RFQ 19H08021Q0057
Climate Control Equipment Data Center
Solicitation Questions & Answers
1. and installation plan, this information. If you have this information, please share it.
A: See enclosed floor plan distribution
2. Do you have more information about the voltage level that exist on site? A: Three-Phase electrical power
3. Do you have more information about the distance from the electrical main panel to the precision conditioning air units? A: On or about 10 meters
4. Do you know the distances from the evaporator unit (inside) and the condensing unit (outside)?
A: On or about 5 meters
5. Do you know the distance from the evaporator unit to the closer water supply and the closer drain?
A: On or about 10 meters
6. On site will be installed Technical Floor (false floor)?, it will be used as a plenum?, and how tall will it be?
A: There will be a false flooring installed, the elevation will be 30cm (1 foot)
7. The air return of “hot” air will be a free return (natural return)? Or it will be trough air ducts? A: supply from above and return from front trough air ducts in cool hallway between 18
communication racks
8. The air units will be integrated to a fire suppression system?
A: there will be a separate installation for a Fire Suppression System (NOVEC-1230)
9. The units requested can be and we recommend it shall be monitored in network though SNMP protocol, the network connection for each unit will be provide by the HNP? A: Yes
10. Please indicate the geographic location (site coordinates) of the site to install the unit.
A: 14.056771, -87.259344
11. Considering the time, it will take to have the answer to the questions about the process and the time it will take to formulate the offers after having the answers, we respectfully request that the date to present the proposals be extended by at least two weeks.
A: Due date to submit the offers is August 23, 2021
12. What will be the operating voltage of the machines?
A: three-phase
13. What will the air flow be like? Supply low and return high?
A: Supply from above and return from front
14. If there is a false floor, what is its height?
A: 30cm
15. The distance between the controller and the condensers. And if they are going to be at the same
level or on different floors.
A: distance between the controller and the condensers (see the attached drawing) the two
will be on the same level
16. Are the driving units going to be on the first level? We need, if it will be necessary, the use of
cranes or loaders to locate the equipment in its final position.
A: There is enough space around the building in question to be able to locate the units
17. If you can provide us with a plan of the Data Center where the units will be located?
A: See attached drawing
18. Do the units need a humidifier and dehumidifier?
A: preferably with a dehumidifier to maintain a humidity-free environment and protect the
network devices to be installed
19. The units require remote communication and in what protocol?
A: No
20. Will the equipment be installed near a coastal area or at a height greater than 3000 meters?
A: The installation will not be in the capital (Tegucigalpa) attached the exact coordinates of
the site where the equipment will be installed (A: 14.056771, -87.259344)
21. What is the amount of sensible cooling that is needed?
A: The acceptable operating range for a Data Center ranges from 15 ° C to 25 ° C, and within
this acceptable range, the optimal range is between 17 ° C and 21 ° C. Any temperature
greater than 25 ° C must be corrected immediately, since it implies putting the Data Center
equipment at risk.
22. • The following annual average environmental conditions of the site where the equipment will
be installed
o Internal temperature required
• the optimum temperature range to be achieved is between 17 ° C and 21 ° C
o Internal relative humidity required
• the relative humidity should be between 40% and 55%
o External temperature
• This varies according to the season of the year
o External humidity
• This varies according to the season of the year
o Height of the site above sea level
• Approximately 990 meters above sea level
23. • Are air conditioning units required to be connected to other equipment such as the fire
suppression system?
A: No, a fire suppression system will be installed separately (NOVEC-1230)
