Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
RISK MANAGEMENT FOR LNG IN PORTS
Olga Aneziris
24th September 2020
1
OUTLINE
• Introduction
• Risk Definition
• Basic steps for Quantitative Risk Assessment
• Hazard Identification
• Methods for Hazard Identification
• Accident Sequences
• Methods for Accident Sequence Modelling andQuantification
• Risk Integration
2
LNG CYCLE
3Ref: https://www.fluxys.com/
SHIP TO SHORE LNG BUNKERING
4
Ref: http://www.emsa.europa.eu/
WHAT IS RISK?
5
• ”Organizations of all types and sizes face internal and externalfactors and influences that make it uncertain whether theywill achieve their objectives. The effect this uncertainty has onan organization’s objectives is “risk” (ISO 31000 Riskmanagement – Principles and guidelines)
• Risk refers always to the future and it refers to the multitudeof different possible outcomes each with differentconsequences some of which are undesirable.
WHAT IS RISK?
6
• Combination of probability of occurrence ofharm and the severity of that harm (ISO 18683Guidelines for systems and installations for supplyof LNG as a fuel to ships)
• Risk is now a series of possible consequences andthe associated probabilities
• (𝑝1, 𝑐1), … , (𝑝𝑖 , 𝑐𝑖), … , (𝑝𝑛, 𝑐𝑛)
TYPES OF CONSEQUENCES IN CASE OF ACCIDENTS
7
QUANTITATIVE RISK ASSESSMENT
9
ANSWERS TO THE FOLLOWING QUESTIONS
• WHAT CAN GO WRONG?
• HOW OFTEN THIS CAN HAPPEN?
• WHAT ARE THE POSSIBLE CONSEQUENCES?
• HOW FREQUENT THESE CONSEQUENCES ARE?
BASIC QUESTIONS OF QRA
10
• WHAT CAN GO WRONG?
• HOW OFTEN THIS CANHAPPEN?
• WHAT ARE THE POSSIBLECONSEQUENCES?
• HOW FREQUENT THESECONSEQUENCES ARE?
ACCIDENT SEQUENCES
CONSEQUENCE ASSESSMENT
PROBABILITY OFCONSEQUENCES
ACCIDENT FREQUENCY
MAJOR STEPS FOR QRA
11
HAZARD IDENTIFICATION
12
Plant Familiarization
Hazard source identification
Initiating events
• Description of installation
• Document review, interviews
• Systems, operations
• LNG quantities, storage and transportation
• HAZOP
• FMEA
• Master Logic diagrams
• Accident Databases
13
HAZOP process is a qualitative technique which identifies:
• DEVIATIONS from intended design/ operation
• CAUSES of deviations
• UNDESIRABLE EVENTS
• SAFEGUARDS to prevent causes
Recommends ACTIONS in design to improve safety and operability.
HAZOP is based on use of guide words which question how operating
conditions might not be achieved. It is carried out by a multi-
disciplinary team during a set of meetings.
HAZOP (HAZARD AND OPERABILITY ANALYSIS)
DEVIATION CONSEQUENCE SAFEGUARDS ACTIONS
HAZOP RESULTS
15
HAZOP results are recorded in special TABLES.
KEYWORD DEVIATION CONSEQUENCE SAFEGUARDS ACTIONS
High Level in tank
Overfilling of tank
LT 901ALAH 902
Stop loading
Example: Loading a tank
MASTER LOGIC DIAGRAMS
16
It is a Logic Diagram and starts with a Top Event,considered undesirable.
The top event is “Loss of Containment”.
It continues decomposing into simpler events untilevents challenging safety systems are identified.
These are the initiating events.
MASTER LOGIC DIAGRAM FOR LOSS OF CONTAINMENT
17
LOSS OF
CONTAINMENT
STRUCTURAL
FAILURELOSS OF
BOUNDARY
CONTAINMENT
BYPASS
EXCESS
TEMPERA-
TURE
LOW
LEVEL
LOW
TEMPERA-
TURE
DIRECT
PRESSURE
INCREASE
FROM GAS
COOLING
MALFUN-
CTION
EXCESS
HEATOVRFILLING
INTERNAL EXTERNAL
FIRE
CHEMICAL
INCOMPATIBLE
MATERIAL
RUN AWAY
REACTIONCOMBUSTI-
ON
ROLL OVER PRESSURE
SHOCK IN
HOSE
INTERNAL
PRESSURE
INCREASE
FLOODINGSNOW, ICE SEISMIC HIGH
WINDS
NATURAL
PHENOMEN
A
SUPPORTS
FAIL
EXTRA
LOADS
HIGH
TEMPE-
RATURE
UNDER-
PRESSURE
VIBRATION EXTERNAL
LOADING
OVERPRESSU-
RE
CONTAINMENT
OPENED
CONTAINMENT
OPENS
CORROSION ERROSION
LAYOUT OF LNG STORAGE IN A PORT
18
Decomposition of port in areas where HAZOP orMLD may be applied
Areas of the port
• Hose-loading arm• Ship receiving LNG• Buffer ship• Storage tanks
19
HAZARD IDENTIFICATION IN PORTS HANDLING LNG
20
LNG storage tank
• Boiloff removal malfunction, during unloading or storage
• External fire in storage tank area
• Level rise beyond safety height, or overfilling
• Extra loads
INITIATING EVENTS OF A PORT HANDLING LNG Loading arm section
• Excess external heat in jetty area
• Water hammer in loading arm, due to inadvertent valve closure
• Inadequate cooling of loading arm
• High winds during loading-unloading
• High winds
• Extra loads
Sendout section
• Inadvertent closureof valve in send out
Truck
Buffer Ship
Ship receiving LNG
SAFETY SYSTEMS
22
SAFETY SYSTEMS FOR INITIATING EVENT:Level rise beyond safety limit
Manual stop of Loading - Communication
Emergency Shutdown System (ESD)
Pressure Safety Valves (PSV)
EVENT TREE
23
PSV release
PLANT DAMAGE STATES
24
Definition
• A plant damage state uniquelycharacterizes the installation-dependent conditions of releaseof the hazardous substance.
