Upload
dodung
View
215
Download
0
Embed Size (px)
Citation preview
SSRG International Journal of Civil Engineering - (ICETM-2017) - Special Issue - March 2017
ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 1
Risk management in highway construction
using risk priority matrix and SPSS software
K.Abhinaya1 PG student, Construction engineering and management,
Sona college of technology,
Salem-636005,Tamilnadu
S.Priscil Nidhu2
Assistant Proffesor,
Sona college of technology,
Salem- 636005,Tamilnadu
Abstract - Risk events associated with road
construction and highway construction projects
have a major impact on issues related to cost, time
and quality of project delivery. Unexpected risk
events result in either positive and negative
outcomes often causing deviations from project
plans particularly prone to risk. Despite the
extensive research on risk management in the
construction industry and there is limited literature
dealing specifically with project risk in developing
countries, especially within the Asian context. It is
against this background that our study investigates
the use and awareness of risk assessment and
management processes with respect to cost
efficiency, time and quality of highway and road
construction projects. Our paper highlights the
risks associated with highway construction projects
with forty eight risks are identified through detailed
literature review. A questionnaire is then developed
to solicit opinion of the construction professionals
as to the probability and impact of those risks in
addition to their proper allocation. In person
surveys were completed and implemented in the
analysis. Statistical Package for the Social
Sciences (SPSS) software was used for analysis of
various risk factors from Questionnaires survey
data for preventive measures or mitigation
techniques for various risks on construction site.
The responses provided both quantitative and
qualitative data from several highway construction
projects completed in the past. Statistical
dependency correlation analyses are showed that
the use of risk assessment in the reported projects
has improved quality of project and construction
management.
Key words: Risk Management; Highway
Construction; SPSS; Risk priority matrix.
I. INTRODUCTION
Risk management is the systematic process of
identifying, responding and analyzing to project
risk. It includes maximizing the consequences and
probability of positive events and minimizing the
consequences and probability of adverse events to
project objectives.
Risk is generally a choice in an environment
rather than a fate. It is uncertainty inherent in
possibility and plans of something happening that
can affect prospects of achieving, business and
project goals. The money spend fund shipments
overseas was the example of risk business in the
early days of travel. Each activity we do involve
risk, only the amount of risk varies.
1.1. Definition of Risk
The situation where there exists no knowledge
of its outcomes.
An exposure to the change of injury or loss;
dangerous or a hazard chance, to run risks.
Every risk is proportional to the expected losses
which caused by a risky event and to the
probability of this event.
1.2. Concept of risk and risk management
Multi-faucet concept is called as risk. In the
context of construction industry risk could be the
likelihood of the occurrence of a definite event or
factors which occur during the whole construction
process to determine the project a lack of
predictability about structure outcome or
consequences in a decision and planning situation,
uncertainty risk associated with estimates of
outcomes-there is a chance that results could be
better than expected.
1.3. Risk exposure
The following are the several factors risk
exposure.
• Team size: the higher probability of a problem
arising. For example, communications can be
more difficult when the number of participants
increases. The number of interactions among
people increases and they require greater
coordination.
• History: new projects are riskier because the
processes have not been refined. More times a
SSRG International Journal of Civil Engineering - (ICETM-2017) - Special Issue - March 2017
ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 1
project of a similar nature has been done,
greater the likelihood of success.
• Staff expertise and experience: if the staff lacks
direct knowledge and experience of the
subject, people will struggle to learn as they go
along, time and possibly introducing errors
happened when robbing the project.
• Complexity: the more sophisticated a project,
there is a greater the opportunity of a mistake
and problem.
• Management stability: management stability
implies when unity of direction, which in turn
means reaching the goals. The management
irritability can lead to insufficient use of
resources.
• Time compression: if a schedule is highly
compressed mean the risks are magnified.
Having more times means greater flexibility
and the opportunity to prevent and mitigate the
impact of errors.
• Resource availability: the more resources that are
available when the greater the ability to
respond to problem as they arise. Plentiful
resource, of course, does not guarantee
protection from risk; however they do provide
the means to respond to it.
