38
Robin Rigg | WTG Decommissioning Project Decommissioning Project Review and Lessons Learnt 25 th January 2017

Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Robin Rigg | WTG Decommissioning Project

Decommissioning Project Review and Lessons Learnt

25th January 2017

Page 2: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Robin Rigg

2

Situated 11km from the Dumfries and

Galloway coast & 13km North West

of the Port of Workington.

58 x Vestas, V90 3MW Wind Turbine

Generators (WTG)

2 x offshore substations (East &

West)

2 x132kV cables connect near

Seaton, Cumbria where they travel

2km inland to the onshore

substation.

Commissioned 2009

Page 3: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

3

Page 4: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Foundation Integrity Management – What is Required?

Conduct bathymetric surveys to identify;

- Any movement of the seabed or,

- Local changes to the seabed as a result of installation of foundations i.e. scour

development around the foundations

Monitor Natural Frequency of the WTG;

- The frequency of vibration or oscillation in which a system will inherently adopt

according to its structure given a suitable excitation e.g. wind

- The foundation structures are designed to operate between 1P and 2P/3P

frequencies of the WTG i.e. prevent resonance of the system.

- A change to the water depth, scour or seabed movements, will reduce the

natural frequency of the structure, potential to meet the natural frequency of the

WTG which would result in resonance and performance issues.4

Page 5: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Post- Commission Foundation Management Strategy

Bathymetric surveys to be completed annually.

3 Annual Bathymetric Surveys showing no change

Survey results up to and including 2012 evidenced that the seabed was

relatively stable although deeper than anticipated at design scour pits were

recorded in the south eastern corner of the site (deep water locations).

To abate further scour develop a retrospective scour installation campaign was

completed in October 2016.

No significant seabed movements or scour pit development (greater than

anticipated by design) were identified in any other areas of the site.

EON continued with a ‘monitor’ strategy with respect to foundation integrity and

seabed stability based on the available data.

5

Page 6: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

6

Identification of Issue and Action Taken

In Autumn 2013 natural frequency of WTG A1 was at ‘high’ end of operational

frequency range

Jan 2014 a significant frequency drop was observed

May 2014 the natural frequency was recorded at lower operational limit of the

WTG.

Decision Made to Resurvey

A bathymetric survey was completed in May 2014, a reduction in seabed

of approximately 15m since the previous bathymetric survey was

recorded at WTG A01

Page 7: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Post-May 2014 Survey

7

Immediate steps taken;

Discussion with MHI Vestas to assess operational limits of WTG –

agreement to reduce safety margin allowing continued operation.

Review of storm and environmental events that may have resulted in

significant mobility changes to seabed i.e. identification of immediate

root cause of geomorphological changes to seabed.

Tidal surge events had occurred in Dec 2013 & Jan 2014

Page 8: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

8

2012 Bathymetric Survey

Page 9: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

9

2015 Bathymetric Survey

Page 10: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Seabed Profile at Location A1

10

Page 11: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

11

Assessment of Structural Integrity

2 independent elements of work were commissioned in order to:

(1) identify any potential geotechnical and / or structural solutions to avoid or

defer decommissioning the turbines and

(2) complete a review of foundation stability under revised environmental load

conditions subject to significant seabed lowering.

Page 12: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Assessment of Structural Integrity

12

Findings

Initial assessment carried out identified 2 WTG which would need to be

decommissioned due to risk of collapse

Further work was conducted to assess the suitability of scour protection systems

to abate further seabed lowering at other ‘at risk’ locations.

Further Options

EON engaged EngD through ‘REMS’ University research programme to assess

the structural contribution of rock fill / soil infill solutions and determine if an

alternative option to decommissioning could be developed.

Page 13: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Options

13

Rock fill and ‘reinstatement’ of the eroded material were identified as possible

solutions.

However they were not considered feasible options due to:

No engineering basis to justify that rock fill / replenishment would re-

establish foundation stability & may exacerbate structural integrity /

stability issues.

Unproven offshore (installation methodology and long term performance),

Strong tidal currents likely to restrict / inhibit placement and performance.

