41
Richard Hefti, PE Carla Talich, PE May 5, 2016

Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

  • Upload
    donhu

  • View
    216

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Richard Hefti, PECarla Talich, PE

May 5, 2016

Page 2: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Agenda:1. Introduction2. Pre-design3. Design and Permitting4. Construction

Page 3: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

1: Introduction

Page 4: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Regional Water Supply

4.5 billion gallons

50 billion gallons

Page 4

Page 5: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Drinking Water System

• 96 direct wholesale customers(33 Group A & 63 Group B)

• Tulalip Tribes• Over 27,000 connections• Service area population ~ 600,000

Page 5

Page 6: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Water Transmission• 2, 3, 4, & 5 Lines• 42” – 52” diameter• 70 miles

Page 6

Page 7: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

The Everett Drinking Water Treatment Plant produced an average of 52.7 MGD of water in 2015, a 5.9 percent increase from the 49.6 MGD produced in 2014 and 5.6 percent increase from the previous four-year average of 49.8 MGD.

Page 7

52.9 54.6

48.9 4951 49.4 49.6

52.7

40

45

50

55

60

2008 2009 2010 2011 2012 2013 2014 2015

Average Daily Production of Drinking Water (MILLION GALLONS PER DAY)

Page 8: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Drinking Water Distribution(PERCENT OF DEMAND)

Alderwood Water & Wastewater

52.7%

Everett23.8%

PUD No.1 of Snohomish County - 8.1%

Marysville - 5.8%

Monroe - 3.9%

Mukilteo Water & Wastewater - 1.9%

Snohomish - 1.2%

Silver Lake Water & Sewer – 0.5%

Other - 2%

Page 8

Page 9: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Page 9

– 1965 Design• 51” ID steel pipe, 7/16” thick• Double welded lap joints• Coating: coal tar enamel 3/32” thick, 15# bonded

asbestos felt, and kraft paper• Lining: Jet-Set primer and 3/32” thick coal tar enamel

5 Line at Pilchuck River

5 Line

Water Transmission Line 5

2, 3 & 4 Lines

Page 10: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pilchuck River Crossing

Page 10

Many users = Many considerations

Page 11: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

2: Pre-design

Page 12: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pre-Design Condition Assessment

– Pipeline exposed and subject to scour and impact from debris

– Multiple repairs to provide cover and protection

– Non-destructive testing and pipe condition assessment concluded reduced life expectancy / risk of failure

Page 12

Conclusion: Repair / Replace

Page 13: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pre-DesignAlternatives

– Repair

– Horizontal Directional Drilling

– Microtunneling

– Overhead Bridge

– Open Trench

Page 13

POTENTIAL NEW PIPELINE

ALIGNMENT CROSSING RIVER

Page 14: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pre-Design Alternative – Repair: Grade Control Structure

– Pros • Fastest way to provide

protection• Lowest cost

– Cons• History (recent repairs did not

last)• Pipe condition assessment

showed limited longevity

Presentation Title Page 14

Conclusion: Replace the pipeline at the crossing

Page 15: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pre-Design Alternative – Horizontal Directional Drilling

– Pros • Underground pipeline

preferred (more secure)

– Cons• Marginal feasibility / high risk

(sand, gravel, cobbles, boulders, debris)

Conclusion: Ruled out due to feasibility/risk

Page 15

Page 16: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pre-design Alternative – Microtunneling

– Pros • Underground pipeline

preferred (more secure)• Lower risk than HDD

– Cons• Risk (boulders, stumps, mixed

face conditions)• Highest cost

Conclusion: Ruled out due to risk

Page 16

Page 17: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pre-Design Alternative – Overhead Crossing

Page 17

AWWA D100, 5MG, Welded steel

10 MG lined AWWA D110, Type 1, 5MG

ACI 350, CIP, 50MG– Pros • Feasible / low risk

construction

– Cons• Above ground (less secure,

conflicts with City policy)

Conclusion: Ruled out due to security

Page 18: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pre-Design Alternative – Open Trench

Page 18

Existing 15MG lined, open top

New 13MG CIP

– Pros• Underground pipeline• Technically feasible

– Cons• Permits (longest timeline)• Challenging soil conditions• Surface and groundwater

controlConclusion: Preferred Alternative for Design Phase

Page 19: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

3: Design and Permitting –Open Cut Replacement

Page 20: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Design Bid Build for 2012 Construction

– Pipeline Design Elements• 430 LF • Welded Steel, 0.5” thick • Coating: 40 mil polyurethane • Lining: 20 mil polyurethane• Connections • Access manways• Draining and dechlorination

Page 20

EXISTING PIPE

PROPOSED NEW PIPE

Page 21: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pipeline Design

– Operating pressure: 160 psi – Connections• Volume of water to drain, treat,

discharge to river = 1MG• Total Down-time allowed for 5-Line:

12 hour target

Presentation Title Page 21

Water filter plant,El. 694

Pipeline El. 40’

Drain appx.10,000 LF

Page 22: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Dechlorination Vaults