1.4. Sources of Risk in Construction Projects
• Misunderstanding of contract terms and
conditions
• Design changes and errors
• Poorly co-ordinate work
• Poor estimates
• Poorly defined roles and responsibilities
• Unskilled staff
• Natural hazards
• Political and legal problems
1.5. Advantages of Risk Management
• Less uncertainty
• Achievement of objectives
• Reliability
• Reduction of capital cost
• Creation of value
1.6. Limitations of Risk Management
• If risks are improperly prioritized and
assessed, time can be waste in dealing
with risk of losses that not likely to occur
• Spending too much time managing and
assessing unlikely risks can divert
resources that could be more profitably.
• Unlikely events to occur, but if the risk is
unlikely enough to occur, it may be better
to simply retain the risk & deal with the
result if the loss does in fact occur.
II. LITERATURE REVIEW
2.1 Historical data
Sharmila Mane and Dr. S.S. Pimplikar (2012)
listed the various risk faced in BOT projects into
three types as Financial Risk, Political Risk and
Technical Risk. Avoidance, Transference,
Mitigation and Acceptance are the Risk response
strategies followed in India. Delays in approval,
Change in Law, Cost overrun, Land acquisition and
compensation, Enforceability of contracts,
Construction schedule, financial closing, Tariff
adjustment and Environmental risk are the critical
risks in BOT projects. Maintaining good
relationship with government authorities help to
avoid the risk of delay in approval, obtaining
government’s guarantees via adjusting tariff or
extending concession period help to avoid the risk
due to change in law, choosing quality and trust
worthy consultants with knowledge of how to
handle everyday construction issues help to avoid
risk of delay in construction schedule, etc.,
Yukiya Sato, Keiichi Kitazume and Kazuaki
Miyamoto (2005) discussed about the risk faced by
road projects at different project stage.
Questionnaire is done and from the results some
conclusions regarding cost and period is arrived.
2.2 Case based approach
Lusa Persia et al (2016) focused on the
management of road infrastructure safety to a set of
procedures that support a road authority in decision
making related to the improvement of safety on a
road network. For this data will be collected from
infrastructure projects categorizing the risks into
various groups. The modified from can be used for
the whole life cycle of the project.
Sarvari, Valipur, Yahaya and Noor (2014)
studied the risk assessment in malaysian PPP
project. The study consists of risk identification,
assessment in infrastructure projects. The major
risk factors have been identified and collected by
comprehensive literature reviews. After consulting
SSRG International Journal of Civil Engineering - (ICETM-2017) - Special Issue - March 2017
ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 1
it with experts (in PPP contracts) these factors are
categorized and ranked. The data for analysis was
obtained from face to face interview and
questionnaire survey. Based on the survey results,
risk index was calculated by probability and impact
value.
V.R Ganapathy, S.K Subramaniam, A.B
Mohamad Diah (2008) have explained the picture
of perfect road construction site is the one that
utilizes conventional vertical road signs and a
flagman to optimize the traffic flow with minimum
hazel to the public. Some former research was
carried by the Department of occupational Safety
and Health. This paper highlights on hazardous
zones in a certain road construction.
2.3 Tools and software
David Ndiang ui Wambui, Dr. Kepha Ombui,
Dr. Assumptah Kagiri (2015) have explained how
to analyse risk factors affecting completion of road
construction Projects with the help of SPSS
software.Statistical techniques were applied to risk
variables and the research is done to check which
variables in the set form coherent subsets that are
relatively independent to one another.Also studied
the significance of the risk, whether to choose it for
study purpose or not by doing component analysis.
2.4 Probability impact matrix
Tzavi, Aaron J. Shenhar and Dov Dvir (2002)
have analyzed about risk management tools and
techniques which have been developed to improve
project success. They found that the risk
management practices are not widely used and also
found that risk management practices were more
applicable to higher risk projects. They found some
differences according levels of technological
uncertainty. They took interviews for data
collection and did SWOT analysis, Probabilistic
risk analysis and methodic trade-off analysis. The
assessment were measured along four dimensions
such as meeting functional specification, meeting
technical specifications, meeting schedule and
meeting planned budget. They suggest that all risk
management practices are positively correlated
with meeting budget goals in the high uncertainty
group, while for the low risk group the correlation
is weaker and less likely to be statistical significant.