INDICE Y PORTADA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
01
PROPIETARIO
UBICACION:
28ARQ
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
Direccion de Logistica
POLICIA NACIONAL
A1- INDICE GENERAL DE PLANOSA2- PLANTA DE LEVANTAMIENTOA3- PLANTA DEMOLICIONES Y CIERRESA4- FACHADAS LEVANTAMIENTOA5- PLANTA ARQUITECTONICA NIVEL IA6- PLANTA ARQUITECTONICA NIVEL IIA7- ARQUITECTONICA DE TECHOSA8- ELEVACION PRINCIPAL
A10- ELEVACIONES IZQUIERDA Y DERECHA A11- PLANTA CONSTRUCTIVA NIVEL IA12- PLANTA CONSTRUCTIVA NIVEL IIA13- CUADRO DE PUERTAS Y VENTANASA14- CUBIERTA DE TECHOS CONSTRUCTIVAA15- PLANTA DE CIMENTACIONA16- PLANTA DE ENTREPISOA17- PLANTA ESTRUCTURAL DE TECHOS
A19- PLANTA DE ILUMINACION NIVEL IIA20- PLANTA DE FUERZA Y DATOS NIVEL IA21- PLANTA DE FUERZA Y DATOS NIVEL IIA22- PANEL DE DISTRIBUCION Y DETALLES
A9- ELEVACION POSTERIOR
A18- PLANTA DE ILUMINACION NIVEL I
A23- PLANTA HIDROSANITARIA NIVEL IA24- PLANTA HIDROSANITARIA NIVEL IIA25- DETALLES GENERALES IA26- DETALLES GENERALES IIA27- PLANTA DE ACABADOS NIVEL IA28- PLANTA DE ACABADOS NIVEL I
0.2
8
ANDÉN CARGA
ESCALA 1:200
22.78
9.1
5
22.78
3.20 3.66 3.33 3.24 3.35 3.06 2.96
9.1
5
3.2
83
.2
02
.6
7
3.203.66 3.32 3.25 3.35 3.06 2.96
3.1
32
.7
43
.2
8
2.0
5
1.0
7
0.9
9
2.81
1.53
1 2 3 4 5 6 87
A
B
C
D
1 2 3 4 5 6 87
Planta Levantamiento
PLANTA LEVANTAMIENTO
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
02
PROPIETARIO
UBICACION:
28LEV
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
Direccion de Logistica
POLICIA NACIONAL
PLANTA DEMOLICIONES
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
03
PROPIETARIO
UBICACION:
28LEV
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
Direccion de Logistica
POLICIA NACIONALANDÉN CARGA
ESCALA 1:200
Planta Demoliciones y Cierres
Y CIERRES
SIMBOLOGÍADESCRIPCIÓNSÍMBOLOS
INDICA NIVEL DE PISO TERMINADO
DEMOLICIONES
COLUMNA NUEVA
COLUMNA EXISTENTE
CIERRES
PAREDES NUEVAS
fachadas LEVANTAMIENTO
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
04
PROPIETARIO
UBICACION:
28LEV
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
Direccion de Logistica
POLICIA NACIONAL
22.78
3.20 3.66 3.33 3.24 3.35 3.06 2.96
1 2 3 4 5 6 87
22.78
3.203.663.333.243.353.062.96
1234568 7
ESCALA 1:200
Elevacion frontal Levantamiento
ESCALA 1:200
Elevacion frontal Levantamiento
27.509
.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta Arquitectonica Nivel I
PLANTA ARQUITECTONICA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
05
PROPIETARIO
UBICACION:
28ARQ
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL I
Direccion de Logistica
POLICIA NACIONAL
18.77
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta Arquitectonica Nivel II
PLANTA ARQUITECTONICA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
06
PROPIETARIO
UBICACION:
28ARQ
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL II
Direccion de Logistica
POLICIA NACIONAL
SIMBOLOGÍADESCRIPCIÓNSÍMBOLOS
INDICA NIVEL DE PISO TERMINADO
PAREDES DE BLOQUE DE 6"
COLUMNA NUEVA
COLUMNA EXISTENTE
PAREDES DE TABLA YESO
PAREDES DE DUROCK
19.70
4.76
ESCALA 1:200
Planta Arquitectonica de Techos
PLANTA ARQUITECTO
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
07
PROPIETARIO
UBICACION:
28ARQ
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
TECHO
Direccion de Logistica
POLICIA NACIONAL
27.50
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
82
.7
43
.1
3
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
30%
30%
30%
30%
6.0
2
NPT
+4.50
P-01
V-04 V-04
V-05 V-05
V-01
V-06
30%
30%
2 3 4 5 6 81 9 10
NPT
+0.00
NLT
+3.20
NPT
-0.58
FACHADA FRONTAL
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
08
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
CG
Direccion de Logistica
POLICIA NACIONAL
ESCALA 1:200
Fachada Frontal
2.74
4.00 4.00 4.00 4.00 3.59
3.2
0
1.3
0
3.0
00
.3
0
2.68
2.2
52
.2
0
3.9
91
.5
2
5.5
2
0.8
73
.5
7
1.0
01
.1
01
.5
5
1.5
00
.6
01
.5
5
3.6
5
0.2
0
1.1
4
0.0
0
4.3
0
Cubierta de techo lámina
troquelada de aluzinc
calibre 26 sobre
estructura de canaleta
metálica 2"x6"
Fascia de techo
de durock
h:0.20m
Cubierta de techo lámina
troquelada de aluzinc
calibre 26 sobre
estructura de canaleta
metálica 2"x6"
Fascia de
techo de
durock h:0.20m
2.94 2.22
Cizas 1"
@0.75m
Cizas 1"
@0.75m
Cizas 1"
@0.75m
Louvers
Cizas 1"
@0.75m
Dirección de Telemática
DATA CENTER
