Risk Assesment of Estonian Oil Fields

  • Upload
    jake-aj

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

  • 8/12/2019 Risk Assesment of Estonian Oil Fields

    1/7

    The 12 th International Conference ofInternational Association for Computer Methods and Advances in Geomechanics (IACMAG)1-6 October, 2008Goa, India

    Risk Assessment of Surface Miner for Estonian Oil Shale MiningIndustry

    S. Sabanov, J-R. PastarusDept. of Mining, Tallinn University of Technology, Tallinn, Estonia

    O. Nikitin, E. VliDept. of Development, AS Eesti Plevkivi, Jhvi, Estonia

    Keywords: high-selective mining, risk estimation

    The paper deals with risk assessment of a high-selective oil-shale mining technology using surface miner Wirtgen2500SM. This study addresses risk associated with productivity and cutting quality on example of Estonian oilshale deposit in areas with complicated layering conditions. The risk assessment method allows choosingrelevant technology with friendly environment and economic value. For risk estimation the event tree is used. Theresults of the risk assessment are of practical interest for different purposes.

    1 Introduction

    About 98% of electric power and a large share of thermal power were produced from Estonian oil shale. Miningsector faces challenges to increase the output of mines and to minimize the environmental impact of mining atthe same time. Continuous mining and milling techniques for the hard rock industry are up to now limited throughthe hardness of rock material. The application limits for the future technique will be placed above the limits ofbucket wheel excavating systems with a diggability of normal up to 10 MPa of uniaxial compressive strength(UCS). This can be expanded with special designed excavators for frozen hard coal or soft limestone (Wilke at al.1993). Horizontal and vertical ripping techniques are currently used for materials up to 50 MPa UCS, sometimescombined with in-pit crushing systems.

    Surface mining is carried out in open casts with maximum overburden thickness of 30 m. Draglines with 90 mboom length and 15 m 3 bucket size are used for overburden removal. Hard overburden consists of limestonelayers and is blasted before excavation. Oil shale layers are blasted as well or broken by ripping (semi-selectivemining). Disadvantage of ripping is excessive crushing of oil shale by bulldozer crawlers. Excavated rock istransported with 32-42 or 60 tonnes trucks (Belaz and Euclid) to the processing or crushing plant depending onopencast.

    Aim of the research and in-situ SM testing is to introduce continuous mining technology on example of Estonianoil shale deposit in areas with arduous layering conditions. The results of in-situ testing can be used to improveexisting situation in mining fields with complicated geological conditions and in densely populated regions.

    Continuous surface miners can find their natural applications in projects where drilling and blasting is prohibitedor where selective mining of mineral seams, partings and overburden is required. Besides they offer furtheradvantages less mineral loss and dilution, improved mineral recovery especially in areas sensitive to blasting,less stress and strain on trucks due to minimum impact of the excavated material, primary crushing and

    fragmentation of mineral rock, reduced capacity requirements for preparation plants.

    The high-selective oil-shale mining technology introduces by surface miner (SM) Wirtgen SM2500 and the first 9months of testing results at Narva open-pit in Estonia. The technology allows to decrease oil-shale loses from10-15% up to 5-7% on in-situ conditions. Mining process of the surface miner has a lower disturbing impact,which is topical in open casts and quarries especially in densely populated areas. The low level of dust and noiseemissions and also very low vibration are arguments to mine oil shale with surface miner instead of drilling-blasting operations. (Nikitin at al., 2007)

    The most perspective advantage of SM is high-selective mining. Surface miner can cut limestone and oil-shaleseams separately and more exactly than rippers (2-7 cm) with deviations about one centimeter. It is estimatedthat due to precise cutting enables surface miner to increase the output of oil shale up to 1 tone per square

    1836

  • 8/12/2019 Risk Assesment of Estonian Oil Fields

    2/7

    meter. It means, that oil-shale looses on the case of SM technology can be decreased from conventional 12 up to5 percent

    2 Risk analysis of surf ace miner Wirtgen 2500M techno logy

    Continuous surface miner, which are designed to cut softer rock materials like sandstone, clay, bauxite, hardcoal, phosphate, gypsum and marl are operating between 10 MPa and 70 MPa compressive strength. Nowadays,road cutting machines are working materials up to 100-110 MPa compressive strength. The very recentdevelopments show that there is a need for investigations to enlarge the mentioned application limits.

    The Wirtgen 2500SM design with a mid-located cutting drum (diameter 1.4m, cutting width 2.5m) was expected tobe more promising for hard rock (80-110 MPa) applications than the front-end designs. Here, the whole weight ofthe machine (100 t) is available for the penetration process and only a smaller torque resulting from the cuttingprocess (cutting depth up to 0.6m) has to be counterbalanced. Besides, the surface miner with middle drumconcept moves during the winning process. Due to this great moved mass, much more dynamic mass forces arepossible than during the movement of the small mass of the cutting organ mounted on a boom.

