Monte Vista Elementary School Modular Bathroom Project Update
Board of Education MeetingInformation Report No. 7
Date: April 16, 2019
Presented by: Hagop Kassabian, Administrator: Planning, Development & Facilities
Stephen Dickinson, Chief Business & Financial Office
Revised 04/16/2019
Modular Bathroom Project Update
• Requests have been made to improve restroom access to Monte Vista Elementary School o Current status of site is in compliance, but additional need has
been established
• Planning & Development staff met with site staff and District Administrators o Staff walked the site and discussed possible locations for a portable
restroom building near the current bungalows
2
Improvements at Monte Vista Elementary
• Beautification project at the bungalow area o Painting of the bungalows o Awning installation at classrooms 8110-8111 o Tree planting in courtyard – completed o Installation of benches in courtyard o Removal of grates from the windows of the bungalows – completed
• Moving classrooms so that grade alike rooms are in close proximity
• Installation of modular restroom building o Project has not been finalized or approved by the Board
3
Installation of Modular Restroom
• A primary location was identified and is recommendedo Two alternate locations are available
• Project is anticipated to take 6 to 12 months to be completed from the time of Board approval
• 12’ x 40’ building will fit in the recommended location o Two toilets, two urinals, and two sinks in boys sectiono Three toilets and two sinks in girls section o One gender-neutral staff restroom
• Cost is estimated to be approximately $205,000 to $255,000o To be funded by Developer Fees funds
4
Installation of Modular Restroom (cont.)
5
Boys BoysGirls GirlsStaff
Installation of Modular Restroom (cont.)
6
Option 1: Recommended location
Option 2
Option 3
Three Options for Location of Building
Option 1 – Southeast corner • Pros
o Shorter delivery and installation lead time
o Larger number of fixtureso Staff restroom o Pre-plan check approved
buildingo Close proximity to existing
bungalows• Cons
o Site access for installation
7
Options 2 and 3• Pros
o Close proximity to existing bungalows
• Conso Longer delivery and
installation lead time o Loss of open play areao Need for DSA plan check
approval o Limited number of fixtures
Next Steps
• Staff is seeking direction from the Board to proceed with the project
• Staff is prepared to bring an item to the Board for approval at the May 7 Board meeting
8
Slide Number 1Modular Bathroom Project Update Improvements at Monte Vista ElementaryInstallation of Modular Restroom Installation of Modular Restroom (cont.)Installation of Modular Restroom (cont.)Three Options for Location of Building Next Steps