Structural solutions identified carried significant risk from both a long term

performance and engineering / installation complexity

All options carried significant H&S risks during install

Page 14: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

14

Structural Integrity Assessment & Access Safety

Assessment

Structural assessment under revised environmental conditions to

understand the effect of seabed lowering on foundation stability.

Analysis confirmed stability

severely compromised in

extreme storm events.

Further work undertaken by

EON to demonstrate

conditions under which

foundation stable and safe

for personnel to access

(required to complete

essential enabling works

prior to decommissioning).

Page 15: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

15

Independent Assessment of Dynamic Changes to Seabed

Aim was to:

Review dynamic changes to seabed and overall impact on the Robin Rigg

sandbank area,

Identification of ‘at-risk’ turbines,

Predication of future changes to seabed levels and impact of ongoing subsea

channel migration on the wind farm.

Page 16: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

16

Seabed Erosion

Page 17: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

17

Seabed Erosion Review

Key points of the review:

Overall extent of scour hole local to A01 was 120m x 60m x 20m in

March 2015 – further analysis in June 2015 indicated this had

increased further.

Changes in seabed level driven by global effects, further lowering of the

seabed local to A01 was predicted with a further reduction in

embedment depth.

WTG B01 had also seen a significant lowering of the seabed and

corresponding reduction in natural frequency.

Extent of scour and effect of global lowering identified that installation of

scour protection in the existing scour hole would not abate ongoing

global lowering and associated scour i.e. no intervention options at

WTG A01.

Page 18: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Seabed Erosion Review - March 2015

18

In March 2015 monopile embedment depth was circa 10m, design

embedment depth was 20m.

Seabed erosion modelling work indicated that ongoing erosion local

to WTG A01 had the potential to reduce the seabed further with a

final embedment depth of 5m anticipated.

Page 19: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Key Issues & Considerations

Robin Rigg site is an operational site, so how to decommission 2 WTG

during operations?

What method could you use to do this which does not put the WTG,

personnel completing the works and vessels at risk whilst doing so?

Lease arrangements consider decommission as the ‘whole’ site at end of

life?

Has WTG decommission been done previously? What methods were

available?

19

Page 20: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Works Planning – Site and Operational ConsiderationsEngagement of all key stakeholders essential to deliver the project within the

required timescales (requirement to decommission identified April 2015, works

to be completed Summer / Autumn 2015)

Key Stakeholders had to be consulted:

20

Page 21: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Works Planning – Site and Operational Considerations

Marine License Operational issues

Requirements as identified in the S36

consent,

Current licensing requirements

Interim or ‘full’ decommissioning

Impact on array cable string layout,

Isolation of WTG B2

Impact on back-link for A and B strings.

21

Impact on Site Activities Occupational Safety Issues

CTV requirements,

Marine coordination,

24/7 operations,

Prioritisation of decommissioning works

affecting statutory maintenance

Safety case approach to assess risks to

personnel for continued access to

WTG’s

Page 22: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Wind Farm Site Layout and Cable Strings

22

Page 23: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Planning - Decommissioning Specific Considerations

23

Outcome of Assessment:

Decommissioning was only envisaged at end of operational life, as such no

established methodology or consents / licenses in place to allow works to be

completed

No known partial decommission completed to date

Many methodologies unproven

Need to look at other industries and to look at potentially unproven techniques

Page 24: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Planning - Decommissioning Specific Considerations

24

Project team conducted a review of existing oil and gas and conventional inshore

decommissioning techniques. Issues identified included;

Robin Rigg Monopile diameter greater than any decommissioning undertaken in

O&G,

Grouted connection rather than flange connection introduced added complexity,

Length of Monopile to be removed required decommissioning of foundation

structure to be completed in two sections.

Limited planning time meant that full fracture mechanics failure assessment not

completed, therefore all cutting required the foundation to remain on the hook of the

main vessel crane to ensure stability of the foundation structure throughout the

decommissioning works.

Page 25: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Review of Decommissioning Methodology

Robin Rigg is an environmentally challenging site, vessel stability issues during

construction and scouring around jack-up legs was an identified issue so

decision made to utilise the existing Charter with MPI who had previous

experience operating on Robin Rigg to minimise the risk

Marine Warranty Surveyor utilised throughout planning stages and present on

the vessel for the majority of the campaign.

Avoidance of spring tides and monitoring or scouring around legs during

operations essential.

