55
HAL Id: hal-02061788 https://hal.archives-ouvertes.fr/hal-02061788 Submitted on 22 Oct 2021 HAL is a multi-disciplinary open access archive for the deposit and dissemination of sci- entific research documents, whether they are pub- lished or not. The documents may come from teaching and research institutions in France or abroad, or from public or private research centers. L’archive ouverte pluridisciplinaire HAL, est destinée au dépôt et à la diffusion de documents scientifiques de niveau recherche, publiés ou non, émanant des établissements d’enseignement et de recherche français ou étrangers, des laboratoires publics ou privés. Distributed under a Creative Commons Attribution - NonCommercial| 4.0 International License Risk management and policy implications for concentrating solar power technology investments in Tunisia Damien Bazin, Nouri Chtourou, Amna Omri To cite this version: Damien Bazin, Nouri Chtourou, Amna Omri. Risk management and policy implications for con- centrating solar power technology investments in Tunisia. Journal of Environmental Management, Elsevier, 2019, 237, pp.504-518. hal-02061788

Risk management and policy implications for concentrating

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Risk management and policy implications for concentrating

HAL Id: hal-02061788https://hal.archives-ouvertes.fr/hal-02061788

Submitted on 22 Oct 2021

HAL is a multi-disciplinary open accessarchive for the deposit and dissemination of sci-entific research documents, whether they are pub-lished or not. The documents may come fromteaching and research institutions in France orabroad, or from public or private research centers.

L’archive ouverte pluridisciplinaire HAL, estdestinée au dépôt et à la diffusion de documentsscientifiques de niveau recherche, publiés ou non,émanant des établissements d’enseignement et derecherche français ou étrangers, des laboratoirespublics ou privés.

Distributed under a Creative Commons Attribution - NonCommercial| 4.0 InternationalLicense

Risk management and policy implications forconcentrating solar power technology investments in

TunisiaDamien Bazin, Nouri Chtourou, Amna Omri

To cite this version:Damien Bazin, Nouri Chtourou, Amna Omri. Risk management and policy implications for con-centrating solar power technology investments in Tunisia. Journal of Environmental Management,Elsevier, 2019, 237, pp.504-518. �hal-02061788�

Page 2: Risk management and policy implications for concentrating

1

Title

Risk management and policy implications for concentrating solar power technology

investments in Tunisia

Authors’ names and affiliations

Emna Omria,b,*, Nouri Chtouroua, Damien Bazinb

a University of Sfax, Faculty of economics and management of Sfax, LED, Airport road, Km

4, 3018 Sfax, Tunisia

b Côte d’Azur University, CNRS, GREDEG, France

* Corresponding author

E-mail address: [email protected]

Tel.: + 216 50 768 421

© 2019 published by Elsevier. This manuscript is made available under the CC BY NC user licensehttps://creativecommons.org/licenses/by-nc/4.0/

Version of Record: https://www.sciencedirect.com/science/article/pii/S0301479719302002Manuscript_9acb6cabe9709326a997e63db4a6381b

Page 3: Risk management and policy implications for concentrating

2

Abstract

Concentrating solar power (CSP) is a promising technology in Tunisia. However, its diffusion

is facing many barriers which deter investments. Through the analysis of a CSP plant in

Southern Tunisia by using the Global Risk Analysis (GRA) method, we try to analyze the

main risks faced by investors. The main objective of this research is to identify and analyze

the risks faced by CSP investors in Tunisia and develop strategies that should be adopted to

accelerate the process of diffusion of this technology.

This analysis allows us to conclude that the CSP project is very exposed to political, financial,

physical-chemical, legal, and strategic hazards. Moreover, we show that among the four

phases of the project, the preparation phase is the most vulnerable to hazards.

In fact, the GRA method makes it possible to determine the list of the major risks, such as the

risk of not obtaining permission to build a CSP plant, the risk of non compliance with the

deadline, the risk of failure to achieve the expected performance, the risk of insufficient

access to capital, and the risk of conflicts with local residents.

In order to de-risk CSP technology in Tunisia, we propose some strategies, such as

strengthening the public-private partnerships, using participatory approaches, creating local

employment, etc.

Keywords

Concentrating solar power; Investment risks, Global Risk Analysis; Tunisia

Page 4: Risk management and policy implications for concentrating

3

1. Introduction

While the benefits and advantages of energy for economic development are multiple and well

known, it is rather the damages related to our energy-intensive societies that deserve the

greatest attention. According to a recent report prepared by the Renewable Energy Policy

Network for the 21st Century (REN21, 2018), the total final energy consumption was

dominated by fossil fuels (oil, natural gas, and coal) by about 79.5%, in 2016. Therefore,

energy demand is mainly covered by the use of fossil fuels which are the main sources of

greenhouse gas (GHG) emissions.

In fact, the increase of GHG concentrations in the atmosphere is the main cause of climate

change. As a result, the prevention of the catastrophic consequences of the climate change

requires the stabilization of the atmospheric concentration of these GHG and especially the

carbon dioxide (IPCC, 2007). In this case, the challenge for all countries is to implement a

transition to a safer and less carbon emitting energy system without hampering economic and

social development (IEA, 2007). The transition to renewable energies (RE) is the evident

solution to satisfy the increasing demand while respecting the environment and ensuring a

green economic growth (Omri et al., 2015a).

Moreover, many recent reports have indicated that transition towards RE has already started

as a result of the increase of the installed capacity and cost competitiveness of wind power

and solar PV (IRENA, 2018; REN21, 2018). In fact, the year 2017 presented a new record-

breaking for the RE sector since it is marked by an impressive decrease of the costs, the

expansion of investments, and the development of the installed capacities (REN21, 2018).

Solar energy is one of the most promising RE due to its competitive costs and its abundance

in many countries (Astolfi et al., 2017; Sindhu et al., 2016). The two main solar technologies

are the concentrating solar power technology (CSP) and the solar photovoltaic technology

(PV) (Mekhilef et al., 2011).

The comparison of the corresponding costs of the different RE options is often based on the

use of levelized cost of electricity (LCOE). This comparison leads to the fact that PV is more

competitive than CSP (IEA, 2014; Pietzcker et al., 2014).

Joskow (2011) criticized the use of LCOE because it undervalues dispatchable power plants

compared to the intermittent electricity generating technologies. In fact, while PV is an

intermittent generating technology, CSP plants can generate dispatchable power when they

are equipped with thermal storage systems. In this case, it is possible to store heat energy

Page 5: Risk management and policy implications for concentrating

4

obtained during the day in order to be transformed into electricity at night, which facilitates its

integration into the existent electricity grid (Brand et al., 2012; Trieb et al., 2014).

In fact, CSP technology with a thermal storage represents one of the few renewable

technologies that can offer dispatchable electricity (IEA, 2010; Lilliestam et al., 2018).The

assessment of the benefits and of the economic advantages of the CSP dipatchability was

detailed in many studies, such as that of Poullikkas et al. (2010).

Although dispatchability is a very important asset for CSP technology, the grid stability

aspect regarding the increasing penetration of RE should be treated seriously. In fact, the

increase of the proportion of RE in the electricity mix can face many operational challenges,

such as the voltage stability of the grid and the load balancing. Hence, it is necessary to ensure

the flexibility of the grid and the development of the necessary transmission infrastructure.

Unlike CSP, solar PV is an intermittent technology which, in order to become dispatchable,

needs a separate storage system like batteries. Nowadays CSP with a thermal storage is less

expensive and more competitive than PV with batteries. However, the maintaining of this

advantage in the future is not certain and depends a lot on the future evolution of the costs of

PV cells and batteries (Lilliestam et al., 2018).

Therefore, it is clear that CSP technology with a thermal storage has many advantages

compared to the solar PV and wind power. However, the reality shows that solar PV and wind

power are winning the battle and there is a risk that CSP technology will remain in its small

niche if the support from policymakers remains insufficient (Lilliestam et al., 2018). In fact,

in 2017, the cumulative PV capacity reached 402 Giga watt (GW) compared to just 4.9 GW

for CSP (REN21, 2018).

Hence, despite the advantages of CSP technology, the achievements are modest. This fact

proves that the widespread diffusion of CSP technology is facing several obstacles (del Rio et

al., 2018; Haas et al., 2018) and requires an adequate support policy to take off (Lilliestam et

al., 2018).

In fact, the Middle East and North Africa (MENA) region is one of the most favorable regions

for large-scale solar energy deployment. Moreover, the high direct normal irradiation (DNI)

in North Africa can make this region a major exporter of the electricity produced by CSP

plants in the desert and then transmitted to Europe (IEA, 2010). For these reasons, the

feasibility and financing aspects of the export of electricity produced by CSP technology in

North Africa have attracted the attention of several researchers, such as Kost et al. (2011),

Page 6: Risk management and policy implications for concentrating

5

Trieb et al. (2012, 2011), Viebahn et al. (2011), Williges et al. (2010), etc. Moreover, the

advantage of the thermal storage can make the electricity produced by CSP plants an

important component of the future electricity mix. Therefore, the African deserts will be a

source of baseload and dispatchable power (Pfenninger et al., 2014; Trieb et al., 2014).

For these reasons, there are many studies that focus on CSP technology in the MENA region,

especially the barriers and risks hindering its large scale development (Komendantova et al.,

2012; Lilliestam et al., 2012). Morocco has attracted the attention of many researchers.

However, to our best knowledge, there has not been yet any study that deals with barriers and

risks of investing in CSP technology in Tunisia.

In fact, Tunisia enjoys a great potential of solar resources and many suitable factors for large

scale deployment of CSP technology (Balghouthi et al., 2016). However, there are no

achievements that are in harmony with the enormous solar potential of this country. In 2017,

the cumulative installed capacity of solar PV accounted for about 47.1 Megawatt electric

(MWe) and there has not been yet any large-scale operational CSP plant in Tunisia (IRENA

Resource, 2018). Nevertheless, there are many planned plants, such as a parabolic trough

plant of 50 MW and another one of 2,500 MW using a power tower technology. Although

these projects were planned many years ago, the construction has not begun yet.

Furthermore, despite the advantages that can be offered by the use of CSP technology in

Tunisia, achievements in this field are inexistent. This fact leads us to set the following

questions: what are the most challenging barriers that hinder CSP investments in Tunisia? In

other words, what are the risks of investing in CSP technology in Tunisia? And what are the

effective policy measures to mitigate these risks?

To answer these questions, we used a risk management approach and particularly a Global

Risk Analysis (GRA) method in order to assess the risks concerning the case of a CSP plant

that will take place in the South of Tunisia.

As a consequence, our study is structured as follows. The theoretical background is presented

in section 2. Section 3 is devoted to the current status of CSP technology. The Barriers facing

the CSP expansion are detailed in section 4. Then, section 5 describes the case study of the

CSP plant, introduces the GRA method that will be applied, and explains all the steps required

for the application of this method. The results are described in section 6 along with a related

discussion and suggestions in terms of policy implications. Finally, the concluding remarks

are provided in section 7.

Page 7: Risk management and policy implications for concentrating

6

2. Theoretical background

Climate change is a serious threat to the well-being of future generations and economic

growth. To deal with this threat, it is necessary to reduce GHG emissions by using adaptation

and mitigation measures in order to move to a low carbon economy (IPCC, 2007). However,

the current energy system appears to be highly dependent on fossil fuels and the process of

transition to RE is relatively slow mainly in the heating, cooling, and transport sectors

(REN21, 2018).

This section will focus on the transition to RE, the barriers facing this process, particularly the

“carbon lock-in” effect, and finally the importance of RE policy in eliminating these barriers.

2.1. The transition to RE

RE satisfy the same needs as conventional energies. Indeed, they can be used to generate

electricity; in this case they can supply electricity to farms, homes and buildings. RE can also

be used for heating, cooling, and transport (REN21, 2018). Besides, RE can offer rural areas

the opportunity of access to clean and decentralized energy sources (OECD, 2012).

In recent years, the transition to RE has been motivated by two main reasons. The first one is

linked to the growing concern with sustainable development (Elum and Momodu, 2017;

González et al., 2017; Omri et al., 2015b). The second reason concerns the great attention

given to the concepts of “green recovery” and “green growth” since the economic crisis of

2008 (Omri et al., 2015a).

The reduction of GHG (Goh and Ang, 2018) and the creation of green jobs (Fragkos and

Paroussos, 2018) are among the most known advantages of the transition to RE. Although the

benefits of RE use are well known and efforts for large-scale exploitation are provided in

many countries, fossil fuels still dominate (REN21, 2018). In fact, theoretical arguments and

empirical research studies indicated that the current energy system is locked-in a complex

context of high-carbon technologies and infrastructures (Arentsen, et al., 2002; Davis et al.,

2010; IEA, 2011; Rip and Kemp, 1998; Schmidt and Marschinski, 2009).

Moreover, despite the awareness of the damage caused by the use of fossil fuels, the

industrialized economies are in a locked-in position in favor of fossil fuels (Unruh, 2000) and

attempts to turn to RE are facing many barriers (Painuly, 2001). In fact, the main barrier to the

rapid diffusion of RE is the carbon lock-in effect which creates a market and policies that can

slow down or even block the spread of RE technologies, even though they have many

Page 8: Risk management and policy implications for concentrating

7

environmental and economic benefits (Unruh, 2002; 2000). This concept will be explained in

the following sub-section.

2.2.The carbon lock-in effect

The technological lock-in effect has been increasingly explained by many researchers since

the mid-1980s (Arthur, 1989; Cowan, 1990; David, 1985; Liebowitz and Margolis, 1995;

Perkins, 2003). The explanations given for the existence of the technological lock-in effect

are: the existence of technological paradigms and the increasing returns to adoption.

