Upload
sandra-apps
View
218
Download
1
Tags:
Embed Size (px)
Citation preview
risk management and assessment for business
Advances in Process Control 920 September 2011, York, United Kingdom
Advances in Process Control 9 Jasjeet Singh
APC 9
Are Blowout Preventers and Fire & Gas Systems ready to be classified as Safety Instrumented Systems on offshore installations?
Presented By:
Jasjeet Singh MCMI, AMIChemE, MBA, BE (Chemical)
Senior Engineer, Risktec Solutions Limited
Advances in Process Control 9 Jasjeet Singh
APC 9Objectives
Introduce briefly to Blowout Preventer (BOP), and Fire and Gas Systems (FGS) in offshore oil & gas installation context;
Simplistically evaluate the Safety Integrity Level (SIL) these systems would be expected to achieve; and,
Discuss if these systems should be designated as Safety Instrumented Systems (SIS);
Discuss “challenges” in upgrading BOP and FGS to SIS status.
Advances in Process Control 9 Jasjeet Singh
APC 9Functional Safety Definition
What is Functional Safety?
The industry standard IEC 61511 defines it as “Functional safety is part of the overall safety that depends on a system or equipment operating correctly in response to its inputs.”
Example:
An over-temperature protection device, using a thermal sensor in the windings of an electric motor to de-energise the motor before they can overheat, is an instance of functional safety.
Specialised insulation to withstand high temperatures is not an instance of functional safety (although it is still an instance of safety and could protect against exactly the same hazard).
Advances in Process Control 9 Jasjeet Singh
APC 9Basic SIS Configuration
Detect
Decide
Execute
Sensor Elements Pressure Temperature Flowrate Composition
Logic Control Safety PLC Relay Logic
Final Elements Valve Assemblies Circuit Breakers Power Drives Secondary Systems
Advances in Process Control 9 Jasjeet Singh
APC 9Systems under the Scanner
Blow Out Preventer Fire and Gas System
Advances in Process Control 9 Jasjeet Singh
APC 9Blow Out Preventer
A Blow Out Preventer (BOP) is a combination of several valves installed at the wellhead.
Function: Prevention of escape of well fluids from primary containment
BOP Typical Location: Beneath the rig for land rigs; At the water’s surface on jack-up rigs; On the seafloor for floating offshore rigs.
What is a Blow Out Preventer?
Advances in Process Control 9 Jasjeet Singh
APC 9What a BOP Looks Like…
Advances in Process Control 9 Jasjeet Singh
APC 9Simplistic LOPA on a BOP System
ScenarioUnexpected release of high pressure gas in the reservoir into the well causing abnormal and sudden increase in riser pressure. Potential for release of high pressure oil / gas jet at the platform from the well (Blow-Out).
Consequences Multiple fatalities from fire & explosion on the installation; MATTE
Target Frequency Factor 6 (equivalent to 10-6 per year)
Initiating Event Unexpected well pressure due to accumulated gas
Initiating Event Frequency Factor 3 (equivalent to 1 in 1000 well sites)
Conditional Modifiers Ignition Control – 0 (No credit)
Exposure – 0 (No credit)
Advances in Process Control 9 Jasjeet Singh
APC 9Simplistic LOPA on a BOP System
Independent Protection Layers Risk Reduction Factor
BPCS Indication of pressure in the control room and process shut down 1
Alarms Linked to the BPCS system – Not Independent 0
Mitigated Event Factor (6) – (3) – (1) 2
Required SIL for chosen SIF 2
Hence the “BOP System” may be required to meet SIL 2 requirements.
Advances in Process Control 9 Jasjeet Singh
APC 9BOP Control System
Primary Functions: To ensure that sufficient hydraulic pressure is conveyed to the BOP assembly when a
demand is placed; Ensure that the sequence of valve activation is executed as per design;
Elements: Pressure measurement devices (an array of pressure transmitters / switches at
different strategic locations) Logic Control (Sub sea modules and on Topsides) Final Elements (The BOP assembly - Actuators & Valves) Support Elements (Hydraulic Power Unit)
Advances in Process Control 9 Jasjeet Singh
APC 9Typical BOP System
Advances in Process Control 9 Jasjeet Singh
APC 9Challenges in upgrading BOP to SIS Status
Technical Challenges: Complex System – An array of devices including multiple sensors Manufacturing high integrity equipment for subsea environment
Operation and Maintenance Challenges: Proof Testing as per requirements of the Standard
• “End to End” tests in operation are not feasible - Destructive nature of final elements
• Maintenance of equipment under harsh & corrosive environment
Compliance / Standards related Challenges: Human in the loop – limited reliability issues Same Equipment – Different Requirements
LOOP, LOOP AND THE WHOLE LOOP, NOTHING BUT THE LOOP
Advances in Process Control 9 Jasjeet Singh
APC 9
PHAS
E 11
– S
afet
y Li
fe C
ycle
Str
uctu
re a
nd P
lann
ing
(IEC
6151
1-1
Clau
se 6
.2)
PHASE 1
Hazard and Risk Assessment
PHASE 2
Allocation of Safety Functions to Protection Layers
PHASE 3
SIS Safety Requirements Specifications
PHASE 4
SIS Design & Engineering
PHASE 5
SIS Installation, Commissioning & Validation
PHASE 6
SIS Operation & Maintenance
PHASE 7
SIS Modification
PHASE 8
SIS Decommissioning
IEC 61511-1 Clause 8
IEC 61511-1 Clause 9
IEC 61511-1 Clause 10, 12
IEC 61511-1 Clause 11, 12
IEC 61511-1 Clause 14, 15
IEC 61511-1 Clause 16
IEC 61511-1 Clause 17
IEC 61511-1 Clause 18PHAS
E 10
– S
IS F
uncti
onal
Saf
ety
Asse
ssm
ent (
IEC
6151
1-1
Clau
se 5
)
PHAS
E 9
– SI
S Ve
rifica
tion
(IEC
6151
1-1
Clau
se 7
, 12.