Sobrerepello
Ducto de durock
para BALL
FACHADA POSTERIOR
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
09
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
CG
Direccion de Logistica
POLICIA NACIONAL
ESCALA 1:200
Fachada Posterior
30%
234568 1910
2.744.004.004.004.003.59
3.0
00
.3
0
3.2
42
.2
8
5.5
2
2.8
8
0.2
0
1.9
2
0.0
0
4.3
0
Cubierta de techo lámina
troquelada de aluzinc
calibre 26 sobre
estructura de canaleta
metálica 2"x6"
Fascia de techo
de durock
h:0.20m
Cubierta de techo lámina
troquelada de aluzinc
calibre 26 sobre
estructura de canaleta
metálica 2"x6"
2.942.22
Louvers
30%
2.1
70
.6
01
.1
1
0.6
3
V-04
V-03 V-03
NPT
-0.58
NPT
+4.50
NPT
+0.00
NLT
+3.20
1.2
01
.1
00
.7
8
1.0
01
.1
00
.7
8
0.2
0
4.4
5
0.2
0
4.4
5
NPT
-0.20
Portón Generador
Ducto de durock
para BALL
Ducto de durock
para BALL
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
10
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
CG
Direccion de Logistica
POLICIA NACIONAL
FACHADA LATERALDERECHA Y FACHADALATERAL IZQUIERDA
E D C B A
NPT
-0.58
NPT
+4.50
P-05P-04
2.96 1.69 1.05 3.30
2.9
6
3.7
4
4.7
2
5.7
24
.9
9
5.0
90
.6
4
Cizas 2"
@0.75m
2.1
9
3.3
0
0.70
Fascia de techo
de durock
h:0.20m
Fascia de techo
de durock
h:0.20m
ESCALA 1:200
Fachada Lateral derecha
V-03
1.2
01
.1
01
.0
3
V-04
1.5
30
.6
4
0.6
0
5.5
2
6.1
6
1.4
4
4.6
5
5.0
8
EDBA
2.962.733.30
2.9
6
5.0
9
Fascia de techo
de durock
h:0.20m
NPT
+4.50
P-01
V-03 V-07
2.24
2.50
NLT
+3.20
NPT
+0.00
2.2
51
.5
00
.7
0
3.0
0
0.3
0
1.2
0
4.5
0
1.0
01
.1
02
.9
9
ESCALA 1:200
Fachada Lateral izquierda
Cizas 1"
@0.75m
Cizas 1"
@0.75m
Cotas 2"
@0.75m
27.509
.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta Constructiva Nivel I
PLANTA CONSTRUCTIVA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
11
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
NIVEL I
Direccion de Logistica
POLICIA NACIONAL
0.33 3.67 0.33 3.67 0.33 3.67 0.33 3.67 0.330.28
0.0
70
.2
85
.4
60
.2
8
0.2
85
.4
60
.2
81
.7
00
.1
00
.7
70
.2
8
0.33 3.67 0.33 3.67 0.33 3.67 0.33 3.67 0.330.28 3.16 0.33 2.53
0.2
82
.5
70
.2
82
.5
20
.1
53
.1
3
0.151.350.158.370.154.900.153.050.152.350.15
0.1
53
.1
80
.1
52
.4
53
.4
1
0.15 2.35 0.15
0.1
60
.1
02
.0
00
.2
02
.8
5
3.0
70
.1
52
.5
9
0.32 1.12 0.10 1.00 0.100.400.15 2.71 0.10 2.00
0.09
0.15
0.09
2.00 0.10 1.57 0.33 3.67 0.330.28
2.5
20
.1
52
.7
90
.2
80
.0
7
5.4
60
.2
82
.5
70
.2
80
.0
7
0.2
82
.5
70
.2
80
.0
7
0.0
70
.2
81
.4
70
.1
01
.0
00
.2
85
.4
60
.2
80
.0
7
0.2
80
.2
82
.5
7
0.2
41
.8
51
.0
00
.1
00
.3
30
.9
80
.2
01
.0
0
0.1
0
0.1
8
0.2
8
1.7
81
.0
70
.0
7
1.430.640.152.620.153.100.154.370.157.141.100.902.96
1.4
61
.5
2
0.32 3.68 0.33 3.67 0.33 3.67 0.33 3.67 0.33 1.89 0.15 1.40 0.33 2.53 0.15 1.10 0.98
2.07
1.0
9
0.8
80
.9
3
1.3
7
0.501.55
0.9
80
.2
01
.0
00
.2
8
0.2
8
2.8
50
.0
7
2.750.151.420.151.290.288.310.154.900.153.05
2.2
30
.1
00
.8
0
3.1
3
1.35 4.37
1.27 0.15 1.42 0.15 2.75 0.28
0.22 1.40 0.15 1.40 0.33 2.47 0.28
0.150.14 2.00 0.140.28 2.03 0.15 0.88 1.64 3.33 1.27 3.19 0.32 2.65 0.582.17
0.2
04
.3
0
2.15 0.300.30 0.43
5.5
0
4.8
0
0.2
5
2.2
00
.2
81
.8
01
.0
50
.2
81
.0
0
V-02
P-01
P-02P-01 P-01
P-02
P-03
P-05
P-04
P-05
P-01 V-01
0.7
5
1.2
0
0.75
0.4
91
.1
5
2.26
3@
0.2
5 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
SIMBOLOGÍADESCRIPCIÓNSÍMBOLOS
INDICA NIVEL DE PISO TERMINADONPT ±#.##m
PAREDES DE BLOQUE DE 6"
ALTURA DE CIELO FALSOH=
TIPO DE VENTANA
TIPO DE PUERTA
V-xx
P-xx
PAREDES DE TABLA YESO
PAREDES DE DUROCK
V-03
1.44 0.28 2.89 0.33 3.18 2.85 0.34 2.74 0.62 2.89 0.32 2.00 0.74 0.32 0.85 1.80 0.30 1.97 0.20
0.2
83
.0
0
0.2
8
0.2
82
.7
2
0.2
02
.1
50
.1
52
.1
50
.2
04
.3
00
.2
0
1.19 0.23 1.33 0.32
V-04
V-04
P-070.62
1.34
0.62
1.40
0.3
8
0.3
8
0.62
18.77
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
82
.7
43
.1
3
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta Constructiva Nivel II
PLANTA CONSTRUCTIVA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
12
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR.
NIVEL II
Direccion de Logistica
POLICIA NACIONAL
0.2
81
.0
90
.1
01
.8
50
.1
00
.9
90
.1
01
.2
30
.2
82
.5
70
.2
8
0.33 1.20 0.10 1.07 0.10 1.20 0.33 1.76 0.15 1.76 0.33 1.67 0.10 1.90 0.33 1.67 0.10 1.90 0.33 3.44 0.33
0.33 1.76 0.15 1.76 0.33 1.76 0.15 1.76 0.33 0.81 0.10 1.85 0.10 0.81 0.33 0.81 0.10 1.85 0.10 0.81 0.33
0.2
82
.6
50
.1
52
.6
50
.2
