46
Risk Assessment of Loss of Mains Protection – Phase II 23 March 2015 Adam Dyśko University of Strathclyde Glasgow, UK e-mail: [email protected]

Risk Assessment of Loss of Mains Protection – Phase II · levels depend on test). PV emulator outputs DC voltage and current within set limits ... Frequency ramps : ramp down then

Embed Size (px)

Citation preview

Risk Assessment of Loss of Mains Protection – Phase II

23 March 2015

Adam DyśkoUniversity of StrathclydeGlasgow, UKe-mail: [email protected]

Outline

WP1 – Hardware testing based characterisation of DG – PNDC

WP3 – Risk assessment calculation DG connection register analysis (WPD) Establishing dominant connection groups Mixing generation profiles Methodology

WP2 – Simulation based characterisation of DG

PV emulator supplying single phase 3kW Fronius inverter. Desired power output set (power

levels depend on test). PV emulator outputs DC voltage

and current within set limits using MPPT curve.

Fluke power quality analyser measurements at: Inverter output. PCC (convention set as export

to grid).

Single phase load bank used as local load (1kW steps).

Test Setup

WP1 – Hardware testing based characterisation of DG – PNDC

Islanding: 2kW load while inverter output is adjusted to minimise PCC power flow. The public grid is used in this case.

Frequency ramps: ramp down then ramp up between 49.5-48.5Hz at a +/-0.5Hz/s rate. The MG set is used in this case.

HV fault: 60Ω single phase earth fault applied on the upstream 11kV network. The MG set is used in this case.

Tests conducted

5kW PV Emul.

Grid

PCC

ABC

11kV/0.433kV

5kW PV Emul.

MP, Q

meas.M-G setRL load

bank

WP1 – Hardware testing based characterisation of DG – PNDC

At the point of islanding: Measured inverter output around 2.03kW and -20VAr. Measured PCC export around +/-2W and 140VAr.

Inverter trips within 4 cycles.

Islanding results – Inverter Power

Time (s)95 95.2 95.4 95.6 95.8 96 96.2 96.4 96.6 96.8 97

Pow

er (W

, VA

r)

-100

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900

2000

2100Inverter Output Power - Islanding

ReactivePower

ActivePower

WP1 – Hardware testing based characterisation of DG – PNDC

Islanding results – Inverter Voltage

Time (s)0.4 0.45 0.5 0.55 0.6 0.65 0.7

Vol

tage

(V)

-400

-300

-200

-100

0

100

200

300

400Inverter Output Voltage - Islanding

Voltage

WP1 – Hardware testing based characterisation of DG – PNDC

Islanding results – Inverter Current

Time (s)0.4 0.45 0.5 0.55 0.6 0.65 0.7

Cur

rent

(A)

-15

-10

-5

0

5

10

15Inverter Output Current - Islanding

Current

WP1 – Hardware testing based characterisation of DG – PNDC

Islanding results – PCC Power

Time (s)121 121.2 121.4 121.6 121.8 122 122.2 122.4 122.6 122.8 123

Pow

er (W

, VA

r)

-10

0

10

20

30

40

50

60

70

80

90

100

110

120

130

140

150

160PCC Power - Islanding

ActivePower

ReactivePower

WP1 – Hardware testing based characterisation of DG – PNDC

Islanding results – PCC Voltage

Time (s)0.3 0.35 0.4 0.45 0.5 0.55 0.6

Vol

tage

(V)

-400

-300

-200

-100

0

100

200

300

400PCC Voltage - Islanding

Voltage

WP1 – Hardware testing based characterisation of DG – PNDC

Islanding results – PCC Current

Time (s)0.3 0.35 0.4 0.45 0.5 0.55 0.6

Cur

rent

(A)

-3

-2

-1

0

1

2

3PCC Current - Islanding

Current

WP1 – Hardware testing based characterisation of DG – PNDC

MG set speed controlled tightly using RTDS: Ramp up and down rate of +/-0.5Hz/s within 49.5Hz – 48.5Hz band. Band selected to avoid HV network protection or inverter tripping caused by MG

set speed control overshoot.

Inverter remains stable during and after ramps.

Frequency ramp results – Frequency profile

Time (s)60 70 80 90 100 110 120

Freq

uenc

y (H

z)

48.2

48.3

48.4

48.5

48.6

48.7

48.8

48.9

49

49.1

49.2

49.3

49.4

49.5

49.6

49.7

49.8Grid Frequency Profile

Frequency

WP1 – Hardware testing based characterisation of DG – PNDC

MG set speed controlled tightly using RTDS: Ramp up and down rate of +/-0.5Hz/s within 49.5Hz – 48.5Hz band. Band selected to avoid HV network protection or inverter tripping caused by MG

set speed control overshoot.

Inverter remains stable during and after ramps.

Frequency ramp results – Frequency profile

Time (s)60 70 80 90 100 110 120

Freq

uenc

y (H

z)

48.2

48.3

48.4

48.5

48.6

48.7

48.8

48.9

49

49.1

49.2

49.3

49.4

49.5

49.6

49.7

49.8Grid Frequency Profile

Frequency

WP1 – Hardware testing based characterisation of DG – PNDC

-5

-4

-3

-2

-1

0

1

2

3

4

60 61 62 63 64 65

ROCOF

• Load bank set to 2kW.• Inverter output set to around1.4kW.• Measured inverter output reactive power of around 20VAr.