• Accident sequences resultinginto the same conditions ofrelease are grouped into groupseach corresponding to aparticular plant damage state.
DAMAGE STATES
25
LNG Storage Tank• Tank rupture owing to overpressure, overfilling
Loading arm- Unloading section• Pipe rupture• Hose rupture
Truck• Truck rupture• BLEVE of tank
Fueled Ship• Tank rupture owing to overpressure, overfilling
Buffer Ship• Buffer ship rupture
BOWTIES AND SAFETY BARRIERS
26
TARGETBarrier
PREVENTION MITIGATION
ACCIDENTInitiating event
Barrier
28
BOWTIE FOR LOSS OF CONTAINMENT (LOC) FROM LOADING ARM WITH LNG
29
LOC OF PIPE WITH LNG- LEFT HAND SIDE
31
Data and Parameter Assessment
Estimate frequencies of the initiating events, component
unavailability, probabilities of human actions
Data Gathering and parameter value assessment (HSE, NFPA,
RIVM, OREDA)
Accident Sequence and Plant damage State Quantification
Calculate frequency of occurrence of accident sequences and
Damage states using the event trees of the logic model.
FREQUENCY ASSESSMENT OF DAMAGE STATES
EVENT TREE QUANTIFICATION
32
10-1/y
10-3
1.55 10-2
10-2
1.55 10-7/y
FAULT TREES
34
“AND” GATE - “OR” GATE
T: NO WATER AT POINT E
FAULT TREES
35
TOP EVENT: Failure of high level control
MINIMAL CUT SETS OF FT “FAILURE OF HIGH LEVEL CONTROL”
38
TERM (#) MINIMAL CUT SETS PROBABILITY (UNAVAILABILITY)
1 ESD FAILURE LEVEL 1.22E-02
2 COMM 1.13E-03
3 LEVEL TRANSMITTER 2.64E-04
4 AIR COMPRESSOR 3.6 E-04
5 PR. VALVE FAILS 6.84E-04
6 LOSS OF AC DIESEL GER 1.8 E-06
TOTAL 1.46E-02
FAULT TREE –EVENT TREE QUANTIFICATION
39
• In case of event tree quantification a big fault tree isconstructed with a top event the “damage state”, an ANDgate and inputs: Initiating event and all other failures in theET sequence.
HIGH LEVEL IN TANK
FAILURE OF MANUAL STOP
FAILURE OF LEVEL CONTROL
FAILURE OFPSV
LNG TANK RUPTURE OWING TO HIGH LEVEL
FREQUENCIES OF PLANT DAMAGE STATES AND RELEASED LNG
40
TASKS OF QUANTITATIVE RISK ASSESSMENT
41
METHODS Event trees Fault trees Bowties
QUANTITATIVE RISK ASSESSMENT (CONSEQUENCE ASSESSMENT)
42
CONSEQUENCE ANALYSIS
43
CONSEQUENCE ASSESSMENT
44
• DOSE ASSESSMENT: The integrated, over time, exposure of anindividual to the extreme phenomenon generated by theflammable material is calculated. This defines the “dose” anindividual receives. Any emergency response plans or othermitigations action are taken into account at this point.
• Consequence Assessment: Appropriate dose/response modelsreceiving as input the dose of heat radiation or overpressurecalculate the probability of fatality or injury of the individualreceiving the dose.
CONDITIONAL ISO RISK CONTOURS
45
Conditional iso-risk contours from plant damage state pressurised LNG tank rupture, and BLEVE (10-2, 10-1, 1)
RISK INTEGRATION AND RISK INDICES
46
• Integration of the results obtained so far, that is combiningfrequencies of various accidents and correspondingconsequences.
• INDIVIDUAL RISK: is defined as the probability of death peryear of exposure to an individual at a certain distance from thehazardous source. It is usually expressed in the form of isoriskcontours.
• GROUP RISK: is a measure of risk for a group of people,expressed as fatalities per year. It is most often expressed interms of the frequency distribution of multiple casualty events(F/N curve).
TOTAL INDIVIDUAL RISK CONTOURS
47
Total Unconditional iso-risk contours (10-7, 10-6, 10-5/yr) for LNG storage plant at port
CONCLUSIONS
51
• QRA estimates the risk level of a port handling LNG (inside andoutside the port).
• Safety of a port is depicted by accident sequences, theirfrequencies of occurrence and the corresponding consequences.
• QRA provides information to decision makers and assists riskreduction strategies in hazardous installations.
• QRA may prevent the occurrence of Major accidents in portshandling LNG and/or limit their consequences.
Olga AnezirisNCSRD DEMOKRITOSAgia Paraskevi Attikis, 15310 GreeceEmail: [email protected]
Thank you for listening. Any Questions?