82
.5
70
.2
8
0.2
82
.5
70
.2
8
0.333.440.333.670.331.660.800.150.800.260.333.670.330.960.800.150.800.960.33
0.152.851.004.090.151.002.004.940.15
0.18 7.67 0.09
7.94
4.2
1
4.0
80
.1
3
0.1
34
.1
0
0.1
34
.0
8
0.09 7.67 0.18
0.1
34
.0
81
.2
30
.0
72
.7
90
.1
3
3.97
1.2
9
1.2
9
11.97
0.74 3.23
1.4
71
.3
0
0.18 1.76 0.15 1.76
2.7
7
1.4
71
.3
0
1.00 0.91
1.1
3
1.2
6
1.2
6
0.910.91
5.06
2.5
10
.2
6
2.7
7
2.7
7
2.46
0.091.660.800.150.800.26
0.33
3.76
0.1
42
.5
70
.2
81
.2
3
0.1
40
.9
91
.5
80
.2
81
.2
3
0.33 3.44 0.09 0.153.670.09
2.25 1.16
0.2
80
.9
40
.2
51
.3
80
.0
7
1.21 0.74 1.05
1.9
60
.1
51
.9
60
.1
51
.2
9
0.88 2.00 1.00 0.15 7.94
0.09 1.67 0.10 1.90 0.33
V-04 V-04 V-05 V-05 V-06
V-03V-03
V-03
V-07
V-08 V-09
P-06 P-06
0.2
91
.0
0
P-05
P-03 P-03P-03 P-03
H=3.20 mH=3.20 m H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
2.44
3.5
6
2.05
0.3
02
.9
60
.3
0
0.30 2.05 0.30
0.1
42
.5
70
.0
7
SIMBOLOGÍADESCRIPCIÓNSÍMBOLOS
INDICA NIVEL DE PISO TERMINADONPT ±#.##m
PAREDES DE BLOQUE DE 6"
ALTURA DE CIELO FALSOH=
TIPO DE VENTANA
TIPO DE PUERTA
V-xx
P-xx
PAREDES DE TABLA YESO
PAREDES DE DUROCK
0.60
1.3
3
1.95
CUADRO DE PUERTAS
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
13
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
Y VENTANAS
Direccion de Logistica
POLICIA NACIONAL
27.50
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
82
.7
43
.1
3
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta Constructiva de Techos
PLANTA CONSTRUCTIVA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
14
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
TECHO
Direccion de Logistica
POLICIA NACIONAL
30%
30%
30%
30%
2.65
0.17 16.01
0.16 8.52 0.75
10
.2
7
10
.5
1
0.7
08
.8
70
.7
0
0.16
16.02
0.15
8.52 0.18
6.5
83
.6
9
6.5
03
.7
6
27.50
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta de Cimentacion Nivel I
PLANTA DE CIMENTACION
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
15
PROPIETARIO
UBICACION:
28EST
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
Y ESTRUCTURA NIVEL I
Direccion de Logistica
POLICIA NACIONAL
Z-1
1.50
1.50
Z-1
DETALLE - 1
1.50 a 2.00
1.50
0.300.21
sin escala
ZAPATA AISLADA PEDESTAL
0.25
S-1
Z-1 Z-1 Z-1 Z-1
Z-1Z-1Z-1Z-1Z-1Z-1
Z-1 Z-1 Z-1 Z-1 Z-1 Z-1
DET-1
DET-1
DET-1
VER PLANO DE DETALLES
VER PLANO DE DETALLES
S 1S 1
S 1S 1 S 1
S 1
S 1S 1
S 2
S 2
S 2
S 2
S 2
S 1
S 1
S 1
S 1
S 1
S 2
S 2
S 2
S 2
S 2 S 2 S 2
SOLERA INFERIORS-2
SOLERA TENSORAS-1
PEDESTALP-1
Z-2
Z-2
Z-2 Z-2 Z-2
Z-2
Z-2
Z-2
Z-2
28.10
11.70
0.60
0.20
DETALLE - 2
Z-2
DET-1
DET-2
DET-2
DET-2
C 3 C 3 C 3C 3
C 3
C 3
C 3
C 3 C 3 C 3 C 3 C 3 C 3 C 3 C 3 C 3 C 3 C 3 C 3
2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50
C 3
C 3C 3
C 3
C 3
C 3
2.25
2.25
2.33
2.33
C 3
C 3C 3
C 3
1.30 1.15 0.50 1.05 1.76 2.24 2.24 1.76 2.00 2.00
C 3
C 3
3.28
2.00
C 3
C 3
C 4
C 4
C 4
C 4
C 4
C 4
C 4
CASTILLOC-3
CASTILLOC-4
V -1
SIN ESCALA
DETALLE TIPICO DE GRADAS
0.60
0.20
S 2
Z 2
DETALLE - 3
DET-3
C 1 C 1 C 1 C 1 C 1
C 1 C 1 C 1 C 1 C 1
C 1 C 1 C 1 C 1 C 1
C 1
C 1
COLUMNAC-1
Z-2
18.77
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
PLANTA DE ENTREPISO
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
16
PROPIETARIO
UBICACION:
28EST
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
Y ESTRUCTURA NIVEL II
Direccion de Logistica
POLICIA NACIONAL
C 1 C 1 C 1 C 1 C 1
C 1 C 1 C 1 C 1 C 1
C 1 C 1 C 1 C 1 C 1
C 1
C 1
V 1V 1
V 1 V 1 V 1
V 1V 1V 1
V 1
V 1
V 1 V 1
V 1
V 1
#2 "@ 10cm.
0.60
0.60
0.60
0.01
0.60
1.20
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
1.00 1.00 2.00 2.00 1.00 1.00 1.00 2.00 1.00 1.00 1.00 2.00 0.45
3.66
VIGA DE LOSAV-1
C 3
C 3
C 3
C 3C 3
C 3 C 3 C 3 C 3C 3C 3
C 3
C 3
C 3 C 3C 3C 3
C 3
C 3
C 3
C 3
C 3
ESCALA 1:200
Planta de Entrepiso
C 4
CASTILLOC-3
CASTILLOC-4
COLUMNAC-1
DETALLE DE ESTRUCTURAS
[]6"x4"x1/16" @0.60m
ISOMETRICO ARMADO DE ENTREPISO TECHO
1
0.03
0.10LAMINA ONDA STD. CAL. 26
LEGITIMA
[] de 6"x4"x1/16"
DETALLE DE LOSA DE ENTREPISOS
LOSA
#2 @ 0.30 A/S
0.60 0.60
NOTAS ESTRUCTURALES
1. Resistencia de materiales:
1.1. Concreto reforzado
1.1.1. Esfuerzo de compresión a los 28 dias =
3000 psi
1.1.2. Acero de refuerzo grado 60
1.2. Acero Estructural
1.2.1. Vigas W ASTM A-50
Angulares ASTM-A36
1.2.2. Aplicar 2 manos de anticorrosivo gris a todos
los elementos Metalicos antes del montaje, y
2 manos color blanco despues del montaje.