WTG and WTG Tower

Adopted a ‘reverse’ engineering approach as no established methodology.

On review ‘bunny ear’ configuration not suitable with respect to back deck

laydown and transportation post decommissioning. 25

Page 26: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Decommission Operations as follows:

26

Blades removed individually and stacked on deck in a 3 x 2 configuration,

Nacelle and hub lifted as one unit,

Tower removed as a single or two section lift (dependent on available lifting

beam)

6 x Major lifts were required per location to dismantle the WTG and tower.

Page 27: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Review of Decommissioning Methodology

Marine License

The proposed decommissioning the first of its kind, no precedence set.

EON presented as an interim decommissioning with opportunity to revisit or

complete further works at the end of the operational life of the wind farm.

MS LOT agreed to a cut off height of the MP 2m above the current seabed

level on this basis.

The 2m above seabed level allowed use of external cutting tool without

requirement to dredge or excavate around the base of the MP.

.

27

Page 28: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Review of Decommissioning Methodology

28

Cabling and Impact on Continued Operation

WTG’s A01 and B01 are located at the end of array cable strings, therefore

impact on individual strings negligible.

The backlink between A and B array cable strings is situated between A01

and B01, therefore decommissioning of these WTG’s would cut the backlink

increasing production risk.

WTG B02 would be isolated by decommissioning of A01 and B01 so there

was a requirement to complete offshore joints between existing cables or lay

new cables between WTG’s to maintain array cable connections

Page 29: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Review of Decommissioning Methodology

An initial review confirmed that the foundation would need to be removed in

two lifts to be accommodated on the back deck. For ease and simplicity for

transportation, the cuts would be located as follows;

1st cut 1m below the bottom of the grout skirt / transition piece,

2nd cut 2m above the current seabed level.

29

Page 30: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Review of Decommissioning Methodology

30

Transition Piece

Exposure of the TP / WTG tower interface flange provided solid lifting

points of known integrity.

TP would be sea fastened vertically utilising grillage already on the MPI

Adventure.

Monopile

2No. Holes would be cut through the top can of the remaining MP stub,

shackles and chains would be attached to provide stable lift.

Internal sand column would be dredged prior to cutting to reduce lift weight

minimum (steelwork only)

Page 31: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

CDM Original decommissioning strategy in the H&S File assumed all

decommissioning at the end of life of the site – very limited information in

O&M manual, did not have an ‘in service’ decommissioning requirement

No indication on ‘how’ to decommission a WTG on a live site

UK Regulator were kept in the loop on the proposed works

All procedures written from scratch, very detailed review process completed

to ensure all interfaces identified and understood

Construction Phase H&S Plan developed to manage full work scope.

HSE involvement - Risks openly addressed in early discussions – kept in

loop and invited to observe works on the vessel.

31

Page 32: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

32

WTG / Tower Removal

Page 33: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

33

WTG / Tower Removal

Page 34: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

34

TP Removal

Page 35: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

35

TP Removal

Page 36: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Project Lessons Learnt

36

The Decommissioning Strategy should be should be reviewed by the O&M Team

post construction

A Decommissioning Strategy Should:

identify restrictions and constraints from a decommissioning aspect

The clear proposed decommission method options and configurations

rather than ‘let’s figure it out later’

Equipment assumptions that should be used should be listed

Designs & Layouts should consider any potential need for disconnection

points for EOS and WTG/Strings

Vessel capability requirements should be listed

Decommission method options should aim to minimise diving

Page 37: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Project Lessons Learnt

37

Bathymetric Surveys should not be treated as ‘Routine Maintenance’

Surveys should be planned Annually as a minimum

After major storm events and Tidal Surge Events, additional surveys

should be considered, particularly in at risk locations

Surveys should extend outside of the WTG site a reasonable distance in

order to consider wider sea bed movements in local vicinity, which may

indicate potential threats to operational Site areas

Sites which are in close proximity each other should consider sharing

survey data

Page 38: Robin Rigg | WTG Decommissioning Project · WTG’s A01 and B01 are located at the end of array cable strings, therefore impact on individual strings negligible. The backlink between

Thank you

38

Phillipa Cassie

E.ON Climate & Renewables

[email protected]