    Modifications and development work for the tested SM focused mainly on the corresponding cutting drums(number of cutting lines) and specifications of the cutting tools, different loading technologies (windrowing ordirect truck loading) also (Figure 1 a, b).

    (a)

    (b)

    Figure 1. Different loading technologies: windrowing (a) and direct truck loading (b)

    2.1 Rock Breakability Results

    To be able to transfer the achieved results to other EU rock mines, it is necessary to identify the SM and cuttingrock parameters responsible for the breakability factor of a deposit. The development of such a generalisedclassification system is therefore an important objective of the project as well.

    Applying statistical distribution according to Weibull, the function of size distribution of oil-shale particles may beassumed as follows:

    W = 1 exp[( d/d0)m] (1)

    where d0 = d 0.63 is diameter of screen opening to pass 63.2% of broken oil shale; m is breakability factor.

    The results from sieving analysis made for limestone and oil-shale layers show that for Narva open pit test siteconditions breakability factor m = 1.1. Hence, the share of oil shale passing the 25 25-mm screen in the totalmine-run shale equals to

    25 = d 25 = 1 [(25/ d0.63 )1.1 ] (2)

    where, d0.63 = 20.0 + 2.16S for SM up-cutting direction (see Figure ); S is cross-section of cut, cm2.

    In 1968 E. Reinsalu had proposed an approximate relationship between energy consumption by differentmethods of breaking and average size of mined oil-shale particles, which was later completed with the present

    1837

  • 8/12/2019 Risk Assesment of Estonian Oil Fields

    3/7

    investigation data (Figure 2).

    Concentratibility and trade oil shale grade depend on sizing extracted oil shale, which, in its turn, is closely relatedto energy consumption and the selected method of oil shale breaking. Equation (3) and Figures 3 a, 3 bdemonstrates the correlation of the distribution law parameters and specific energy consumption with theparameters of oil-shale and limestone particles sizing. The tested SM sizing parameters are inside the areas withnumber 7 and 8 ( Figure 2 a).

    (a) (b)

    Figure 2. Effect of method of breakage on specific energy consumption (A.) and the resulting average oil shaleand limestone sizing (B.)

    Where, 1 drilling in limestone; 2 drilling in oil shale; 3 cutting machine in limestone; 4 cutting machine in oilshale; 5 cutting of layer B with shearer loader UKR-1; 6 cutting with shearer; 7 cutting with DKS (a mean formeasuring cuttability) in limestone; 8 cutting with DKS in oil shale; 9 breaking with ripper (surface mining);Wirtgen 2500SM sizing data (up-cutting direction): cutting in oil-shale complex EF (0.43m); cutting inlimestone seams A/B (0.18m) and C/D (0.25m); cutting in oil-shale complex CB (0.36m).

    3 Risk estimation of surface miner testing results

    The Wirtgen 2500SM was delivered to AS Eesti Plevkivi at the end of 2006. The testing of SM was beginning atNarva oil-shale open cast. The SM testing was held from 01.01.2007 to 30.09.2007 and was estimated by fourtesting phase (Figure 3). The machine was operated in two or three-shift systems.

    During the first testing phase (I) 145 total operating hours from 200 available (9.4 m/min) and during the secondtesting phase (II) 151 from 208 available shift-hours (9.0 m/min) the SM with direct truck loading was tested. Butthe real cutting time was 35 and 41% from available shift-hours for the each period correspondingly. During thethird testing phase (III), 4130 total operating hours from 5416 available shift-hours the SM with about 26% ofwindrowing. For the fourth testing phase (IV) 111 total operating hours from 112 available shift-hours the SMwindrowing achieved 100%. The average cutting speed during the real cutting time was 11.5 m/min. For thewhile period real cutting time is about 46%, where on average during the shift-time 33% SM operated on oil-shalelayers and 13% on limestone (layers C/D and B/A). The Figure 3 illustrates the shift-hours distribution graphics forthe testing phases.

    1838

  • 8/12/2019 Risk Assesment of Estonian Oil Fields

    4/7

    Direct truck loading Direct truck loading

    I testing phase

    24%

    36%

    27%

    13%

    S er vi ce C ut ti ng Wai ti ng Ma ne uve rs

    II testing phase

    29%

    41%

    27%

    3%

    S er vi ce C ut ti ng Wai ti ng M an eu ve rs

    Windrowing 26% Windrowing 100%

    III testing phase

    30%

    46%

    20%4%

    S er vi c e C ut ti ng Wa it in g M an eu ve rs

    IV testing phase

    56%35%

    1% 8%

    S er vi c e C ut ti ng Wa it in g M an eu ve rs

    Figure 3. The shift-hours distribution graphics for the while testing period.