Frequency ramp results – Inverter Power

Time (s)60 70 80 90 100 110 120

Pow

er (W

, VA

r)

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500Inverter Power Output - Frequency Ramp

ActivePower

ReactivePower

WP1 – Hardware testing based characterisation of DG – PNDC

In the process of ordering further inverters for further testing: 5kW SMA SunnyBoy. 5kW ABB (PowerOne). 5kW Kaco. 10kW SMA TriPower (three phase).

Testing will include up to 2 single phase inverters simultaneously. Installation of new inverters and testing planned for second half of

April. Build working group feedback into upcoming testing.

Next steps

WP1 – Hardware testing based characterisation of DG – PNDC

WP3 – Risk assessment calculation

DG register analysis (WPD)

WP3 – Risk assessment calculation

Technology mapping (based on WPD data).

Primary substation Generator type Connected export capacity [kW]

Accepted not yet

connected export

capacity [kW]

Total export capacity [kW]

Abington 33/11kv Photovoltaic 79.38 0 79.38Acreage Lane 33/11kv Hydro 3.56 0 3.56Acreage Lane 33/11kv Landfill Gas Sewage Gas Biogas (not CHP) 11700 0 11700Acreage Lane 33/11kv Other Generation 1200 0 1200Acreage Lane 33/11kv Photovoltaic 503.21 0 503.21

Alford 33/11kv Photovoltaic 260.389 0 260.389Allenton 33/11kv Micro CHP (Domestic) 0.215 0 0.215Allenton 33/11kv Photovoltaic 883.01 0 883.01

Alliance & Leicester 33/11kv Biomass & Energy Crops (not CHP) 1850 0 1850Alliance & Leicester 33/11kv Landfill Gas Sewage Gas Biogas (not CHP) 2590 0 2590Alliance & Leicester 33/11kv Other Generation 1000 0 1000Alliance & Leicester 33/11kv Photovoltaic 225.564 0 225.564

Ambergate 33/11kv Onshore Wind 91 225 316Ambergate 33/11kv Photovoltaic 131.36 0 131.36

Anderson Lane 33/11kv Photovoltaic 597.94 0 597.94Annesley (Kirkby) 11kv S Stn Onshore Wind 11 500 511

WP3 – Risk assessment calculation

Technology mapping (based on WPD data). All types of connections were mapped onto 5 main generating

technologiesBiomass & Energy Crops (not CHP) SMHydro IM

Landfill Gas Sewage Gas Biogas (not CHP) SM

Large CHP (>=50mw) SMMedium CHP (>5MW <50MW) SMMicro CHP (Domestic) SMMini CHP (<1MW) SMOffshore Wind PMSGOnshore Wind DFIGOther Generation SMPhotovoltaic PVSmall CHP (>1MW <5MW) SMWaste Incineration (not CHP) SM

WP3 – Risk assessment calculation

Technologies with cumulative contribution of 10% or less were removed from the mix.

The remaining generation was scaled up to the full capacity installed at the primary substation

WP3 – Risk assessment calculation

Establishing dominant groups.

WP3 – Risk assessment calculation

Establishing dominant groups.

Groups of primary substations with more than 5% of the total population were only considered for risk assessment analysis.

Group Substations PercentageSM 60 5.5PV 544 49.5DFIG 5 0.5IM 0 0.0PMSG 0 0.0SM, PV 283 25.8SM, DFIG 10 0.9SM, IM 1 0.1SM, PMSG 0 0.0PV, DFIG 139 12.7PV, IM 10 0.9PV, PMSG 1 0.1DFIG, IM 0 0.0DFIG, PMSG 0 0.0IM, PMSG 0 0.0SM, PV, DFIG 39 3.6SM, PV, IM 1 0.1SM, PV, PMSG 0 0.0SM, DFIG, IM 0 0.0SM, DFIG, PMSG 0 0.0SM, IM, PMSG 0 0.0PV, DFIG, IM 3 0.3PV. DFIG, PMSG 1 0.1PV, IM, PMSG 0 0.0DFIG, IM, PMSG 0 0.0SM, PV, DFIG, IM 1 0.1SM, PV, DFIG, PMSG 0 0.0SM, PV, IM, PMSG 0 0.0SM, DFIG, IM, PMSG 0 0.0PV, DFIG, IM, PMSG 0 0.0Total 1098 100.0

WP3 – Risk assessment calculation

Distribution of dominant groups.

Generation profile mixingExample: 33% SM (fixed PQ), 33% PV (solar), 33% DFIG (wind)

WP3 – Risk assessment calculation

0 20 40 60 80 100 120 140 160-2

-1

0

1

2

3

4

5

time [h]

P[M

W],Q

[MV

Ar]

PgenQgen

Methodology/assumptions Perform risk assessment based on the number of possible

islands rather (substations) than number of generators.