1.2.3. Electrodo para soldadura E-7018
2. Recubrimiento de elementos estructurales de
concreto
2.1. Vigas = 2.5 cms
2.2. Columnas = 2.5 cms
2.3. Zapatas = 7 cms
2.4. Soleras y castillos= 2 cms
27.50
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
82
.7
43
.1
3
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta Estructural de Techos
PLANTA ESTRUCTURAL
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
17
PROPIETARIO
UBICACION:
28EST
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
CG
TECHO
Direccion de Logistica
POLICIA NACIONAL
3.7
6
SIMBOLOGÍADESCRIPCIÓNSÍMBOLOS
CANALETA DE CIERRE 2"x 4" CHAPA 14
CANALETA DE 2"x 4" CHAPA 14
ARRIOSTRES 3/8" @ 0.90m
CANALETA 3"x 8" CHAPA 14
HIJUELOS DE CANALETA 2"x 4" CHAPA 14
FLASHING LAMINA METALICA
0.7
0
0.70
30%
30%
30%
30%
ESCALA 1:200
Planta Iluminación Nivel I
PLANTA ILUMINACION
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
18
PROPIETARIO
UBICACION:
28ELEC.
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL I
Direccion de Logistica
POLICIA NACIONAL
Luminaria empotrable , 2'X4', 120 V
Cableado luminarias (3x#12, PVC 3/4"-CED 20)
Interruptor Doble, 15 amps, 120v.
Interruptor Doble Vaiven, 15 amps, 120 v.
Cableado interruptores (2#12, PVC 3/4"-CED 20)
Centro de Carga trifasico, 42 espacios,
Acometida general, es necesario revisar la distancia
nota: todos los equipos electricos seran calidad "UL"
225 amps en barra, empotrable
de donde se conectara esta acometida
Interruptor Sencillo, 15 amps, 120v.
Luminaria fluorescente empotrable en pared"tipo Canasta" para exterior de 120 v
Luminaria empotrable , 2'X2', 120 V
Luminaria circular tipo spot
27.50
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
Cto # 1
PVC Electrico Ced. 40
Cto # 2
Cto # 3
PVC Electrico Ced. 40
Cto # 4
PVC Electrico Ced. 40
Cto # 5
PVC Electrico Ced. 40
2#12 +1#14 THHN
2#12 +1#14 THHN
2#12 +1#14 THHN
2#12 +1#14 THHN
PVC Electrico Ced. 40
2#12 +1#14 THHN
ESCALA 1:200
Planta Iluminación Nivel II
PLANTA ILUMINACION
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
19
PROPIETARIO
UBICACION:
28
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL II
Direccion de Logistica
POLICIA NACIONAL
Luminaria empotrable , 2'X4', 120 V
Cableado luminarias (3x#12, PVC 3/4"-CED 20)
Interruptor Doble, 15 amps, 120v.
Interruptor Doble Vaiven, 15 amps, 120 v.
Cableado interruptores (2#12, PVC 3/4"-CED 20)
Centro de Carga trifasico, 42 espacios,
Acometida general, es necesario revisar la distancia
nota: todos los equipos electricos seran calidad "UL"
225 amps en barra, empotrable
de donde se conectara esta acometida
Interruptor Sencillo, 15 amps, 120v.
Luminaria fluorescente empotrable en pared"tipo Canasta" para exterior de 120 v
Luminaria empotrable , 2'X2', 120 V
Luminaria circular tipo spot
ELEC.
18.77
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
Cto # 6
PVC Electrico Ced. 40
Cto # 7
PVC Electrico Ced. 40
Cto # 8
PVC Electrico Ced. 40
Cto # 9
PVC Electrico Ced. 40
2#12 +1#14 THHN
2#12 +1#14 THHN
2#12 +1#14 THHN
2#12 +1#14 THHN
ESCALA 1:200
Planta de Fuerza Nivel I
PLANTA FUERZA Y DATOS
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
20
PROPIETARIO
UBICACION:
28
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL I
Direccion de Logistica
POLICIA NACIONAL
Tomacorriente doble polarizado, 20 amps, 120 v,
Tomacorriente especial para estufa, 240 v,E
Centro de Carga trifasico, 42 espacios,
Cableado Tomas (2x#10+1X#14, PVC 3/4"-CED 20)
en pared, (2x#10+1X#14, PVC 3/4"-CED 20)
50 amps (2x#8 + 1X#14, PVC 1"-CED 20),para refrigeradora (2x#10+1X#12, PVC 3/4"-CED 20)
225 amps en barra, empotrable
Tomacorriente A/C, 240 v, 50 ampsA/C
(2x#8 + 1X#14, PVC 1"-CED 20)
ELEC.27.50
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
Cto # A
PVC Electrico Ced. 40
2#10 +1#12 THHN
Cto # B
PVC Electrico Ced. 40
2#10 +1#12 THHN
Cto # C
PVC Electrico Ced. 40
2#10 +1#12 THHN
A/C
Cto # a
2#8 +1#10 THHN
PVC Electrico Ced. 40
A/C
Cto # b
2#8 +1#10 THHN
PVC Electrico Ced. 40
A/C
Cto # c
A/C
2#8 +1#10 THHN
PVC Electrico Ced. 40
ESCALA 1:200
Planta de Fuerza Nivel II
PLANTA FUERZA Y DATOS
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
21
PROPIETARIO
UBICACION:
28
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL II
Direccion de Logistica
POLICIA NACIONAL
Tomacorriente doble polarizado, 20 amps, 120 v,
Tomacorriente especial para estufa, 240 v,E
Centro de Carga trifasico, 42 espacios,
Cableado Tomas (2x#10+1X#14, PVC 3/4"-CED 20)
en pared, (2x#10+1X#14, PVC 3/4"-CED 20)
50 amps (2x#8 + 1X#14, PVC 1"-CED 20),para refrigeradora (2x#10+1X#12, PVC 3/4"-CED 20)
225 amps en barra, empotrable
Tomacorriente A/C, 240 v, 50 ampsA/C
(2x#8 + 1X#14, PVC 1"-CED 20)
ELEC.