    During the testing phase registered waiting is about 27%. Obviously, the main reason is direct truck loadingmethod. Analysis has shown that by direct truck loading method, truck-waiting downtime decrease real cuttingtime by 1.0-1.5 hour per shift and average cutting speed by 20-25%. The percent of waiting include about 7% oftime looses for trucks exchanging, about 6% for SM upper conveyor manoeuvres, then about 6% for spade-work(SM controlling before and after the shift) and up to 10% time looses due to the ground water problems.

    y = 16,299e 0,0226x

    R2

    = 0,8288

    0

    20

    40

    60

    80

    0 20 40 60 80

    Windrowing, %

    P r o

    d u c

    t i v

    i t y ,

    %

    Figure 4. Dependence of SM productivity on windrowing percentages

    As you can see from the graph (Figure 4), there is a great SM productivity potential when windrowing percent isgrowing. The additional LHD-machine operating and SM depreciation costs greater oil-shale excavation rate iscoating. As a result the oil shale operating cost can be reduced up to 10-15%.

    Main aspects influencing the efficiency of the combine work concern the duration of the processes. Cuttingdifferent layers, track dumper loading (waiting), manoeuvres and maintenance processes are the most importantfactors. Investigations have shown that duration of the processes influence on productivity. The main quantitativeapproach used in risk estimation is the event tree method (Calow, P. 1998). This method was selected as the

    1839

  • 8/12/2019 Risk Assesment of Estonian Oil Fields

    5/7

    most appropriate one for the risk estimation of the SM. In the first stage of the project time factor was taken intoconsideration. For probability determination the empirical approach was used (Williams at al. 2004). The eventtree indicating the probabilities of the SM processes and spent time. It is possible to select different variants andto determine the probability of one.

    The event tree allows determining time deviations from average value (Figure 5). Four different testing phases (I-IV) of the SM were observed. For determination suitable variant greatest negative numbers were chosen incomparison analysis with maximal possible productivity received during the tests. Application of the fault tree is

    presented in Table 1. Selected variant of the tests give different value of the probabilities and deviations from theaverage value. For determination the higher productivity is necessary to give attention on processes with positivevalue and improve it quality (Figure 5).

    0.06 0.957

    - 0.530

    -0.216

    -0.110

    -0.013

    -0.244

    -0.311

    0.258

    -0.308

    -0.164

    -0.141

    0.6140.449

    0.429

    0.075

    I

    II

    III

    -0.10

    - 0.01

    -0.03

    -0.02

    0.02

    0.21

    -0.05

    -0.06

    - 0.11

    -0.05

    0.01

    0.08

    0.08

    -0.11

    Cutting

    Manoeuvres

    Waiting

    Maintenance

    Full circle

    0.46

    0.35

    0.06

    0.19

    I

    I

    I

    II

    II

    II

    III

    III

    III

    IV

    IV

    IV

    Figure 5. Event tree of different processes

    In case of excluding complicated geological condition higher productivity can achieve owning to the windrowingmethod.

    Table 1. Time deviations from the average value

    Testing phases I II III IV

    Maintenance -0.308 -0.164 -0.141 0.614

    Cutting -0.216 -0.110 -0.013 -0.244

    Waiting 0.449 0.429 0.075 -

    Maneuvers 0.957 -0.530 -0.311 0.258

    4 Risk evaluation

    The thickest and harder limestone seam C/D (60-80 MPa) has sufficient quality to produce aggregate for roadbuilding and concrete. Separately extracted limestone (C/D and A'/B) can be left directly in mine, which reduceshaul costs and increase run-out oil shale heating value without additional processing.

    The oil yield increase by 30%, up to 1 barrel per tone during the oil shale retorting, because of better quality. Thesame principle is valid for oil shale burning in power plants because of less limestone containing in oil shale. Itsresults higher efficiency of boilers, because up to 30% of energy is wasted for limestone decompose during the

    1840

  • 8/12/2019 Risk Assesment of Estonian Oil Fields

    6/7

    burning process. Positive effect would result in lower carbon dioxide and ash emissions (Adamson at. al 2006).

    Another perspective of surface miner would apparent in places with relative small overburden thickness (less than10 m) and near the towns where the removal of hard overburden with SM should be considered as well instead ofoverburden blasting. On these cases the SM would cut considerably operating costs of stripping and possibilitymine out reserves near the densely populated areas.