Represent each predominant island group with an equivalent NDZ. Five predominant have been identified. The largest population is formed by single generation PV for which ROCOF setting change will have no impact.

Profiles for predominant groups are synthesised using the available generation profiles.

In NDZ assessment and generation profile mixing it is assumed all technologies have equal contribution. Cumulative contributions of less than 10% are removed though. (discuss)

Risk assessment will be performed systematically based on group capacity distribution in substations.

WP3 – Risk assessment calculation

Data still desirable

Monitoring data 1s resolution data from example 11kV feeder or

substation in WPD with min load <5MW (pending) 1s or 5s resolution data (P, Q) of small PV unit output

in different seasons (summer, winter, mid-season) (pending – contact from Michael has not responded)

Number of primes in WPD?

WP3 – Risk assessment calculation

WP2 – Simulation based characterisation of DG

Most popular generation mixes have been considered.

Synchronous, PV-Inverter, PMSG-Inverter, DFIG and Asynchronous based generation were modelled.

WP2 – Simulation based characterisation of DG

Individual Connection Stability Studies

Synchronous Generator

Grid

33kV / 11kV

PCCSynchronous

Generator

ABC

E

F

D

Power Island

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Synchronous generator can be Ssable during LOM event

Assess Non Detection Zone forActive and Reactive Power.

Synchronous Generator

WP2 – Simulation based characterisation of DG

Non Detection Zone Assessment

Setting Option 10.13 Hz/s

, 0 Sec

Setting Option 20.2 Hz/s ,

0 Sec

Setting Option 31.0 Hz/s ,

0.5 Sec

NDZ-P [%] 1.3 1.4 9.44

NDZ-Q [%]

7.9 9.14 43

Synchronous Generator

WP2 – Simulation based characterisation of DG

Photovoltaic Panels

Grid

33kV / 11kV

PCCPV

ABC

E

F

D

Power Island

Individual Connection Stability Studies

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Photovoltaic Panels are unstableduring LOM event, even forcomplete Active and Reactivepower balance at PCC.

No NDZ

WP2 – Simulation based characterisation of DG

Induction Generator

Grid

33kV / 11kV

PCCInduction Generator

ABC

E

F

D

Power Island

Individual Connection Stability Studies

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Induction Generator createshigh ROCOF + frequency shiftsaccording to generator slip

No NDZ

WP2 – Simulation based characterisation of DG

DFIG

Individual Connection Stability Studies

Grid

33kV / 11kV

PCCDFIG

ABC

E

F

D

Power Island

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Model 1

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Model 2

WP2 – Simulation based characterisation of DG

Grid

33kV / 11kV

PCC DG

ABC

E

F

D

Power Island

SynchronousGenerator

InductionGenerator

Generation Mix Stability Studies

Synchronous Generator & Induction Generator

WP2 – Simulation based characterisation of DG

Total Power : 2 MVASG [%] IG [%]

90 10

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synchronous

Induction

WP2 – Simulation based characterisation of DG

Total Power : 2 MVASG [%] IG [%]

80 20

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synchronous

Induction

WP2 – Simulation based characterisation of DG

Total Power : 2 MVASG [%] IG [%]

70 30

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synchronous

Induction

WP2 – Simulation based characterisation of DG

Grid

33kV / 11kV

PCC DG

ABC

E

F

D

Power Island

SynchronousGenerator

Photovoltaic

Generation Mix Stability Studies

Synchronous Generator & Photovoltaic Panels

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synch…

PV

Total Power : 2 MVA

SG [%] PV [%]

95 5

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synch…

PV

Total Power : 2 MVA

SG [%] PV [%]

90 10

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synch…

PV

Total Power : 2 MVA

SG [%] PV [%]

80 20

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synch…

PVTotal Power : 2 MVA

SG [%] PV [%]

70 30

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synch…PVTotal Power : 2 MVA

SG [%] PV [%]

60 40

WP2 – Simulation based characterisation of DG

Active Power Imbalance: 0%Reactive Power Imbalance: 0%

Active Power Imbalance: 5%Reactive Power Imbalance: 0%

Active Power Imbalance: 0%Reactive Power Imbalance: 5%

Synch…PVTotal Power : 2 MVA

SG [%] PV [%]

50 50

WP2 – Simulation based characterisation of DG

WP2 – Simulation based characterisation of DG

ROCOF setting optionsLOM Option LOM Protection Type Settings

1 ROCOF 0.13 Hz/s (no time delay)

2 ROCOF 0.2 Hz/s (no time delay)

3 (prev. 5) ROCOF 0.5 Hz/s (0.5s delay)

4 (prev. 6) ROCOF 1.0 Hz/s (0.5s delay)

5 (prev. 7) V & f Only G59 Recommended

AmplifierReal Time Simulator

(RTDS)

LOMProtection

(Relay)

ExtractRecords

Configure IED

Control & MonitorSimulation

Tripping Signal

3-PhaseVoltages

3-PhaseVoltages

Due to large amounts of testing and limited access to RTDS facility it is proposed to performNDZ assessment usingan existing ROCOFrelay model (?).