The first explanation of the technological lock-in effect is the fact that the features and the

orientation of technological progress are strongly influenced by the cognitive framework of

the actors in the technological community. Nelson and Winter (1977) used the term

“technological regime” to characterize these frameworks, while Dosi (1982) used the term

“technological paradigm”. Although the terms used are different, their senses are quite

similar.

According to Perkins (2003), the consequence of the existence of these mental frameworks

called technological paradigms or technological regimes is that the efforts made to bring

forward the efficiency of technology often focus on specific and well-defined directions

which are based on past accomplishments, common beliefs and state of knowing of the

technological community. This situation can create powerful exclusionary effects on

innovative technological possibilities and solutions outside the “dominant technological

paradigm”. This “exclusion effect” was explained by Dosi (1982).

The second explanation given to the technological lock-in effect, which is strongly linked to

the first one, is the presence of increasing returns to adoption which represent a positive

feedback process and make an adopted technology more attractive than a new one. This idea

was well explained by Arthur (1989) and David (1985) who believe that in a situation where

many technologies are competing, the existence of increasing returns implies that the

technology that has benefited from initial adoption advancement may eventually be more

performing. There are generally four classes of increasing adoption returns that are involved

in the technological lock-in effect. These four classes are: economies of scale, learning

economies, adaptive expectations, and network economies (Arthur, 1994).

Recently, the technological lock-in concept has interested many researchers who are involved

in the fields of technological change and the environment. These researchers highlighted the

negative effects of the use of fossil fuels on climate change and the barriers facing

Page 9: Risk management and policy implications for concentrating

8

industrialized economies in moving to a low-carbon energy system. This problem is caused

by the carbon lock-in effect (Kemp, 1994; Mattauch et al., 2015; Rip and Kemp, 1998; Unruh,

2000).

Indeed, since the 1990s, a growing interest has been given to the effect of carbon lock-in,

which is considered as an obstacle to the transition to low-carbon technologies (Ayres 1991;

Freeman and Soete 1997; Kemp 1994; Unruh 2000). Mattauch et al. (2015) confirmed that the

major obstacle to the transition to a low-carbon economy is the carbon lock-in effect. They

considered that fossil fuels dominate the market although their alternatives, mainly RE, are

dynamically more efficient.

On the other hand, Pinkse and Buuse (2012) considered that past investments in fossil fuels

can influence the perception of decision-makers in oil companies about the risk-return couple,

bringing them to see more opportunities in their previous trajectory than in the less familiar

RE trajectory.

It should be emphasized that the carbon lock-in situation is not a permanent situation but

rather a persistent state that creates barriers to fossil fuel alternatives (Unruh, 2000). Indeed,

this effect is manifested in reality by a situation in which investments in RE projects face

several barriers of different types (economic, institutional, financial, social, etc.) which

represent significant risks for investors. In the next sub-section, we will focus on the necessity

of RE policy to eliminate these barriers and to accelerate RE development.

2.3.The role of RE policy

Policy makers either in the developed or developing countries are promoting RE technologies

by implementing specific policies which include fiscal incentives, targets, public support, and

new regulations. By the end of 2017, 179 countries had set RE goals (REN21, 2018).

The main barrier to RE diffusion is its high cost compared to conventional sources (Mezher et

al., 2012). Therefore, the expansion of the RE sector requires government support either

through fiscal incentives, targets, public financial support, and regulations to encourage

investment in this sector (REN21, 2018), or through other instruments, such as the elimination

of perverse subsidies and the internalization of negative environmental externalities caused by

fossil fuels (Unruh, 2000).

Although the costs have significantly declined in recent years, RE technologies still require

support schemes to keep this trend. In fact, in 2017, the global weighted average LCOE of

onshore wind plants reached USD 0.06/kilowatt-hours (kWh), while for utility-scale of solar

Page 10: Risk management and policy implications for concentrating

9

PV was around USD 0.10/kWh. However, CSP technology has been dragging out for many

years, by having a global weighted average LCOE around USD 0.22/kWh (IRENA, 2018).

Despite the abundance of RE resources, their share remains modest due probably to the small-

scale production, the insufficient learning effects, and the lack of institutional support. The

government policy based on goals, strategies and instruments is very important for the

development of RE. In fact, Research and Development (R&D) subsidies and the creation of

market niches are recommended to stimulate these new options (Kemp, 1994).

Researchers and analysts who studied and evaluated RE support systems used many different

ways to describe and classify them. The most used typology is the one that differentiates

between price-based and quantity-based instruments (Menanteau et al., 2003). In fact, the

instruments and mechanisms used to accelerate the diffusion of RE are various, they include:

Renewable Porfolio Standard (Xin-gang et al., 2018), Green Certificates (Hustveit et al.,

2017), Feed-in Tariffs (Böhringer et al., 2017), and Renewable Obligation (Nock and Baker,

2017).

3. Current status of CSP technology

CSP plants produce electricity by using heat. In a similar manner as a magnifying glass,

mirrors concentrate the direct solar radiation on a receiver filled with a heat transfer fluid. The

heat absorbed by the fluid is used to produce steam that drives a turbine to produce electricity.

Unlike solar PV technology, CSP technology has the advantage of storing heat energy for

later conversion into electricity. In this case, the production of electricity in the absence of

sunlight is possible by using thermal energy storage systems. This characteristic enables CSP

plants to provide dispatchable power.

The CSP plants can be divided into four different technology types: parabolic troughs, linear

Fresnel mirrors, central receiver systems, and dish Stirling systems. The CSP market is still

dominated by parabolic troughs.

Areas favorable to the development of the CSP technology are regions that enjoy a maximum

DNI, such as the MENA region, Central Asia, South Africa, South of Spain, etc. The solar

limit required for potential sites is set at a DNI of at least 2,000 kWh/m²/year due to economic

constraints.

Unlike most natural resources, solar energy in the form of DNI exists in all continents. In

addition, the populated areas are quite close and can be connected to those regions that have

Page 11: Risk management and policy implications for concentrating

10

excellent solar conditions. Indeed, the electricity produced in the sunniest areas of the planet

can be transmitted by means of high voltage direct current (HVDC) lines over several

thousand of kilometers.

With the exception of Spain and the United States of America (USA), which are leaders in

CSP technology, very few countries have large CSP facilities connected to the national

electricity grid with a capacity of more than 50 MW. These countries are China, India,

Morocco, South Africa, and the United Arab Emirates (UAE).

The new CSP installed capacity in 2017 was 100 MW and the global installed capacity

reached 4.9 GW by the end of 2017 (REN21, 2018). On the other hand, Spain and the USA

continue to be the leaders in terms of existing CSP capacity, but the growth of the CSP market

is driven outside of these traditional markets and directed to new emerging markets, such as

South Africa, India, China, and Morocco.

With the exception of Morocco and the UAE, which are key drivers of CSP expansion, the

development of CSP technology in the MENA region is still below expectations regarding the

enormous potentials in these countries. However, in Saudi Arabia and Kuwait, many CSP

facilities are under construction which can shift the CSP activity from Spain and the USA to

the MENA region in the next few years. In fact, the MENA region is one of the most

favorable regions for the large-scale deployment of CSP technology. Moreover, this region is

characterized by exceptional geographical features, such as high DNI, low precipitation,

especially in desert areas, and the existence of flat and unused lands that are not far from

power grids and roads. So, this region is very convenient for the widespread deployment of

CSP technology and the export of the electricity produced to Europe using HVDC lines.

The economic impacts resulting from the development of a local industry of CSP technology

in North Africa was explained in many papers. For example, Kost et al. (2012) demonstrated

that the development of a CSP market in North Africa will positively influence the local

economies and significantly contribute to the national gross domestic product. They actually

found that total generated revenues from the potential market size of CSP plants could attain

120 Billion Euros by 2030.

4. Barriers to CSP expansion

The cost of CSP technology is one of the most prominent barriers to its large scale diffusion

(del Rio et al., 2018). Therefore, support policies must be implemented in order to make

Page 12: Risk management and policy implications for concentrating

11

investment profitable for existing firms, encourage new entrants to the CSP market, support

innovation, and make CSP technology more competitive.

Lilliestam et al. (2018) considered that the CSP industry is facing two crucial risks. The first

one is that many experienced firms leave the CSP market, which leads to the loss of a lot of

tacit knowledge, know-how, and experience. The second risk is that developers and operators

ignore innovations by using well-known components in order to avoid technology risks. This

attitude is a great barrier to cost reduction.

On the other hand, the financing risk is among the risks that have attracted much attention.

For example, Lilliestam et al. (2012) considered that, among the major barriers to scaling-up

CSP technology, there are the expansion of electricity transmission lines and financing risks.

In fact, the lack of experience with CSP investment in most emerging economies increases

financing risks. Indeed, these countries are suffering from small financial markets, which are

not convenient for financing large scale CSP plants, especially in terms of high interest rates

and the absence of debts with long maturities (Stadelmann et al., 2014). In this case, reducing

these risks is necessary to encourage developers and scale-up private investments.

Technical risks are also of a great importance. Indeed, Amato et al. (2011) carried out a very

original study by assessing the risks associated with business interruption and loss of assets

resulting from the emergence of undesirable internal or external events. These authors

identified a list of critical hazards, such as malfunction of the orientation system, turbine

failure, turbine leakage, salt solidification, and orientation system stopping.

In fact, there are many other country-specific analyses that focused on the barriers that

hamper the development of CSP technology in some countries, such as Chile (Haas et al.,

2018) and China (Zongxian et al., 2012), or some other regions, like the European Union (del

Rio et al., 2018) and the Sub-Saharan Africa (Labordena et al., 2017).

On the other hand, the MENA region has attracted the attention of many researchers. For

example, Komendantova et al. (2012) conducted three stages of interviews with experts to

investigate their perceptions of risks in the case of CSP projects in North Africa. The results

of unstructured expert interviews showed that bureaucratic procedures and corruption have

been identified as significant barriers by more than half of all the interviewed experts. Other

risks, such as the instability of national regulations, the low level of political stability, and the

absence of guarantees from national governments, have also been identified as significant

barriers.

Page 13: Risk management and policy implications for concentrating

12

Although political corruption and bureaucracy are considered as the main concerns of

investors in North Africa (Komendantova et al., 2011), the availability of water in the MENA

region is also a serious challenge that should be taken into account (Balghouthi et al., 2016;

Belgasim et al., 2018; Xu et al., 2016). In fact, CSP plants require a large amount of water for

the cooling process and for cleaning mirrors. However, in arid locations where the annual

irradiance levels are high, there is a scarcity of water. This problem can possibly be solved by

the use of dry cooling technology. For example, Trabelsi et al. (2016) showed that a CSP

plant with dry cooling can reduce water consumption by 93.3%.

Morocco is the country of the MENA region that has attracted much attention over the past

few years. For example, Wiesinger et al. (2018) evaluated a very important technical risk

which is the erosion effect on the glass due to airborne sand and dust in two sites in Morocco.

This risk can increase the losses of optical energy and also the operation and maintenance

costs.

On the other hand, Medina et al. (2015) showed that, for the case of companies without an

earlier presence in Morocco, uncertainty, insecurity and informality are the main obstacles

affecting the decision to invest in the CSP sector. Regarding companies that are already active

in Morocco, financial and legal barriers are of a great importance. For the same case of

Morocco, Mahia et al. (2014) conducted a survey in order to examine the potential of CSP

market and barriers for establishing a CSP manufacturing industry. They also showed that

policy related barriers, such as the absence of fiscal and legislative framework for CSP

development, are more crucial than entrepreneurial or market barriers. However, other studies

discussed rather risk reduction strategies. For example, Frisari and Stadelmann (2015)

examined the importance of national policy makers and international finance institutions in

de-risking CSP technology in India and Morocco. Some other studies focused on de-risking

CSP investments in the MENA region. For example, Schinko and Komendantova (2016)

employed an LCOE model in order to analyze the impacts of a de-risking approach on the

cost of electricity from CSP in four specific North African countries (Algeria, Egypt,

Morocco, and Tunisia). They showed that in order to have a weighted average cost of capital

(WACC) in North Africa equivalent to that in Europe, the CSP costs should be reduced by

39%. Trieb et al. (2011) proposed long term power purchase agreements as a de-risking tool

for CSP investments in the MENA region.

Page 14: Risk management and policy implications for concentrating

13

Although the studies that addressed risks for the case of CSP technology are multiple and

treated many countries, Tunisia has not received yet the attention of researchers and there is

no study that deals with CSP barriers in Tunisia.

In addition to that, the existing scientific literature has used expert interviews, literature

reviews, surveys, and scenario analyses, but the GRA method has not been used yet for the

case of a CSP project. In fact, using this method in an environmental study is new and

innovative since there is only one published study that applies the GRA method for the case

of a wind farm, which is that of Desroches et al. (2016). Actually, this method is usually used

for studies in the field of chemistry, industry, and mainly medicine, such as the one by

Mazeron et al. (2014).

Therefore, the aim of this paper is to fill in this gap by making two contributions to the

existing literature: i) treating the barriers to CSP deployment in Tunisia; ii) using the risk

management approach and particularly the GRA method for the case of a CSP project.

5. Method and data

In this section, we will briefly introduce the case studied which concerns a CSP plant, then we

will describe all the steps of the GRA method, and we will finish by applying this method to

analyze all the risks that hinder the implementation of this CSP project.

5.1.Case study: a CSP project in Tunisia

We chose to study the case of the first CSP export project between the Sahara region and the

South of Europe. This CSP power plant will be established in Southern Tunisia, which is

characterized by a favorable solar radiation level of 2,500 kWh /m2/year.

The installed capacity will be 2,250 MW: a first stage of 250 MW and a second stage of 2,000

MW. This mega CSP project consists of the construction of a CSP power plant using the solar

tower technology with thermal storage, the transmission of the produced electricity to Italy

using underground and sea cables, and finally the electricity sale in the European energy

market.

