Risk Based Asset Management in Capital Works Delivery

Vito Albicini

Former Director Infrastructure Services

Bill Sharpe

Manager Sustainable Asset Management

Yarra City Council

Page 2: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

A Common Story

Page 3: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

A Common Story• Redevelopment Project funded in 2010 for

$200,000 to accommodate New Tenant. Project was to be completed by February 2011

• 2012, Project on hold and not complete

• Project cost now $400,000 due to poor scoping and planning.

• Project target completion date June 2012

• Tenant not happy

• Common story for Councils?

• What do we do to stop this?

Page 4: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Key Messages• Poor Project Planning results in poor project

delivery and unsatisfied customers.

• Project risks need to be understood and managed.

• Sound Capital Works Planning considers the ;– Capacity to deliver projects, – Life cycle cost of the project, – Environmental and social benefits – Quality and cost– Amount of stakeholder involvement, and – Councillor and Community expectations.

• Project Implementation Plans are a tool to support good planning and delivery of projects.

• Project Monitoring is also needed to ensure risks are managed and projects are delivered.

Page 5: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Failure to appropriately manage and control capital works leads to uncontrolled and inappropriate expenditure resulting in financial and reputational loss.

Corporate Risk

Page 6: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• Poor planning with limited renewal and replacement expenditure

• Conflict with the long term financial plan• Poor prioritisation of works in Capital Works

Program• Political influence on the priority of discretionary

works• Poor project scope, understanding of project

budget and project programming• Lack of understanding financial burden to Council –

Life Cycle Costing• Not understanding environmental, social and

compliance (Town Planning) implications

What are Project Planning Risks?

Page 7: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• Insufficient Project Management Skills across Organisation

• Poor project management principles, processes and systems to manage projects

• Lack of clarity of roles, responsibility and governance structure to deliver projects – Project Manager / Project Sponsor

• Lack of appropriate consultation with stakeholders• No centralised electronic capital works

programming, recording and tracking system

What are Project Delivery Risks?

Page 8: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• Asset Management Policy 2011• Capital Works Planning

– Forecaster electronic capital works programming and management system

– 30 Year Projected Capital Expenditure reporting process

– Project Implementation Plans

• Capital Works Monitoring – CAPMON, Executive CAPMON & PCG

• Sustainable Infrastructure Network (SIN)• Project Management Principals and monitoring

systems• Responsibilities clear between PM and PS• Staff professional and experienced

Risk Control Measures

Page 9: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Capital Works Planning

Page 10: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• The Council Plan, the long term financial plan (LTFP) and the relevant Asset Management Plan (AMP) are the core considerations for proposing capital programs;

• Projects are sorted into renewals, upgrades, new or compliance projects, initial priority ranking is provided by the Project Sponsor;

• Projects submitted for consideration shall be given a priority if they are derived from a Strategic Plan, AMP, Master Plan, UDF (and the like) or from a specific Council or Executive resolution;

 

• Projects to be submitted after integrated discussions across asset classes has occurred to encourage optimum use of resources, outputs and Project Implementation Plans developed ;

Capital Works Planning Parameters

Page 11: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• Projects over $250k will be planned to be delivered over a three year period. The typical delivery model will be:-– Year 1 -Concept planning, consultation & sign off of

project brief;– Year 2 - Detailed design and obtaining permits;– Year 3+ - Construction and defects liability

monitoring.

• Discussions and sign off between the Project Sponsor, (Service Manager), and Project Manager is required in the development of all projects. For renewal projects Asset Manager and Service Manager require sign off. For new and upgrade projects Service Manager requires sign off from Asset Manager and Project Manager; and

• Projects without some level of mature planning will not progress. For example projects that are poorly scoped,

or lack consultation will not be supported

Capital Works Planning Parameters

Page 12: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

SUSTAINABILITY

COUNCIL

COMMUNITY

FINANCIAL PLAN

LEGISLATION

RESOURCES

ASSET STRATEGY ASSET POLICY

COUNCIL PLAN

Non Discretional Capital Works(essentially the renewal of existing assets)

Discretional Capital Works (essentially the acquisition of new assets)

