31
Robot Automation TEAM 07 2017-2018

Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Robot AutomationTEAM 072017-2018

Page 2: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Nathan Casey (ECE)

Josh Tempelman(ME)

Michael Bissetta(ECE)

The Team

Alex Keizer(ME)

2Intro Old Project New Project Moving Forward

Page 3: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Presentation Outline

Overview

Initial mechanical design

Initial electrical design

Design Change

Final mechanical design

Final electrical design

3Intro Old Project New Project Moving Forward

Page 4: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

The Customer

• Specializes in machining, assembly, inspection

• Serves wide variety of industries: automotive, office, medical, and more

• Currently uses little automation

4Intro Old Project New Project Moving Forward

Page 5: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Project overview

• Parts are currently being produced in a lathe operated by a worker.

• The pucks are put into a lathe twice, machined to precise dimensions, and measured.

• Our task was to automate this process, decreasing cost and increasing part quality.

5Intro Old Project New Project Moving Forward

Page 6: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Ethics and Design Norms

Delightful Harmony TransparencyTrust

6Intro Old Project New Project Moving Forward

Page 7: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Initial design requirements

• Manufacture parts with little to no human interference

• Operate robustly and reliably

• Manufacture 120 parts per hour

• Track dimensions of finished parts

• Comply with safety standards

• All designs are owned by Prefferred Quality Services, not Team07

7Intro Old Project New Project Moving Forward

Page 8: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Initial mechanical plan - indexing table

8Intro Old Project New Project Moving Forward

Page 9: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Initial mechanical plan – End of Arm Tool

- Electromagentic Gripping

- Simple Bracket Configuration

9Intro Old Project New Project Moving Forward

Page 10: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Initial electrical plan - Communication

10Intro Old Project New Project Moving Forward

Page 11: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Initial electrical plan - Block Diagram

11Intro Old Project New Project Moving Forward

Page 12: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Anticipated challenges

● Reliable measurements

● Consistent part grabbing

● Lack experience in networking and programming

12Intro Old Project New Project Moving Forward

Page 13: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Project Change

3+ years of production anticipated on the part created by the cell

November 16 the OEM notified PQS that the part will bediscontinued in Q1 of 2018

PQS has assigned a new project to the team to replace this one

OEM

SUPPLIER

PQS

Old Part New Part

13Intro Old Project New Project Moving Forward

Page 14: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New requirements

• New heavier part + how to machine it

• New table

• New electrical hardware and requirements

• No measurement system

14Intro Old Project New Project Moving Forward

Page 15: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Lessons learned

• Scrapped ideas (ex. Gantry robot, two motors for original table design)

• Engineering in industry can be volatile

• Must be able to adapt quickly

• It is important to research deeply as well as broadly

15Intro Old Project New Project Moving Forward

Page 16: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Safety

• Cage keeps employees away from moving parts

• Three Emergency stop buttons

• Safety Relay connects all E-stops and handles emergency procedure

• Safety mat and speaker ensures no one is near table when it rotates.

• Stack lights indicate machine state

16Intro Old Project New Project Moving Forward

Page 17: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Finances

• Cost savings was a important factor for our customer

• With the change of project costs increased significantly and that had to be communicated to the

customer

• We updated our budget regularly and kept the customer informed on all changes

• We saved a lot of the cost by going through several robot suppliers

• We can also save cost in the future by using parts that have long lifespans

17Intro Old Project New Project Moving Forward

Page 18: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New System Design

18 of 30

Key Components:-HAAS Lathe-Fanuc Arcmate 6-Axis Robot-Rotating Part Loading Table-Part Check Ramp-Finished Part Bin-Velox Safety Caging

Intro Old Project New Project Moving Forward

Page 19: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New mechanical plan - indexing table

Key Components:-Oriental Motor-Polycarbonate Shields-E-stop Switch-80/20 Framing

Key Metrics/Decisions:-Modular-Cost Effective-Portability-Safety-Manufacturability

19Intro Old Project New Project Moving Forward

Page 20: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Part Table Progress

20Intro Old Project New Project Moving Forward

Page 21: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New mechanical plan - parts slot

21

Key Components:-80/20 Framing-Low Friction Polycarbonate Slides-Housing for Electrical Hardware-Touch Screen Display

Intro Old Project New Project Moving Forward

Page 22: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New mechanical plan – End of Arm Tool

22

Key Components:-Machined Aluminum Plumbing-Venturi Vacuum Pumps-Two Laser Distance Sensors-Proxy sensor-Homing Rods

Intro Old Project New Project Moving Forward

Page 23: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

FEA and Calcs

23

0 0.5 1 1.5 2-60

-40

-20

0

20

40

60

t [s]

To

rqu

eta

ble

[N

*m]

Intro Old Project New Project Moving Forward

Page 24: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New electrical design plan - power distribution

24Intro Old Project New Project Moving Forward

Page 25: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New electrical design plan - Communication

25Intro Old Project New Project Moving Forward

Page 26: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New electrical design plan - software

26Intro Old Project New Project Moving Forward

Page 27: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New electrical design plan - software

27Intro Old Project New Project Moving Forward

Page 28: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

New electrical design - Progress

28Intro Old Project New Project Moving Forward

Page 29: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Lessons learned

- Working with distributors can be difficult

- Software can have a lead time

- Inter-team communication is important

- Don’t assume things about the customer

- Solid plans make work go much faster

29Intro Old Project New Project Moving Forward

Page 30: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Moving Forward

• Finish programing

• Wire and power all components once drops are installed

• Finish installation of arm and cage

• Begin working through test plan

30Intro Old Project New Project Moving Forward

Page 31: Robot Automation - engr.calvinblogs.orgengr.calvinblogs.org/17-18/srdesign07/wp-content/uploads/2018/04/… · Robot Automation TEAM 07 2017-2018. Nathan Casey (ECE) Josh Tempelman

Questions

31