The British developer of this CSP project estimated that the overall cost will be around 10

billion Euros. Once operating, this project will have many positive impacts on the Tunisian

economy in terms of job creation and implementation of an industrial area devoted to solar

technologies in Southern Tunisia since most of the components will be locally manufactured.

Page 15: Risk management and policy implications for concentrating

14

Table 1

The main features of the CSP project.

Location South of Tunisia

Annual generation 9,000 Gigawattheure (GWh)

Area 10,000 hectares

Technology CSP tower technology with thermal storage

Storage equipment Molten salt

Status Partially permitted

In fact, the feasibility study of this project began in 2009, however, until now, the

construction has not started yet. The project is a perfect illustration of the existence of many

barriers to the investment in CSP technology in Tunisia. In order to analyze all the barriers

and risks faced by the developers, we used a risk management approach and especially the

GRA method that will be explained in the next sub-section.

5.2.The GRA method

The GRA is a global analysis method which is used to appreciate and manage risks of

different natures, such as company’s risks, project risks, and product risks, following an

invariable process. Its specificity depends on the nature of the considered system and the

mapping of the considered hazards and not on the actual analysis process.

The GRA is the name given by Desroches (2013) to the up-to-date Preliminary Risk Analysis

(PRA) method which was developed in the 1960’s in the aerospace industry and recently

extended to many other sectors, including military, chemistry, transport, medicine, and more

recently the environment. This analysis is particularly used in health organizations and civil

aviation. This paper presents the first application of the GRA for the case of a CSP plant.

In fact, the GRA is a priori (proactive), an analytical, bottom up, and semi quantitative risk

analysis method (Desroches et al., 2016) which implements all the risk analysis and

management steps in compliance with the ISO 31000:2018 norm (an international standard

that provides principles and guidelines for risk management). Besides, it includes context

establishment, risk identification, risk assessment, initial risk reduction (prevention/

protection), and residual risk assessment and management (monitoring/insurance taking). It

can be used for the management of risks of different natures, such as enterprise risk, project

risk, and product risk (Desroches, 2013).

Moreover, the GRA is based on the accident scenario presented in Fig.1. An accident scenario

is defined as a sequence or a combination of events ending up in an accident (A) that has

consequences (S). This scenario begins with the occurrence of a contact event or an

Page 16: Risk management and policy implications for concentrating

15

exposition factor (EF) which creates the exposition of the system (S) to a hazard (H) and

therefore, creates a hazardous situation (HS). Then, the exposition of the hazardous situation

(HS) to an initiating or a triggering factor (TF) leads to the accident (A). Finally, the

occurrence of a circumstantial event or an aggravating factor (AF) defines and characterises

the occurrence, the nature, and the severity of the consequences (S). The causes (hazard,

contact event, and trigger event) are related to the parameter “likelihood” of the risk. The

nature and the intensity of the consequences are related to the parameter “Severity” of the

risk.

Fig 1. Accident scenario (Desroches, 2013).

The GRA process (Fig.2) contains three consecutive steps: the system GRA, the scenario

GRA and the risk management. The first step consists in: (i) defining the perimeter of the

studied system which is the CSP project divided into phases and sub-phases (Appendix A);

(ii) identifying all the hazards that could potentially affect the implementation of the project in

a hierarchical list composed of generic hazards (generic categories), specific hazards (sub-

categories specifically to the system) and hazardous elements/events (translation of the

specific hazards in terms of events or elements); and, finally, (iii) identifying the interactions

between hazardous events and sub-phases of the system leading to hazardous situations. The

structure of the mapping of hazardous situations is made by the crossed juxtaposition of the

system and the mapping of hazards. The hazard/system interaction is the factor that generates

hazardous situations. The interactions should normally be considered as determinists.

The second step, which is the scenario GRA, consists, first of all, in defining the risk

assessment parameters, such as the severity and likelihood scales (Table 3 and Table 4). The

Unwanted Event (UE)

or

Accident

(A)

5

• Consequence(S)

7

Aggravating factor (AF)

6

System

Hazard(H)

1

Contact Event

(CE) or Exposition Factor (EF)

2

• Hazardous

Situation(HS)

3

Trigger Event

(TE) or Triggering Factor (TF)

4

Page 17: Risk management and policy implications for concentrating

16

severity scale is based on 5 levels of decreasing severity. In compliance with basic principles

of dependability, levels S5 and S4 are related to safety whereas levels S3 and S2 are related to

the performance of the system (reliability/availability). Concerning the likelihood scale, it is

semi-quantitative and based on 5 levels of likelihood, which can be associated with a scale of

system-dependent return periods.

Once the assessment scales are identified, the criticality matrix can be built (Table 6). Finally,

the scenarios are identified and described, and the associated initial risks are assessed. If

needed (initial criticality C2 or C3), initial risk reduction actions are identified in terms of

prevention (decrease of the likelihood) and protection (decrease of severity) and the

subsequent residual risk is assessed. Again, if needed (residual criticality C2), residual risk

management actions are defined in terms of risk control/monitoring and insurance taking

(Appendix D. Scenario_GRA).

The third step, which is risk management and result dissemination, comes after data

performing. Therefore, risk mappings are built (Kiviat and Farmer diagrams, but only Kiviat

diagrams are presented in this paper) based on the statistical treatment of the analysis. The

minimal, average and maximal risks are represented per hazards and per phases. Then, the list

of 5 to 10 major risks is elaborated. Moreover, the practical management of risks is made by

the drafting of action sheets and the development of an action follow-up table for initial and

residual risks. The software used to perform this analysis is the version 2.091 of StatCart

GRA developed by MAD-environment.

Fig.2. The GRA process.

The GRA method requires in-depth knowledge of the studied system, which is the CSP

project. For this reason, this method has been applied during a six-month internship at the

National Agency for Energy Conservation (ANME: Agence Nationale pour la Maîtrise de

1. System GRA

•System description

•Hazard mapping

•Hazardous situation mapping

2. Scenario GRA

•Severity and likelihoodscales

•Criticality matrix

•Scenarios identification and assesment of associatedinitial and residual risks

3. Risk management and results dissemination

•Overall results for initial and residual risks

•Risk mapping per hazard

•Risk mapping per system element

•List of top risks

•Initial risk reduction plan

•Residual risk management plan

Page 18: Risk management and policy implications for concentrating

17

l’Energie), which is the leader in the institutional organization of energy efficiency and RE in

Tunisia. This internship has facilitated meetings with several experts, especially during the

numerous congresses organized by the ANME during the training period. In addition, this

internship has been an opportunity to benefit from the knowledge and advice of experts and

engineers who are working at the ANME. We have also conducted open interviews with the

chief executive officer of the project. In addition, we have used a review of the data provided

by the ANME, the state electricity utility STEG (STEG: (Société Tunisienne de l’Electricité

et du Gaz), and a compilation of secondary sources (books, scientific articles, reports prepared

by international organizations, press articles, etc.), as well as a feedback from similar projects,

such as the case of the CSP plant in Morocco.

Based on professional advice from experts, managers and engineers in the field of RE as well

as experience feedback, we have been able to carry out all stages of the GRA which require a

multidisciplinary team. The use of the GRA method for this case is adequate for two main

reasons. The first one is that this method is a priori (proactive) risk analysis method so, it can

be used to analyze risks of a project or an activity before it takes place. This is adequate to

this case study since the construction of the CSP plant has not begun yet. The second reason is

that the construction of this CSP plant was postponed many times and since 2009, there has

been no real progress, which proves that the implementation of the project faces several

barriers and risks that hinder its implementation. Hence, a risk analysis using the GRA

method is needed to identify the main barriers.

5.3.The application of the GRA method for the case of a CSP project

In this sub-section, we will apply the two first steps of the GRA process, which are the system

GRA and the scenario GRA, to the case of the CSP project while the risk management step

which comes after data processing will be explained in the result section.

5.3.1. System GRA

The system GRA contains the following steps: the description of the CSP project (Appendix

A), the elaboration of the hazard mapping (Appendix B), and finally the elaboration of the

hazardous situation mapping (Appendix C. Mapping_HS).

5.3.1.1. Description of the CSP project

The first required step is a detailed description of the CSP project. In fact, a deep analysis of

the CSP project enabled us to divide it into four main steps (feasibility study, preparation,

construction, and operation), 20 phases, and 51 sub-phases (Appendix A).

Page 19: Risk management and policy implications for concentrating

18

5.3.1.2.Elaboration of the hazard mapping

The list of generic and specific hazards has been established similarly to the one proposed by

Desroches (2013), and the hazardous events have been determined according to the

characteristics of the CSP project in terms of technology, operating methods, required

resources, etc. Finally, we got 14 generic hazards (political, environment, insecurity, image,

management, strategic, technological, communication and crises, legal, financial,

infrastructure and premises, materials and equipment, information system, and physical-

chemical) detailed in many hazardous events which can affect the sub-phases of the CSP

project (Appendix B). In fact, the hazardous events were identified by reviewing many

studies, such as those of Gabriel (2016), Otieno and Loosen (2016), Painuly (2001),

international reports, press articles, feedback from similar CSP systems (for example, the CSP

plant Noor in Morocco), and especially discussions with experts working in the ANME and

with the chief executive officer of the project.

5.3.1.3.The hazardous situation mapping

The sub-phases of the CSP project have been confronted to the hazardous events in a double

entry table in order to obtain the hazardous situation mapping (Appendix C. Mapping_HS).

The development of the hazardous situation mapping is the fundamental cornerstone of the

analysis since it requires a rigorous and detailed work, and especially a thorough knowledge

of the studied project. In addition to that, the determination of hazardous situations is the key

step that will be used to determine risk scenarios, risk maps and the list of the major risks.

Fig. 3. The elaboration of the hazardous situation mapping.

Page 20: Risk management and policy implications for concentrating

19

In fact, each interaction between a hazardous event and a vulnerable element of the system

represents a hazardous situation which has been evaluated, when relevant, by assigning a

priority index. Then, the hazardous situations have been classified into three priority levels

according to the priority indexes explained in Table 2. For example, when the interaction

between the vulnerable element of the system and the hazardous event is strong and the

evaluation and treatment of this hazardous situation is needed immediately, we put a priority

index “1” in the cell.

Table 2

The interactions between the hazards and the system.

Priority

Index (Ip) Interaction Hazard/System

Decision to perform an

analysis, an evaluation and

treatment

Blank or 0 No interaction

1 Strong to very strong interaction Immediately

10 Strong to very strong interaction Later

2 Weak to medium interaction Afterwards

Source: Desroches et al. (2016)

In our study, we have been able to identify 169 hazardous situations, which have been divided

into 33 hazardous situations with a priority index “1” (19%), 62 hazardous situations with a

priority index “2” (37%), and 74 hazardous situations with a priority index “10” (44%). Then,

we have only analyzed hazardous situations with a priority index “1”.

5.3.2. Scenario GRA

The scenario GRA contains the following steps: the elaboration of severity and likelihood

scales (Table 3 and Table 4) and criticality matrix (Table 6), and the identification of all

possible scenarios according to the process explained in Fig.1 in order to obtain the scenario

GRA (Appendix D. Scenario_GRA).

5.3.2.1.The severity and likelihood scales

The risk assessment is based on two aspects:

- The severity of consequences (S), which is based on a severity scale (Table 3) composed of

5 levels: S1 (insignificant, which corresponds to no real impact on mission or safety), S2

(minor or significant, which corresponds to the mission degradation without any impact on

safety), S3 (major or severe, which corresponds to the mission failure without any impact on

safety), S4 (hazardous or critical, which corresponds to safety degradation), and S5

(catastrophic, which corresponds to safety failure).

Page 21: Risk management and policy implications for concentrating

20

- The likelihood of occurrence (L) which is based on a likelihood scale (Table 4) composed of

5 levels: L1 (extremely improbable), L2 (improbable), L3 (remote), L4 (occasional), and L5

(frequent).

The severity and likelihood scales have been developed in a working group that takes into

account the experience feedback of similar projects, the data collected from different sources,

and the knowledge of each member of the multidisciplinary group.

Table 3

Severity scale.

Severity level Severity name Severity index Description of consequences

S1 Insignificant 1 10 No impact on the system performance or safety

11 Insignificant reduction in performance without impact on

activity

12 Inconsequential operational constraints

13 Temporary unavailability of structure or equipment

14 Injury on duty without work stoppage

S2 Minor 2 20 Degradation of the system performance with no impact on

safety

21 Unavailability of services or equipment on the scheduled date

22 Unavailability of equipment, premises or staff less than one day

23 Injury on duty with work stoppage less than 21 days

24 Controllable pollution

S3 Major 3 30 Significant degradation or failure of the system performance

with no impact on safety

31Significant performance degradation

32 Very degraded or failed activity

33 Significant operational constraints

34 Significant damage to infrastructure or goods

35 Injury on duty with work stoppage for more than 21 days

S4 Hazardous 4 40 Degradation of the system’s safety or integrity

41 Severe injury or temporary disability

42 Partial destruction of infrastructure or assets

43 Significant damage to the environment

44 Temporary staff disability

45 Delay in project implementation

S5 Catastrophic 5 50 Significant degradation or failure of the system safety or its loss

51 Loss of life or disability

52 Total destruction of infrastructure or assets

53 Irreversible damage to the environment

54 Huge financial loss

55 Permanent discontinuation of the project

The likelihood scale (Table 4) contains 5 likelihood levels associated with a recurrence

period. Recurrence periods are determined according to the temporality, lifetime and technical

characteristics of the CSP plant.

Table 4

Likelihood scale.

Likelihood levels Level name Likelihood index Likelihood description

L1 Extremely improbable 1 Less than once per 25 years

L2 Improbable 2 Between once per 25 years and once per 5 years

L3 Remote 3 Between once per 5 years and once a year

Page 22: Risk management and policy implications for concentrating

21

L4 Occasional 4 Between once a year and once a month

L5 Frequent 5 More than once a month

5.3.2.2.The criticality matrix

The risk criticality represents the function of decision: C = fd (S,L). The definition domain of

fd is 25 couples (S,L) and its domain of values is {C1,C2,C3}. The criticality is the result of a

decision function linked to a scale of political, social, human values, etc. (Desroches et al.,

2016).