SeptemberCall for List of Projects to be reviewed

and submittedBids

submitted to Capital Works

Planner by end

November

List of projects is entered into BIDDER in priority order by Service Managers

Draft list of projects considered by Council at Councillor workshop in

early December

Draft Capital Works Program considered by SIN and Executive

Second Draft Capital Works Program considered by SIN & Executive

Council Approve Final Draft Capital Works Program as part of budget

process in March

Executive make changes if required to address Council

Plan goals and objectives

Compliance / Risk Projects

Information Systems, Fleet & Plant & Equipment:- policy & replacement programs, draft AMP

Prioritised Lists for each Asset Component is prepared and entered into Forecaster

First Draft Capital Works Program Compiled by Capital Works Planning

Early November

Second Draft Capital Works Program Completed in February and presented

to 2nd Councillor workshop

Consider Carry Over Projects(essentially projects in the current capital works program that will be

completed next financial year)

CAPMONApproves list of projects

and any carry over amounts (if any)

Capital Works Program

advertised for Public Comment

during April

Road , Open Space, BuildingsAsset Management Plans

Finance Branch provides $ value for Capital Works Program based on long

term financial plan

Consider Carry Over Projects(essentially projects in the current capital works program that will be

completed next financial year)

CAPMONApproves list of projects

and any carry over amounts (if any)

Project implementation Plans are prepared by Service Managers and

Agreed to by Project Managers Received and Reviewed by Capital

Works Planning

Call for Councillors to provide list of

Priority projects

Final Draft Capital Works Program considered by SIN & Executive

Executive make changes if required to address Council

Plan goals and objectives

Executive make changes if required to address Council

Plan goals and objectives

Council Adopts Capital Works Program as part of budget process in

June

Project implementation Plans are further refined by Service Managers and Agreed to by Project Managers Received and Reviewed by Capital

Works Planning

Page 13: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• PRE PLANNING Distribution of Adopted 10 Capital Works Program for review by Project Sponsors and Project Managers. (AUG)

• STEP 1: INITIATION MEETING (Sept)

• STEP 2: PREPARING PRIORITY LISTS FOR A PROGRAM (Sept – Mid Oct.)

Assets Managers - Renewals

Service Managers - Upgrades and New Works

• STEP 3: DEVELOP DRAFT CAPITAL WORKS PROGRAM (Late Oct)

Capital Works Planner

• STEP 4: REVIEW OF DRAFT CAPITAL WORKS PROGRAM (Nov)

SIN and Executive Team

Capital Works Planning

Page 14: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• STEP 5: DECEMBER WORKSHOP WITH COUNCILLORS:

Seek Council input in reviewing 5 year Capital Works and proposed New / Upgrade projects for Year 1

• STEP 6: COMPLETION OF PROJECT IMPLEMENTATION PLANS FOR DISCRETIONARY UPGRADES AND NEW PROJECTS SELECTED BY COUNCIL. (Dec – Jan)

Service Managers and Project Managers

• STEP 7: SECOND REVIEW OF DRAFT CAPITAL WORKS PROGRAM (Feb)

Capital Works Planner and presented to SIN and Executive

• STEP 8: COUNCIL BRIEFING ON BUDGET (mid Feb.) – REFINEMENT OF YEAR 1 BUDGET AND WORKS

• STEP 9: ADOPTION OF DRAFT CAPITAL WORKS PROGRAM (March – April)

• STEP 10: FINALISATION OF THE CAPITAL WORKS PROGRAM (June)

Capital Works Planning

Page 15: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Step 6COMPLETION OF PROJECT IMPLEMENTATION PLANS FOR DISCRETIONARY UPGRADES

AND NEW PROJECTS. (Dec – Jan)

Page 16: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Project Implementation Plans

– Roles and Responsibilities, establish Project Working Team and Project Control Group

– Project Brief / Scope– Project Objectives / Outcomes– Project Assumptions– Environmental Issues to be considered– Social Implications to be considered– Project Risks– Project Constraints– Details of Other Income Sources– Detail of Planning / Approval Requirements

(Permits/Required Approvals) – Community Engagement (Consultation) Process

Page 17: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Project Implementation Plans

– Key Stakeholders– What ESD measures / Sustainability Initiatives are

included in this project– Social Benefit Initiatives – Related Projects/Integration of Other Projects– Major Tasks – Responsibility, Timing & Costs– Life Cycle Cost / NPV / Annual Average Service Cost /

Operational Costs – (New / Upgrades)– Implementation Plan (How will project be delivered e.g.

traditional, single contract, fast track, design & construct etc.)