18.77
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
PS PSPS
PS
PS
PS PS
RACK
PS
PS
PS PS
PS
PS
PS
E
E
Cto # e
2#8 +1#10 THHN
PVC Electrico Ced. 40
Cto # d
2#8 +1#10 THHN
PVC Electrico Ced. 40
Cto # D
PVC Electrico Ced. 40
2#10 +1#12 THHN
Cto # E
PVC Electrico Ced. 40
2#10 +1#12 THHN
A/C
Cto # f
A/C
2#8 +1#10 THHN
PVC Electrico Ced. 40
A/CA/C
Cto # g
2#8 +1#10 THHN
PVC Electrico Ced. 40
A/CA/C
Cto # h
2#8 +1#10 THHN
PVC Electrico Ced. 40
A/CA/C
Cto # i
2#8 +1#10 THHN
PVC Electrico Ced. 40
PS PS PS
PSPS PS
PSPS PS
PS PS PSPS
Cto # E
PVC Electrico Ced. 40
2#10 +1#12 THHN
Cto # F
PVC Electrico Ced. 40
2#10 +1#12 THHN
Detalles
0,30
Toma Electricidad Jacket / conector RJ45
Distancia minima entre salidas de sitemas
Bandeja de datos 10"
0,70
cielo falso
Distancia minima entre Bandeja y Pared
Bandeja para cable de datos 10"
Simbologia Descripcion
Access Point (redinalambrica)
RACK con SWITCH y Patch Panels (1)
Cable UTP Categoria 6
Punto de salida de Bandeja
Jacket / conector RJ45PS
RACK
WI.FI
INIFILAR Y DETALLES
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
22
PROPIETARIO
UBICACION:
28
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
ELECTRICOS
Direccion de Logistica
POLICIA NACIONAL
DIAGRAMA UNIFILAR
CENTRO DE CARGA DE 48 ESPACIOS
CKTO. #-1 D-3/4
ILUM. 2#-12 +1#14
L1 L2
TOMAS DOBLES
CKTO.#-A
2#10 + 1#12 T.H.W
CKTO. #-3 D-3/4
CKTO. #-5 D-3/4
CKTO. #-7 D-3/4
DETALLE DE BASE PARA CONTADOR
0.20x0.60x0.60mts.
3.50
1#6 TIERRA
1#2 NEGRO
ZAPATA
CCP
MUFA DE 1-1/2"
1-1/2"
4#3, #[email protected].
COLUMNA DE 0.25x0.25mts.
P.V.C. DE 1-1/2" ELECTRICO
UL C-40
5/8"x8' DE LONGITUD
VARILLA COPPERWELD
2.00
40 ESPACIOS
200 AMP. DE
TABLERO MONOFASICO
EN ACOMETIDA CABLE COAXIAL
DIAGRAMA ACOMETIDATELEFONICA Y CABLE DE T.V.
DE 3/4"
DUCTO DE P.V.C.
COLUMNA DE 0.25x0.1mts.
4#3, #[email protected].
MUFA DE 1-3/4"
USAR CABLE 4X22 TELEFONICO
EN ACOMETIDA CABLE TELEFONICO
0.20x0.60x0.60mts.
ZAPATA
3/4"
3.50
CAJA DE
REGISTRO
DE 4x4
P.V.C, ELECTRICO DE 3/4"
.- C-40
.- P.V.C. 1-1/2"
.- 1#6
.- 1#2
.- 2#-1/0
MAIN DE
200 AMP.
M ESTACION
USAR CABLE RG-59
2#1/0
1#2 NEGRO
1#6 TIERRA
0.25
Especificaciones Eléctricas
1. Los interruptores irán a 1.10 m del
nivel del piso terminado.
2. Los tomacorrientes se
colocaran a 0.30m del npt.
3. El centro de carga se colocara a
2.00m de altura del npt.
4. Poliducto de 3/4" en circuito de
tomas e iluminación.
ILUM. 2#-12 +1#14
ILUM. 2#-12 +1#14
ILUM. 2#-12 +1#14
CKTO. #-9 D-3/4
ILUM. 2#-12 +1#14
CKTO. #-4 D-3/4
ILUM. 2#-12 +1#14
CKTO. #-6 D-3/4
ILUM. 2#-12 +1#14
CKTO. #-2 D-3/4
ILUM. 2#-12 +1#14
CKTO. #-d D-1
ESPECIAL 2#8 +1#10
INS- E
CKTO. #-8 D-3/4
ILUM. 2#-12 +1#14
TOMAS DOBLES
CKTO.#-C
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-B
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-E
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-D
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-G
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-F
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-I
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-H
2#10 + 1#12 T.H.W
TOMAS DOBLES
CKTO.#-J
2#10 + 1#12 T.H.W
CKTO. #-e D-2
ESPECIAL 2#8 +1#10
CKTO. #-a D-1
A/C. 2#-8 +1#10
CKTO. #-c D-1
A/C. 2#-8 +1#10
CKTO. #-e D-1
A/C. 2#-8 +1#10
CKTO. #-g D-1
A/C. 2#-8 +1#10
CKTO. #-i D-1
A/C. 2#-8 +1#10
CKTO. #-b D-1
A/C. 2#-8 +1#10
CKTO. #-d D-1
A/C. 2#-8 +1#10
CKTO. #-f D-1
A/C. 2#-8 +1#10
CKTO. #-h D-1
A/C. 2#-8 +1#10
CKTO. #-j D-1
A/C. 2#-8 +1#10
A FUTURO
A FUTURO
A FUTURO
A FUTURO
A FUTURO
27.50
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
82
.7
43
.1
3
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta Instalaciones Hidrosanitarios Nivel 1
PLANTA HIDROSANITARIA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
23
PROPIETARIO
UBICACION:
28
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL I
Direccion de Logistica
POLICIA NACIONAL
NOTAS GENERALES:
1. TODA LA TUBERIA DE AGUA POTABLE
S E D E S P L A Z A R A D E B A J O D E
ENTREPISO EXISTENTE, SUBIENDO
LA ALIMENTACION A CADA APARATO
S A N I T A R I O S E G U N D I A M E T R O
I N D I C A D O E N P L A N O .