The first and most important step is to divide all the project risks into three categories

according to their criticality. The criticality classes are: acceptable (C1), tolerable under

control (C2), and unacceptable (C3) of respective colors: green, yellow, and red (Table 5).

Each criticality class corresponds to a well-defined action.

Table 5

Criticality scale.

Criticality

level Risk level Decisions and actions

C1 Acceptable Nothing needs to be done.

C2 Tolerable under control No action to reduce the risk is mandatory, but a close monitoring

needs to be implemented in terms of risk management.

C3 Unacceptable The risk needs to be reduced, otherwise, the activity must be

stopped partially or totally.

Source: Desroches et al. (2016)

The criticality matrix (Table 6) is a two-dimensional presentation that presents the two

components of risk: likelihood versus severity. It allows the association of a criticality level to

each severity-likelihood pair. Thus, a severity level S5 associated with a likelihood level L5

corresponds to a maximum criticality level C3.

Indeed, by defining the domain of unacceptability, we delimit the domain in which the risks

must absolutely be refused and by defining the domain of tolerability or acceptability, we

delimit the domain in which all the risks must be with or without a treatment.

Table 6 Criticality matrix.

Severity

1 2 3 4 5

Lik

elih

oo

d 5 1 2 3 3 3

4 1 2 2 3 3

3 1 1 2 2 3

2 1 1 1 2 2

1 1 1 1 1 1

Page 23: Risk management and policy implications for concentrating

22

Likelihood and severity scales and criticality matrix have been used to evaluate all the risk

scenarios according to the severity of consequences and likelihood of occurrence and, then,

have been prioritized by criticality. The criticality of each scenario has been determined and

all scenarios have been divided into 3 categories of criticalities: C1, C2, and C3. Corrective

actions have been set up in order to reduce initial risks. Once the categorization of initial risks

was done, corrective actions are proposed to reduce scenarios with criticality C3 and C2. The

criticality of residual risks has also been re-evaluated by according a new level of criticality

that integrates the impacts of the corrective actions implemented to initial risks. (Appendix D.

Scenario_GRA).

6. Results and discussions

Once the scenario GRA is elaborated by using the hazardous situation mapping, the

assessment scales and the criticality matrix, we move on to data performing by using the

version 2.091 of StatCart GRA developed by MAD-environment.

The application of the GRA method to the CSP project enables us to analyze the risks that

impede the implementation of this project. The results are explained in details in this section.

We have just analyzed the hazardous situations with priority index “1” given the serious

impacts they may have on the CSP project. The scenario GRA has allowed us to identify 33

risk scenarios from the 33 hazardous situations of priority index “1”.

In order to present the main results, we start with the distribution of hazardous situations by

type of generic hazard, which enables us to identify the type of hazard that is likely to cause

the highest number of hazardous situations and risk scenarios. We find that the political

hazard creates the highest number of hazardous situations, which means that the political

hazard must be taken seriously by the developers of this project (Table 7). Concerning the

distribution of hazardous situations by project phase (feasibility study, preparation,

construction, and operation), we conclude that the preparation phase of the project contains

the highest number of hazardous situations (12 hazardous situations among the 33 analyzed

hazardous situations). Therefore, this phase is the most affected by the different types of

generic hazards and requires the most attention (Table 8).

Then, we present the distribution of risk scenarios per initial and residual criticality classes

(C1, C2, and C3). We note that the risk reduction actions explained in the scenario GRA

(Appendix D. Scenario_GRA) allow us to move on from 10 initial risks with C3 criticality

(Table 9) to no residual risk with C3 criticality (Table 10).

Page 24: Risk management and policy implications for concentrating

23

Afterwards, we present the Kiviat diagram which provides a representation of minimal,

average and maximal risks per hazard and per phase while integrating at the same time

criticality. According to this diagram, the risks resulting from the legal hazard have the

minimum, medium and maximum risk indexes with C3 criticality (unacceptable), which

means that the risks caused by the legal hazard must be taken very seriously by investors

(Fig.6). We also note that the initial risks arising from the preparation phase have an average

risk index with C3 criticality, which confirms the vulnerability of this phase (Fig.7).

Finally, the GRA method allows us to determine the list of top risks, such as the risk of not

obtaining permission to build the CSP plant, the risk of non compliance with deadlines, the

risk of failure to achieve the expected performance, the risk of insufficient access to capital,

and the risk of conflicts with local residents. We explain in details the main causes of the top

risks and the convenient strategies and actions that we propose to reduce them.

6.1. Distribution of risk scenarios per type of generic hazard and per project

phase

We note that the political hazard is likely to cause the highest number of hazardous situations

and risk scenarios (10 scenarios). The physical-chemical, financial and strategic hazards

generate respectively 4, 3 and 3 risk scenarios (Table 7).

These findings are in line with the results of most studies, especially with regard to the

importance of political and financial hazards in the MENA countries. However, this study

emphasizes the physical-chemical hazard which is often neglected in RE projects.

Table 7

Number of identified hazardous situations and analyzed scenarios per generic hazard.

Type of hazard Index Number of

hazardous situations

Number of risk

scenarios

Political POL 10 10

Environment ENV 2 2

Insecurity INS 1 1

Image IMG 1 1

Management MAN 2 2

Strategic STR 3 3

Technological TEC 1 1

Communication and crises COM 1 1

Legal LEG 2 2

Financial FIN 3 3

Infrastructure and premises INF 1 1

Materials and equipment MAT 1 1

Information system IS 1 1

Physico-chemical PCH 4 4

Page 25: Risk management and policy implications for concentrating

24

The 33 hazardous situations of priority index “1”, which are grouped per generic hazard type,

are shown in percentages in Fig.4. This representation shows two groups of hazards that can

be classified according to their relative importance:

- Hazards with prime importance: political (30%), physical-chemical (13%), financial (9%),

strategic (9%), environment (6%), management (6%), and legal (6%).

- Hazards with medium to low importance: material and equipment (3%), information system

(3%), infrastructure and premises (3%), communication and crisis (3%), technological (3%),

insecurity (3%), and image (3%).

Fig. 4. Distribution of hazardous situations per generic hazard.

It is therefore clear that the CSP project is too exposed to political hazard since the latter

generates the greatest part of hazardous situations. This is quite logical given the current

situation in Tunisia which is characterized by political instability following the 2010

revolution and the birth of a young democracy.

Table 8

Number of identified hazardous situations and scenarios analyzed per phase of the project.

Phase of the project Index Number of hazardous situations Number of risk scenarios

Feasibility study A 3 3

Preparation B 12 12

Construction C 8 8

Operation D 10 10

Concerning the identified hazardous situations and the scenarios analyzed per project phase

(Table 8), the results show that the preparation and operation phases of the CSP project

contain the highest number of hazardous situations. The preparation phase is the phase the

most exposed to the 14 generic hazards since it generates 12 hazardous situations of priority

index “1”. This is due to the complexity of administrative, legal and financial procedures

required to have all the necessary authorizations and agreements. Indeed, this phase is

POL

30%

ENV

6%

INS

3%IMG

3%

MAN

6%STR

9%TEC

3%

COM

3%

LEG

6%

FIN

9%

INF

3%

MAT

3%

IS

3%PCH

13%

Page 26: Risk management and policy implications for concentrating

25

decisive for the implementation of the project. Moreover, for more than 6 years, the project

has been blocked in this phase without any progress towards the phase of construction. These

results demonstrate the delicacy of the preparation phase and its high vulnerability to the

different classes of generic hazards.

The 33 hazardous situations of priority index “1” grouped per project phase are shown in

percentages in Fig.5 in which the preparation and operation phases contain respectively 37%

and 30% of all the identified hazardous situations, while the construction phase contains 24%

and the feasibility study contains just 9% of all the hazardous situations.

Fig. 5. Distribution of hazardous situations per project phase.

6.2.Distribution of risk scenarios per initial and residual criticality

The following tables (Table 9 and Table 10) present the number of risk scenarios analyzed

according to the “severity-likelihood” couple, as well as before and after the actions of

reduction of initial risks presented in the scenario GRA (Appendix D. Scenario_GRA). We

note that before starting these actions (Table 9), we have one initial risk with C1 criticality

(acceptable), 22 initial risks with C2 criticality (tolerable under control), and 10 initial risks

with C3 criticality (unacceptable).

Table 9

The criticality matrix for initial risks.

Severity

1 2 3 4 5

Lik

elih

oo

d 5 1 2

4 4 7 6

3 7 2 2

2 2

1

33

C1 1

C2 22

9%

37%

24%

30%Feasibility study

Preparation

Construction

Operation

Page 27: Risk management and policy implications for concentrating

26

C3 10

33

The risk reduction actions allow us to reduce the criticality of initial risks by reducing the

likelihood or the severity, or both at the same time in order to have residual risks with C1

(acceptable) or C2 (tolerable under control) criticality and no residual risk with C3 criticality

(unacceptable). This is well respected in our analysis since we have 23 residual risks with C1

criticality (acceptable), 10 residual risks with C2 criticality (tolerable under control), and no

residual risk with C3 criticality (unacceptable) (Table 10).

Table 10

The criticality matrix for residual risks.

Severity

1 2 3 4 5

Lik

elih

oo

d 5 1

4 2

3 4 7 6

2 5 5 2

1 1

33

C1 23

C2 10

C3 0

33

6.3.Risk mapping per hazard

The Kiviat diagram provides an overview of the risks associated with the CSP project and

facilitates their comparison. In fact, it provides a detailed analysis of the initial and residual

risks per generic hazard or per project phase. This representation allows us to make the

appropriate decisions according to the general context and the vulnerability of the project.

The axes of the diagram represent the 14 generic hazards. The minimum, average and

maximum indexes of the different initial and residual risks are positioned on these axes. The

Kiviat diagram also shows the three risk criticality areas (C1, C2 and C3, respectively with

the colors green, yellow, and red).

Page 28: Risk management and policy implications for concentrating

27

Fig. 6. Kiviat diagrams of initial and residual risks per hazard.

According to the left-sided Kiviat diagram in Fig.6, we notice that the initial risks descended

from environmental, political, physical-chemical, financial, and legal hazards have a

maximum risk index of C3 criticality. Thus, the risks arising from these types of hazards must

be a priority for project developers and managers in order to avoid serious consequences.

Among these generic hazards, only the legal hazard can cause initial risks with a minimum

risk index of C3 criticality. This leads us to note that the legal hazard must be taken very

seriously by investors, since the risks resulting from this hazard have the minimum, medium

and maximum risk indexes with C3 criticality. Thus, even if the share of risks arising from

legal hazard is not very high (only 6% compared to 30% for political hazard and 13% for

physical-chemical hazard), this hazard can cause risks with catastrophic and therefore

unacceptable consequences for the project.

The right-sided Kiviat diagram in Fig.6 provides an assessment of the effectiveness and

magnitude of risk reduction actions. After the implementation of the initial risk reduction

actions, we can make the following remarks:

- None of the residual risk indexes (minimum, average or maximum) has a C3 cirticality.

Thus, the risk reduction actions implemented have succeeded in bringing all the risk indexes

to C2 or C1 criticality levels. This result proves the effectiveness of the applied actions.

Page 29: Risk management and policy implications for concentrating

28

- The residual risks arising from political, financial, legal and environmental hazards have an

average risk index of C2 criticality. Thus, the residual risks arising from these hazards are

tolerable under control and therefore require control actions, such as insurance.

- The residual risks resulting from the legal hazard have a minimum risk index of C2

criticality. Consequently, even after the implementation of the initial risk reduction measures,

the residual risks arising from the legal hazard should always be under the continuous control

and monitoring by applying control measures.

6.4.Risk mapping per project phase

In the case of the analysis per project phase, the axes of the Kiviat diagram (Fig.7) represent

the 4 phases of the project (feasibility study (A), preparation (B), construction (C), and

operation (D)) that have been presented and explained in the detailed analysis of the project.

The axes also contain the minimum, average and maximum risk indexes corresponding to

each phase of the project. The Kiviat diagram also shows the three criticality areas.

Fig. 7. Kiviat diagram for initial and residual risks per project phase

According to the left-sided Kiviat diagram in Fig.7, we notice that the initial risks that emerge

from the four phases of the project have maximum risk indexes with C3 criticality. Thus, all

the four phases should be a priority for project managers in order to avoid serious

consequences. In fact, among the four phases, only the initial risks arising from the

preparation phase (B) have an average risk index with C3 criticality. This result confirms the

vulnerability of this phase, which requires more importance than the other three phases.

Page 30: Risk management and policy implications for concentrating

29

After the implementation of the initial risk reduction actions (right-sided Kiviat diagram in

Fig.7), we can make the following remarks:

- None of the residual risk indexes (minimum, average or maximum) from the four phases has

a C3 cirticality. Thus, the risk reduction actions implemented have succeeded in bringing all

the risk indexes to criticality levels C2 or C1. This result proves the effectiveness of the

applied actions.

-The residual risks arising from the preparation (B) and construction (C) phases have a

residual average risk index of C2 criticality. Consequently, the residual risks arising from

these phases are tolerable under control and require control actions, such as insurance. This

observation leads us to stress the high vulnerability of the preparation phase to generic

hazards.

6.5.List of major risks and recommendations

The GRA method allows us to determine the list of top risks. We will explain in details in this

sub-section the main causes of the top risks and the convenient strategies and actions that we

propose to reduce these risks.

