excessive bank erosion
• Recover water table to enhance ephemeral flow
Tributary #2
Tributary #3
UpperMain Stem
Tributary #1Tributary #1Tributary #1
• Work with a ditch that is not severely incised
• Recreate meanders where bank erosionis attempting to form them
• Reconstruct channel where a remnanthistoric channel exists
• Raise bed level of ditch where goodroot strength in banks exists
5
Tributary #1, 2003
Old
New
Meander Reconstruction
Cedar buriedat grade
Cedar keyedinto bank
12
34 5
6
Fill and Capwith rock
400 feet of newChannel construction
Filled Ditch
New Channel
Tributary #1 Pre- and Post-treatment long profiles, 2003
3035404550556065707580
0 500 1000 1500
Slope Dist (ft)
Elev
atio
n (ft
)
BeforeAfter
1 2 3 4 56
1.4%
2.0%
1.7%
New Channel@ 1.4%
6
Tributary #1 - Meander construction
Sept, 2003
Tributary #1 - Meander construction
7
Tributary #1 - Meander construction, wood at grade
Tributary #1,Meander construction,
Wood at grade
8
Sept, 2003
Tributary #1,Meander
construction,wood at grade
Ditch to befilled & capped
with rock
Buried wood being finished
New MeanderOld Ditch
Finishing upper meander #6 and Ditch Fill/Cap section
Sept, 2003
9
Winter flow, meander #6 – upper end
Buried wood
January 7, 2004
Winter flow, meander #6 - middle
January 7, 2004
10
Winter flow, meander #6 – lower end
January 7, 2004January 3, 2006
Buried Wood
December 1, 2005
Tributary #1,Meander #5,
keyed-in woodat high flow
Cedar log
11
Tributary #1, Meander #3, keyed in wood
January 19, 2006
Buried wood
January 19, 2006
Wood jam
Tributary #1, Meander #2, gravel accumulation
12
Tributary #1 - Partial ditch fill capped with rock
January, 2004January, 2006January, 2006
Tributary #1 – Lower 400’ of channel construction
Sept, 2003
13
Tributary #1,Lower channel Gravel seeding
• No wood at grade inthis channel
• Gravels weresprinkled in channel
Sept, 2003
Sept, 2003
Reference TreeReference Tree
January 7, 2004
Lower Tributary #1- channel construction
14
• Wood keyed into banks and bed workedwell for stability of meanders. Bed erosion occurred without wood in newchannel section.
• New meanders built off of slightly entrenched channel doing well. Bank erosion reduced.
• Substrate currently moving throughthe system.
Tributary #1 observations & lessons learned
• Gravel seeding in newly constructedchannel must account for shear stressand proper substrate size.
• Partially filling the ditch and cappingwith rock worked well where there was existing root strength in banks.
• New alluvial fan area at the bottom isstill evolving.
Tributary #1 observations & lessons learned
15
Karnowsky Creek Stream RestorationUpper Main Stem Restoration Objectives
UpperMain Stem
• Build new channel to replace extremely incisedditch in upper valley
• Work with existing pieces of old channel,which have historic meander geometry
• Learn from lessons of Trib. #1
• Incorporate valley gradient changesinto new channel
90 0 90 180 270 Feet
N
EW
S
Upper Main Stem Channel, 2002-2004
Winter 2004/2005 – first flow
2003 & 2004 – treated riffles with gravel and wood, armored pool tail crests
2002 – initial construction
Fan #4Fan #3
Regrade
Fan #1
Fan #2
Diversion pond/structure
2004 – plugs placed in ditch andponds connected to main channel
16
Main stemflow
Ditch
Diversion Plug – 2004 Tributary
New Channel2002
2003REGRADE
Stockpile2003
Stockpile2003
Channel Connected2003
POND
Diversion from Ditchinto new upper Channel
Karnowsky Upper Channel Post- Construction Long Profile, 2004
70
75
80
85
90
95
100
105
110
0 500 1000 1500 2000 2500
Slope Distance (ft)
Elev
atio
n (ft
)
2004
0.3%1.6%
0.8%1.6%
0.5%1.1%
1.04%
17
Upper Channel Construction
Upper Channel Construction
18
Winter Flow, January 2006
Main stem Side trib.
New channel
Scour holes in remnant channel section
19
Upper Channel Wood
Built up outsidemeander
CorrespondingPoint bar Buildup
Upper Channel observations & lessons learned
• Don’t short circuit the gravel transport. Gravelscoured at the top end of the channel is notbeing replaced due to pond deposition.
• Diversion pond is filling and will likely reconnect gravel transport in the first 5 yearsafter water release.
• Transitions from vegetated to non-vegetatedbed were problematic. Wait an extra year?
20
• Steep remnant sections show most scourat this point in time.
• Losing some pool tail crests. Proper substrate size is hard to obtain but is criticalto success.
• Lower half of channel looks very goodincluding flood plain inundation during highflow. Point bars are building but pools are allmaintaining.
Upper Channel observations & lessons learned
In SummaryReconstructing channels at slopes greater than1.5% can be very challenging. It takes lots of
planning, thought and iterative design.
Rectifying severely incised channels is costly and labor intensive. Consider cost benefit.
Tributary #1 is stable and serves as a gooddemo for landowners.
The upper main stem channel is stilltransitioning and will be monitored.
21
Tributary #3 – Step pool channel, 2005
80 0 80 160 Feet
N
EW
S
Tributary #3
Entire DitchFilled
RemnantChannels
2.7% overall = step pool channel
Re-graded valley floor
22
Karnowsky Creek, Trib #3, Long Profiles, 2005 and 2006
7580859095
100105110
0 200 400 600 800 1000 1200Slope Distance (ft)
Elev
atio
n (ft
20052006
2.7%
Tributary #3 construction
Ditch Preparation
23
Tributary #3 – ditch filling