2. LA ALTURA DE LAS REGADERAS EN
SEGUNDO NIVEL SERA DE 1.80 M
CON VALVULA DE BAÑO A 1.00 M
S O B R E E L N I V E L D E P I S O
T E R M I N A D O .
P
V
C
2
"
Ø
P
V
C
2
"
Ø
P
V
C
2
"
Ø
P
V
C
2
"
Ø
P
V
C
4
"
Ø
PV
C 4" Ø
PV
C 4" Ø
PV
C 4" Ø
PV
C 4" Ø
PV
C 4" Ø
PV
C 3
" Ø
TUBERIA DE PVC Ø 2"
TUBERIA DE PVC Ø 3"
VENTILA DE Ø 2"
SUBIDA PARA AGUA POTABLE
SIMBOLOGIA DE AGUAS NEGRAS
Y AGUA POTABLE
TUBERIA DE PVC Ø 4"
SIFON DE PISO /O TRAMPA
TUBERIA DE PVC Ø 1/2"
VALVULA DE COMPUERTA SEGUN
DIAMETRO DE TUBERIA
CAJA DE REGISTRO
BAJANTE DE AGUAS NEGRAS
TUBERIA DE 4"
PVC 4" Ø
PVC 4" Ø
PVC 4" Ø
PVC 4" Ø
PV
C 4" Ø
PV
C 4" Ø
P
V
C
2
"
Ø
P
V
C
4
"
Ø
P
V
C
2
"
Ø
VIENE DE CISTERNA
PVC 3/4" Ø
PVC 3/4" Ø
PVC 1/2" Ø
PVC 1/2" Ø
PV
C 1/2" Ø
PV
C 1/2" Ø
PV
C 1/2" Ø
PV
C 1/2" Ø
PV
C 1/2
" Ø
PV
C 1/2
" Ø
INS- H
TUBERIA DE PVC Ø 1/2"
18.77
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
PLANTA HIDROSANITARIA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
24
PROPIETARIO
UBICACION:
28
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
NIVEL II
Direccion de Logistica
POLICIA NACIONAL
PV
C 4
" Ø
PV
C 2" Ø
PV
C 2" Ø
NOTAS GENERALES:
1. T O D A L A T U B E R I A D E A G U A
POTABLE SE DESPLAZARA DEBAJO
D E E N T R E P I S O E X I S T E N T E ,
SUBIENDO LA ALIMENTACION A
CADA APARATO SANITARIO SEGUN
DIAMETRO INDICADO EN PLANO.
2. LA ALTURA DE LAS REGADERAS EN
SEGUNDO NIVEL SERA DE 1.80 M
CON VALVULA DE BAÑO A 1.00 M
S O B R E E L N I V E L D E P I S O
T E R M I N A D O .
P
V
C
4
"
Ø
INS- H
TUBERIA DE PVC Ø 2"
TUBERIA DE PVC Ø 3"
VENTILA DE Ø 2"
SUBIDA PARA AGUA POTABLE
SIMBOLOGIA DE AGUAS NEGRAS
Y AGUA POTABLE
TUBERIA DE PVC Ø 4"
SIFON DE PISO /O TRAMPA
TUBERIA DE PVC Ø 1/2"
VALVULA DE COMPUERTA SEGUN
DIAMETRO DE TUBERIA
CAJA DE REGISTRO
BAJANTE DE AGUAS NEGRAS
TUBERIA DE 4"
TUBERIA DE PVC Ø 3/4"
Planta Instalaciones Hidrosanitarios Nivel 2
A
0.40
0.50
0.60
0.40
(NO PEDREGOSO)
MATERIAL DEL SITIO
2"
DIAM.
6"
4"
3"
TAMIZADO Y
MATERIAL SELECTO
DIMENSIONES PARA
ZANJAS
COMPACTADO
COLOCACIÓN DE TUBERÍAS ENTERRADASSIN ESCALA
SIN ESCALA
DETALLE DE LLAVE DE RIEGO
LOSA O PARED
MANGUITO DE HFD
MAYOR QUE LA TUBERÍA
UN DIÁMETRO COMERCIAL
PARED O LOSA
TUBERÍA
EN LOSAS Y PAREDESSIN ESCALA
MANGUITO DE PASO
ADAPTADOR PVC HEMBRA
UNION UNIVERSAL
VALVULA COMPUERTA
MEDIDOR
NIPLE PVC
M
1
1
2
2
333
33
3
4
4
5
55
VALVULA CHECK
1
2
3
4
5
6
66
6
6
66
6
66
6
DETALLE PARA CONEXIÓN DE MEDIDORSIN ESCALA
2
33
6
6
6
233
66
6
6
VALVULA DE CONTROL ADENTRO DEL
APARTAMENTO
VALVULA DE CONTROL ADENTRO DEL
APARTAMENTO
1 22
3
VARILLA #3 @ ESQUINA
AL EDIFICIO
1 VALVULA DE CORTE
2 UNION DE TOPE
3 AGARRADERA VAR. #5
MARCO DE ANGULAR 50x50x6mm
MARCO DE ANGULAR44x44x6mm
MALLA VARILLA #3@ 0.10m SOLDADAAL MARCO
GRAVA
0.30
5.19
A
A
PLANTA
´
´
DETALLE DE VÁLVULAS DE COMPUERTASSIN ESCALA
min.= 0.40
PLANTA
SECCIÓN A-A
AFINADO
REPELLO Y
REPELLO EXTERIOR
min.= 2%
hasta 1.50 0.80 x 0.80
hasta 1.20 0.70 x 0.70
hasta 1.00 0.60 x 0.60
hasta 0.80 0.50 x 0.50
-
-
colocar peldaño
colocar peldaños
-0.40 x 0.40
OBSERVACIONES
bxb
ÁREA LIBRE
H
hasta 0.70
DIMENSIONAMIENTO DE CAJAS DE REGISTRO
Refuerzo, Vrs 3/8
@ 10 cm en ambas direcciones
R
=
0
.