The list of top risks identified in the present study is in line with many studies dealing with

barriers to CSP investment in the MENA region. In fact, previous studies have pointed out the

importance of financing barriers (Lilliestam et al., 2012), the bureaucracy and corruption

(Komendantova et al., 2011), and the regulatory risk which can delay obtaining a permission

(Komendantova et al., 2012). However, we find that the risk of conflicts with local residents

is a serious risk that should be taken into account by developers. This result is in contrast with

the analysis of Hanger et al. (2016) which shows that community acceptance is almost

universal for the case of the CSP plant Noor in Morocco.

Concerning the risk of failure to achieve the expected performance because of the use of

tower technology with dry cooling, this result is in contrast with the analysis of Trabelsi et al.

(2016) which proves that due to the high DNI in Southern Tunisia, CSP plants with dry

cooling are technically and economically competitive with the wet cooled CSP plants.

Nevertheless, this research deals with parabolic trough technology and not tower technology

which is used in our case study.

The major risks that can affect the CSP plant, their causes and the main actions that we

propose to reduce these risks are explained as follows:

Page 31: Risk management and policy implications for concentrating

30

• The risk of not obtaining a permission to build a CSP plant

This risk results from the absence of a legal framework for the export of electricity produced

from RE, in Tunisia, and the complexity of approval procedures. Moreover, the political

instability since the revolution and the lack of visibility in the medium and long-term are all

factors that have aggravated the situation.

In order to eliminate this legal barrier and have a suitable legal framework for this project,

the project managers have initiated, since 2010, discussions with the government officials in

order to develop a new regulation suitable for this project. Fortunately, after many years of

waiting, a new law which authorizes the export of green electricity was approved in 2015.

• The risk of non compliance with deadlines

These delays can be caused mainly by bureaucracy, corruption, long and complicated

administrative procedures, administrative inefficiency, delays in signing contracts, and a poor

estimation of the processing time.

Moreover, uncertainty and unexpected events are linked to any large scale project so, there is

always the possibility of delays. In Tunisia, this risk is more frequent due to bureaucracy and

corruption, therefore, the project managers should set realistic deadlines taking into account

the Tunisian context. In addition, many delays are predictable and quite common to all RE

projects in the developing countries so, they can be expected and integrated into the schedule

in advance. Finally, the project managers should be very proactive and have a great

experience concerning large scale projects in Tunisia.

• The risk of failure to achieve the expected performance

This risk can be caused by the use of tower technology that is not widely used in the MENA

region, as is the case for the parabolic trough technology. It can also be caused by the use of

dry cooling that has not been widely experienced yet. In addition, there is a lack of experience

feedback in Tunisia, since it is the first CSP project of a large size.

In order to reduce this risk, feedback from similar projects will be very useful. In fact, the

CSP tower technology is used today in several countries, such as India, Spain, South Africa

and the USA. Recently, the project Noor III using the same technology (CSP tower with

molten salt storage) has been successfully implemented, which will help us to have a very

interesting feedback from a country very similar to Tunisia. The conclusion of insurance

Page 32: Risk management and policy implications for concentrating

31

contracts, the use of internationally renowned suppliers and the use of preventive and regular

maintenance are also highly recommended.

• The risk of insufficient access to capital

This risk is caused by the high cost of capital, the short pay-back periods of credits and the

lack of private sector participation. This risk is very common in many developing countries

and can be reduced by the following measures:

-Strengthening the public private partnerships (PPP) to finance large CSP projects. In fact,

PPP are an interesting solution for Tunisia, which suffers from serious budgetary constraints

and does not have the means either to cover the financial losses of public enterprises or to

invest in the renovation and extension of its electricity network. To ensure the success of PPP,

Tunisia must put in place a strong business climate that attracts investors. This requires

reducing administrative procedures to access markets, establishing a solid and stable financial

system and appealing to international assistance funds, such as the Public-Private

Infrastructure Advisory Facility (PPIAF).

-The implementation of feed-in tariff mechanism. This mechanism was very effective, in

many countries, both in stimulating installed capacity and in developing local industry. In

fact, tariffs should be set at a level that ensures the cost-effectiveness of RE projects. As a

result, the market risk incurred by the project developer is inexistent and the profitability of

the project depends essentially on cost control and attainment of maximum performance.

-Requesting the assistance and the support from international financial institutions and

development agencies to reduce the costs of financing this project. In fact, they generally

offer low-rate loans for longer periods compared to commercial banks.

• The risk of conflicts with local residents

This risk can be caused by the opposition to the implementation of the CSP plant and

nimbyism. In order to reduce this risk, we propose the following measures:

-The use of participatory approaches which have several advantages. First of all, the

participation of the various actors in the decision-making process gives some legitimacy and

transparency to this decision and thus reduces the risk of non-acceptance of the decision by

these same actors. In addition, the participatory approach allows decision-makers to have

access to a very interesting database that concerns the preferences and expectations of

different actors, especially, in terms of local employment and development of the region. In

Page 33: Risk management and policy implications for concentrating

32

fact, it is essential to organize public consultations to collect the different issues and the main

occupations of the local population and discuss these concerns with stakeholders in order to

satisfy the expectations of the citizens.

-The creation of local employment is recommended. Local employees must be privileged,

especially, during the construction phase which requires a high number of low-skilled

workers. Indeed, the project can increase the activity of small and medium-sized local firms

for the supply of the materials and the necessary equipments for the construction work, the

housing and the restoration of the workers. Hence, it is also highly recommended to set up an

employment commission to study the best way to promote local employment and organize

short-term training for young graduates in order to acquire new skills and qualifications

required for this project, while trying to achieve parity between the employment of women

and men.

-The communication about the RE sector must be adequate and effective. Indeed, citizens and

all the actors involved in the RE sector should have the necessary and up-to-date information

on the objectives of the government, the means implemented, the regulatory and legal

framework, and the achievements made. In order to ensure such communication, an updated

website, discussion forums, and workshops at national and regional levels should be set up.

7. Conclusion

The application of the GRA method for the case of a CSP plant in Tunisia helped us to

analyze in depth, the types of hazards that most affect the project, the phase of the project that

is the most vulnerable to hazards, and the major risks that hinder its implementation.

The results of the analysis by generic hazard type show that the project is very exposed to

political, physical-chemical, financial, and strategic hazards. The political hazard generates

30% of all hazardous situations, which means that the political situation in Tunisia has a

negative influence on the realization of this project. The Kiviat diagram shows that, even

though the legal hazard generates only 2 hazardous situations, it should be taken very

seriously by investors since risks resulting from this hazard have the minimum, medium and

maximum risk indexes of C3 criticality (unacceptable).

With regard to the analysis per project phase (feasibility study, preparation, construction, and

operation), the two phases of preparation and operation contain the highest shares of

hazardous situations, which makes them more exposed to the 14 generic hazards than the

feasibility study and the construction phases. The Kiviat diagram demonstrates that, among

Page 34: Risk management and policy implications for concentrating

33

the four phases, only the initial risks arising from the preparation phase have an average risk

index of C3 criticality. This further proves the vulnerability of this phase, which requires

more attention than the other three phases. In fact, this phase encompasses all administrative

procedures relating to authorizations for the construction and connection to the electricity grid

and may even last for many years. In Tunisia, the case is even more serious as the project has

been blocked in this phase for more than 6 years.

In addition to that, the GRA enabled us to identify the list of major risks that may affect the

CSP project which are: the risk of not obtaining permission to build the CSP plant, the risk of

non compliance with the deadline, the risk of failure to achieve the expected performance, the

risk of insufficient access to capital, and the risk of conflicts with local residents. Then, their

causes and the main actions proposed to reduce them are explained. In fact, in order to reduce

these investment risks, we have proposed many measures and strategies, such as the

strengthening of the public private partnership to finance this project, the use of participatory

approaches, the creation of local employment, and the recourse to international financial

institutions and development agencies to reduce the costs of the project.

The list of top risks identified in the present study is in line with many studies dealing with

barriers to CSP investment in the MENA region which pointed out the importance of

financing barriers, the bureaucracy and corruption, and the regulatory risk (Komendantova et

al., 2011, 2012; Lilliestam et al., 2012).

However, we found that the risk of conflicts with local residents is a major risk that should be

taken into account. This result is in contrast with the analysis of Hanger et al. (2016). We can

explain this difference by the fact that the electricity produced by the CSP plant studied in this

paper is intended for exports while the other cases deal with CSP plants producing electricity

to strengthen the national grid and satisfy the national demand. In fact, producing electricity

to be totally exported is seen by many citizens as an exploitation of national energy resources

by the countries of the North.

We also found that the risk of failure to achieve the expected performance because of the use

of tower technology with dry cooling is a major risk, which is in contrast with the result found

by Trabelsi et al. (2016). This contrast can be explained by the fact that these authors treated

parabolic trough technology, which is a more mature and used technology than tower

technology that will be used for the CSP studied in this paper.

Page 35: Risk management and policy implications for concentrating

34

It should be noted that, over the past few years, Tunisia has begun many structural changes in

the RE sector in order to de-risk and promote this sector. In fact, a new law for RE was

approved in 2015. This law authorizes the exportation of electricity from RE and encourages

citizens and local communities to produce green electricity. However, the distribution of

electricity remains under the monopoly of STEG.

Furthermore, in order to create a favorable climate for PPP, a new law for PPP was adopted in

2015. This law is supposed to facilitate, clarify and organize PPP procedures and, above all,

ensure an efficient management of the contractual risks that are frequent in this complex type

of contracts. Therefore, the objective of this law is to provide a unified legislative and

institutional framework that encourages private investors.

Even though Tunisia has made some progress, mainly in terms of legal framework, there are

still several challenges and obstacles that slow down the development of CSP technology and

RE in general as it is demonstrated by the present analysis.

However, like any research work, this study has limitations. Indeed, it is limited to a semi-

quantitative study (since there are the severity and likelihood indexes). In addition, it remains

general with no focus on financial risks, which are among the most serious and worrying risks

for investors in the RE sector.

Although, it is very important to use the GRA method at the beginning of a project to give an

overall view of the risks that may occur, this is not enough since the GRA should also

accompany the whole life of the project and therefore must be revised and completed as the

project progresses. The other disadvantage of this method lies in the subjectivity in risk

assessment. Indeed, the estimation of the likelihood of occurrence and the severity of

consequences in order to deduce the criticality remains a very subjective process.

In addition, this case study cannot be generalized to all CSP projects in Tunisia, since each

CSP project remains unique and different and has specific risks, but this study remains very

important and gives a general and an approximate idea of the barriers that may be encountered

by future CSP investors in Tunisia.

In order to overcome these limitations, in future research studies, it will be highly

recommended to complete this research by the quantitative AGR method (AGRq). The use of

this method will be very interesting in the case of availability of probabilities related to risk

factors. The main contribution of this method is the possibility of having a probabilistic

representation of the risks and a financial evaluation of the cost/risk ratios.

Page 36: Risk management and policy implications for concentrating

35

Acknowledgments

We are especially grateful to Prof. Alain Desroches from Ecole Centrale Paris who

generously shared with us his knowledge on risk management and Global Risk Analysis

method as well as to Dr. Sébastien Delmotte from MAD Environnement (www.mad-

environnement.com) for his helpful suggestions and practical advice about the use of the

SATATCART GRA software.

Appendixes. Supplementary material

References

Amato, A., Compare, M., Gallisto, M., Maccari, A., Paganelli, M., Zio, E., 2011. Business

interruption and loss of assets risk assessment in support of the design of an innovative

concentrating solar power plant. Renew. Energy 36, 1558–1567.

Arentsen, M., Kemp, R., Luiten, E., 2002. Technological change and innovation for climate

protection: The governance challenge, in: Kok, M., Vermeulen, W., Faaij, A., De Jager,

D. (Eds.), Global Warming and Social Innovation: The Challenge of a Climate Neutral

Society. Earthscan, London, pp. 59–82.

Arthur, B., 1989. Competing technologies: Increasing returns and lock-in by historical events.

Econ. J. 99, 116–131.

Arthur, B., 1994. Increasing Returns and Path Dependence in the Economy, first ed.

University of Michigan Press, Ann Arbor.

Astolfi, M., Binotti, M., Mazzola, S., Zanellato, L., Manzolini, G., 2017. Heliostat aiming

point optimization for external tower receiver. Sol. Energy 157, 1114–1129.

Ayres, R.U., 1991. Evolutionary economics and environmental imperatives. Struct. Chang.

Econ. Dyn. 2, 255–273.

Balghouthi, M., Trabelsi, S.E., Ben Amara, M., Bel Hadjali, A., Guizani, A., 2016. Potential

of concentrating solar power (CSP) technology in Tunisia and the possibility of

interconnection with Europe. Renew. Sustain. Energy Rev. 56, 1227–1248.

Belgasim, B., Aldali, Y., Abdunnabi, M.J.R., Hashem, G., Hossin, K., 2018. The potential of

concentrating solar power (CSP) for electricity generation in Libya. Renew. Sustain.

Energy Rev. 90, 1–15.

Page 37: Risk management and policy implications for concentrating

36

Böhringer, C., Cuntz, A., Harhoff, D., Asane-Otoo, E., 2017. The impact of the German feed-

in tariff scheme on innovation: Evidence based on patent filings in renewable energy

technologies. Energy Econ. 67, 545–553.

Brand, B., Stambouli, A.B., Zejli, D., 2012. The value of dispatchability of CSP plants in the

electricity systems of Morocco and Algeria. Energy Policy 47, 321–331.

Cowan, R., 1990. Nuclear power reactors: A study in technological lock-in. J. Econ. Hist. 50,

541–567.

David, P.A., 1985. Clio and the economics of QWERTY. Am. Econ. Rev. 75, 332–337.

Davis, S.J., Caldeira, K., Matthews, H.D., 2010. Future CO2 emissions and climate change

from existing energy infrastructure. Science 329, 1330–1333.

del Río, P., Peñasco, C., Mir-Artigues, P., 2018. An overview of drivers and barriers to

concentrated solar power in the European Union. Renew. Sustain. Energy Rev. 81,

1019–1029.