Ibrahim Mahamid (2013) discuss about the
common risks affecting time overrun in road
construction projects beyond their normal
operation. Here study is done for around 45 firms
and several risk factors found related to project
management and the contractors also have views
on factors that have not been identified previously
such as low equipment efficiency , high
competitions in bids and the political situation.
2.5 Hierarchical risk breakdown structure
Mohamed F. Diab, Khaled Nassar (2012)
explained about the need of risk assessment to
improve highway construction projects. A survey
questionnaire was developed to collect the
quantitative and qualitative data and 660
professionals were chosen for sample and received
responses from 246 people and arrived with 31 risk
drivers which are categorized under five broad
categories such as project scope , right of way,
utility conflicts, A/E services and project
construction management. Hypothesis testing was
done for these risk drivers and risks which affect
cost and schedule growth of construction project
were identified. Raj V. Ponnaluri (2012) discusses
about India’s quickly changing transportation
scenario, especially road traffic crash concerns.
Their objectives of work were concerned. Exposure
risks are calculated from vehicles and their accident
percentage are noted. Finally calculate crash risk at
police-regulated locations was 40% less than at
traffic signals.
III. SCOPE AND OBJECTIVES
• To identify the various risk factors in
construction of highway construction
projects.
• To analyze the sources of risk factors arising in
the highway projects.
• Using the literature survey the questionnaire is
prepared.
• The survey will be conducted to the
construction industries through questionnaire.
• The result will be analyzed from the
questionnaire.
• The risk will be solved using the software like
SPSS.
• The result and discussion about the risk factors
solving in the construction projects.
IV. METHODOLOGY
The methodology adopted in this project is
given below:
Study of literature related to Time and
Financial Management risks.
Preparation of questionnaire.
Site visit to major construction
project.
Questionnaire survey and personal
interviews with Site-Engineers,
Supervisor and managers.
Analyzing the questionnaire.
SSRG International Journal of Civil Engineering - (ICETM-2017) - Special Issue - March 2017
ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 1
Factor analysis of data obtained from
site and identifies the root cause.
Remedial measures are to be
suggested and the present data is to be
recorded for future reference.
Conclusions, recommendations and
suggestions for future study.
V. ANALYSIS AND RESULTS
Risk Priority Matrix is done with the help of
likelihood and impact results obtained from the
samples collected through questionnaire, which
was prepared based on the risk factors obtained
from several literature reviews. A risk priority
matrix is easier to make, since most of the
information can be easily extracted from the
questionnaire. It is made in the form of a simple
table where the risk factors are grouped based on
their likelihood and impact made by the risk
factors.From the likelihood and impact levels of the
risk factors, consequences are understood, risk is
prioritized and risk priority matrix is created. Risk
priority matrix provides the quick view of the risks
and the priority with which each of these risks
needs to be managed to overcome its impact. Risk
Priority matrix can be created in Excel or in table
format to assess the risk factors.
Table 5.1 Scale used to identify factor’s severity
and frequency of occurrence
Figure 5.1 The risk map
The map is classified into three zones:
Green zone: risks in this zone are low
level, and can be ignored.
Yellow zone: risks in this zone are of
moderate importance, and should be
controlled.
Red zone: risks in this zone are of critical
importance, and a close attention should
be paid.
The questionnaire was sent out to a total of 41
contracting firms asking their contribution in
identifying the risk map for the 45 factors in terms
of severity and frequency of occurrence. The
contractors were randomly selected from available
list in PCU including 50 contractors. Only a total of
34 completed questionnaires were returned
representing a response rate of 83%. Most of the
participating contractors have more than 10 years
of experience in road construction.
5.1 Denotes sample risk priority matrix
Table 2 illustrates the risk map for factors under
project group. Six factors are considered under this
group. The results indicate that three factors are
located in the yellow zone, namely: inconvenient
site access, disturbance to public activities, and
limited construction area. The other three factors
are located in the green zone, they are: poor terrain
condition, poor soil drillability, and poor soil
suitability.