• Permanent structure located above OHWM with temporary pipe connections

• Internal baffle to dissipate energy

• Used for:o treating and discharging water

from 5-Lineo During testing of new pipelineo Prior to final connections

Presentation Title Page 22

Page 23: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Design

Page 23

– Geotechnical• Investigation and data report• Performance based dewatering

and shoring specifications

– River Hydraulics• Scour depth / cover over pipeline• Geomorphic review• Channel and streambank restoration• Zero rise analysis

Page 24: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

River Diversion / Isolated Work Area

– Purpose• Obtain permits for in-water work• Isolate work area• Protect aquatic life

– Goals • Work within easement

– Concept• Two phased approach, if needed• Contractor to final design

Presentation Title Page 24

Page 25: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

– Permit Agencies• US Army Corps of Engineers (Corps 404)• US Fish and Wildlife Service (ESA consultation)• National Marine Fisheries Service (ESA consultation)• Washington State Department of Fish and Wildlife (HPA)• Washington State Department of Ecology (401Certification)• Washington State Department of Natural Resources (Aquatic Easement)• Snohomish County (Shoreline, Flood Hazard, Building Permit, LDA)

– Permits finalized in May 2012

– Contractor Award June 2012

– In-water Work period August 1 to August 31, 2012

Permits and Approvals

Page 25

Page 26: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

4: Construction

Page 27: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Construction – Design Bid Build 2012

– Permitted in-water work period: • 30 Days (August 1 to August 31)

– River Diversion (phase 1):• ~ 2/3 of the river around work area

Page 27

– No dewatering wells installed

– Contractor needed more time to plan and construct

Page 28: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Construction – Design Bid Build 2012

– Sheet pile and shoring installed August 19-20

– Attempted to remove water from trench without success

– Contractor withdrew• Isolated work area dismantled • Banks restored• Site secured for future

construction

Page 28

Page 29: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Construction –Design-Build 2015

– Contractor team planned from RFQ, RFP, and through construction

– Permit revisions: Longer in-water work period (July 1 to August 31) River diversion around the work area

– Planning and ownership of soil and groundwater conditions

Page 29

Page 30: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Early planning / preparation for in-water work window

– Groundwater wells:• Test wells (winter 2014/2015)• Well installation east trench April 2015• Low water year, so in June 2015, worked with agencies to install wells

below OHW (close to the edge of the river)

Page 30

Page 31: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

East Pipe Trench

• Installed prior to in-water work (May/June 2015)

• Test section of pipe to learn about soil and groundwater

• River diversion channel to be constructed over top this new section of pipe

Lessons Learned• Significant amount of water in

pipe trench, “like a waterfall”• Bulkhead installed to help cutoff

flow of water into the trench

Page 31

Page 32: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Diversion Channel Construction / River By-pass

– Open channel, lined with geomembrane and rock

– Constructed out of the OHW prior to in-water work period

Page 32

Page 33: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Diverting the River into Diversion Channel

– Upstream end – Downstream end

Page 33

Page 34: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Fish Removal / Start work to “dry” river bed

– River is diverted

– Now time for fish removal

– Route surface water out of channel

– Groundwater well installationand trench shoring

Page 34

Page 35: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Pipe Trench Across River

– 20 feet below river bottom

Page 35

Page 36: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Connection Points (old / new pipe)

– East• Looser material than west side• Many large boulders encountered• Difficult groundwater conditions

– West • Highly cemented soils• Less groundwater

Page 36

Page 37: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

River Crossing Complete

Page 37

Construction Everett-HD.mp4

Page 38: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Bank Restoration

– Rock riprap below OHWM

– Soil/coir fabric wraps

– Live stakes / native vegetation

– Restore diversion channel cut through private property

– Cottonwood to be used for restoration

Page 38

Page 39: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Dewatering Existing 5-Line / Preparing for Connections

– October 22-23, 2015• Pipeline shutdown at 10 PM, 10/22• Gravity drained by 2:15 AM

• Multiple crews both sides of river (pumping out water, welding, coatings)

• Connections complete and water restored 8 PM, 10/23.

Page 39

Page 40: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Summary and Lessons Learned

Page 40

– Design Build• Provided excellent planning opportunity for dewatering and river diversion• Good and direct communication with permitting agencies allowed for

meeting deadlines– Increased time for in-water work– Can talk with permit agencies directly about means and methods– Coordinated permission to encroach on OHWM areas– Removal of existing pipeline

» Condition of Aquatic Lease Agreement (by 2022)» Easily added to permit through direct coordination with Agencies based on

actual Contractor methods» Successful removal in November 2015

• Contractor’s team had to think about it from RFQ to RFP selection. • Paid off as work went seamlessly.

– Sentiment after 1st try was to go trenchless• Low feasibility / High Risk due to geologic and groundwater conditions

– Verified via construction

Page 41: Richard Hefti, PE Carla Talich, PE - PNWS-AWWA Sessi… · Drinking Water System • 96 direct wholesale customers (33 Group A & 63 Group B) • Tulalip Tribes • Over 27,000 connections

Thank YouRichard Hefti, PESenior Engineer, City of Everett Public WorksD: 425-257-7215, [email protected]

Carla Talich, PESenior Civil Engineer/Project Manager, AECOMD: 206-438-2125 [email protected]