– Procurement Plan (What types of contracts packages are proposed?)

– Project Control (How the project will be monitored and managed?)

Page 18: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 19: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 20: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 21: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 22: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 23: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 24: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 25: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 26: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 27: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 28: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 29: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 30: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 31: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 32: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 33: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 34: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Capital Works Planning

Key Benefits:• Asset Renewal funding meets 20 year Asset Management

Plans• Legal / Compliance needs identified and funded

(eliminating Council risks)• Upgrades and New funding determined by Council to support

priority service needs• Councillors able to understand the cost to Council to

fund all New / Upgrade desires listed in current Master Plans and Strategies

• Organisation and Councillors have a better understanding of Councils financial sustainability with a 20 – 30 years list of works

• Improved alignment with the Community and Council Plan• Improved pre-planning for Capital Works Implementation• Allocates resources to the highest priority• Better Governance as decisions based on facts.

Page 35: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Capital Works Monitoring- CAPMON- Exec CAPMON- Exec PCG

Page 36: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

• Chaired by Manager Sustainable Asset Management Monthly reporting meeting with Project Managers to monitor progress of delivering all projects, renewals, upgrades or new.

• Identify delivery risks and ensure control measures are in place

• Guidance given to Project Managers and staff to assist with the delivery the projects

• Project Managers are able to request changes to project priority and to seek direction on possible carryovers or deferrals.

CAPMON

Page 37: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 38: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 39: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 40: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Exec CAPMON / Exec PCG

• Monthly reporting meeting with Executive to monitor progress of delivering due to significant number of politically sensitive / major projects that require Executive input or Executive Decisions

• Minimises the need for Executives to attend all PCG meetings for individual projects

• Maximise use of time of the Executive• Empowers Project Managers and staff to deliver the

projects• Project Managers are required to report to Cap Mon

Exec / Exec PCG.• Meeting split in two stages

– Cap Mon Exec reviews the whole of the Capital Program– Exec PCG reviews major projects

Page 41: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 42: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 43: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Capital Works monitoring – Exec PCG

Page 44: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 45: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 46: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Capital Works Monitoring

KEY BENEFITS:• 90% of Capital Program Delivered

(previous average 83%)

• Executive are briefed on status of Capital Works Program

• Decision can be made to remove blockages

• Risks are managed

• Good Governance

Page 47: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Does it all work ?

Page 48: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Collingwood Leisure Centre – another Example

Page 49: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Collingwood Leisure Centre

Preplanning completed prior to provision of budget – Good Business Case

Project Implementation Plan in place Good Governance structure in place that included

Service Manager Skilled internal Project Manager Good Specifications Good Architect, Consultants and Builder Good Project Management Systems in place to Manage

Time Cost Quality Relationships well managed Good Capital Works Reporting Tool Regular reporting to PWT, Exec PCG and Council

The Result????

Page 50: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Collingwood Leisure CentreSuccessfully Delivered

Page 51: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Collingwood Leisure Centre

RESULT: Delivered under budget - $7.8 Million Delivered by Christmas as required – 16

December 2011 ESD elements included Quality achieved Happy Service Managers Happy Stakeholders Happy Councillors

Happy Community

Page 52: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management
Page 53: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

In Summary

• Poor project planning results in poor project delivery

• Understand and manage Project Risks

• Consider capacity to deliver projects, life cycle costs, environmental and social benefits.

• Allow Planning time. Time for, cost, quality , governance and stakeholder management.

• Use of Project Implementation Plans a must.

• Monitor performance to ensure projects are delivered.

Page 54: Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management

Risk Based Asset Management in Capital Works Delivery

Questions…….