Desroches, A., 2013. Le management des risques par l’analyse globale des risques. Transfus.

Clin. Biol. 20, 198–210.

Desroches, A., Aguini, N., Dadoun, M., Delmotte, S., 2016. L’Analyse Globale des Risques_

Principes et Pratiques, deuxième ed. Hermès Science Publications, Paris.

Dosi, G., 1982. Technological paradigms and technological trajectories: A suggested

interpretation of the determinants and directions of technical change. Res. Policy 11,

147–162.

Elum, Z.A., Momodu, S., 2017. Climate change mitigation and renewable energy for

sustainable development in Nigeria: A discourse approach. Renew. Sustain. Energy

Rev. 76, 72–80.

Fragkos, P., Paroussos, L., 2018. Employment creation in EU related to renewables

expansion. Appl. Energy 230, 935–945.

Freeman, C., Soete, L., 1997. The Economics of Industrial Innovation, third ed. MIT Press,

Cambridge.

Frisari, G., Stadelmann, M., 2015. De-risking concentrated solar power in emerging markets:

The role of policies and international finance institutions. Energy Policy 82, 12–22.

Page 38: Risk management and policy implications for concentrating

37

Gabriel, C-A., 2016. What is challenging renewable energy entrepreneurs in developing

countries? Renew. Sustain. Energy Rev. 64, 362–371.

Goh, T., Ang, B.W., 2018. Quantifying CO2 emission reductions from renewables and

nuclear energy – Some paradoxes. Energy Policy 113, 651–662.

González, M.O.A., Gonçalves, J.S., Vasconcelos, R.M., 2017. Sustainable development: Case

study in the implementation of renewable energy in Brazil. J. Clean. Prod. 142, 461–

475.

Haas, J., Palma-Behnke, R., Valencia, F., Araya, P., Díaz-Ferrán, G., Telsnig, T., Eltrop, L.,

Díaz, M., Püschel, S., Grandel, M., Román, R., Jiménez-Estévez, G., 2018. Sunset or

sunrise? Understanding the barriers and options for the massive deployment of solar

technologies in Chile. Energy Policy 112, 399–414.

Hanger, S., Komendantova, N., Schinke, B., Zejli, D., Ihlal, A., Patt, A., 2016. Community

acceptance of large-scale solar energy installations in developing countries: Evidence

from Morocco. Energy Res. Soc. Sci. 14, 80–89.

Hustveit, M., Frogner, J.S., Fleten, S-E., 2017.Tradable green certificates for renewable

support: The role of expectations and uncertainty. Energy 141, 1717–1727.

IEA, 2007. World Energy Outlook 2007, China and India Insights. International Energy

Agency, Paris.

IEA, 2010. Technology Roadmap-Concentrating Solar Power. International Energy Agency.

https://www.iea.org/publications/freepublications/publication/csp_roadmap.pdf

(accessed 13 February 2014).

IEA, 2011. World Energy Outlook 2011. International Energy Agency.

www.iea.org/publications/freepublications/publication/WEO2011_WEB.pdf (accessed

7 January 2012).

IEA, 2014. Technology Roadmap: Solar Thermal Electricity. International Energy Agency.

https://www.iea.org/publications/freepublications/publication/TechnologyRoadmapSola

rThermalElectricity_2014edition.pdf (accessed 3 October 2018).

IPCC, 2007. Climate Change 2007: Impacts, Adaptation and Vulnerability. Contribution of

Working Group II to the Fourth Assessment Report of the Intergovernmental Panel on

Climate Change. Intergovernmental Panel on Climate Change, Cambridge, United

Kingdom and New York, USA.

Page 39: Risk management and policy implications for concentrating

38

IRENA Resource, 2018. International Renewable Energy Agency Resource.

http://resourceirena.irena.org/gateway/dashboard/?topic=4&subTopic=16 (accessed 19

September 2018).

IRENA, 2018. Renewable Power Generation Costs in 2017. International Renewable Energy

Agency, Abu Dhabi.

Joskow, P.L., 2011. Comparing the costs of intermittent and dispatchable electricity

generating technologies. Am. Econ. Rev. 101, 238–241.

Kemp, R., 1994. Technology and the transition to environmental sustainability: The problem

of technological regime shifts. Futures 26, 1023–1046.

Komendantova, N., Patt, A., Williges, K., 2011. Solar power investment in North Africa:

Reducing perceived risks. Renew. Sustain. Energy Rev. 15, 4829–4835.

Komendantova, N., Patt, A., Barras, L., Battaglini, A., 2012. Perception of risks in renewable

energy projects: The case of concentrated solar power in North Africa. Energy Policy

40, 103–109.

Kost, C., Pfluger, B., Eichhammer, W., Ragwitz, M., 2011. Fruitful symbiosis: Why an export

bundled with wind energy is the most feasible option for North African concentrated

solar power. Energy Policy 39, 7136–7145.

Kost, C., Engelken, M., Schlegl, T., 2012. Value generation of future CSP projects in North

Africa. Energy Policy 46, 88–99.

Labordena, M., Patt, A., Bazilian, M., Howells, M., Lilliestam, J., 2017. Impact of political

and economic barriers for concentrating solar power in Sub-Saharan Africa. Energy

Policy 102, 52–72.

Liebowitz, S.J., Margolis, S.E., 1995. Path dependence, lock-in and history. J. L. Econ. &

Org. 11, 205–226.

Lilliestam, J., Bielicki, J. M., Patt, A.G., 2012. Comparing carbon capture and storage (CCS)

with concentrating solar power (CSP): Potentials, costs, risks, and barriers. Energy

Policy 47, 447–455.

Lilliestam, J., Barradi, T., Caldés, N., Gomez, M., Hanger, S., Kern, J., Komendantova, N.,

Mehos, M., Hong, W.M., Wang, Z., Patt, A., 2018. Policies to keep and expand the

Page 40: Risk management and policy implications for concentrating

39

option of concentrating solar power for dispatchable renewable electricity. Energy

Policy 116, 193–197.

Mahia, R., de Arce, R., Medina, E., 2014. Assessing the future of a CSP industry in Morocco.

Energy Policy 69, 586–597.

Mattauch, L., Creutzig, F., Edenhofer, O., 2015. Avoiding carbon lock-in: Policy options for

advancing structural change. Econ. Model. 50, 49–63.

Mazeron, R., Aguini, N., Rivin, E., Baudré, A., Bour, M-S., Dumas, I., Hubert, F., Lopes, S.,

Desroches, A., Deutsch, E., Lefkopoulos, D., Bourhis, J., 2014. Improving safety in

radiotherapy: the implementation of the Global Risk Analysis method. Radiother.

Oncol. 112, 205-211.

Medina, E., de Arce, R., Mahía, R., 2015. Barriers to the investment in the Concentrated Solar

Power sector in Morocco: A foresight approach using the Cross Impact Analysis for a

large number of events. Futures 71, 36–56.

Mekhilef, S., Saidur, R., Safari, A., 2011. A review on solar energy use in industries. Renew.

Sustain. Energy Rev. 15, 1777–1790.

Menanteau, P., Finon, D., Lamy, M-L., 2003. Prices versus Quantities: choosing policies for

promoting the development of renewable energy. Energy Policy 31, 799–812.

Mezher, T., Dawelbait, G., Abbas, Z., 2012. Renewable energy policy options for Abu Dhabi:

Drivers and barriers. Energy Policy 42, 315–328.

Nelson, R.R., Winter, S.G., 1977. In search of useful theory of innovation. Res. Policy 6, 36–

76.

Nock, D., Baker, E., 2017. Unintended consequences of Northern Ireland’s renewable

obligation policy. The Electricity Journal 30, 47–54.

OECD, 2012. Linking Renewable Energy to Rural Development, OECD Publishing.

www.oecd.org/regional/regional-policy/Renewable-rural-energy-summary.pdf

(accessed 25 November 2018).

Omri, E., Chtourou, N., Bazin, D., 2015a. Rethinking the green recovery through renewable

energy expansion. Int. J. Sustain. Dev. 18, 59–76.

Page 41: Risk management and policy implications for concentrating

40

Omri, E., Chtourou, N., Bazin, D., 2015b. Solar thermal energy for sustainable development

in Tunisia: The case of the PROSOL project. Renew. Sustain. Energy Rev. 41, 1312–

1323.

Otieno, G.A., Loosen, A.E., 2016. An analysis of key environmental and social risks in the

development of concentrated solar power projects. AIP Conference Proceedings 1734,

160012.

Painuly, J.P., 2001. Barriers to renewable energy penetration: a framework for analysis.

Renew. Energy 24, 73–89.

Perkins, R., 2003. Technological Lock-in. International Society for Ecological Economics,

Internet Encyclopedia of Ecological Economics. http://isecoeco.org/pdf/techlkin.pdf

(accessed 23 July 2015).

Pfenninger, S., Gauche, P., Lilliestam, J., Damerau, K., Wagner, F., Patt, A., 2014. Potential

for concentrating solar power to provide baseload and dispatchable power. Nat. Clim.

Change 4, 689–692.

Pietzcker, R.C., Stetter, D., Manger, S., Luderer, G., 2014. Using the sun to decarbonize the

power sector: the economic potential of photovoltaics and concentrating solar power.

Appl. Energy 135, 704–720.

Pinkse, J., Buuse, D.V.D., 2012. The development and commercialization of solar PV

technology in the oil industry. Energy Policy 40, 11–20.

Poullikkas, A., Hadjipaschalis, I., Kourtis, G., 2010. The cost of integration of parabolic

trough CSP plants in isolated Mediterranean power systems. Renew. Sustain. Energy

Rev. 14, 1469–1476.

REN21, 2018. Renewables 2018: Global Status Report. Renewable Energy Policy Network

for the 21st Century. http://www.ren21.net/wp-content/uploads/2018/06/17-

8652_GSR2018_FullReport_web_final_.pdf (accessed 15 September 2018).

Rip, A., Kemp, R., 1998. Technological change, in: Rayner, S., Malone, E. (Eds.), Human

Choice and Climate Change-Volume 2: Resources and Technology. Battelle Press,

Columbus, pp. 327–399.

Schinko, T., Komendantova, N., 2016. De-risking investment into concentrated solar power in

North Africa: Impacts on the costs of electricity generation. Renew. Energy 92, 262–

272.

Page 42: Risk management and policy implications for concentrating

41

Schmidt, R.C., Marschinski, R., 2009. A model of technological breakthrough in the

renewable energy sector. Ecol. Econ. 69, 435–444.

Sindhu, S.P., Nehra, V., Luthra, S., 2016. Recognition and prioritization of challenges in

growth of solar energy using analytical hierarchy process: Indian outlook. Energy 100,

332–348.

Stadelmann, M., Frisari, G., Konda, C., 2014. The Role of Public Finance in CSP: Case Study

Rajasthan Sun Technique. Climate Policy Initiative, India.

http://climatepolicyinitiative.org/wp-content/uploads/2014/03/SGG-Case-Study-The-

Role-of-Public-Finance-in-CSP-Rajasthan-Sun-Technique-India.pdf (accessed 7 April

2016).

Trabelsi, S.E., Chargui, R., Qoaider, L., Liqreina, A., Guizani, A.A., 2016. Techno-economic

performance of concentrating solar power plants under the climatic conditions of the

southern region of Tunisia. Energy Convers. Manag. 119, 203–214.

Trieb, F., Müller-Steinhagen, H., Kern, J., 2011. Financing concentrating solar power in the

Middle East and North Africa—subsidy or investment? Energy Policy 39, 307–317.

Trieb, F., Schillings, C., Pregger, T., O’Sullivan, M., 2012. Solar electricity imports from the

Middle East and North Africa to Europe. Energy Policy 42, 341–353.

Trieb, F., Fichter, T., Moser, M., 2014. Concentrating solar power in a sustainable future

electricity mix. Sustain. Sci. 9, 47–60.

Unruh, G.C., 2000. Understanding carbon lock-in. Energy Policy 28, 817–830.

Unruh, G.C., 2002. Escaping carbon lock-in. Energy Policy 30, 317–325.

Viebahn, P., Lechon, Y., Trieb, F., 2011. The potential role of concentrated solar power

(CSP) in Africa and Europe: a dynamic assessment of technology development, cost

development and life cycle inventories until 2050. Energy Policy 39, 4420–4430.

Wiesinger, F., Sutter, F., Wolfertstetter, F., Hanrieder, N., Fernández-García, A., Pitz-Paal,

R., Schmücker, M., 2018. Assessment of the erosion risk of sandstorms on solar energy

technology at two sites in Morocco. Sol. Energy 162, 217–228.

Williges, K., Lilliestam, J., Patt, A., 2010. Making concentrated solar power competitive with

coal: the costs of a European feed-in tariff. Energy Policy 38, 3089–3097.

Page 43: Risk management and policy implications for concentrating

42

Xin-gang, Z., Ling-zhi, R., Yu-zhuo, Z., Guan, W., 2018. Evolutionary game analysis on the

behavior strategies of power producers in renewable portfolio standard. Energy 162,

505–516.

Xu, X., Vignarooban, K., Xu, B., Hsu, K., Kannan, A.M., 2016. Prospects and problems of

concentrating solar power technologies for power generation in the desert regions.

Renew. Sustain. Energy Rev. 53, 1106–1131.

Zongxian, Z., Yang, W., Xiaofei, S., Ming, Z., 2012. Risk assessment of concentrating solar

power based on fuzzy comprehensive evaluation. Syst. Eng. Procedia 4, 99–106.

Page 44: Risk management and policy implications for concentrating

43

Appendix A. The CSP project depicted in steps, phases and sub-phases.