Table 5.2 Risk map for factor under project
group
5.2 Result using Excel software
The analysis of 45 factors considered in a
survey indicates that 8 factors are located in the
green zone (low frequency, low severity), 30
factors are in the yellow zone, and 7 factors in the
red zone (high frequency, high severity) in the risk
map. The most critical factors are: payment delays
by the owner, the political situation, the
segmentation of the West Bank, the financial status
of the contractor, poor communication between the
construction parties, lack of equipment efficiency
and high competition in bids.
SSRG International Journal of Civil Engineering - (ICETM-2017) - Special Issue - March 2017
ISSN: 2348 – 8352 www.internationaljournalssrg.org Page 1
5.3 Statistical. Package for the Social Sciences
SPSS Statistics is a software package used
for statistical analysis. Long produced by SPSS
Inc., it was acquired by IBM in 2009. The current
versions (2015) are officially named IBM SPSS
Statistics. Companion products in the same family
are used for survey authoring and deployment
(IBM SPSS Data Collection), data mining (IBM
SPSS Modeler), text analytics, and collaboration
and deployment (batch and automated scoring
services).
The figures below shows the example for
analysis of results, the analysis was done using
SPSS software in which the Response Percentage
for risk factor was obtained.
Figure 5.2 Risk in project group
From fig no 5.2, it can be interpreted that 32%
respondents strongly agreed that improper project
group causes risk in highway project. While 25%
respondents agreed that improper project group has
very high impact on construction of project.
Other risks are analyzed and got the maximum risk.
The risks are
Managerial group
Consultant group
Financial group
External group
Construction labours group
VI. CONCLUSION AND
RECOMMENDATIONS
Risk management in highway construction of
any project is very important and it should be
prioritize by every
construction project. The success of every project
mostly is determined by the ability of the
construction team to minimize the risk factors and
the implementation of the project should be proper.
For a project to be successful the
following recommendations are hereby presented:
Adequate planning should be provided
before the commencement of project
construction.
Safety, rules and regulations in
construction site should fully be
maintained from the initial to final stage
of construction.
Durable and quality materials for
construction should be supply and use
properly.
Efficient and Economical use of all the
available resources should be adopted by
all associates of construction team.
Effective communications and
corporations between all members of
construction team should be adopted.
Well trained and experienced workmen
should be employed where necessary.
REFERENCES
[1] Akintoye, A. and MacLeod, M. (1997) "Risk analysis and
management in construction." International Journal of Project
Management, 15 (1), 31-38.
[2] Ashley, D., Diekmann, J., and Molenaar, K. (2006). "Guide
to risk assessment and allocation for highway construction
management." FHA, International Technology Scanning
Program. Office of international program, FHA, Washington,
DC, 4-17.
[3] Diab, M. (2011) Analyses of highway project construction
risks, performance, and contingency, ProQuest, Ann Arbor, MI,
56-102.
[4] Flyvbjerg, B., Holm, M., and Buhl, S. (2002).
“Underestimating Costs in Public Works Projects-Error or
Lie?”. APA Journal, 68 (3), 279-295.
[5] Lam, P. (1999). "A Sectoral review of risks associated with
major infrastructure projects". International Journal of Project
Management 17, (2), 77-87.
[6] Molenaar, K. (2005). "Programmatic cost risk analysis for
highway megaprojects". Journal of Construction Engineering
and Management 131(3), 343-353.
[7] Nassar, K., Nassar, W., and Hegab, M. (2005) “Evaluating
Cost Overruns of Asphalt Paving Project Using Statistical
Process Control Methods”. Journal of Construction Engineering
and Management 131(11), 1173-1178.
[8] PMI. (2004). "A Guide to the project management body of
knowledge." Project Management Institute, Newtown Square,
PA, 237-268.
[9] Kumaraswamy, M.M. (1997) Conflicts, claims and disputes
in construction,Engineering, Construction and Architectural
Management, 4(2): 95- 111.
[10] Kumaraswamy, M.M. and Chan, D.W.M. (1998)
Contributors to construction delays, Construction Management
and Economics, 16: 17-29.
[11] Lester, A. (2007), “Project Management, Planning and
Control”, 5th ed. Elsevier Ltd.
[12] Manelele, I. and Muya, M. (2008) “Risk Identification on
community-based construction projects in Zambia”, Journal of
Engineering, Design and Technology, 6(2): 145 – 161.