    Another problem is the oil-shale bed geological characteristics. Estonian oil-shale bed consists from oil-shale and

    limestone seams with different thickness and compressive strength. Oil shale is relatively soft rock with UCS 15-40 MPa but limestone is 40-80 MPa. There are also places near the karsts zones with 100-120 MPa compressivestrength. During the cutting process the loads in cutting tools vary greatly due to the differences in rock physicaland mechanical parameters, which lead increased loading of the cutting drum.

    The applicants have recently encountered many situations where manufacturers cutting drum/head designs couldbe significantly improved upon, as they were not tailored to the actual geotechnical conditions predominant at themine. However, without more user-friendly tools, the opportunity to make such improvements in practice has beenlimited. Improved designs have the potential to increase cutting speed and efficiency, reduce pick replacementcosts, reduce machine down time through gearbox failure and pick changing, improve machine reliability byreducing excessive vibration during cutting, improve loading efficiency and reduce fine oil shale and dustproduction. Research program to develop design of cutting tools/drums to minimise cutting tools consumption andmachine down time on the basis of testing data will be develop. New design of cutting drums will lead to improvedtool cutting (pick) loading efficiency with less fine rock and dust production. The result of this work will be takeninto account for the next SM design.

    Development of mining machinery and mining technology by the way of selective mining will improveenvironmental situation in Europe and Baltic Sea region. Effect can be achieved in decreasing CO 2 emission, ashand water pollution.

    Selective mining enhances the quality of oil shale. Through the cutting quality the mineral resource utilisation ismore effective and environmental impact is lower. The disturbing impact of drilling-blasting operations in quarriesand open casts next to densely populated areas causes vibration, dust and noise emissions which are argumentsto stop operations where blasting is used. Surface miner high-selective technology has perspectives due toreduced dust and noise, non-existent vibration and dust emission levels also.

    By extending the applicability of the surface miner/road cutting technology from soft material into semi-hard andhard rocks with UCS of up to 110-120 MPa, an economically and environmentally acceptable alternative to drillingand blasting could be available. By taking into account the rock-mechanical and mine planning aspects of the testapplication, an evaluation of the overall economical feasibility and the transfer of the results to other hard rockmines can be ensured.

    5 Conclusions

    Event tree allow determining suitable variant of different processes for continuous surface miner. Fordetermination suitable variant greatest negative numbers were chosen in comparison analysis with maximalpossible productivity received during the tests. Surface miner higher productivity in testing phase (IV) wasachieved on account of 100 % windrowing method. The high cutting performance can be explainable absence ofwaiting time. This information allows finding adequate decision to improve quality of the processes and avoidnegative influence.

    Results obtained by this project can be using in different industrial sectors. The main applications will be found inthe surface mining and road construction sectors. New usage could be in zones where rock soils will transformedinto zones with agricultural capacities.

    There is a couple of direct and indirect effects which reduce oil shale cost prise on 20% due to less minerallosses, loading method (windrowing) can optimize fuel consumption when high-selective mining technology withsurface miner is applied. The result of this work will be taken into account for the next surface miner design.

    6 Acknowledgements

    The research was supported by the Estonian Science Foundation (Grant ETF 6558).

    7 References

    Adamson, A., Jostov, M., Kattel, T. 2006. Perspectives for the Mining of Oil Shale and Limestone with Surface Miner inEstonia. Proc. ISCSM Aachen 2006.

    1841

  • 8/12/2019 Risk Assesment of Estonian Oil Fields

    7/7

    Calow, P. 1998. Handbook of Environmental Risk Assessment and Management. Oxford, Blackwell Science,

    Nikitin, O.; Vli, E. ; Sabanov, S.; Pastarus, J.-R. 2007. The surface miner sustainable technology introduction for oil-shalemining in Estonia. In: Environment. Technology. Resources: Proc. 6th International Scientific and Practical Conference,Rezekne, Latvia, 20-22 June, 2007. (Toim.) Noviks, G.; Morozov, V.; Tepfers, R.; Leal, W.; Chrzan, T.. Rezekne, Latvia: RAIzdevnieciba, 55 - 61.

    Williams, D. J., Loch, R. J., Vacher, C. 2004. Risk assessment applied to tunnel erosion of mine spoils // Proc. of the 11thTailings and Mine Waste Conference. 1013 October 2004, Vail, Colorado, USA. P. 6370.

    Wilke, F.L., Spachtholz, F.X. 1993. Operational Conditions for Continuous Mining Systems in Hard Rock Open Pit Mines. BriteEuRam II project BE 6044 of the European Commission, www.tu-berlin.de.

    1842