Steps Phases Sub-phases

Feasibility study (A) Site identification Determining available sites

Site selection

Resource estimation Estimation of solar radiation

Estimation of the electricity generated

Estimation of the possibility of connection Estimation of power that can be connected to the grid

Determining interconnection costs

Economic study Project cost estimate

Estimation of potential demand

Estimation of the project profitability

Environmental study Study of the geological characteristics of the site

Preparation (B) Technical study Solar resource characterization

Fixing the technical characteristics of the mirrors used

Determining the necessary equipments

Environmental and social study Study of environmental impacts

Study of social impacts

Selection of partners Identification of partners

Sharing roles

Coordination between partners

Creation of a project team

Elaboration of a financing plan Determination of the overall cost of the project

Identification of available financial assistance

Determining the amount of potential subsidies

Determining the necessary loans

Fixing the repayment terms

Completing the necessary administrative

procedures

Real estate negotiation

Building permit application

Choosing the legal structure of the project-carrying unit

Signing contracts

Tariff agreement

Determining an action plan Organization of working meetings

Identification of project duration

Determination of construction phases

Determination of start up and completion dates

Mobilization of required human resources Organization of job interviews

Communication Communication with the local community

Project media coverage

Construction (C) Installation Ensuring access roads to the site

Site development

Site water supply

Acquiring the necessary equipments

Solar field's construction

Generator construction

Construction of the energy evacuation device

Construction of the storage structure

Installation of associated infrastructure

Preparing connection to the national electricity grid

Preparing the necessary infrastructure

Implementation of HVDC lines between Tunisia and Italy

Operation (D) Generation of electricity Collection of solar radiation using mirrors

Concentration of the sunlight on a receiver

Heating a heat transfer fluid

Production of heat in the form of steam

Steam drives turbine/generator to produce electricity

Storage of heat in molten salt

Connection to the national electricity grid

Export of electricity to Italy

Loan repayments

Page 45: Risk management and policy implications for concentrating

44

Appendix B. The hazard mapping.

Generic hazards Abbreviation Specific hazards Hazardous events

Political POL International No more world bank support for CSP projects

Decrease in fossil fuel prices

Setting grade by rating agencies

Non-compliance with the European regulatory

framework for electricity

National Bad choice of installation site

Complexity of bureaucratic procedures

Corruption

Bad governance of public enterprises

Political instability

Lack of guarantees from the government

Revolution

Political uncertainty

Increase of subsidies for fossil fuels

Recurrence of strikes and sit-ins in Tunisia

Recurrent changes in government

Uncertain government policies

Lack of transparency

Lack of infrastructure

Environment ENV Natural Sandstorm

The depth of the Mediterranean sea

Strong wind

Erosion

Earthquake

Lightning

Insecurity INS Computer Computer virus

Identity theft

Material Terrorism

Unavailability of equipments

Image IMA Media Lack of media support for the project

Lack of awareness of the benefits of RE

Unfavorable testimonials on social media

Management MAN Organization Bad organization of work

Insufficient site observation period

Unrealistic project implementation schedule

Underestimated time of file’s processing

Delay in construction

Unavailability of project managers

Human resources Technical consultants not experienced in the

field of large projects

Insufficient staff training

Poor proficiency in English

Poor proficiency in Arabic

Non-recruitment of local staff

Poor knowledge of the activity

Human factor Failure to follow safety instructions

Uncomfortable working conditions

Bad decision

Overwork

Stress

Strategic STR Cooperation Poor cooperation with the African Development

Bank

Poor cooperation with the energy transition fund

Page 46: Risk management and policy implications for concentrating

45

Poor cooperation with the World Bank

Bad choice of partners

Poor cooperation with STEG-ER

Poor cooperation with local authorities

Technological TECH Process Poor choice of the technology used

A technology at R&D stage

Computer Very complicated hardware

Communication

and crises

COM Internal Absence of crisis communication unit

Lack of a participatory approach

Lack of written communication

Poor management of alerts

Lack of schematic panels

External Poor relationship with local residents and the

local community

Poor relationship with partners (conflicts of

interest)

Lack of communication about safety

instructions to local residents

Lack of communication about the project's

benefits

Poor involvement of stakeholders in decision

making

Legal LEG Criminal liability Legal action by the local population

Lack of precision in contracts

Non-compliance with terms and conditions of

contracts

Civil liability Absence of regulatory compliance

Regulation Lack of a stable legal framework

Regulatory framework does not allow export of

RE electricity

Internal rules Failure to comply with internal terms

Non respect of charters (landscape charter or

others)

Financial FIN Subsidies Delay or absence of subsidies

Credits Inability to repay credits

Increase in the interest rate

Exchange rate fluctuation

Delay in obtaining credits

Budget High investment cost

Inflation

Poor estimate of predicted budget

Under-estimated construction cost

Expenses Unexpected expenses

Infrastructure and

premises

INFRA Premises Premises unsuitable for the storage of fragile

products

Premises unsuitable for the storage of hazardous

products

Materials and

equipment

MAT Logistical Telephone network failure

Defective pieces

Absence / Mismanagement of stocks

Absence / Mismanagement of warehouses

Maintenance Absence of preventive maintenance

Absence of maintenance fund

Mismanagement of preventive maintenance

Page 47: Risk management and policy implications for concentrating

46

Information

system

IS Network Internet connection cut

Data Incomplete or wrong data

Data classification error

Loss of files

Poor experience feedback

Unavailability of data

Failure to anonymize data

System System does not respond to the situation reality

Software Very complicated software

physical/chemical PCH Electrical Overvoltage

Power cut

Insufficient electricity

Mechanical Noise

Fall

Explosion

Vibration

Thermal Fire

Hot spot

Hydraulic Overpressure

Leakage

Breakage

Chemical Pollution

Corrosion

Chemical reaction

Explosion

Oxidation

Flammability

Biological Toxicity

Page 48: Risk management and policy implications for concentrating

47

Appendix C. Mapping_HS

Cartography and risk management of a concentrated solar power plant Feasibility study (A) Preparation (B) Construction (C) Operation (D)

33 62 74

Sit

e id

enti

fica

tion

Res

ou

rce

Est

imat

ion

Est

imat

ion

of

the

po

ssib

ilit

y o

f co

nn

ecti

on

Eco

no

mic

stu

dy

Env

iro

nm

enta

l st

udy

Tec

hnic

al s

tudy

Env

iro

nm

enta

l an

d s

oci

al

study

Sel

ecti

on

of

par

tner

s

Ela

bo

rati

on

of

a fi

nan

cing

pla

n

Co

mp

lete

the

nec

essa

ry

adm

inis

trat

ive

pro

ced

ure

s

Det

erm

inin

g a

n a

ctio

n

pla

n

Mobil

izat

ion

of

hu

man

reso

urc

es

req

uir

ed

Co

mm

un

icat

ion

Inst

alla

tion

Pre

par

atio

n o

f th

e co

nn

ecti

on t

o t

he

nat

ion

al e

lect

rici

ty g

rid

Pre

par

ing

the

nec

essa

ry i

nfr

astr

uct

ure

Imp

lem

enta

tion

of

HV

DC

lin

es b

etw

een

Tun

isia

an

d I

taly

Gen

erat

ion

of

elec

tric

ity

Conn

ecti

on

to

th

e n

atio

nal

ele

ctri

city

gri

d

Exp

ort

of

elec

tric

ity

to

Ita

ly

Lo

an r

epay

men

ts

GENERIC HAZARDS SPECIFIC HAZARDS DANGEROUS EVENTS OR ELEMENTS

Det

erm

inin

g a

vai

lab

le s

ites

Sit

e se

lect

ion

Est

imat

ion

of

sola

r ra

dia

tion

Est

imat

ion

of

the

elec

tric

ity

gen

erat

ed

Est

imat

ion

of

po

wer

that

can

be

connec

ted

to t

he

gri

dD

iscu

ssio

n w

ith

th

e n

etw

ork

op

erat

or

on

inte

rcon

nec

tio

n c

ost

s

Pro

ject

co

st e

stim

ate

Est

imat

ion

of

po

tenti

al d

eman

d

Est

imat

ion

of

the

pro

ject

pro

fita

bil

ity

Stu

dy o

f th

e g

eolo

gic

al c

har

acte

rist

ics

of

the

site

So

lar

reso

urc

e ch

arac

teri

zati

on

Fix

ing

the

tech

nic

al c

har

acte

rist

ics

of

the

mir

rors

use

d

Det

erm

inin

g t

he

nec

essa

ry e

quip

men

t

Stu

dy o

f en

vir

on

men

tal

imp

acts

Stu

dy o

f so

cial

im

pac

ts

Iden

tifi

cati

on

of

par

tner

s

Sh

arin

g r

ole

s

Org

aniz

atio

n o

f co

ord

inat

ion

bet

wee

n

par

tner

s

Cre

ate

a p

roje

ct t

eam

Det

erm

inat

ion

of

the

over

all

cost

of

the

pro

ject

Iden

tifi

cati

on

of

avai

lable

fin

anci

al

assi

stan

ceD

eter

min

ing

the

amoun

t o

f po

tenti

al

sub

sid

ies

Det

erm

inin

g t

he

nec

essa

ry l

oan

s

Fix

ing

the

rep

aym

ent

term

s

Rea

l es

tate

neg

oti

atio

n

Buil

din

g p

erm

it a

pp

lica

tion

Th

e ch

oic

e o

f th

e le

gal

str

uct

ure

of

the

pro

ject

-car

ryin

g u

nit

Sig

nin

g c

on

trac

ts

Tar

iff

agre

emen

t

Org

aniz

atio

n o

f w

ork

ing

mee

tin

gs

Iden

tifi

cati

on

of

pro

ject

du

rati

on

Det

erm

inat

ion

of

con

stru

ctio

n p

has

es

Det

erm

inat

ion

of

star

t up

and

com

ple

tion

dat

es

Org

aniz

atio

n o

f jo

b i

nte

rvie

ws

Co

mm

un

icat

ing w

ith t

he

loca

l co

mm

unit

y

Pro

ject

med

iati

zati

on

Sel

ecti

on

of

a dev

elop

er i

n c

har

ge

of

con

stru

ctio

n

En

sure

acc

ess

road

s to

th

e si

te

Sit

e dev

elop

men

t

Sit

e w

ater

su

pp

ly

Acq

uir

ing

the

nec

essa

ry e

qu

ipm

ent

So

lar

fiel

d's

con

stru

ctio

n

Gen

erat

or

con

stru

ctio

n

Con

stru

ctio

n o

f th

e en

ergy

ev

acu

atio

n

dev

ice

Con

stru

ctio

n o

f th

e st

ora

ge

stru

ctu

re

Inst

alla

tion

of

asso

ciat

ed i

nfr

astr

uct

ure

Coll

ecti

on o

f so

lar

rad

iati

on

usi

ng

mir

rors

Con

centr

atio

n o

f th

e fl

ux

on

a r

ecei

ver

Th

e re

ceiv

er h

eats

a h

eat

tran

sfer

flu

id

Pro

du

ctio

n o

f hea

t in

the

form

of

stea

m

Ste

am d

rives

tu

rbin

e/gen

erat

or

to p

rod

uce

elec

tric

ity

Sto

rag

e o

f hea

t in

molt

en s

alt

Political

International

No more world bank support to CSP projects 10 10

Decrease in fossil fuel price 10 10

10

Rating agencies 2 1

Non-compliance with the European regulatory framework for electricity 2 1

National

Bad choice of installation site 10 2 2 2 10

The complexity of bureaucratic procedures 2 2 1 10

Corruption 10 10

Bad governance of public entreprises 1 1 2

Political instability

Lack of guarantees from government 2 10

1

2

Revolution 2

Political incertainty

Increase in subsidies for fossil fuels 10 2

Recurrence of strikes and sit-ins in Tunisia 10 1

Recurrent changes in government 10 1

Absence of decision or late decision by the tunisian government 1 2

Lack of transparency 10 10

Absence or delay of decisions on improving access roads 10 1

Environment Natural

Sandstorm 1

The depth of the Mediterranean sea 1 10 10

Strong Wind 10 2 2 2

erosion

Earthquake

Lightning

Insecurity

Computer Computer virus 2 10

Identity theft 2

Material Terrorism 2 10 2 1

Theft of equipment

Image Media

Lack of media support for the project 10 2

1 Lack of awareness of the benefits of renewable energies 2

Unfavorable testimonials on social networks 2

Management

Organization

Bad organization of work 2 10 2 10

Insufficient site observation period 1 10

Unrealistic project implementation schedule 2

10 10 2

Underestimated time of file's processing 2

Delay in construction 2 2

Unavailability of project managers 10 2

Human ressources

Technical consultants not experienced in the field of large projects 10 10

Insufficient staff training 2

Poor proficiency in English 10

Poor proficiency in Arabic 2

Non-recruitment of local staff 2

Poor knowledge of the activity

Human factor

Failure to follow safety instructions 10

Uncomfortable working conditions

Bad decision 10 1

Overwork 2

Stress

Strategic Cooperation

Poor cooperation with the African Development Bank

Poor cooperation with the energy transition fund 2 2 2

Poor cooperation with Desertec 2

Poor cooperation with World Bank 2

Bad choice of partners 2 2

Poor cooperation with STEG-ER 1 1 1

Poor cooperation with local authorities 10

Technological Process

Poor choice of the technology used 2 2

A technology at R&D stage 1

Computer Very complicated hardware

Communication and Crises Internal

Absence of crisis communication unit

Lack of a participatory approach 2 2

Lack of written communication

Poor management of alerts

Lack of schematic panels 10

External Poor relationship with local residents and the local community 1

Page 49: Risk management and policy implications for concentrating

48

Poor relationship with partners (conflicts of interest) 10

Lack of communication of safety instructions to local residents 2 2 10

Lack of communication about the project's benefits

Poor coordination with funders 10 10 10 10

Legal

Criminal liability

Legal action by the local population

Lack of precision in contracts 10 2

Non compliance with terms of contracts with partners 2

Civil liability Absence of regulatory compliance

Regulation Lack of a stable legal framework (for export or import of RE) 10

1 2

1 10 2 2

Regulatory framework does not allow export of RE 2

Internal rules

Failure to comply with internal terms 2

Non respect of charters (eg : landscape charter or other)

