8
Monte Vista Elementary School Modular Bathroom Project Update Board of Education Meeting Information Report No. 7 Date: April 16, 2019 Presented by: Hagop Kassabian, Administrator: Planning, Development & Facilities Stephen Dickinson, Chief Business & Financial Office Revised 04/16/2019

Revised 04/16/2019 Monte Vista Elementary School...Apr 16, 2019  · Modular Bathroom Project Update • Requests have been made to improve restroom access to Monte Vista Elementary

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • Monte Vista Elementary School Modular Bathroom Project Update

    Board of Education MeetingInformation Report No. 7

    Date: April 16, 2019

    Presented by: Hagop Kassabian, Administrator: Planning, Development & Facilities

    Stephen Dickinson, Chief Business & Financial Office

    Revised 04/16/2019

  • Modular Bathroom Project Update

    • Requests have been made to improve restroom access to Monte Vista Elementary School o Current status of site is in compliance, but additional need has

    been established

    • Planning & Development staff met with site staff and District Administrators o Staff walked the site and discussed possible locations for a portable

    restroom building near the current bungalows

    2

  • Improvements at Monte Vista Elementary

    • Beautification project at the bungalow area o Painting of the bungalows o Awning installation at classrooms 8110-8111 o Tree planting in courtyard – completed o Installation of benches in courtyard o Removal of grates from the windows of the bungalows – completed

    • Moving classrooms so that grade alike rooms are in close proximity

    • Installation of modular restroom building o Project has not been finalized or approved by the Board

    3

  • Installation of Modular Restroom

    • A primary location was identified and is recommendedo Two alternate locations are available

    • Project is anticipated to take 6 to 12 months to be completed from the time of Board approval

    • 12’ x 40’ building will fit in the recommended location o Two toilets, two urinals, and two sinks in boys sectiono Three toilets and two sinks in girls section o One gender-neutral staff restroom

    • Cost is estimated to be approximately $205,000 to $255,000o To be funded by Developer Fees funds

    4

  • Installation of Modular Restroom (cont.)

    5

    Boys BoysGirls GirlsStaff

  • Installation of Modular Restroom (cont.)

    6

    Option 1: Recommended location

    Option 2

    Option 3

  • Three Options for Location of Building

    Option 1 – Southeast corner • Pros

    o Shorter delivery and installation lead time

    o Larger number of fixtureso Staff restroom o Pre-plan check approved

    buildingo Close proximity to existing

    bungalows• Cons

    o Site access for installation

    7

    Options 2 and 3• Pros

    o Close proximity to existing bungalows

    • Conso Longer delivery and

    installation lead time o Loss of open play areao Need for DSA plan check

    approval o Limited number of fixtures

  • Next Steps

    • Staff is seeking direction from the Board to proceed with the project

    • Staff is prepared to bring an item to the Board for approval at the May 7 Board meeting

    8

    Slide Number 1Modular Bathroom Project Update Improvements at Monte Vista ElementaryInstallation of Modular Restroom Installation of Modular Restroom (cont.)Installation of Modular Restroom (cont.)Three Options for Location of Building Next Steps