4 an
d 12
.7)
STAGE 1: Analysis Stage
STAGE 2: Realization Stage STAGE 4: Management and Planning Stage
STAGE 3: Operations and Maintenance Stage
SIS Safety Life Cycle –Where will a BOP cause issues
?
?
?
?
Advances in Process Control 9 Jasjeet Singh
APC 9Regulator’s Position
United Kingdom
HSE Offshore Division’s Guide GASCET (April 2006) includes BOP as one of the devices for which a functional safety assessment is recommended using:
UKOOA Guidelines for Instrument Based Protective Systems
IEC 61508
IEC 61511
Norway United States
Australia Middle East -
South Asia -
?
?
?
Advances in Process Control 9 Jasjeet Singh
APC 9Fire and Gas System
Fire and Gas ‘Detection’ SystemsThree principal types of detectors commonly in use on off-shore installations:
Heat, Flame & Smoke Flammable Gas Toxic Gas
Fire and Gas System – ‘Final Elements’ HVAC System Emergency Shut Down Sequence Initiation Shut Off / Isolation Valves Blowdown and Depressurisation System
Advances in Process Control 9 Jasjeet Singh
APC 9Simplistic LOPA on a FGS
Scenario Release of flammable gas. Potential for jet fire / VCE.
Consequences Multiple fatalities from fire & explosion on the installation
Target Frequency Factor 6 (equivalent to 10-6 per year)
Initiating Event 10” gas pipeline failure due to vessel impact
Initiating Event Frequency Factor 3
Conditional Modifiers Ignition Control – 0 (No credit)
Exposure – 0 (No credit)
Advances in Process Control 9 Jasjeet Singh
APC 9Simplistic LOPA on a FGS
Independent Protection Layers Risk Reduction Factor
BPCS Process shut down. Isolation of pipeline from nearest isolation valves. 1
Alarms Non - Independent Alarms 0
SRPS Temporary refuges & escape crafts 1
Mitigated Event Factor (6) – (3) – (1) 1
Required SIL for chosen SIF 1
Hence the “FGS” may be required meet SIL 1 requirements.
Advances in Process Control 9 Jasjeet Singh
APC 9Challenges in upgrading FGS to SIS Status
Technical Challenges: FSG is also a complex system and is linked with the Emergency Shutdown System FSG is a combination of a number of loops – multiple SIFs with different SIL requirements
Operation and Maintenance Challenges: A large amount of kit to be maintained
Compliance / Standards related Challenges: Usual suspects
LOOP, LOOP AND THE WHOLE LOOP, NOTHING BUT THE LOOP
Advances in Process Control 9 Jasjeet Singh
APC 9BOP and FGS as SIS – The Two Sides
Against ForField devices and technologies are fundamentally different …
But the devices are available, and are being developed…
Not be considered performing a critical safety function…
They do. ESD is only part of the overall safety & risk control…
IEC 61508 is not applicable… Covers all E/E/PE systems...
Too costly… Not more than cost of an accident…
Difficult to materialise … Effort should be made – necessity is mother of invention…
Regulator does not want this… Post DwH, they do…mostly…
Industry has been operating this way – Why now? Continuous improvement …
Advances in Process Control 9 Jasjeet Singh
APC 9Recommendations
Oil and gas industry should explore the possibility of upgrading the BOP and FGS to SIS.
IEC, Industry and Regulators should red-define / amend the relevant requirements to clarify the issue.
Design engineers and safety consultants should be aware of the issue and endeavour to improve the safety system .
Advances in Process Control 9 Jasjeet Singh
APC 9Closing Remarks
Not all safety systems are created equal and every installation has different performance, risks and financial goals to meet.
Small regional operators are much less likely to make this step change in the way the BOP and the FGS are managed due to limited resources. It is up to global organisations to take this initiative, and raise standard of best practice in managing these systems.
Advances in Process Control 9 Jasjeet Singh
APC 9
Thank You for Your Attention