Financial

Subsidies Delay or absence of subsidies 2 10 10

Credits

Inability to repay credits 10

Increase in the interest rate 10 1

Exchange rate fluctuation

Delay in obtaining credits 1

Budget

High investment cost 1 2 2

Inflation 2

Poor estimate of predicted budget

Under-estimated construction cost 10

Expenses Unexpected expenses 2 2

Infrastructure and premises Premises Premises unsuitable for the storage of fragile products 2 2

Premises unsuitable for the storage of hazardous products 1

Materials and equipment

Logistical

Telephone network failure

Defective pieces 2 2

Absence / Mismanagement of stocks

Absence / Mismanagement of warehouses 10

Maintenance

Absence of preventive maintenance 10

Absence of maintenance fund

Mismanaged preventive maintenance 1

Computer system

Network Internet connection cut

Data

Incomplete or wrong data 10 10 2

Data classification error 2 2

Loss of files

Poor experience feedback

Unavailability of data 10 2

Failure to anonymize data

System System does not respond to reality of the situation 10

Software Very complicated software 1

Physico-chemical

Electrical

Overvoltage

Power cut

Insufficient electricity

Short circuit

Mechanical

Noise 1 10

Fall 2

Explosion 10 1

Burst pipe

Bad clogging

Vibration

Thermal Fire 10 2

Hot spot

Hydraulic

Overpressure 1

Leakage 2

2

Breakage

Chemical

Pollution 2 1

Corrosion 10

Chemical reaction

Explosion 10

Oxidation

Flammability

Biological Toxicity 10

P1 3 12 8 10 33

P10 15 22 9 16 62

P2 15 24 18 17 74

Page 50: Risk management and policy implications for concentrating

49

Appendix D. Scenario_GRA

Generic Hazard

System Hazardous Situation

Contact Cause Unwanted Event Trigger Cause

Existing risk treatments including detection or alert means

Consequences G i

L i

C i

Risk reduction actions and implementation accountable

PE G r

L r

C r

Management of residual risk

POL A Slow procedures STEG is in a monopoly position

Failure to obtain a construction permit

The Tunisian regulatory framework does not allow the export of renewable energies

Absence of means

45Delay in project implementation

4 4 3

A1 A2 A1: Initiate discussions with government officials to change the regulatory framework and facilitate procedures with STEG A2: The formation of a team of specialists to discuss all the necessary points with the STEG officials.

2 4 2 2

P1 P1: Continuous monitoring of the progress of discussions with the government

MAN A An erroneous estimate of the resource

First experience in the tunisian desert

Overestimation of the project performance

A site observation period of less than one year

Absence of means

54Huge financial loss

5 2 2

A3 A4 A3: Requiring a site observation period of one year A4: Hiring experienced professionals to assess the total energy output of the facility

3 2 2 1

STR A

The requirement of exorbitant costs for connection to the grid

STEG is in a monopoly position

The increase in the cost of the project

The bureaucracy

Absence of means

31Unacceptable performance degradation

3 3 2

A5 A6 A5: The sale of part of the electricity produced to the national market A6: Using the mechanism of feed in tariff

2 2 2 1

POL B The discouragement of private investors

Degradation of Tunisia's sovereign rating by rating agencies

Few financing funds are interested in a project in Tunisia

Political instability

Absence of means

33Significant operational constraints

3 4 2

A7 A8 A7: The choice of solid financial partners A8: The cooperation with the World Bank and the African Development Bank

2 2 3 1

POL B Slow administrative procedures

Poor governance of tunisian public administrations

Delay in granting authorization for the construction of the solar power plant

Recurring changes in government

Absence of means

45Delay in project implementation

4 4 3

A9 A10 A9: To form a team of tunisian experts to accelerate administrative procedures A10: To prepare a plan describing the procedures for obtaining the various permits and authorizations required

2 3 3 2

P2 P2 : To establish a checklist of the various permits and authorizations required

Page 51: Risk management and policy implications for concentrating

50

POL B An unreliable action plan

Lack of transparency

An unfeasible action plan

The tunisian revolution

Absence of means

12Acceptable operational constraints

1 5 1

POL B Lack of visibility in the short and medium term

Political uncertainty

No detailed and final action plan

Regulatory barriers

Absence of means

33Significant operational constraints

3 4 2 A11 A11: Continuous adjustment of the action plan

2 2 3 1

POL B Slow administrative procedures

Lack of a clear political commitment for renewable energies promotion

An increase in the project cost

Lack of transparency

Absence of means

31Unacceptable performance degradation

3 5 3

A12 A13 A12: The formation of a crisis unit in charge of communication with the political decision-makers and the public administrations A13: To minimize expenses during the preparation phase (travel, premises...)

2 3 3 2

P3 P3 : To implement a procedure for continuous monitoring and evaluation of progress in administrative procedures

POL B An increase in the project cost

Increase in spending

Increase in capital spending

Lack of political will

Absence of means

54Huge financial loss

5 3 3

A14 A15 A14: Minimize all costs in the preparation phase A15: Decrease the number of staff during the preparation phase

2 3 3 2

P4 P4 : To establish a plan for monitoring the application of austerity procedures

ENV B Lack of experience feedback

The first project for the transmission of electricity with a depth of 2,000 m

Uncertainty about the success of this first experience

Technology in research and development phase

Absence of means

32Very degraded or failed activity

3 3 2

A16 A16 : Obtain manufacturer's necessary warranties that HVDC cables support the 2,000 m depth

2 2 2 1

MAN B Wrong choice of cooling system

Taking into account only the environmental aspect

The choice of dry cooling which is less effective than wet cooling

Water scarcity in the desert

Absence of means

33Significant operational constraints

3 4 2 A17 A17: Continuous monitoring of the efficiency of dry cooling

2 2 2 1

STR B Delay in signing contracts

STEG is in a monopoly position

Failure to meet deadlines

Poor estimation of file processing time

Absence of means

33Significant operational constraints

3 3 2

A18 A18: Develop clear contracts that define in detail the responsibilities of each party

2 2 3 1

Page 52: Risk management and policy implications for concentrating

51

LEG B Difficulty to find convenient partners

Political instability

Difficulty in attracting private investors

Lack of a regulatory framework which allows the export of renewable energies

Absence of means

33Significant operational constraints

3 5 3

A19 A20 A19: Accelerate discussions with government A 20: Organize seminars with private investors and members of government to discuss and ensure the government's willingness to change existing regulations

2 3 3 2

P5 P5 : Put private investors up to date with all the advances made in discussions with the government

LEG B Slow discussions with policy makers

Lack of political will

Failure to meet deadlines

Absence of firm decision

Absence of means

45Delay in project implementation

4 4 3

A21 A22 A21: Intensify discussions with policy makers to change regulation A22: Try to give the maximum guarantees to the government on the expected benefits of this project on local employment

2 3 3 2

P6 P6 : Exercise continuous control over the progress of the discussions and the obstacles to be overcome

FIN B Huge funding requirement

A huge project Difficulty in raising funds

No participation of the Tunisian government in the financing

Absence of means

45Delay in project implementation

4 4 3

A23 A24 A25 A23 : Construction by phases A24 : The recourse to the World Bank A25 : The recourse to the African Development Bank

3 3 4 2

P7 P8 P7 : Reduce construction and assembly costs P8 : Reduce maintenance costs

POL C Delay in delivery of necessary equipment

Poor Organisation

Discontinuity in the construction phase

recurring interruptions in the installation

Absence of means

33Significant operational constraints

3 3 2

A26 A27 A26: implement a preventive action plan A27: Recruit a stock manager

2 3 2 1

POL C Access roads not suitable for large trucks

The slowness of procedures

Road accidents

Road traffic due to the construction site

Absence of means

23Injury on duty with work stoppage less than 21 days

2 4 2

A28 A29 A30 A28: Organize handling operations during off-peak period A29: Set up traffic signs and signs of speed reduction A30: Heavy and light vehicles must show a recent technical inspection

1 2 3 1

ENV C Hard working conditions

Absence of barriers around the site

Temporary cessation of work

Lack of permanent drainage

Absence of means

45Delay in project implementation

4 4 3

A31 A32 A31: Establish barriers around the site A32: Inform drivers and employees if weather forecasts indicate the possibility of sandstorms

1 3 4 2

P9 P10 P9 : Permanent drainage of the site P10 : Continuous monitoring of weather forecasts

Page 53: Risk management and policy implications for concentrating

52

IMG C

Confrontations with local residents who are against the installation

Lack of participatory approach

Conflicts of interest

The existence of inhabitants who use the site for camels

Absence of means

33Significant operational constraints

3 4 2

A33 A34 A35 A33: Collaboration with local authorities A34: Setting up focus groups A35: Inform the shepherds at the beginning of the project to adapt the movements of their flocks

1 2 3 1

FIN C Funding difficulties Non-compliance with project specifications

Failure to meet construction deadlines

Temporary stop of the construction

Absence of means

45Delay in project implementation

4 4 3

A36 A36: Prepare an activity report and an interim financial report every six months

2 3 3 2

P 11 P11 : Financial audit to ensure conformity between the specifications, progress of implementation, disbursements and loan agreement

INF C

The existence of hazardous products in warehouses

Storage of fossil fuels and molten salt

Soil pollution Leakage Absence of means

24Controllable pollution

2 4 2

A37 A38 A37: Impervious storage area which is equipped with retention of adequate volumes A38: Develop an environmental monitoring program

1 1 3 1

PCH C Noise Significant equipment requirements

Difficult working conditions

Increase in dust and releases to air

Absence of means

23Injury on duty with work stoppage less than 21 days

2 4 2

A39 A40 A41 A39: Keep vehicles of the construction site in good condition A40: Equipping workers with acoustic protection A41: Watering of the access roads to limit the dust lifting

1 1 3 1

PCH C Degradation of air quality

Machines and trucks

Air pollution Long construction time

Absence of means

43Significant damage to the environment

4 3 2

A42 A43 A44 A42: Construction site machinery and trucks must be well maintained A43: Trucks must comply with current exhaust-gas emission laws A44: Implementation of a specification relating to the standards of the construction site

1 3 2 1

Page 54: Risk management and policy implications for concentrating

53

POL D

Non-compliance with the electricity purchasing regulations of european countries

Lack of follow-up of all changes in European legislation

Temporary cessation of activity

Slow discussions

Absence of means

33Significant operational constraints

3 3 2

A45 A45 : A detailed analysis of all the opportunities and threats presented in the various countries interested in buying the electricity produced

2 2 3 1

INS D The possibility of acts of violence by extremists

The existence of extremist groups that are against foreign companies

Delay in project implementation

Lack of political stability

Absence of means

34Significant damage to infrastructure or goods

3 3 2

A46 A47 A48 A46 : Regular communication between project representatives and local stakeholders A47: Create a positive perception of the project (employment, reputation of the city ...) A48: Underwriting political risk insurance with the Multilateral Investment Guarantee Agency (World Bank)

2 2 2 1

STR D Bad service of STEG

Absence of clauses that penalize STEG in case of bad service

Recurrence of conflicts

Lack of precision in contracts

Absence of means

31Unacceptable performance degradation

3 4 2

A49 A49: Define clearly the responsibilities and penalties of each party in case of non-compliance with commitments

1 2 3 1

TEC D Not achieving desired performance

HVDC cables never used for this depth

Non-compliance with commitments

Technology in research and development phase

Absence of means

32Very degraded or failed activity

3 3 2

A50 A50: The recourse to known manufacturers to manufacture cables that support this depth

2 3 1 1

MAT D

Decrease in the frequency of preventive maintenance

Cost reduction strategy

Recurrence of breakdowns

Absence of a maintenance fund

Absence of means

21Unavailability of services or equipment on the scheduled date

2 4 2

A51 A52 A51 : The creation of a maintenance fund A52 : A maintenance plan will be established annually and updated monthly

2 1 3 1

FIN D Inability to repay credits

Exchange rate and interest rate fluctuations

The increase in debts

Economic crisis Absence of means

54Huge financial loss

5 2 2

A53 A54 A53: Conclude a SWAP contract A54: Conclude a contract of Forward Rate Agreement

3 3 2 1

CS D Fault on the part of employees

Short training period

Recurrence of mistakes

The language used is English

Absence of means

31Unacceptable performance degradation

3 4 2 A55 A55: Require excellent knowledge of English

1 1 3 1

Page 55: Risk management and policy implications for concentrating

54

PCH D The use of fossil fuels

Keep molten salt at high temperature

Fire Leakage Absence of means

42Partial destruction of infrastructure or assets

4 3 2

A56 A57 A58 A59 A56: Absorbent material will be available near the transformer and warehouses A57: No smoking A58: Installation of fire extinguishers A59: Underwriting of fire insurance

3 3 2 1

PCH D Pressure and heated running of the tribune

Existence of high pressure steam

Explosion The presence of flame or fire

Absence of means

52Total destruction of infrastructure or assets

5 3 3

A60 A61 A62 A63 A60: Electrical appliances A61: No smoking A62: Installation of fire extinguishers A63: Develop a fire safety management plan

3 4 2 2

P12 P13 P12: Access to the construction site prohibited to the public P13: A buffer zone of at least 10 m wide will surround the entire project

COM D The lack of acceptance of local residents

The noise of the building site

Complaints from local residents

Road traffic

Inform local residents of the start of the work and the duration

33Significant operational constraints

3 4 2

A64 A65 A64: Set up a complaint management unit for local residents A65: Use local human resources who have the required skills

1 3 2 1