1
5
15% 15%
Concreto 3000psi
Tapadera de concreto (3000psi)
con marco angular y con refuerzo
de
3
8
" @ 10 cm en ambos sentidod
Haladera de
3
8
"
Casquete de concreto
(3000psi) con refuerzo de
3
8
"
0.2
0
DETALLE DE CAJAS DE REGISTROSIN ESCALA
NPT
Tubo PVC Ø2"
SIFÓN TERMINAL DE 2"
TUBO PVC 2"
CODO PVC Ø2"
0.10
0.10
0.04
COLADERA DE PISOSIN ESCALA
DETALLES
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
26
PROPIETARIO
UBICACION:
28INS- H
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
HIDROSANITARIO
Direccion de Logistica
POLICIA NACIONAL
27.509
.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta de Acabados Nivel I
PLANTA ACABADOS
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
28
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
NIVEL I
Direccion de Logistica
POLICIA NACIONAL
SIMBOLOGÍADESCRIPCIÓNSÍMBOLOS
PAREDES DE BLOQUE DE 6"
PAREDES DE TABLA YESO
PAREDES DE DUROCKCERAMICA DE PARED 30X60 cmDuchas: 1.80 m y baños: 1.50 mPINTURA LATEX ACABADO MATE COLOR CACATUA
01 01 01 01
01 01 01 01
01
01
01 01 01 01 01
01
01
01
01
0101
01
01
01
01
01
01
01
01
0101
01
01
01
01
CIELO FALSO DE VINILICO SIN DISEÑOCOLOR BLANCO, 2"X2"
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 mH=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
H=3.20 m
01PISO FLOTANTE ANTIFATIGA NPT +0.80 m
01
02
02PISO PORCELANATO ALTO TRAFICO
02
02 02
02
02
02
0202
02
PLANTA DE CISTERNA
0.200.20
0.2
02.3
00.2
0
2.5
0
0.20
0.2
0
0.20
0.2
00.5
10.6
5
TAPA PRA INSPECCION METALICA
2.60
PLANTA
2.1
4
4 VARILLAS #3ANILLO #2 @ 0.154 VARILLAS #3
ANILLO #2 @ 0.15
4 VARILLAS #3ANILLO #2 @ 0.15
TUBO PVC Ø 114"
ALIMENTACION CASAREF. HORIZONTAL
2 VARILLAS #3 @ 2 HILADAS
CHAFLANCHAFLAN
PARED DE BLOQUE 8"FUNDIDO CON 1.5 cm. DE LIGA
REF. VERTICAL1 VARILLA #5 @ 0.20
NIVEL MAXIMO DE AGUA
INTERIOR RPELLADO ESP. 2 cm. YDADO FINO TIPO PILAREF. HORIZONTAL
2 VARILLAS #3 @ 2 HILADAS
TUBO PVC Ø VIENE DERED MUNICIPAL
REF. POR FLEXION# 3 @ 0.125. A/S
TAPA METALICA PARA INSPECCION
0.2
0
0.1
20.0
50.0
6
0.5
00.3
00.1
7
0.12 0.58
VALVULA FLOTADOR Ø 1 2"
0.1
2
0.13 0.13
0.65
0.08 0.08
CHAFLAN
0.2
0
0.1
5
0.2
0
0.30
0.1
6
0.0
4
0.40
0.150.150.45
0.3
5
2.5
8
0.2
02.1
40.3
5
0.1
0
0.58
REF. POR FLEXION# 4 @ 0.125. A/S
2.0
1
2.5
0
SECCION
SECCION DE CISTERNA
PLANTA DE CISTERNA
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
27
PROPIETARIO
UBICACION:
28
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
A.G.S.R.
Direccion de Logistica
POLICIA NACIONAL
INS- H
18.77
9.1
5
27.50
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.2
83
.2
02
.6
7
4.00 4.00 4.00 4.00 2.02 1.56 2.96
3.1
32
.7
43
.2
8
2 3 4 5 6 7 98
A
B
D
E
1
2.74
10
2.22
2.22
2.74
A
B
D
E
C
9.1
5
2 3 4 5 6 7 981 10
ESCALA 1:200
Planta de Acabados Nivel II
PLANTA ACABADOS
Indicada
E S C A L A G R A F I C A E N M t s.
A P R O B O
PLANO LLAVE
PROYECTO:
CONTENIDO
F E C H A :
HOJA Nº:
29
PROPIETARIO
UBICACION:
28CON
DESPACHO DE SEGURIDADSECRETARIA DE ESTADO EN EL
REMODELACION DATA CENTER
Unidad Ejecutora de Proyectos
U E P
TELEMATICA
D I B U J O
MR
NIVEL II
Direccion de Logistica
POLICIA NACIONAL
01 01
01 01
0101
01
010101
01 01 01
010101
01
0101
01
01 01
01
01
01
01
H=3.20 m H=3.20 m
H=3.20 mH=3.20 m
H=3.20 m
H=3.20 m H=3.20 m
02
02
02
02
020202
02 02
SIMBOLOGÍADESCRIPCIÓNSÍMBOLOS
PAREDES DE BLOQUE DE 6"
PAREDES DE TABLA YESO
PAREDES DE DUROCKCERAMICA DE PARED 30X60 cmDuchas: 1.80 m y baños: 1.50 mPINTURA LATEX ACABADO MATE COLOR CACATUA 01
CIELO FALSO DE VINILICO SIN DISEÑOCOLOR BLANCO, 2"X2"
01PISO FLOTANTE ANTIFATIGA NPT +0.80 m
02PISO PORCELANATO ALTO TRAFICO